SlideShare a Scribd company logo
1 of 128
BUSN7024 Project Management Principles
Semester 2, 2010 – Major Assignment
Project Management Plan
Algae Nursery System
Azim Khan U4009419
Emma Shaw U4924015
Osama Nasir U 4786695
Ruoying Liang U4638781
Stephanie Mutiara U4820179
Word Count: 21,310
Due Date: Friday, 22 October 2010
E-copy: via email to walter.fernandez@anu.edu.au
Paper copy: assignment box, ABIS School Office
File Name: project-management-plan11514.doc
Writing Documentation That Works Project Communication Management
Team Number: 7
By signing on Table 1 each member acknowledges his or her agreement with the
stated contribution to the overall assignment made by each team member.
Name Student No Contribution Signature
Azim Khan U4009419 A
Emma Shaw U4924015 A
Osama Nasir U4786695 A
Ruoying Liang U4638781 A
Stephanie Mutiara U4820179 A
Table 1: Membership and Individual Contribution.
Writing Documentation That Works Project Communication Management
Use the following convention to state each member contribution to the total effort
• A = very good contribution, the team member went above the expected
participation level.
• B = good contribution, the member participated as expected and was diligent
in performing the assigned tasks.
• C = less than satisfactory contribution, the member participation and
contribution was less than the average for the team.
• D = the member had minimal participation on the team effort, shown lack of
commitment to the team and significantly increased other members’
workload.
• E = the team member did not contribute at all to the team.
The team shall discuss and agree on the contribution level for each team member.
Your signature on Table 1 indicates your agreement with the assessment of
contribution. A lack of signature will indicate dissatisfaction with the attribution.
Please note, if half or less than half of the team sign the contribution assessment, a
penalty of 5% will apply to the assignment’s mark.
To encourage the teams to strive to perform as a team, penalties will be assigned to
students that perform below the minimum expected level (see Table 2).
Individual contribution to the team’s effort. Penalty to be applied to the assignment’s
mark for the particular student
A 0%
B. 0%
C 15%
D 50%
E 100%
Table 2: Human Resources Mismanagement Penalties.
This page is confidential and will NOT be seen by the class. The lecturer will
delete this page before releasing the document for class access on the web site.
Writing Documentation That Works Project Communication Management
Acknowledgement
Walter Fernandez is grateful to the author of this
template, David Tuffley, who generously allowed him to
modify the template and to use it at ANU.
Plagiarism
✍ Plagiarism will not be tolerated. It is the responsibility of
the team to ensure that proper citation and quotation
conventions are followed. Failure to observe this rule will
result in a zero mark for the entire assignment, regardless
of the magnitude of the infringement. Further action(s)
might be considered on a case-by-case basis.
i of of v
Writing Documentation That Works Project Communication Management
Contents
Contents..................................................................................................ii
1. Executive Summary............................................................................1
2. Project Introduction...........................................................................2
3. Project Integration Management.......................................................3
3.1. Project Plan Development.............................................................3
3.2. Project Plan Execution..................................................................4
3.2.1. Project Initiation......................................................................4
3.2.2. Project Direction.....................................................................4
3.2.3. Project Planning, Monitoring and Controlling Cycle..............4
3.2.4. Project Closing.......................................................................4
3.3. Integrated Change Control...........................................................5
4. Project Scope Management...............................................................6
4.1. Initiation..........................................................................................6
4.1.1. Product Description................................................................6
4.1.2. Strategic Plan.........................................................................7
4.1.3. Project Selection Criteria .......................................................7
4.2. Scope Planning.............................................................................8
4.2.1. Product Description................................................................8
4.2.2. Project Charter........................................................................8
4.3. Scope Definition.............................................................................9
4.3.1. Scope Statement....................................................................9
4.3.2. Work Breakdown Structure (WBS)......................................10
4.4. Scope Verification........................................................................10
4.4.1. Critical Success Factors.......................................................10
4.4.2. Evaluation Measures............................................................10
4.5. Scope Change Control................................................................11
4.5.1. Scope Changes....................................................................11
4.5.2. Corrective Action..................................................................11
4.5.3. Documentation.....................................................................12
5. Project Time Management................................................................13
5.1. Activity Definition.........................................................................13
5.2. Activity Sequencing.....................................................................13
5.3. Activity Duration Estimating.........................................................14
5.3.1. Basis of Estimates................................................................14
5.4. Schedule Development................................................................14
5.4.1. Project Schedule..................................................................14
ii of of v
Writing Documentation That Works Project Communication Management
5.4.2. Schedule Management Plan................................................14
5.4.3. Resource Requirement Update............................................15
5.4.4. Constraints and Assumptions...............................................15
5.5. Schedule Control.........................................................................15
5.5.1. Schedule Updates ...............................................................15
5.5.2. Corrective Actions................................................................16
6. Project Cost Management................................................................17
6.1. Resource Planning......................................................................17
6.1.1. Resource Requirement........................................................18
6.2. Cost Estimating...........................................................................20
6.3. Cost Budgeting............................................................................26
6.4. Cost Monitoring, Controlling and Reporting................................26
6.5. Other considerations...................................................................29
7. Project Quality Management............................................................30
7.1. Scope...........................................................................................30
7.2. Quality Objective.........................................................................31
7.3. Quality Control.............................................................................31
7.4. Organisational Structure and Responsibilities............................33
Quality Management Process............................................................35
7.4.1. Quality Planning...................................................................35
7.4.2. Quality Assurance................................................................40
7.4.3. Quality Control......................................................................41
7.5. Other Considerations...................................................................43
7.5.1. Quality Cost Monitoring and Reporting................................43
7.5.2. Leadership............................................................................44
7.5.3. Organisational Influence, Workplace Factors and Quality..44
7.5.4. Expectations and Cultural Differences.................................44
8. Project Human Resource Management..........................................45
8.1. Human Resource Planning..........................................................45
This human resource plan is created to identify and document
project roles, responsibilities, and reporting relationships involved
in the project. The Organizational Chart, Roles and
Responsibilities Assignments, RACI Chart, Staffing management
plan in this plan are used to ensure project success.....................45
8.1.1. Organizational Chart............................................................45
8.1.2. Roles and Responsibilities Assignment...............................46
8.1.3. RACI Chart...........................................................................48
8.1.4. Staffing Management Plans and Resource Histogram........49
8.1.4.1. Resource Histogram.....................................................50
8.1.4.2. Staffing Management Plan............................................51
8.2. Staff Acquisition...........................................................................51
This section sets forth the acquisition strategy, defines the efforts
required to implement it to ensure coordination of the project
iii of of v
Writing Documentation That Works Project Communication Management
manager and the human resource department to get the right
people to fulfil the project’s needs..................................................51
8.2.1. Resource Assignment..........................................................51
8.2.1.1. Staff Pooling Description..............................................52
8.2.1.2. Recruitment Practices...................................................53
8.2.1.3. Project Staff Assigned...................................................54
8.2.1.4. Project Team Directory.................................................55
8.3. Team Development......................................................................55
The main goal of this team development plan is to help people
work together more effectively to improve project performance and
achieve the project goals................................................................55
8.3.1. Training.................................................................................55
8.3.2. Team Building Activities.......................................................55
8.3.3. Input to Performance Appraisals..........................................55
8.3.3.1. Employee Self-Evaluation Assessment........................56
Employee Information....................................................................56
Goals..............................................................................................56
Risks and Expectations.................................................................56
Comments......................................................................................56
8.3.3.2. Employee Performance Review....................................57
8.3.4. Performance Improvements.................................................57
8.3.4.1. Improvement in Individual Skills...................................58
8.3.4.2. Improvement in Team Behaviours................................59
8.4. Team Management......................................................................59
Team management is essential in Human Resource Management
Plan. The Project Manager is required to do the followings to
motivate and manage his/her team members in case changes are
requested to the project..................................................................59
9. Project Communication Management.............................................60
9.1. Communications Planning...........................................................60
9.2. Information Distribution...............................................................61
9.2.1. Introductions to New Stakeholders and Negotiation............62
9.2.2. Meetings, Presentation and Reports....................................65
9.2.3. File Management..................................................................68
9.3. Performance Reporting................................................................71
9.3.1. Communications Hierarchy..................................................74
9.3.1.1. Top Down Communication............................................75
9.3.1.2. Bottom Up Communication...........................................76
9.3.1.3. Middle Out Communication...........................................77
9.4. Administrative Closure.................................................................79
9.5. Other techniques for information and communications
management.......................................................................................81
10. Project Risk Management..............................................................82
10.1. Risk Management Planning......................................................83
10.1.1. Organisational Risk Management Policies........................83
iv of of v
Writing Documentation That Works Project Communication Management
10.1.2. Risk Planning Meetings and Analysis................................84
10.1.3. Risk Management Plan......................................................85
10.1.4. Methodology.......................................................................86
10.1.5. Roles and Responsibilities.................................................86
10.1.6. Risk Categories..................................................................88
10.1.7. Project Risks.......................................................................88
10.2. Risk Identification ....................................................................92
10.2.1. Tools and Techniques........................................................92
10.2.2. Risk Register......................................................................94
10.3. Qualitative Risk Analysis..........................................................94
10.4. Quantitative Risk Analysis........................................................95
10.5. Risk Monitoring and Control.....................................................96
10.5.1. Monitoring...........................................................................96
10.5.2. Controlling..........................................................................96
10.5.3. Reporting............................................................................97
10.6. Risk Response Planning..........................................................97
10.6.1. Negative Risks....................................................................98
10.6.2. Positive Risks.....................................................................98
11. Project Procurement Management..............................................100
11.1. Procurement Planning............................................................100
11.2. Solicitation Planning ..............................................................101
11.3. Solicitation..............................................................................102
11.4. Source Selection.....................................................................103
11.5. Contract Administration..........................................................104
11.6. Contract Closeout...................................................................105
12. Conclusion.....................................................................................106
13. Appendix A - Project Gantt Chart................................................107
14. Appendix B - Table 6.3. Project Cost Baseline..........................108
15. Appendix C - Monthly Project Financial Performance Report
Template...............................................................................................109
16. Appendix D - Year to Date Project Financial Performance Report
...............................................................................................................110
17. Appendix E - Labour Cost Analysis Report...............................111
18. Appendix F – WBS........................................................................112
19. Appendix G – WBS Dictionary.....................................................113
20. References.....................................................................................117
v of of v
Writing Documentation That Works Project Communication Management
vi of of v
Writing Documentation That Works Project Communication Management
1. Executive Summary
The Nursery System Project will automate the early
cultivation of micro-algae. Automation of this process is
needed in order to prepare commercial quantities of
micro-algae which can in turn produce commercial
quantities of bio-fuel. The Nursery System will monitor
and control the growth of micro-algae from the laboratory
to the large tanks in which the micro-algae is grown.
This project will be considered successful based on
stakeholder acceptance of the project, with all changes
noted and documented and stakeholder acceptance of
these changes, as well as a working nursery system that
endures an allotted amount of time without technical
failures.
This project management plan details each phase of the
project the project manager must complete in order to
deliver a successful product. This includes project cost,
time and scope management, project quality
management, communications, risk, procurement and
human resources management, and overall project
integration management procedures and methods for the
successful project manager.
The project will cost $$$ and will take 271 days to
complete. The project has been planned to produce a
product of high quality, ensuring the commercial viability
of the Nursery System. The project will be complete when
key stakeholders from the ANU BioSolar Program are
satisfied that the Nursery System meets their
requirements.
The major risks for this project include:
Page 1 of 117
Writing Documentation That Works Project Communication Management
2. Project Introduction
The Australian National University has developed bio-
technology which allows crude oil to be sourced from
micro-algae. The development of this technology allows
for a renewable source of energy. In a world of finite non-
renewable energies, the uses for this renewable source
of energy are many and varied.
However, the micro-algae needs carefully grown and
monitored. The environment in which it is grown must be
carefully regulated for light, pH, temperature and water to
ensure that the algae do not die. Current processes for
encouraging the growth of algae involve transferring the
algae by hand from a series of smaller ponds into a
series of larger ponds, to ensure that the algae does not
die from overexposure to water.
The Nursery System project will automate this process.
By automating the process, the project will not only
reduce the time and effort required in growing algae into
commercial quantities for oil production, but create an
exportable system in which any business can use the
nursery system to develop its own algae for bio-fuel
production.
The nursery system project includes the development of a
user manual, which will enhance the marketability of the
system, and also ensure that the technology can be
widely used.
By creating the nursery system, the project team will be
contributing to the transfer from reliance on fossil fuels to
a more environmentally friendly use of renewable bio-
fuels.
Page 2 of 117
Writing Documentation That Works Project Communication Management
3. Project Integration Management
Project integration management is key to ensuring the
overall success of the project. It involves coordinating all
of the other project management areas throughout the
project’s life cycle.
3.1. Project Plan Development
The Project Plan has been created following the nine key
project management principles – cost, time, scope,
quality, communications, risk, procurement, human
resources and project integration – so that project
management plan provides a comprehensive overview.
This project management plan provides consistency
across all nine areas to ensure that all aspects of the
project have been planned for.
Please, refer to the table of contents for a full list of
all the plans and documents that have been designed
for this project.
Page 3 of 117
Writing Documentation That Works Project Communication Management
3.2. Project Plan Execution
3.2.1. Project Initiation
The project will be initiated at the instigation of the ANU
BioSolar Program. The project will be selected by key
stakeholders from the ANU BioSolar Program, who will
also consider the development of the business case,
determine scope, time and cost constraints, identify the
project sponsor, and select a project manager.
3.2.2. Project Direction
The project will be directed by the project manager, under
whose authority all decisions will be made, in conjunction
with the Change Control Committee. The project
manager’s decision will be final. The project manager
alone can endorse and initiate each of the work activities
under the Work Breakdown Structure.
3.2.3. Project Planning, Monitoring and Controlling
Cycle
The project planning, monitoring and controlling Cycle
will be performed through constant communication, both
oral and written. Formally, monitoring and controlling will
be managed through written documents which include the
weekly progress report, exception reports for
management on issues of particular interest that arise
during the project, and the final lessons learned report.
The planning, monitoring and controlling cycle will
constitute a ‘feedback loop’ in which any deviations from
the project schedule, budget or scope are fed back into
the planning and executing phases so that any changes
are accounted for and absorbed, ensuring that the project
will meet its deliverables.
Documenting ensures that all project team members and
management have a full record of the execution phase of
the project.
3.2.4. Project Closing
The closing phase of the project includes formal acceptance of
the nursery system, administrative activities associated with the
Page 4 of 117
Writing Documentation That Works Project Communication Management
end of the project, and the preparation of reports for
stakeholders and the wider community.
3.3. Integrated Change Control
Integrated change control will be performed in this
project. Any change requests will be considered by a
Change Control Committee, consisting of the project
manager, project sponsor, and key stakeholders such as
the head of the ANU BioSolar program. Any change will
be considered in the light of its impact on project
schedule, cost, quality and overall potential improvement
of the Nursery System. All rejected and approved
changes, and the reasons for rejection or approval, will
be documented in a Change Management document,
which, together with the original scope statement, will
form the project scope baseline. For more detail about
integrated change control, please see section 4.5.
Page 5 of 117
Writing Documentation That Works Project Communication Management
4. Project Scope Management
The scope of this project is described below. It has been
compartmentalized into the following areas: initiation;
planning; definition; verification and change control.
4.1. Initiation
The project has been authorized by Dr. Walter Fernandez
as a part of the bio duel solar energy program. The
reason for its authorization is the ultimate need of an
automated system for the early cultivation of algae before
pouring it to the large ponds. The business need that this
project has been developed is to automate the process of
early cultivation algae in the nursery considering all of the
factors that affect the cultivation. This is important to the
industry because it will minimize the human effort. In its
early stages, micro-algae need to be carefully cultivated
to ensure it does not die. The micro-algae are sensitive to
fluctuations in water quantity, temperature, light, pH and
nutrients. The survival of the micro-algae in its early
stages is vital to ensuring commercial production of the
micro-algae later.
This is the plan for the initial planning phase of the
project, it is anticipated that once the project enters
execution phase a new or modified plan will be
established updating the various changing criterion.
The main purpose of the project is to automate the
process of micro algae early cultivation that helps in the
production of bio fuel.
4.1.1. Product Description
The product that will be produced at the end of this
project will be a nursery system that can be supplied to
any where required. The nursery system will consider all
the important factors that affect the cultivation of algae
and its quality i.e., temperature, pH and nutrients etc. The
nursery system will consist of number of tanks with
different sizes. Since, algae grow initially in smaller tanks
and then need a large area to cultivate; nursery system
will monitor and control the flow of algae in these tanks
with considering the factors affecting it.
Page 6 of 117
Writing Documentation That Works Project Communication Management
4.1.2. Strategic Plan
This project is congruent with the strategic plan and long-
term objectives of the organisation. This is reflected
particularly strongly by the will to enter the bio fuel
production markets.
4.1.3. Project Selection Criteria
This project has been selected because there was a
severe need of an automated system to control the flow
of algae in the early cultivation of algae. This project is
also an integral part of the overall bio fuel solar energy
program to assist the production of bio fuel.
The product of this project is a nursery system that can
be transferred to anywhere it is required and control the
early cultivation of algae.
Page 7 of 117
Writing Documentation That Works Project Communication Management
4.2. Scope Planning
4.2.1. Product Description
For a description of the product of this plan, please refer
to topic 4.1.1.
4.2.2. Project Charter
• The Business Need
The business need of the system is to minimize
the amount of human effort in the early cultivation
of algae. This is important to the business
because large number of human efforts require
large amount of money. With the automated
system human effort will be decreased and this
system will be one time investment.
• Product Description
The product that will be produced at the end of this
project will be a nursery system that can be
supplied to anywhere required. The nursery
system will consider all the important factors that
affect the cultivation of algae and its quality i.e.,
temperature, pH and nutrients etc. The nursery
system will consist of number of tanks with
different sizes. Since, algae grow initially in
smaller tanks and then need a large area to
cultivate; nursery system will monitor and control
the flow of algae in these tanks with considering
the factors affecting it.
• Product Manager
The project manager for this project is to be Mr.
XYZ. XYZ will have the full authority over the
budget and resources allocated to this project. No
further seeking of resources will be accepted
unless it is presented by XYZ.
• Constraints
Page 8 of 117
Writing Documentation That Works Project Communication Management
• Budgets and time
• Availability of Human Resources
• Assumptions
It is assumed that:
• There will be constant easy access to
the Program Director;
• Bio fuel will not be superseded by
another type of technology before
production begins;
• No member of the project team will
leave the team before the end of the
project.
4.3. Scope Definition
4.3.1. Scope Statement
The scope of the project is to develop a project
management plan for nursery system project. The
Nursery System Project Management Plan will provide a
project plan for the development of a Nursery System
which can be exported anywhere around Australia. The
business need of the system is to minimize the amount of
human effort in the early cultivation of algae.
Page 9 of 117
Writing Documentation That Works Project Communication Management
4.3.2. Work Breakdown Structure (WBS)
Please, refer to Appendix F – WBS.
4.4. Scope Verification
This section seeks to identify the critical success factors
and evaluation of those factors upon delivery of the
strategic plan to the stakeholders.
4.4.1. Critical Success Factors
There are number of critical success factors that will
decide whether the project has been successfully
completed. They are described as follows:
1. The nursery system is completed meeting all the
required specifications;
2. The project is completed in a time as was planned;
3. The nursery system is in a working condition with
ease;
4. It is easy to train a person with all the functional &
technical specification of the system; and
5. The system meets all of the quality standards as
were planned.
4.4.2. Evaluation Measures
Stakeholders can check the quality by deploying the
prototype system on a small scale. The output of the
system can be analyzed. After testing the prototype
system, the system will be deployed on the production
site where the output can be further analyzed.
After testing this, stakeholders can decide whether
system is meeting all of the requirements or is it missing
few of the features as planned.
Page 10 of 117
Writing Documentation That Works Project Communication Management
4.5. Scope Change Control
This section defines how planning and management of
changes to the scope, via change request, is carried out.
This section also details how any scope management
plans; corrective actions and lessons learnt
documentation should be completed.
4.5.1. Scope Changes
Any change requests will be considered by a Change
Control Committee, consisting of the project manager,
project sponsor, and key stakeholders such as the head
of the ANU BioSolar program. Any change will be
considered in the light of its impact on project schedule,
cost, quality and overall potential improvement of the
Nursery System. All rejected and approved changes, and
the reasons for rejection or approval, will be documented
in a Change Management document, which, together with
the original scope statement, will form the project scope
baseline.
For any change requests that come during the project, a
proper path of communication will be required to
communicate the change to the respective authority. The
request must include the strong justification and grounds
for implementing the change. The request should be
submitted to and approved by the project manage. If the
project manager feels that this change request is of any
worth, then he may approve it and forward to the program
manager. Both project and program managers will
reserve the right to contest the change based on
practicalities and delays caused, costs incurred and
quality effects. Once approved, the requested changes
will be integrated in to the project plan, which will be
disseminated to each stakeholder, including the effects
on costs, timeliness and quality. The base line should
remain the same and the changes should be mentioned
separately.
4.5.2. Corrective Action
Where a scope change request has been submitted and
approved, the following corrective actions shall apply.
Page 11 of 117
Writing Documentation That Works Project Communication Management
1. It will be integrated into the project plan in a
separate section;
2. New costs, timeframes and quality effects will be
detailed;
3. All new tasks will be integrated into the WBS and
assigned;
4. All cost increases will be factored into phasing and
overall budgets; and
5. The scope verification adapted to suit new
deliverables.
If there is any change or delay in the timeline, which is
not caused by any scope change, it has to be reported to
the project manager. The program manager has to be
informed about this delay by project manager. If the delay
can be recovered through additional hours, the overtime
can be paid to the employees who will work on it.
In the event of a major delay, a corrective action report
(CAR) will be created giving options of how to proceed.
This will include the amount required to get back on time,
the quality drop that will be required to get back on time
or the time that will be lost. This will be disseminated to
the program manager and internal stakeholders.
4.5.3. Documentation
All changes, the efforts required to work on those
changes and the communication done for the change
requests are to be documented and approved by the
project manager. The documentation has to be shared on
Google Docs so that the whole project team has access
on it. (Refer to Project Communications Plan for further
description.)
Page 12 of 117
Writing Documentation That Works Project Communication Management
5. Project Time Management
This section describes all the strategies that have been
adopted to manage the time, which affects one of the
most important aspects of a project, i.e. Schedule. The
section will start from the activity definition, continue with
defining the duration of activities, the resources used in
the activities, schedule development and will end with
explaining how to manage control the time management
process in schedule control section.
5.1. Activity Definition
Please see below the activity list for this project. All
constraints and assumptions are listed in the project
charter, in the scope initiation section (4.1.1).
Please, refer to the Appendix A – Project Gantt chart,
Appendix F – WBS and Appendix G – WBS Dictionary.
5.2. Activity Sequencing
We have used Network diagram to show sequencing of
activities. Network diagram is a schematic display of the
logical relationships among, or sequencing of, project
activities.
Please, refer to the Appendix A – Project Gantt Chart.
Page 13 of 117
Writing Documentation That Works Project Communication Management
5.3. Activity Duration Estimating
The Work Breakdown Structure contains the times that
have been estimated, as shown below.
5.3.1. Basis of Estimates
This is a list of further assumptions that were taken
during development of the estimates.
• The number of human resources is assumed.
• Raw material can be supplied without any interruption.
• Feed of preliminary design and prototype will be
provided on time.
5.4. Schedule Development
This section details the start and finish dates and how to
manage the timelines for the project. The schedule
assumes that the standard hours of the project are 8
hours per day 5 days per week, excluding public
holidays.
5.4.1. Project Schedule
To view the project schedule, please refer to the Gantt
chart attached in Appendix A – Project Gantt Chart.
5.4.2. Schedule Management Plan
If there is a schedule change or a delay in any specific
task is identified before the activity becomes late, the
project manager is to reallocate the necessary resources
according to the changes that have occurred. The Project
Manager should investigate why there was a delay going
to happen. If it’s because of the resources that were
assigned to the activities, necessary action should be
taken against them.
Page 14 of 117
Writing Documentation That Works Project Communication Management
5.4.3. Resource Requirement Update
In the event of corrective actions being approved by the
Project Manager, where there are cost or resource
implications, these are to be tracked and included in the
budget. This will be done by formal notification to the
project accountant via email and followed up in writing. If
there is an issue with the number of required resources,
Project Manager should try to fill the space as soon as
possible.
5.4.4. Constraints and Assumptions
The constraints on this section include standard hours to
be worked, because it limits the ability of workers to
complete tasks by their allotted time.
Assumptions
• The number of required employees will always
be available on time throughout the project.
• The attendance of the employees will remain
constant.
• No employee will resign during the project.
• There will be no significant and unrecoverable
‘lags’ in the proposed schedule.
5.5. Schedule Control
5.5.1. Schedule Updates
A schedule update is considered to be anything that
changes the start or finish time of another work activity
down to the level three tasks. These include any level
four tasks or below that affect higher-level tasks. To
assist in schedule management once a task is complete,
the WBS will be updated via the online software. In
addition, the person in control of completing the work
activity is to advise the project manager and anyone
whose task it will affect. The updated WBS will be saved
as a new name with updated date as well. In that way, it
would be easy to keep track of the changes and updates.
Page 15 of 117
Writing Documentation That Works Project Communication Management
5.5.2. Corrective Actions
In the event of a completion time that will affect another
task either by allowing it to start earlier or forcing it later,
a formal schedule update request must be submitted to
the project manager with a corrective actions proposal
including an estimated cost of any such proposal. If
accepted by the project manager – with no corrective
actions available – they will notify the project sponsor,
program manager and any relevant internal and external
stakeholders.
In addition, the project manager will inform the other team
members affected about the change to schedule and
seek any possible corrective actions from that work group
to get the project back on time.
Page 16 of 117
Writing Documentation That Works Project Communication Management
6. Project Cost Management
Cost is one of the Triple Constrains of a project. To
create a successful project, project manager must have a
comprehensive consideration of the cost to achieve the
project goals, any cost overestimate and underestimate
may ruin the project during the project life cycle. This cost
management plan serves to effectively and efficiently
allocate resources for development of a strategic plan for
developing a prototype of a nursery system with the
capacity to cultivate 450 litres of algae for the Bio-fuel
program.
The range of the total cost of the project would be +/-10%
of the estimate cost ($306360), which is between
$275724 and $336996.
As a best practice guide PMBOK recommends the Project
Cost Management processes include the following:
• Resource Planning
• Cost Estimating
• Cost Budgeting
• Cost Monitoring, Controlling and reporting
6.1. Resource Planning
Core resources determination is explicitly based on the
Work Breakdown Structure (WBS) and the project scope
statement presented in the project scope management
section. Other resources, such as the office supplies,
transportation and utilities etc, which are not directly
related to the nursery system but indirectly related to the
performance of the project, are included in the General
and Administrative charges (G&A).
Page 17 of 117
Writing Documentation That Works Project Communication Management
6.1.1. Resource Requirement
The resource requirement table below presents the
summary of core resources in quantity, type, and quality
needed to efficiently develop the nursery system. The
requirements of the job positions are stated in this table,
while the descriptions of the job positions are presented
in Human Resource Management Plan in details. The
allocation and the cost of the resources at the WBS
levels are presented in the cost estimate section.
Table 6.1.1. Resource Requirement Table
Resource Name Hrs
Resource
Description/Requirements
Labour    
Project Manager 512
1. More than five years of
Project management
experience as well as be PMI
certified.
2. Strong planning, motivation
and communication skills.
Senior
Engineer/Analyst
1496
1. Master degree in biology
science and/or engineering.
2. At least five years recent
specialized experience.
Junior
Engineer/Analyst
2
888
1. Bachelor degree in biology
science and/or engineering.
2. At least two years recent
specialized experience.
Junior
Engineer/Analyst
1
584
Accountant 320
1. At least three years
accounting experience, the
majority of which should have
been in a project related
environment.
2. Computer literacy with
experience in MSWord, excel.
3. Must be able to work
independently and meet
deadlines in a team
environment.
Technician 1 440 1. Relevant tertiary
qualifications in biologyTechnician 2 440
Page 18 of 117
Writing Documentation That Works Project Communication Management
science or/and engineering
2. At least two years
experience in biology-related
Technician 3 360
Technician 4 360
Procurement
Specialist
1640
1. A purchasing certification is
preferred.
2. A minimum of two years
working in a general buying
environment.
3. Considerable knowledge of
purchasing methods and
procedures and of the
techniques of specification
writing.
ANU expert 20
Provide suggestions and solve
the technical problems at
technical level.
Hardware    
Desktop PC 10
Each PC will be assigned to
each employee
PC
Model: HP Pavilion P6325A I3-
540 Pc or at the equivalent
level.
Printers 5
Model: Samsung CLP315
Colour Laser Printer or at the
equivalent level.
Coulter Counter 1
Estimate the culture density of
the algae.
Fluorescent Tubes 3
Artificial illumination to
optimize growth.
Immersion Heater 4
2400 watt, 240 volt immersion
heater to control the
temperature for cultivating the
algae at different stage.
Pines and Hoses 5
Transfer the algae from small
tanks to large tanks.
Air Filter 4
Filters for air supply to prevent
contamination.
Tanks 4
Used to contain the growing
algae, the sizes of the tanks
are 250ml, 250ml to 4l, 4l to
20l, 50l, respectively.
Materials    
Fertilizers Nutrient
Media
500
Fertilizer nutrients such as
nitrogen, phosphorus,
potassium and carbon source
are needed to cultivate algae
in the nursery system.
Page 19 of 117
Writing Documentation That Works Project Communication Management
Glassware 5
Contain the sample of the
algae cultures.
6.2. Cost Estimating
Commonly used tools and techniques to assist in creating
a cost estimate include analogous cost estimating,
bottom-up estimating, parametric modelling, resource
cost rates, project management software, vendor bid
analysis and reserve analysis (Kathy Schwalbe, 2007).In
this project, cost estimations are created using bottom-up
estimates and based on the market prices for goods and
services in the Australian economy and the Australian
most popular job site SEEK.COM pay check survey.
Every individual work items or activities in the WBS are
allocated a cost and summed to get the higher level total.
When creating cost estimations and allocating costs to
resources requirements, significant consideration is given
to uncertainties such as major scope changes and
extraordinary events. A 5% contingency reserve
(estimated by predetermined guidelines and the risk level
of the nursery system) is created to allow for future
situations that may be partially planned for, and a 5%
management reserves is set to allow for future situation
that are unpredictable. Hence the budget is therefore
flexible to cater for any uncertainties and the budget itself
forms the cost control mechanism (Meredith J. and
Mantel S, Jr. 2006).
Table 6.2. Project Cost Estimates
Notes:
1. General & Administrative charges (G&A) are
calculated as 10% of the total cost of the core resources.
2. The project manager is assigned to complete several
specific WBS activities in the project while he/she is
managing the whole project, and all the labour costs of
the project manager are calculated in the project
management level.
Page 20 of 117
Writing Documentation That Works Project Communication Management
WBS
activities
Resources
Name
Unit/hr
Cos
t/uni
t/hr
Subtotal
s
WBS
level 1
totals
% of the
total
Project
management
        54681 17.85%
 
Project Manager 512 55 25960    
project
Accountant
320 40 12800    
Desktop PC 10 800 8000    
Printers 5 150 750    
G&A charges     4971    
Initiating         3344 1.09%
Identify key
stakeholders Project Manager
8 NA 0    
Hold project
kick-off
meeting
Project Manager 8 NA 0    
Senior
Engineer/Analyst
8 40 320    
Junior
Engineer/Analyst
1
8 30 240    
Junior
Engineer/Analyst
2
8 30 240    
Review
Scope
Project Manager 56 NA 0    
Senior
Engineer/Analyst
56 40 2240    
  G&A charges     304    
Planning         90640 29.59%
Hold team
planning
meeting
Senior
Engineer/Analyst
40 40 1600    
Prepare
team
contract Project Manager 40 NA
0    
Gather
functional
requirements
Junior
Engineer/Analyst
1
120 30 3600    
Junior
Engineer/Analyst
2
120 30 3600    
Gather
technical
requirements
Junior
Engineer/Analyst
1
120 30 3600    
Junior
Engineer/Analyst
2
120 30 3600    
ANU experts 20 50 1000    
Verify
requirements
Senior
Engineer/Analyst
56 40 2240    
Review of
Sensors
Junior
Engineer/Analyst
40 30 1200    
Page 21 of 117
Writing Documentation That Works Project Communication Management
used
1
Junior
Engineer/Analyst
2
40 30 1200    
Review of
the system
logic
Junior
Engineer/Analyst
1
40 30 1200    
Junior
Engineer/Analyst
2
40 30 1200    
Review
communicati
ons
environment
Junior
Engineer/Analyst
1
40 30 1200    
Junior
Engineer/Analyst
2
40 30 1200    
Review
geographic
factors
Junior
Engineer/Analyst
1
56 30 1680    
Junior
Engineer/Analyst
2
56 30 1680    
Review of
baseline
Senior
Engineer/Analyst
40 40 1600    
Identify
sensors to
use
Junior
Engineer/Analyst
1
40 30 1200    
Junior
Engineer/Analyst
2
40 30 1200    
Identify new
system logic
Junior
Engineer/Analyst
2
40 30 1200    
Junior
Engineer/Analyst
1
40 30 1200    
Identify
communicati
ons
consideratio
ns
Junior
Engineer/Analyst
1 40
30 1200    
Junior
Engineer/Analyst
2 40
30 1200    
Identify
mitigation of
geographic
factors
Junior
Engineer/Analyst
1 40
30 1200    
Junior
Engineer/Analyst
2 40
30 1200    
Identify
target areas
for
improvement
Junior
Engineer/Analyst
1 40
30 1200    
Junior
Engineer/Analyst
2 40
30 1200    
Page 22 of 117
Writing Documentation That Works Project Communication Management
Define
system
requirements
Senior
Engineer/Analyst 160 40
6400    
Define target
performance
metrics
Senior
Engineer/Analyst 48 40
1920    
Hardware
vendors
Procurement
Specialist 40 30
1200    
Coulter Counter 1
200
00
20000    
Fluorescent
Tubes
3 20 60    
Immersion Heater 4 100 400    
Pines and Hoses 5 60 300    
Air Filter 4 100 400    
Tanks 4
100
0
4000    
Communicati
ons vendors
Procurement
Specialist
40 30 1200    
Design
partners
Procurement
Specialist
40 30 1200    
Implementati
on partners
Procurement
Specialist
64 30 1920    
  G&A charges     8240    
Executing         75922 24.78%
Draft
preliminary
design
documents
Senior
Engineer/Analyst 240 40
9600
Preliminary
hardware
design
Senior
Engineer/Analyst 80 40
3200    
Preliminary
communicati
ons design
Senior
Engineer/Analyst 80 40
3200    
Preliminary
support
environment
design
Senior
Engineer/Analyst 80 40
3200    
Review
preliminary
design
documents
Senior
Engineer/Analyst 40 40
1600    
Project Manager 40 NA
0    
Obtain
feedback/inp
ut on design
Project Manager 40 NA 0    
Senior
Engineer/Analyst 40 40
1600    
Review of
design
based on
feedback
Senior
Engineer/Analyst 40 40
1600    
Junior
Engineer/Analyst
1 40 30
1200    
Junior
Engineer/Analyst
40 30 1200    
Page 23 of 117
Writing Documentation That Works Project Communication Management
2
Develop
detailed
hardware
design Project Manager 40 NA
0    
Develop
detailed
support
environment
design Project Manager 40 N A
0    
Align
long/short
term design
with
business
goals
Project Manager 80 NA 0    
Senior
Engineer/Analyst 80 40
3200    
Procure
Materials
Procurement
Specialist 120 30
3600    
fertilizers nutrient
media(ml)
500 NA 1000    
glassware 5 20 100    
Construct
Prototype
Technician 1 96 40 3840    
Technician 2 96 40 3840    
Technician 3 96 40 3840    
Technician 4 96 40 3840    
Test
Prototype
Junior
Engineer/Analyst
2 80 30
2400    
Junior
Engineer/Analyst
1 80 30
2400    
Evaluate
Prototype
against
requirements
Senior
Engineer/Analyst 40 40
1600    
Make
adjustments
to prototype
as needed
Technician 1 40 40 1600    
Technician 2 40 40
1600    
Re-Test
prototype
Junior
Engineer/Analyst
1 40 30
1200    
Junior
Engineer/Analyst
2 40 30
1200    
Senior
Engineer/Analyst 40 40
1600    
Review
deployment
team tasks
and timeline
Senior
Engineer/Analyst 24 40
960    
Project Manager 24 NA
0    
Communicat
e impact to
Project Manager 24 NA 0    
Page 24 of 117
Writing Documentation That Works Project Communication Management
community
Test Nursery
System
Senior
Engineer/Analyst 24 40
960    
Junior
Engineer/Analyst
1 24 30
720    
Release to
production/o
perations
environment
Senior
Engineer/Analyst 24 40
960    
Obtain
feedback
Junior
Engineer/Analyst
1 24 30
720    
Prepare user
manual
Junior
Engineer/Analyst
1 24 30
720    
Junior
Engineer/Analyst
2 24 30
720    
  G&A charges     6902    
Monitoring
and
controlling
        42416 13.85%
Conduct
weekly
progress
meetings Project Manager 0 NA
0    
Document
problem -
tracking
procedures
Senior
Engineer/Analyst 16 40
640    
Manage
contracts
with
suppliers
Procurement
Specialist 1264 30
37920    
  G&A charges     3856    
Closing         11616 3.79%
Prepare final
project
report
Senior
Engineer/Analyst 40 40
1600    
Project Manager 40   0    
Document
lessons
learned
Junior
Engineer/Analyst
2 80 30
2400    
Junior
Engineer/Analyst
1 80 30
2400    
Senior
Engineer/Analyst 80 40
3200    
Distribute to
team
members
Senior
Engineer/Analyst 24 40
960    
  G&A charges     1056    
Page 25 of 117
Writing Documentation That Works Project Communication Management
Reserves         27620 9.06%
Management
reserves
   
13809.9
5
   
Contingency
reserves
     
13809.9
5
   
Total         306360 100.00%
6.3. Cost Budgeting
Project cost budgeting involves allocating the project cost
estimate to individual work items over time. The main
goal of the cost budgeting process is to produce a cost
baseline for measuring project performance and project
funding requirements. Based on the cost estimations, the
following project budget baseline is planned to fully
implement the project from initiation to completion.
The budget allocated in each month includes labour cost,
the cost of hardware and materials that are expected to
incur in that month. The office supplies, such as printers,
desktop PC are depreciated using straight-line method in
the whole project life at the project management level.
The costs of other equipments, such as coulter counter,
immersion heater, etc, which are directly related to the
development of the nursery system are depreciated into
the actual months of their corresponding WBS activities.
Please, refer to Appendix B - Table 6.3. Project Cost
Baseline.
6.4. Cost Monitoring, Controlling and Reporting
Deviations from the cost baseline should signify critical
cost performance signals of the project. Budget overrun
or underutilization should be importantly considered as a
major change to the budget (Project Management
Institute, 2000). Therefore, a well-disciplined cost
monitoring, controlling and reporting system is very
important.
Project Management Institute (2004) suggests, a Project
Manager, when planning for controlling project costs,
should take the following items into account:
Page 26 of 117
Writing Documentation That Works Project Communication Management
1. Influencing the factors that create changes to
the cost baseline.
2. Ensuring requested changes are agreed upon
3. Managing the actual changes when and as
they occur.
4. Assuring that potential cost overruns do not
exceed the authorised funding periodically and
in total for the project.
5. Monitoring cost performance to detect and
understand variances from the cost baseline.
6. Recording all appropriate changes accurately
against the cost baseline.
7. Preventing incorrect, inappropriate, or
unapproved changes from being included in
the reported cost or resource usage.
8. Informing appropriate stakeholders of
approved changes.
9. Acting to bring expected cost overruns within
acceptable limits.
In addition to the above, it is also recommended that a
Project Manager takes into account the following:
1. Thorough planning of the work to be performed
to complete the project
2. Good estimating of time, labour and costs
3. Clear communication of the scope of required
tasks
4. A disciplined budget and authorization of
expenditures.
Project accountant plays an important role in ensuring
that project costs are being routinely monitored,
appropriately controlled and reported in a timely manner.
Page 27 of 117
Writing Documentation That Works Project Communication Management
As such, the following tasks must be performed by the
project accountant in the cost control system:
1. Keeping track of project cost performance
throughout the project life and conduct budget
review in every month, planned milestone and
project phase.
• Refer to the following appendices for report
templates:
• Appendix C - Monthly Project Financial
Performance Report Template
• Appendix D - Life to Date Project
Financial Performance Report
• Appendix E - Labour Cost Analysis
Report
Template 1: monthly project
financial performance report and;
Template 2: Year to date project
financial performance report.
2. Detecting and investigate the cause of the
variance and make necessary
recommendations to the project manager.
3. Ensuring that all appropriate changes are
recorded accurately in the cost baseline under
the project manager’s approval.
Based on the project accountant’s recommendations, the
project manager should:
1. Schedule meetings and inform appropriate
stakeholders of the changes; ensure that changes to
the cost baseline are minimised, authorised and
agreed upon by all stakeholders.
2. Rectify the changes and manage actual changes with
the agreement of the stakeholders.
3. Distribute modified plans to the stakeholders and the
management team.
Page 28 of 117
Writing Documentation That Works Project Communication Management
6.5. Other considerations
The followings are other considerations the project manager and
the project accountant should take into account that may lead to
the budget out of the range.
1. Resources over-allocation or under-allocation will end up
with the delays of the deliverables and the increase of the
costs. (Please refer to Human Resource Section for details)
2. As the budget of the project is estimated based on the
market prices of the goods and services in Australia, the
actual acquisition costs of materials and equipments will
vary among vendors that might create the deviation from the
estimated costs
3. Contingency reserves will be underestimated in the budget
because of misestimating the level of the risks.
Page 29 of 117
Writing Documentation That Works Project Communication Management
7. Project Quality Management
The primary challenge of project management is to
achieve the project goals and objectives while adhering
to project constraints – usually scope, quality, time and
budget (Cline et al, 2010, Schwalbe 2007). Juran (1988)
suggests that, 90% of all problems in organisations are
systematic and beyond the positive influence of staff.
Unfortunately, this also includes issues related to quality
(McManus and Wood-Harper, 2007). One of the greatest
challenges faced by project managers is to get the
process right first time and this means initiating a
rigorous quality regime, which is both defined and
measureable (McManus and Wood-Harper, 2007).
The importance and purpose of Project Quality
Management is to ensure that the project will satisfy the
needs for which it was undertaken (Schwalbe, 2007).
Therefore, having a solid plan to address quality issues
in this project is very important and this will help the
project team to ensure stakeholders are satisfied with the
outputs of this project.
7.1. Scope
This document will cover:
• Quality Objectives
• Quality Policy
• Quality Organisational Structure and
Responsibilities
• Quality Management Process
• Other Considerations
Page 30 of 117
Writing Documentation That Works Project Communication Management
7.2. Quality Objective
1. The final product of this project must be of highest
standard, quality, and meets the approved
performance specifications and requirements of
the ANU’s BioSolar Program.
2. The final product must be flexible and compatible
to accommodate any changes and deviations in
the cost baseline, time baseline and performance
specifications.
7.3. Quality Control
In operations management research there are many
approaches or standard been recommended to address
quality issues in a project management environment. For
example, Total Quality Management (TQM) approach,
ISO 9000 standard on quality, Project Quality Activity
approach and Project Management Planning Quality
Model, Capability Maturity Model to name a few (Zwikael
and Globerson, 2004; Masters and Frazier, 2007;
McManus and Wood-Harper, 2007). Among these, TQM
and ISO 9000 standards are found to be the most
adopted quality management principles in project
management environment.
While both of these approaches are very similar it is
recommended that this project adopts ISO 9000
principles as a matter of policy in managing project
quality related issues. This project policy position is
consistent with the overall project management
framework principle adopted by the ANU (see
http://projects.anu.edu.au/management/index.php,
accessed on 15 September 2010). Table 7.3 outlines this
policy.
Page 31 of 117
Writing Documentation That Works Project Communication Management
Table 7.3. Quality Management Policy
Principles Descriptions
1. Customer
focus
Understanding current and future
customer needs; meet
requirement; strive to exceed
expectations; and link
organisation’s objectives to
customer needs
2. Leadership Leaders establish unity of purpose
and direction for the organisation.
They create the appropriate
internal environment.
3. Involvement
of People
Motivated, committed, and
involved people at all levels
accept ownership of problems,
evaluate their own performance,
and freely share information.
4. Process
approach
Activities and related resources
are managed as processes
resulting in predictable results and
improvement opportunities.
5. Systems
approach to
management
Integrate and align processes;
focus effort on key processes; and
understand interdependencies,
capabilities, and constraints
before starting projects
6. Continual
Improvement
Use a consistent organisation-
wide approach to continual
improvement to include training in
methods, goals to guide, and
measures to track.
7. Factual
approach to
decision
making
Ensure data and information are
accurate, reliable, and accessible;
make decisions and take action
based upon analysing facts; and
challenge opinions and decisions.
8. Mutually
beneficial
supplier
relationships
Identify and select key partners;
jointly develop and improve with
partners; and openly share
communication with them.
Source: The Australian National University (2008),
Course Notes of BUSN7024 – Project Management
Principles, Semester 2, 2010.
Page 32 of 117
Writing Documentation That Works Project Communication Management
7.4. Organisational Structure and
Responsibilities
The organisational structure to carry out the Quality
Management Plan is as follows:
Table 7.4. Quality Review and Audit Team
Quality
Review and
Audit Team
Job Responsibilities
Project
Manager
1. Quality monitoring and control
review and audit process and
arrange audit meetings.
2. Quality policies are
implemented throughout the
entire project.
Project
Accountant
1. Ensure that project is on
budget and cost associated
with quality control is
accounted for through critical
milestone audit points.
2. Conduct professional
audits and report any changes
in actual spend or available
funds that will affect project
quality
Senior Project
Officer
1. Ensure that quality is
maintained at all milestone
points
2. Ensure that all critical events
and activities are carefully
implemented
3. Audit for any deviations,
identify cause, and report for
corrective actions
Senior Project
Consultant
(Scientist from
ANU BioSolar
Program)
1. Review project performance
against the approved technical
performance specification.
2. Provide necessary technical
recommendation to the Project
Manager and Project Director
on quality improvements to
ensure the project satisfies its
Page 33 of 117
Writing Documentation That Works Project Communication Management
technical objectives.
Page 34 of 117
Writing Documentation That Works Project Communication Management
Quality Management Process
Project Management Body of Knowledge (PMBOK)
prescribes three main processes as being quality
management process. These are, planning quality,
performing quality assurance and performing quality
control (PMI, 2004). These are discussed below.
7.4.1. Quality Planning
Quality planning involves identifying which quality
standards are relevant to the project and determining how
to satisfy them (PMI, 2004). PMBOK also recommends
that quality planning should be performed in parallel with
the other project planning processes (PMI, 2004). As
mentioned above in Table 1, the ISO 9000 has been
adopted as a matter of policy for this project and this
table also provides guidance for the Project Manager as
to what needs to be performed during quality planning
stage to ensure that Quality Policy (ISO 9000) is adhered
to during this project.
Researchers in the project management suggests that, by
asking probing questions and challenging the
assumptions i.e., the validity of estimates and project
delivery methods, it is possible to steer a situation
towards an environment where either where either the
problem does not exist or the objectives can co-exist and
hence can be collectively achieved (Gill, 2008).
Following this approach the PM can empower each
project team member to raise any quality issues that may
adversely impact customer satisfaction KPIs. PM then
can raise those issues in the Quality Review and Audit
Team to resolve them and document the issue and
resolution in the Quality Management Plan. This could
significantly minimise any potential risk of poor customer
satisfaction from project deliverables.
Page 35 of 117
Writing Documentation That Works Project Communication Management
Project scope is an important consideration in planning
for project quality management. It is PM’s responsibility
to ensure that s/he takes project scope into account in
planning and executing project quality management.
Project quality planning also involves communicating the
correct actions for ensuring quality in a format that is
understandable and complete (Schwalbe, 2007). For
example, in order to satisfy the first principles of ISO
9000, the Project Manager should carefully document
and explain any key performance indicators (KPIs) that
may have been given by the customers to the entire
project team (including any third party resource provider).
This will ensure that customer needs are fully understood
by each member of the project team.
PMBOK suggests that a quality management plan may be
formal or informal, highly detailed or broadly framed,
based on the requirements of the project (PMI, 2004).
Due to the level of technical complexity that could be
involved in executing this project, it is recommended that
the quality management plan is prepared is a formal and
as detailed plan as practical to ensure the quality policy
can be adhered to through out the project.
In summary, organisational policies related to quality, the
particular project scope statement and product
descriptions, and related standards and regulations are
all important input to the quality planning process
(Schwalbe, 2007)
Table 7.5.1 summarises a range of checkpoints, at
various WBS levels, that the PM should ensure that the
recommendations provided in this quality management
plan is adhered to.
Table 7.5.1. Quality Management Plan
WBS
Number
Activities Recommendation on Quality Management
1.1 Project
Initiating
• Project manager must ensure that the project team has the
correct information on Project Scope and Project Budget and
an approved copy of this Project Management Plan before
Project Kick-Off meeting.
• In Project Kick-Off meeting, PM must go through the project
scope thoroughly and seek feedback from the respective
team members to ensure the project scope is clearly
Page 36 of 117
Writing Documentation That Works Project Communication Management
understood by team members.
1.2 Project
Planning
• Project manager must ensure that performance and process
audits are done at all milestone points throughout the
project.
1.2.3.3 Verify
Technical
and
Functional
Requirement
• At this point, Project Manager must ensure that the technical
and functional requirements have been reviewed and
endorsed by Senior Scientific Consultant.
• Report any process and performance deviations to relevant
stakeholders and take immediate corrective actions
• Obtain sign-off from the Quality Management Committee to
ensure project objectives have been catered for in identifying
the technical and functional project requirements.
1.2.4 Analysis • Appropriate data analysis methods (qualitative or
quantitative) must be used to analyse data through out the
project
• Data analysis process must be clearly defined and free of
personal influences and subjective information
• Analysed data must be accurately tabulated and presented
for documentation
• Adequate funding must be allocated for quality data analysis
• Data analysis must be conducted within the planned budget
• Any deviation/variance to the cost baseline must be notified
and investigated
• Corrective actions must be immediately taken to rectify
• Sufficient time must be allocated for quality data analysis
• Data analysis must be conducted within the planned
schedule/time
• Any delays/ over-run to the scheduled time must be notified
and investigated
1.2.4.2 Review of
baseline
• Obtain sign-off from the Quality Management Committee to
ensure all requirements in Project Scope are achievable
within the Project Baseline.
• Report any process and performance deviations to relevant
stakeholders and take immediate corrective actions
• Project Accountant must conduct financial and cost audits at
all milestone points throughout the project life
• Report any variances from the cost baseline to project
manager to take necessary actions
• Time/schedule audits must be conducted to ensure that
Page 37 of 117
Writing Documentation That Works Project Communication Management
lower level activities are implemented on time to achieve
higher level/ milestone activities
• Causes of delays or early execution must be investigated
and necessary actions immediately taken to ensure quality
1.2.4.6 Review
Current
Market
Solution
Vendors
Project Manager should utilize the Project Procurement Plan
to ensure quality process is maintained during procurement
process. Research on current suppliers and type, kind,
quantity, and quality of raw materials is a crucial milestone
activity of the project. The research method, type, time
allocation, sources of information, and qualifications and
skills of research officers are critical for quality research
outcome. This high level activity is the core activity of the
project; hence, adequate funding and time must be allocated
to achieve high performance and quality. Following factors
must be addressed and performed during procurement
process:
• Research problem/area must be properly stated and
specifically defined
• Research officers must be qualified and have necessary
research skills and knowledge
• Research must be conducted within the planned budget
• Research must be conducted within the planned
schedule/time
• Appropriate research design, methodology and type must by
employed
• Genuine and reliable sources of data are used for literature
review
• Adequate funding must be allocated for quality research
outcome
• Any deviation/variance to the cost baseline must be notified
and investigated
• Corrective actions must be immediately taken to rectify
• Sufficient time must be allocated for quality research
outcome
• Any delays/ over-run to the scheduled time must be notified
and investigated
• Corrective actions must be immediately taken to rectify
•
1.3 Executing • Implementation should be according to this Project
Management plan
Page 38 of 117
Writing Documentation That Works Project Communication Management
• Implementation process should be according to planned
quality procedures and standards
• Performance audits/checks must be conducted through
meetings at every key milestones or deliverables
• Any deviations must be accounted for and sources identified
for immediate corrective actions
• Adequate funding must be allocated for strategic plan
implementation
• Implementation process must be executed within the
planned budget/costing
• Any deviation/variance to the cost baseline must be notified
and causes/sources investigated
• Corrective actions must be taken immediately rectification
• Budget provisions must be made to cater for any
contingencies during the course of strategy implementation
• Sufficient time must be allocated for strategic plan
implementation
• Implementation process must be executed within the
planned schedule/time
• Any delays/ over-runs to the scheduled time baseline must
be investigated and identified
• Corrective actions must be immediately taken to rectify
sources
• Time allowance must be made to cater for any changes to
the scheduled time baseline
1.4 Monitoring,
Controlling
and
Reporting
• Performance audit/risk management committee must be
established
• Performance audits/checks must be conducted through
meetings at every key milestones /deliverables
• Any deviations/changes must be accounted for and sources
identified for immediate corrective actions
• Adequate funding must be allocated for strategic plan
implementation reviews
• Review process must be executed within the planned
budget/costing
• Any deviation/variance to the cost baseline must be notified
and causes/sources investigated
• Corrective actions must be taken immediately rectification
Page 39 of 117
Writing Documentation That Works Project Communication Management
• Sufficient time must be allocated for strategic plan
implementation review process
• Review process must be executed within the planned
schedule/time
• Any delays/ over-runs to the scheduled time baseline must
be investigated and identified
• Corrective actions must be immediately taken to rectify
sources
• Time allowance must be made to cater for any changes to
the scheduled time baseline
7.4.2. Quality Assurance
The Quality Review Team should hold regular meeting
(either weekly or fortnightly) to address any quality issues
related to this project. Figure 7.5.2 outlines the
recommended flow of activities to ensure quality is
maintained throughout every step of this project.
Figure 7.5.2. Quality Assurance Approach
Page 40 of 117
Quality Audit and
review team Meeting
Convened
Quality
Deviations/Defects in
time, cost, and
performance
specifications identified
and thoroughly
discussed.
Resolutions in according
with Quality Management
Policy of this project and
recommendations
adopted and plans made
for immediate corrective
actions
PM to report to
stakeholders on critical
changes in scope, cost,
schedule and
performance for approval
and resource
requirements
Approved Quality
improvement
recommendations and
resolutions are
implemented by
respective project teams
Reports on the
corrective actions
including normal audit
reports are ready for
the next meeting and
communicated to the
relevant stakeholders.
Writing Documentation That Works Project Communication Management
Quality assurance (QA) provides an umbrella for another
important quality activity, continuous process
improvement (PMI, 2004). Activity and information flows
in Figure 7.5.2 hinges on the ongoing fostering of
continuous improvement culture and motivation within the
project team. By fostering continuous improvement
philosophy within the project team will reduce waste of
resources and non-value-added activities, which in turn
allows processes to operate at increased levels of
efficiency and effectiveness.
7.4.3. Quality Control
Performing quality control (QC) in a project involves
monitoring specific project results to determine whether
they comply with relevant quality standards and
identifying ways to eliminate causes of unsatisfactory
results. Although one of the main goals of quality control
is to improve quality, the main outcomes of this process
are acceptance decisions, rework, and process
adjustments (Schwalbe, 2007). PMBOK recommends
that quality control should be performed throughout the
project duration (PMI, 2004).
There are many general tools and techniques to assist in
performing quality control. Table 7.5.3 below provides a
brief description of these tools.
Page 41 of 117
Writing Documentation That Works Project Communication Management
Table 7.5.3. Tools of Quality Control
Tools / Methods Short Descriptions
1. Cause and Effect Diagram
(Fishbone or Ishikawa
Diagram)
Illustrate how various factors might be linked to potential
problems or effects.
2. Control Charts Purpose of Control Chart is to determine whether or not a
process is stable or has predictable performance. This
may also serve as a data gathering tool.
3. Run Chart This method shows the history and pattern of variation. A
run chart is a line graph that shows data points plotted in
the order in which they occur. Trend analysis is
performed using run charts.
4. Scatter Diagram A scatter diagram shows the pattern of relationship
between two variables. This tool allows the quality team
to study and identify the possible relationship between
changes observed in two variables.
5. Histogram Histogram is bar chart showing a distribution of variables.
Each column represents an attribute or characteristic of a
problem/situation.
6. Pareto Charts Pareto chart is a specific type of histogram, ordered by
frequency of occurrence, which shows how many defects
were generated by type or category of identified cause.
7. Flow Chart Flowcharting helps to analyse how problems occur. A
flowchart is a graphical representation of a process. While
there are many styles of flowchart, all process flowcharts
show activities, decision points and the order of
processing.
8. Statistical Sampling Statistical sampling involves choosing part of a population
of interest for inspection. Appropriate sampling can often
reduce the cost of quality control.
9. Inspection An inspection is the examination of a work product to
determine whether it conforms to standards. Generally,
the results of an inspection include measurements.
Inspection can be conducted at any level.
10. Defect Repair Review Defect repair review is an action taken by the quality
control department or similarly titled organisation or team
to ensure that product defects are repaired and brought
into compliance with requirements or specifications.
Source: PMI (2004)
Page 42 of 117
Writing Documentation That Works Project Communication Management
The first seven of the tools in Table 7.5.3 are known as
“Seven Basic Tools of Quality” (PMI, 2004).
Given the nature of this project, it is recommended that
the PM uses a combination of the abovementioned
approaches to monitor, control and report on quality
management related issues. This will allow and benefit
the PM to monitor, control and report on both technical
and non-technical oriented quality related issues.
This project management plan recommends the following
approaches/tools to analyse, monitor, report and control
quality for this project:
• Cause and Effect Diagram
• Flow Chart
• Run Chart
• Inspection
• Defect Repair Review
7.5. Other Considerations
In addition to the above suggestions and plans provided
for good quality planning, quality assurance and quality
control, there are several other important issues involved
in improving the quality of a project (Schwalbe, 2007).
Strong and supportive leadership, understanding the cost
of quality, providing a good workplace to enhance quality,
and working toward improving the organisation’s overall
maturity level in project management can all assist in
improving quality.
7.5.1. Quality Cost Monitoring and Reporting
The cost of quality is the cost of conformance and non-
conformance in meeting the project specification and
fitness for use. There are various types of cost of quality
that the PM needs to be aware of during the execution of
this project. Schwalbe (2007) suggested that the
following costs are related quality cost:
• Prevention cost
• Appraisal cost
Page 43 of 117
Writing Documentation That Works Project Communication Management
• Internal failure cost
• External failure cost
• Measurement and test equipment cost
To control budget, it is strongly recommended that during
the execution of this project there is structured and
routine reporting and monitoring on quality cost. This will
allow PM to take corrective action in a timely manner
without compromising quality.
7.5.2. Leadership
Quality expert, Joseph M. Juran once (in1945) said, “It is
most important that top management be quality minded
(cited by Schwalbe, 2007). Indeed, without sincere
manifestation of interest in maintaining high standard of
quality at the top level management of an organisation,
there is high risk in a project in producing poor quality
output. For this project to accomplish its objective, it is
important that top management must create a culture that
embraces quality.
7.5.3. Organisational Influence, Workplace
Factors and Quality
Research shows that organisational issues can have
much greater influence on productivity than the technical
environment or superiority (Schwalbe, 2007). As such,
the PM of this project should keep in mind factors such as
organisational politics. The PM function is to remove
political roadblocks and create an environment where
negative organisational influence does not adversely
impact project quality and objective.
7.5.4. Expectations and Cultural Differences
Schwalbe (2007) argues that there are many aspects of
quality can be defined and measured, many cannot. She
suggests that different project sponsors, customers, users
and other stakeholders have different expectations about
various aspects of a project. Therefore, it is very
important for the PM of this to understand these
expectations and manage any conflicts that might occur
due to differences in expectations from various
stakeholders.
Page 44 of 117
Writing Documentation That Works Project Communication Management
8. Project Human Resource Management
People are the most important asset as they determine
the success and failure of organizations and projects
(Kathy Schwalbe. 2007). This section is created to assist
the project manager in managing human resources
effectively; the components of this section are as follows:
• Human resource planning
• Staff acquisition
• Team development
• Team management
8.1. Human Resource Planning
This human resource plan is created to identify and
document project roles, responsibilities, and reporting
relationships involved in the project. The
Organizational Chart, Roles and Responsibilities
Assignments, RACI Chart, Staffing management plan
in this plan are used to ensure project success.
8.1.1. Organizational Chart
This organizational chart provides an organizational
structure to manage the project team members that come
from different backgrounds and have different functions in
the project.
Page 45 of 117
Writing Documentation That Works Project Communication Management
Note: The positions of Technician 2, Technician 3, and
Technician 4 are beneath Technician 1, they are
responsible for reporting to Technician 1, and Technician
1 is responsible for reporting to the Project Manager
directly.
8.1.2. Roles and Responsibilities Assignment
Position descriptions and qualification criteria are
essential to select the right people to do the job and
ensure all the tasks in the project are assigned to certain
people.
Table 1.2. Roles and Responsibilities Assignment
Project
Management
Position
Responsibilities Qualifications
Project Manager  Ensure the Project Team
completes the project
 1. More than five
years of Project
Page 46 of 117
Writing Documentation That Works Project Communication Management
 Develop the Project Plan
with the team and
manages the team’s
performance of project
tasks
 Secure acceptance and
approval of deliverables
from the Project Sponsor
and Stakeholders
 Make sure the project is
delivered in budget, on
schedule, and within
scope.
management
experience as well
as be PMI certified.
 2. Strong planning,
motivation and
communication
skills.
Project
Accountant
 Keeping track of project
cost performance
throughout the project life
and conduct budget
review in every month,
planned milestone and
project phase.
 Detecting and investigate
the cause of the variance
and make necessary
recommendations to the
project manager.
 Ensuring that all
appropriate changes are
recorded accurately in the
cost baseline under the
project manager’s
approval.
 At least three years
accounting
experience, the
majority of which
should have been in
a project related
environment.
 Computer literacy
with experience in
MSWord, excel.
 Must be able to
work independently
and meet deadlines
in a team
environment.
Senior
Engineer/Analyst
 Establishing and
maintaining project
technical requirements
 Directing the technical
implementation according
to established schedules
and budgets
 1. Master degree in
biology science
and/or engineering.
 2. At least five years
recent specialized
experience.
Junior
Engineer/Analyst
1
 Watching day-to-day
progress and quality of
work, supervising the work
as per specification,
maintaining quality control
records carrying out
quality control tests
 Assess the requirements
of materials like, fertilisers
nutrient media, Immersion
Heater, and coulter
counter etc. for the
 Bachelor degree in
biology science
and/or engineering.
 2. At least two years
recent specialized
experience.
Junior
Engineer/Analyst
2
Page 47 of 117
Writing Documentation That Works Project Communication Management
nursery system
Technician 2  Constructing and
maintaining the works
involved to develop the
prototype of the nursery
system
 Top of Form
 1. Relevant tertiary
qualifications in
biology science
or/and engineering
2. At least two years
experience in
biology-related field
3. Excellent
communication skills
to work in a team.
Bottom of Form
Technician 3
Technician 4
Technician 1  Same as above, but strong
role in supervising the
construction of the nursery
system and reporting
progresses and problems
to the project manager
 
Procurement
Specialist
 Develop the solicitation
document that states the
requirements for acquiring
of raw material for nursery
system.
 Develop a Proposal
Evaluation Plan for
evaluating the proposals
to describe the specific
evaluation criteria (such
as qualifications,
methodology for
completing the work,
references and cost), and
the methods that will be
used to apply the criteria.
 Research and evaluate
suppliers based on price,
quality, selection, service,
support, availability,
reliability, production, and
distribution capabilities as
well as the reputation and
history
 1. A purchasing
certification is
preferred.
 2. A minimum of two
years working in a
general buying
environment.
 3. Considerable
knowledge of
purchasing methods
and procedures and
of the techniques of
specification writing.
8.1.3. RACI Chart
In order to show the position roles to the project
stakeholders, we created the RACI Chart to identify the
responsibility (R), accountability (A), consultation (C) and
informed (I) roles to execute the project.
Page 48 of 117
Writing Documentation That Works Project Communication Management
Project
manager
Project
accountant
Senior
engineer
/analyst
Junior
engineer
/analyst
Technician Procurement
specialist
Design Nursery
System
R I A C
Build Nursery
System
I &C I R A A A
Deployment R I A A C
R=Responsibility, only one R per task
A=Accountability
C=Consultation
I =Informed
8.1.4. Staffing Management Plans and Resource
Histogram
The purpose of the staffing plan below is to make certain
the project has sufficient staffs with the right skills and
experience to ensure a successful project completion
Page 49 of 117
Writing Documentation That Works Project Communication Management
8.1.4.1. Resource Histogram
The Resource Histogram presents the number of human
resources assigned to the project over time. From the
chart, the project manager can determine the number of
the people needed each month, which he/she can base
on to design the staffing plan to acquire the necessary
staffs and develop the project team.
Page 50 of 117
Writing Documentation That Works Project Communication Management
8.1.4.2. Staffing Management Plan
After creating the Resource Histogram, the Project
Manager is required to prepare the staffing management
plan for recruitment; the staffing management plan
(Appendix H – Staffing Management Plan) should
include the overall staffing approach, the training plan
and reassignment plan.
8.2. Staff Acquisition
This section sets forth the acquisition strategy,
defines the efforts required to implement it to ensure
coordination of the project manager and the human
resource department to get the right people to fulfil
the project’s needs.
8.2.1. Resource Assignment
Page 51 of 117
Writing Documentation That Works Project Communication Management
8.2.1.1. Staff Pooling Description
The staff pooling description table assists the project
manager and Human Resource Department in assessing
the characteristics of potential staffs and make decisions
of hiring staffs.
Table 8.2.1.1. Staff Pooling Description Table
Employee
Name
Employee
ID
Job Title Period
required
Department Date
Characteristic
s
Performance R
(1
5
Previous
Experience
Personal
Interests
Personal
Characteristics
Availability
Competencies
Proficiencies
Overall Assessment
Page 52 of 117
Writing Documentation That Works Project Communication Management
8.2.1.2. Recruitment Practices
During the recruiting, all the staffs must strictly abide by
the policies, guidelines and procedures governing staff
assignments. Additionally, all the updates to the staffing
management plan must be recorded by the project
manager. The recruitment gives priorities to current
employees in the bio-fuel program.
Page 53 of 117
Writing Documentation That Works Project Communication Management
8.2.1.3. Project Staff Assigned
Based on the needs of the project, staff may be assigned
full time, part time, or variably, which is presented in the
resource requirement in project time management
section.
Page 54 of 117
Writing Documentation That Works Project Communication Management
8.2.1.4. Project Team Directory
The template below is to be used by the project team
when taking down details of relevant members and
stakeholders.
Employee
Name
Employee
ID
Role Phone Mobile Fax Email Address
8.3. Team Development
The main goal of this team development plan is to
help people work together more effectively to improve
project performance and achieve the project goals.
8.3.1. Training
To ensure all the team members are qualified for the
project, they are arranged to take specific training
courses based on information from the Roles and
Responsibilities Assignments table and the staff pooling
description.
8.3.2. Team Building Activities
Project manager is recommended to organize team-
building activities monthly; the options of team building
activities, physical challenges or psychological
preference indicators are determined by the performance
of the team members and the requirements of the
upcoming tasks.
8.3.3. Input to Performance Appraisals
The performance reports below are used to evaluate the
performance of the team members, as documentation for
updates to the human resources management plans.
Page 55 of 117
Writing Documentation That Works Project Communication Management
8.3.3.1. Employee Self-Evaluation Assessment
Self-evaluations help employees measure how they are
performing in their job. This assessment form can provide
guidance and consistency within our project, to help the
Project Manager and Human Resources department to
record, track, and report information for the employee
evaluation process. This form is required to assess
monthly.
Template 8.3.3.1. Employee self-evaluation
assessment
Employee Information
Employee
Name:     
 
Employee
ID:     
 
Job Title:
     
Date
:
     
Department:
     
Manager:
     
Review
Period:
      To      
Goals
Describe the goals you had set out to accomplish for this time period:
ch goals did you accomplish? Which other objectives did you meet, beyond your stated goals?
Which achievements are you most proud of?
Which goals did you not accomplish and why not?
Risks and Expectations
What kind of risks did you take during the time span of this evaluation?
What are your expectations for the next evaluation time span?
What can your manager do to help you achieve your future goals?
What are your goals for the next evaluation? Please be clear and concise
Comments
Additional Comments:
Page 56 of 117
Writing Documentation That Works Project Communication Management
8.3.3.2. Employee Performance Review
The template below is to assess employees’ performance
by their superior (refer to the organizational chart)
monthly.
Please, refer to Appendix I - Employee Performance
Review.xlsx.
8.3.4. Performance Improvements
Project management has the responsibility to set up the
HR management mechanism to improve employees’
performance.
Page 57 of 117
Writing Documentation That Works Project Communication Management
8.3.4.1. Improvement in Individual Skills
a) Set up reward and recognition system.
b) Discuss work and personal issues with
employees via e-mail, telephone, or other
communication media (refer to communication
management plan for details).
c) Provide training opportunities to employees
who are in need. (Refer to training section.)
Page 58 of 117
Writing Documentation That Works Project Communication Management
8.3.4.2. Improvement in Team Behaviours
a) Keep an issue log to document, monitor, and
track issues that needed to solve for the
project team to work effectively.
b) Organize team-building activities to help
employees to understand and value each
other’s differences in order to work effectively
as a team. (Refer to team building section).
8.4. Team Management
Team management is essential in Human Resource
Management Plan. The Project Manager is required to
do the followings to motivate and manage his/her
team members in case changes are requested to the
project.
a) Have formal or informal conversion with employees
regularly; discuss any issue with them when they
are in need.
b) Record and keep track on all the updates to human
resources plans.
c) Inform any personnel changes to stakeholders in a
timely manner
d) Maintain and update the Reward and Recognition
System regularly.
e) Take corrective or preventive actions to deal with
any unexpected event, such as employee leaves the
project.
Page 59 of 117
Writing Documentation That Works Project Communication Management
9. Project Communication Management
In order to keep the project activities dynamic between
team members and other stakeholders within the project
itself, it is mandatory that all communications align
perfectly and are up to date.
Communications management incorporates methods for
collecting, gathering and disseminating communication,
as well as information across the internal teams and
stakeholders of the project.
This documentation will list methods of communication,
as well as the technology that will help communication
during various tasks where communication is needed.
9.1. Communications Planning
Before one is to follow the guidelines for distributing
information discussed below, it is important to run skill
checks on team members and also stakeholders.
This will be used to find the most optimized method of
carrying out these communication processes i.e., to find
out which software is most commonly used by individual
members (this will decrease new learning curves, saves
time and increases productivity since they are already
familiar with the software).
In this project, there is a probability that members will
have to work remotely from time to time. Therefore, the
team must be flexible in terms of communicating.
Although, the guidelines below conjure the recommended
method of communication i.e., written or verbal, members
are able to make themselves adapt to which of the two
methods they prefer to use during a certain situation.
Page 60 of 117
Writing Documentation That Works Project Communication Management
Lastly, along the course of the project, it is expected for
the Internet and phone to be the primary channel for
conveying information. Fax and postage mails are not to
be considered for daily and active communication but are
to be used whenever necessary. Domestic or
international shipping will be used whenever tangible
products, prototypes or deliverables are to be sent.
9.2. Information Distribution
The English language is taken into account being the de
facto language for all communication and documentation
in this project, although, not being the de jure language of
communication meaning stakeholders are still able to
verbally communicate in other languages beside English.
The types of communication that are discussed in this
documentation have been divided into either or both
dynamic/verbal and/or passive/written communication.
Dynamic/verbal communication is when communication is
synchronous and happens in real time e.g., talking face
to face from one human being to another. Passive/written
communication describes communication that happens
asynchronously meaning one party is able to reply the
opposing party on a different time e.g., sending and
replying emails through technological devices.
Relating to the previous point made on dynamic and
passive communication, this documentation suggests
which should be used during a certain task of
communication.
One should note that dates on which new communication
has commenced should be recorded inside the
perspective documentation for future reference, not to
mention evidence for legal issues if they were to arise.
Page 61 of 117
Writing Documentation That Works Project Communication Management
9.2.1. Introductions to New Stakeholders and
Negotiation
Task Method Technology Goal
Introducing an
existing
stakeholder to a
new stakeholder
Verbal/written
communication
When introducing an
existing member on the
team to a new member
or a new stakeholder,
must notify the existing
member in prior to the
introduction.
It is considered
inconvenient for one to
meet a new colleague
without warning
beforehand.
• Face to face
• Phone/audio/
video/confer
ence calls
• SMS
• Email
• Instant
Messenger
This allows the
existing team
member to be
prepared
mentally in order
to convey the
preferred first
impression.
Commencing
communication/Int
roduction with new
individuals and
stakeholders
Verbal/written
communication
The initial project team
must consider good
etiquette at all times,
particularly, the Project
Manager.
Greetings should be
conveyed politely and
with adequate.
This is a very crucial
task to be completed
properly, especially
when first impressions
are to take place.
• Face to face
• Phone/audio/
video/confer
ence calls
• SMS
• Email
• Instant
Messenger
The goal to
achieve after
new
communication
has started is to
allow the
mentioned
parties to be
comfortable with
one another.
If this is
achieved, in
return, the
parties will have
a more relaxed
and pleasant
environment
when
communicating.
Commencing
negotiation
Written
communication
It is a significant issue
when one needs to
perform negotiation with
another human being.
Written communication
is recommended when a
• SMS
• Email
• Instant
Messenger
This allows
parties to make
their own initial
statements,
ideas and points
concisely.
Page 62 of 117
Writing Documentation That Works Project Communication Management
negotiation is to
commence. This allows
both parties to be
concise, exact and
follow the concept of
brevity when delivering
their points.
If one prefers to
commence a
negotiation verbally with
another party, one is
allowed to as there are
no strict restrictions to
using this method.
Although, a note should
be taken to be synoptic
but detailed.
In return, this
allows each
party to at least
predict a small
portion of one
another’s
favoured
decision.
Commencing
negotiation with
individuals from
different cultures
Written
communication
It is an even more
significant issue when
one needs to perform
negotiation with another
human being coming
from a different culture
and background.
Before making an
attempt at this task, it is
wise to study and
analyse how the
particular culture
communicates and
performs negotiation
organically. Thus, one
is able to adapt to their
environment and dive
into natural
communication
methods.
Also ensure to use more
common words that
most English speakers
are familiar with.
• SMS
• Email
• Instant
Messenger
Beyond the
previous task
mentioning
commencing
negotiation in
general, written
communication
is also preferred
when
communicating
with individuals
of different
cultures and
native
languages.
Written
language is
better
understood by
both native and
non-native
speakers than
verbal language
due to dialect
and accent
differences.
Page 63 of 117
Project Management Plan_1
Project Management Plan_1
Project Management Plan_1
Project Management Plan_1
Project Management Plan_1
Project Management Plan_1
Project Management Plan_1
Project Management Plan_1
Project Management Plan_1
Project Management Plan_1
Project Management Plan_1
Project Management Plan_1
Project Management Plan_1
Project Management Plan_1
Project Management Plan_1
Project Management Plan_1
Project Management Plan_1
Project Management Plan_1
Project Management Plan_1
Project Management Plan_1
Project Management Plan_1
Project Management Plan_1
Project Management Plan_1
Project Management Plan_1
Project Management Plan_1
Project Management Plan_1
Project Management Plan_1
Project Management Plan_1
Project Management Plan_1
Project Management Plan_1
Project Management Plan_1
Project Management Plan_1
Project Management Plan_1
Project Management Plan_1
Project Management Plan_1
Project Management Plan_1
Project Management Plan_1
Project Management Plan_1
Project Management Plan_1
Project Management Plan_1
Project Management Plan_1
Project Management Plan_1
Project Management Plan_1
Project Management Plan_1
Project Management Plan_1
Project Management Plan_1
Project Management Plan_1
Project Management Plan_1
Project Management Plan_1
Project Management Plan_1
Project Management Plan_1
Project Management Plan_1
Project Management Plan_1
Project Management Plan_1
Project Management Plan_1
Project Management Plan_1

More Related Content

Similar to Project Management Plan_1

This unit forms part of the following qualification BSB50420
This unit forms part of the following qualification BSB50420 This unit forms part of the following qualification BSB50420
This unit forms part of the following qualification BSB50420 TakishaPeck109
 
Project evaluation
Project evaluationProject evaluation
Project evaluationManish Nepal
 
Project Management Msc. 7Pjmn009W Project Management Project.
Project Management Msc. 7Pjmn009W Project Management Project.Project Management Msc. 7Pjmn009W Project Management Project.
Project Management Msc. 7Pjmn009W Project Management Project.Renee Jones
 
1 Australian Institute of Higher Education CRICOS Prov.docx
1 Australian Institute of Higher Education CRICOS Prov.docx1 Australian Institute of Higher Education CRICOS Prov.docx
1 Australian Institute of Higher Education CRICOS Prov.docxkarisariddell
 
Project Management Strategy and Tactics 1 Course Learning .docx
Project Management Strategy and Tactics 1 Course Learning .docxProject Management Strategy and Tactics 1 Course Learning .docx
Project Management Strategy and Tactics 1 Course Learning .docxpauline234567
 
How good is my project management framework
How good is my project management frameworkHow good is my project management framework
How good is my project management frameworkHari Thapliyal
 
Atifa Capstone Final Report First Draft. (1)
Atifa Capstone Final Report First Draft. (1)Atifa Capstone Final Report First Draft. (1)
Atifa Capstone Final Report First Draft. (1)Atifa Mahmoodi
 
C. Burcham - Project Closure Report
C. Burcham - Project Closure ReportC. Burcham - Project Closure Report
C. Burcham - Project Closure ReportCheryl Burcham
 
2 b. project termination
2 b. project termination2 b. project termination
2 b. project terminationDr.R. SELVAM
 
Pm assignment -5111570030
Pm assignment -5111570030Pm assignment -5111570030
Pm assignment -5111570030adzoyi
 
Assignment 3 Project PerformanceDue Week 8 and worth 150 .docx
Assignment 3 Project PerformanceDue Week 8 and worth 150 .docxAssignment 3 Project PerformanceDue Week 8 and worth 150 .docx
Assignment 3 Project PerformanceDue Week 8 and worth 150 .docxbraycarissa250
 
2.1 integration management
2.1 integration management2.1 integration management
2.1 integration managementIrefuser1
 
Project Manual
Project ManualProject Manual
Project ManualJoe Lynn
 
project of audit
project of auditproject of audit
project of auditUswa Malik
 
I need help with my course project.docx
I need help with my course project.docxI need help with my course project.docx
I need help with my course project.docxwrite4
 
I need help with my course project.docx
I need help with my course project.docxI need help with my course project.docx
I need help with my course project.docxbkbk37
 
Writing evaluation report of a project
Writing evaluation report of a projectWriting evaluation report of a project
Writing evaluation report of a project03363635718
 
scope-statement-sample.doc
scope-statement-sample.docscope-statement-sample.doc
scope-statement-sample.docAhsanRahman13
 

Similar to Project Management Plan_1 (20)

This unit forms part of the following qualification BSB50420
This unit forms part of the following qualification BSB50420 This unit forms part of the following qualification BSB50420
This unit forms part of the following qualification BSB50420
 
Project evaluation
Project evaluationProject evaluation
Project evaluation
 
Project Management Sample
Project Management SampleProject Management Sample
Project Management Sample
 
Project Management Msc. 7Pjmn009W Project Management Project.
Project Management Msc. 7Pjmn009W Project Management Project.Project Management Msc. 7Pjmn009W Project Management Project.
Project Management Msc. 7Pjmn009W Project Management Project.
 
1 Australian Institute of Higher Education CRICOS Prov.docx
1 Australian Institute of Higher Education CRICOS Prov.docx1 Australian Institute of Higher Education CRICOS Prov.docx
1 Australian Institute of Higher Education CRICOS Prov.docx
 
Project Management Strategy and Tactics 1 Course Learning .docx
Project Management Strategy and Tactics 1 Course Learning .docxProject Management Strategy and Tactics 1 Course Learning .docx
Project Management Strategy and Tactics 1 Course Learning .docx
 
How good is my project management framework
How good is my project management frameworkHow good is my project management framework
How good is my project management framework
 
Atifa Capstone Final Report First Draft. (1)
Atifa Capstone Final Report First Draft. (1)Atifa Capstone Final Report First Draft. (1)
Atifa Capstone Final Report First Draft. (1)
 
C. Burcham - Project Closure Report
C. Burcham - Project Closure ReportC. Burcham - Project Closure Report
C. Burcham - Project Closure Report
 
2 b. project termination
2 b. project termination2 b. project termination
2 b. project termination
 
Pm assignment -5111570030
Pm assignment -5111570030Pm assignment -5111570030
Pm assignment -5111570030
 
Assignment 3 Project PerformanceDue Week 8 and worth 150 .docx
Assignment 3 Project PerformanceDue Week 8 and worth 150 .docxAssignment 3 Project PerformanceDue Week 8 and worth 150 .docx
Assignment 3 Project PerformanceDue Week 8 and worth 150 .docx
 
2.1 integration management
2.1 integration management2.1 integration management
2.1 integration management
 
Project Manual
Project ManualProject Manual
Project Manual
 
Session 22 4th edition PMP
Session 22 4th edition PMPSession 22 4th edition PMP
Session 22 4th edition PMP
 
project of audit
project of auditproject of audit
project of audit
 
I need help with my course project.docx
I need help with my course project.docxI need help with my course project.docx
I need help with my course project.docx
 
I need help with my course project.docx
I need help with my course project.docxI need help with my course project.docx
I need help with my course project.docx
 
Writing evaluation report of a project
Writing evaluation report of a projectWriting evaluation report of a project
Writing evaluation report of a project
 
scope-statement-sample.doc
scope-statement-sample.docscope-statement-sample.doc
scope-statement-sample.doc
 

Project Management Plan_1

  • 1. BUSN7024 Project Management Principles Semester 2, 2010 – Major Assignment Project Management Plan Algae Nursery System Azim Khan U4009419 Emma Shaw U4924015 Osama Nasir U 4786695 Ruoying Liang U4638781 Stephanie Mutiara U4820179 Word Count: 21,310 Due Date: Friday, 22 October 2010 E-copy: via email to walter.fernandez@anu.edu.au Paper copy: assignment box, ABIS School Office File Name: project-management-plan11514.doc
  • 2. Writing Documentation That Works Project Communication Management Team Number: 7 By signing on Table 1 each member acknowledges his or her agreement with the stated contribution to the overall assignment made by each team member. Name Student No Contribution Signature Azim Khan U4009419 A Emma Shaw U4924015 A Osama Nasir U4786695 A Ruoying Liang U4638781 A Stephanie Mutiara U4820179 A Table 1: Membership and Individual Contribution.
  • 3. Writing Documentation That Works Project Communication Management Use the following convention to state each member contribution to the total effort • A = very good contribution, the team member went above the expected participation level. • B = good contribution, the member participated as expected and was diligent in performing the assigned tasks. • C = less than satisfactory contribution, the member participation and contribution was less than the average for the team. • D = the member had minimal participation on the team effort, shown lack of commitment to the team and significantly increased other members’ workload. • E = the team member did not contribute at all to the team. The team shall discuss and agree on the contribution level for each team member. Your signature on Table 1 indicates your agreement with the assessment of contribution. A lack of signature will indicate dissatisfaction with the attribution. Please note, if half or less than half of the team sign the contribution assessment, a penalty of 5% will apply to the assignment’s mark. To encourage the teams to strive to perform as a team, penalties will be assigned to students that perform below the minimum expected level (see Table 2). Individual contribution to the team’s effort. Penalty to be applied to the assignment’s mark for the particular student A 0% B. 0% C 15% D 50% E 100% Table 2: Human Resources Mismanagement Penalties. This page is confidential and will NOT be seen by the class. The lecturer will delete this page before releasing the document for class access on the web site.
  • 4. Writing Documentation That Works Project Communication Management Acknowledgement Walter Fernandez is grateful to the author of this template, David Tuffley, who generously allowed him to modify the template and to use it at ANU. Plagiarism ✍ Plagiarism will not be tolerated. It is the responsibility of the team to ensure that proper citation and quotation conventions are followed. Failure to observe this rule will result in a zero mark for the entire assignment, regardless of the magnitude of the infringement. Further action(s) might be considered on a case-by-case basis. i of of v
  • 5. Writing Documentation That Works Project Communication Management Contents Contents..................................................................................................ii 1. Executive Summary............................................................................1 2. Project Introduction...........................................................................2 3. Project Integration Management.......................................................3 3.1. Project Plan Development.............................................................3 3.2. Project Plan Execution..................................................................4 3.2.1. Project Initiation......................................................................4 3.2.2. Project Direction.....................................................................4 3.2.3. Project Planning, Monitoring and Controlling Cycle..............4 3.2.4. Project Closing.......................................................................4 3.3. Integrated Change Control...........................................................5 4. Project Scope Management...............................................................6 4.1. Initiation..........................................................................................6 4.1.1. Product Description................................................................6 4.1.2. Strategic Plan.........................................................................7 4.1.3. Project Selection Criteria .......................................................7 4.2. Scope Planning.............................................................................8 4.2.1. Product Description................................................................8 4.2.2. Project Charter........................................................................8 4.3. Scope Definition.............................................................................9 4.3.1. Scope Statement....................................................................9 4.3.2. Work Breakdown Structure (WBS)......................................10 4.4. Scope Verification........................................................................10 4.4.1. Critical Success Factors.......................................................10 4.4.2. Evaluation Measures............................................................10 4.5. Scope Change Control................................................................11 4.5.1. Scope Changes....................................................................11 4.5.2. Corrective Action..................................................................11 4.5.3. Documentation.....................................................................12 5. Project Time Management................................................................13 5.1. Activity Definition.........................................................................13 5.2. Activity Sequencing.....................................................................13 5.3. Activity Duration Estimating.........................................................14 5.3.1. Basis of Estimates................................................................14 5.4. Schedule Development................................................................14 5.4.1. Project Schedule..................................................................14 ii of of v
  • 6. Writing Documentation That Works Project Communication Management 5.4.2. Schedule Management Plan................................................14 5.4.3. Resource Requirement Update............................................15 5.4.4. Constraints and Assumptions...............................................15 5.5. Schedule Control.........................................................................15 5.5.1. Schedule Updates ...............................................................15 5.5.2. Corrective Actions................................................................16 6. Project Cost Management................................................................17 6.1. Resource Planning......................................................................17 6.1.1. Resource Requirement........................................................18 6.2. Cost Estimating...........................................................................20 6.3. Cost Budgeting............................................................................26 6.4. Cost Monitoring, Controlling and Reporting................................26 6.5. Other considerations...................................................................29 7. Project Quality Management............................................................30 7.1. Scope...........................................................................................30 7.2. Quality Objective.........................................................................31 7.3. Quality Control.............................................................................31 7.4. Organisational Structure and Responsibilities............................33 Quality Management Process............................................................35 7.4.1. Quality Planning...................................................................35 7.4.2. Quality Assurance................................................................40 7.4.3. Quality Control......................................................................41 7.5. Other Considerations...................................................................43 7.5.1. Quality Cost Monitoring and Reporting................................43 7.5.2. Leadership............................................................................44 7.5.3. Organisational Influence, Workplace Factors and Quality..44 7.5.4. Expectations and Cultural Differences.................................44 8. Project Human Resource Management..........................................45 8.1. Human Resource Planning..........................................................45 This human resource plan is created to identify and document project roles, responsibilities, and reporting relationships involved in the project. The Organizational Chart, Roles and Responsibilities Assignments, RACI Chart, Staffing management plan in this plan are used to ensure project success.....................45 8.1.1. Organizational Chart............................................................45 8.1.2. Roles and Responsibilities Assignment...............................46 8.1.3. RACI Chart...........................................................................48 8.1.4. Staffing Management Plans and Resource Histogram........49 8.1.4.1. Resource Histogram.....................................................50 8.1.4.2. Staffing Management Plan............................................51 8.2. Staff Acquisition...........................................................................51 This section sets forth the acquisition strategy, defines the efforts required to implement it to ensure coordination of the project iii of of v
  • 7. Writing Documentation That Works Project Communication Management manager and the human resource department to get the right people to fulfil the project’s needs..................................................51 8.2.1. Resource Assignment..........................................................51 8.2.1.1. Staff Pooling Description..............................................52 8.2.1.2. Recruitment Practices...................................................53 8.2.1.3. Project Staff Assigned...................................................54 8.2.1.4. Project Team Directory.................................................55 8.3. Team Development......................................................................55 The main goal of this team development plan is to help people work together more effectively to improve project performance and achieve the project goals................................................................55 8.3.1. Training.................................................................................55 8.3.2. Team Building Activities.......................................................55 8.3.3. Input to Performance Appraisals..........................................55 8.3.3.1. Employee Self-Evaluation Assessment........................56 Employee Information....................................................................56 Goals..............................................................................................56 Risks and Expectations.................................................................56 Comments......................................................................................56 8.3.3.2. Employee Performance Review....................................57 8.3.4. Performance Improvements.................................................57 8.3.4.1. Improvement in Individual Skills...................................58 8.3.4.2. Improvement in Team Behaviours................................59 8.4. Team Management......................................................................59 Team management is essential in Human Resource Management Plan. The Project Manager is required to do the followings to motivate and manage his/her team members in case changes are requested to the project..................................................................59 9. Project Communication Management.............................................60 9.1. Communications Planning...........................................................60 9.2. Information Distribution...............................................................61 9.2.1. Introductions to New Stakeholders and Negotiation............62 9.2.2. Meetings, Presentation and Reports....................................65 9.2.3. File Management..................................................................68 9.3. Performance Reporting................................................................71 9.3.1. Communications Hierarchy..................................................74 9.3.1.1. Top Down Communication............................................75 9.3.1.2. Bottom Up Communication...........................................76 9.3.1.3. Middle Out Communication...........................................77 9.4. Administrative Closure.................................................................79 9.5. Other techniques for information and communications management.......................................................................................81 10. Project Risk Management..............................................................82 10.1. Risk Management Planning......................................................83 10.1.1. Organisational Risk Management Policies........................83 iv of of v
  • 8. Writing Documentation That Works Project Communication Management 10.1.2. Risk Planning Meetings and Analysis................................84 10.1.3. Risk Management Plan......................................................85 10.1.4. Methodology.......................................................................86 10.1.5. Roles and Responsibilities.................................................86 10.1.6. Risk Categories..................................................................88 10.1.7. Project Risks.......................................................................88 10.2. Risk Identification ....................................................................92 10.2.1. Tools and Techniques........................................................92 10.2.2. Risk Register......................................................................94 10.3. Qualitative Risk Analysis..........................................................94 10.4. Quantitative Risk Analysis........................................................95 10.5. Risk Monitoring and Control.....................................................96 10.5.1. Monitoring...........................................................................96 10.5.2. Controlling..........................................................................96 10.5.3. Reporting............................................................................97 10.6. Risk Response Planning..........................................................97 10.6.1. Negative Risks....................................................................98 10.6.2. Positive Risks.....................................................................98 11. Project Procurement Management..............................................100 11.1. Procurement Planning............................................................100 11.2. Solicitation Planning ..............................................................101 11.3. Solicitation..............................................................................102 11.4. Source Selection.....................................................................103 11.5. Contract Administration..........................................................104 11.6. Contract Closeout...................................................................105 12. Conclusion.....................................................................................106 13. Appendix A - Project Gantt Chart................................................107 14. Appendix B - Table 6.3. Project Cost Baseline..........................108 15. Appendix C - Monthly Project Financial Performance Report Template...............................................................................................109 16. Appendix D - Year to Date Project Financial Performance Report ...............................................................................................................110 17. Appendix E - Labour Cost Analysis Report...............................111 18. Appendix F – WBS........................................................................112 19. Appendix G – WBS Dictionary.....................................................113 20. References.....................................................................................117 v of of v
  • 9. Writing Documentation That Works Project Communication Management vi of of v
  • 10. Writing Documentation That Works Project Communication Management 1. Executive Summary The Nursery System Project will automate the early cultivation of micro-algae. Automation of this process is needed in order to prepare commercial quantities of micro-algae which can in turn produce commercial quantities of bio-fuel. The Nursery System will monitor and control the growth of micro-algae from the laboratory to the large tanks in which the micro-algae is grown. This project will be considered successful based on stakeholder acceptance of the project, with all changes noted and documented and stakeholder acceptance of these changes, as well as a working nursery system that endures an allotted amount of time without technical failures. This project management plan details each phase of the project the project manager must complete in order to deliver a successful product. This includes project cost, time and scope management, project quality management, communications, risk, procurement and human resources management, and overall project integration management procedures and methods for the successful project manager. The project will cost $$$ and will take 271 days to complete. The project has been planned to produce a product of high quality, ensuring the commercial viability of the Nursery System. The project will be complete when key stakeholders from the ANU BioSolar Program are satisfied that the Nursery System meets their requirements. The major risks for this project include: Page 1 of 117
  • 11. Writing Documentation That Works Project Communication Management 2. Project Introduction The Australian National University has developed bio- technology which allows crude oil to be sourced from micro-algae. The development of this technology allows for a renewable source of energy. In a world of finite non- renewable energies, the uses for this renewable source of energy are many and varied. However, the micro-algae needs carefully grown and monitored. The environment in which it is grown must be carefully regulated for light, pH, temperature and water to ensure that the algae do not die. Current processes for encouraging the growth of algae involve transferring the algae by hand from a series of smaller ponds into a series of larger ponds, to ensure that the algae does not die from overexposure to water. The Nursery System project will automate this process. By automating the process, the project will not only reduce the time and effort required in growing algae into commercial quantities for oil production, but create an exportable system in which any business can use the nursery system to develop its own algae for bio-fuel production. The nursery system project includes the development of a user manual, which will enhance the marketability of the system, and also ensure that the technology can be widely used. By creating the nursery system, the project team will be contributing to the transfer from reliance on fossil fuels to a more environmentally friendly use of renewable bio- fuels. Page 2 of 117
  • 12. Writing Documentation That Works Project Communication Management 3. Project Integration Management Project integration management is key to ensuring the overall success of the project. It involves coordinating all of the other project management areas throughout the project’s life cycle. 3.1. Project Plan Development The Project Plan has been created following the nine key project management principles – cost, time, scope, quality, communications, risk, procurement, human resources and project integration – so that project management plan provides a comprehensive overview. This project management plan provides consistency across all nine areas to ensure that all aspects of the project have been planned for. Please, refer to the table of contents for a full list of all the plans and documents that have been designed for this project. Page 3 of 117
  • 13. Writing Documentation That Works Project Communication Management 3.2. Project Plan Execution 3.2.1. Project Initiation The project will be initiated at the instigation of the ANU BioSolar Program. The project will be selected by key stakeholders from the ANU BioSolar Program, who will also consider the development of the business case, determine scope, time and cost constraints, identify the project sponsor, and select a project manager. 3.2.2. Project Direction The project will be directed by the project manager, under whose authority all decisions will be made, in conjunction with the Change Control Committee. The project manager’s decision will be final. The project manager alone can endorse and initiate each of the work activities under the Work Breakdown Structure. 3.2.3. Project Planning, Monitoring and Controlling Cycle The project planning, monitoring and controlling Cycle will be performed through constant communication, both oral and written. Formally, monitoring and controlling will be managed through written documents which include the weekly progress report, exception reports for management on issues of particular interest that arise during the project, and the final lessons learned report. The planning, monitoring and controlling cycle will constitute a ‘feedback loop’ in which any deviations from the project schedule, budget or scope are fed back into the planning and executing phases so that any changes are accounted for and absorbed, ensuring that the project will meet its deliverables. Documenting ensures that all project team members and management have a full record of the execution phase of the project. 3.2.4. Project Closing The closing phase of the project includes formal acceptance of the nursery system, administrative activities associated with the Page 4 of 117
  • 14. Writing Documentation That Works Project Communication Management end of the project, and the preparation of reports for stakeholders and the wider community. 3.3. Integrated Change Control Integrated change control will be performed in this project. Any change requests will be considered by a Change Control Committee, consisting of the project manager, project sponsor, and key stakeholders such as the head of the ANU BioSolar program. Any change will be considered in the light of its impact on project schedule, cost, quality and overall potential improvement of the Nursery System. All rejected and approved changes, and the reasons for rejection or approval, will be documented in a Change Management document, which, together with the original scope statement, will form the project scope baseline. For more detail about integrated change control, please see section 4.5. Page 5 of 117
  • 15. Writing Documentation That Works Project Communication Management 4. Project Scope Management The scope of this project is described below. It has been compartmentalized into the following areas: initiation; planning; definition; verification and change control. 4.1. Initiation The project has been authorized by Dr. Walter Fernandez as a part of the bio duel solar energy program. The reason for its authorization is the ultimate need of an automated system for the early cultivation of algae before pouring it to the large ponds. The business need that this project has been developed is to automate the process of early cultivation algae in the nursery considering all of the factors that affect the cultivation. This is important to the industry because it will minimize the human effort. In its early stages, micro-algae need to be carefully cultivated to ensure it does not die. The micro-algae are sensitive to fluctuations in water quantity, temperature, light, pH and nutrients. The survival of the micro-algae in its early stages is vital to ensuring commercial production of the micro-algae later. This is the plan for the initial planning phase of the project, it is anticipated that once the project enters execution phase a new or modified plan will be established updating the various changing criterion. The main purpose of the project is to automate the process of micro algae early cultivation that helps in the production of bio fuel. 4.1.1. Product Description The product that will be produced at the end of this project will be a nursery system that can be supplied to any where required. The nursery system will consider all the important factors that affect the cultivation of algae and its quality i.e., temperature, pH and nutrients etc. The nursery system will consist of number of tanks with different sizes. Since, algae grow initially in smaller tanks and then need a large area to cultivate; nursery system will monitor and control the flow of algae in these tanks with considering the factors affecting it. Page 6 of 117
  • 16. Writing Documentation That Works Project Communication Management 4.1.2. Strategic Plan This project is congruent with the strategic plan and long- term objectives of the organisation. This is reflected particularly strongly by the will to enter the bio fuel production markets. 4.1.3. Project Selection Criteria This project has been selected because there was a severe need of an automated system to control the flow of algae in the early cultivation of algae. This project is also an integral part of the overall bio fuel solar energy program to assist the production of bio fuel. The product of this project is a nursery system that can be transferred to anywhere it is required and control the early cultivation of algae. Page 7 of 117
  • 17. Writing Documentation That Works Project Communication Management 4.2. Scope Planning 4.2.1. Product Description For a description of the product of this plan, please refer to topic 4.1.1. 4.2.2. Project Charter • The Business Need The business need of the system is to minimize the amount of human effort in the early cultivation of algae. This is important to the business because large number of human efforts require large amount of money. With the automated system human effort will be decreased and this system will be one time investment. • Product Description The product that will be produced at the end of this project will be a nursery system that can be supplied to anywhere required. The nursery system will consider all the important factors that affect the cultivation of algae and its quality i.e., temperature, pH and nutrients etc. The nursery system will consist of number of tanks with different sizes. Since, algae grow initially in smaller tanks and then need a large area to cultivate; nursery system will monitor and control the flow of algae in these tanks with considering the factors affecting it. • Product Manager The project manager for this project is to be Mr. XYZ. XYZ will have the full authority over the budget and resources allocated to this project. No further seeking of resources will be accepted unless it is presented by XYZ. • Constraints Page 8 of 117
  • 18. Writing Documentation That Works Project Communication Management • Budgets and time • Availability of Human Resources • Assumptions It is assumed that: • There will be constant easy access to the Program Director; • Bio fuel will not be superseded by another type of technology before production begins; • No member of the project team will leave the team before the end of the project. 4.3. Scope Definition 4.3.1. Scope Statement The scope of the project is to develop a project management plan for nursery system project. The Nursery System Project Management Plan will provide a project plan for the development of a Nursery System which can be exported anywhere around Australia. The business need of the system is to minimize the amount of human effort in the early cultivation of algae. Page 9 of 117
  • 19. Writing Documentation That Works Project Communication Management 4.3.2. Work Breakdown Structure (WBS) Please, refer to Appendix F – WBS. 4.4. Scope Verification This section seeks to identify the critical success factors and evaluation of those factors upon delivery of the strategic plan to the stakeholders. 4.4.1. Critical Success Factors There are number of critical success factors that will decide whether the project has been successfully completed. They are described as follows: 1. The nursery system is completed meeting all the required specifications; 2. The project is completed in a time as was planned; 3. The nursery system is in a working condition with ease; 4. It is easy to train a person with all the functional & technical specification of the system; and 5. The system meets all of the quality standards as were planned. 4.4.2. Evaluation Measures Stakeholders can check the quality by deploying the prototype system on a small scale. The output of the system can be analyzed. After testing the prototype system, the system will be deployed on the production site where the output can be further analyzed. After testing this, stakeholders can decide whether system is meeting all of the requirements or is it missing few of the features as planned. Page 10 of 117
  • 20. Writing Documentation That Works Project Communication Management 4.5. Scope Change Control This section defines how planning and management of changes to the scope, via change request, is carried out. This section also details how any scope management plans; corrective actions and lessons learnt documentation should be completed. 4.5.1. Scope Changes Any change requests will be considered by a Change Control Committee, consisting of the project manager, project sponsor, and key stakeholders such as the head of the ANU BioSolar program. Any change will be considered in the light of its impact on project schedule, cost, quality and overall potential improvement of the Nursery System. All rejected and approved changes, and the reasons for rejection or approval, will be documented in a Change Management document, which, together with the original scope statement, will form the project scope baseline. For any change requests that come during the project, a proper path of communication will be required to communicate the change to the respective authority. The request must include the strong justification and grounds for implementing the change. The request should be submitted to and approved by the project manage. If the project manager feels that this change request is of any worth, then he may approve it and forward to the program manager. Both project and program managers will reserve the right to contest the change based on practicalities and delays caused, costs incurred and quality effects. Once approved, the requested changes will be integrated in to the project plan, which will be disseminated to each stakeholder, including the effects on costs, timeliness and quality. The base line should remain the same and the changes should be mentioned separately. 4.5.2. Corrective Action Where a scope change request has been submitted and approved, the following corrective actions shall apply. Page 11 of 117
  • 21. Writing Documentation That Works Project Communication Management 1. It will be integrated into the project plan in a separate section; 2. New costs, timeframes and quality effects will be detailed; 3. All new tasks will be integrated into the WBS and assigned; 4. All cost increases will be factored into phasing and overall budgets; and 5. The scope verification adapted to suit new deliverables. If there is any change or delay in the timeline, which is not caused by any scope change, it has to be reported to the project manager. The program manager has to be informed about this delay by project manager. If the delay can be recovered through additional hours, the overtime can be paid to the employees who will work on it. In the event of a major delay, a corrective action report (CAR) will be created giving options of how to proceed. This will include the amount required to get back on time, the quality drop that will be required to get back on time or the time that will be lost. This will be disseminated to the program manager and internal stakeholders. 4.5.3. Documentation All changes, the efforts required to work on those changes and the communication done for the change requests are to be documented and approved by the project manager. The documentation has to be shared on Google Docs so that the whole project team has access on it. (Refer to Project Communications Plan for further description.) Page 12 of 117
  • 22. Writing Documentation That Works Project Communication Management 5. Project Time Management This section describes all the strategies that have been adopted to manage the time, which affects one of the most important aspects of a project, i.e. Schedule. The section will start from the activity definition, continue with defining the duration of activities, the resources used in the activities, schedule development and will end with explaining how to manage control the time management process in schedule control section. 5.1. Activity Definition Please see below the activity list for this project. All constraints and assumptions are listed in the project charter, in the scope initiation section (4.1.1). Please, refer to the Appendix A – Project Gantt chart, Appendix F – WBS and Appendix G – WBS Dictionary. 5.2. Activity Sequencing We have used Network diagram to show sequencing of activities. Network diagram is a schematic display of the logical relationships among, or sequencing of, project activities. Please, refer to the Appendix A – Project Gantt Chart. Page 13 of 117
  • 23. Writing Documentation That Works Project Communication Management 5.3. Activity Duration Estimating The Work Breakdown Structure contains the times that have been estimated, as shown below. 5.3.1. Basis of Estimates This is a list of further assumptions that were taken during development of the estimates. • The number of human resources is assumed. • Raw material can be supplied without any interruption. • Feed of preliminary design and prototype will be provided on time. 5.4. Schedule Development This section details the start and finish dates and how to manage the timelines for the project. The schedule assumes that the standard hours of the project are 8 hours per day 5 days per week, excluding public holidays. 5.4.1. Project Schedule To view the project schedule, please refer to the Gantt chart attached in Appendix A – Project Gantt Chart. 5.4.2. Schedule Management Plan If there is a schedule change or a delay in any specific task is identified before the activity becomes late, the project manager is to reallocate the necessary resources according to the changes that have occurred. The Project Manager should investigate why there was a delay going to happen. If it’s because of the resources that were assigned to the activities, necessary action should be taken against them. Page 14 of 117
  • 24. Writing Documentation That Works Project Communication Management 5.4.3. Resource Requirement Update In the event of corrective actions being approved by the Project Manager, where there are cost or resource implications, these are to be tracked and included in the budget. This will be done by formal notification to the project accountant via email and followed up in writing. If there is an issue with the number of required resources, Project Manager should try to fill the space as soon as possible. 5.4.4. Constraints and Assumptions The constraints on this section include standard hours to be worked, because it limits the ability of workers to complete tasks by their allotted time. Assumptions • The number of required employees will always be available on time throughout the project. • The attendance of the employees will remain constant. • No employee will resign during the project. • There will be no significant and unrecoverable ‘lags’ in the proposed schedule. 5.5. Schedule Control 5.5.1. Schedule Updates A schedule update is considered to be anything that changes the start or finish time of another work activity down to the level three tasks. These include any level four tasks or below that affect higher-level tasks. To assist in schedule management once a task is complete, the WBS will be updated via the online software. In addition, the person in control of completing the work activity is to advise the project manager and anyone whose task it will affect. The updated WBS will be saved as a new name with updated date as well. In that way, it would be easy to keep track of the changes and updates. Page 15 of 117
  • 25. Writing Documentation That Works Project Communication Management 5.5.2. Corrective Actions In the event of a completion time that will affect another task either by allowing it to start earlier or forcing it later, a formal schedule update request must be submitted to the project manager with a corrective actions proposal including an estimated cost of any such proposal. If accepted by the project manager – with no corrective actions available – they will notify the project sponsor, program manager and any relevant internal and external stakeholders. In addition, the project manager will inform the other team members affected about the change to schedule and seek any possible corrective actions from that work group to get the project back on time. Page 16 of 117
  • 26. Writing Documentation That Works Project Communication Management 6. Project Cost Management Cost is one of the Triple Constrains of a project. To create a successful project, project manager must have a comprehensive consideration of the cost to achieve the project goals, any cost overestimate and underestimate may ruin the project during the project life cycle. This cost management plan serves to effectively and efficiently allocate resources for development of a strategic plan for developing a prototype of a nursery system with the capacity to cultivate 450 litres of algae for the Bio-fuel program. The range of the total cost of the project would be +/-10% of the estimate cost ($306360), which is between $275724 and $336996. As a best practice guide PMBOK recommends the Project Cost Management processes include the following: • Resource Planning • Cost Estimating • Cost Budgeting • Cost Monitoring, Controlling and reporting 6.1. Resource Planning Core resources determination is explicitly based on the Work Breakdown Structure (WBS) and the project scope statement presented in the project scope management section. Other resources, such as the office supplies, transportation and utilities etc, which are not directly related to the nursery system but indirectly related to the performance of the project, are included in the General and Administrative charges (G&A). Page 17 of 117
  • 27. Writing Documentation That Works Project Communication Management 6.1.1. Resource Requirement The resource requirement table below presents the summary of core resources in quantity, type, and quality needed to efficiently develop the nursery system. The requirements of the job positions are stated in this table, while the descriptions of the job positions are presented in Human Resource Management Plan in details. The allocation and the cost of the resources at the WBS levels are presented in the cost estimate section. Table 6.1.1. Resource Requirement Table Resource Name Hrs Resource Description/Requirements Labour     Project Manager 512 1. More than five years of Project management experience as well as be PMI certified. 2. Strong planning, motivation and communication skills. Senior Engineer/Analyst 1496 1. Master degree in biology science and/or engineering. 2. At least five years recent specialized experience. Junior Engineer/Analyst 2 888 1. Bachelor degree in biology science and/or engineering. 2. At least two years recent specialized experience. Junior Engineer/Analyst 1 584 Accountant 320 1. At least three years accounting experience, the majority of which should have been in a project related environment. 2. Computer literacy with experience in MSWord, excel. 3. Must be able to work independently and meet deadlines in a team environment. Technician 1 440 1. Relevant tertiary qualifications in biologyTechnician 2 440 Page 18 of 117
  • 28. Writing Documentation That Works Project Communication Management science or/and engineering 2. At least two years experience in biology-related Technician 3 360 Technician 4 360 Procurement Specialist 1640 1. A purchasing certification is preferred. 2. A minimum of two years working in a general buying environment. 3. Considerable knowledge of purchasing methods and procedures and of the techniques of specification writing. ANU expert 20 Provide suggestions and solve the technical problems at technical level. Hardware     Desktop PC 10 Each PC will be assigned to each employee PC Model: HP Pavilion P6325A I3- 540 Pc or at the equivalent level. Printers 5 Model: Samsung CLP315 Colour Laser Printer or at the equivalent level. Coulter Counter 1 Estimate the culture density of the algae. Fluorescent Tubes 3 Artificial illumination to optimize growth. Immersion Heater 4 2400 watt, 240 volt immersion heater to control the temperature for cultivating the algae at different stage. Pines and Hoses 5 Transfer the algae from small tanks to large tanks. Air Filter 4 Filters for air supply to prevent contamination. Tanks 4 Used to contain the growing algae, the sizes of the tanks are 250ml, 250ml to 4l, 4l to 20l, 50l, respectively. Materials     Fertilizers Nutrient Media 500 Fertilizer nutrients such as nitrogen, phosphorus, potassium and carbon source are needed to cultivate algae in the nursery system. Page 19 of 117
  • 29. Writing Documentation That Works Project Communication Management Glassware 5 Contain the sample of the algae cultures. 6.2. Cost Estimating Commonly used tools and techniques to assist in creating a cost estimate include analogous cost estimating, bottom-up estimating, parametric modelling, resource cost rates, project management software, vendor bid analysis and reserve analysis (Kathy Schwalbe, 2007).In this project, cost estimations are created using bottom-up estimates and based on the market prices for goods and services in the Australian economy and the Australian most popular job site SEEK.COM pay check survey. Every individual work items or activities in the WBS are allocated a cost and summed to get the higher level total. When creating cost estimations and allocating costs to resources requirements, significant consideration is given to uncertainties such as major scope changes and extraordinary events. A 5% contingency reserve (estimated by predetermined guidelines and the risk level of the nursery system) is created to allow for future situations that may be partially planned for, and a 5% management reserves is set to allow for future situation that are unpredictable. Hence the budget is therefore flexible to cater for any uncertainties and the budget itself forms the cost control mechanism (Meredith J. and Mantel S, Jr. 2006). Table 6.2. Project Cost Estimates Notes: 1. General & Administrative charges (G&A) are calculated as 10% of the total cost of the core resources. 2. The project manager is assigned to complete several specific WBS activities in the project while he/she is managing the whole project, and all the labour costs of the project manager are calculated in the project management level. Page 20 of 117
  • 30. Writing Documentation That Works Project Communication Management WBS activities Resources Name Unit/hr Cos t/uni t/hr Subtotal s WBS level 1 totals % of the total Project management         54681 17.85%   Project Manager 512 55 25960     project Accountant 320 40 12800     Desktop PC 10 800 8000     Printers 5 150 750     G&A charges     4971     Initiating         3344 1.09% Identify key stakeholders Project Manager 8 NA 0     Hold project kick-off meeting Project Manager 8 NA 0     Senior Engineer/Analyst 8 40 320     Junior Engineer/Analyst 1 8 30 240     Junior Engineer/Analyst 2 8 30 240     Review Scope Project Manager 56 NA 0     Senior Engineer/Analyst 56 40 2240       G&A charges     304     Planning         90640 29.59% Hold team planning meeting Senior Engineer/Analyst 40 40 1600     Prepare team contract Project Manager 40 NA 0     Gather functional requirements Junior Engineer/Analyst 1 120 30 3600     Junior Engineer/Analyst 2 120 30 3600     Gather technical requirements Junior Engineer/Analyst 1 120 30 3600     Junior Engineer/Analyst 2 120 30 3600     ANU experts 20 50 1000     Verify requirements Senior Engineer/Analyst 56 40 2240     Review of Sensors Junior Engineer/Analyst 40 30 1200     Page 21 of 117
  • 31. Writing Documentation That Works Project Communication Management used 1 Junior Engineer/Analyst 2 40 30 1200     Review of the system logic Junior Engineer/Analyst 1 40 30 1200     Junior Engineer/Analyst 2 40 30 1200     Review communicati ons environment Junior Engineer/Analyst 1 40 30 1200     Junior Engineer/Analyst 2 40 30 1200     Review geographic factors Junior Engineer/Analyst 1 56 30 1680     Junior Engineer/Analyst 2 56 30 1680     Review of baseline Senior Engineer/Analyst 40 40 1600     Identify sensors to use Junior Engineer/Analyst 1 40 30 1200     Junior Engineer/Analyst 2 40 30 1200     Identify new system logic Junior Engineer/Analyst 2 40 30 1200     Junior Engineer/Analyst 1 40 30 1200     Identify communicati ons consideratio ns Junior Engineer/Analyst 1 40 30 1200     Junior Engineer/Analyst 2 40 30 1200     Identify mitigation of geographic factors Junior Engineer/Analyst 1 40 30 1200     Junior Engineer/Analyst 2 40 30 1200     Identify target areas for improvement Junior Engineer/Analyst 1 40 30 1200     Junior Engineer/Analyst 2 40 30 1200     Page 22 of 117
  • 32. Writing Documentation That Works Project Communication Management Define system requirements Senior Engineer/Analyst 160 40 6400     Define target performance metrics Senior Engineer/Analyst 48 40 1920     Hardware vendors Procurement Specialist 40 30 1200     Coulter Counter 1 200 00 20000     Fluorescent Tubes 3 20 60     Immersion Heater 4 100 400     Pines and Hoses 5 60 300     Air Filter 4 100 400     Tanks 4 100 0 4000     Communicati ons vendors Procurement Specialist 40 30 1200     Design partners Procurement Specialist 40 30 1200     Implementati on partners Procurement Specialist 64 30 1920       G&A charges     8240     Executing         75922 24.78% Draft preliminary design documents Senior Engineer/Analyst 240 40 9600 Preliminary hardware design Senior Engineer/Analyst 80 40 3200     Preliminary communicati ons design Senior Engineer/Analyst 80 40 3200     Preliminary support environment design Senior Engineer/Analyst 80 40 3200     Review preliminary design documents Senior Engineer/Analyst 40 40 1600     Project Manager 40 NA 0     Obtain feedback/inp ut on design Project Manager 40 NA 0     Senior Engineer/Analyst 40 40 1600     Review of design based on feedback Senior Engineer/Analyst 40 40 1600     Junior Engineer/Analyst 1 40 30 1200     Junior Engineer/Analyst 40 30 1200     Page 23 of 117
  • 33. Writing Documentation That Works Project Communication Management 2 Develop detailed hardware design Project Manager 40 NA 0     Develop detailed support environment design Project Manager 40 N A 0     Align long/short term design with business goals Project Manager 80 NA 0     Senior Engineer/Analyst 80 40 3200     Procure Materials Procurement Specialist 120 30 3600     fertilizers nutrient media(ml) 500 NA 1000     glassware 5 20 100     Construct Prototype Technician 1 96 40 3840     Technician 2 96 40 3840     Technician 3 96 40 3840     Technician 4 96 40 3840     Test Prototype Junior Engineer/Analyst 2 80 30 2400     Junior Engineer/Analyst 1 80 30 2400     Evaluate Prototype against requirements Senior Engineer/Analyst 40 40 1600     Make adjustments to prototype as needed Technician 1 40 40 1600     Technician 2 40 40 1600     Re-Test prototype Junior Engineer/Analyst 1 40 30 1200     Junior Engineer/Analyst 2 40 30 1200     Senior Engineer/Analyst 40 40 1600     Review deployment team tasks and timeline Senior Engineer/Analyst 24 40 960     Project Manager 24 NA 0     Communicat e impact to Project Manager 24 NA 0     Page 24 of 117
  • 34. Writing Documentation That Works Project Communication Management community Test Nursery System Senior Engineer/Analyst 24 40 960     Junior Engineer/Analyst 1 24 30 720     Release to production/o perations environment Senior Engineer/Analyst 24 40 960     Obtain feedback Junior Engineer/Analyst 1 24 30 720     Prepare user manual Junior Engineer/Analyst 1 24 30 720     Junior Engineer/Analyst 2 24 30 720       G&A charges     6902     Monitoring and controlling         42416 13.85% Conduct weekly progress meetings Project Manager 0 NA 0     Document problem - tracking procedures Senior Engineer/Analyst 16 40 640     Manage contracts with suppliers Procurement Specialist 1264 30 37920       G&A charges     3856     Closing         11616 3.79% Prepare final project report Senior Engineer/Analyst 40 40 1600     Project Manager 40   0     Document lessons learned Junior Engineer/Analyst 2 80 30 2400     Junior Engineer/Analyst 1 80 30 2400     Senior Engineer/Analyst 80 40 3200     Distribute to team members Senior Engineer/Analyst 24 40 960       G&A charges     1056     Page 25 of 117
  • 35. Writing Documentation That Works Project Communication Management Reserves         27620 9.06% Management reserves     13809.9 5     Contingency reserves       13809.9 5     Total         306360 100.00% 6.3. Cost Budgeting Project cost budgeting involves allocating the project cost estimate to individual work items over time. The main goal of the cost budgeting process is to produce a cost baseline for measuring project performance and project funding requirements. Based on the cost estimations, the following project budget baseline is planned to fully implement the project from initiation to completion. The budget allocated in each month includes labour cost, the cost of hardware and materials that are expected to incur in that month. The office supplies, such as printers, desktop PC are depreciated using straight-line method in the whole project life at the project management level. The costs of other equipments, such as coulter counter, immersion heater, etc, which are directly related to the development of the nursery system are depreciated into the actual months of their corresponding WBS activities. Please, refer to Appendix B - Table 6.3. Project Cost Baseline. 6.4. Cost Monitoring, Controlling and Reporting Deviations from the cost baseline should signify critical cost performance signals of the project. Budget overrun or underutilization should be importantly considered as a major change to the budget (Project Management Institute, 2000). Therefore, a well-disciplined cost monitoring, controlling and reporting system is very important. Project Management Institute (2004) suggests, a Project Manager, when planning for controlling project costs, should take the following items into account: Page 26 of 117
  • 36. Writing Documentation That Works Project Communication Management 1. Influencing the factors that create changes to the cost baseline. 2. Ensuring requested changes are agreed upon 3. Managing the actual changes when and as they occur. 4. Assuring that potential cost overruns do not exceed the authorised funding periodically and in total for the project. 5. Monitoring cost performance to detect and understand variances from the cost baseline. 6. Recording all appropriate changes accurately against the cost baseline. 7. Preventing incorrect, inappropriate, or unapproved changes from being included in the reported cost or resource usage. 8. Informing appropriate stakeholders of approved changes. 9. Acting to bring expected cost overruns within acceptable limits. In addition to the above, it is also recommended that a Project Manager takes into account the following: 1. Thorough planning of the work to be performed to complete the project 2. Good estimating of time, labour and costs 3. Clear communication of the scope of required tasks 4. A disciplined budget and authorization of expenditures. Project accountant plays an important role in ensuring that project costs are being routinely monitored, appropriately controlled and reported in a timely manner. Page 27 of 117
  • 37. Writing Documentation That Works Project Communication Management As such, the following tasks must be performed by the project accountant in the cost control system: 1. Keeping track of project cost performance throughout the project life and conduct budget review in every month, planned milestone and project phase. • Refer to the following appendices for report templates: • Appendix C - Monthly Project Financial Performance Report Template • Appendix D - Life to Date Project Financial Performance Report • Appendix E - Labour Cost Analysis Report Template 1: monthly project financial performance report and; Template 2: Year to date project financial performance report. 2. Detecting and investigate the cause of the variance and make necessary recommendations to the project manager. 3. Ensuring that all appropriate changes are recorded accurately in the cost baseline under the project manager’s approval. Based on the project accountant’s recommendations, the project manager should: 1. Schedule meetings and inform appropriate stakeholders of the changes; ensure that changes to the cost baseline are minimised, authorised and agreed upon by all stakeholders. 2. Rectify the changes and manage actual changes with the agreement of the stakeholders. 3. Distribute modified plans to the stakeholders and the management team. Page 28 of 117
  • 38. Writing Documentation That Works Project Communication Management 6.5. Other considerations The followings are other considerations the project manager and the project accountant should take into account that may lead to the budget out of the range. 1. Resources over-allocation or under-allocation will end up with the delays of the deliverables and the increase of the costs. (Please refer to Human Resource Section for details) 2. As the budget of the project is estimated based on the market prices of the goods and services in Australia, the actual acquisition costs of materials and equipments will vary among vendors that might create the deviation from the estimated costs 3. Contingency reserves will be underestimated in the budget because of misestimating the level of the risks. Page 29 of 117
  • 39. Writing Documentation That Works Project Communication Management 7. Project Quality Management The primary challenge of project management is to achieve the project goals and objectives while adhering to project constraints – usually scope, quality, time and budget (Cline et al, 2010, Schwalbe 2007). Juran (1988) suggests that, 90% of all problems in organisations are systematic and beyond the positive influence of staff. Unfortunately, this also includes issues related to quality (McManus and Wood-Harper, 2007). One of the greatest challenges faced by project managers is to get the process right first time and this means initiating a rigorous quality regime, which is both defined and measureable (McManus and Wood-Harper, 2007). The importance and purpose of Project Quality Management is to ensure that the project will satisfy the needs for which it was undertaken (Schwalbe, 2007). Therefore, having a solid plan to address quality issues in this project is very important and this will help the project team to ensure stakeholders are satisfied with the outputs of this project. 7.1. Scope This document will cover: • Quality Objectives • Quality Policy • Quality Organisational Structure and Responsibilities • Quality Management Process • Other Considerations Page 30 of 117
  • 40. Writing Documentation That Works Project Communication Management 7.2. Quality Objective 1. The final product of this project must be of highest standard, quality, and meets the approved performance specifications and requirements of the ANU’s BioSolar Program. 2. The final product must be flexible and compatible to accommodate any changes and deviations in the cost baseline, time baseline and performance specifications. 7.3. Quality Control In operations management research there are many approaches or standard been recommended to address quality issues in a project management environment. For example, Total Quality Management (TQM) approach, ISO 9000 standard on quality, Project Quality Activity approach and Project Management Planning Quality Model, Capability Maturity Model to name a few (Zwikael and Globerson, 2004; Masters and Frazier, 2007; McManus and Wood-Harper, 2007). Among these, TQM and ISO 9000 standards are found to be the most adopted quality management principles in project management environment. While both of these approaches are very similar it is recommended that this project adopts ISO 9000 principles as a matter of policy in managing project quality related issues. This project policy position is consistent with the overall project management framework principle adopted by the ANU (see http://projects.anu.edu.au/management/index.php, accessed on 15 September 2010). Table 7.3 outlines this policy. Page 31 of 117
  • 41. Writing Documentation That Works Project Communication Management Table 7.3. Quality Management Policy Principles Descriptions 1. Customer focus Understanding current and future customer needs; meet requirement; strive to exceed expectations; and link organisation’s objectives to customer needs 2. Leadership Leaders establish unity of purpose and direction for the organisation. They create the appropriate internal environment. 3. Involvement of People Motivated, committed, and involved people at all levels accept ownership of problems, evaluate their own performance, and freely share information. 4. Process approach Activities and related resources are managed as processes resulting in predictable results and improvement opportunities. 5. Systems approach to management Integrate and align processes; focus effort on key processes; and understand interdependencies, capabilities, and constraints before starting projects 6. Continual Improvement Use a consistent organisation- wide approach to continual improvement to include training in methods, goals to guide, and measures to track. 7. Factual approach to decision making Ensure data and information are accurate, reliable, and accessible; make decisions and take action based upon analysing facts; and challenge opinions and decisions. 8. Mutually beneficial supplier relationships Identify and select key partners; jointly develop and improve with partners; and openly share communication with them. Source: The Australian National University (2008), Course Notes of BUSN7024 – Project Management Principles, Semester 2, 2010. Page 32 of 117
  • 42. Writing Documentation That Works Project Communication Management 7.4. Organisational Structure and Responsibilities The organisational structure to carry out the Quality Management Plan is as follows: Table 7.4. Quality Review and Audit Team Quality Review and Audit Team Job Responsibilities Project Manager 1. Quality monitoring and control review and audit process and arrange audit meetings. 2. Quality policies are implemented throughout the entire project. Project Accountant 1. Ensure that project is on budget and cost associated with quality control is accounted for through critical milestone audit points. 2. Conduct professional audits and report any changes in actual spend or available funds that will affect project quality Senior Project Officer 1. Ensure that quality is maintained at all milestone points 2. Ensure that all critical events and activities are carefully implemented 3. Audit for any deviations, identify cause, and report for corrective actions Senior Project Consultant (Scientist from ANU BioSolar Program) 1. Review project performance against the approved technical performance specification. 2. Provide necessary technical recommendation to the Project Manager and Project Director on quality improvements to ensure the project satisfies its Page 33 of 117
  • 43. Writing Documentation That Works Project Communication Management technical objectives. Page 34 of 117
  • 44. Writing Documentation That Works Project Communication Management Quality Management Process Project Management Body of Knowledge (PMBOK) prescribes three main processes as being quality management process. These are, planning quality, performing quality assurance and performing quality control (PMI, 2004). These are discussed below. 7.4.1. Quality Planning Quality planning involves identifying which quality standards are relevant to the project and determining how to satisfy them (PMI, 2004). PMBOK also recommends that quality planning should be performed in parallel with the other project planning processes (PMI, 2004). As mentioned above in Table 1, the ISO 9000 has been adopted as a matter of policy for this project and this table also provides guidance for the Project Manager as to what needs to be performed during quality planning stage to ensure that Quality Policy (ISO 9000) is adhered to during this project. Researchers in the project management suggests that, by asking probing questions and challenging the assumptions i.e., the validity of estimates and project delivery methods, it is possible to steer a situation towards an environment where either where either the problem does not exist or the objectives can co-exist and hence can be collectively achieved (Gill, 2008). Following this approach the PM can empower each project team member to raise any quality issues that may adversely impact customer satisfaction KPIs. PM then can raise those issues in the Quality Review and Audit Team to resolve them and document the issue and resolution in the Quality Management Plan. This could significantly minimise any potential risk of poor customer satisfaction from project deliverables. Page 35 of 117
  • 45. Writing Documentation That Works Project Communication Management Project scope is an important consideration in planning for project quality management. It is PM’s responsibility to ensure that s/he takes project scope into account in planning and executing project quality management. Project quality planning also involves communicating the correct actions for ensuring quality in a format that is understandable and complete (Schwalbe, 2007). For example, in order to satisfy the first principles of ISO 9000, the Project Manager should carefully document and explain any key performance indicators (KPIs) that may have been given by the customers to the entire project team (including any third party resource provider). This will ensure that customer needs are fully understood by each member of the project team. PMBOK suggests that a quality management plan may be formal or informal, highly detailed or broadly framed, based on the requirements of the project (PMI, 2004). Due to the level of technical complexity that could be involved in executing this project, it is recommended that the quality management plan is prepared is a formal and as detailed plan as practical to ensure the quality policy can be adhered to through out the project. In summary, organisational policies related to quality, the particular project scope statement and product descriptions, and related standards and regulations are all important input to the quality planning process (Schwalbe, 2007) Table 7.5.1 summarises a range of checkpoints, at various WBS levels, that the PM should ensure that the recommendations provided in this quality management plan is adhered to. Table 7.5.1. Quality Management Plan WBS Number Activities Recommendation on Quality Management 1.1 Project Initiating • Project manager must ensure that the project team has the correct information on Project Scope and Project Budget and an approved copy of this Project Management Plan before Project Kick-Off meeting. • In Project Kick-Off meeting, PM must go through the project scope thoroughly and seek feedback from the respective team members to ensure the project scope is clearly Page 36 of 117
  • 46. Writing Documentation That Works Project Communication Management understood by team members. 1.2 Project Planning • Project manager must ensure that performance and process audits are done at all milestone points throughout the project. 1.2.3.3 Verify Technical and Functional Requirement • At this point, Project Manager must ensure that the technical and functional requirements have been reviewed and endorsed by Senior Scientific Consultant. • Report any process and performance deviations to relevant stakeholders and take immediate corrective actions • Obtain sign-off from the Quality Management Committee to ensure project objectives have been catered for in identifying the technical and functional project requirements. 1.2.4 Analysis • Appropriate data analysis methods (qualitative or quantitative) must be used to analyse data through out the project • Data analysis process must be clearly defined and free of personal influences and subjective information • Analysed data must be accurately tabulated and presented for documentation • Adequate funding must be allocated for quality data analysis • Data analysis must be conducted within the planned budget • Any deviation/variance to the cost baseline must be notified and investigated • Corrective actions must be immediately taken to rectify • Sufficient time must be allocated for quality data analysis • Data analysis must be conducted within the planned schedule/time • Any delays/ over-run to the scheduled time must be notified and investigated 1.2.4.2 Review of baseline • Obtain sign-off from the Quality Management Committee to ensure all requirements in Project Scope are achievable within the Project Baseline. • Report any process and performance deviations to relevant stakeholders and take immediate corrective actions • Project Accountant must conduct financial and cost audits at all milestone points throughout the project life • Report any variances from the cost baseline to project manager to take necessary actions • Time/schedule audits must be conducted to ensure that Page 37 of 117
  • 47. Writing Documentation That Works Project Communication Management lower level activities are implemented on time to achieve higher level/ milestone activities • Causes of delays or early execution must be investigated and necessary actions immediately taken to ensure quality 1.2.4.6 Review Current Market Solution Vendors Project Manager should utilize the Project Procurement Plan to ensure quality process is maintained during procurement process. Research on current suppliers and type, kind, quantity, and quality of raw materials is a crucial milestone activity of the project. The research method, type, time allocation, sources of information, and qualifications and skills of research officers are critical for quality research outcome. This high level activity is the core activity of the project; hence, adequate funding and time must be allocated to achieve high performance and quality. Following factors must be addressed and performed during procurement process: • Research problem/area must be properly stated and specifically defined • Research officers must be qualified and have necessary research skills and knowledge • Research must be conducted within the planned budget • Research must be conducted within the planned schedule/time • Appropriate research design, methodology and type must by employed • Genuine and reliable sources of data are used for literature review • Adequate funding must be allocated for quality research outcome • Any deviation/variance to the cost baseline must be notified and investigated • Corrective actions must be immediately taken to rectify • Sufficient time must be allocated for quality research outcome • Any delays/ over-run to the scheduled time must be notified and investigated • Corrective actions must be immediately taken to rectify • 1.3 Executing • Implementation should be according to this Project Management plan Page 38 of 117
  • 48. Writing Documentation That Works Project Communication Management • Implementation process should be according to planned quality procedures and standards • Performance audits/checks must be conducted through meetings at every key milestones or deliverables • Any deviations must be accounted for and sources identified for immediate corrective actions • Adequate funding must be allocated for strategic plan implementation • Implementation process must be executed within the planned budget/costing • Any deviation/variance to the cost baseline must be notified and causes/sources investigated • Corrective actions must be taken immediately rectification • Budget provisions must be made to cater for any contingencies during the course of strategy implementation • Sufficient time must be allocated for strategic plan implementation • Implementation process must be executed within the planned schedule/time • Any delays/ over-runs to the scheduled time baseline must be investigated and identified • Corrective actions must be immediately taken to rectify sources • Time allowance must be made to cater for any changes to the scheduled time baseline 1.4 Monitoring, Controlling and Reporting • Performance audit/risk management committee must be established • Performance audits/checks must be conducted through meetings at every key milestones /deliverables • Any deviations/changes must be accounted for and sources identified for immediate corrective actions • Adequate funding must be allocated for strategic plan implementation reviews • Review process must be executed within the planned budget/costing • Any deviation/variance to the cost baseline must be notified and causes/sources investigated • Corrective actions must be taken immediately rectification Page 39 of 117
  • 49. Writing Documentation That Works Project Communication Management • Sufficient time must be allocated for strategic plan implementation review process • Review process must be executed within the planned schedule/time • Any delays/ over-runs to the scheduled time baseline must be investigated and identified • Corrective actions must be immediately taken to rectify sources • Time allowance must be made to cater for any changes to the scheduled time baseline 7.4.2. Quality Assurance The Quality Review Team should hold regular meeting (either weekly or fortnightly) to address any quality issues related to this project. Figure 7.5.2 outlines the recommended flow of activities to ensure quality is maintained throughout every step of this project. Figure 7.5.2. Quality Assurance Approach Page 40 of 117 Quality Audit and review team Meeting Convened Quality Deviations/Defects in time, cost, and performance specifications identified and thoroughly discussed. Resolutions in according with Quality Management Policy of this project and recommendations adopted and plans made for immediate corrective actions PM to report to stakeholders on critical changes in scope, cost, schedule and performance for approval and resource requirements Approved Quality improvement recommendations and resolutions are implemented by respective project teams Reports on the corrective actions including normal audit reports are ready for the next meeting and communicated to the relevant stakeholders.
  • 50. Writing Documentation That Works Project Communication Management Quality assurance (QA) provides an umbrella for another important quality activity, continuous process improvement (PMI, 2004). Activity and information flows in Figure 7.5.2 hinges on the ongoing fostering of continuous improvement culture and motivation within the project team. By fostering continuous improvement philosophy within the project team will reduce waste of resources and non-value-added activities, which in turn allows processes to operate at increased levels of efficiency and effectiveness. 7.4.3. Quality Control Performing quality control (QC) in a project involves monitoring specific project results to determine whether they comply with relevant quality standards and identifying ways to eliminate causes of unsatisfactory results. Although one of the main goals of quality control is to improve quality, the main outcomes of this process are acceptance decisions, rework, and process adjustments (Schwalbe, 2007). PMBOK recommends that quality control should be performed throughout the project duration (PMI, 2004). There are many general tools and techniques to assist in performing quality control. Table 7.5.3 below provides a brief description of these tools. Page 41 of 117
  • 51. Writing Documentation That Works Project Communication Management Table 7.5.3. Tools of Quality Control Tools / Methods Short Descriptions 1. Cause and Effect Diagram (Fishbone or Ishikawa Diagram) Illustrate how various factors might be linked to potential problems or effects. 2. Control Charts Purpose of Control Chart is to determine whether or not a process is stable or has predictable performance. This may also serve as a data gathering tool. 3. Run Chart This method shows the history and pattern of variation. A run chart is a line graph that shows data points plotted in the order in which they occur. Trend analysis is performed using run charts. 4. Scatter Diagram A scatter diagram shows the pattern of relationship between two variables. This tool allows the quality team to study and identify the possible relationship between changes observed in two variables. 5. Histogram Histogram is bar chart showing a distribution of variables. Each column represents an attribute or characteristic of a problem/situation. 6. Pareto Charts Pareto chart is a specific type of histogram, ordered by frequency of occurrence, which shows how many defects were generated by type or category of identified cause. 7. Flow Chart Flowcharting helps to analyse how problems occur. A flowchart is a graphical representation of a process. While there are many styles of flowchart, all process flowcharts show activities, decision points and the order of processing. 8. Statistical Sampling Statistical sampling involves choosing part of a population of interest for inspection. Appropriate sampling can often reduce the cost of quality control. 9. Inspection An inspection is the examination of a work product to determine whether it conforms to standards. Generally, the results of an inspection include measurements. Inspection can be conducted at any level. 10. Defect Repair Review Defect repair review is an action taken by the quality control department or similarly titled organisation or team to ensure that product defects are repaired and brought into compliance with requirements or specifications. Source: PMI (2004) Page 42 of 117
  • 52. Writing Documentation That Works Project Communication Management The first seven of the tools in Table 7.5.3 are known as “Seven Basic Tools of Quality” (PMI, 2004). Given the nature of this project, it is recommended that the PM uses a combination of the abovementioned approaches to monitor, control and report on quality management related issues. This will allow and benefit the PM to monitor, control and report on both technical and non-technical oriented quality related issues. This project management plan recommends the following approaches/tools to analyse, monitor, report and control quality for this project: • Cause and Effect Diagram • Flow Chart • Run Chart • Inspection • Defect Repair Review 7.5. Other Considerations In addition to the above suggestions and plans provided for good quality planning, quality assurance and quality control, there are several other important issues involved in improving the quality of a project (Schwalbe, 2007). Strong and supportive leadership, understanding the cost of quality, providing a good workplace to enhance quality, and working toward improving the organisation’s overall maturity level in project management can all assist in improving quality. 7.5.1. Quality Cost Monitoring and Reporting The cost of quality is the cost of conformance and non- conformance in meeting the project specification and fitness for use. There are various types of cost of quality that the PM needs to be aware of during the execution of this project. Schwalbe (2007) suggested that the following costs are related quality cost: • Prevention cost • Appraisal cost Page 43 of 117
  • 53. Writing Documentation That Works Project Communication Management • Internal failure cost • External failure cost • Measurement and test equipment cost To control budget, it is strongly recommended that during the execution of this project there is structured and routine reporting and monitoring on quality cost. This will allow PM to take corrective action in a timely manner without compromising quality. 7.5.2. Leadership Quality expert, Joseph M. Juran once (in1945) said, “It is most important that top management be quality minded (cited by Schwalbe, 2007). Indeed, without sincere manifestation of interest in maintaining high standard of quality at the top level management of an organisation, there is high risk in a project in producing poor quality output. For this project to accomplish its objective, it is important that top management must create a culture that embraces quality. 7.5.3. Organisational Influence, Workplace Factors and Quality Research shows that organisational issues can have much greater influence on productivity than the technical environment or superiority (Schwalbe, 2007). As such, the PM of this project should keep in mind factors such as organisational politics. The PM function is to remove political roadblocks and create an environment where negative organisational influence does not adversely impact project quality and objective. 7.5.4. Expectations and Cultural Differences Schwalbe (2007) argues that there are many aspects of quality can be defined and measured, many cannot. She suggests that different project sponsors, customers, users and other stakeholders have different expectations about various aspects of a project. Therefore, it is very important for the PM of this to understand these expectations and manage any conflicts that might occur due to differences in expectations from various stakeholders. Page 44 of 117
  • 54. Writing Documentation That Works Project Communication Management 8. Project Human Resource Management People are the most important asset as they determine the success and failure of organizations and projects (Kathy Schwalbe. 2007). This section is created to assist the project manager in managing human resources effectively; the components of this section are as follows: • Human resource planning • Staff acquisition • Team development • Team management 8.1. Human Resource Planning This human resource plan is created to identify and document project roles, responsibilities, and reporting relationships involved in the project. The Organizational Chart, Roles and Responsibilities Assignments, RACI Chart, Staffing management plan in this plan are used to ensure project success. 8.1.1. Organizational Chart This organizational chart provides an organizational structure to manage the project team members that come from different backgrounds and have different functions in the project. Page 45 of 117
  • 55. Writing Documentation That Works Project Communication Management Note: The positions of Technician 2, Technician 3, and Technician 4 are beneath Technician 1, they are responsible for reporting to Technician 1, and Technician 1 is responsible for reporting to the Project Manager directly. 8.1.2. Roles and Responsibilities Assignment Position descriptions and qualification criteria are essential to select the right people to do the job and ensure all the tasks in the project are assigned to certain people. Table 1.2. Roles and Responsibilities Assignment Project Management Position Responsibilities Qualifications Project Manager  Ensure the Project Team completes the project  1. More than five years of Project Page 46 of 117
  • 56. Writing Documentation That Works Project Communication Management  Develop the Project Plan with the team and manages the team’s performance of project tasks  Secure acceptance and approval of deliverables from the Project Sponsor and Stakeholders  Make sure the project is delivered in budget, on schedule, and within scope. management experience as well as be PMI certified.  2. Strong planning, motivation and communication skills. Project Accountant  Keeping track of project cost performance throughout the project life and conduct budget review in every month, planned milestone and project phase.  Detecting and investigate the cause of the variance and make necessary recommendations to the project manager.  Ensuring that all appropriate changes are recorded accurately in the cost baseline under the project manager’s approval.  At least three years accounting experience, the majority of which should have been in a project related environment.  Computer literacy with experience in MSWord, excel.  Must be able to work independently and meet deadlines in a team environment. Senior Engineer/Analyst  Establishing and maintaining project technical requirements  Directing the technical implementation according to established schedules and budgets  1. Master degree in biology science and/or engineering.  2. At least five years recent specialized experience. Junior Engineer/Analyst 1  Watching day-to-day progress and quality of work, supervising the work as per specification, maintaining quality control records carrying out quality control tests  Assess the requirements of materials like, fertilisers nutrient media, Immersion Heater, and coulter counter etc. for the  Bachelor degree in biology science and/or engineering.  2. At least two years recent specialized experience. Junior Engineer/Analyst 2 Page 47 of 117
  • 57. Writing Documentation That Works Project Communication Management nursery system Technician 2  Constructing and maintaining the works involved to develop the prototype of the nursery system  Top of Form  1. Relevant tertiary qualifications in biology science or/and engineering 2. At least two years experience in biology-related field 3. Excellent communication skills to work in a team. Bottom of Form Technician 3 Technician 4 Technician 1  Same as above, but strong role in supervising the construction of the nursery system and reporting progresses and problems to the project manager   Procurement Specialist  Develop the solicitation document that states the requirements for acquiring of raw material for nursery system.  Develop a Proposal Evaluation Plan for evaluating the proposals to describe the specific evaluation criteria (such as qualifications, methodology for completing the work, references and cost), and the methods that will be used to apply the criteria.  Research and evaluate suppliers based on price, quality, selection, service, support, availability, reliability, production, and distribution capabilities as well as the reputation and history  1. A purchasing certification is preferred.  2. A minimum of two years working in a general buying environment.  3. Considerable knowledge of purchasing methods and procedures and of the techniques of specification writing. 8.1.3. RACI Chart In order to show the position roles to the project stakeholders, we created the RACI Chart to identify the responsibility (R), accountability (A), consultation (C) and informed (I) roles to execute the project. Page 48 of 117
  • 58. Writing Documentation That Works Project Communication Management Project manager Project accountant Senior engineer /analyst Junior engineer /analyst Technician Procurement specialist Design Nursery System R I A C Build Nursery System I &C I R A A A Deployment R I A A C R=Responsibility, only one R per task A=Accountability C=Consultation I =Informed 8.1.4. Staffing Management Plans and Resource Histogram The purpose of the staffing plan below is to make certain the project has sufficient staffs with the right skills and experience to ensure a successful project completion Page 49 of 117
  • 59. Writing Documentation That Works Project Communication Management 8.1.4.1. Resource Histogram The Resource Histogram presents the number of human resources assigned to the project over time. From the chart, the project manager can determine the number of the people needed each month, which he/she can base on to design the staffing plan to acquire the necessary staffs and develop the project team. Page 50 of 117
  • 60. Writing Documentation That Works Project Communication Management 8.1.4.2. Staffing Management Plan After creating the Resource Histogram, the Project Manager is required to prepare the staffing management plan for recruitment; the staffing management plan (Appendix H – Staffing Management Plan) should include the overall staffing approach, the training plan and reassignment plan. 8.2. Staff Acquisition This section sets forth the acquisition strategy, defines the efforts required to implement it to ensure coordination of the project manager and the human resource department to get the right people to fulfil the project’s needs. 8.2.1. Resource Assignment Page 51 of 117
  • 61. Writing Documentation That Works Project Communication Management 8.2.1.1. Staff Pooling Description The staff pooling description table assists the project manager and Human Resource Department in assessing the characteristics of potential staffs and make decisions of hiring staffs. Table 8.2.1.1. Staff Pooling Description Table Employee Name Employee ID Job Title Period required Department Date Characteristic s Performance R (1 5 Previous Experience Personal Interests Personal Characteristics Availability Competencies Proficiencies Overall Assessment Page 52 of 117
  • 62. Writing Documentation That Works Project Communication Management 8.2.1.2. Recruitment Practices During the recruiting, all the staffs must strictly abide by the policies, guidelines and procedures governing staff assignments. Additionally, all the updates to the staffing management plan must be recorded by the project manager. The recruitment gives priorities to current employees in the bio-fuel program. Page 53 of 117
  • 63. Writing Documentation That Works Project Communication Management 8.2.1.3. Project Staff Assigned Based on the needs of the project, staff may be assigned full time, part time, or variably, which is presented in the resource requirement in project time management section. Page 54 of 117
  • 64. Writing Documentation That Works Project Communication Management 8.2.1.4. Project Team Directory The template below is to be used by the project team when taking down details of relevant members and stakeholders. Employee Name Employee ID Role Phone Mobile Fax Email Address 8.3. Team Development The main goal of this team development plan is to help people work together more effectively to improve project performance and achieve the project goals. 8.3.1. Training To ensure all the team members are qualified for the project, they are arranged to take specific training courses based on information from the Roles and Responsibilities Assignments table and the staff pooling description. 8.3.2. Team Building Activities Project manager is recommended to organize team- building activities monthly; the options of team building activities, physical challenges or psychological preference indicators are determined by the performance of the team members and the requirements of the upcoming tasks. 8.3.3. Input to Performance Appraisals The performance reports below are used to evaluate the performance of the team members, as documentation for updates to the human resources management plans. Page 55 of 117
  • 65. Writing Documentation That Works Project Communication Management 8.3.3.1. Employee Self-Evaluation Assessment Self-evaluations help employees measure how they are performing in their job. This assessment form can provide guidance and consistency within our project, to help the Project Manager and Human Resources department to record, track, and report information for the employee evaluation process. This form is required to assess monthly. Template 8.3.3.1. Employee self-evaluation assessment Employee Information Employee Name:        Employee ID:        Job Title:       Date :       Department:       Manager:       Review Period:       To       Goals Describe the goals you had set out to accomplish for this time period: ch goals did you accomplish? Which other objectives did you meet, beyond your stated goals? Which achievements are you most proud of? Which goals did you not accomplish and why not? Risks and Expectations What kind of risks did you take during the time span of this evaluation? What are your expectations for the next evaluation time span? What can your manager do to help you achieve your future goals? What are your goals for the next evaluation? Please be clear and concise Comments Additional Comments: Page 56 of 117
  • 66. Writing Documentation That Works Project Communication Management 8.3.3.2. Employee Performance Review The template below is to assess employees’ performance by their superior (refer to the organizational chart) monthly. Please, refer to Appendix I - Employee Performance Review.xlsx. 8.3.4. Performance Improvements Project management has the responsibility to set up the HR management mechanism to improve employees’ performance. Page 57 of 117
  • 67. Writing Documentation That Works Project Communication Management 8.3.4.1. Improvement in Individual Skills a) Set up reward and recognition system. b) Discuss work and personal issues with employees via e-mail, telephone, or other communication media (refer to communication management plan for details). c) Provide training opportunities to employees who are in need. (Refer to training section.) Page 58 of 117
  • 68. Writing Documentation That Works Project Communication Management 8.3.4.2. Improvement in Team Behaviours a) Keep an issue log to document, monitor, and track issues that needed to solve for the project team to work effectively. b) Organize team-building activities to help employees to understand and value each other’s differences in order to work effectively as a team. (Refer to team building section). 8.4. Team Management Team management is essential in Human Resource Management Plan. The Project Manager is required to do the followings to motivate and manage his/her team members in case changes are requested to the project. a) Have formal or informal conversion with employees regularly; discuss any issue with them when they are in need. b) Record and keep track on all the updates to human resources plans. c) Inform any personnel changes to stakeholders in a timely manner d) Maintain and update the Reward and Recognition System regularly. e) Take corrective or preventive actions to deal with any unexpected event, such as employee leaves the project. Page 59 of 117
  • 69. Writing Documentation That Works Project Communication Management 9. Project Communication Management In order to keep the project activities dynamic between team members and other stakeholders within the project itself, it is mandatory that all communications align perfectly and are up to date. Communications management incorporates methods for collecting, gathering and disseminating communication, as well as information across the internal teams and stakeholders of the project. This documentation will list methods of communication, as well as the technology that will help communication during various tasks where communication is needed. 9.1. Communications Planning Before one is to follow the guidelines for distributing information discussed below, it is important to run skill checks on team members and also stakeholders. This will be used to find the most optimized method of carrying out these communication processes i.e., to find out which software is most commonly used by individual members (this will decrease new learning curves, saves time and increases productivity since they are already familiar with the software). In this project, there is a probability that members will have to work remotely from time to time. Therefore, the team must be flexible in terms of communicating. Although, the guidelines below conjure the recommended method of communication i.e., written or verbal, members are able to make themselves adapt to which of the two methods they prefer to use during a certain situation. Page 60 of 117
  • 70. Writing Documentation That Works Project Communication Management Lastly, along the course of the project, it is expected for the Internet and phone to be the primary channel for conveying information. Fax and postage mails are not to be considered for daily and active communication but are to be used whenever necessary. Domestic or international shipping will be used whenever tangible products, prototypes or deliverables are to be sent. 9.2. Information Distribution The English language is taken into account being the de facto language for all communication and documentation in this project, although, not being the de jure language of communication meaning stakeholders are still able to verbally communicate in other languages beside English. The types of communication that are discussed in this documentation have been divided into either or both dynamic/verbal and/or passive/written communication. Dynamic/verbal communication is when communication is synchronous and happens in real time e.g., talking face to face from one human being to another. Passive/written communication describes communication that happens asynchronously meaning one party is able to reply the opposing party on a different time e.g., sending and replying emails through technological devices. Relating to the previous point made on dynamic and passive communication, this documentation suggests which should be used during a certain task of communication. One should note that dates on which new communication has commenced should be recorded inside the perspective documentation for future reference, not to mention evidence for legal issues if they were to arise. Page 61 of 117
  • 71. Writing Documentation That Works Project Communication Management 9.2.1. Introductions to New Stakeholders and Negotiation Task Method Technology Goal Introducing an existing stakeholder to a new stakeholder Verbal/written communication When introducing an existing member on the team to a new member or a new stakeholder, must notify the existing member in prior to the introduction. It is considered inconvenient for one to meet a new colleague without warning beforehand. • Face to face • Phone/audio/ video/confer ence calls • SMS • Email • Instant Messenger This allows the existing team member to be prepared mentally in order to convey the preferred first impression. Commencing communication/Int roduction with new individuals and stakeholders Verbal/written communication The initial project team must consider good etiquette at all times, particularly, the Project Manager. Greetings should be conveyed politely and with adequate. This is a very crucial task to be completed properly, especially when first impressions are to take place. • Face to face • Phone/audio/ video/confer ence calls • SMS • Email • Instant Messenger The goal to achieve after new communication has started is to allow the mentioned parties to be comfortable with one another. If this is achieved, in return, the parties will have a more relaxed and pleasant environment when communicating. Commencing negotiation Written communication It is a significant issue when one needs to perform negotiation with another human being. Written communication is recommended when a • SMS • Email • Instant Messenger This allows parties to make their own initial statements, ideas and points concisely. Page 62 of 117
  • 72. Writing Documentation That Works Project Communication Management negotiation is to commence. This allows both parties to be concise, exact and follow the concept of brevity when delivering their points. If one prefers to commence a negotiation verbally with another party, one is allowed to as there are no strict restrictions to using this method. Although, a note should be taken to be synoptic but detailed. In return, this allows each party to at least predict a small portion of one another’s favoured decision. Commencing negotiation with individuals from different cultures Written communication It is an even more significant issue when one needs to perform negotiation with another human being coming from a different culture and background. Before making an attempt at this task, it is wise to study and analyse how the particular culture communicates and performs negotiation organically. Thus, one is able to adapt to their environment and dive into natural communication methods. Also ensure to use more common words that most English speakers are familiar with. • SMS • Email • Instant Messenger Beyond the previous task mentioning commencing negotiation in general, written communication is also preferred when communicating with individuals of different cultures and native languages. Written language is better understood by both native and non-native speakers than verbal language due to dialect and accent differences. Page 63 of 117