1. GREEN BUILDING DESIGN
& CONSTRUCTION
A LEGAL PERSPECTIVE
Presented to:
September 16, 2008
AGC of TN
Middle TN Branch
2. Overview
• What is a Green Building?
• LEED – Today
• LEED – Future
• Why Build “Green”?
• Design & Construction of a Green Building
• Implementing LEED: GC’s Role
• Enhanced Risks When Building Green
• Effectively Managing, Mitigating & Allocating Green-Related
Risks
• Issues Related to Design & Construction of a Green Building
• Exposure for Contractors
• Abercorn Case Study
• Summary & Recommendations
4. • High-performance building that reduces its environmental
footprint through sustainable site selection and conservation
of energy and resources, while improving the health and
productivity of its occupants.
• 3rd
Party Certification (USGBC-LEED; Energy Star; Green
Globes)
• LEED is currently the preeminent 3rd
party certification
program.
– Leadership in Energy and Environmental Design (LEED)
– 5 Major Categories:
1. Sustainable Site Development
2. Water Savings
3. Energy Efficiency
4. Materials Selection
5. Indoor Air Quality
8. • LEED 2009 Changes (Version 3)
– New 110 point scale
– Certain credits with more environmental impact now worth multiple
points, with intention to reward owners for employing these strategies
– Water Efficiency Prerequisite – 20% overall water use reduction
(excluding irrigation)
– 4 additional points available through development density and
community connectivity (intent to drive development toward infill
sites)
– 4 regional points into NC
10. • Advantages of Buildings vs. Conventional Buildings
– Cost Savings (First-Cost Savings; Ongoing Operating Expense
Reductions)
– Minimize Impact on Environment
– Enhanced Health & Productivity of Occupants
– Increased Value & Lease-Up Rates
– Community & Social Benefits
– Other Owner Benefits (Lender Incentives; Tax Abatements; Etc.)
11. • Green Will Become Standard
– Required by Government
Code in Europe
Washington, DC and Pasadena, CA: Require certain private development
projects to meet LEED requirements.
Boston, MA: All new and rehabilitation construction projects > 50,000 s.f.
must earn at least 26 LEED points.
Dallas, TX: Government buildings > 10,000 s.f. must achieve LEED silver
Rating. New ordinance recently adopted; applicable to private development
Chamblee, GA: All new construction > 20,000 s.f. must achieve LEED
certification as a condition of C.O.
Los Angeles, CA: Commercial projects > 50,000 s.f. must be LEED
certified.
San Francisco, CA: Most stringent green building ordinance to date (enacted
August, 2008). Newly constructed commercial buildings > 5,000 s.f.,
residential buildings > 75 ft. in height, and renovations of buildings >
25,000 s.f., must meet LEED or other 3rd
party green standards.
12. – Required by Owners
Lender Requirements & Expectations
- Overhaul of CMBS Standards on Wall Street
- Green Programs
- Incentive Programs
Tenant & Occupant Expectations
- Corporate green policies
- Reputation/marketing
- Health & productivity of occupants
Permitting & Incentives
- Expedited permitting process
- Variances
- Tax credits & abatements
Growing Private Equity Demand/Requirement
13. • Any Trends Away from Green Building?
– Short-term: Pending suit regarding constitutionality of green building
laws.
Albuquerque, NM suit by HVAC contractors, et al. Misguided perception
that green building standards will negatively impact contractors’ business
and right to earn a living.
– Long-term: Green building will become the norm in U.S.
Legislation – will become Code
Lender expectations
Tenant expectations
Reputation in community
15. • Green Building vs. Conventional Building
– Newer Materials & Technologies with Less of a Track Record
– Enhanced Operations Procedures During Construction
Activity Pollution Control (ESC Plan)
Construction Waste Management Plan
- Diversion of Waste from Landfill
- Recycling and/or Salvaging On-Site
Re-Use of Materials
Indoor Air Quality Management Plan
– Stringent Requirements Associated with 3rd
Party Certification (LEED)
17. • Prerequisite 1 Construction Activity Pollution Prevention
– Create and implement an Erosion and Sedimentation Control (ESC)
plan for all construction activities associated with the project.
• Credit 5.1 Protect or Restore Habitat
– On greenfield sites, limit all site disturbance to 40 feet beyond the
building perimeter; 10 feet beyond surface walkways, patios, surface
parking and utilities less that 12 inches in diameter; 15 feet beyond
primary roadway curbs and main utility branch trenches; and 25 feet
beyond constructed areas with permeable surfaces (such as pervious
paving areas, stormwater detention facilities and playing fields) that
require additional staging areas in order to limit compaction in the
constructed area.
– On previously developed or graded sites, restore or protect a minimum
of 50% of the site area (excluding the building footprint) with native or
adapted vegetation.
18. • Credit 2.1 Construction Waste Management: Divert 50% from
disposal
– Recycle and/or salvage at least 50% of non-hazardous construction and
demolition.
– Develop and implement a construction waste management plan that, at
a minimum, identifies the materials to be diverted from disposal and
whether the materials will be sorted on site or commingled.
• Credit 2.2 Construction Waste Management: Divert 75% from
disposal
• Credit 3.1 Materials Reuse: 5%
– Use salvaged, refurbished or reused materials such that the sum of
these materials constitutes at least 5%, based on cost, of the total value
of materials on the project.
• Credit 3.2 Materials Reuse: 10%
19. • Credit 4.1 Recycled Content: 10% (post-consumer + ½ pre-
consumer)
– Use materials with recycled content such that the sum of post-
consumer recycled content plus one-half of the pre-consumer content
constitutes at least 10% (based on cost) of the total value of the
materials in the project.
• Credit 4.2 Recycled Content: 20% (post-consumer +1/2 pre-
consumer)
• Credit 5.1 Regional Materials: 10% Extracted, Processed, and
Manufactured Locally
– Use building materials or products that have been extracted, harvested
or recovered, as well as manufactured, within 500 miles of the project
site for a minimum of 10% (based on cost) of the total materials value.
• Credit 5.2 Regional Materials: 20% Extracted, Processed, and
Manufactured Locally
20. • Credit 6 Rapidly Renewable
Materials
– Use rapidly renewable building
materials and products (made from
plants that are typically harvested
within a ten-year cycle or shorter) for
2.5% of the total value of all building
materials and products used in the
project, based on cost.
• Credit 7 Certified Wood
– Use a minimum of 50% of wood-based
materials and products, which are
certified in accordance with the Forest
Stewardship Council’s (FSC)
Principles and Criteria, for wood
building components.
21. • Credit 3.1 Construction IAQ Management Plan – During
Construction
– Develop and implement and Indoor Air Quality (IAQ) /management
Pan for the construction and pre-occupancy phases of the building.
During construction meet or exceed the recommended Control Measures
of the SMACNA IAQ Guidelines for Occupied Buildings under
Construction, 1995, Chapter 3.
Protect stored on-site or installed absorptive materials from moisture
damage.
If permanently installed air handlers are used during construction, filtration
media with a MERV of 8 shall be used at each return grille. Replace all
filtration media immediately prior to occupancy.
22. • Credit 3.2 Construction IAQ Management Plan – Before
Occupancy
– Option 1 – Flush Out
After construction ends, prior to occupancy with all interior finishes
installed, supply a total air volume of 14,000 cu.ft. of outside air per sq.ft.
of floor area while maintaining and internal temperature of at least 60°F
and relative humidity no higher than 60%
If occupancy is necessary prior to completion of the flush out, the space
may be occupied following delivery of 3,500 cu.ft. of outdoor are per sq.ft.
Once occupied, space must be ventilated at a minimum of 0.30 cfm/sq.ft.
– Option 2 – Air Quality Testing
Conduct baseline IAQ testing using testing protocols consistent with the
United States Environmental Protection Agency Compendium of Methods
for the Determination of Air Pollutants in Indoor Air.
• Traditionally, developer and architect drive the ship, but LEED
requires integrated planning between design and construction.
General contractor will need to play a larger role in the
transition from DD’s to CD’s.
23. • Ask for a LEED checklist and modify existing practices based
on which points are targeted.
• For some points, it is best practice to implement overall
program changes.
– Construction waste management
– IEQ management plan can be a set of standard best practices employed
on all job sites.
– Construction activity pollution prevention
– Develop policy for sourcing material that maintains integrity of targeted
points.
MR credit 4.1 and 4.2: Recycled Content; 5.1 and 5.2: Regional Materials
EQ credit 4.1-4.4: low-emitting materials (adhesives, sealants, paints,
coatings, carpet systems, and composite wood and agrifiber)
• General Conditions/Pricing should reflect additional time and
effort for targeted points.
– Materials and Resources 4.1: Recycled Content
– Sustainable Sites 5.1: Protect or Restore Habitat
25. • Design & Construction Issues
– Failure of innovative materials to meet performance requirements
– Improper installation due to inexperience of contractors
– Unanticipated performance failures due to design or construction
flaws.
– Construction Delays
– Failure to maintain adequate records
• Failure to Achieve 3rd
Party Certification
• Owner Impacts
– Loss of Financing
– Loss of Permitting or Incentives
– Loss of Tenants
26. • Contractual Issues
– Ambiguity in contracts as to expectations, responsibilities and
liabilities of parties
– Enhanced obligations and liabilities of architects and contractors
– Greater exposure to litigation and consequential damages
• Failure of Building to Meet Ongoing Performance
Requirements
– Failure to properly train operations personnel
– Lack of continual measurement & verification
– Lack of performance of materials or technologies
– Unanticipated side-effects
– Failure to properly regulate tenant behavior under leases (need
experienced green leasing counsel)
28. • Clearly Define Roles & Responsibilities of Various Parties
(architects, engineers contractors, commissioning agent, etc.)
Through Design Charrettes
• Contracting Process
– Clearly define roles and responsibilities of parties in contracts
Contracts for project team, when aggregated, should include everything
required to complete project with no overlap
– Specify expectations regarding construction waste management
(salvaging; recycling; diversion from landfill measurement)
– Clearly specify the types of materials to be used
– No change or substitution of materials unless approved by owner,
contractor and LEED consultant
– Responsibility for training operating personnel
– Record keeping
– On-going measurement & verification responsibilities
29. • Exposure For Contractors
– Standard of Care & Liability
Enhanced standard of care of architect and contractor in green building
context
- Failure of materials or technologies to perform
- Compliance with new rapidly evolving green legislation
Usually required when construction permit application submitted
Can conceivably cause project to be re-designed and/or
reconstructed
Should take adequate measures to limit liability:
- Limit obligations to compliance with legislation in effect at time of
contract execution
- Owner indemnity for any issues arising from newly-enacted
legislation
30. – Damages
Great exposure to consequential damages in green building context
(loss of 3rd
party certification, governmental incentives (tax
credits/abatements), financing and/or tenants; reputation)
Consider liquidated damages provision if damages not quantifiable
(Caps on damages negotiable)
– Warranties
Define with specificity the breadth of the coverage
In green building context, may cover unanticipated green-related
obligations, such as innovative materials and technologies required
under LEED
31. • Indemnity
– In green context, may expose architect and contractor to greater
liability:
Liability with respect to non-performance of innovative materials and
technologies
Exposure to broader consequential damages (loss of financing, tenants,
etc.)
– Must confirm if covers green aspects of project
– Thoroughly investigate materials and technologies being used; be
consistently sensitive to LEED requirements
32. • Keep Detailed & Accurate Records (LEED; Demonstrate
Performance)
• Assure Adequate Measures in Place DURING AND AFTER
Design & Construction Process to Ensure Design,
Construction and Performance of Building Meets 3rd
Party
Certification Requirements and Expectations of Parties
– Proper training of operating personnel
– Operation manuals
– Periodic testing procedures
– Ongoing measurement & verification
• Ensure a LEED AP Consultant is Engaged by Owner; Proper
Allocation of Responsibilities for LEED Issues
33. • Education About LEED
• Insurance & Performance Bonds
– Insurance
Design Team – Errors and Omissions Insurance (E&O)
- Protects against claims that insured did not perform up to
required standard of care (level of care and skill of similar
professionals in same locality)
- Insures against design defects, not construction defects
Contractors – Commercial General Liability Insurance (CGL)
- Typically covers construction defects caused by negligence of
contractor or subcontractors (insures negligence, not
perfection)
Owner – Property Insurance in a Builder’s Risk Policy
- Traditionally, excludes losses resulting from design defect or
faulty workmanship
34. Green-Related Issues Regarding Exclusions from E&O and CGL Policies
- Typically, the standard of care (i.e., negligence) is not sufficient to
cover the enhanced green-related obligations, so must confirm extent
of coverage, and must thoroughly investigate the materials and
technologies being used, and consistently be sensitive LEED
requirements
- No coverage for the following:
Warranties or guaranties or claims arising therefrom
Contractual obligation to achieve a certain LEED Rating (i.e.,
LEED Silver or Gold)
Contractual obligation to cause certain energy reductions or
similar outcomes
Certifications, declarations or warranties in connection with
LEED template
- For the foregoing reasons, contractors and design professionals must
be very prudent as to the contractual obligations they subject
themselves to, as the same may not be covered by insurance.
35. New products out on the market:
- Fireman’s Fund – Amended in 2006 to include green building specific
coverage
- Aon Corporation – Green Building Property Program assures
reimbursement for repair or replacement of green building
components, enabling owners to upgrade to environmentally efficient
components (covers certified and non-certified buildings). Tied to
local government mandates, as well as LEED and other recognized
standards
- XL Insurance – Sustainable Property Endorsement allows insured to
collect an amount greater than value of damaged property if replaced
with environmentally acceptable substitute (tied to LEED)
- Travelers – Just recently joined USGBC. Likely to lead to additional
green building insurance products in the market
– Performance Bonds
Guaranty, not insurance
Guarantees owner that a contractor will perform as required by its contract,
and will pay for required materials and labor
Insurance companies may be reluctant to guarantee the enhanced
contractual obligations of contractor in green building context
42. Abercorn Common Shopping Center, Savannah GA. – A Case Study
Vegetated Roof & White Roof Membrane to
Reflect/Absorb Heat and Keep Center Building Cooler
Pervious pavement diverts storm water
Concrete paving reflects
heat, keeping the center
and parking lot cooler
White roof membrane reflects heat, keeping the center cooler
43. Pervious Pavement
• Almost 1 acre of pervious
pavement, which allows water
to infiltrate the ground
(runoff coefficient of .3 vs .95 for
traditional concrete)
• Decreases the need for
municipal stormwater treatment
• Helps remove sediment and
pollutants
• Decreases site runoff by 25%
45. • Low-flow toilets & Faucets and
waterless urinals – reduce water
use
• Tighter envelope, better glazing &
high efficiency HVAC & lighting
to reduce energy consumption
• Located ¼ mile from 3 bus stops,
preferred parking for hybrid
vehicles; bike racks & changing
facilities – encourages use of
carpooling & alternate
transportation
46. • Low-emitting paints, sealants and adhesives used
– Zero or low volatile organic compounds (VOCs)
• No smoking (including restaurants) – before GA became
non-smoking
• Increased ventilation – 30% over ASHRAE 62
Indoor Environmental Quality
47. Abercorn Common Shopping Center, Savannah GA. – A Case Study
Waste Reduction
• Stringent construction waste management practices
– prevented 85% of construction waste from
landfills
• Over 6,000 tons were recycled or reused
48. Abercorn Common Shopping Center, Savannah GA. – A Case Study
• Over 70% of materials manufactured within a 500
mile radius
• Over 20% recycled materials by cost
• FSC Forest Stewardship Council Certified Wood
used at McDonald’s
500 mile
radius of
Savannah, GA
Materials and Resources
49. Abercorn Common is:
• 30% more energy efficient than code (ASHRAE 90.1)
• 55% more water efficient (than 1992 Energy Policy Act)
• Healthier indoor air – less toxins and more fresh air
• Has 30% Less stormwater runoff
• Uses no potable water for irrigation
Summary
50. Summary & Recommendations
• Green Building is here to stay
• LEED rating system is likely standard
• Contractor directly affects several prerequisites and point
• Enhanced risk issues for contractors
• Knowledge and careful allocation of contractual liabilities and
obligations is critical
• Rapidly evolving marketplace