Building Diagnostics
BUILDING SURVEYORS
INTENSIVE COURSE
24 Aug 2013 (Saturday)
Holiday Inn Glenmarie, Shah Alam, Selangor
Adi Irfan Che-Ani
UKM
http://www.eagle-wi.gov
UKM:Che-Ani 2013
PRESENTATION
OUTLINE
1. Survey & defect
2. Building defect: example
3. Building condition
survey: inspection
4. Building condition
survey: reporting
(CPBS101)
5. Summary
Page  3
Survey & Defect
UKM:Che-Ani 2013
http://myprservices.com
“Defects will occur in buildings. It is one of the great certainties in
construction, the equivalent of death and taxes in life more generally”.
(Professor Anthony Lavers)
Survey (Hollis & Gibson – Surveying
Buildings, 2005):
Inspection & investigation of construction &
services of property in sufficient details to enable
surveyor to advise what impact the condition &
circumstances of that property will have upon client.
http://www.buildingdefects.com.au/
http://www.blaketurner.com
Defects:
areas of non-compliance to the bye-
law, regulation, standard (mostly not subjective)
Out of acceptable condition (subjective)
Page  4
Survey & Defect
UKM:Che-Ani 2013
http://myprservices.com
Building Diagnostics:
Process of data collection
Further steps in building inspection
Normally using NDT equipment
What it is not:
- just identify defects
- simple walk through survey
- seeing from distance
- seeing off-site
Should answer: what is going to happen if the defect
is left unattended (prognosis/prediction)?
http://solteccorp.com/Images/PDF/soltec/images/
T00048IR.JPG
Page  5
Survey & Defect
UKM:Che-Ani 2013
From: Alan Mark Forster, James Douglas, (2010) "Condition
survey objectivity and philosophy driven masonry repair: An
increased probability for project divergence?", Structural
Survey, 28(5): 384 – 407.
Page  6
Survey & Defect
UKM:Che-Ani 2013
http://en.wikipedia.org/wiki/Category:Building_defects
Page  7
Growth of mould and algae due
to water ponding and continuous
dampness Water ponding due to blockage
of outlet to rainwater downpipe
(due to small outlet) – it’s very
hot during the course of
inspection
Page  8
Water mark on the ceiling
surface due to water penetration
from leaking roof (the brown
color suggest it dripped via
timber trusses, perhaps the
trusses need structural
inspection)
Stalactite effect due to
water proofing failure at
upstairs toilet
Page  9 UKM:Che-Ani 2013
BUILDING DEFECT
http://youtu.be/UfJ3HX4jIFQ
Page  10 UKM:Che-Ani 2013
BUILDING CONDITION SURVEY : INSPECTION
http://www.nienergyrating.com
An apparent defect has been
perceived when
It looks
wrong Something
smells strange
It just felt
wrong
(perhaps sixth
sense?)
Someone
heard
something
Something
felt…
http://webpages.s
hepherd.edu/JHE
NCK01/st_senses
.jpg
Page  11
Inspect All seem
OK?
Allocate priority in
accord with agreed
criteria
Is a matter of
health and safety
Record and
keep in mind
for future
Defect
confirmed
No further
action at this
time
UKM:Che-Ani 2013
BUILDING CONDITION SURVEY : INSPECTION
Page  12
Initiate urgent
action
Check and record work in progress early
on and periodically
Commission rectification work
Discuss and agree with client and users
Select
appropriate
specialists for
further
inspection
Prepare or select
appropriate
rectification
specification
Review periodically
(annually)?UKM:Che-Ani 2013
Page  13
 Various standard available
BUILDING CONDITION SURVEY : REPORTING
UKM:Che-Ani 2013
No Piawaian/
Dokumen
Tahun
dibang-
unkan
Kerja Pra-
Pemeriksaan
Kerja
ukur
kondisi
Keperluan
nilai
pasaran
Keperluan
anggaran
kos
Kaedah
pengkadaran/
numerik
Penggunaan
kod warna
Input data Cadangan
pembaikan
Kandungan
utama
pelaporan
1 RICS Building
Survey Report
2005 Kajian Meja Protokol
1 (visual)
Tidak
perlu
Tidak
perlu
Tiada Tiada Keadaan,
sebab,
tahap
kerosakan
Ada Pemeriksaan,
Laporan,
Penilaian
2 BRE Design
Quality Manual
2007 Tiada Protokol
1 (visual)
Perlu Perlu Ada Tiada Keadaan Ada Pemeriksaan,
Laporan,
Penilaian
3 ASTM E-2018 2008 Penelitian
dokumen &
temubual
Protokol
1 (visual)
Perlu Tiada Tiada Keadaan Ada Laporan
Keadaan
Hartanah
4 The RICS Home
Buyer Report
2009
2009 Tidak perlu Protokol
1 (visual)
Perlu Perlu 3 kadaran Ada Keadaan Ada Pemeriksaan,
Laporan,
Penilaian
5 Matriks CSP1 2010 Kajian meja Protokol
1 (visual)
Tidak
perlu
Tidak
perlu
Keadaan (5
kadaran) &
Keutamaan (4
kadaran)
Ada Keadaan,
Kepenting
an
Tiada Jadual keadaan
bangunan,
Kotak
gambarfoto,
pelan tandaan
kecacatan
6 RICS Condition
Report
2010 Tidak perlu Protokol
1 (visual)
Tidak
perlu
Tidak
perlu
3 kadaran Ada Keadaan Tiada Pemeriksaan,
Laporan
7 CP BS101 2011 Kajian meja Protokol
1 (visual)
Tidak
perlu
Perlu Ada (Building
Assessment &
Rating System
– BARIS)
Ada Keadaan,
Kepenting
an
Ada Jadual keadaan
bangunan,
Kotak
gambarfoto,
pelan tandaan
kecacatan
And many more…
Page  14 UKM:Che-Ani 2013
BUILDING CONDITION SURVEY : REPORTING
Problem: No standard is adopted….
Then you need
to be
certified….but
who certified
Page  15 UKM:Che-Ani 2013
Defects Group For Assessment Of
Architectural Works (Internal Finishes)
Weightage for
architectural elements
Sampling guideline for
architectural works
 Qlassic (construction quality)
BUILDING CONDITION SURVEY : REPORTING
Page  16 UKM:Che-Ani 2012
http://www.home-building-inspectors-ny.com/
CPBS101: Code of Practice for
Building Inspection Reports
BUILDING CONDITION SURVEY : REPORTING
Page  17
Contents
PART B : MAIN REPORT
PART A : EXECUTIVE SUMMARY
 Property Information
 Appointment Letter
 Terms of Reference
 Limitation of Inspection
 Finding & Recommendation
 Surveyor Declaration
 Copy of Inspection Certification
 Surveyor’s Competency
 Introduction
 Description of Property
 Method of Inspection
 Building Condition Assessment
i. External / Site Condition
ii. Fabric & Component
iii. Services
 Defect Analysis
 Conclusion & Recommendation
INTRODUCTION
Page  18
Contents
ATTACHMENT
PART C : APPENDICES
 Location & Site Plan
 As Build Drawing / Building Plan
 Defect Sheet
 Defect Indication Plan
 Building Specification (if any)
 Previous Report (if any from other consultants
 Appendix A – Sample of Inspection Certificate
 Appendix B – Details of BARIS Assessment
 Appendix C – Sample of the Schedule of Building Condition
Appendix E – Sample of Defect Sheet
 Appendix F – Schedule of Professional Fees
 Appendix G – Sample of Surveyor’s Competency
Page  19
PART A : EXECUTIVE SUMMARY
Page  20
PART A : EXECUTIVE SUMMARY
• Indicates the names of the owner, details of the
address & purpose of the report.
• Can be presented in a point form format.
• Attach with the endorsement by the client or his/ her
representative & dated.
• Indicate the agreed consultancy fees & basic for
payment & additional fees subject to the latest
approved scale of fees.
• Describes the scope of work & limitations of the
report that are required by surveyor.
• Covers the detailed instruction given by the client
(purpose of the survey, inspection date, the likely
delivery date of the report any specialist inspection
required, insurance details, dispute
procedure, payment method & any limitation).
• Limitation of the report could cover any assumption
made, general content of the report, hazardous
materials, human & environmental issues.
APPOINTMENT
LETTER
PROPERTY
INFORMATION
TERMS OF
REFERENCE
Page  21
PART A : EXECUTIVE SUMMARY
• Describes the protocol & practices of inspection
adopted (i.e. only Protocol 1: Visual Inspection).
• Lists the area/space that is not readily accessible
during the course of inspection, or any inspection
work that may have risk & may affect to the existing
condition of building or injury to the surveyor or the
third party.
• Surveyor also need to list any assumptions made in
order to express the inspection work diligently.
• Explains the overall building rating (extracted from
BARIS) either Good, Fair or Dilapidated.
• States the total marks, number of defects & total
score; for the overall defect.
• Surveyor needs to highlight any indication of the
building elements or components that might
become worst if left unattended over period of time,
particularly yellow-coded defects (if any).
• Surveyor must highlight to the client any other
information that in his/her opinion that affects the
current and future condition of the building.
FINDING &
RECOMMENDATION
LIMITATION OF
INSPECTION
Page  22
PART A : EXECUTIVE SUMMARY
SURVEYOR’S
DECLARATION
• Certify the inspection work that was carried
out, together with endorsement & qualification.
• “I hereby testify that the building has been inspected
on (dd/m/yy) until (dd/m/yy) and certify that the
condition level of the building as marked and described
in this report and its assessment rating is stated in the
attached Inspection Declaration Certificate”.
• Copy of the inspection certificate need to be
attached in this section.
• Surveyor need to attach his/ her competency
certificate that is issued by The Royal Institution of
Surveyors Malaysia.
COPY OF
INSPECTION
CERTIFICATION
SURVEYOR’S
DECLARATION
SURVEYOR’S
COMPETENCY
APPENDIX
A1
Page  24
APPENDIX
A2
Page  25
APPENDIX
G
Page  26
PART B : MAIN REPORT
Page  27
PART B : MAIN REPORT
• States client instruction, scope & limitation of
inspection work, building capacity & surveyor’s
competency (i.e. weather condition at the time
visit, purpose of inspection & related scope of work.
DESCRIPTION
OF PROPERTY
• Describes location & physical accessibility, types of
building, general design, physical condition & type
of construction, estimated age of building, special
features, materials, function & usage, tenure/ lease
period, record of previous inspection &
maintenance (if any) & full address of the property.
• Includes a brief history of property, ownership &
post construction scenario (i.e.
renovation, alteration, conservation, preservation
damages, defects, breakdowns, malfunctions of
services, change of use, previous & current
maintenance activities conducted).
DESCRIPTION
OF
PROPERTY
INTRODUCTION
Page  28
PART B : MAIN REPORT
• Describes survey protocols employed for
inspection, tool & equipment used for rating &
measurements, manpower, programme & schedule of
work & any specific service collaboration with other
professional.
• Examine condition & significant defects of the
building, in which the worst defect shall be described first.
• Defects may be supported by photographs or sketches
& technical provision used to express surveyor’s
findings.
• Data acquisition during building inspection shall be used
to describe building condition & analysis in BARIS
(Building Assessment Rating System).
• Details of BARIS is shown in Appendix B.
• In defect indication plan (Appendix C), the following
coding shall be used:
E (External/site)
F (Fabric)
S (Services)
i.e. E1 for ground condition, F1 for roof top & S1 for hot &
cold water supply.
DESCRIPTION
OF PROPERTY
BUILDING
CONDITION
ASSESSMENT
METHOD OF
INSPECTION
Page  29
BARIS Assessment APPENDIX
B
Scale
Priority Assessment
E4 U3 R2 N1
Condition
Assessment
5 20 15 10 5
4 16 12 8 4
3 12 9 6 3
2 8 6 4 2
1 4 3 2 1
No Matrix Score
1 Plan Maintenance 1 to 4
2 Condition Monitoring 5 to 12
3 Serious Attention 13 to 20
No Building Rating Score
1 Good 1 to 4
2 Fair 5 to 12
3 Dilapidated 13 to 20
Overall Building Rating
Page  30
BARIS Assessment APPENDIX
B
Condition Scale Value Description (Value)
1 New/ As New Minor Servicing
2 Fair Minor Repair
3 Poor Major Repair/Replacement
4 Very Poor Malfunction
5 Dilapidated Damage/Missing
Priority Scale Value Description (Value)
Normal 1 Functional, only cosmetic defect
Routine 2
Minor defect, but can lead to serious defect
if left unattended
Urgent 3
Serious defect, cannot function to an
acceptable standard
Emergency 4
Element/structure not function at all; OR
Risks that can lead to fatality and/or injury
Condition Assessment
Priority Assessment
Page  31
APPENDIX
D
Page  32
APPENDIX C
Page  33
Building
Condition
Assessment
EXTERNAL/
SITE
CONDITION
PART B : MAIN REPORT
Describes site &
ground
condition, exterior
elements of
building, parking
areas, driveway, cover
ed car
park, landscape, comp
ound
lightings, perimeter
fences, gates & refuse
disposal.
Describes building
mechanical & electrical
services (i.e. hot & cold water
supply, air conditioning &
mechanical ventilation
system, sanitation &
cleansing system, sewerage
system, fire protection
system, vertical & horizontal
transportation system, gas,
special services, public,
address system,
communication & network
system, surveillance system,
electrical services, safety &
security & sustainable
services system.
Describes the components of the building envelope
(i.e. the roof top; parapet, external & internal façade;
apron, perimeter drain, beam, column, floor, staircase,
ceiling, wall, window & door.
SERVICES
FABRIC &
COMPONENT
Page  34
PART B : MAIN REPORT
• Describes analysis that illustrates frequency and/or
percentage concerning the defects in Schedule of
Building Condition.
• Might be presented in the form of bar chart, pie
chart, line or spider web charts.
• Overall defects findings are analysed and shall be
presented using Schedule of Building Condition.
• ICT/ related software (i.e. GIS, SPSS, Microsoft
Excel, BUILD-IR) shall be mentioned.
• BARIS shall be used to indicate the overall building co
conditions.
• Details of the Schedule of Building Condition Appendix D.
• Provides overall building condition assessment &
rating of property.
• Includes any recommendation for repair &
remedial works to be carried out.
• Recommendation may be shown under separate
heading.
• Estimated cost of repair may be included if it is
specified in the scope of work.
CONCLUSION &
RECOMMENDATION
DEFECT
ANALYSIS
Page  35
PART C : APPENDICES
Page  36
PART C : APPENDICES
• Show the site & its boundary.
• Surveyor should identify the inspected building (i.e.
outlining it in red).
• Site plan must clearly identify the inspected building
& its boundary.
• Photograph of the site, its surrounding & façade of
inspected building can be included.
• Provides full set of drawings/plan of the existing
inspected building.
• Should provide “as-is”, that shows the existing
condition of the building during the course of
inspection.
• Drawing/ plan depicts the actual existing
condition/ space layout/ openings, as apposed to
designs or proposed conditions.
• Should be tidy & free from any marking (i.e. no
marking of defects location).
AS BUILT
DRAWING/
BUILDING PLANT
LOCATION &
SITE PLAN
Page  37
PART C : APPENDICES
• Simplified format of the on-site survey checklist.
• Must be in parallel & is accordance to Schedule of
Building Condition & Defect Indication Plan.
• Information shall comprise of (but not limited to) defect
sheet number, photograph/ sketch
section, level, location, element/component, scoring
information (i.e. BARIS), defect description, possible
causes & any necessary information.
• Sample is shown in Appendix E.
• Must be in parallel & accordance to Schedule of
Building Condition & Defect Sheet.
• All defects must be shown in this plan/elevation,
according to their coding system.
• Only the coding is shown.
• Surveyor is free to include any photographs that
might be useful in reading this plan, provided that it
is placed in a neat & tidy manner.
• Sample is shown in Appendix C.
DEFECT
INDICATION
PLAN
DEFECT SHEET
Page  38
APPENDIX E
Page  39
APPENDIX C
Page  40
PART C : APPENDICES
• An extraction from the tender/contract document of
the building.
• Record the specification of main building elements &
any specific construction or services that are being
installed to the building.
• List & contact of all consultants, main contractor &
any other stakeholders that are listed in the
tender/contract document shall be made available.
• Building inspection work might require a specific
report (i.e. mechanical equipment testing, soil
stabilization survey, condition monitoring & other
services provided by specialist and/or construction
professionals).
• Surveyor should procure & coordinate such special
report as part of the main report.
• All special report attached must be prepared &
certified in accordance with prevailing professional
standards & ethics, in which the special report must
adhere.
PREVIOUS
REPORT
(IF ANY FROM
OTHER)
BUILDING
SPECIFICATION
(IF ANY)
Page  41
How “defect” benefit us…
UKM:Che-Ani 2013
It wasn’t hit by the massive earthquake. In true fashion of the Ripley Legacy, it
was built to reflect the odd 1812 earthquake that measured 8.0 on the rick.
The building has now become one of the most photographed in the world.
Page  42
SUMMARY
UKM:Che-Ani 2013
 Start up: building defects identification – more than an “album”
 Inspection: building defect diagnostic – defects are here & there:
so what? You might need a tool
 Reporting: standard and certified – qualify to stand in court
 For Building Surveyors: Follow CPBS101
“We do not want a structural survey. If you can just have a quick
look at the house to make sure that it is structurally sound, that
will be fine”
(Extract from client’s letter of instruction)
Page  43
Thank you very much
adiirfan@gmail.com
- reflection -

Contenu connexe

Tendances

Sectional completion and partial possession by employer PP2 Coursework 1
Sectional completion and partial possession by employer PP2 Coursework 1Sectional completion and partial possession by employer PP2 Coursework 1
Sectional completion and partial possession by employer PP2 Coursework 1Arissa Loh
 
Building Technology I : Project 1 : IBS
Building Technology I : Project 1 : IBSBuilding Technology I : Project 1 : IBS
Building Technology I : Project 1 : IBSJing Fan Koh
 
Industrialised Building Solution
Industrialised Building SolutionIndustrialised Building Solution
Industrialised Building SolutionLee Wan Xuan
 
Assignment - Preliminary Cost Appraisal
Assignment - Preliminary Cost AppraisalAssignment - Preliminary Cost Appraisal
Assignment - Preliminary Cost AppraisalKai Yun Pang
 
DIFFERENCE BETWEEN CONTRACT FORM JKR 203A & PAM
DIFFERENCE BETWEEN CONTRACT FORM JKR 203A & PAMDIFFERENCE BETWEEN CONTRACT FORM JKR 203A & PAM
DIFFERENCE BETWEEN CONTRACT FORM JKR 203A & PAMAnep Botak
 
Building Technology Project 1
Building Technology Project 1Building Technology Project 1
Building Technology Project 1zerospaces_
 
A. meaning of_fixtures
A. meaning of_fixturesA. meaning of_fixtures
A. meaning of_fixturesFlora Norman
 
ECA Workshop - ECA Form
ECA Workshop - ECA FormECA Workshop - ECA Form
ECA Workshop - ECA FormKai Yun Pang
 
Project management (1)
Project management (1)Project management (1)
Project management (1)aarenneoone
 
Bq preamble
Bq preambleBq preamble
Bq preambleaizat76
 
Group Assignment:IBS System
Group Assignment:IBS SystemGroup Assignment:IBS System
Group Assignment:IBS System마 이환
 
Tender evaluation procedure
Tender evaluation procedureTender evaluation procedure
Tender evaluation procedureayushida
 
HOW CONSERVATION WORKS TAKE PLACE IN MALAYSIA
HOW CONSERVATION WORKS TAKE PLACE IN MALAYSIAHOW CONSERVATION WORKS TAKE PLACE IN MALAYSIA
HOW CONSERVATION WORKS TAKE PLACE IN MALAYSIAFakhrul Afifi
 
B.tech Project 1 - Industrialised Building Systems
B.tech Project 1 - Industrialised Building SystemsB.tech Project 1 - Industrialised Building Systems
B.tech Project 1 - Industrialised Building SystemsCarmen Chan
 
ECA Workshop - Brief
ECA Workshop - BriefECA Workshop - Brief
ECA Workshop - BriefKai Yun Pang
 
site visit report (final)
site visit report (final)site visit report (final)
site visit report (final)Jia Hong Mui
 

Tendances (20)

Sectional completion and partial possession by employer PP2 Coursework 1
Sectional completion and partial possession by employer PP2 Coursework 1Sectional completion and partial possession by employer PP2 Coursework 1
Sectional completion and partial possession by employer PP2 Coursework 1
 
Building Technology I : Project 1 : IBS
Building Technology I : Project 1 : IBSBuilding Technology I : Project 1 : IBS
Building Technology I : Project 1 : IBS
 
Industrialised Building Solution
Industrialised Building SolutionIndustrialised Building Solution
Industrialised Building Solution
 
Assignment - Preliminary Cost Appraisal
Assignment - Preliminary Cost AppraisalAssignment - Preliminary Cost Appraisal
Assignment - Preliminary Cost Appraisal
 
Site possession
Site possessionSite possession
Site possession
 
DIFFERENCE BETWEEN CONTRACT FORM JKR 203A & PAM
DIFFERENCE BETWEEN CONTRACT FORM JKR 203A & PAMDIFFERENCE BETWEEN CONTRACT FORM JKR 203A & PAM
DIFFERENCE BETWEEN CONTRACT FORM JKR 203A & PAM
 
Building Technology Project 1
Building Technology Project 1Building Technology Project 1
Building Technology Project 1
 
RIBA plan of work
RIBA plan of workRIBA plan of work
RIBA plan of work
 
A. meaning of_fixtures
A. meaning of_fixturesA. meaning of_fixtures
A. meaning of_fixtures
 
ECA Workshop - ECA Form
ECA Workshop - ECA FormECA Workshop - ECA Form
ECA Workshop - ECA Form
 
Project management (1)
Project management (1)Project management (1)
Project management (1)
 
Pp2 chapter 1 cheeyong & yih shyang
Pp2 chapter 1 cheeyong & yih shyangPp2 chapter 1 cheeyong & yih shyang
Pp2 chapter 1 cheeyong & yih shyang
 
Bq preamble
Bq preambleBq preamble
Bq preamble
 
Group Assignment:IBS System
Group Assignment:IBS SystemGroup Assignment:IBS System
Group Assignment:IBS System
 
Tender evaluation procedure
Tender evaluation procedureTender evaluation procedure
Tender evaluation procedure
 
HOW CONSERVATION WORKS TAKE PLACE IN MALAYSIA
HOW CONSERVATION WORKS TAKE PLACE IN MALAYSIAHOW CONSERVATION WORKS TAKE PLACE IN MALAYSIA
HOW CONSERVATION WORKS TAKE PLACE IN MALAYSIA
 
B.tech Project 1 - Industrialised Building Systems
B.tech Project 1 - Industrialised Building SystemsB.tech Project 1 - Industrialised Building Systems
B.tech Project 1 - Industrialised Building Systems
 
ECA Workshop - Brief
ECA Workshop - BriefECA Workshop - Brief
ECA Workshop - Brief
 
site visit report (final)
site visit report (final)site visit report (final)
site visit report (final)
 
Elemental Cost Analysis
Elemental Cost AnalysisElemental Cost Analysis
Elemental Cost Analysis
 

En vedette

Building condition survey whats more
Building condition survey whats moreBuilding condition survey whats more
Building condition survey whats moreAdiirfan Che-ani
 
Building condition assessment
Building condition assessmentBuilding condition assessment
Building condition assessmentabhishekabhi123
 
Sustainable in asset management
Sustainable in asset managementSustainable in asset management
Sustainable in asset managementAdiirfan Che-ani
 
Defective Construction Work
Defective Construction WorkDefective Construction Work
Defective Construction WorkAdiirfan Che-ani
 
Journal Writing: Lets Start
Journal Writing: Lets StartJournal Writing: Lets Start
Journal Writing: Lets StartAdiirfan Che-ani
 
Risk Analysis and Management Process Flow Chart
Risk Analysis and Management Process Flow ChartRisk Analysis and Management Process Flow Chart
Risk Analysis and Management Process Flow ChartKathy Vinatieri
 
Facility Condition Assessment And Asset Management With GIS
Facility Condition Assessment And Asset Management With GISFacility Condition Assessment And Asset Management With GIS
Facility Condition Assessment And Asset Management With GISJohn Przybyla
 
Fire protection io may 2014 c
Fire protection io may 2014 cFire protection io may 2014 c
Fire protection io may 2014 cAmit PATNI
 
Ada Transition Plans (Apbp webinar)
Ada Transition Plans (Apbp webinar)Ada Transition Plans (Apbp webinar)
Ada Transition Plans (Apbp webinar)Franz Loewenherz
 
2014 Accessibility and the ADA CES Course
2014 Accessibility and the ADA CES Course2014 Accessibility and the ADA CES Course
2014 Accessibility and the ADA CES CourseMike Santos
 

En vedette (20)

Building condition survey whats more
Building condition survey whats moreBuilding condition survey whats more
Building condition survey whats more
 
Building condition assessment
Building condition assessmentBuilding condition assessment
Building condition assessment
 
GBI: Role of BS
GBI: Role of BSGBI: Role of BS
GBI: Role of BS
 
Fm getting online
Fm getting onlineFm getting online
Fm getting online
 
Mpam 3 basic steps
Mpam 3 basic stepsMpam 3 basic steps
Mpam 3 basic steps
 
Sustainable in asset management
Sustainable in asset managementSustainable in asset management
Sustainable in asset management
 
Taklimat ifolio pelajar
Taklimat ifolio pelajarTaklimat ifolio pelajar
Taklimat ifolio pelajar
 
Defective Construction Work
Defective Construction WorkDefective Construction Work
Defective Construction Work
 
Journal Writing: Lets Start
Journal Writing: Lets StartJournal Writing: Lets Start
Journal Writing: Lets Start
 
BOE Referendum Discussion 9-10-15
BOE Referendum Discussion 9-10-15BOE Referendum Discussion 9-10-15
BOE Referendum Discussion 9-10-15
 
twintech wshop2-main ppt
twintech wshop2-main ppttwintech wshop2-main ppt
twintech wshop2-main ppt
 
Building Analysis-1
Building Analysis-1Building Analysis-1
Building Analysis-1
 
twintech wshop1-main ppt
twintech wshop1-main ppttwintech wshop1-main ppt
twintech wshop1-main ppt
 
Risk Analysis and Management Process Flow Chart
Risk Analysis and Management Process Flow ChartRisk Analysis and Management Process Flow Chart
Risk Analysis and Management Process Flow Chart
 
Facility Condition Assessment And Asset Management With GIS
Facility Condition Assessment And Asset Management With GISFacility Condition Assessment And Asset Management With GIS
Facility Condition Assessment And Asset Management With GIS
 
Fire protection io may 2014 c
Fire protection io may 2014 cFire protection io may 2014 c
Fire protection io may 2014 c
 
Building survrying
Building survryingBuilding survrying
Building survrying
 
Guidance 2010 ada_standards_prt
Guidance 2010 ada_standards_prtGuidance 2010 ada_standards_prt
Guidance 2010 ada_standards_prt
 
Ada Transition Plans (Apbp webinar)
Ada Transition Plans (Apbp webinar)Ada Transition Plans (Apbp webinar)
Ada Transition Plans (Apbp webinar)
 
2014 Accessibility and the ADA CES Course
2014 Accessibility and the ADA CES Course2014 Accessibility and the ADA CES Course
2014 Accessibility and the ADA CES Course
 

Similaire à Building Diagnostics Survey

Similaire à Building Diagnostics Survey (20)

Deterioration of Concrete
Deterioration of ConcreteDeterioration of Concrete
Deterioration of Concrete
 
1. Quality Assurance and Quality Control.pdf
1. Quality Assurance and Quality Control.pdf1. Quality Assurance and Quality Control.pdf
1. Quality Assurance and Quality Control.pdf
 
1. Quality Assurance and Quality Control.pdf
1. Quality Assurance and Quality Control.pdf1. Quality Assurance and Quality Control.pdf
1. Quality Assurance and Quality Control.pdf
 
2014-2015
2014-20152014-2015
2014-2015
 
Farrukh ali hassan civil engineer cv
Farrukh ali hassan   civil engineer cvFarrukh ali hassan   civil engineer cv
Farrukh ali hassan civil engineer cv
 
QA/QC INSPECTION ENGINEER
QA/QC INSPECTION ENGINEERQA/QC INSPECTION ENGINEER
QA/QC INSPECTION ENGINEER
 
UPDATED RESUME 2016
UPDATED RESUME 2016UPDATED RESUME 2016
UPDATED RESUME 2016
 
Sujit TPI CV
Sujit TPI CVSujit TPI CV
Sujit TPI CV
 
VA Cx Presentation_SRE Training 2013 Final_v2
VA Cx Presentation_SRE Training 2013 Final_v2VA Cx Presentation_SRE Training 2013 Final_v2
VA Cx Presentation_SRE Training 2013 Final_v2
 
Quality Management Plan
Quality Management PlanQuality Management Plan
Quality Management Plan
 
QA-QC_CIVIL ENGINEER
QA-QC_CIVIL ENGINEERQA-QC_CIVIL ENGINEER
QA-QC_CIVIL ENGINEER
 
Resume_Inst. QC_Hasnat
Resume_Inst. QC_HasnatResume_Inst. QC_Hasnat
Resume_Inst. QC_Hasnat
 
Forensic
ForensicForensic
Forensic
 
QC Civil A. Afzal
QC Civil A. AfzalQC Civil A. Afzal
QC Civil A. Afzal
 
Construction phases
Construction phasesConstruction phases
Construction phases
 
James
JamesJames
James
 
edwin cv for QA-QC Engineer
edwin cv for QA-QC Engineeredwin cv for QA-QC Engineer
edwin cv for QA-QC Engineer
 
commissioning guideline
commissioning guidelinecommissioning guideline
commissioning guideline
 
Pp1 seminar
Pp1 seminarPp1 seminar
Pp1 seminar
 
Kazi nazmul cv with all attachments
Kazi nazmul cv with all attachments Kazi nazmul cv with all attachments
Kazi nazmul cv with all attachments
 

Dernier

Call Girls In Mayur Vihar Delhi ☆↫8447779280 ❤Escorts Service In Delhi
Call Girls In Mayur Vihar Delhi ☆↫8447779280 ❤Escorts Service In DelhiCall Girls In Mayur Vihar Delhi ☆↫8447779280 ❤Escorts Service In Delhi
Call Girls In Mayur Vihar Delhi ☆↫8447779280 ❤Escorts Service In Delhiasmaqueen5
 
Premium Villa Projects in Sarjapur Road Bengaluru
Premium Villa Projects in Sarjapur Road BengaluruPremium Villa Projects in Sarjapur Road Bengaluru
Premium Villa Projects in Sarjapur Road BengaluruShivaSeo3
 
Majestique Viman Nagar Pune Brochure.pdf
Majestique Viman Nagar Pune Brochure.pdfMajestique Viman Nagar Pune Brochure.pdf
Majestique Viman Nagar Pune Brochure.pdfBabyrudram
 
9990771857 Call Girls in Dwarka Sector 1 Delhi (Call Girls) Delhi
9990771857 Call Girls in Dwarka Sector 1 Delhi (Call Girls) Delhi9990771857 Call Girls in Dwarka Sector 1 Delhi (Call Girls) Delhi
9990771857 Call Girls in Dwarka Sector 1 Delhi (Call Girls) Delhidelhimodel235
 
Call Girls In Hari Nagar Dadb Block {8447779280}Hari Nagar {West Delhi Escort...
Call Girls In Hari Nagar Dadb Block {8447779280}Hari Nagar {West Delhi Escort...Call Girls In Hari Nagar Dadb Block {8447779280}Hari Nagar {West Delhi Escort...
Call Girls In Hari Nagar Dadb Block {8447779280}Hari Nagar {West Delhi Escort...asmaqueen5
 
Call Girls In Chand Nagar (Delhi)+918447779280 Welcome To Vip Women Seeking M...
Call Girls In Chand Nagar (Delhi)+918447779280 Welcome To Vip Women Seeking M...Call Girls In Chand Nagar (Delhi)+918447779280 Welcome To Vip Women Seeking M...
Call Girls In Chand Nagar (Delhi)+918447779280 Welcome To Vip Women Seeking M...asmaqueen5
 
How to Build Multifamily and Laneway Suites in Toronto!! (feat. Expert Archi...
How to Build Multifamily and Laneway Suites  in Toronto!! (feat. Expert Archi...How to Build Multifamily and Laneway Suites  in Toronto!! (feat. Expert Archi...
How to Build Multifamily and Laneway Suites in Toronto!! (feat. Expert Archi...Volition Properties
 
TENANT SCREENING REPORT SERVICES​ How Tenant Screening Reports Work
TENANT SCREENING REPORT SERVICES​ How Tenant Screening Reports WorkTENANT SCREENING REPORT SERVICES​ How Tenant Screening Reports Work
TENANT SCREENING REPORT SERVICES​ How Tenant Screening Reports WorkTurbo Tenant
 
Raquel Thompson: Combining Creativity with Practicality in Architecture
Raquel Thompson: Combining  Creativity with Practicality in ArchitectureRaquel Thompson: Combining  Creativity with Practicality in Architecture
Raquel Thompson: Combining Creativity with Practicality in ArchitectureRaquel Thompson Barbados
 
Shapoorji Pallonji Joyville Vista Pune | Spend Your Family Time Together
Shapoorji Pallonji Joyville Vista Pune | Spend Your Family Time TogetherShapoorji Pallonji Joyville Vista Pune | Spend Your Family Time Together
Shapoorji Pallonji Joyville Vista Pune | Spend Your Family Time Togetheraidasheikh47
 
Mahindra Happinest Tathawade Pune Brochure.pdf
Mahindra Happinest Tathawade Pune Brochure.pdfMahindra Happinest Tathawade Pune Brochure.pdf
Mahindra Happinest Tathawade Pune Brochure.pdfBabyrudram
 
Call Girls in Adarsh Nagar Delhi 💯Call Us 🔝 9582086666🔝 South Delhi Escorts S...
Call Girls in Adarsh Nagar Delhi 💯Call Us 🔝 9582086666🔝 South Delhi Escorts S...Call Girls in Adarsh Nagar Delhi 💯Call Us 🔝 9582086666🔝 South Delhi Escorts S...
Call Girls in Adarsh Nagar Delhi 💯Call Us 🔝 9582086666🔝 South Delhi Escorts S...delhimodel235
 
Aparna Greenscapes Kompally Hyderabad E - Brochure.pdf
Aparna Greenscapes Kompally Hyderabad E - Brochure.pdfAparna Greenscapes Kompally Hyderabad E - Brochure.pdf
Aparna Greenscapes Kompally Hyderabad E - Brochure.pdffaheemali990101
 
Kohinoor Flats In Hinjewadi Phase 2 | Homes Built To Suit Your Needs
Kohinoor Flats In Hinjewadi Phase 2 | Homes Built To Suit Your NeedsKohinoor Flats In Hinjewadi Phase 2 | Homes Built To Suit Your Needs
Kohinoor Flats In Hinjewadi Phase 2 | Homes Built To Suit Your Needsaidasheikh47
 
FULL ENJOY - 8264348440 Call Girls in DLf Phase 4 | Gurgaon
FULL ENJOY - 8264348440 Call Girls in DLf Phase 4 | GurgaonFULL ENJOY - 8264348440 Call Girls in DLf Phase 4 | Gurgaon
FULL ENJOY - 8264348440 Call Girls in DLf Phase 4 | Gurgaonsoniya singh
 
Call Girls in Noida Sector 77 Noida 💯Call Us 🔝 9582086666 🔝 South Delhi Escor...
Call Girls in Noida Sector 77 Noida 💯Call Us 🔝 9582086666 🔝 South Delhi Escor...Call Girls in Noida Sector 77 Noida 💯Call Us 🔝 9582086666 🔝 South Delhi Escor...
Call Girls in Noida Sector 77 Noida 💯Call Us 🔝 9582086666 🔝 South Delhi Escor...delhimodel235
 
Maha Mauka Squarefeet Brochure |Maha Mauka Squarefeet PDF Brochure|
Maha Mauka Squarefeet Brochure |Maha Mauka Squarefeet PDF Brochure|Maha Mauka Squarefeet Brochure |Maha Mauka Squarefeet PDF Brochure|
Maha Mauka Squarefeet Brochure |Maha Mauka Squarefeet PDF Brochure|AkshayJoshi575980
 
Call Girls In Laxmi Nagar Delhi +91-8447779280! !Best Woman Seeking Man Escor...
Call Girls In Laxmi Nagar Delhi +91-8447779280! !Best Woman Seeking Man Escor...Call Girls In Laxmi Nagar Delhi +91-8447779280! !Best Woman Seeking Man Escor...
Call Girls In Laxmi Nagar Delhi +91-8447779280! !Best Woman Seeking Man Escor...asmaqueen5
 
9711199012 Call {Girls Delhi} Very Low rate Vaishali DownLoad PDF
9711199012 Call {Girls Delhi} Very Low rate Vaishali DownLoad PDF9711199012 Call {Girls Delhi} Very Low rate Vaishali DownLoad PDF
9711199012 Call {Girls Delhi} Very Low rate Vaishali DownLoad PDFMs Riya
 
Call Girls in laxmi Nagar Delhi 💯Call Us 🔝 9582086666🔝 South Delhi Escorts Se...
Call Girls in laxmi Nagar Delhi 💯Call Us 🔝 9582086666🔝 South Delhi Escorts Se...Call Girls in laxmi Nagar Delhi 💯Call Us 🔝 9582086666🔝 South Delhi Escorts Se...
Call Girls in laxmi Nagar Delhi 💯Call Us 🔝 9582086666🔝 South Delhi Escorts Se...delhimodel235
 

Dernier (20)

Call Girls In Mayur Vihar Delhi ☆↫8447779280 ❤Escorts Service In Delhi
Call Girls In Mayur Vihar Delhi ☆↫8447779280 ❤Escorts Service In DelhiCall Girls In Mayur Vihar Delhi ☆↫8447779280 ❤Escorts Service In Delhi
Call Girls In Mayur Vihar Delhi ☆↫8447779280 ❤Escorts Service In Delhi
 
Premium Villa Projects in Sarjapur Road Bengaluru
Premium Villa Projects in Sarjapur Road BengaluruPremium Villa Projects in Sarjapur Road Bengaluru
Premium Villa Projects in Sarjapur Road Bengaluru
 
Majestique Viman Nagar Pune Brochure.pdf
Majestique Viman Nagar Pune Brochure.pdfMajestique Viman Nagar Pune Brochure.pdf
Majestique Viman Nagar Pune Brochure.pdf
 
9990771857 Call Girls in Dwarka Sector 1 Delhi (Call Girls) Delhi
9990771857 Call Girls in Dwarka Sector 1 Delhi (Call Girls) Delhi9990771857 Call Girls in Dwarka Sector 1 Delhi (Call Girls) Delhi
9990771857 Call Girls in Dwarka Sector 1 Delhi (Call Girls) Delhi
 
Call Girls In Hari Nagar Dadb Block {8447779280}Hari Nagar {West Delhi Escort...
Call Girls In Hari Nagar Dadb Block {8447779280}Hari Nagar {West Delhi Escort...Call Girls In Hari Nagar Dadb Block {8447779280}Hari Nagar {West Delhi Escort...
Call Girls In Hari Nagar Dadb Block {8447779280}Hari Nagar {West Delhi Escort...
 
Call Girls In Chand Nagar (Delhi)+918447779280 Welcome To Vip Women Seeking M...
Call Girls In Chand Nagar (Delhi)+918447779280 Welcome To Vip Women Seeking M...Call Girls In Chand Nagar (Delhi)+918447779280 Welcome To Vip Women Seeking M...
Call Girls In Chand Nagar (Delhi)+918447779280 Welcome To Vip Women Seeking M...
 
How to Build Multifamily and Laneway Suites in Toronto!! (feat. Expert Archi...
How to Build Multifamily and Laneway Suites  in Toronto!! (feat. Expert Archi...How to Build Multifamily and Laneway Suites  in Toronto!! (feat. Expert Archi...
How to Build Multifamily and Laneway Suites in Toronto!! (feat. Expert Archi...
 
TENANT SCREENING REPORT SERVICES​ How Tenant Screening Reports Work
TENANT SCREENING REPORT SERVICES​ How Tenant Screening Reports WorkTENANT SCREENING REPORT SERVICES​ How Tenant Screening Reports Work
TENANT SCREENING REPORT SERVICES​ How Tenant Screening Reports Work
 
Raquel Thompson: Combining Creativity with Practicality in Architecture
Raquel Thompson: Combining  Creativity with Practicality in ArchitectureRaquel Thompson: Combining  Creativity with Practicality in Architecture
Raquel Thompson: Combining Creativity with Practicality in Architecture
 
Shapoorji Pallonji Joyville Vista Pune | Spend Your Family Time Together
Shapoorji Pallonji Joyville Vista Pune | Spend Your Family Time TogetherShapoorji Pallonji Joyville Vista Pune | Spend Your Family Time Together
Shapoorji Pallonji Joyville Vista Pune | Spend Your Family Time Together
 
Mahindra Happinest Tathawade Pune Brochure.pdf
Mahindra Happinest Tathawade Pune Brochure.pdfMahindra Happinest Tathawade Pune Brochure.pdf
Mahindra Happinest Tathawade Pune Brochure.pdf
 
Call Girls in Adarsh Nagar Delhi 💯Call Us 🔝 9582086666🔝 South Delhi Escorts S...
Call Girls in Adarsh Nagar Delhi 💯Call Us 🔝 9582086666🔝 South Delhi Escorts S...Call Girls in Adarsh Nagar Delhi 💯Call Us 🔝 9582086666🔝 South Delhi Escorts S...
Call Girls in Adarsh Nagar Delhi 💯Call Us 🔝 9582086666🔝 South Delhi Escorts S...
 
Aparna Greenscapes Kompally Hyderabad E - Brochure.pdf
Aparna Greenscapes Kompally Hyderabad E - Brochure.pdfAparna Greenscapes Kompally Hyderabad E - Brochure.pdf
Aparna Greenscapes Kompally Hyderabad E - Brochure.pdf
 
Kohinoor Flats In Hinjewadi Phase 2 | Homes Built To Suit Your Needs
Kohinoor Flats In Hinjewadi Phase 2 | Homes Built To Suit Your NeedsKohinoor Flats In Hinjewadi Phase 2 | Homes Built To Suit Your Needs
Kohinoor Flats In Hinjewadi Phase 2 | Homes Built To Suit Your Needs
 
FULL ENJOY - 8264348440 Call Girls in DLf Phase 4 | Gurgaon
FULL ENJOY - 8264348440 Call Girls in DLf Phase 4 | GurgaonFULL ENJOY - 8264348440 Call Girls in DLf Phase 4 | Gurgaon
FULL ENJOY - 8264348440 Call Girls in DLf Phase 4 | Gurgaon
 
Call Girls in Noida Sector 77 Noida 💯Call Us 🔝 9582086666 🔝 South Delhi Escor...
Call Girls in Noida Sector 77 Noida 💯Call Us 🔝 9582086666 🔝 South Delhi Escor...Call Girls in Noida Sector 77 Noida 💯Call Us 🔝 9582086666 🔝 South Delhi Escor...
Call Girls in Noida Sector 77 Noida 💯Call Us 🔝 9582086666 🔝 South Delhi Escor...
 
Maha Mauka Squarefeet Brochure |Maha Mauka Squarefeet PDF Brochure|
Maha Mauka Squarefeet Brochure |Maha Mauka Squarefeet PDF Brochure|Maha Mauka Squarefeet Brochure |Maha Mauka Squarefeet PDF Brochure|
Maha Mauka Squarefeet Brochure |Maha Mauka Squarefeet PDF Brochure|
 
Call Girls In Laxmi Nagar Delhi +91-8447779280! !Best Woman Seeking Man Escor...
Call Girls In Laxmi Nagar Delhi +91-8447779280! !Best Woman Seeking Man Escor...Call Girls In Laxmi Nagar Delhi +91-8447779280! !Best Woman Seeking Man Escor...
Call Girls In Laxmi Nagar Delhi +91-8447779280! !Best Woman Seeking Man Escor...
 
9711199012 Call {Girls Delhi} Very Low rate Vaishali DownLoad PDF
9711199012 Call {Girls Delhi} Very Low rate Vaishali DownLoad PDF9711199012 Call {Girls Delhi} Very Low rate Vaishali DownLoad PDF
9711199012 Call {Girls Delhi} Very Low rate Vaishali DownLoad PDF
 
Call Girls in laxmi Nagar Delhi 💯Call Us 🔝 9582086666🔝 South Delhi Escorts Se...
Call Girls in laxmi Nagar Delhi 💯Call Us 🔝 9582086666🔝 South Delhi Escorts Se...Call Girls in laxmi Nagar Delhi 💯Call Us 🔝 9582086666🔝 South Delhi Escorts Se...
Call Girls in laxmi Nagar Delhi 💯Call Us 🔝 9582086666🔝 South Delhi Escorts Se...
 

Building Diagnostics Survey

  • 1. Building Diagnostics BUILDING SURVEYORS INTENSIVE COURSE 24 Aug 2013 (Saturday) Holiday Inn Glenmarie, Shah Alam, Selangor Adi Irfan Che-Ani UKM http://www.eagle-wi.gov UKM:Che-Ani 2013
  • 2. PRESENTATION OUTLINE 1. Survey & defect 2. Building defect: example 3. Building condition survey: inspection 4. Building condition survey: reporting (CPBS101) 5. Summary
  • 3. Page  3 Survey & Defect UKM:Che-Ani 2013 http://myprservices.com “Defects will occur in buildings. It is one of the great certainties in construction, the equivalent of death and taxes in life more generally”. (Professor Anthony Lavers) Survey (Hollis & Gibson – Surveying Buildings, 2005): Inspection & investigation of construction & services of property in sufficient details to enable surveyor to advise what impact the condition & circumstances of that property will have upon client. http://www.buildingdefects.com.au/ http://www.blaketurner.com Defects: areas of non-compliance to the bye- law, regulation, standard (mostly not subjective) Out of acceptable condition (subjective)
  • 4. Page  4 Survey & Defect UKM:Che-Ani 2013 http://myprservices.com Building Diagnostics: Process of data collection Further steps in building inspection Normally using NDT equipment What it is not: - just identify defects - simple walk through survey - seeing from distance - seeing off-site Should answer: what is going to happen if the defect is left unattended (prognosis/prediction)? http://solteccorp.com/Images/PDF/soltec/images/ T00048IR.JPG
  • 5. Page  5 Survey & Defect UKM:Che-Ani 2013 From: Alan Mark Forster, James Douglas, (2010) "Condition survey objectivity and philosophy driven masonry repair: An increased probability for project divergence?", Structural Survey, 28(5): 384 – 407.
  • 6. Page  6 Survey & Defect UKM:Che-Ani 2013 http://en.wikipedia.org/wiki/Category:Building_defects
  • 7. Page  7 Growth of mould and algae due to water ponding and continuous dampness Water ponding due to blockage of outlet to rainwater downpipe (due to small outlet) – it’s very hot during the course of inspection
  • 8. Page  8 Water mark on the ceiling surface due to water penetration from leaking roof (the brown color suggest it dripped via timber trusses, perhaps the trusses need structural inspection) Stalactite effect due to water proofing failure at upstairs toilet
  • 9. Page  9 UKM:Che-Ani 2013 BUILDING DEFECT http://youtu.be/UfJ3HX4jIFQ
  • 10. Page  10 UKM:Che-Ani 2013 BUILDING CONDITION SURVEY : INSPECTION http://www.nienergyrating.com An apparent defect has been perceived when It looks wrong Something smells strange It just felt wrong (perhaps sixth sense?) Someone heard something Something felt… http://webpages.s hepherd.edu/JHE NCK01/st_senses .jpg
  • 11. Page  11 Inspect All seem OK? Allocate priority in accord with agreed criteria Is a matter of health and safety Record and keep in mind for future Defect confirmed No further action at this time UKM:Che-Ani 2013 BUILDING CONDITION SURVEY : INSPECTION
  • 12. Page  12 Initiate urgent action Check and record work in progress early on and periodically Commission rectification work Discuss and agree with client and users Select appropriate specialists for further inspection Prepare or select appropriate rectification specification Review periodically (annually)?UKM:Che-Ani 2013
  • 13. Page  13  Various standard available BUILDING CONDITION SURVEY : REPORTING UKM:Che-Ani 2013 No Piawaian/ Dokumen Tahun dibang- unkan Kerja Pra- Pemeriksaan Kerja ukur kondisi Keperluan nilai pasaran Keperluan anggaran kos Kaedah pengkadaran/ numerik Penggunaan kod warna Input data Cadangan pembaikan Kandungan utama pelaporan 1 RICS Building Survey Report 2005 Kajian Meja Protokol 1 (visual) Tidak perlu Tidak perlu Tiada Tiada Keadaan, sebab, tahap kerosakan Ada Pemeriksaan, Laporan, Penilaian 2 BRE Design Quality Manual 2007 Tiada Protokol 1 (visual) Perlu Perlu Ada Tiada Keadaan Ada Pemeriksaan, Laporan, Penilaian 3 ASTM E-2018 2008 Penelitian dokumen & temubual Protokol 1 (visual) Perlu Tiada Tiada Keadaan Ada Laporan Keadaan Hartanah 4 The RICS Home Buyer Report 2009 2009 Tidak perlu Protokol 1 (visual) Perlu Perlu 3 kadaran Ada Keadaan Ada Pemeriksaan, Laporan, Penilaian 5 Matriks CSP1 2010 Kajian meja Protokol 1 (visual) Tidak perlu Tidak perlu Keadaan (5 kadaran) & Keutamaan (4 kadaran) Ada Keadaan, Kepenting an Tiada Jadual keadaan bangunan, Kotak gambarfoto, pelan tandaan kecacatan 6 RICS Condition Report 2010 Tidak perlu Protokol 1 (visual) Tidak perlu Tidak perlu 3 kadaran Ada Keadaan Tiada Pemeriksaan, Laporan 7 CP BS101 2011 Kajian meja Protokol 1 (visual) Tidak perlu Perlu Ada (Building Assessment & Rating System – BARIS) Ada Keadaan, Kepenting an Ada Jadual keadaan bangunan, Kotak gambarfoto, pelan tandaan kecacatan And many more…
  • 14. Page  14 UKM:Che-Ani 2013 BUILDING CONDITION SURVEY : REPORTING Problem: No standard is adopted…. Then you need to be certified….but who certified
  • 15. Page  15 UKM:Che-Ani 2013 Defects Group For Assessment Of Architectural Works (Internal Finishes) Weightage for architectural elements Sampling guideline for architectural works  Qlassic (construction quality) BUILDING CONDITION SURVEY : REPORTING
  • 16. Page  16 UKM:Che-Ani 2012 http://www.home-building-inspectors-ny.com/ CPBS101: Code of Practice for Building Inspection Reports BUILDING CONDITION SURVEY : REPORTING
  • 17. Page  17 Contents PART B : MAIN REPORT PART A : EXECUTIVE SUMMARY  Property Information  Appointment Letter  Terms of Reference  Limitation of Inspection  Finding & Recommendation  Surveyor Declaration  Copy of Inspection Certification  Surveyor’s Competency  Introduction  Description of Property  Method of Inspection  Building Condition Assessment i. External / Site Condition ii. Fabric & Component iii. Services  Defect Analysis  Conclusion & Recommendation INTRODUCTION
  • 18. Page  18 Contents ATTACHMENT PART C : APPENDICES  Location & Site Plan  As Build Drawing / Building Plan  Defect Sheet  Defect Indication Plan  Building Specification (if any)  Previous Report (if any from other consultants  Appendix A – Sample of Inspection Certificate  Appendix B – Details of BARIS Assessment  Appendix C – Sample of the Schedule of Building Condition Appendix E – Sample of Defect Sheet  Appendix F – Schedule of Professional Fees  Appendix G – Sample of Surveyor’s Competency
  • 19. Page  19 PART A : EXECUTIVE SUMMARY
  • 20. Page  20 PART A : EXECUTIVE SUMMARY • Indicates the names of the owner, details of the address & purpose of the report. • Can be presented in a point form format. • Attach with the endorsement by the client or his/ her representative & dated. • Indicate the agreed consultancy fees & basic for payment & additional fees subject to the latest approved scale of fees. • Describes the scope of work & limitations of the report that are required by surveyor. • Covers the detailed instruction given by the client (purpose of the survey, inspection date, the likely delivery date of the report any specialist inspection required, insurance details, dispute procedure, payment method & any limitation). • Limitation of the report could cover any assumption made, general content of the report, hazardous materials, human & environmental issues. APPOINTMENT LETTER PROPERTY INFORMATION TERMS OF REFERENCE
  • 21. Page  21 PART A : EXECUTIVE SUMMARY • Describes the protocol & practices of inspection adopted (i.e. only Protocol 1: Visual Inspection). • Lists the area/space that is not readily accessible during the course of inspection, or any inspection work that may have risk & may affect to the existing condition of building or injury to the surveyor or the third party. • Surveyor also need to list any assumptions made in order to express the inspection work diligently. • Explains the overall building rating (extracted from BARIS) either Good, Fair or Dilapidated. • States the total marks, number of defects & total score; for the overall defect. • Surveyor needs to highlight any indication of the building elements or components that might become worst if left unattended over period of time, particularly yellow-coded defects (if any). • Surveyor must highlight to the client any other information that in his/her opinion that affects the current and future condition of the building. FINDING & RECOMMENDATION LIMITATION OF INSPECTION
  • 22. Page  22 PART A : EXECUTIVE SUMMARY SURVEYOR’S DECLARATION • Certify the inspection work that was carried out, together with endorsement & qualification. • “I hereby testify that the building has been inspected on (dd/m/yy) until (dd/m/yy) and certify that the condition level of the building as marked and described in this report and its assessment rating is stated in the attached Inspection Declaration Certificate”. • Copy of the inspection certificate need to be attached in this section. • Surveyor need to attach his/ her competency certificate that is issued by The Royal Institution of Surveyors Malaysia. COPY OF INSPECTION CERTIFICATION SURVEYOR’S DECLARATION SURVEYOR’S COMPETENCY
  • 26. Page  26 PART B : MAIN REPORT
  • 27. Page  27 PART B : MAIN REPORT • States client instruction, scope & limitation of inspection work, building capacity & surveyor’s competency (i.e. weather condition at the time visit, purpose of inspection & related scope of work. DESCRIPTION OF PROPERTY • Describes location & physical accessibility, types of building, general design, physical condition & type of construction, estimated age of building, special features, materials, function & usage, tenure/ lease period, record of previous inspection & maintenance (if any) & full address of the property. • Includes a brief history of property, ownership & post construction scenario (i.e. renovation, alteration, conservation, preservation damages, defects, breakdowns, malfunctions of services, change of use, previous & current maintenance activities conducted). DESCRIPTION OF PROPERTY INTRODUCTION
  • 28. Page  28 PART B : MAIN REPORT • Describes survey protocols employed for inspection, tool & equipment used for rating & measurements, manpower, programme & schedule of work & any specific service collaboration with other professional. • Examine condition & significant defects of the building, in which the worst defect shall be described first. • Defects may be supported by photographs or sketches & technical provision used to express surveyor’s findings. • Data acquisition during building inspection shall be used to describe building condition & analysis in BARIS (Building Assessment Rating System). • Details of BARIS is shown in Appendix B. • In defect indication plan (Appendix C), the following coding shall be used: E (External/site) F (Fabric) S (Services) i.e. E1 for ground condition, F1 for roof top & S1 for hot & cold water supply. DESCRIPTION OF PROPERTY BUILDING CONDITION ASSESSMENT METHOD OF INSPECTION
  • 29. Page  29 BARIS Assessment APPENDIX B Scale Priority Assessment E4 U3 R2 N1 Condition Assessment 5 20 15 10 5 4 16 12 8 4 3 12 9 6 3 2 8 6 4 2 1 4 3 2 1 No Matrix Score 1 Plan Maintenance 1 to 4 2 Condition Monitoring 5 to 12 3 Serious Attention 13 to 20 No Building Rating Score 1 Good 1 to 4 2 Fair 5 to 12 3 Dilapidated 13 to 20 Overall Building Rating
  • 30. Page  30 BARIS Assessment APPENDIX B Condition Scale Value Description (Value) 1 New/ As New Minor Servicing 2 Fair Minor Repair 3 Poor Major Repair/Replacement 4 Very Poor Malfunction 5 Dilapidated Damage/Missing Priority Scale Value Description (Value) Normal 1 Functional, only cosmetic defect Routine 2 Minor defect, but can lead to serious defect if left unattended Urgent 3 Serious defect, cannot function to an acceptable standard Emergency 4 Element/structure not function at all; OR Risks that can lead to fatality and/or injury Condition Assessment Priority Assessment
  • 33. Page  33 Building Condition Assessment EXTERNAL/ SITE CONDITION PART B : MAIN REPORT Describes site & ground condition, exterior elements of building, parking areas, driveway, cover ed car park, landscape, comp ound lightings, perimeter fences, gates & refuse disposal. Describes building mechanical & electrical services (i.e. hot & cold water supply, air conditioning & mechanical ventilation system, sanitation & cleansing system, sewerage system, fire protection system, vertical & horizontal transportation system, gas, special services, public, address system, communication & network system, surveillance system, electrical services, safety & security & sustainable services system. Describes the components of the building envelope (i.e. the roof top; parapet, external & internal façade; apron, perimeter drain, beam, column, floor, staircase, ceiling, wall, window & door. SERVICES FABRIC & COMPONENT
  • 34. Page  34 PART B : MAIN REPORT • Describes analysis that illustrates frequency and/or percentage concerning the defects in Schedule of Building Condition. • Might be presented in the form of bar chart, pie chart, line or spider web charts. • Overall defects findings are analysed and shall be presented using Schedule of Building Condition. • ICT/ related software (i.e. GIS, SPSS, Microsoft Excel, BUILD-IR) shall be mentioned. • BARIS shall be used to indicate the overall building co conditions. • Details of the Schedule of Building Condition Appendix D. • Provides overall building condition assessment & rating of property. • Includes any recommendation for repair & remedial works to be carried out. • Recommendation may be shown under separate heading. • Estimated cost of repair may be included if it is specified in the scope of work. CONCLUSION & RECOMMENDATION DEFECT ANALYSIS
  • 35. Page  35 PART C : APPENDICES
  • 36. Page  36 PART C : APPENDICES • Show the site & its boundary. • Surveyor should identify the inspected building (i.e. outlining it in red). • Site plan must clearly identify the inspected building & its boundary. • Photograph of the site, its surrounding & façade of inspected building can be included. • Provides full set of drawings/plan of the existing inspected building. • Should provide “as-is”, that shows the existing condition of the building during the course of inspection. • Drawing/ plan depicts the actual existing condition/ space layout/ openings, as apposed to designs or proposed conditions. • Should be tidy & free from any marking (i.e. no marking of defects location). AS BUILT DRAWING/ BUILDING PLANT LOCATION & SITE PLAN
  • 37. Page  37 PART C : APPENDICES • Simplified format of the on-site survey checklist. • Must be in parallel & is accordance to Schedule of Building Condition & Defect Indication Plan. • Information shall comprise of (but not limited to) defect sheet number, photograph/ sketch section, level, location, element/component, scoring information (i.e. BARIS), defect description, possible causes & any necessary information. • Sample is shown in Appendix E. • Must be in parallel & accordance to Schedule of Building Condition & Defect Sheet. • All defects must be shown in this plan/elevation, according to their coding system. • Only the coding is shown. • Surveyor is free to include any photographs that might be useful in reading this plan, provided that it is placed in a neat & tidy manner. • Sample is shown in Appendix C. DEFECT INDICATION PLAN DEFECT SHEET
  • 40. Page  40 PART C : APPENDICES • An extraction from the tender/contract document of the building. • Record the specification of main building elements & any specific construction or services that are being installed to the building. • List & contact of all consultants, main contractor & any other stakeholders that are listed in the tender/contract document shall be made available. • Building inspection work might require a specific report (i.e. mechanical equipment testing, soil stabilization survey, condition monitoring & other services provided by specialist and/or construction professionals). • Surveyor should procure & coordinate such special report as part of the main report. • All special report attached must be prepared & certified in accordance with prevailing professional standards & ethics, in which the special report must adhere. PREVIOUS REPORT (IF ANY FROM OTHER) BUILDING SPECIFICATION (IF ANY)
  • 41. Page  41 How “defect” benefit us… UKM:Che-Ani 2013 It wasn’t hit by the massive earthquake. In true fashion of the Ripley Legacy, it was built to reflect the odd 1812 earthquake that measured 8.0 on the rick. The building has now become one of the most photographed in the world.
  • 42. Page  42 SUMMARY UKM:Che-Ani 2013  Start up: building defects identification – more than an “album”  Inspection: building defect diagnostic – defects are here & there: so what? You might need a tool  Reporting: standard and certified – qualify to stand in court  For Building Surveyors: Follow CPBS101 “We do not want a structural survey. If you can just have a quick look at the house to make sure that it is structurally sound, that will be fine” (Extract from client’s letter of instruction)
  • 43. Page  43 Thank you very much adiirfan@gmail.com - reflection -