SlideShare une entreprise Scribd logo
1  sur  2
Télécharger pour lire hors ligne
PMBOK 4th Edition              PMI-CCVC Time managment PMP Prep                                      6/18/2011




                                      Progressive elaboration where near term work is planned in detail and
  1       Define Activities       a
                                      future work is planned at a higher level of the WBS.

                                      The process of estimating the type and quantities of material, people,
  2     Sequence Activities       b
                                      equipment, or supplies required to perform each activity.

         Estimate Activity            The process of monitoring the status of the project to update project
  3                               c
             Resources                progress and managing changes to the schedule baseline.

         Estimate Activity            Specify when and how long identified project resources are available.
  4                               d
             Durations                This includes resource skill level and geographical locations of orgin.
                                      The process of identifying and documenting relationships among the
  5      Develop Schedule         e
                                      project activities.
                                      Preferred logic, preferential logic, or soft logic. When fast tracking
  6      Control Schedule         f   techniques are used, these should be reviewed and considered for
                                      modification or removal.
                                      A project schedule developed from the schedule network analysis. It is
      Finalized and Approved          accepted and approved by the project management team as the
  7                               g
              Schedule                schedule with start and finish dates. It is a component of the project
                                      management plan.
                                      Uses Most likely, Optimistic and Pessimistic values for Three-Point
  8       Decomposition           h
                                      Estimates.
                                      Resource need is estimated and the quantities are totaled for each
  9    Rolling Wave Planning      i
                                      activitiy's resources.
                                      Uses parameters such as duration, budget, size, weight and complexity
 10      Activity Attributes      j   from a previous project as the basis for estimating the same parameter
                                      for a future project.
            Precedence
                                      Used for schedule development and for selecting, ordering, and sorting
 11    Diagramming Method         k
                                      the planned activities in reports.
              (PDM)
           Discretionary
 12                               l   The baseline that is used in the Control Schedule process.
           dependencies
                                      Subdividing the project work packages into smaller, more manageable
 13     Resource Calendars        m
                                      compoents called activities.
                                      Uses boxes, referred to as nodes, to represent activities, and connects
 14    Bottom-Up Estimating       n   them with arrows that show the logical relationships that exist
                                      between them. This technique is also called Activity-On-Node (AON).

       Resource Breakdown             A structure of identified resources by resource category and resource
 15                               o
            Structure                 type.

                                      A schedule network analysis technique applied to a schedule that has
 16    Analogous Estimating       p been analysised by critical path method. Can be used when shared
                                      resources are only available at certain times or limited quantities.

      Program Evaluation and
                                      Schedule performance measurements (SV, SPI) are used to assess the
 17      Review Technique         q
                                      changes from the original schedule baseline.
              (PERT)

                                           Page 1 of 2
PMBOK 4th Edition            PMI-CCVC Time managment PMP Prep                                      6/18/2011


         Schedule Network           Uses analytical techniques such as critical path method, critical chain
 18                             r
             Analysis               method and resource leveling for generating a project schedule.

                                    The process of approximating the number of work periods needed to
 19      Resource Leveling      s
                                    complete individual activities with estimated resources.

                                    The process of analyzing activity sequences, durations, resource
 20      Schedule Baseline      t
                                    requirements, and schedule constraints to create the project schedule.
                                    The process of identifying the specific actions to be performed to
 21      Variance Analysis      v
                                    produce the project deliverables.




                                         Page 2 of 2

Contenu connexe

Tendances

Harvey.tony
Harvey.tonyHarvey.tony
Harvey.tonyNASAPMC
 
Harrison.g.poole.k
Harrison.g.poole.kHarrison.g.poole.k
Harrison.g.poole.kNASAPMC
 
Pmbok 4th edition chapter 6 - Project Time Management
Pmbok 4th edition   chapter 6 - Project Time Management Pmbok 4th edition   chapter 6 - Project Time Management
Pmbok 4th edition chapter 6 - Project Time Management Ahmad Maharma, PMP,RMP
 
Borchardt.heidemarie
Borchardt.heidemarieBorchardt.heidemarie
Borchardt.heidemarieNASAPMC
 
Sally.godfrey
Sally.godfrey Sally.godfrey
Sally.godfrey NASAPMC
 
Greathouse
GreathouseGreathouse
GreathouseNASAPMC
 
Schedule Design AACE
Schedule Design AACESchedule Design AACE
Schedule Design AACEChris Carson
 
Line of balance in civil engineering
Line of balance in civil engineeringLine of balance in civil engineering
Line of balance in civil engineeringrathodjaydeep2
 
PM Session 6
PM Session 6PM Session 6
PM Session 6dmdk12
 
Qimonda Pm Foils
Qimonda Pm FoilsQimonda Pm Foils
Qimonda Pm Foilstrahanr
 
TIME & RESOURCE PLANNING,MANAGEMENT SOFTWARE
TIME & RESOURCE PLANNING,MANAGEMENT SOFTWARETIME & RESOURCE PLANNING,MANAGEMENT SOFTWARE
TIME & RESOURCE PLANNING,MANAGEMENT SOFTWAREKHUSHBU SHAH
 
Back to Basics: Resource planning
Back to Basics: Resource planningBack to Basics: Resource planning
Back to Basics: Resource planningThomas Sarlandie
 
Schedule levels-as-presented 02-may11
Schedule levels-as-presented  02-may11Schedule levels-as-presented  02-may11
Schedule levels-as-presented 02-may11PMA Consultants
 
Louis.cioletti
Louis.ciolettiLouis.cioletti
Louis.ciolettiNASAPMC
 

Tendances (19)

Harvey.tony
Harvey.tonyHarvey.tony
Harvey.tony
 
Harrison.g.poole.k
Harrison.g.poole.kHarrison.g.poole.k
Harrison.g.poole.k
 
Risk Management
Risk ManagementRisk Management
Risk Management
 
Pmbok 4th edition chapter 6 - Project Time Management
Pmbok 4th edition   chapter 6 - Project Time Management Pmbok 4th edition   chapter 6 - Project Time Management
Pmbok 4th edition chapter 6 - Project Time Management
 
Borchardt.heidemarie
Borchardt.heidemarieBorchardt.heidemarie
Borchardt.heidemarie
 
Resource allocation and smoothing
Resource allocation and smoothingResource allocation and smoothing
Resource allocation and smoothing
 
Sally.godfrey
Sally.godfrey Sally.godfrey
Sally.godfrey
 
Greathouse
GreathouseGreathouse
Greathouse
 
Pmbok6
Pmbok6Pmbok6
Pmbok6
 
105 project time management
105 project time management105 project time management
105 project time management
 
Schedule Design AACE
Schedule Design AACESchedule Design AACE
Schedule Design AACE
 
Line of balance in civil engineering
Line of balance in civil engineeringLine of balance in civil engineering
Line of balance in civil engineering
 
PM Session 6
PM Session 6PM Session 6
PM Session 6
 
Ch6 resources
Ch6 resourcesCh6 resources
Ch6 resources
 
Qimonda Pm Foils
Qimonda Pm FoilsQimonda Pm Foils
Qimonda Pm Foils
 
TIME & RESOURCE PLANNING,MANAGEMENT SOFTWARE
TIME & RESOURCE PLANNING,MANAGEMENT SOFTWARETIME & RESOURCE PLANNING,MANAGEMENT SOFTWARE
TIME & RESOURCE PLANNING,MANAGEMENT SOFTWARE
 
Back to Basics: Resource planning
Back to Basics: Resource planningBack to Basics: Resource planning
Back to Basics: Resource planning
 
Schedule levels-as-presented 02-may11
Schedule levels-as-presented  02-may11Schedule levels-as-presented  02-may11
Schedule levels-as-presented 02-may11
 
Louis.cioletti
Louis.ciolettiLouis.cioletti
Louis.cioletti
 

En vedette

Ritetrac consulting training calender in 2017
Ritetrac consulting training calender in 2017Ritetrac consulting training calender in 2017
Ritetrac consulting training calender in 2017Ojiugo Ajunwa
 
O Q U E F A Z E M O S M I L I T A R E S E M I
O  Q U E  F A Z E M  O S  M I L I T A R E S    E M IO  Q U E  F A Z E M  O S  M I L I T A R E S    E M I
O Q U E F A Z E M O S M I L I T A R E S E M Irobsonnasc
 
Pmp exam prep Pdf- 2
Pmp exam prep Pdf- 2Pmp exam prep Pdf- 2
Pmp exam prep Pdf- 2Amr Miqdadi
 
Prevención y detección de amenazas avanzadas
Prevención y detección de amenazas avanzadasPrevención y detección de amenazas avanzadas
Prevención y detección de amenazas avanzadasDavid Hernandez
 
Gender and Something 2016
Gender and Something 2016Gender and Something 2016
Gender and Something 2016Ross Logan
 
Vías de las pentosas 1
Vías de las pentosas 1Vías de las pentosas 1
Vías de las pentosas 1Mario Cordero
 
Prezentacija o sokobanji
Prezentacija o sokobanji Prezentacija o sokobanji
Prezentacija o sokobanji Jocky86
 
Madrid Agudelo Juliana_AporteIndividual
Madrid Agudelo Juliana_AporteIndividualMadrid Agudelo Juliana_AporteIndividual
Madrid Agudelo Juliana_AporteIndividualJuliana Madrid
 
Gissela sociologia proyecto
Gissela sociologia proyectoGissela sociologia proyecto
Gissela sociologia proyectogissela1996
 
Next-L Enju 開発ワークショップ #57
Next-L Enju 開発ワークショップ #57Next-L Enju 開発ワークショップ #57
Next-L Enju 開発ワークショップ #57Kosuke Tanabe
 
Sexualidad e instinto sexual slideshare
Sexualidad e instinto sexual  slideshareSexualidad e instinto sexual  slideshare
Sexualidad e instinto sexual slideshareMaria Bravo
 
初一科学第九章:太阳和太阳系
初一科学第九章:太阳和太阳系初一科学第九章:太阳和太阳系
初一科学第九章:太阳和太阳系轩 宝宝
 

En vedette (18)

Ritetrac consulting training calender in 2017
Ritetrac consulting training calender in 2017Ritetrac consulting training calender in 2017
Ritetrac consulting training calender in 2017
 
O Q U E F A Z E M O S M I L I T A R E S E M I
O  Q U E  F A Z E M  O S  M I L I T A R E S    E M IO  Q U E  F A Z E M  O S  M I L I T A R E S    E M I
O Q U E F A Z E M O S M I L I T A R E S E M I
 
T353 Web
T353 WebT353 Web
T353 Web
 
T326
T326T326
T326
 
Pmp integration management
Pmp integration managementPmp integration management
Pmp integration management
 
Pmp exam prep Pdf- 2
Pmp exam prep Pdf- 2Pmp exam prep Pdf- 2
Pmp exam prep Pdf- 2
 
Famílias imigrantes
Famílias imigrantesFamílias imigrantes
Famílias imigrantes
 
Prevención y detección de amenazas avanzadas
Prevención y detección de amenazas avanzadasPrevención y detección de amenazas avanzadas
Prevención y detección de amenazas avanzadas
 
Gender and Something 2016
Gender and Something 2016Gender and Something 2016
Gender and Something 2016
 
Vías de las pentosas 1
Vías de las pentosas 1Vías de las pentosas 1
Vías de las pentosas 1
 
Presentación trabajo colaborativo
Presentación trabajo colaborativoPresentación trabajo colaborativo
Presentación trabajo colaborativo
 
Prezentacija o sokobanji
Prezentacija o sokobanji Prezentacija o sokobanji
Prezentacija o sokobanji
 
Madrid Agudelo Juliana_AporteIndividual
Madrid Agudelo Juliana_AporteIndividualMadrid Agudelo Juliana_AporteIndividual
Madrid Agudelo Juliana_AporteIndividual
 
Gissela sociologia proyecto
Gissela sociologia proyectoGissela sociologia proyecto
Gissela sociologia proyecto
 
CV-A.MOGHAZY 2
CV-A.MOGHAZY  2CV-A.MOGHAZY  2
CV-A.MOGHAZY 2
 
Next-L Enju 開発ワークショップ #57
Next-L Enju 開発ワークショップ #57Next-L Enju 開発ワークショップ #57
Next-L Enju 開発ワークショップ #57
 
Sexualidad e instinto sexual slideshare
Sexualidad e instinto sexual  slideshareSexualidad e instinto sexual  slideshare
Sexualidad e instinto sexual slideshare
 
初一科学第九章:太阳和太阳系
初一科学第九章:太阳和太阳系初一科学第九章:太阳和太阳系
初一科学第九章:太阳和太阳系
 

Similaire à Capm time mgmt matching exercise

Ipao great houseetc-programmatic analysis ll
Ipao great houseetc-programmatic analysis llIpao great houseetc-programmatic analysis ll
Ipao great houseetc-programmatic analysis llNASAPMC
 
TIME MANAGEMENT chapter(6), PMBOK5
TIME MANAGEMENT chapter(6), PMBOK5TIME MANAGEMENT chapter(6), PMBOK5
TIME MANAGEMENT chapter(6), PMBOK5Hisham Ali,PMP
 
PROJECT PLANNING METHODOLOGIES.pdf
PROJECT  PLANNING METHODOLOGIES.pdfPROJECT  PLANNING METHODOLOGIES.pdf
PROJECT PLANNING METHODOLOGIES.pdfSurashmie Kaalmegh
 
PMICOS Webinar: Building a Sound Schedule in an Enterprise Environment
PMICOS Webinar: Building a Sound Schedule in an Enterprise EnvironmentPMICOS Webinar: Building a Sound Schedule in an Enterprise Environment
PMICOS Webinar: Building a Sound Schedule in an Enterprise EnvironmentAcumen
 
Projectmanagement anupama-Amit Payal
Projectmanagement anupama-Amit PayalProjectmanagement anupama-Amit Payal
Projectmanagement anupama-Amit PayalAMIT PAYAL
 
Topic 11 - Project Schedule Management.pdf
Topic 11 - Project Schedule Management.pdfTopic 11 - Project Schedule Management.pdf
Topic 11 - Project Schedule Management.pdfHuyNguyen657394
 
Pmbok 5th planning process group part two
Pmbok 5th planning process group part twoPmbok 5th planning process group part two
Pmbok 5th planning process group part twoHossam Maghrabi
 
Project Management.pptx
 Project  Management.pptx Project  Management.pptx
Project Management.pptxHafixFarhan
 
Project Management Presentation material
Project Management Presentation material Project Management Presentation material
Project Management Presentation material Abdel Rahman okasha
 
OR PERT CPM AND JOB SCHEDULING
OR PERT CPM AND JOB SCHEDULINGOR PERT CPM AND JOB SCHEDULING
OR PERT CPM AND JOB SCHEDULINGJignesh Kariya
 
Time Management within IT Project Management
Time Management within IT Project ManagementTime Management within IT Project Management
Time Management within IT Project Managementrielaantonio
 
Construction Project management
Construction Project management Construction Project management
Construction Project management Anupama holla
 

Similaire à Capm time mgmt matching exercise (20)

Session 8 4th edition PMP
Session 8 4th edition PMPSession 8 4th edition PMP
Session 8 4th edition PMP
 
CHAPTER 1.pptx
CHAPTER 1.pptxCHAPTER 1.pptx
CHAPTER 1.pptx
 
CHAPTER 1.pptx
CHAPTER 1.pptxCHAPTER 1.pptx
CHAPTER 1.pptx
 
Ipao great houseetc-programmatic analysis ll
Ipao great houseetc-programmatic analysis llIpao great houseetc-programmatic analysis ll
Ipao great houseetc-programmatic analysis ll
 
TIME MANAGEMENT chapter(6), PMBOK5
TIME MANAGEMENT chapter(6), PMBOK5TIME MANAGEMENT chapter(6), PMBOK5
TIME MANAGEMENT chapter(6), PMBOK5
 
PROJECT PLANNING METHODOLOGIES.pdf
PROJECT  PLANNING METHODOLOGIES.pdfPROJECT  PLANNING METHODOLOGIES.pdf
PROJECT PLANNING METHODOLOGIES.pdf
 
PMICOS Webinar: Building a Sound Schedule in an Enterprise Environment
PMICOS Webinar: Building a Sound Schedule in an Enterprise EnvironmentPMICOS Webinar: Building a Sound Schedule in an Enterprise Environment
PMICOS Webinar: Building a Sound Schedule in an Enterprise Environment
 
Projectmanagement anupama-Amit Payal
Projectmanagement anupama-Amit PayalProjectmanagement anupama-Amit Payal
Projectmanagement anupama-Amit Payal
 
Pm chapter 5
Pm chapter 5Pm chapter 5
Pm chapter 5
 
Pm chapter 5
Pm chapter 5Pm chapter 5
Pm chapter 5
 
Topic 11 - Project Schedule Management.pdf
Topic 11 - Project Schedule Management.pdfTopic 11 - Project Schedule Management.pdf
Topic 11 - Project Schedule Management.pdf
 
Pm chapter 5...
Pm chapter 5...Pm chapter 5...
Pm chapter 5...
 
Pmbok 5th planning process group part two
Pmbok 5th planning process group part twoPmbok 5th planning process group part two
Pmbok 5th planning process group part two
 
Project Management.pptx
 Project  Management.pptx Project  Management.pptx
Project Management.pptx
 
Project Management Presentation material
Project Management Presentation material Project Management Presentation material
Project Management Presentation material
 
PRINCE2
PRINCE2PRINCE2
PRINCE2
 
OR PERT CPM AND JOB SCHEDULING
OR PERT CPM AND JOB SCHEDULINGOR PERT CPM AND JOB SCHEDULING
OR PERT CPM AND JOB SCHEDULING
 
Time Management within IT Project Management
Time Management within IT Project ManagementTime Management within IT Project Management
Time Management within IT Project Management
 
Slides chapters 24-25
Slides chapters 24-25Slides chapters 24-25
Slides chapters 24-25
 
Construction Project management
Construction Project management Construction Project management
Construction Project management
 

Plus de University High School - Fresno (12)

Capm time mgmt fas track as
Capm time mgmt fas track asCapm time mgmt fas track as
Capm time mgmt fas track as
 
Capm test taking preparation hints
Capm test taking preparation hintsCapm test taking preparation hints
Capm test taking preparation hints
 
Capm process cheat sheet
Capm process cheat sheetCapm process cheat sheet
Capm process cheat sheet
 
Capm time 150 question final key
Capm time 150 question final keyCapm time 150 question final key
Capm time 150 question final key
 
Capm scenario identifying the critical path answers
Capm scenario identifying the critical path   answersCapm scenario identifying the critical path   answers
Capm scenario identifying the critical path answers
 
Capm scenario identifying the critical path answers
Capm scenario identifying the critical path   answersCapm scenario identifying the critical path   answers
Capm scenario identifying the critical path answers
 
Simple perl scripts
Simple perl scriptsSimple perl scripts
Simple perl scripts
 
Zoskctr hints tips 20090723doc
Zoskctr hints tips 20090723docZoskctr hints tips 20090723doc
Zoskctr hints tips 20090723doc
 
Simple perl scripts
Simple perl scriptsSimple perl scripts
Simple perl scripts
 
Source code examples
Source code examplesSource code examples
Source code examples
 
Business computing survey
Business computing surveyBusiness computing survey
Business computing survey
 
Watson
WatsonWatson
Watson
 

Dernier

Call Girls In DLf Gurgaon ➥99902@11544 ( Best price)100% Genuine Escort In 24...
Call Girls In DLf Gurgaon ➥99902@11544 ( Best price)100% Genuine Escort In 24...Call Girls In DLf Gurgaon ➥99902@11544 ( Best price)100% Genuine Escort In 24...
Call Girls In DLf Gurgaon ➥99902@11544 ( Best price)100% Genuine Escort In 24...lizamodels9
 
Mysore Call Girls 8617370543 WhatsApp Number 24x7 Best Services
Mysore Call Girls 8617370543 WhatsApp Number 24x7 Best ServicesMysore Call Girls 8617370543 WhatsApp Number 24x7 Best Services
Mysore Call Girls 8617370543 WhatsApp Number 24x7 Best ServicesDipal Arora
 
Ensure the security of your HCL environment by applying the Zero Trust princi...
Ensure the security of your HCL environment by applying the Zero Trust princi...Ensure the security of your HCL environment by applying the Zero Trust princi...
Ensure the security of your HCL environment by applying the Zero Trust princi...Roland Driesen
 
Lucknow 💋 Escorts in Lucknow - 450+ Call Girl Cash Payment 8923113531 Neha Th...
Lucknow 💋 Escorts in Lucknow - 450+ Call Girl Cash Payment 8923113531 Neha Th...Lucknow 💋 Escorts in Lucknow - 450+ Call Girl Cash Payment 8923113531 Neha Th...
Lucknow 💋 Escorts in Lucknow - 450+ Call Girl Cash Payment 8923113531 Neha Th...anilsa9823
 
Enhancing and Restoring Safety & Quality Cultures - Dave Litwiller - May 2024...
Enhancing and Restoring Safety & Quality Cultures - Dave Litwiller - May 2024...Enhancing and Restoring Safety & Quality Cultures - Dave Litwiller - May 2024...
Enhancing and Restoring Safety & Quality Cultures - Dave Litwiller - May 2024...Dave Litwiller
 
The Coffee Bean & Tea Leaf(CBTL), Business strategy case study
The Coffee Bean & Tea Leaf(CBTL), Business strategy case studyThe Coffee Bean & Tea Leaf(CBTL), Business strategy case study
The Coffee Bean & Tea Leaf(CBTL), Business strategy case studyEthan lee
 
Russian Faridabad Call Girls(Badarpur) : ☎ 8168257667, @4999
Russian Faridabad Call Girls(Badarpur) : ☎ 8168257667, @4999Russian Faridabad Call Girls(Badarpur) : ☎ 8168257667, @4999
Russian Faridabad Call Girls(Badarpur) : ☎ 8168257667, @4999Tina Ji
 
VIP Call Girls In Saharaganj ( Lucknow ) 🔝 8923113531 🔝 Cash Payment (COD) 👒
VIP Call Girls In Saharaganj ( Lucknow  ) 🔝 8923113531 🔝  Cash Payment (COD) 👒VIP Call Girls In Saharaganj ( Lucknow  ) 🔝 8923113531 🔝  Cash Payment (COD) 👒
VIP Call Girls In Saharaganj ( Lucknow ) 🔝 8923113531 🔝 Cash Payment (COD) 👒anilsa9823
 
Best VIP Call Girls Noida Sector 40 Call Me: 8448380779
Best VIP Call Girls Noida Sector 40 Call Me: 8448380779Best VIP Call Girls Noida Sector 40 Call Me: 8448380779
Best VIP Call Girls Noida Sector 40 Call Me: 8448380779Delhi Call girls
 
Event mailer assignment progress report .pdf
Event mailer assignment progress report .pdfEvent mailer assignment progress report .pdf
Event mailer assignment progress report .pdftbatkhuu1
 
Understanding the Pakistan Budgeting Process: Basics and Key Insights
Understanding the Pakistan Budgeting Process: Basics and Key InsightsUnderstanding the Pakistan Budgeting Process: Basics and Key Insights
Understanding the Pakistan Budgeting Process: Basics and Key Insightsseri bangash
 
Yaroslav Rozhankivskyy: Три складові і три передумови максимальної продуктивн...
Yaroslav Rozhankivskyy: Три складові і три передумови максимальної продуктивн...Yaroslav Rozhankivskyy: Три складові і три передумови максимальної продуктивн...
Yaroslav Rozhankivskyy: Три складові і три передумови максимальної продуктивн...Lviv Startup Club
 
Monte Carlo simulation : Simulation using MCSM
Monte Carlo simulation : Simulation using MCSMMonte Carlo simulation : Simulation using MCSM
Monte Carlo simulation : Simulation using MCSMRavindra Nath Shukla
 
Call Girls Navi Mumbai Just Call 9907093804 Top Class Call Girl Service Avail...
Call Girls Navi Mumbai Just Call 9907093804 Top Class Call Girl Service Avail...Call Girls Navi Mumbai Just Call 9907093804 Top Class Call Girl Service Avail...
Call Girls Navi Mumbai Just Call 9907093804 Top Class Call Girl Service Avail...Dipal Arora
 
Monthly Social Media Update April 2024 pptx.pptx
Monthly Social Media Update April 2024 pptx.pptxMonthly Social Media Update April 2024 pptx.pptx
Monthly Social Media Update April 2024 pptx.pptxAndy Lambert
 
Regression analysis: Simple Linear Regression Multiple Linear Regression
Regression analysis:  Simple Linear Regression Multiple Linear RegressionRegression analysis:  Simple Linear Regression Multiple Linear Regression
Regression analysis: Simple Linear Regression Multiple Linear RegressionRavindra Nath Shukla
 
Sales & Marketing Alignment: How to Synergize for Success
Sales & Marketing Alignment: How to Synergize for SuccessSales & Marketing Alignment: How to Synergize for Success
Sales & Marketing Alignment: How to Synergize for SuccessAggregage
 
9599632723 Top Call Girls in Delhi at your Door Step Available 24x7 Delhi
9599632723 Top Call Girls in Delhi at your Door Step Available 24x7 Delhi9599632723 Top Call Girls in Delhi at your Door Step Available 24x7 Delhi
9599632723 Top Call Girls in Delhi at your Door Step Available 24x7 DelhiCall Girls in Delhi
 

Dernier (20)

Call Girls In DLf Gurgaon ➥99902@11544 ( Best price)100% Genuine Escort In 24...
Call Girls In DLf Gurgaon ➥99902@11544 ( Best price)100% Genuine Escort In 24...Call Girls In DLf Gurgaon ➥99902@11544 ( Best price)100% Genuine Escort In 24...
Call Girls In DLf Gurgaon ➥99902@11544 ( Best price)100% Genuine Escort In 24...
 
Mysore Call Girls 8617370543 WhatsApp Number 24x7 Best Services
Mysore Call Girls 8617370543 WhatsApp Number 24x7 Best ServicesMysore Call Girls 8617370543 WhatsApp Number 24x7 Best Services
Mysore Call Girls 8617370543 WhatsApp Number 24x7 Best Services
 
Ensure the security of your HCL environment by applying the Zero Trust princi...
Ensure the security of your HCL environment by applying the Zero Trust princi...Ensure the security of your HCL environment by applying the Zero Trust princi...
Ensure the security of your HCL environment by applying the Zero Trust princi...
 
Lucknow 💋 Escorts in Lucknow - 450+ Call Girl Cash Payment 8923113531 Neha Th...
Lucknow 💋 Escorts in Lucknow - 450+ Call Girl Cash Payment 8923113531 Neha Th...Lucknow 💋 Escorts in Lucknow - 450+ Call Girl Cash Payment 8923113531 Neha Th...
Lucknow 💋 Escorts in Lucknow - 450+ Call Girl Cash Payment 8923113531 Neha Th...
 
Enhancing and Restoring Safety & Quality Cultures - Dave Litwiller - May 2024...
Enhancing and Restoring Safety & Quality Cultures - Dave Litwiller - May 2024...Enhancing and Restoring Safety & Quality Cultures - Dave Litwiller - May 2024...
Enhancing and Restoring Safety & Quality Cultures - Dave Litwiller - May 2024...
 
The Coffee Bean & Tea Leaf(CBTL), Business strategy case study
The Coffee Bean & Tea Leaf(CBTL), Business strategy case studyThe Coffee Bean & Tea Leaf(CBTL), Business strategy case study
The Coffee Bean & Tea Leaf(CBTL), Business strategy case study
 
Russian Faridabad Call Girls(Badarpur) : ☎ 8168257667, @4999
Russian Faridabad Call Girls(Badarpur) : ☎ 8168257667, @4999Russian Faridabad Call Girls(Badarpur) : ☎ 8168257667, @4999
Russian Faridabad Call Girls(Badarpur) : ☎ 8168257667, @4999
 
VIP Call Girls In Saharaganj ( Lucknow ) 🔝 8923113531 🔝 Cash Payment (COD) 👒
VIP Call Girls In Saharaganj ( Lucknow  ) 🔝 8923113531 🔝  Cash Payment (COD) 👒VIP Call Girls In Saharaganj ( Lucknow  ) 🔝 8923113531 🔝  Cash Payment (COD) 👒
VIP Call Girls In Saharaganj ( Lucknow ) 🔝 8923113531 🔝 Cash Payment (COD) 👒
 
Best VIP Call Girls Noida Sector 40 Call Me: 8448380779
Best VIP Call Girls Noida Sector 40 Call Me: 8448380779Best VIP Call Girls Noida Sector 40 Call Me: 8448380779
Best VIP Call Girls Noida Sector 40 Call Me: 8448380779
 
Event mailer assignment progress report .pdf
Event mailer assignment progress report .pdfEvent mailer assignment progress report .pdf
Event mailer assignment progress report .pdf
 
Understanding the Pakistan Budgeting Process: Basics and Key Insights
Understanding the Pakistan Budgeting Process: Basics and Key InsightsUnderstanding the Pakistan Budgeting Process: Basics and Key Insights
Understanding the Pakistan Budgeting Process: Basics and Key Insights
 
Yaroslav Rozhankivskyy: Три складові і три передумови максимальної продуктивн...
Yaroslav Rozhankivskyy: Три складові і три передумови максимальної продуктивн...Yaroslav Rozhankivskyy: Три складові і три передумови максимальної продуктивн...
Yaroslav Rozhankivskyy: Три складові і три передумови максимальної продуктивн...
 
Monte Carlo simulation : Simulation using MCSM
Monte Carlo simulation : Simulation using MCSMMonte Carlo simulation : Simulation using MCSM
Monte Carlo simulation : Simulation using MCSM
 
Nepali Escort Girl Kakori \ 9548273370 Indian Call Girls Service Lucknow ₹,9517
Nepali Escort Girl Kakori \ 9548273370 Indian Call Girls Service Lucknow ₹,9517Nepali Escort Girl Kakori \ 9548273370 Indian Call Girls Service Lucknow ₹,9517
Nepali Escort Girl Kakori \ 9548273370 Indian Call Girls Service Lucknow ₹,9517
 
Call Girls Navi Mumbai Just Call 9907093804 Top Class Call Girl Service Avail...
Call Girls Navi Mumbai Just Call 9907093804 Top Class Call Girl Service Avail...Call Girls Navi Mumbai Just Call 9907093804 Top Class Call Girl Service Avail...
Call Girls Navi Mumbai Just Call 9907093804 Top Class Call Girl Service Avail...
 
Monthly Social Media Update April 2024 pptx.pptx
Monthly Social Media Update April 2024 pptx.pptxMonthly Social Media Update April 2024 pptx.pptx
Monthly Social Media Update April 2024 pptx.pptx
 
Regression analysis: Simple Linear Regression Multiple Linear Regression
Regression analysis:  Simple Linear Regression Multiple Linear RegressionRegression analysis:  Simple Linear Regression Multiple Linear Regression
Regression analysis: Simple Linear Regression Multiple Linear Regression
 
Sales & Marketing Alignment: How to Synergize for Success
Sales & Marketing Alignment: How to Synergize for SuccessSales & Marketing Alignment: How to Synergize for Success
Sales & Marketing Alignment: How to Synergize for Success
 
VVVIP Call Girls In Greater Kailash ➡️ Delhi ➡️ 9999965857 🚀 No Advance 24HRS...
VVVIP Call Girls In Greater Kailash ➡️ Delhi ➡️ 9999965857 🚀 No Advance 24HRS...VVVIP Call Girls In Greater Kailash ➡️ Delhi ➡️ 9999965857 🚀 No Advance 24HRS...
VVVIP Call Girls In Greater Kailash ➡️ Delhi ➡️ 9999965857 🚀 No Advance 24HRS...
 
9599632723 Top Call Girls in Delhi at your Door Step Available 24x7 Delhi
9599632723 Top Call Girls in Delhi at your Door Step Available 24x7 Delhi9599632723 Top Call Girls in Delhi at your Door Step Available 24x7 Delhi
9599632723 Top Call Girls in Delhi at your Door Step Available 24x7 Delhi
 

Capm time mgmt matching exercise

  • 1. PMBOK 4th Edition PMI-CCVC Time managment PMP Prep 6/18/2011 Progressive elaboration where near term work is planned in detail and 1 Define Activities a future work is planned at a higher level of the WBS. The process of estimating the type and quantities of material, people, 2 Sequence Activities b equipment, or supplies required to perform each activity. Estimate Activity The process of monitoring the status of the project to update project 3 c Resources progress and managing changes to the schedule baseline. Estimate Activity Specify when and how long identified project resources are available. 4 d Durations This includes resource skill level and geographical locations of orgin. The process of identifying and documenting relationships among the 5 Develop Schedule e project activities. Preferred logic, preferential logic, or soft logic. When fast tracking 6 Control Schedule f techniques are used, these should be reviewed and considered for modification or removal. A project schedule developed from the schedule network analysis. It is Finalized and Approved accepted and approved by the project management team as the 7 g Schedule schedule with start and finish dates. It is a component of the project management plan. Uses Most likely, Optimistic and Pessimistic values for Three-Point 8 Decomposition h Estimates. Resource need is estimated and the quantities are totaled for each 9 Rolling Wave Planning i activitiy's resources. Uses parameters such as duration, budget, size, weight and complexity 10 Activity Attributes j from a previous project as the basis for estimating the same parameter for a future project. Precedence Used for schedule development and for selecting, ordering, and sorting 11 Diagramming Method k the planned activities in reports. (PDM) Discretionary 12 l The baseline that is used in the Control Schedule process. dependencies Subdividing the project work packages into smaller, more manageable 13 Resource Calendars m compoents called activities. Uses boxes, referred to as nodes, to represent activities, and connects 14 Bottom-Up Estimating n them with arrows that show the logical relationships that exist between them. This technique is also called Activity-On-Node (AON). Resource Breakdown A structure of identified resources by resource category and resource 15 o Structure type. A schedule network analysis technique applied to a schedule that has 16 Analogous Estimating p been analysised by critical path method. Can be used when shared resources are only available at certain times or limited quantities. Program Evaluation and Schedule performance measurements (SV, SPI) are used to assess the 17 Review Technique q changes from the original schedule baseline. (PERT) Page 1 of 2
  • 2. PMBOK 4th Edition PMI-CCVC Time managment PMP Prep 6/18/2011 Schedule Network Uses analytical techniques such as critical path method, critical chain 18 r Analysis method and resource leveling for generating a project schedule. The process of approximating the number of work periods needed to 19 Resource Leveling s complete individual activities with estimated resources. The process of analyzing activity sequences, durations, resource 20 Schedule Baseline t requirements, and schedule constraints to create the project schedule. The process of identifying the specific actions to be performed to 21 Variance Analysis v produce the project deliverables. Page 2 of 2