GAS CCUS IN MEXICO
Abigail González Díaz
José Miguel González-Santaló
Instituto de Investigaciones Electricas (IIE) Mexico
Gas CCS Meeting
Brighton, UK
June 25, 2014
1. Why CCS and CO2 for EOR in Mexico?
• Growth in electricity production
• Electricity generation
• Natural gas and oil production
• CO2-EOR Potential
2. Current status of CO2-EOR in PEMEX-CFE
3. Future plant on CCUS
Outline
MAIN SOURCES OF INFORMATION
1. Estrategia Nacional de Energía 2013-2027
Prospectiva del Sector Eléctrico 2013-2027
Secretaría de Energía, México
www.sener.gob.mx/portal/publicaciones.html
2. R. Lacy et al. Initial assessment of the potential for future CCUS
with EOR projects in Mexico using CO2 captured from fossil fuel
industrial plants, International Journal of Greenhouse Gas Control
19 (2013) 212–219
3. Fernando Rodríguez de la Garza, CO2 – EOR program in Mexico,
Gas networking meeting , Cuernavaca Morelos, Mexico 11-12
February 2014
The two major energy companies in Mexico are state owned
1. The Mexican oil company Petróleos Mexicanos (PEMEX) is
the second most profitable company in Latin America
2. The Utility Company Comisión Federal de Electricidad (CFE)
Mexican oil has been controlled exclusively by the state-owned
Pemex for more than 75 years
MEXICO OPENS UP ITS ENERGY MARKETS
On December 12, 2013, Mexican legislators approved
controversial reforms to the country’s energy sector
Why CCS and CO2 for EOR?
• Fast growth. Installed capacity of 62 GW in 2009, 113 GW in
2028
• Natural gas is and will be the dominant energy source in 2028
• The oil industry will require large amounts of CO2 for EOR
Mexico ‘s mitigation target
“reduce GHG emissions by 50% below 2002 levels by 2050”
Growth in electricity production
Values in TW-hr
Electricity generation 2012-2028
2/ Nueva generación limpia (NGL): Nuclear, carboeléctrica o ciclo combinado con captura y confinamiento de CO2, o renovable
2012real
60,459 MW
2028
113,708 MW
POISE 2014-2028
Geotermoeléctrica
1.3%
Ciclo combinado
31.2%
Termoeléctrica
convencional
19.7%
Turbogás
5.6%
Combustión
interna
0.5%
Eoloeléctrica
1.8%
Hidroeléctrica
19.3%
Carboeléctrica
8.9%
Nucleoeléctrica
2.7%Solar
0.0%
Coque
0.9%Biomasa
0.1%
Autoabastecimien
to local
7.9%
Geotermoeléctrica
1.0%
Ciclo combinado
45.2%
Termoeléctrica
convencional
1.7% Turbogás
1.9%
Combustión
interna
0.3% Eoloeléctrica
10.9%
Hidroeléctrica
13.8%
Carboeléctrica
4.2%
Nucleoeléctrica
1.2%
Solar
1.6%
NGL
11.5%
Coque
0.8%
Biomasa
0.3%
Autoabastecimien
to local
5.5%
2/
In 2013 . In construction
Total: 3,522 MW → NGCC 1,934 MW
Capacity authorized for public service
Total: 9,679 MW → NGCC 7,283 MW
Aditional capacity between 2016 – 2022
Total: 14,795 MW → NGCC 10,704 MW
Aditional capacity between 2023 – 2028
Total: 26,955 MW1 → NGCC 11,013 MW
POISE 2014-2028
Total: 3,522 MW
Centrales terminadas y en proceso de
construcción, en 2013. Servicio público
1/ Agua Prieta II (operación de una TG en ciclo abierto 134 MW) en Julio de 2014
MW
1,934
3,522
Ciclo combinado
Total
Eoloeléctrica 103
Geotermoeléctrica 107
Combustión interna 58.6
Turbogás-cogeneración 521
Termosolar 14
Baja
California II
TG Fase I
(139 MW)
Guerrero Negro III
(12 MW)
Baja California
Sur IV
(Coromuel)
(44 MW)
Humeros II Fases A y B
(2x27 MW )
Salamanca Fase I
(382 MW )
Azufres III
Fase I
(53 MW)
Sureste I Fase II
(103 MW)
Centro
(658 MW)
Termosolar Agua Prieta II
(14 MW)
Agua Prieta II 1/
(404 MW)
Piloto Solar
(5 MW)
Norte II
(Chihuahua)
(445 MW)
Santa Rosalía
(2.6 MW)
Aura Solar
(30 MW)
La Yesca U1 y U2
(750 MW)
Manzanillo I rep U2
(427 MW)
Solar 35
Hidroeléctrica 750
4. POISE 2014-2028
Total: 9,679 MW
capacidad en licitación autorizada y condicionada
para Servicio Público
Hidroeléctrica
Ciclo
combinado
Turbogás
Geotermoeléctrica
Total
MW
480
7,283
86
29
9,679
Eoloeléctrica 1,688
Combustión interna 109
Las Cruces
(240 MW
(203 MW)
Sureste I Fase I
Solar 4
Rumorosa
(3x100 MW)
I,II y III
Santa Rosalía Ciclo
binario
(2 MW)
Santa Rosalía (FV)
(4 MW)
Santa Rosalía II
(15 MW)
Noroeste y Topolobampo III
(847 y 700 MW)
(2 x 735 MW)
Guaymas II y III
(43 MW)
Baja California Sur VI
La Paz
(117 MW)
Noreste (Escobedo)
(1,034 MW)
Lerdo (Norte IV)
(990 MW)
Valle de México II
(601MW)
Chicoasén II
(240 MW)
(1,185 MW)
Surestes II, III IV V
Baja California II (276 MW)
Baja California II TG Fase II (86 MW)
Norte III
(Juárez)
(954 MW)
(43 MW)
Baja California Sur V
(Coromuel)
Guerrero Negro IV
(8 MW)
Baja California III
(La Jovita)
(294 MW)
Humeros III
(Fase A)
(27 MW)
4. POISE 2014-2028
1/ Las cifras están redondeadas a números enteros, por lo que los totales podrían no corresponder exactamente
2/ No incluidos en el mapa
Total: 14,795 MW1/
Hidroeléctrica
Ciclo
combinado
Solar 2/
Turbogás
Geotermoeléctrica
Total
MW
1,133
10,704
790
432
135
14,7951/
Manzanillo II rep.
U1 y U2
(2 x460 MW)
Francisco Villa (Norte V)
(958 MW)
Todos Santos
(137 MW)
Central Tula
(1,162 MW )
Angostura II
Eoloeléctrica 1,600
Mexicali I
(27 MW)
La Parota U1 y U2
(455 MW)
Mérida
(526 MW)
Tamaulipas
(3 x 200 y 300 MW)
(136 MW)
I, II, III y IV
Aguascalientes
(872 MW)
(1,088 MW)
Monterrey IV
Centro II
(660 MW )
Baja California IV (SLRC) 522 MW
San Luis Potosí
(862 MW)
Guadalajara I
(908 MW)
Mazatlán
(867 MW)
Eólica I
(200 MW)
Cerritos
Colorados
Fase I y II
(2x27 MW)
Paso de la Reina
(543 MW)
Mérida TG
(169 MW)
Eólica II
(200 MW)
Los Cabos I TG
(94 MW)
Salamanca 680 MW
Valladolid IV
(542 MW)
Coahuila I y II
(300 MW)
Azufres III Fase
II
(27MW)
Humeros III Fase B
(27 MW)
Cancún TG
(169 MW)
capacidad requerida adicional
Servicio público 2016 – 2022
4. POISE 2014-2028
1/ Las cifras están redondeadas a números enteros, por lo que los totales podrían no corresponder exactamente
Total: 26,955 MW1/
Hidroeléctrica
Ciclo Combinado
Nueva
Generación limpia
Total
MW
1,180
11,013
12,775
26,955 1/
Eoloeléctrica 1,200
Turbogás 94
Noroeste II y IV
(2X1400 MW)
Valladolid V
(542 MW)
Baja California VI
(Ensenada)
Pacífico II y III
(1x700 MW)
Oriental l, II, III, IV, IX Y X
(3x1225 MW)
(565 MW)
Salamanca II
(680 MW)
Mérida V
(540 MW)
Norte VI y VII (Chih.)
(2x968 MW)
Valle de México III
(601 MW) Tenosique
(422 MW)
Central II (Tula)
(1,162 MW)
Baja California V (Mexicali)
(522 MW)
Todos Santos II
(123 MW)
Sistema Pescados (La Antigua)
(121 MW)
Xúchile
s
(54 MW)
La Paz II
(117 MW)
Tamazunchale II y III
(2x1,121MW)
Omitlán
(231 MW)
Madera (352 MW)
Todos Santos III
(123 MW)
Occidental I y II
(1400MW)
Los Cabos II TG
(94 MW)
Cd. Constitución
(137 MW)
Eólica III, VI,
(4X200 MW)
Santa Rosalía III
(11 MW)
Solar 600
Solar V
(100 MW)
Geotermoeléctrica 81
Cerritos Colorados
Fase III
(27 MW)
Sabinas I y II
(2X700 MW)
Eólica IV
(200 MW)
Solar VI
(100 MW)
San Luis Potosi
II
(862 MW)
Eólica V
(200 MW)
Geotermoeléctrica I y II
(2X27 MW)
Solar VII
(100 MW)
(1x1400 MW)
Solar VIII
(100 MW)
Solar X
(100 MW)
Aguascalientes
II
(872MW)
VII y VIII
Combustión Interna 11
Oriental V y VI
(1400 MW)
Solar IX
(100 MW)
capacidad requerida adicional
Servicio público (2023 – 2028)
4. POISE 2014-2028
EOR IN OIL PRODUCTION
Millionsofbarrelsperday
EOR
Oil production
The world's largest nitrogen-injection EOR project, led by PEMEX in Cantarrell
GAS PRODUCTION IN ENE. INCLUDES SHALE GAS
bcf
Natural gas production (bcf)
EOR
• 600 trillion cubic feet of shale gas. Ranks 6th largest in the world
• 13 billion barrels of recoverable shale oil resources . Ranks 8th largest in the world.
http://oilprice.com/Energy/Energy-General/Mexico-Shale-Gas-Industry-and-Energy-
Reform.html
LOCATION OF SHALE GAS RESERVES IN MEXICO
Localization of Shale gas in Mexico
1. The large Mexican oil fields,
that are candidates for EOR, is
expected to need up 50
million tons of CO2 per year
2. The largest emitter region of
CO2 (20.1 million tons per
year)
CO2-EOR Potential
The Gulf of Mexico is
R. Lacy et al. / International Journal of
Greenhouse Gas Control 19 (2013) 212–219
CO2 sources in the Gulf of Mexico 2013
R. Lacy et al. / International Journal of Greenhouse Gas Control 19 (2013) 212–219
It is to increase oil production by CO2-EOR
from 659 to 1,758 MMB
CO2-EOR Potential
Potential CO2 - EOR
Anthropogenic sources of CO2
Federal comission of Electricity
Natural sources of CO2
Quebrache (260 MMSCFD / 13 MTonne/D)
Ogarri
o
Coyotes
San Andrés
Carmit
o
Cosoleacaque: CPQC (80 MMSCFD / 4
MTonne/D)
CFE Tuxpan (390 MMSCFD / 19.5 MTonne/D)
Tres Hermanos (5 MMSCFD / 250 Tonne/D)
Maloob
Copy right by Fernando Rodríguez de la Garza, CO2 – EOR program in Mexico, Gas networking
meeting , Cuernavaca Morelos, Mexico 11-12 February 2014
CO2 can be capture from Tuxpan power station to inject on
Chicontepec fields.
Pilot testing will be necessary in order to confirm oil recovery using CO2
19
• In 2008 CFE started several actions related to CCS
• 2009 CFE contracted to the Mario Molina Center and IIE to
do preliminary studies for a demostrative CO2 capture plant
• 2010 a pilot test of CO2 continuous injection was performed
in the Coyotes field
• In 2012 the Mexican Congress approved the General Climate
Change Law to reduce greenhouse gas emissions
One of its strategies to reach this objective is the application
of CCS on fossil fuel power plants and in the oil industry for
EOR
Current status of CO2-EOR in
PEMEX-CFE
Future plans on CCUS
CCS project funded by The global CCS institute and U.S. DOE 2014
• Workshop on storage in Mexico City IPN in August- Focus on Burgos and Sabinas
basins. Geologists from industry and academy
• Workshop in Mexico City CFE in September –Students including chemists &
engineers from industry, academia and research institutions
• Workshop Hermosillo CFE and will be directed at undergraduate students in the
earth sciences area
IEAGHG Summer school 2016 will be hosted by IIE Cuernavaca Morelos
CCUS-EOR project of PEMEX funded by Mexican government (start 2015
a period of 3 years)
• Design and implement a CO2-EOR pilot test at the Cinco Presidentes field by using
the high purity CO2 to be captured in the ammonia plants in Petrochemical Center
of Cosoleacaque, CPQC.
• Full scale CO2-EOR implementation in the selected field will allow for elimination
of current CO2 emissions from CPQC, of about 100-120 MMSCFD.
• ( 5,000 a 6,000 ton/d)
• It is expected that 60-70% of the injected CO2 will remain sequestered in
the reservoir. It will be confirmed by the pilot results
Long term
SENER- SEMARNAT before 2018 (SENER, Enero 2014, SEMARNAT)
• Pilot plant 50 MW to provide 5 MMSCF/d CO2 for a EOR project
• Demostration plant 250 MW to provide 25 MMSCF/d CO2 for EOR
project in a big reservoir
CCS SENER – WORLD BANK
Pilot plant 2 MW in Poza Rica Veracruz
• SENER-PEMEX-CFE–SEMARNAT: Currently defining the
Technology Route Map for CCUS-EOR of Mexico. Implementation will
start later in 2014.
Future plan on CCUS
•CCS in NGCC will be needed due to the large participation
of this technology in Power Generation
•There are several projects in CCS that are being promoted
and carried out
•PEMEX will need CO2 for its EOR projects that exceeds
the natural sources available
•PEMEX needs to assess the effectiveness of CO2 EOR in
the Mexican oil fields
•Resources are limited and are slowing down some projects
•EOR is one on the main drivers for CCS in Mexico because
CO2 for EOR provides a positive immediate economic
benefit, as well as helping to mitigate long-term
environmental impacts.
Conclusions

Contenu connexe

Tendances

Sesti project: Global Sustainable Energy options
Sesti project: Global Sustainable Energy optionsSesti project: Global Sustainable Energy options
Sesti project: Global Sustainable Energy optionsVictor Van Rij
 
Meier_REET_425_Final_Project
Meier_REET_425_Final_ProjectMeier_REET_425_Final_Project
Meier_REET_425_Final_Projectjmeier72
 
M.Sc thesis Presentation
M.Sc thesis PresentationM.Sc thesis Presentation
M.Sc thesis Presentationubongsimon
 
Pakistan nuclear energy vs electricity by noman javed
Pakistan nuclear energy vs electricity by noman javed Pakistan nuclear energy vs electricity by noman javed
Pakistan nuclear energy vs electricity by noman javed noman
 
Zimtu Research: Lakeland Resources Inc. Update - Athabasca Basin Uranium Expl...
Zimtu Research: Lakeland Resources Inc. Update - Athabasca Basin Uranium Expl...Zimtu Research: Lakeland Resources Inc. Update - Athabasca Basin Uranium Expl...
Zimtu Research: Lakeland Resources Inc. Update - Athabasca Basin Uranium Expl...Lakeland Resources Inc. (TSXv: LK)
 
Greening Iew 2007
Greening Iew 2007Greening Iew 2007
Greening Iew 2007LGDoone
 
GEOTHERMAL INDONESIA 2014
GEOTHERMAL INDONESIA 2014GEOTHERMAL INDONESIA 2014
GEOTHERMAL INDONESIA 2014Dinno Kurniawan
 
Climate finance sato (jica)coop geothermal energy dvpt indonesia-ccxg gf marc...
Climate finance sato (jica)coop geothermal energy dvpt indonesia-ccxg gf marc...Climate finance sato (jica)coop geothermal energy dvpt indonesia-ccxg gf marc...
Climate finance sato (jica)coop geothermal energy dvpt indonesia-ccxg gf marc...OECD Environment
 
Opportunities and challenges for renewable energy policy in India
Opportunities and challenges for renewable energy policy in IndiaOpportunities and challenges for renewable energy policy in India
Opportunities and challenges for renewable energy policy in IndiaPallav Purohit
 
kundankulan nuclear power plant 2
kundankulan nuclear power plant 2kundankulan nuclear power plant 2
kundankulan nuclear power plant 2akshay ghanwat
 
Réflexions sur le secteur nucléaire américain
Réflexions sur le secteur nucléaire américainRéflexions sur le secteur nucléaire américain
Réflexions sur le secteur nucléaire américainGuillaume Vaast
 
Roopur power plant and iran nuclear conflict
Roopur power plant and iran nuclear conflictRoopur power plant and iran nuclear conflict
Roopur power plant and iran nuclear conflictImran Sajol
 

Tendances (19)

Sesti project: Global Sustainable Energy options
Sesti project: Global Sustainable Energy optionsSesti project: Global Sustainable Energy options
Sesti project: Global Sustainable Energy options
 
Meier_REET_425_Final_Project
Meier_REET_425_Final_ProjectMeier_REET_425_Final_Project
Meier_REET_425_Final_Project
 
M.Sc thesis Presentation
M.Sc thesis PresentationM.Sc thesis Presentation
M.Sc thesis Presentation
 
Pakistan nuclear energy vs electricity by noman javed
Pakistan nuclear energy vs electricity by noman javed Pakistan nuclear energy vs electricity by noman javed
Pakistan nuclear energy vs electricity by noman javed
 
Zimtu Research: Lakeland Resources Inc. Update - Athabasca Basin Uranium Expl...
Zimtu Research: Lakeland Resources Inc. Update - Athabasca Basin Uranium Expl...Zimtu Research: Lakeland Resources Inc. Update - Athabasca Basin Uranium Expl...
Zimtu Research: Lakeland Resources Inc. Update - Athabasca Basin Uranium Expl...
 
R.a. 9513-chapter-1
R.a. 9513-chapter-1R.a. 9513-chapter-1
R.a. 9513-chapter-1
 
3 mwpv plant
3 mwpv plant3 mwpv plant
3 mwpv plant
 
Greening Iew 2007
Greening Iew 2007Greening Iew 2007
Greening Iew 2007
 
GEOTHERMAL INDONESIA 2014
GEOTHERMAL INDONESIA 2014GEOTHERMAL INDONESIA 2014
GEOTHERMAL INDONESIA 2014
 
Climate finance sato (jica)coop geothermal energy dvpt indonesia-ccxg gf marc...
Climate finance sato (jica)coop geothermal energy dvpt indonesia-ccxg gf marc...Climate finance sato (jica)coop geothermal energy dvpt indonesia-ccxg gf marc...
Climate finance sato (jica)coop geothermal energy dvpt indonesia-ccxg gf marc...
 
Opportunities and challenges for renewable energy policy in India
Opportunities and challenges for renewable energy policy in IndiaOpportunities and challenges for renewable energy policy in India
Opportunities and challenges for renewable energy policy in India
 
Eia of clp jhajjar
Eia of clp jhajjarEia of clp jhajjar
Eia of clp jhajjar
 
Energy
EnergyEnergy
Energy
 
Utah Clean Power Plan Stakeholder Process
Utah Clean Power Plan Stakeholder ProcessUtah Clean Power Plan Stakeholder Process
Utah Clean Power Plan Stakeholder Process
 
kundankulan nuclear power plant 2
kundankulan nuclear power plant 2kundankulan nuclear power plant 2
kundankulan nuclear power plant 2
 
Réflexions sur le secteur nucléaire américain
Réflexions sur le secteur nucléaire américainRéflexions sur le secteur nucléaire américain
Réflexions sur le secteur nucléaire américain
 
Roopur power plant and iran nuclear conflict
Roopur power plant and iran nuclear conflictRoopur power plant and iran nuclear conflict
Roopur power plant and iran nuclear conflict
 
Reaol
ReaolReaol
Reaol
 
Pv plant references
Pv plant referencesPv plant references
Pv plant references
 

Similaire à Gas CCUS in Mexico - Abigail Gonzalez Diaz at the UKCCSRC Gas CCS Meeting, University of Sussex, 25 June 2014

Geothermal Development in Guatemala.pptx
Geothermal Development  in Guatemala.pptxGeothermal Development  in Guatemala.pptx
Geothermal Development in Guatemala.pptxluisherrera184466
 
Concentrated Solar Power Training : Markets
Concentrated Solar Power Training : MarketsConcentrated Solar Power Training : Markets
Concentrated Solar Power Training : MarketsLeonardo ENERGY
 
Submarine geothermics. hydrothermal vents and electricity generation
Submarine geothermics. hydrothermal vents and electricity generationSubmarine geothermics. hydrothermal vents and electricity generation
Submarine geothermics. hydrothermal vents and electricity generationjjsoto00
 
01 Green Power.ppt form uit rgpv very important topic
01 Green Power.ppt form uit rgpv very important topic01 Green Power.ppt form uit rgpv very important topic
01 Green Power.ppt form uit rgpv very important topicsahaniashish582003
 
Greening Iew 2007
Greening Iew 2007Greening Iew 2007
Greening Iew 2007guest443235
 
The glg slide deck as 1700 edt monday 2 may 2011
The glg slide deck as 1700 edt monday 2 may 2011 The glg slide deck as 1700 edt monday 2 may 2011
The glg slide deck as 1700 edt monday 2 may 2011 tdrolet
 
Advanced Fossil Energy Technologies: Presentation by the US Dept of Energy Of...
Advanced Fossil Energy Technologies: Presentation by the US Dept of Energy Of...Advanced Fossil Energy Technologies: Presentation by the US Dept of Energy Of...
Advanced Fossil Energy Technologies: Presentation by the US Dept of Energy Of...atlanticcouncil
 
Energy Survey Future Use
Energy Survey  Future UseEnergy Survey  Future Use
Energy Survey Future UseDavid Tennant
 
UNU-GTP-2013-20.pdf
UNU-GTP-2013-20.pdfUNU-GTP-2013-20.pdf
UNU-GTP-2013-20.pdfhenoch16
 
Climate Change, Can Technological Development save the world ?
Climate Change, Can Technological Development save the world ?Climate Change, Can Technological Development save the world ?
Climate Change, Can Technological Development save the world ?Mohammed Alnajjar
 
ENERGY AND ENERGY SYSTEMS OF THE FUTURE : Keynote address at ICCES14 at M E A...
ENERGY AND ENERGY SYSTEMS OF THE FUTURE : Keynote address at ICCES14 at M E A...ENERGY AND ENERGY SYSTEMS OF THE FUTURE : Keynote address at ICCES14 at M E A...
ENERGY AND ENERGY SYSTEMS OF THE FUTURE : Keynote address at ICCES14 at M E A...Prof. Mohandas K P
 
Apec workshop 2 presentation 12 lh ci cinco presidentes-pemex-apec workshop 2
Apec workshop 2 presentation 12 lh ci cinco presidentes-pemex-apec workshop 2Apec workshop 2 presentation 12 lh ci cinco presidentes-pemex-apec workshop 2
Apec workshop 2 presentation 12 lh ci cinco presidentes-pemex-apec workshop 2Global CCS Institute
 
Nuclear Power in Brazil and Latin America
Nuclear Power in Brazil and Latin AmericaNuclear Power in Brazil and Latin America
Nuclear Power in Brazil and Latin AmericaLeonam Guimarães
 
IEEE Presentation on Shale Resources and Environmental Cost of Energy
IEEE Presentation on Shale Resources and Environmental Cost of EnergyIEEE Presentation on Shale Resources and Environmental Cost of Energy
IEEE Presentation on Shale Resources and Environmental Cost of EnergyDan Arthur
 
Daniel Kammen-La ciencia y la política de la energía sostenible
Daniel Kammen-La ciencia y la política de la energía sostenibleDaniel Kammen-La ciencia y la política de la energía sostenible
Daniel Kammen-La ciencia y la política de la energía sostenibleFundación Ramón Areces
 
Lyubovsky argus methanol forum sept 2018
Lyubovsky argus methanol forum sept 2018Lyubovsky argus methanol forum sept 2018
Lyubovsky argus methanol forum sept 2018Maxim Lyubovsky
 
AlChE-Global-CCS_Institute-Presentation-101813
AlChE-Global-CCS_Institute-Presentation-101813AlChE-Global-CCS_Institute-Presentation-101813
AlChE-Global-CCS_Institute-Presentation-101813Global CCS Institute
 

Similaire à Gas CCUS in Mexico - Abigail Gonzalez Diaz at the UKCCSRC Gas CCS Meeting, University of Sussex, 25 June 2014 (20)

Geothermal Development in Guatemala.pptx
Geothermal Development  in Guatemala.pptxGeothermal Development  in Guatemala.pptx
Geothermal Development in Guatemala.pptx
 
Concentrated Solar Power Training : Markets
Concentrated Solar Power Training : MarketsConcentrated Solar Power Training : Markets
Concentrated Solar Power Training : Markets
 
Submarine geothermics. hydrothermal vents and electricity generation
Submarine geothermics. hydrothermal vents and electricity generationSubmarine geothermics. hydrothermal vents and electricity generation
Submarine geothermics. hydrothermal vents and electricity generation
 
Atlantic Council - Darren Mollot
Atlantic Council - Darren MollotAtlantic Council - Darren Mollot
Atlantic Council - Darren Mollot
 
01 Green Power.ppt form uit rgpv very important topic
01 Green Power.ppt form uit rgpv very important topic01 Green Power.ppt form uit rgpv very important topic
01 Green Power.ppt form uit rgpv very important topic
 
Greening Iew 2007
Greening Iew 2007Greening Iew 2007
Greening Iew 2007
 
Argentina s12
Argentina s12Argentina s12
Argentina s12
 
The glg slide deck as 1700 edt monday 2 may 2011
The glg slide deck as 1700 edt monday 2 may 2011 The glg slide deck as 1700 edt monday 2 may 2011
The glg slide deck as 1700 edt monday 2 may 2011
 
Advanced Fossil Energy Technologies: Presentation by the US Dept of Energy Of...
Advanced Fossil Energy Technologies: Presentation by the US Dept of Energy Of...Advanced Fossil Energy Technologies: Presentation by the US Dept of Energy Of...
Advanced Fossil Energy Technologies: Presentation by the US Dept of Energy Of...
 
Energy Survey Future Use
Energy Survey  Future UseEnergy Survey  Future Use
Energy Survey Future Use
 
UNU-GTP-2013-20.pdf
UNU-GTP-2013-20.pdfUNU-GTP-2013-20.pdf
UNU-GTP-2013-20.pdf
 
Climate Change, Can Technological Development save the world ?
Climate Change, Can Technological Development save the world ?Climate Change, Can Technological Development save the world ?
Climate Change, Can Technological Development save the world ?
 
ENERGY AND ENERGY SYSTEMS OF THE FUTURE : Keynote address at ICCES14 at M E A...
ENERGY AND ENERGY SYSTEMS OF THE FUTURE : Keynote address at ICCES14 at M E A...ENERGY AND ENERGY SYSTEMS OF THE FUTURE : Keynote address at ICCES14 at M E A...
ENERGY AND ENERGY SYSTEMS OF THE FUTURE : Keynote address at ICCES14 at M E A...
 
Apec workshop 2 presentation 12 lh ci cinco presidentes-pemex-apec workshop 2
Apec workshop 2 presentation 12 lh ci cinco presidentes-pemex-apec workshop 2Apec workshop 2 presentation 12 lh ci cinco presidentes-pemex-apec workshop 2
Apec workshop 2 presentation 12 lh ci cinco presidentes-pemex-apec workshop 2
 
Nuclear Power in Brazil and Latin America
Nuclear Power in Brazil and Latin AmericaNuclear Power in Brazil and Latin America
Nuclear Power in Brazil and Latin America
 
IEEE Presentation on Shale Resources and Environmental Cost of Energy
IEEE Presentation on Shale Resources and Environmental Cost of EnergyIEEE Presentation on Shale Resources and Environmental Cost of Energy
IEEE Presentation on Shale Resources and Environmental Cost of Energy
 
Daniel Kammen-La ciencia y la política de la energía sostenible
Daniel Kammen-La ciencia y la política de la energía sostenibleDaniel Kammen-La ciencia y la política de la energía sostenible
Daniel Kammen-La ciencia y la política de la energía sostenible
 
Lyubovsky argus methanol forum sept 2018
Lyubovsky argus methanol forum sept 2018Lyubovsky argus methanol forum sept 2018
Lyubovsky argus methanol forum sept 2018
 
CCS for Gas-Fired Power Plants presented at the MIT Carbon Sequestration Foru...
CCS for Gas-Fired Power Plants presented at the MIT Carbon Sequestration Foru...CCS for Gas-Fired Power Plants presented at the MIT Carbon Sequestration Foru...
CCS for Gas-Fired Power Plants presented at the MIT Carbon Sequestration Foru...
 
AlChE-Global-CCS_Institute-Presentation-101813
AlChE-Global-CCS_Institute-Presentation-101813AlChE-Global-CCS_Institute-Presentation-101813
AlChE-Global-CCS_Institute-Presentation-101813
 

Plus de UK Carbon Capture and Storage Research Centre

Plus de UK Carbon Capture and Storage Research Centre (20)

CCUS Roadmap for Mexico - presentation by M. Vita Peralta Martínez (IIE - Ele...
CCUS Roadmap for Mexico - presentation by M. Vita Peralta Martínez (IIE - Ele...CCUS Roadmap for Mexico - presentation by M. Vita Peralta Martínez (IIE - Ele...
CCUS Roadmap for Mexico - presentation by M. Vita Peralta Martínez (IIE - Ele...
 
Advances in Rock Physics Modelling and Improved Estimation of CO2 Saturation,...
Advances in Rock Physics Modelling and Improved Estimation of CO2 Saturation,...Advances in Rock Physics Modelling and Improved Estimation of CO2 Saturation,...
Advances in Rock Physics Modelling and Improved Estimation of CO2 Saturation,...
 
Numerical Modelling of Fracture Growth and Caprock Integrity During CO2 Injec...
Numerical Modelling of Fracture Growth and Caprock Integrity During CO2 Injec...Numerical Modelling of Fracture Growth and Caprock Integrity During CO2 Injec...
Numerical Modelling of Fracture Growth and Caprock Integrity During CO2 Injec...
 
Assessing Uncertainty of Time Lapse Seismic Response Due to Geomechanical Def...
Assessing Uncertainty of Time Lapse Seismic Response Due to Geomechanical Def...Assessing Uncertainty of Time Lapse Seismic Response Due to Geomechanical Def...
Assessing Uncertainty of Time Lapse Seismic Response Due to Geomechanical Def...
 
20 Years and 20Mt, Statoil Storage Experience, Andrew Cavanagh - Geophysical ...
20 Years and 20Mt, Statoil Storage Experience, Andrew Cavanagh - Geophysical ...20 Years and 20Mt, Statoil Storage Experience, Andrew Cavanagh - Geophysical ...
20 Years and 20Mt, Statoil Storage Experience, Andrew Cavanagh - Geophysical ...
 
Modelling Fault Reactivation, Induced Seismicity, and Leakage During Undergro...
Modelling Fault Reactivation, Induced Seismicity, and Leakage During Undergro...Modelling Fault Reactivation, Induced Seismicity, and Leakage During Undergro...
Modelling Fault Reactivation, Induced Seismicity, and Leakage During Undergro...
 
Pore scale dynamics and the interpretation of flow processes - Martin Blunt, ...
Pore scale dynamics and the interpretation of flow processes - Martin Blunt, ...Pore scale dynamics and the interpretation of flow processes - Martin Blunt, ...
Pore scale dynamics and the interpretation of flow processes - Martin Blunt, ...
 
Passive seismic monitoring for CO2 storage sites - Anna Stork, University of ...
Passive seismic monitoring for CO2 storage sites - Anna Stork, University of ...Passive seismic monitoring for CO2 storage sites - Anna Stork, University of ...
Passive seismic monitoring for CO2 storage sites - Anna Stork, University of ...
 
Multiphase flow modelling of calcite dissolution patterns from core scale to ...
Multiphase flow modelling of calcite dissolution patterns from core scale to ...Multiphase flow modelling of calcite dissolution patterns from core scale to ...
Multiphase flow modelling of calcite dissolution patterns from core scale to ...
 
Long term safety of geological co2 storage: lessons from Bravo Dome Natural C...
Long term safety of geological co2 storage: lessons from Bravo Dome Natural C...Long term safety of geological co2 storage: lessons from Bravo Dome Natural C...
Long term safety of geological co2 storage: lessons from Bravo Dome Natural C...
 
Challenges in the chemical industry, jay brookes (boc) industry ccs worksho...
Challenges in the chemical industry, jay brookes (boc)   industry ccs worksho...Challenges in the chemical industry, jay brookes (boc)   industry ccs worksho...
Challenges in the chemical industry, jay brookes (boc) industry ccs worksho...
 
Overall Network Issues, Tim Dumenil (Pale Blue Dot) - Industry CCS Workshop, ...
Overall Network Issues, Tim Dumenil (Pale Blue Dot) - Industry CCS Workshop, ...Overall Network Issues, Tim Dumenil (Pale Blue Dot) - Industry CCS Workshop, ...
Overall Network Issues, Tim Dumenil (Pale Blue Dot) - Industry CCS Workshop, ...
 
Challenges in the Steel Industry and the Network, James Watt (Amec) - Industr...
Challenges in the Steel Industry and the Network, James Watt (Amec) - Industr...Challenges in the Steel Industry and the Network, James Watt (Amec) - Industr...
Challenges in the Steel Industry and the Network, James Watt (Amec) - Industr...
 
Horizon 2020 Update, Jon Gibbins, University of Edinburgh - UKCCSRC Strathcly...
Horizon 2020 Update, Jon Gibbins, University of Edinburgh - UKCCSRC Strathcly...Horizon 2020 Update, Jon Gibbins, University of Edinburgh - UKCCSRC Strathcly...
Horizon 2020 Update, Jon Gibbins, University of Edinburgh - UKCCSRC Strathcly...
 
Guangdong Offshore CCUS Project (GOCCUS) - Xi Liang, University of Edinburgh ...
Guangdong Offshore CCUS Project (GOCCUS) - Xi Liang, University of Edinburgh ...Guangdong Offshore CCUS Project (GOCCUS) - Xi Liang, University of Edinburgh ...
Guangdong Offshore CCUS Project (GOCCUS) - Xi Liang, University of Edinburgh ...
 
Changes in the Dutch CCS Landscape - Jan Brouwer, CATO - UKCCSRC Strathclyde ...
Changes in the Dutch CCS Landscape - Jan Brouwer, CATO - UKCCSRC Strathclyde ...Changes in the Dutch CCS Landscape - Jan Brouwer, CATO - UKCCSRC Strathclyde ...
Changes in the Dutch CCS Landscape - Jan Brouwer, CATO - UKCCSRC Strathclyde ...
 
Research Coordination Network on Carbon Capture, Utilization and Storage Fund...
Research Coordination Network on Carbon Capture, Utilization and Storage Fund...Research Coordination Network on Carbon Capture, Utilization and Storage Fund...
Research Coordination Network on Carbon Capture, Utilization and Storage Fund...
 
Carbon Capture and Storage in Australia - Tania Constable, CO2CRC - UKCCSRC S...
Carbon Capture and Storage in Australia - Tania Constable, CO2CRC - UKCCSRC S...Carbon Capture and Storage in Australia - Tania Constable, CO2CRC - UKCCSRC S...
Carbon Capture and Storage in Australia - Tania Constable, CO2CRC - UKCCSRC S...
 
Computational Modelling and Optimisation of Carbon Capture Reactors, Daniel S...
Computational Modelling and Optimisation of Carbon Capture Reactors, Daniel S...Computational Modelling and Optimisation of Carbon Capture Reactors, Daniel S...
Computational Modelling and Optimisation of Carbon Capture Reactors, Daniel S...
 
Effective Adsorbents for Establishing Solids Looping as a Next Generation NG ...
Effective Adsorbents for Establishing Solids Looping as a Next Generation NG ...Effective Adsorbents for Establishing Solids Looping as a Next Generation NG ...
Effective Adsorbents for Establishing Solids Looping as a Next Generation NG ...
 

Dernier

Call Girls Wakad Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Wakad Call Me 7737669865 Budget Friendly No Advance BookingCall Girls Wakad Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Wakad Call Me 7737669865 Budget Friendly No Advance Bookingroncy bisnoi
 
Unleashing the Power of the SORA AI lastest leap
Unleashing the Power of the SORA AI lastest leapUnleashing the Power of the SORA AI lastest leap
Unleashing the Power of the SORA AI lastest leapRishantSharmaFr
 
University management System project report..pdf
University management System project report..pdfUniversity management System project report..pdf
University management System project report..pdfKamal Acharya
 
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 BookingVIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Bookingdharasingh5698
 
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...ranjana rawat
 
Thermal Engineering Unit - I & II . ppt
Thermal Engineering  Unit - I & II . pptThermal Engineering  Unit - I & II . ppt
Thermal Engineering Unit - I & II . pptDineshKumar4165
 
BSides Seattle 2024 - Stopping Ethan Hunt From Taking Your Data.pptx
BSides Seattle 2024 - Stopping Ethan Hunt From Taking Your Data.pptxBSides Seattle 2024 - Stopping Ethan Hunt From Taking Your Data.pptx
BSides Seattle 2024 - Stopping Ethan Hunt From Taking Your Data.pptxfenichawla
 
VIP Call Girls Palanpur 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Palanpur 7001035870 Whatsapp Number, 24/07 BookingVIP Call Girls Palanpur 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Palanpur 7001035870 Whatsapp Number, 24/07 Bookingdharasingh5698
 
Double Revolving field theory-how the rotor develops torque
Double Revolving field theory-how the rotor develops torqueDouble Revolving field theory-how the rotor develops torque
Double Revolving field theory-how the rotor develops torqueBhangaleSonal
 
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...roncy bisnoi
 
Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...Call Girls in Nagpur High Profile
 
chapter 5.pptx: drainage and irrigation engineering
chapter 5.pptx: drainage and irrigation engineeringchapter 5.pptx: drainage and irrigation engineering
chapter 5.pptx: drainage and irrigation engineeringmulugeta48
 
VIP Model Call Girls Kothrud ( Pune ) Call ON 8005736733 Starting From 5K to ...
VIP Model Call Girls Kothrud ( Pune ) Call ON 8005736733 Starting From 5K to ...VIP Model Call Girls Kothrud ( Pune ) Call ON 8005736733 Starting From 5K to ...
VIP Model Call Girls Kothrud ( Pune ) Call ON 8005736733 Starting From 5K to ...SUHANI PANDEY
 
Call Girls Walvekar Nagar Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Walvekar Nagar Call Me 7737669865 Budget Friendly No Advance BookingCall Girls Walvekar Nagar Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Walvekar Nagar Call Me 7737669865 Budget Friendly No Advance Bookingroncy bisnoi
 
Java Programming :Event Handling(Types of Events)
Java Programming :Event Handling(Types of Events)Java Programming :Event Handling(Types of Events)
Java Programming :Event Handling(Types of Events)simmis5
 
Generative AI or GenAI technology based PPT
Generative AI or GenAI technology based PPTGenerative AI or GenAI technology based PPT
Generative AI or GenAI technology based PPTbhaskargani46
 

Dernier (20)

Call Girls Wakad Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Wakad Call Me 7737669865 Budget Friendly No Advance BookingCall Girls Wakad Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Wakad Call Me 7737669865 Budget Friendly No Advance Booking
 
Unleashing the Power of the SORA AI lastest leap
Unleashing the Power of the SORA AI lastest leapUnleashing the Power of the SORA AI lastest leap
Unleashing the Power of the SORA AI lastest leap
 
University management System project report..pdf
University management System project report..pdfUniversity management System project report..pdf
University management System project report..pdf
 
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 BookingVIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Booking
 
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
 
Thermal Engineering Unit - I & II . ppt
Thermal Engineering  Unit - I & II . pptThermal Engineering  Unit - I & II . ppt
Thermal Engineering Unit - I & II . ppt
 
BSides Seattle 2024 - Stopping Ethan Hunt From Taking Your Data.pptx
BSides Seattle 2024 - Stopping Ethan Hunt From Taking Your Data.pptxBSides Seattle 2024 - Stopping Ethan Hunt From Taking Your Data.pptx
BSides Seattle 2024 - Stopping Ethan Hunt From Taking Your Data.pptx
 
VIP Call Girls Palanpur 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Palanpur 7001035870 Whatsapp Number, 24/07 BookingVIP Call Girls Palanpur 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Palanpur 7001035870 Whatsapp Number, 24/07 Booking
 
Double Revolving field theory-how the rotor develops torque
Double Revolving field theory-how the rotor develops torqueDouble Revolving field theory-how the rotor develops torque
Double Revolving field theory-how the rotor develops torque
 
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
 
Call Now ≽ 9953056974 ≼🔝 Call Girls In New Ashok Nagar ≼🔝 Delhi door step de...
Call Now ≽ 9953056974 ≼🔝 Call Girls In New Ashok Nagar  ≼🔝 Delhi door step de...Call Now ≽ 9953056974 ≼🔝 Call Girls In New Ashok Nagar  ≼🔝 Delhi door step de...
Call Now ≽ 9953056974 ≼🔝 Call Girls In New Ashok Nagar ≼🔝 Delhi door step de...
 
Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...
 
chapter 5.pptx: drainage and irrigation engineering
chapter 5.pptx: drainage and irrigation engineeringchapter 5.pptx: drainage and irrigation engineering
chapter 5.pptx: drainage and irrigation engineering
 
VIP Model Call Girls Kothrud ( Pune ) Call ON 8005736733 Starting From 5K to ...
VIP Model Call Girls Kothrud ( Pune ) Call ON 8005736733 Starting From 5K to ...VIP Model Call Girls Kothrud ( Pune ) Call ON 8005736733 Starting From 5K to ...
VIP Model Call Girls Kothrud ( Pune ) Call ON 8005736733 Starting From 5K to ...
 
(INDIRA) Call Girl Aurangabad Call Now 8617697112 Aurangabad Escorts 24x7
(INDIRA) Call Girl Aurangabad Call Now 8617697112 Aurangabad Escorts 24x7(INDIRA) Call Girl Aurangabad Call Now 8617697112 Aurangabad Escorts 24x7
(INDIRA) Call Girl Aurangabad Call Now 8617697112 Aurangabad Escorts 24x7
 
Call Girls in Ramesh Nagar Delhi 💯 Call Us 🔝9953056974 🔝 Escort Service
Call Girls in Ramesh Nagar Delhi 💯 Call Us 🔝9953056974 🔝 Escort ServiceCall Girls in Ramesh Nagar Delhi 💯 Call Us 🔝9953056974 🔝 Escort Service
Call Girls in Ramesh Nagar Delhi 💯 Call Us 🔝9953056974 🔝 Escort Service
 
(INDIRA) Call Girl Bhosari Call Now 8617697112 Bhosari Escorts 24x7
(INDIRA) Call Girl Bhosari Call Now 8617697112 Bhosari Escorts 24x7(INDIRA) Call Girl Bhosari Call Now 8617697112 Bhosari Escorts 24x7
(INDIRA) Call Girl Bhosari Call Now 8617697112 Bhosari Escorts 24x7
 
Call Girls Walvekar Nagar Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Walvekar Nagar Call Me 7737669865 Budget Friendly No Advance BookingCall Girls Walvekar Nagar Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Walvekar Nagar Call Me 7737669865 Budget Friendly No Advance Booking
 
Java Programming :Event Handling(Types of Events)
Java Programming :Event Handling(Types of Events)Java Programming :Event Handling(Types of Events)
Java Programming :Event Handling(Types of Events)
 
Generative AI or GenAI technology based PPT
Generative AI or GenAI technology based PPTGenerative AI or GenAI technology based PPT
Generative AI or GenAI technology based PPT
 

Gas CCUS in Mexico - Abigail Gonzalez Diaz at the UKCCSRC Gas CCS Meeting, University of Sussex, 25 June 2014

  • 1. GAS CCUS IN MEXICO Abigail González Díaz José Miguel González-Santaló Instituto de Investigaciones Electricas (IIE) Mexico Gas CCS Meeting Brighton, UK June 25, 2014
  • 2. 1. Why CCS and CO2 for EOR in Mexico? • Growth in electricity production • Electricity generation • Natural gas and oil production • CO2-EOR Potential 2. Current status of CO2-EOR in PEMEX-CFE 3. Future plant on CCUS Outline
  • 3. MAIN SOURCES OF INFORMATION 1. Estrategia Nacional de Energía 2013-2027 Prospectiva del Sector Eléctrico 2013-2027 Secretaría de Energía, México www.sener.gob.mx/portal/publicaciones.html 2. R. Lacy et al. Initial assessment of the potential for future CCUS with EOR projects in Mexico using CO2 captured from fossil fuel industrial plants, International Journal of Greenhouse Gas Control 19 (2013) 212–219 3. Fernando Rodríguez de la Garza, CO2 – EOR program in Mexico, Gas networking meeting , Cuernavaca Morelos, Mexico 11-12 February 2014
  • 4. The two major energy companies in Mexico are state owned 1. The Mexican oil company Petróleos Mexicanos (PEMEX) is the second most profitable company in Latin America 2. The Utility Company Comisión Federal de Electricidad (CFE) Mexican oil has been controlled exclusively by the state-owned Pemex for more than 75 years MEXICO OPENS UP ITS ENERGY MARKETS On December 12, 2013, Mexican legislators approved controversial reforms to the country’s energy sector
  • 5. Why CCS and CO2 for EOR? • Fast growth. Installed capacity of 62 GW in 2009, 113 GW in 2028 • Natural gas is and will be the dominant energy source in 2028 • The oil industry will require large amounts of CO2 for EOR Mexico ‘s mitigation target “reduce GHG emissions by 50% below 2002 levels by 2050”
  • 6. Growth in electricity production Values in TW-hr
  • 7. Electricity generation 2012-2028 2/ Nueva generación limpia (NGL): Nuclear, carboeléctrica o ciclo combinado con captura y confinamiento de CO2, o renovable 2012real 60,459 MW 2028 113,708 MW POISE 2014-2028 Geotermoeléctrica 1.3% Ciclo combinado 31.2% Termoeléctrica convencional 19.7% Turbogás 5.6% Combustión interna 0.5% Eoloeléctrica 1.8% Hidroeléctrica 19.3% Carboeléctrica 8.9% Nucleoeléctrica 2.7%Solar 0.0% Coque 0.9%Biomasa 0.1% Autoabastecimien to local 7.9% Geotermoeléctrica 1.0% Ciclo combinado 45.2% Termoeléctrica convencional 1.7% Turbogás 1.9% Combustión interna 0.3% Eoloeléctrica 10.9% Hidroeléctrica 13.8% Carboeléctrica 4.2% Nucleoeléctrica 1.2% Solar 1.6% NGL 11.5% Coque 0.8% Biomasa 0.3% Autoabastecimien to local 5.5% 2/
  • 8. In 2013 . In construction Total: 3,522 MW → NGCC 1,934 MW Capacity authorized for public service Total: 9,679 MW → NGCC 7,283 MW Aditional capacity between 2016 – 2022 Total: 14,795 MW → NGCC 10,704 MW Aditional capacity between 2023 – 2028 Total: 26,955 MW1 → NGCC 11,013 MW POISE 2014-2028
  • 9. Total: 3,522 MW Centrales terminadas y en proceso de construcción, en 2013. Servicio público 1/ Agua Prieta II (operación de una TG en ciclo abierto 134 MW) en Julio de 2014 MW 1,934 3,522 Ciclo combinado Total Eoloeléctrica 103 Geotermoeléctrica 107 Combustión interna 58.6 Turbogás-cogeneración 521 Termosolar 14 Baja California II TG Fase I (139 MW) Guerrero Negro III (12 MW) Baja California Sur IV (Coromuel) (44 MW) Humeros II Fases A y B (2x27 MW ) Salamanca Fase I (382 MW ) Azufres III Fase I (53 MW) Sureste I Fase II (103 MW) Centro (658 MW) Termosolar Agua Prieta II (14 MW) Agua Prieta II 1/ (404 MW) Piloto Solar (5 MW) Norte II (Chihuahua) (445 MW) Santa Rosalía (2.6 MW) Aura Solar (30 MW) La Yesca U1 y U2 (750 MW) Manzanillo I rep U2 (427 MW) Solar 35 Hidroeléctrica 750 4. POISE 2014-2028
  • 10. Total: 9,679 MW capacidad en licitación autorizada y condicionada para Servicio Público Hidroeléctrica Ciclo combinado Turbogás Geotermoeléctrica Total MW 480 7,283 86 29 9,679 Eoloeléctrica 1,688 Combustión interna 109 Las Cruces (240 MW (203 MW) Sureste I Fase I Solar 4 Rumorosa (3x100 MW) I,II y III Santa Rosalía Ciclo binario (2 MW) Santa Rosalía (FV) (4 MW) Santa Rosalía II (15 MW) Noroeste y Topolobampo III (847 y 700 MW) (2 x 735 MW) Guaymas II y III (43 MW) Baja California Sur VI La Paz (117 MW) Noreste (Escobedo) (1,034 MW) Lerdo (Norte IV) (990 MW) Valle de México II (601MW) Chicoasén II (240 MW) (1,185 MW) Surestes II, III IV V Baja California II (276 MW) Baja California II TG Fase II (86 MW) Norte III (Juárez) (954 MW) (43 MW) Baja California Sur V (Coromuel) Guerrero Negro IV (8 MW) Baja California III (La Jovita) (294 MW) Humeros III (Fase A) (27 MW) 4. POISE 2014-2028
  • 11. 1/ Las cifras están redondeadas a números enteros, por lo que los totales podrían no corresponder exactamente 2/ No incluidos en el mapa Total: 14,795 MW1/ Hidroeléctrica Ciclo combinado Solar 2/ Turbogás Geotermoeléctrica Total MW 1,133 10,704 790 432 135 14,7951/ Manzanillo II rep. U1 y U2 (2 x460 MW) Francisco Villa (Norte V) (958 MW) Todos Santos (137 MW) Central Tula (1,162 MW ) Angostura II Eoloeléctrica 1,600 Mexicali I (27 MW) La Parota U1 y U2 (455 MW) Mérida (526 MW) Tamaulipas (3 x 200 y 300 MW) (136 MW) I, II, III y IV Aguascalientes (872 MW) (1,088 MW) Monterrey IV Centro II (660 MW ) Baja California IV (SLRC) 522 MW San Luis Potosí (862 MW) Guadalajara I (908 MW) Mazatlán (867 MW) Eólica I (200 MW) Cerritos Colorados Fase I y II (2x27 MW) Paso de la Reina (543 MW) Mérida TG (169 MW) Eólica II (200 MW) Los Cabos I TG (94 MW) Salamanca 680 MW Valladolid IV (542 MW) Coahuila I y II (300 MW) Azufres III Fase II (27MW) Humeros III Fase B (27 MW) Cancún TG (169 MW) capacidad requerida adicional Servicio público 2016 – 2022 4. POISE 2014-2028
  • 12. 1/ Las cifras están redondeadas a números enteros, por lo que los totales podrían no corresponder exactamente Total: 26,955 MW1/ Hidroeléctrica Ciclo Combinado Nueva Generación limpia Total MW 1,180 11,013 12,775 26,955 1/ Eoloeléctrica 1,200 Turbogás 94 Noroeste II y IV (2X1400 MW) Valladolid V (542 MW) Baja California VI (Ensenada) Pacífico II y III (1x700 MW) Oriental l, II, III, IV, IX Y X (3x1225 MW) (565 MW) Salamanca II (680 MW) Mérida V (540 MW) Norte VI y VII (Chih.) (2x968 MW) Valle de México III (601 MW) Tenosique (422 MW) Central II (Tula) (1,162 MW) Baja California V (Mexicali) (522 MW) Todos Santos II (123 MW) Sistema Pescados (La Antigua) (121 MW) Xúchile s (54 MW) La Paz II (117 MW) Tamazunchale II y III (2x1,121MW) Omitlán (231 MW) Madera (352 MW) Todos Santos III (123 MW) Occidental I y II (1400MW) Los Cabos II TG (94 MW) Cd. Constitución (137 MW) Eólica III, VI, (4X200 MW) Santa Rosalía III (11 MW) Solar 600 Solar V (100 MW) Geotermoeléctrica 81 Cerritos Colorados Fase III (27 MW) Sabinas I y II (2X700 MW) Eólica IV (200 MW) Solar VI (100 MW) San Luis Potosi II (862 MW) Eólica V (200 MW) Geotermoeléctrica I y II (2X27 MW) Solar VII (100 MW) (1x1400 MW) Solar VIII (100 MW) Solar X (100 MW) Aguascalientes II (872MW) VII y VIII Combustión Interna 11 Oriental V y VI (1400 MW) Solar IX (100 MW) capacidad requerida adicional Servicio público (2023 – 2028) 4. POISE 2014-2028
  • 13. EOR IN OIL PRODUCTION Millionsofbarrelsperday EOR Oil production The world's largest nitrogen-injection EOR project, led by PEMEX in Cantarrell
  • 14. GAS PRODUCTION IN ENE. INCLUDES SHALE GAS bcf Natural gas production (bcf) EOR • 600 trillion cubic feet of shale gas. Ranks 6th largest in the world • 13 billion barrels of recoverable shale oil resources . Ranks 8th largest in the world. http://oilprice.com/Energy/Energy-General/Mexico-Shale-Gas-Industry-and-Energy- Reform.html
  • 15. LOCATION OF SHALE GAS RESERVES IN MEXICO Localization of Shale gas in Mexico
  • 16. 1. The large Mexican oil fields, that are candidates for EOR, is expected to need up 50 million tons of CO2 per year 2. The largest emitter region of CO2 (20.1 million tons per year) CO2-EOR Potential The Gulf of Mexico is R. Lacy et al. / International Journal of Greenhouse Gas Control 19 (2013) 212–219
  • 17. CO2 sources in the Gulf of Mexico 2013 R. Lacy et al. / International Journal of Greenhouse Gas Control 19 (2013) 212–219 It is to increase oil production by CO2-EOR from 659 to 1,758 MMB
  • 18. CO2-EOR Potential Potential CO2 - EOR Anthropogenic sources of CO2 Federal comission of Electricity Natural sources of CO2 Quebrache (260 MMSCFD / 13 MTonne/D) Ogarri o Coyotes San Andrés Carmit o Cosoleacaque: CPQC (80 MMSCFD / 4 MTonne/D) CFE Tuxpan (390 MMSCFD / 19.5 MTonne/D) Tres Hermanos (5 MMSCFD / 250 Tonne/D) Maloob Copy right by Fernando Rodríguez de la Garza, CO2 – EOR program in Mexico, Gas networking meeting , Cuernavaca Morelos, Mexico 11-12 February 2014 CO2 can be capture from Tuxpan power station to inject on Chicontepec fields. Pilot testing will be necessary in order to confirm oil recovery using CO2
  • 19. 19 • In 2008 CFE started several actions related to CCS • 2009 CFE contracted to the Mario Molina Center and IIE to do preliminary studies for a demostrative CO2 capture plant • 2010 a pilot test of CO2 continuous injection was performed in the Coyotes field • In 2012 the Mexican Congress approved the General Climate Change Law to reduce greenhouse gas emissions One of its strategies to reach this objective is the application of CCS on fossil fuel power plants and in the oil industry for EOR Current status of CO2-EOR in PEMEX-CFE
  • 20. Future plans on CCUS CCS project funded by The global CCS institute and U.S. DOE 2014 • Workshop on storage in Mexico City IPN in August- Focus on Burgos and Sabinas basins. Geologists from industry and academy • Workshop in Mexico City CFE in September –Students including chemists & engineers from industry, academia and research institutions • Workshop Hermosillo CFE and will be directed at undergraduate students in the earth sciences area IEAGHG Summer school 2016 will be hosted by IIE Cuernavaca Morelos CCUS-EOR project of PEMEX funded by Mexican government (start 2015 a period of 3 years) • Design and implement a CO2-EOR pilot test at the Cinco Presidentes field by using the high purity CO2 to be captured in the ammonia plants in Petrochemical Center of Cosoleacaque, CPQC. • Full scale CO2-EOR implementation in the selected field will allow for elimination of current CO2 emissions from CPQC, of about 100-120 MMSCFD. • ( 5,000 a 6,000 ton/d)
  • 21. • It is expected that 60-70% of the injected CO2 will remain sequestered in the reservoir. It will be confirmed by the pilot results Long term SENER- SEMARNAT before 2018 (SENER, Enero 2014, SEMARNAT) • Pilot plant 50 MW to provide 5 MMSCF/d CO2 for a EOR project • Demostration plant 250 MW to provide 25 MMSCF/d CO2 for EOR project in a big reservoir CCS SENER – WORLD BANK Pilot plant 2 MW in Poza Rica Veracruz • SENER-PEMEX-CFE–SEMARNAT: Currently defining the Technology Route Map for CCUS-EOR of Mexico. Implementation will start later in 2014. Future plan on CCUS
  • 22. •CCS in NGCC will be needed due to the large participation of this technology in Power Generation •There are several projects in CCS that are being promoted and carried out •PEMEX will need CO2 for its EOR projects that exceeds the natural sources available •PEMEX needs to assess the effectiveness of CO2 EOR in the Mexican oil fields •Resources are limited and are slowing down some projects •EOR is one on the main drivers for CCS in Mexico because CO2 for EOR provides a positive immediate economic benefit, as well as helping to mitigate long-term environmental impacts. Conclusions