Q1. Draw the positive, negative and zero sequence impedance networks for the power system given in the figure.
    Choose a base of 50 MVA, 220kV in the 100 ohms transmission line and mark all impedances in pu. The
    ratings of the generators and transformers are:
    Generator 1: 25 MVA, 11kV, X1=20%; X2=20%;
    Generator 2: 25 MVA, 11kV, X1=20%; X2=20%;
    Three-phase transformer (each): 20MVA, 11 Y/220 Y kV, X=15%. The zero sequence reactance of each
    machine is 8%. The neutral reactance is 5% on individual machine ratings.




Q2. Draw the positive, negative and zero sequence impedance networks for the power system given in

    the figure. Choose a base of 50 MVA, 220kV in the 50Ω transmission lines and mark all impedances

    in pu. The ratings of the generators and transformers are:

        Generator 1: 25 MVA, 11kV, X1=X2=20%, Xg0 = 10%

        Generator 2: 25 MVA, 11kV, X1=X2=15%, Xg0 = 8%

        Three-phase transformer (each): 20MVA, 11 Y/220 Y kV, X=15%

        The zero sequence reactance of each machine is 8%. Assume that the zero sequence reactance
        of the lines is 250% of their positive sequence reactance.
Q3. Draw the positive, negative and zero sequence impedance networks for the power system given in

    the figure. Choose a base of 100 MVA, 200kV in the 100 ohms transmission line and mark all

    impedances in pu. The ratings of the generators, transformers are:

    G1: 20 MVA, 11kV, X1=20%; X2=10%;          G2: 50 MVA, 33kV, X1=20%; X2=15%;

    YY Transformer: 50MVA, 200/11KV, X= 10%; Y∆ Transformer: 45MVA, 200/33KV, X = 15%.

    The zero sequence reactance of each machine is 5%.

    The neutral reactance is 3% on individual machine ratings.




Q4. Draw all the sequence networks for the power system shown in the figure below:
    Choose a base of 50 MVA, 220KV in the 50 ohm transmission lines and mark all the reactances in
    pu. The ratings of the generators and the transformers are:
    Generator 1 : 25MVA, 11KV, X1=X2=15%, Xg0 = 5%
    Generator 2 : 25MVA, 11KV, X1=X2=10%, Xg0 = 8%
    3 phase transformers(each) = 20 MVA, 11 /220 KV, X = 15%
    The negative sequence reactance of each synchronous machine is equal to its positive seq.
    reactance. The zero sequence reactance of each machine is 8%. The neutral reactance is 5%.
Q5. Draw the positive, negative and zero sequence impedance networks for the power system given in

     the figure. Choose a base of 150 MVA, 220kV in the 60 ohms transmission line and mark all

     impedances in pu. The ratings of the generators, transformers are:

     G1: 50 MVA, 13kV, X1=25%; X2=15%;                 G2: 40 MVA, 25kV, X 1=15%; X2=10%;

     YY Transformer: 45MVA, 220/15KV, X= 15%;          Y∆ Transformer: 50MVA, 230/35KV, X = 10%.

The zero sequence reactance
of each machine is 4%.

The neutral reactance is 5%
on individual machine ratings.

Contenu connexe

Tendances

Questions From 1st Unit Nagrath
Questions From 1st Unit NagrathQuestions From 1st Unit Nagrath
Questions From 1st Unit NagrathAbha Tripathi
 
Unit 1, Power system Analysis
Unit 1, Power system AnalysisUnit 1, Power system Analysis
Unit 1, Power system AnalysisAbha Tripathi
 
Unit 2 samplesolutions
Unit 2 samplesolutionsUnit 2 samplesolutions
Unit 2 samplesolutionsAbha Tripathi
 
Unit 2 Questions_Nagrath kothari
Unit 2 Questions_Nagrath kothariUnit 2 Questions_Nagrath kothari
Unit 2 Questions_Nagrath kothariAbha Tripathi
 
Eet3082 binod kumar sahu lecturer_23
Eet3082 binod kumar sahu lecturer_23Eet3082 binod kumar sahu lecturer_23
Eet3082 binod kumar sahu lecturer_23BinodKumarSahu5
 
Power system fault analysis ppt
Power system fault analysis pptPower system fault analysis ppt
Power system fault analysis pptkarikalan123
 
Chapter1 Questions
Chapter1 QuestionsChapter1 Questions
Chapter1 Questionsguest4ca222
 
Power system safety and protection
Power system safety and protectionPower system safety and protection
Power system safety and protectionHakim Futra
 
Electrical machines solved objective
Electrical machines solved objectiveElectrical machines solved objective
Electrical machines solved objectivemaheshwareshwar
 
Lecture no 4 power system analysis elc353 et313
Lecture no 4 power system analysis elc353 et313Lecture no 4 power system analysis elc353 et313
Lecture no 4 power system analysis elc353 et313Fazal Ur Rehman
 
EEP301: Transducer and instrumentation
EEP301: Transducer and instrumentationEEP301: Transducer and instrumentation
EEP301: Transducer and instrumentationUmang Gupta
 

Tendances (20)

Unit v
Unit vUnit v
Unit v
 
Unit1questions
Unit1questionsUnit1questions
Unit1questions
 
Questions From 1st Unit Nagrath
Questions From 1st Unit NagrathQuestions From 1st Unit Nagrath
Questions From 1st Unit Nagrath
 
Soln unit5
Soln unit5Soln unit5
Soln unit5
 
Unit 1, Power system Analysis
Unit 1, Power system AnalysisUnit 1, Power system Analysis
Unit 1, Power system Analysis
 
Unit 2 samplesolutions
Unit 2 samplesolutionsUnit 2 samplesolutions
Unit 2 samplesolutions
 
Unit 2 Questions_Nagrath kothari
Unit 2 Questions_Nagrath kothariUnit 2 Questions_Nagrath kothari
Unit 2 Questions_Nagrath kothari
 
Unit 3 Part 1
Unit 3 Part 1Unit 3 Part 1
Unit 3 Part 1
 
Unsymmetrical Fault
Unsymmetrical FaultUnsymmetrical Fault
Unsymmetrical Fault
 
Eet3082 binod kumar sahu lecturer_23
Eet3082 binod kumar sahu lecturer_23Eet3082 binod kumar sahu lecturer_23
Eet3082 binod kumar sahu lecturer_23
 
Power system fault analysis ppt
Power system fault analysis pptPower system fault analysis ppt
Power system fault analysis ppt
 
Chapter1 Questions
Chapter1 QuestionsChapter1 Questions
Chapter1 Questions
 
EE551_HW6
EE551_HW6EE551_HW6
EE551_HW6
 
electrical objective
electrical objectiveelectrical objective
electrical objective
 
EEP303: Exp5
EEP303: Exp5EEP303: Exp5
EEP303: Exp5
 
Power system safety and protection
Power system safety and protectionPower system safety and protection
Power system safety and protection
 
Electrical machines solved objective
Electrical machines solved objectiveElectrical machines solved objective
Electrical machines solved objective
 
Lecture no 4 power system analysis elc353 et313
Lecture no 4 power system analysis elc353 et313Lecture no 4 power system analysis elc353 et313
Lecture no 4 power system analysis elc353 et313
 
Electrical machines-lab-i-ee0209
Electrical machines-lab-i-ee0209Electrical machines-lab-i-ee0209
Electrical machines-lab-i-ee0209
 
EEP301: Transducer and instrumentation
EEP301: Transducer and instrumentationEEP301: Transducer and instrumentation
EEP301: Transducer and instrumentation
 

Similaire à Questions unit3

Symmetrical Components Fault Calculations
Symmetrical Components Fault CalculationsSymmetrical Components Fault Calculations
Symmetrical Components Fault Calculationsmichaeljmack
 
Power-System-Slide-1.pptx
Power-System-Slide-1.pptxPower-System-Slide-1.pptx
Power-System-Slide-1.pptxssuser99d6551
 
CHAPTER 3 - Three Phase Network.ppt
CHAPTER 3 - Three Phase Network.pptCHAPTER 3 - Three Phase Network.ppt
CHAPTER 3 - Three Phase Network.pptLiewChiaPing
 
Power System Analysis!
Power System Analysis!Power System Analysis!
Power System Analysis!PRABHAHARAN429
 
Symmetrical Fault Analysis
Symmetrical Fault AnalysisSymmetrical Fault Analysis
Symmetrical Fault AnalysisSANTOSH GADEKAR
 
UNIT -I per unit calculation,EQUIVALENT CIRCUIT
UNIT -I per unit calculation,EQUIVALENT CIRCUITUNIT -I per unit calculation,EQUIVALENT CIRCUIT
UNIT -I per unit calculation,EQUIVALENT CIRCUITAbinaya Saraswathy T
 
ECE4762011_Lect10.ppt
ECE4762011_Lect10.pptECE4762011_Lect10.ppt
ECE4762011_Lect10.pptbabu717541
 
ECE4762011_Lect10.ppt
ECE4762011_Lect10.pptECE4762011_Lect10.ppt
ECE4762011_Lect10.pptThomasNikola
 
Lab 2 Report More Linear Operational Amplifiers
Lab 2 Report More Linear Operational AmplifiersLab 2 Report More Linear Operational Amplifiers
Lab 2 Report More Linear Operational AmplifiersKatrina Little
 
Analysis-of-Faults-AREVA.ppt
Analysis-of-Faults-AREVA.pptAnalysis-of-Faults-AREVA.ppt
Analysis-of-Faults-AREVA.pptHariNair812688
 
Modelling of 25 kV Electric Railway System
Modelling of 25 kV Electric Railway SystemModelling of 25 kV Electric Railway System
Modelling of 25 kV Electric Railway SystemBérengère VIGNAUX
 
Lecture dc machines
Lecture dc machinesLecture dc machines
Lecture dc machinessudeep kumar
 
Emec 1 bank nee 301
Emec 1 bank nee 301Emec 1 bank nee 301
Emec 1 bank nee 301Ravi Anand
 
Ee 1351 power system analysis
Ee 1351 power system analysisEe 1351 power system analysis
Ee 1351 power system analysisHari Kumar
 
NEW APPROACH OF DESIGNING AND EXPLOATATION OF ELECTRICAL TRACTION SUBSTATIONS
NEW APPROACH OF DESIGNING AND EXPLOATATION OF ELECTRICAL TRACTION SUBSTATIONSNEW APPROACH OF DESIGNING AND EXPLOATATION OF ELECTRICAL TRACTION SUBSTATIONS
NEW APPROACH OF DESIGNING AND EXPLOATATION OF ELECTRICAL TRACTION SUBSTATIONSDženan Ćelić
 
Three phase balanced load circuits and synchronous generators
Three phase balanced load circuits and synchronous generatorsThree phase balanced load circuits and synchronous generators
Three phase balanced load circuits and synchronous generatorsIsham Rashik
 

Similaire à Questions unit3 (20)

Symmetrical Components Fault Calculations
Symmetrical Components Fault CalculationsSymmetrical Components Fault Calculations
Symmetrical Components Fault Calculations
 
Power-System-Slide-1.pptx
Power-System-Slide-1.pptxPower-System-Slide-1.pptx
Power-System-Slide-1.pptx
 
CHAPTER 3 - Three Phase Network.ppt
CHAPTER 3 - Three Phase Network.pptCHAPTER 3 - Three Phase Network.ppt
CHAPTER 3 - Three Phase Network.ppt
 
Power System Analysis!
Power System Analysis!Power System Analysis!
Power System Analysis!
 
Symmetrical Fault Analysis
Symmetrical Fault AnalysisSymmetrical Fault Analysis
Symmetrical Fault Analysis
 
Lecture 8
Lecture 8Lecture 8
Lecture 8
 
UNIT -I per unit calculation,EQUIVALENT CIRCUIT
UNIT -I per unit calculation,EQUIVALENT CIRCUITUNIT -I per unit calculation,EQUIVALENT CIRCUIT
UNIT -I per unit calculation,EQUIVALENT CIRCUIT
 
Per unit analysis
Per unit analysisPer unit analysis
Per unit analysis
 
ALL DAY EFFICIENCY
ALL DAY EFFICIENCYALL DAY EFFICIENCY
ALL DAY EFFICIENCY
 
ECE4762011_Lect10.ppt
ECE4762011_Lect10.pptECE4762011_Lect10.ppt
ECE4762011_Lect10.ppt
 
ECE4762011_Lect10.ppt
ECE4762011_Lect10.pptECE4762011_Lect10.ppt
ECE4762011_Lect10.ppt
 
Lab 2 Report More Linear Operational Amplifiers
Lab 2 Report More Linear Operational AmplifiersLab 2 Report More Linear Operational Amplifiers
Lab 2 Report More Linear Operational Amplifiers
 
Analysis-of-Faults-AREVA.ppt
Analysis-of-Faults-AREVA.pptAnalysis-of-Faults-AREVA.ppt
Analysis-of-Faults-AREVA.ppt
 
Modelling of 25 kV Electric Railway System
Modelling of 25 kV Electric Railway SystemModelling of 25 kV Electric Railway System
Modelling of 25 kV Electric Railway System
 
Lecture dc machines
Lecture dc machinesLecture dc machines
Lecture dc machines
 
Emec 1 bank nee 301
Emec 1 bank nee 301Emec 1 bank nee 301
Emec 1 bank nee 301
 
Ee 1351 power system analysis
Ee 1351 power system analysisEe 1351 power system analysis
Ee 1351 power system analysis
 
NEW APPROACH OF DESIGNING AND EXPLOATATION OF ELECTRICAL TRACTION SUBSTATIONS
NEW APPROACH OF DESIGNING AND EXPLOATATION OF ELECTRICAL TRACTION SUBSTATIONSNEW APPROACH OF DESIGNING AND EXPLOATATION OF ELECTRICAL TRACTION SUBSTATIONS
NEW APPROACH OF DESIGNING AND EXPLOATATION OF ELECTRICAL TRACTION SUBSTATIONS
 
Three phase balanced load circuits and synchronous generators
Three phase balanced load circuits and synchronous generatorsThree phase balanced load circuits and synchronous generators
Three phase balanced load circuits and synchronous generators
 
POWER POINT TRACKING
POWER POINT TRACKINGPOWER POINT TRACKING
POWER POINT TRACKING
 

Plus de Abha Tripathi

Power system Stability, Equal area criteria
Power system Stability, Equal area criteriaPower system Stability, Equal area criteria
Power system Stability, Equal area criteriaAbha Tripathi
 
Non Conventional (Renewable) Energy Sources 01
Non Conventional (Renewable) Energy Sources 01Non Conventional (Renewable) Energy Sources 01
Non Conventional (Renewable) Energy Sources 01Abha Tripathi
 
Conventional sources of energy (power generation) 01
Conventional sources of energy (power generation) 01Conventional sources of energy (power generation) 01
Conventional sources of energy (power generation) 01Abha Tripathi
 
Symmetrical components
Symmetrical componentsSymmetrical components
Symmetrical componentsAbha Tripathi
 
Representation of power system components
Representation of power system componentsRepresentation of power system components
Representation of power system componentsAbha Tripathi
 
Gas and diesel Plant
Gas and diesel PlantGas and diesel Plant
Gas and diesel PlantAbha Tripathi
 
NPP, Nuclear Power Plant,
NPP, Nuclear Power Plant, NPP, Nuclear Power Plant,
NPP, Nuclear Power Plant, Abha Tripathi
 
Grading The Insulator Problem
Grading The Insulator ProblemGrading The Insulator Problem
Grading The Insulator ProblemAbha Tripathi
 

Plus de Abha Tripathi (15)

Power system Stability, Equal area criteria
Power system Stability, Equal area criteriaPower system Stability, Equal area criteria
Power system Stability, Equal area criteria
 
Non Conventional (Renewable) Energy Sources 01
Non Conventional (Renewable) Energy Sources 01Non Conventional (Renewable) Energy Sources 01
Non Conventional (Renewable) Energy Sources 01
 
Conventional sources of energy (power generation) 01
Conventional sources of energy (power generation) 01Conventional sources of energy (power generation) 01
Conventional sources of energy (power generation) 01
 
Symmetrical components
Symmetrical componentsSymmetrical components
Symmetrical components
 
Representation of power system components
Representation of power system componentsRepresentation of power system components
Representation of power system components
 
Questions unit2 ch3
Questions unit2 ch3Questions unit2 ch3
Questions unit2 ch3
 
Renewable Sor
Renewable SorRenewable Sor
Renewable Sor
 
Gas and diesel Plant
Gas and diesel PlantGas and diesel Plant
Gas and diesel Plant
 
NPP, Nuclear Power Plant,
NPP, Nuclear Power Plant, NPP, Nuclear Power Plant,
NPP, Nuclear Power Plant,
 
Hydro E
Hydro EHydro E
Hydro E
 
Thermal power plant
Thermal power plantThermal power plant
Thermal power plant
 
Unit 3 Part 1
Unit 3 Part 1Unit 3 Part 1
Unit 3 Part 1
 
Grading The Insulator Problem
Grading The Insulator ProblemGrading The Insulator Problem
Grading The Insulator Problem
 
Dc Distribution
Dc DistributionDc Distribution
Dc Distribution
 
Dc Distributed Load
Dc Distributed LoadDc Distributed Load
Dc Distributed Load
 

Dernier

What is Model Inheritance in Odoo 17 ERP
What is Model Inheritance in Odoo 17 ERPWhat is Model Inheritance in Odoo 17 ERP
What is Model Inheritance in Odoo 17 ERPCeline George
 
Concurrency Control in Database Management system
Concurrency Control in Database Management systemConcurrency Control in Database Management system
Concurrency Control in Database Management systemChristalin Nelson
 
Full Stack Web Development Course for Beginners
Full Stack Web Development Course  for BeginnersFull Stack Web Development Course  for Beginners
Full Stack Web Development Course for BeginnersSabitha Banu
 
How to Add Barcode on PDF Report in Odoo 17
How to Add Barcode on PDF Report in Odoo 17How to Add Barcode on PDF Report in Odoo 17
How to Add Barcode on PDF Report in Odoo 17Celine George
 
ANG SEKTOR NG agrikultura.pptx QUARTER 4
ANG SEKTOR NG agrikultura.pptx QUARTER 4ANG SEKTOR NG agrikultura.pptx QUARTER 4
ANG SEKTOR NG agrikultura.pptx QUARTER 4MiaBumagat1
 
AUDIENCE THEORY -CULTIVATION THEORY - GERBNER.pptx
AUDIENCE THEORY -CULTIVATION THEORY -  GERBNER.pptxAUDIENCE THEORY -CULTIVATION THEORY -  GERBNER.pptx
AUDIENCE THEORY -CULTIVATION THEORY - GERBNER.pptxiammrhaywood
 
ICS2208 Lecture6 Notes for SL spaces.pdf
ICS2208 Lecture6 Notes for SL spaces.pdfICS2208 Lecture6 Notes for SL spaces.pdf
ICS2208 Lecture6 Notes for SL spaces.pdfVanessa Camilleri
 
Earth Day Presentation wow hello nice great
Earth Day Presentation wow hello nice greatEarth Day Presentation wow hello nice great
Earth Day Presentation wow hello nice greatYousafMalik24
 
ISYU TUNGKOL SA SEKSWLADIDA (ISSUE ABOUT SEXUALITY
ISYU TUNGKOL SA SEKSWLADIDA (ISSUE ABOUT SEXUALITYISYU TUNGKOL SA SEKSWLADIDA (ISSUE ABOUT SEXUALITY
ISYU TUNGKOL SA SEKSWLADIDA (ISSUE ABOUT SEXUALITYKayeClaireEstoconing
 
INTRODUCTION TO CATHOLIC CHRISTOLOGY.pptx
INTRODUCTION TO CATHOLIC CHRISTOLOGY.pptxINTRODUCTION TO CATHOLIC CHRISTOLOGY.pptx
INTRODUCTION TO CATHOLIC CHRISTOLOGY.pptxHumphrey A Beña
 
How to do quick user assign in kanban in Odoo 17 ERP
How to do quick user assign in kanban in Odoo 17 ERPHow to do quick user assign in kanban in Odoo 17 ERP
How to do quick user assign in kanban in Odoo 17 ERPCeline George
 
4.16.24 Poverty and Precarity--Desmond.pptx
4.16.24 Poverty and Precarity--Desmond.pptx4.16.24 Poverty and Precarity--Desmond.pptx
4.16.24 Poverty and Precarity--Desmond.pptxmary850239
 
USPS® Forced Meter Migration - How to Know if Your Postage Meter Will Soon be...
USPS® Forced Meter Migration - How to Know if Your Postage Meter Will Soon be...USPS® Forced Meter Migration - How to Know if Your Postage Meter Will Soon be...
USPS® Forced Meter Migration - How to Know if Your Postage Meter Will Soon be...Postal Advocate Inc.
 
Field Attribute Index Feature in Odoo 17
Field Attribute Index Feature in Odoo 17Field Attribute Index Feature in Odoo 17
Field Attribute Index Feature in Odoo 17Celine George
 
Influencing policy (training slides from Fast Track Impact)
Influencing policy (training slides from Fast Track Impact)Influencing policy (training slides from Fast Track Impact)
Influencing policy (training slides from Fast Track Impact)Mark Reed
 
Virtual-Orientation-on-the-Administration-of-NATG12-NATG6-and-ELLNA.pdf
Virtual-Orientation-on-the-Administration-of-NATG12-NATG6-and-ELLNA.pdfVirtual-Orientation-on-the-Administration-of-NATG12-NATG6-and-ELLNA.pdf
Virtual-Orientation-on-the-Administration-of-NATG12-NATG6-and-ELLNA.pdfErwinPantujan2
 
Inclusivity Essentials_ Creating Accessible Websites for Nonprofits .pdf
Inclusivity Essentials_ Creating Accessible Websites for Nonprofits .pdfInclusivity Essentials_ Creating Accessible Websites for Nonprofits .pdf
Inclusivity Essentials_ Creating Accessible Websites for Nonprofits .pdfTechSoup
 
4.16.24 21st Century Movements for Black Lives.pptx
4.16.24 21st Century Movements for Black Lives.pptx4.16.24 21st Century Movements for Black Lives.pptx
4.16.24 21st Century Movements for Black Lives.pptxmary850239
 
MULTIDISCIPLINRY NATURE OF THE ENVIRONMENTAL STUDIES.pptx
MULTIDISCIPLINRY NATURE OF THE ENVIRONMENTAL STUDIES.pptxMULTIDISCIPLINRY NATURE OF THE ENVIRONMENTAL STUDIES.pptx
MULTIDISCIPLINRY NATURE OF THE ENVIRONMENTAL STUDIES.pptxAnupkumar Sharma
 
Integumentary System SMP B. Pharm Sem I.ppt
Integumentary System SMP B. Pharm Sem I.pptIntegumentary System SMP B. Pharm Sem I.ppt
Integumentary System SMP B. Pharm Sem I.pptshraddhaparab530
 

Dernier (20)

What is Model Inheritance in Odoo 17 ERP
What is Model Inheritance in Odoo 17 ERPWhat is Model Inheritance in Odoo 17 ERP
What is Model Inheritance in Odoo 17 ERP
 
Concurrency Control in Database Management system
Concurrency Control in Database Management systemConcurrency Control in Database Management system
Concurrency Control in Database Management system
 
Full Stack Web Development Course for Beginners
Full Stack Web Development Course  for BeginnersFull Stack Web Development Course  for Beginners
Full Stack Web Development Course for Beginners
 
How to Add Barcode on PDF Report in Odoo 17
How to Add Barcode on PDF Report in Odoo 17How to Add Barcode on PDF Report in Odoo 17
How to Add Barcode on PDF Report in Odoo 17
 
ANG SEKTOR NG agrikultura.pptx QUARTER 4
ANG SEKTOR NG agrikultura.pptx QUARTER 4ANG SEKTOR NG agrikultura.pptx QUARTER 4
ANG SEKTOR NG agrikultura.pptx QUARTER 4
 
AUDIENCE THEORY -CULTIVATION THEORY - GERBNER.pptx
AUDIENCE THEORY -CULTIVATION THEORY -  GERBNER.pptxAUDIENCE THEORY -CULTIVATION THEORY -  GERBNER.pptx
AUDIENCE THEORY -CULTIVATION THEORY - GERBNER.pptx
 
ICS2208 Lecture6 Notes for SL spaces.pdf
ICS2208 Lecture6 Notes for SL spaces.pdfICS2208 Lecture6 Notes for SL spaces.pdf
ICS2208 Lecture6 Notes for SL spaces.pdf
 
Earth Day Presentation wow hello nice great
Earth Day Presentation wow hello nice greatEarth Day Presentation wow hello nice great
Earth Day Presentation wow hello nice great
 
ISYU TUNGKOL SA SEKSWLADIDA (ISSUE ABOUT SEXUALITY
ISYU TUNGKOL SA SEKSWLADIDA (ISSUE ABOUT SEXUALITYISYU TUNGKOL SA SEKSWLADIDA (ISSUE ABOUT SEXUALITY
ISYU TUNGKOL SA SEKSWLADIDA (ISSUE ABOUT SEXUALITY
 
INTRODUCTION TO CATHOLIC CHRISTOLOGY.pptx
INTRODUCTION TO CATHOLIC CHRISTOLOGY.pptxINTRODUCTION TO CATHOLIC CHRISTOLOGY.pptx
INTRODUCTION TO CATHOLIC CHRISTOLOGY.pptx
 
How to do quick user assign in kanban in Odoo 17 ERP
How to do quick user assign in kanban in Odoo 17 ERPHow to do quick user assign in kanban in Odoo 17 ERP
How to do quick user assign in kanban in Odoo 17 ERP
 
4.16.24 Poverty and Precarity--Desmond.pptx
4.16.24 Poverty and Precarity--Desmond.pptx4.16.24 Poverty and Precarity--Desmond.pptx
4.16.24 Poverty and Precarity--Desmond.pptx
 
USPS® Forced Meter Migration - How to Know if Your Postage Meter Will Soon be...
USPS® Forced Meter Migration - How to Know if Your Postage Meter Will Soon be...USPS® Forced Meter Migration - How to Know if Your Postage Meter Will Soon be...
USPS® Forced Meter Migration - How to Know if Your Postage Meter Will Soon be...
 
Field Attribute Index Feature in Odoo 17
Field Attribute Index Feature in Odoo 17Field Attribute Index Feature in Odoo 17
Field Attribute Index Feature in Odoo 17
 
Influencing policy (training slides from Fast Track Impact)
Influencing policy (training slides from Fast Track Impact)Influencing policy (training slides from Fast Track Impact)
Influencing policy (training slides from Fast Track Impact)
 
Virtual-Orientation-on-the-Administration-of-NATG12-NATG6-and-ELLNA.pdf
Virtual-Orientation-on-the-Administration-of-NATG12-NATG6-and-ELLNA.pdfVirtual-Orientation-on-the-Administration-of-NATG12-NATG6-and-ELLNA.pdf
Virtual-Orientation-on-the-Administration-of-NATG12-NATG6-and-ELLNA.pdf
 
Inclusivity Essentials_ Creating Accessible Websites for Nonprofits .pdf
Inclusivity Essentials_ Creating Accessible Websites for Nonprofits .pdfInclusivity Essentials_ Creating Accessible Websites for Nonprofits .pdf
Inclusivity Essentials_ Creating Accessible Websites for Nonprofits .pdf
 
4.16.24 21st Century Movements for Black Lives.pptx
4.16.24 21st Century Movements for Black Lives.pptx4.16.24 21st Century Movements for Black Lives.pptx
4.16.24 21st Century Movements for Black Lives.pptx
 
MULTIDISCIPLINRY NATURE OF THE ENVIRONMENTAL STUDIES.pptx
MULTIDISCIPLINRY NATURE OF THE ENVIRONMENTAL STUDIES.pptxMULTIDISCIPLINRY NATURE OF THE ENVIRONMENTAL STUDIES.pptx
MULTIDISCIPLINRY NATURE OF THE ENVIRONMENTAL STUDIES.pptx
 
Integumentary System SMP B. Pharm Sem I.ppt
Integumentary System SMP B. Pharm Sem I.pptIntegumentary System SMP B. Pharm Sem I.ppt
Integumentary System SMP B. Pharm Sem I.ppt
 

Questions unit3

  • 1. Unit III Practice Questions Q1. Draw the positive, negative and zero sequence impedance networks for the power system given in the figure. Choose a base of 50 MVA, 220kV in the 100 ohms transmission line and mark all impedances in pu. The ratings of the generators and transformers are: Generator 1: 25 MVA, 11kV, X1=20%; X2=20%; Generator 2: 25 MVA, 11kV, X1=20%; X2=20%; Three-phase transformer (each): 20MVA, 11 Y/220 Y kV, X=15%. The zero sequence reactance of each machine is 8%. The neutral reactance is 5% on individual machine ratings. Q2. Draw the positive, negative and zero sequence impedance networks for the power system given in the figure. Choose a base of 50 MVA, 220kV in the 50Ω transmission lines and mark all impedances in pu. The ratings of the generators and transformers are: Generator 1: 25 MVA, 11kV, X1=X2=20%, Xg0 = 10% Generator 2: 25 MVA, 11kV, X1=X2=15%, Xg0 = 8% Three-phase transformer (each): 20MVA, 11 Y/220 Y kV, X=15% The zero sequence reactance of each machine is 8%. Assume that the zero sequence reactance of the lines is 250% of their positive sequence reactance.
  • 2. Q3. Draw the positive, negative and zero sequence impedance networks for the power system given in the figure. Choose a base of 100 MVA, 200kV in the 100 ohms transmission line and mark all impedances in pu. The ratings of the generators, transformers are: G1: 20 MVA, 11kV, X1=20%; X2=10%; G2: 50 MVA, 33kV, X1=20%; X2=15%; YY Transformer: 50MVA, 200/11KV, X= 10%; Y∆ Transformer: 45MVA, 200/33KV, X = 15%. The zero sequence reactance of each machine is 5%. The neutral reactance is 3% on individual machine ratings. Q4. Draw all the sequence networks for the power system shown in the figure below: Choose a base of 50 MVA, 220KV in the 50 ohm transmission lines and mark all the reactances in pu. The ratings of the generators and the transformers are: Generator 1 : 25MVA, 11KV, X1=X2=15%, Xg0 = 5% Generator 2 : 25MVA, 11KV, X1=X2=10%, Xg0 = 8% 3 phase transformers(each) = 20 MVA, 11 /220 KV, X = 15% The negative sequence reactance of each synchronous machine is equal to its positive seq. reactance. The zero sequence reactance of each machine is 8%. The neutral reactance is 5%.
  • 3. Q5. Draw the positive, negative and zero sequence impedance networks for the power system given in the figure. Choose a base of 150 MVA, 220kV in the 60 ohms transmission line and mark all impedances in pu. The ratings of the generators, transformers are: G1: 50 MVA, 13kV, X1=25%; X2=15%; G2: 40 MVA, 25kV, X 1=15%; X2=10%; YY Transformer: 45MVA, 220/15KV, X= 15%; Y∆ Transformer: 50MVA, 230/35KV, X = 10%. The zero sequence reactance of each machine is 4%. The neutral reactance is 5% on individual machine ratings.