Raspberry Pi 5: Challenges and Solutions in Bringing up an OpenGL/Vulkan Driv...
Case Study - NSR 2010
1. Case Study - NSR 2010
Colin McCall
All4 Inc.
NCASI 2010 Southern Regional Meeting
Charleston, SC
June 29, 2010
2. Agenda
Overview of Project
PSD Applicability Approach
Review Process and U.S. EPA Involvement
Mill Response and Project Impact
Conclusions
2
3. The Project
Modify recovery furnace:
• DCE to NDCE
Modify combination fuel boiler:
• Upgrades for additional biomass/alternative fuels
• Overfire air improvements
• Steamside efficiency increases
Install new steam turbine generator set and
new cooling tower
3
4. Positive Environmental Aspects
Recovery furnace modifications:
• Low odor conversion
• Eliminates BLOX
• Predicted reductions in SO2, VOC, CO, PM,
PM10, PM2.5, and TRS
Combination fuel boiler modifications:
• Projected decrease in fossil fuel
• Improved combustion efficiency
• Predicted reductions in NOX, CO
4
5. PSD Applicability
Actual-to-projected actual applicability analysis
• Projected actual emissions (PAE) for modified
recovery furnace for all but NOX and PM, potential
to emit (PTE) for NOX and PM
• PAE developed for combination fuel boiler based on
Mill business projections
• PAE for combination fuel boiler excluded emissions
that it could have accommodated during baseline
• PTE for new cooling tower
5
6. PSD Applicability
PSD Assessment:
• Step 1 – Are project emissions increases
greater than significance levels?
• Step 2 – Are net emissions increases greater
than significance levels?
6
7. PSD Applicability
Step 1 results:
• Project increases alone were significant for
NOX, PM, TRS
Step 2 results:
• Net decreases from project eliminated TRS
• Project was a PSD major modification for
NOX, PM
7
8. PSD Application
Key PSD application components:
• BACT for NOX on recovery furnace
• BACT for PM on recovery furnace,
combination fuel boiler, cooling tower
• Air quality modeling demonstration for NOX
resulted in predicted annual impacts below
significant impact level (SIL)
8
9. Application Review
Application submitted late 2009
State agency reviewed and forwarded to
U.S. EPA
Permit was anticipated by early May 2010
U.S. EPA commented in early April
9
10. Application Review
U.S. EPA comments:
• If permit not issued by 4/12/10 application
had to address new 1-hr NO2 standard
• Concern w/excluded emissions that boiler
could have accommodated
10
11. Mill Issues/Approach
Project timing critical date - June 2010
Develop immediate response to U.S. EPA
concerns to expedite permit:
• Determine implications of short-term NOX
impacts
• Revisit use of excludable emissions that the
combination boiler could have accommodated
11
12. Mill Issues/Approach
Short term 1-hour NO2 analysis;
• No SIL, no U.S. EPA guidance
• Short-term project NOX emissions increases
modeled
• Results <10% but >5% of new NAAQS
• Time for full NAAQS study not acceptable
12
13. Mill Issues/Approach
Additional NOX reductions evaluated to:
• Determine impact on short-term model results
• Reduce project NOX increases to below PSD
significance level (<40 TPY)
Resulted in management commitment of
significant $$$ to reduce NOX from
combination fuel boiler
13
14. Mill Issues/Approach
Eliminate use of excludable emissions for
combination fuel boiler analysis:
• Down-sized new turbine generator set
• Incorporated new test data for PM10, PM2.5
and condensables from ICR testing
• Incorporate NOX reduction technology
14
15. Project Status
Revised approach presented to state
agency and support obtained at all levels
Formal update to application submitted
and awaiting U.S. EPA review
15
16. Project Conclusions
No grandfathering – be prepared for new
NAAQS and other requirements (SO2, GHG)
Lack of guidance and tools for new standards
will slow process
Concern for ability to demonstrate
compliance with new NAAQS will force
additional reductions
PSD process under NSR Reform continues to
evolve…
16
17. Questions?
cmccall@all4inc.com
All4 Inc.
2393 Kimberton Road
P.O. Box 299
Kimberton, PA 19442
610.933.5246 x20
www.all4inc.com
17