1. GLOBAL CCS INSTITUTE
THE STATUS OF CCS
Meade Harris, Regional Representative
UKCCSC Winter School, Cambridge
January 10, 2011
WWW.GLOBALCCSINSTITUTE.COM
2. GLOBAL CCS INSTITUTE
MISSION
The mission of the Global CCS Institute is:
to be a centre of excellence for CCS knowledge;
to accelerate the development and deployment
of CCS globally; and
to help ensure that CCS has a significant role in
reducing the world’s greenhouse gas emissions.
1
3. GLOBAL CCS INSTITUTE
MEMBERSHIP
Global Region Breakdown – November 2011 Total Membership: 330*
Europe
125
Americas
67 Middle
East Asia
3
57
Africa
4
Australasia
74
Representation Offices:
* Includes Foundation Members and Registered Member Locations
Collaborating Participants
4. GLOBAL CCS INSTITUTE
INSTITUTE-SUPPORTED PROJECTS FOR KNOWLEDGE SHARING
1. RCI 12. Maersk
(Rotterdam CCS Network) (Maersk Oil) 7. ROAD
Storage and shipping studies Shipping EOR / (Maasvlakte CCS)
Feasibility Study FEED studies &
6. Getica
execution planning
(ISPE)
4. Pioneer Feasibility Study
(TransAlta)
FEED studies
8 Chiyoda
(Chiyoda/Tokyo University)
Shuttle shipping study
2. Trailblazer
(Tenaska)
FEED studies
10. Callide Oxyfuel
(OTPL)
3. Nelson 6 Transport and CO2 injection
(Tenaska/Entergy) studies
Development studies
5. Mountaineer 9. Collie Hub
(American Electric Power) (Western Australian Government)
FEED studies General reports
INSTITUTE FUNDING STATUS
11. CarbonNet 13. CarbonNet
(Victorian Government) (Victorian Government)
Active Commercial and Planning studies MMV scope study
Commencing / Under discussion
Completed
16. GLOBAL CCS INSTITUTE
KEY MESSAGES
Early mover projects are found in industrial applications
and with EOR for storage.
Two power projects are now under construction with aid
of government funding and EOR revenue.
A number of power projects are on the verge of FID but
making the business case is proving difficult and time
consuming.
Greater collaboration and transparency between
government and industry is needed.
Storage assessments in deep saline formations can
have long lead times – need to start now.
15