SlideShare une entreprise Scribd logo
1  sur  17
Case Study - NSR 2010

                       Colin McCall
                            All4 Inc.
NCASI 2010 Southern Regional Meeting
                      Charleston, SC

                       June 29, 2010
Agenda
       Overview of Project
       PSD Applicability Approach
       Review Process and U.S. EPA Involvement
       Mill Response and Project Impact
       Conclusions




2
The Project
       Modify recovery furnace:
        • DCE to NDCE
       Modify combination fuel boiler:
        • Upgrades for additional biomass/alternative fuels
        • Overfire air improvements
        • Steamside efficiency increases
       Install new steam turbine generator set and
        new cooling tower



3
Positive Environmental Aspects
       Recovery furnace modifications:
        • Low odor conversion
        • Eliminates BLOX
        • Predicted reductions in SO2, VOC, CO, PM,
          PM10, PM2.5, and TRS
       Combination fuel boiler modifications:
        • Projected decrease in fossil fuel
        • Improved combustion efficiency
        • Predicted reductions in NOX, CO


4
PSD Applicability
   Actual-to-projected actual applicability analysis
    • Projected actual emissions (PAE) for modified
      recovery furnace for all but NOX and PM, potential
      to emit (PTE) for NOX and PM
    • PAE developed for combination fuel boiler based on
      Mill business projections
    • PAE for combination fuel boiler excluded emissions
      that it could have accommodated during baseline
    • PTE for new cooling tower



5
PSD Applicability
       PSD Assessment:
        • Step 1 – Are project emissions increases
          greater than significance levels?
        • Step 2 – Are net emissions increases greater
          than significance levels?




6
PSD Applicability
       Step 1 results:
        • Project increases alone were significant for
          NOX, PM, TRS
       Step 2 results:
        • Net decreases from project eliminated TRS
        • Project was a PSD major modification for
          NOX, PM




7
PSD Application
       Key PSD application components:
        • BACT for NOX on recovery furnace
        • BACT for PM on recovery furnace,
          combination fuel boiler, cooling tower
        • Air quality modeling demonstration for NOX
          resulted in predicted annual impacts below
          significant impact level (SIL)




8
Application Review
       Application submitted late 2009
       State agency reviewed and forwarded to
        U.S. EPA
       Permit was anticipated by early May 2010
       U.S. EPA commented in early April




9
Application Review
        U.S. EPA comments:
         • If permit not issued by 4/12/10 application
           had to address new 1-hr NO2 standard
         • Concern w/excluded emissions that boiler
           could have accommodated




10
Mill Issues/Approach
        Project timing critical date - June 2010
        Develop immediate response to U.S. EPA
         concerns to expedite permit:
         • Determine implications of short-term NOX
           impacts
         • Revisit use of excludable emissions that the
           combination boiler could have accommodated




11
Mill Issues/Approach
        Short term 1-hour NO2 analysis;
         • No SIL, no U.S. EPA guidance
         • Short-term project NOX emissions increases
           modeled
         • Results <10% but >5% of new NAAQS
         • Time for full NAAQS study not acceptable




12
Mill Issues/Approach
        Additional NOX reductions evaluated to:
         • Determine impact on short-term model results
         • Reduce project NOX increases to below PSD
           significance level (<40 TPY)
        Resulted in management commitment of
         significant $$$ to reduce NOX from
         combination fuel boiler




13
Mill Issues/Approach
        Eliminate use of excludable emissions for
         combination fuel boiler analysis:
         • Down-sized new turbine generator set
         • Incorporated new test data for PM10, PM2.5
           and condensables from ICR testing
         • Incorporate NOX reduction technology




14
Project Status

        Revised approach presented to state
         agency and support obtained at all levels
        Formal update to application submitted
         and awaiting U.S. EPA review




15
Project Conclusions
    No grandfathering – be prepared for new
     NAAQS and other requirements (SO2, GHG)
    Lack of guidance and tools for new standards
     will slow process
    Concern for ability to demonstrate
     compliance with new NAAQS will force
     additional reductions
    PSD process under NSR Reform continues to
     evolve…

16
Questions?


      cmccall@all4inc.com

            All4 Inc.
      2393 Kimberton Road
          P.O. Box 299
      Kimberton, PA 19442
        610.933.5246 x20

        www.all4inc.com




17

Contenu connexe

Tendances

Use of Wind Tunnel Refinements in the Dispersion Modeling Analysis of the Ala...
Use of Wind Tunnel Refinements in the Dispersion Modeling Analysis of the Ala...Use of Wind Tunnel Refinements in the Dispersion Modeling Analysis of the Ala...
Use of Wind Tunnel Refinements in the Dispersion Modeling Analysis of the Ala...
Sergio A. Guerra
 
Greenhouse Gas Tailoring Rule
Greenhouse Gas Tailoring RuleGreenhouse Gas Tailoring Rule
Greenhouse Gas Tailoring Rule
All4 Inc.
 
Harrison_Simbol_Presentation Peer Review 2012
Harrison_Simbol_Presentation Peer Review 2012Harrison_Simbol_Presentation Peer Review 2012
Harrison_Simbol_Presentation Peer Review 2012
Stephen Harrison
 
Design, Permitting and Construction Considerations for Marcellus Shale Gas Co...
Design, Permitting and Construction Considerations for Marcellus Shale Gas Co...Design, Permitting and Construction Considerations for Marcellus Shale Gas Co...
Design, Permitting and Construction Considerations for Marcellus Shale Gas Co...
All4 Inc.
 
What YOU Need to Know About the 1-hour NAAQS Implementation Process
What YOU Need to Know About the 1-hour NAAQS Implementation ProcessWhat YOU Need to Know About the 1-hour NAAQS Implementation Process
What YOU Need to Know About the 1-hour NAAQS Implementation Process
All4 Inc.
 
13 update on nea tdb activities and phase vi priorities zavarin llnl-pres-731735
13 update on nea tdb activities and phase vi priorities zavarin llnl-pres-73173513 update on nea tdb activities and phase vi priorities zavarin llnl-pres-731735
13 update on nea tdb activities and phase vi priorities zavarin llnl-pres-731735
leann_mays
 
BlueScape AB 617 Update, The Community Air Protection Program Draft Blueprint...
BlueScape AB 617 Update, The Community Air Protection Program Draft Blueprint...BlueScape AB 617 Update, The Community Air Protection Program Draft Blueprint...
BlueScape AB 617 Update, The Community Air Protection Program Draft Blueprint...
BlueScape
 
Development of Next Generation Low NOx Combustion Promoters Technical Article...
Development of Next Generation Low NOx Combustion Promoters Technical Article...Development of Next Generation Low NOx Combustion Promoters Technical Article...
Development of Next Generation Low NOx Combustion Promoters Technical Article...
Eric F. Griesinger, P.E., CQE
 

Tendances (20)

The complexities of new source review air permitting – a case study ddix 020116
The complexities of new source review air permitting – a case study ddix 020116The complexities of new source review air permitting – a case study ddix 020116
The complexities of new source review air permitting – a case study ddix 020116
 
LNG Facility GHG Mitigation Options - Government of Nova Scotia
LNG Facility GHG Mitigation Options - Government of Nova ScotiaLNG Facility GHG Mitigation Options - Government of Nova Scotia
LNG Facility GHG Mitigation Options - Government of Nova Scotia
 
LNG proposed standardsNova Scotia Liquefied Natural Gas Proposed Greenhouse G...
LNG proposed standardsNova Scotia Liquefied Natural Gas Proposed Greenhouse G...LNG proposed standardsNova Scotia Liquefied Natural Gas Proposed Greenhouse G...
LNG proposed standardsNova Scotia Liquefied Natural Gas Proposed Greenhouse G...
 
Use of Wind Tunnel Refinements in the Dispersion Modeling Analysis of the Ala...
Use of Wind Tunnel Refinements in the Dispersion Modeling Analysis of the Ala...Use of Wind Tunnel Refinements in the Dispersion Modeling Analysis of the Ala...
Use of Wind Tunnel Refinements in the Dispersion Modeling Analysis of the Ala...
 
Developments Under the Clean Air Act Implications and Ramifications
Developments Under the Clean Air Act  Implications and RamificationsDevelopments Under the Clean Air Act  Implications and Ramifications
Developments Under the Clean Air Act Implications and Ramifications
 
Lessons Learned from the Licensing of Fermi 3 Nuclear Power Plant
Lessons Learned from the Licensing of Fermi 3 Nuclear Power PlantLessons Learned from the Licensing of Fermi 3 Nuclear Power Plant
Lessons Learned from the Licensing of Fermi 3 Nuclear Power Plant
 
Greenhouse Gas Tailoring Rule
Greenhouse Gas Tailoring RuleGreenhouse Gas Tailoring Rule
Greenhouse Gas Tailoring Rule
 
Harrison_Simbol_Presentation Peer Review 2012
Harrison_Simbol_Presentation Peer Review 2012Harrison_Simbol_Presentation Peer Review 2012
Harrison_Simbol_Presentation Peer Review 2012
 
1-Hour SO2 NAAQS Implementation Modeling
1-Hour SO2 NAAQS Implementation Modeling1-Hour SO2 NAAQS Implementation Modeling
1-Hour SO2 NAAQS Implementation Modeling
 
Record of Environmental Consideration for the PCAPP Demilitarization Activi...
Record of Environmental Consideration for the PCAPP Demilitarization Activi...Record of Environmental Consideration for the PCAPP Demilitarization Activi...
Record of Environmental Consideration for the PCAPP Demilitarization Activi...
 
Implications of the New NESHAP/NSPS for the Oil and Gas Sector
Implications of the New NESHAP/NSPS for the Oil and Gas SectorImplications of the New NESHAP/NSPS for the Oil and Gas Sector
Implications of the New NESHAP/NSPS for the Oil and Gas Sector
 
California Air Quality in 2019: What You Need to Know
California Air Quality in 2019: What You Need to KnowCalifornia Air Quality in 2019: What You Need to Know
California Air Quality in 2019: What You Need to Know
 
BlueScape GHG Tailoring Rule Webinar 9-9-10
BlueScape GHG Tailoring Rule Webinar  9-9-10BlueScape GHG Tailoring Rule Webinar  9-9-10
BlueScape GHG Tailoring Rule Webinar 9-9-10
 
Elbashir AIChE 2012 - Visulaization
Elbashir AIChE 2012 - VisulaizationElbashir AIChE 2012 - Visulaization
Elbashir AIChE 2012 - Visulaization
 
Design, Permitting and Construction Considerations for Marcellus Shale Gas Co...
Design, Permitting and Construction Considerations for Marcellus Shale Gas Co...Design, Permitting and Construction Considerations for Marcellus Shale Gas Co...
Design, Permitting and Construction Considerations for Marcellus Shale Gas Co...
 
What YOU Need to Know About the 1-hour NAAQS Implementation Process
What YOU Need to Know About the 1-hour NAAQS Implementation ProcessWhat YOU Need to Know About the 1-hour NAAQS Implementation Process
What YOU Need to Know About the 1-hour NAAQS Implementation Process
 
SECARB Plant Barry CCS Project: Sharing Knowledge & Learning - Presentation b...
SECARB Plant Barry CCS Project: Sharing Knowledge & Learning - Presentation b...SECARB Plant Barry CCS Project: Sharing Knowledge & Learning - Presentation b...
SECARB Plant Barry CCS Project: Sharing Knowledge & Learning - Presentation b...
 
13 update on nea tdb activities and phase vi priorities zavarin llnl-pres-731735
13 update on nea tdb activities and phase vi priorities zavarin llnl-pres-73173513 update on nea tdb activities and phase vi priorities zavarin llnl-pres-731735
13 update on nea tdb activities and phase vi priorities zavarin llnl-pres-731735
 
BlueScape AB 617 Update, The Community Air Protection Program Draft Blueprint...
BlueScape AB 617 Update, The Community Air Protection Program Draft Blueprint...BlueScape AB 617 Update, The Community Air Protection Program Draft Blueprint...
BlueScape AB 617 Update, The Community Air Protection Program Draft Blueprint...
 
Development of Next Generation Low NOx Combustion Promoters Technical Article...
Development of Next Generation Low NOx Combustion Promoters Technical Article...Development of Next Generation Low NOx Combustion Promoters Technical Article...
Development of Next Generation Low NOx Combustion Promoters Technical Article...
 

En vedette

Are You Ready For Your Next Air Quality Facility Inspection?
Are You Ready For Your Next Air Quality Facility Inspection?Are You Ready For Your Next Air Quality Facility Inspection?
Are You Ready For Your Next Air Quality Facility Inspection?
All4 Inc.
 
Four Rules Update
Four Rules UpdateFour Rules Update
Four Rules Update
All4 Inc.
 
Greenhouse Gas Emissions Regulatory Update
Greenhouse Gas Emissions Regulatory UpdateGreenhouse Gas Emissions Regulatory Update
Greenhouse Gas Emissions Regulatory Update
All4 Inc.
 

En vedette (7)

Are You Ready For Your Next Air Quality Facility Inspection?
Are You Ready For Your Next Air Quality Facility Inspection?Are You Ready For Your Next Air Quality Facility Inspection?
Are You Ready For Your Next Air Quality Facility Inspection?
 
Four Rules Update
Four Rules UpdateFour Rules Update
Four Rules Update
 
Greenhouse Gas Emissions Regulatory Update
Greenhouse Gas Emissions Regulatory UpdateGreenhouse Gas Emissions Regulatory Update
Greenhouse Gas Emissions Regulatory Update
 
Techniques for SO2 Designations
Techniques for SO2 DesignationsTechniques for SO2 Designations
Techniques for SO2 Designations
 
Major/Area Source Boiler MACT Rule
Major/Area Source Boiler MACT RuleMajor/Area Source Boiler MACT Rule
Major/Area Source Boiler MACT Rule
 
Mark Wenclawiak All4 GHG PSD Permitting Challenges
Mark Wenclawiak All4 GHG PSD Permitting ChallengesMark Wenclawiak All4 GHG PSD Permitting Challenges
Mark Wenclawiak All4 GHG PSD Permitting Challenges
 
SO2 Data Requirements Rule Modeling Strategies
SO2 Data Requirements Rule Modeling StrategiesSO2 Data Requirements Rule Modeling Strategies
SO2 Data Requirements Rule Modeling Strategies
 

Similaire à Case Study - NSR 2010

Strategic Air Planning: Is the time for a PAL here?
Strategic Air Planning: Is the time for a PAL here?Strategic Air Planning: Is the time for a PAL here?
Strategic Air Planning: Is the time for a PAL here?
All4 Inc.
 
Project Planning and Air Permit Issues
Project Planning and Air Permit IssuesProject Planning and Air Permit Issues
Project Planning and Air Permit Issues
All4 Inc.
 
Integrated Delivery of Supply Chain Solutions_5C Contracts_02-Nov-15
Integrated Delivery of Supply Chain Solutions_5C Contracts_02-Nov-15Integrated Delivery of Supply Chain Solutions_5C Contracts_02-Nov-15
Integrated Delivery of Supply Chain Solutions_5C Contracts_02-Nov-15
Ian Carr SCMP, MCIPS
 
BlueScape EPA Tailoring Rule Permit Strategies 07/29/10
BlueScape EPA Tailoring Rule Permit Strategies 07/29/10BlueScape EPA Tailoring Rule Permit Strategies 07/29/10
BlueScape EPA Tailoring Rule Permit Strategies 07/29/10
BlueScape
 

Similaire à Case Study - NSR 2010 (20)

Strategic Air Planning: Is the time for a PAL here?
Strategic Air Planning: Is the time for a PAL here?Strategic Air Planning: Is the time for a PAL here?
Strategic Air Planning: Is the time for a PAL here?
 
Potential PM2.5 and CPM Pitfalls in Permitting, Testing, and Compliance
Potential PM2.5 and CPM Pitfalls in Permitting, Testing, and CompliancePotential PM2.5 and CPM Pitfalls in Permitting, Testing, and Compliance
Potential PM2.5 and CPM Pitfalls in Permitting, Testing, and Compliance
 
Project Planning and Air Permit Issues
Project Planning and Air Permit IssuesProject Planning and Air Permit Issues
Project Planning and Air Permit Issues
 
Strategic Air Planning: Is the Time for a PAL Here?
Strategic Air Planning: Is the Time for a PAL Here?Strategic Air Planning: Is the Time for a PAL Here?
Strategic Air Planning: Is the Time for a PAL Here?
 
Callide oxyfuel project update
Callide oxyfuel project updateCallide oxyfuel project update
Callide oxyfuel project update
 
Srivastav, Piyush, NAQS Environmental Experts, Crash Course in PSD Permitting...
Srivastav, Piyush, NAQS Environmental Experts, Crash Course in PSD Permitting...Srivastav, Piyush, NAQS Environmental Experts, Crash Course in PSD Permitting...
Srivastav, Piyush, NAQS Environmental Experts, Crash Course in PSD Permitting...
 
Impact of New NSPS and NESHAP Regulations on Oil &amp; Gas Industry
Impact of New NSPS and NESHAP  Regulations on Oil &amp; Gas IndustryImpact of New NSPS and NESHAP  Regulations on Oil &amp; Gas Industry
Impact of New NSPS and NESHAP Regulations on Oil &amp; Gas Industry
 
Sgcp14beckmanncp
Sgcp14beckmanncpSgcp14beckmanncp
Sgcp14beckmanncp
 
4 c nsr presentation 032318 all4 mccall
4 c nsr presentation 032318   all4 mccall4 c nsr presentation 032318   all4 mccall
4 c nsr presentation 032318 all4 mccall
 
Overview of Current Directions in Carbon Capture R&D
Overview of Current Directions in Carbon Capture R&DOverview of Current Directions in Carbon Capture R&D
Overview of Current Directions in Carbon Capture R&D
 
Qatar petroleum presentation
Qatar petroleum presentationQatar petroleum presentation
Qatar petroleum presentation
 
An update on the UK Government's CCS policy, Brian Allison, DECC - UKCCSRC St...
An update on the UK Government's CCS policy, Brian Allison, DECC - UKCCSRC St...An update on the UK Government's CCS policy, Brian Allison, DECC - UKCCSRC St...
An update on the UK Government's CCS policy, Brian Allison, DECC - UKCCSRC St...
 
BlueScape Air Modeling for Non-Modelers: What's Up with the New Ambient Stan...
BlueScape Air Modeling for Non-Modelers:  What's Up with the New Ambient Stan...BlueScape Air Modeling for Non-Modelers:  What's Up with the New Ambient Stan...
BlueScape Air Modeling for Non-Modelers: What's Up with the New Ambient Stan...
 
Webinar: CO2 pipeline infrastructure: Lessons learned
Webinar: CO2 pipeline infrastructure: Lessons learnedWebinar: CO2 pipeline infrastructure: Lessons learned
Webinar: CO2 pipeline infrastructure: Lessons learned
 
Coal Fleet Overview 2010
Coal Fleet Overview   2010Coal Fleet Overview   2010
Coal Fleet Overview 2010
 
Integrated Delivery of Supply Chain Solutions_5C Contracts_02-Nov-15
Integrated Delivery of Supply Chain Solutions_5C Contracts_02-Nov-15Integrated Delivery of Supply Chain Solutions_5C Contracts_02-Nov-15
Integrated Delivery of Supply Chain Solutions_5C Contracts_02-Nov-15
 
BlueScape EPA Tailoring Rule Permit Strategies 07/29/10
BlueScape EPA Tailoring Rule Permit Strategies 07/29/10BlueScape EPA Tailoring Rule Permit Strategies 07/29/10
BlueScape EPA Tailoring Rule Permit Strategies 07/29/10
 
CCS within the UNFCCC - Luke Warren, CCSA
CCS within the UNFCCC - Luke Warren, CCSACCS within the UNFCCC - Luke Warren, CCSA
CCS within the UNFCCC - Luke Warren, CCSA
 
BlueScape Air Quality in 2015: What You Need to Know Webinar 2-10-15
BlueScape Air Quality in 2015: What You Need to Know Webinar 2-10-15BlueScape Air Quality in 2015: What You Need to Know Webinar 2-10-15
BlueScape Air Quality in 2015: What You Need to Know Webinar 2-10-15
 
ELEMENTS OF A ROBUST CARBON CAPTURE, UTILIZATION, AND STORAGE BUSINESS MODEL
ELEMENTS OF A ROBUST CARBON CAPTURE, UTILIZATION, AND STORAGE BUSINESS MODELELEMENTS OF A ROBUST CARBON CAPTURE, UTILIZATION, AND STORAGE BUSINESS MODEL
ELEMENTS OF A ROBUST CARBON CAPTURE, UTILIZATION, AND STORAGE BUSINESS MODEL
 

Plus de All4 Inc.

Plus de All4 Inc. (20)

Impacts of U.S. EPA Region 6 Guidance on CMS Downtime and Data Calculations
Impacts of U.S. EPA Region 6 Guidance on CMS Downtime and Data CalculationsImpacts of U.S. EPA Region 6 Guidance on CMS Downtime and Data Calculations
Impacts of U.S. EPA Region 6 Guidance on CMS Downtime and Data Calculations
 
Implementing a DAHS for Compliance with the Refinery Sector Rule
Implementing a DAHS for Compliance with the Refinery Sector RuleImplementing a DAHS for Compliance with the Refinery Sector Rule
Implementing a DAHS for Compliance with the Refinery Sector Rule
 
NSR Reform Updates
NSR Reform Updates NSR Reform Updates
NSR Reform Updates
 
Tceq recent permitting changes 4 c-2019-f_dougherty (1-31-19)
Tceq recent permitting changes 4 c-2019-f_dougherty (1-31-19)Tceq recent permitting changes 4 c-2019-f_dougherty (1-31-19)
Tceq recent permitting changes 4 c-2019-f_dougherty (1-31-19)
 
All4 impacts of recent u.s. epa region 6 guidance on cms downtime and data ...
All4   impacts of recent u.s. epa region 6 guidance on cms downtime and data ...All4   impacts of recent u.s. epa region 6 guidance on cms downtime and data ...
All4 impacts of recent u.s. epa region 6 guidance on cms downtime and data ...
 
D dix awma conference air toxics evaluation requirements 062718
D dix awma conference air toxics evaluation requirements 062718D dix awma conference air toxics evaluation requirements 062718
D dix awma conference air toxics evaluation requirements 062718
 
All4 inc awma re-entrainment
All4 inc awma re-entrainmentAll4 inc awma re-entrainment
All4 inc awma re-entrainment
 
All4 tcc acit pres ipt guidance 2017
All4 tcc acit pres ipt guidance 2017All4 tcc acit pres ipt guidance 2017
All4 tcc acit pres ipt guidance 2017
 
Air Quality Compliance Training 12-8-16
Air Quality Compliance Training 12-8-16Air Quality Compliance Training 12-8-16
Air Quality Compliance Training 12-8-16
 
CEDRI-NextGen
CEDRI-NextGenCEDRI-NextGen
CEDRI-NextGen
 
understanding the validity and increased scrutiny of data used for compliance...
understanding the validity and increased scrutiny of data used for compliance...understanding the validity and increased scrutiny of data used for compliance...
understanding the validity and increased scrutiny of data used for compliance...
 
CUHMMC Presentation
CUHMMC PresentationCUHMMC Presentation
CUHMMC Presentation
 
Preview of ALL4 Air Quality Compliance - PIOGATech
Preview of ALL4 Air Quality Compliance - PIOGATechPreview of ALL4 Air Quality Compliance - PIOGATech
Preview of ALL4 Air Quality Compliance - PIOGATech
 
Top 5 Environmental Compliance Issues for Engineers and Managers
Top 5 Environmental Compliance Issues for Engineers and ManagersTop 5 Environmental Compliance Issues for Engineers and Managers
Top 5 Environmental Compliance Issues for Engineers and Managers
 
The Good vs. Bad: The Specifics for Validating CMS Data
The Good vs. Bad: The Specifics for Validating CMS DataThe Good vs. Bad: The Specifics for Validating CMS Data
The Good vs. Bad: The Specifics for Validating CMS Data
 
Benzene Fenceline Monitoring: An Introduction and What the Regulations Don’...
Benzene Fenceline Monitoring:  An Introduction and What the Regulations Don’...Benzene Fenceline Monitoring:  An Introduction and What the Regulations Don’...
Benzene Fenceline Monitoring: An Introduction and What the Regulations Don’...
 
The Petroleum Refinery Sector Rule: What’s all the fuss about and what are th...
The Petroleum Refinery Sector Rule: What’s all the fuss about and what are th...The Petroleum Refinery Sector Rule: What’s all the fuss about and what are th...
The Petroleum Refinery Sector Rule: What’s all the fuss about and what are th...
 
US EPA's Electronic Reporting Tool and Compliance and Emissions Data Reportin...
US EPA's Electronic Reporting Tool and Compliance and Emissions Data Reportin...US EPA's Electronic Reporting Tool and Compliance and Emissions Data Reportin...
US EPA's Electronic Reporting Tool and Compliance and Emissions Data Reportin...
 
Curveball Problems for Your Benzene Fenceline Monitoring Program and How to H...
Curveball Problems for Your Benzene Fenceline Monitoring Program and How to H...Curveball Problems for Your Benzene Fenceline Monitoring Program and How to H...
Curveball Problems for Your Benzene Fenceline Monitoring Program and How to H...
 
RACT 2 Review - ALL4
RACT 2 Review - ALL4RACT 2 Review - ALL4
RACT 2 Review - ALL4
 

Dernier

IAC 2024 - IA Fast Track to Search Focused AI Solutions
IAC 2024 - IA Fast Track to Search Focused AI SolutionsIAC 2024 - IA Fast Track to Search Focused AI Solutions
IAC 2024 - IA Fast Track to Search Focused AI Solutions
Enterprise Knowledge
 
CNv6 Instructor Chapter 6 Quality of Service
CNv6 Instructor Chapter 6 Quality of ServiceCNv6 Instructor Chapter 6 Quality of Service
CNv6 Instructor Chapter 6 Quality of Service
giselly40
 
Histor y of HAM Radio presentation slide
Histor y of HAM Radio presentation slideHistor y of HAM Radio presentation slide
Histor y of HAM Radio presentation slide
vu2urc
 
Artificial Intelligence: Facts and Myths
Artificial Intelligence: Facts and MythsArtificial Intelligence: Facts and Myths
Artificial Intelligence: Facts and Myths
Joaquim Jorge
 

Dernier (20)

08448380779 Call Girls In Civil Lines Women Seeking Men
08448380779 Call Girls In Civil Lines Women Seeking Men08448380779 Call Girls In Civil Lines Women Seeking Men
08448380779 Call Girls In Civil Lines Women Seeking Men
 
Bajaj Allianz Life Insurance Company - Insurer Innovation Award 2024
Bajaj Allianz Life Insurance Company - Insurer Innovation Award 2024Bajaj Allianz Life Insurance Company - Insurer Innovation Award 2024
Bajaj Allianz Life Insurance Company - Insurer Innovation Award 2024
 
IAC 2024 - IA Fast Track to Search Focused AI Solutions
IAC 2024 - IA Fast Track to Search Focused AI SolutionsIAC 2024 - IA Fast Track to Search Focused AI Solutions
IAC 2024 - IA Fast Track to Search Focused AI Solutions
 
Exploring the Future Potential of AI-Enabled Smartphone Processors
Exploring the Future Potential of AI-Enabled Smartphone ProcessorsExploring the Future Potential of AI-Enabled Smartphone Processors
Exploring the Future Potential of AI-Enabled Smartphone Processors
 
CNv6 Instructor Chapter 6 Quality of Service
CNv6 Instructor Chapter 6 Quality of ServiceCNv6 Instructor Chapter 6 Quality of Service
CNv6 Instructor Chapter 6 Quality of Service
 
Powerful Google developer tools for immediate impact! (2023-24 C)
Powerful Google developer tools for immediate impact! (2023-24 C)Powerful Google developer tools for immediate impact! (2023-24 C)
Powerful Google developer tools for immediate impact! (2023-24 C)
 
Apidays Singapore 2024 - Building Digital Trust in a Digital Economy by Veron...
Apidays Singapore 2024 - Building Digital Trust in a Digital Economy by Veron...Apidays Singapore 2024 - Building Digital Trust in a Digital Economy by Veron...
Apidays Singapore 2024 - Building Digital Trust in a Digital Economy by Veron...
 
What Are The Drone Anti-jamming Systems Technology?
What Are The Drone Anti-jamming Systems Technology?What Are The Drone Anti-jamming Systems Technology?
What Are The Drone Anti-jamming Systems Technology?
 
Scaling API-first – The story of a global engineering organization
Scaling API-first – The story of a global engineering organizationScaling API-first – The story of a global engineering organization
Scaling API-first – The story of a global engineering organization
 
Factors to Consider When Choosing Accounts Payable Services Providers.pptx
Factors to Consider When Choosing Accounts Payable Services Providers.pptxFactors to Consider When Choosing Accounts Payable Services Providers.pptx
Factors to Consider When Choosing Accounts Payable Services Providers.pptx
 
Advantages of Hiring UIUX Design Service Providers for Your Business
Advantages of Hiring UIUX Design Service Providers for Your BusinessAdvantages of Hiring UIUX Design Service Providers for Your Business
Advantages of Hiring UIUX Design Service Providers for Your Business
 
Workshop - Best of Both Worlds_ Combine KG and Vector search for enhanced R...
Workshop - Best of Both Worlds_ Combine  KG and Vector search for  enhanced R...Workshop - Best of Both Worlds_ Combine  KG and Vector search for  enhanced R...
Workshop - Best of Both Worlds_ Combine KG and Vector search for enhanced R...
 
From Event to Action: Accelerate Your Decision Making with Real-Time Automation
From Event to Action: Accelerate Your Decision Making with Real-Time AutomationFrom Event to Action: Accelerate Your Decision Making with Real-Time Automation
From Event to Action: Accelerate Your Decision Making with Real-Time Automation
 
Histor y of HAM Radio presentation slide
Histor y of HAM Radio presentation slideHistor y of HAM Radio presentation slide
Histor y of HAM Radio presentation slide
 
08448380779 Call Girls In Friends Colony Women Seeking Men
08448380779 Call Girls In Friends Colony Women Seeking Men08448380779 Call Girls In Friends Colony Women Seeking Men
08448380779 Call Girls In Friends Colony Women Seeking Men
 
Axa Assurance Maroc - Insurer Innovation Award 2024
Axa Assurance Maroc - Insurer Innovation Award 2024Axa Assurance Maroc - Insurer Innovation Award 2024
Axa Assurance Maroc - Insurer Innovation Award 2024
 
How to Troubleshoot Apps for the Modern Connected Worker
How to Troubleshoot Apps for the Modern Connected WorkerHow to Troubleshoot Apps for the Modern Connected Worker
How to Troubleshoot Apps for the Modern Connected Worker
 
Artificial Intelligence: Facts and Myths
Artificial Intelligence: Facts and MythsArtificial Intelligence: Facts and Myths
Artificial Intelligence: Facts and Myths
 
A Domino Admins Adventures (Engage 2024)
A Domino Admins Adventures (Engage 2024)A Domino Admins Adventures (Engage 2024)
A Domino Admins Adventures (Engage 2024)
 
Raspberry Pi 5: Challenges and Solutions in Bringing up an OpenGL/Vulkan Driv...
Raspberry Pi 5: Challenges and Solutions in Bringing up an OpenGL/Vulkan Driv...Raspberry Pi 5: Challenges and Solutions in Bringing up an OpenGL/Vulkan Driv...
Raspberry Pi 5: Challenges and Solutions in Bringing up an OpenGL/Vulkan Driv...
 

Case Study - NSR 2010

  • 1. Case Study - NSR 2010 Colin McCall All4 Inc. NCASI 2010 Southern Regional Meeting Charleston, SC June 29, 2010
  • 2. Agenda  Overview of Project  PSD Applicability Approach  Review Process and U.S. EPA Involvement  Mill Response and Project Impact  Conclusions 2
  • 3. The Project  Modify recovery furnace: • DCE to NDCE  Modify combination fuel boiler: • Upgrades for additional biomass/alternative fuels • Overfire air improvements • Steamside efficiency increases  Install new steam turbine generator set and new cooling tower 3
  • 4. Positive Environmental Aspects  Recovery furnace modifications: • Low odor conversion • Eliminates BLOX • Predicted reductions in SO2, VOC, CO, PM, PM10, PM2.5, and TRS  Combination fuel boiler modifications: • Projected decrease in fossil fuel • Improved combustion efficiency • Predicted reductions in NOX, CO 4
  • 5. PSD Applicability  Actual-to-projected actual applicability analysis • Projected actual emissions (PAE) for modified recovery furnace for all but NOX and PM, potential to emit (PTE) for NOX and PM • PAE developed for combination fuel boiler based on Mill business projections • PAE for combination fuel boiler excluded emissions that it could have accommodated during baseline • PTE for new cooling tower 5
  • 6. PSD Applicability  PSD Assessment: • Step 1 – Are project emissions increases greater than significance levels? • Step 2 – Are net emissions increases greater than significance levels? 6
  • 7. PSD Applicability  Step 1 results: • Project increases alone were significant for NOX, PM, TRS  Step 2 results: • Net decreases from project eliminated TRS • Project was a PSD major modification for NOX, PM 7
  • 8. PSD Application  Key PSD application components: • BACT for NOX on recovery furnace • BACT for PM on recovery furnace, combination fuel boiler, cooling tower • Air quality modeling demonstration for NOX resulted in predicted annual impacts below significant impact level (SIL) 8
  • 9. Application Review  Application submitted late 2009  State agency reviewed and forwarded to U.S. EPA  Permit was anticipated by early May 2010  U.S. EPA commented in early April 9
  • 10. Application Review  U.S. EPA comments: • If permit not issued by 4/12/10 application had to address new 1-hr NO2 standard • Concern w/excluded emissions that boiler could have accommodated 10
  • 11. Mill Issues/Approach  Project timing critical date - June 2010  Develop immediate response to U.S. EPA concerns to expedite permit: • Determine implications of short-term NOX impacts • Revisit use of excludable emissions that the combination boiler could have accommodated 11
  • 12. Mill Issues/Approach  Short term 1-hour NO2 analysis; • No SIL, no U.S. EPA guidance • Short-term project NOX emissions increases modeled • Results <10% but >5% of new NAAQS • Time for full NAAQS study not acceptable 12
  • 13. Mill Issues/Approach  Additional NOX reductions evaluated to: • Determine impact on short-term model results • Reduce project NOX increases to below PSD significance level (<40 TPY)  Resulted in management commitment of significant $$$ to reduce NOX from combination fuel boiler 13
  • 14. Mill Issues/Approach  Eliminate use of excludable emissions for combination fuel boiler analysis: • Down-sized new turbine generator set • Incorporated new test data for PM10, PM2.5 and condensables from ICR testing • Incorporate NOX reduction technology 14
  • 15. Project Status  Revised approach presented to state agency and support obtained at all levels  Formal update to application submitted and awaiting U.S. EPA review 15
  • 16. Project Conclusions  No grandfathering – be prepared for new NAAQS and other requirements (SO2, GHG)  Lack of guidance and tools for new standards will slow process  Concern for ability to demonstrate compliance with new NAAQS will force additional reductions  PSD process under NSR Reform continues to evolve… 16
  • 17. Questions? cmccall@all4inc.com All4 Inc. 2393 Kimberton Road P.O. Box 299 Kimberton, PA 19442 610.933.5246 x20 www.all4inc.com 17