This document analyzes power line efficiency for Shenandoah Valley Electric Cooperative (SVEC). It finds that nearly 8 GWh were lost in 2010 from transmission and distribution lines in Virginia alone. The purpose is to determine power loss across SVEC's system and identify technologies to improve efficiency and reduce loss. The analysis finds that upgrading to more efficient conductors like Linnet ACSR and NEMA Premium transformers would significantly reduce losses and save SVEC and customers money, with payback periods of less than two years for some upgrades. A multi-stage strategy is proposed that focuses first on replacing outdated equipment and later integrating smart grid technologies system-wide.
Generative Artificial Intelligence: How generative AI works.pdf
Power Distribution Efficiency
1. POWER LINE EFFICIENCY ANALYSIS
Presented by Wade Reynolds
James Madison University – ISAT 493 Senior Capstone
Sponsored by Shenandoah Valley Electric Cooperative
2. INTRODUCTION
In 2010, nearly 8 GWh were lost from
transmission and distribution in Virginia alone
Equivalent to enough energy to power 1.3
million homes
5. PURPOSE
Determine power loss across system and
find technological solutions that can be
implemented to improve efficiency and
reduce loss
6. BACKGROUND
The Rural Electrification Act of 1936 provided
federal assistance for rural electrification
RECs are private, non-profit utilities owned
by the customers they serve
Two types of RECs: Generation and
Distribution
SVEC is a Distribution cooperative that
serves nearly 90,000 customers across
western Virginia
7. RESEARCH QUESTIONS
What are the sources of loss in the system?
Are technologies currently available to
replace SVEC’s current technology and
improve efficiency?
Are these technologies cost-effective?
What will improved efficiency mean to SVEC
and its customers?
8. METHODOLOGY
SCADA software was used to find the current
and voltage at five strategic points across the
system
Focus is on losses due to inefficiency in
conductors and transformers
All formulas and methods used are
consistent with industry standards and
relative to the desired level of accuracy we
wish to achieve
9. CLOVER HILL SYSTEM
Clover Hill Line extends 10.6 miles from the
Dayton Substation
Conductor type = 1/0 Raven ACSR
A single substation transformer and 1,415
distribution transformers located along the
line
Substation transformer rated at 100 MVA
capacity
Each distribution transformer rated at ~10 kVA
capacity
10. CONDUCTOR EFFICIENCY
Calculating Impedance
Resistance
Reactance
Calculating Loss
Total Impedance per unit length
Power Loss = Current2 x Resistance
Calculating Efficiency
Power Loss/Power Supplied
11. FORMULAS
Conductor Impedance:
Ra = Resistance
Xa = Reactance
Xd = Construction Reactance Factor
Construction Reactance Factor:
Xf = Inductive Reactance Spacing Factor
ƒ = Frequency
GMD = Geometric Mean Distance
15. TRANSFORMER ANALYSIS
Type Standard NEMA Premium
Capacity (kVA) 10 15
Efficiency 96% 98%
Average Yearly Load (kWh) 6,000 6,000
Loss Incurred (kWh) 234 96
# of Transformers 1,415 1,415
Total Loss (kWh) 331,110 135,840
Inefficiency Cost Per Year $ 28,707 $ 11,777
16. RESULTS AND FINDINGS
Linnet conductor will have a payback period
of less than 2 years
NEMA Premium transformers will save nearly
$17,000 annually in power losses
17. TECHNOLOGY SOLUTIONS
High-Efficiency Conductors
ACCC cut line loss by 30-40% under equal load
NEMA Premium Efficient Transformers
Meet or exceed DOEs efficiency requirements
Smart-Grid Devices
Two-way communication provides real-time
information to ensure system is operating at
optimal levels
18. BENEFITS
Lower customer electricity bills
Improved reliability
Greater response to power outages
Lower maintenance costs
Reduced need for generating capacity
Lower greenhouse gas emissions
20. STRATEGY
Short-term (2 to 10 years)
Replace blown-out transformers with high-
efficiency transformers
Mid-range (11 to 20 years)
Replace old conductors with either high-
efficiency conductors or larger ACSR conductors
Long-range (beyond 20 years)
Install smart-grid devices across distribution
system
Explain the purpose of increasing the voltage for long distance transmissionExplain why voltage is stepped down before reaching end-usersLead into discussion of P=IV and Loss=I^2R equations
Discuss why these equations are important in terms of efficiencyPower generated at plant must remain constant across systemLow current is ideal for reducing line lossMost energy is lost in the form of waste heat or Joule heatingPower = Current x VoltagePower Loss = Current2 x Resistance
Impedance is the opposition of current flow through an AC circuit. Possesses both magnitude and phase; unlike resistance, which only has magnitudeResistance and reactance are determined by the manufacturer. Are inherent properties of the conductor at a given temperature and frequency
Reactance is the opposition to a change of current due to the build-up of a magnetic fieldConstruction Reactance Factor is an additional opposition to current flow due to the configuration of the wiring systemFormulas used by SVEC
Linnet conductor will have a payback period of less than 2 years
Energy is dissipated in windings, core, and surrounding structuresNo-load losses occur in the transformer core due to hysteresis and eddy current losses, which are always present and constant during normal operationLoad losses occur in the transformer’s electrical circuit, including windings and components, due to resistive loss and are a function of loading conditions
Forecast future demand growth to determine whether technology upgrades are neededConsider further study focused on optimizing distribution transformer sizing and placement based on load requirementsNEMA Premium transformers are ideal upgrade solutionsSmart-grid devices must be adopted by transmission networks before they become beneficial to distribution utilities