SlideShare une entreprise Scribd logo
1  sur  18
Télécharger pour lire hors ligne
TERM PAPER
             OF
          PROJECT
        MANAGEMENT
Project: Nam Con Son Gas Project of British Petroleum, Vietnam

Topic: various controlling procedures, progress control, & project
monitoring system in this project.




Submitted by:                                     Submitted to:
Amit Kumar                                        Ms. Tejbir Kaur
3020070044
RR1709B34
Sec: 1709
Objective of this term paper
The objectives of my term paper are……..


   To get knowledge about the project Nam Con Son project of British
     petroleum, Vietnam.
   What are the various investors investing in this project?
   To study about the various control procedures in a project.
         Various scheduled planning procedures.
         Various cost planning procedures.
         Performance reporting procedures.
         Change control procedures.
   To study about the progress control of the project.
   To study about the monitoring system used in the project.
Nam Con Son Gas Project of British Petroleum,
                       Vietnam

INTRODUCTION TO PROJECT
The Nam Con Son project is Vietnam's largest foreign investment project of $1.3 billion, having
investors like the Vietnam Oil and Gas Corporation (Petro-Vietnam), the UK's BP Group, India's
Oil and Natural Gas Company (ONGC Videsh) and the US's Conoco-Philips. Over the past 14
months, the $1.3 billion Nam Con Son Gas project, operated by BPEOC, has shown outstanding
reliability by meeting almost 100 percent the gas nomination of its customers in the Phu My
power complex in the southern province of Ba Ria-Vung Tau, the largest power complex in
Vietnam so far.


The Project center based in Vietnam needed to update the partners with the latest progress of the
project and accordingly plan/reschedule jobs. The Project partners located at various locations
required to track progress at the earliest and plan or reschedule further progress with immediate
effect. The Project Information was being disseminated through manually printed journals,
generated once in a fortnight, and electronic mails. This method of information dissemination
involved high costs and delayed the planning process.


Various control procedures

      Schedule Planning Procedure: This defines the procedures and responsibilities for
       developing this project baseline schedule. In cooperation with the Project Customer, all
       levels of the project management team are involved in the process of establishing a
       timetable of milestones and activities that will lead to a successful project outcome.
       These following are Schedule Planning procedures:
1. The Project Customer and the Project Manager jointly determine the Baseline Milestones.
        The Project Manager, collaborating with the Project Customer, selects the project
          key events and decision points that constitute the master schedule. Titles,
          definitions and planned dates are determined for each Baseline Milestone.


2. The Project Management & Integrated Planning Division develops the Baseline
   Milestones Schedule.
        Project management & integrated planning division load the Baseline Milestones
          (Level 1 and 2) with their associated planned dates into the Schedule Management
          System forming a Baseline Milestones Schedule.


3. The Project Management & Integrated Planning Division, the Associate Project
   Manager, and the Control Account Manager identify the Intermediate Milestones.
        Based on the defined Baseline Milestones, Project Management & Integrated
          planning division, the Associate Project Manager, and the Control Account
          Manager identify the important Level 3 and 4 milestones of the project.


4. The Project Management & Integrated Planning Division develops the Intermediate
   Milestone Schedule.
        PM&I loads the Intermediate Milestones with their associated planned dates into
          the Schedule Management System forming an Intermediate Milestones Schedule.


 Cost Planning Procedure: The cost planning procedure defines the procedures and
   responsibilities for developing a project cost baseline. With funding guidance from the
   Project Customer, all levels of the project management team are involved in the process
   of producing a project cost estimate. When combined with the project schedule, a timed-
   phase budget will be established against which project performance can be measured.
1. The Project Customer provides funding guidance.
    Based on the desired final product and the expected funding availability, the
         Project Customer will usually provide the Project Manager with a funding profile
         for the project.


2. The Project Manager determines an initial project budget target.
    Taking the funding guidance provided by the Project Customer, the Project
         Manager establishes initial budget targets for the project. With a preliminary BS
         framework, proposed budgets may be prescribed as well as a fiscal year
         breakouts.


3. The Control Account Manager develops the Control Account Plan.
    The Control Account Manager develops an initial Control Account Plan that will
         be used to establish the initial cost estimate.


4. The Associate Project Manager reviews the Control Account Plan.
    The Associate Project Manager reviews the Control Account Plan(s) within his
         area of responsibility. Plans that are not complete are returned to the appropriate
         Control Account Manager for revision. Once satisfactory, the Control Account
         Plan(s) is/are forwarded to the Project Management & Integrated Planning
         Division.


5. The Project Management & Integrated Planning Division reviews the Control Account
Plans.
    PM&I reviews the Control Account Plans to ensure that the project cost estimate
         does not exceed any pre-established funding constraints.


6. The Project Management & Integrated Planning Division establishes the initial cost
estimate.
    The costs from each Control Account Plan are summarized to establish an initial
         cost estimate.
7. The Project Management team reviews and finalizes the cost estimate.
       The Project Management team reviews the consolidated cost estimate for the
          project, and through negotiation, finalize the estimate. The Control Account
          Manager revises the Control Account Plan for each relevant control account based
          on the final negotiated cost estimate for the project.


   8. The Project Management & Integrated Planning Division establishes the cost
      Baseline.
       With approved Control Account Plans, the project cost baseline is established.
          This cost baseline is then integrated with the schedule baseline to produce the
          project Time-Phased Budget.


 Performance Reporting Procedure: This defines the procedures and responsibilities for
   collecting and reporting cost and schedule performance data and analyzing these data to
   assess current and projected future project status. Cost and schedule performance is
   measured and reported monthly for each control account and WBS element, as
   appropriate.


   1. The Project Manager determines the variance thresholds.
       The Project Manager determines the thresholds used to flag variances for each
          control account and WBS element, as appropriate.


   2. The Control Account Manager prepares the Status Update Report.
       At the end of the accounting period, the Control Account Manager reports the
          control account work progress and accomplishments by providing input on the
          Status Update Report.


   3. The Associate Project Manager reviews the Status Update Report.
       The Associate Project Manager validates work activity completions and makes
          assessment of interim progress.
4. The Project Management & Integrated Planning Division determines the Budgeted
   Cost of Work Performed.
    Exporting the data from the Status Update Reports to the Scheduling Management
       System, PM&I calculates BCWP (Earned Value) by summing the budgets of
       work accomplished and completed portions of work in progress for each control
       account.


5. The performing organizations report expenses incurred.
    Performing organizations charge actual costs incurred throughout the reporting
       period using the Jefferson Lab accounting system.


6. The Chief Financial Officer prepares the cost reports.
    The Chief Financial Officer converts time sheets, purchase orders, receipts and
       invoices, travel expense vouchers, and other entry documents into costs and
       commitments for each control account. Labor and cost reports are prepared by the
       Chief Financial Officer and are available to the Control Account Managers and
       Associate Project Managers for review and to Project Management & Integrated
       planning division for entering into the performance database.


7. The Control Account Manager reviews the cost reports.
    The Control Account Manager reviews the cost reports for accuracy and control
       of costs. Unusual or excessive charges are investigated and errors are reported to
       the Chief Financial Officer.


8. The Associate Project Manager reviews the cost reports.
    Each Associate Project Manager reviews actual costs with the Control Account
       Manager directing the effort.
9. The Project Management & Integrated Planning Division prepares the performance
   reports.
    PM&I combines ACWP (Actual Costs) data from accounting, BCWS (Planned
       Value), and Budget At Completion from the Performance Measurement Baseline,
       BCWP (Earned Value) as determined in step 4 above, and Estimate At
       Completion to calculate cost, schedule, and at completion variances. Results are
       published in monthly performance reports (Project Analysis Reports) and charts
       (Earned Value Management Performance Charts/Performance Indicator Charts).
       The Red Flag Report is also generated where significant variances are flagged in
       accordance with the thresholds established by the Project Manager.


10. The Project Management team reviews the Control Account Performance Report.
    The Control Account Performance Report consists of those combined
       performance reports available to the Control Account Manager from the financial
       management system and the schedule/cost management systems. Each Control
       Account Manager reviews the Control Account Performance Report, notes
       variances, and determines reasons for above or below planned performance. Each
       Associate Project Manager reviews the Control Account Performance Reports and
       the technical progress for their area of responsibility and discusses the work, cost,
       and schedule status with the responsible Control Account Manager. The Project
       Manager reviews the all reports and identifies reporting elements of the WBS for
       which formal Variance Analysis Reports are required.


11. The Project Management & Integrated Planning Division issues the Variance
   Analysis Report form.
    PM&I issues a Variance Analysis Report form for each reporting element
       requiring a Variance Analysis Report.
12. The Control Account Manager completes the Variance Analysis Report.
       The Control Account Manager conducts a variance analysis to include the reasons
          for the variances, the anticipated effect on the project cost, schedule or technical
          parameters, and proposed corrective action.


   13. The Project Manager reviews the Variance Analysis Reports with the Control
      Account Managers and Associate Project Managers.
       The Project Manager reviews the Variance Analysis Reports with the Control
          Account Managers and Associate Project Managers to ensure accurate variance
          causes are identified and adequate corrective plans are established. The Variance
          Analysis Report form is signed by the Control Account Manager and the
          Associate Project Manager/Project Manager.


   14. The Project Management & Integrated Planning Division prepares the monthly
      project report.
       PM&I collects all pertinent project performance data and summarizes it for the
          monthly report. PM&I forwards the monthly report, including the revised
          Estimates at Completion, to the Project Manager.


   15. The Project Manager submits the monthly report to the Project Customer.
       The Project Manager reviews the monthly report and submits it to the Project
          Customer.


 Change Control Procedure: The Project Nam Con Son has the approved technical,
   schedule and cost plan for accomplishing all project activities. As the project progresses,
   this baseline may change due to Project Customer redirection, internal replanning, or
   redesign. Changes are classified according to the extent that they impact the Integrated
   Project Baseline. The review process and the approval authority required for a proposed
   change depend upon its classification. This defines the procedures and responsibilities for
   requesting, reviewing, and documenting changes to the Integrated Project Baseline, and
to assure timely implementation of changes once they are approved. The change control
   procedure contains various phases in it. These phases are:
1. Request Phase
   Any project team member may request a change to the technical, schedule, and cost
   baselines by generating a Change Request form and submitting it to a member of the
   Change Control Board for concurrence.
a. The Originator prepares the Change Request.
        The originator prepares the Change Request form in accordance with the
          document instructions. Change Request status at this stage is “New.”


b. The Change Control Board member concurs with the Change Request.
        The originator must then obtain the concurrence of one member of the Change
          Control Board in order for the request to be accepted for consideration. The
          concurring member signs the Change Request in the „Concurrence‟ block.


c. The Change Control Board member initiates the Change Impact Assessment process.
        If the Change Impact Assessment has not been completed on the Change Request
          form, the Change Control Board member assigns actions for analyses of potential
          technical, schedule, cost and quality/safety effects of the proposed change.
          Primary responsibility is typically assigned to a Control Account Manager.


d. The Project Management & Integrated Planning Division enters the Change Request in
   the Change Request Log.
        After Change Control Board member concurrence is obtained, PM&I assigns a
          number (scheme: FY - sequence #, e.g., 05-001) to the Change Request and enters
          it in the Change Request Log as “Open.” PM&I maintains this log as a database,
          updating information each time there is a change to the status of a Change
          Request. For Class 1-2 and Class 3 changes, PM&I distributes the Change
          Request to members of the Change Control Board, and places the Change Request
          on the agenda for the next Change Control Board meeting.
e. The Control Account Manager coordinates inputs to the Change Impact Assessment.

        The assigned Control Account Manager completes the Change Impact
          Assessment. The Change Impact Assessment records the potential impacts of the
          proposed change to the technical, schedule and cost baselines and also to safety
          and quality. The impacts of not approving the change are also documented. The
          Control Account Manager coordinates inputs from relevant parties, such as
          scientists, engineers, contractors, and quality and safety personnel, to document
          these potential impacts. Continuation pages are attached to the Change Request
          form where space is insufficient. Where drawings, specifications, purchase orders,
          Control Account Plans, etc., are affected, changes are marked on copies and
          attached.


f. The Control Account Manager establishes the classification of the Change Request.
        After reviewing the Change Impact Assessment and exhibits, the Control Account
          Manager establishes the Change Request classification. The Control Account
          Manager selects the appropriate class and signs the appropriate block on the
          Change Request form.


g. The Associate Project Manager concurs with the classification of the Change Request.
        The Associate Project Manager reviews the classification assigned by the Control
          Account Manager and, if he concurs, signs the adjacent block.


h. The Project Management & Integrated Planning Division approves the classification of
   the Change Request.
        The PM&I Manager reviews the classification assigned by the Control Account
          Manager and, if he concurs, signs the next block on the Change Request form.
          The classification may also be reviewed and changed by the Change Control
          Board.
2. Review Phase
    After the Change Request has been generated, impacts have been assessed, and an
    approved classification level has been established, it enters the Review Phase where the
    proposed change is evaluated and approved by an appropriate authority. For Class 1-2
    Change Requests that will go to the Project Customer, this will be an external approval
    process. Class 3-5 Change Requests follow an internal approval process.


   External Approval
1. The Project Management & Integrated Planning Division updates the Change Request
Log.
 Once PM&I has approved the classification level, the Change Request enters the Review
    Phase. PM&I monitors the status of Change Requests awaiting action.


2. The Change Control Board evaluates the Class 1-2 Change Request.
 For Class 1-2 Change Requests, PM&I distributes the Change Request to members of the
    Change Control Board and places the Change Request on the agenda for the next board
    meeting. The Change Control Board evaluates the Class 1-2 Change Request package
    and recommends action to the Project Manager.
3. The Project Manager reviews the Class 1-2 Change Request.
 The Project Manager reviews the Class 1-2 Change Request package and Change Control
    Board recommendations. The Project Manager prepares a submission to the Project
    Customer in accordance with customer procedures which may include a Baseline Change
    Control Board. This may include the Change Request as received, with some or all of the
    exhibits, or it may be a letter extracted from the Change Request material with additional
    amplification where necessary.
4. The Project Customer approves/disapproves the Class 1-2 Change Request.
 For Class 1-2 Change Requests, the Project Customer is the final approving authority.
    Approval is indicated by signature in the appropriate 'Final Approval' block on the
    Change Request form. The approved Class 1-2 Change Request package is then returned
    to the Project Manager.


5. The Project Manager reviews the Project Customer Change Request actions.
 The Project Manager reviews the decisions of the Project Customer and documents any
    impacts to the project plans in the Recommendation and Disposition section of the
    Change Request.


6. The Project Management & Integrated Planning Division determines the approval status
    of the Change Request.
 PM&I updates the Change Request Log after the review process has been completed. At
    this stage, the Change Request can be deferred, approved, disapproved or determined to
    be a duplicate of a previously submitted Change Request. Any disapproved CR is sent
    back to the affected Control Account Manager who will consult with the originator to
    determine any further action.


   Internal Approval
1. The Project Management & Integrated Planning Division updates the Change Request
    Log.
 Once PM&I has approved the classification level, the Change Request enters the Review
    Phase. PM&I monitors the status of Change Requests awaiting action.


2. The Change Control Board evaluates the Class 3 Change Request.
 For Class 3 Change Requests, PM&I distributes the Change Request to members of the
    Change Control Board and places the Change Request on the agenda for the next board
    meeting. The Change Control Board evaluates the Class 3 Change Request package and
    recommends action to the Project Manager.
3. The Project Manager reviews the Class 3 Change Request.
 The Project Manager reviews the Class 3 Change Request package and Change Control
   Board recommendations.


4. The Project Manager approves/disapproves the Class 3 Change Requests.
 For Class 3 Change Requests, the Project Manager is the final approving authority.
   Approval is indicated by signature in the appropriate 'Final Approval' block on the
   Change Request form. The approved Class 3 Change Request package is forwarded to
   PM&I.


5. The Associate Project Manager evaluates the Class 4 Change Request.

6. The Associate Project Manager approves/disapproves the Class 4 Change Request.
 For Class 4 Change Requests, the Associate Project Manager is the final approving
   authority. Approval is indicated by signature in the appropriate 'Final Approval' block on
   the Change Request form. The approved Class 4 Change Request package is forwarded to
   PM&I.


7. The Control Account Manager evaluates the Class 5 Change Request.
8. The Control Account Manager approves/disapproves the Class 5 Change Request.
 For Class 5 Change Requests, the Control Account Manager is the final approving
   authority. Approval is indicated by signature in the appropriate 'Final Approval' block on
   the Change Request form. The approved Class 5 Change Request package is forwarded to
   PM&I.


9. The Project Management & Integrated Planning Division determines the approval status
   of the Change Request.
 PM&I updates the Change Request Log after the review process has been completed. At
   this stage, the Change Request can be deferred, approved, disapproved or determined to
   be a duplicate of a previously submitted Change Request. Any disapproved CR is sent
back to the affected Control Account Manager who will consult with the originator to
    determine any further action.


   Documentation Phase
    After the Change Request has been reviewed and approved by the appropriate authority,
    it enters the Documentation Phase where the proposed change is fully documented and
    implemented.

1. The Project Management & Integrated Planning Division issues the Change Order.
 PM&I issues a Change Order for the approved Change Request. The Change Order is a
    completed, approved Change Request.


2. The Associate Project Manager updates the technical documentation.
 Upon receipt of a Change Order, the affected Associate Project Manager ensures any
    relevant technical documentation (drawings, specifications, etc.) is revised.


3. The Project Management & Integrated Planning Division updates the Performance
    Measurement Baseline and Working Detail Schedule.
 PM&I updates the Performance Measurement Baseline, the Working Detail Schedule and
    the associated Earned Value data. Historical EV data will not be revised. To improve
    document traceability, a new project baseline will be generated for each approved
    Change Request.


4. The Control Account Manager implements the approved Control Account Plan.
 The Control Account Manager performs the effort in accordance with the updated
    Control Account Plan.
Project Monitoring System for Nam Con Son Gas Project of British
                       Petroleum, Vietnam

To formulate and sustain the operations of this Gas project operating in 7 geographic locations, a
project monitoring services were required to help to minimize project risk, controlling costs and
providing expert advice on multinational projects. Areas that needed to be covered included
• Permanent milestone monitoring
• Budget control
• Progress Documents management
• Project specialists‟ onsite.


The monitoring system developed in this project is based on the very latest commercial
enterprise detection and correlation technologies adapted to monitor control networks, providing
asset owners with dramatically improved situational awareness. The application has been
conceptualized to increase the visibility about the progress of the Project. The objectives were to:

    1. Meeting the project team requirements
    o What the project is seeking to achieve - the challenge
    o   Who is involved in the project – project organization?
    o How the project is being run - the approach
    o Where the project is being run – map of organization
    o   Monthly progress reporting – schedules and keys measures see below
    o HSE approach – statistics, slogans, awareness etc.
    o Latest news – highlighting people or project developments


    2. Timely process to post Monthly Progress Reports
    o These contain a variety of information: progress against time schedule, key measures
        such as procurement status, approvals status, contract awards and progress or “Scurves”
        current electronic format is a mixture of Excel, Power point & Primavera.


    3. BP A common processes and latest technology applied for Web building, including web
        tools, engines, server instances etc.
4. Simple process for maintenance of the site in the future.


British Petroleum used Virtual Private Network (VPN) as the medium of communication
between its partners except one, who was placed beyond the network. An information base
within the VPN was set which, contained all the project related data, which was sent from the
work sites through a common protocol router shared by the VPN and work site networks. This
data was then electronically published in a HTML format and hosted in a web server which
enabled easy client access through the TCP/IP network protocol .The information base can
contain project data in any format which could automatically be converted to the browser
recognizable MIME. This was collaborated with an online communication component, which
enabled desktop meetings for the managers to track the project progress and reschedule the tasks.
A security system was built into the middle tier to ensure that the data was secure during
transaction, for partners outside the VPN network. The security layer was provided through
encryption. Such data relating to work progress and technology in the Exploration and Projects is
much classified and has a lot of commercial value.


The following benefits will be achieved by implementing the project.
      Bridge the gap between the customer‟s needs and available products
       Use of cutting edge technology to benefit BOYANIKA
       Delivery of best in class services to customers.
      Increase Online Transaction
      Increase customer‟s satisfaction
      Increase productivity
      Reduced operating costs
      Efficient Master data maintenance
      Efficient Event Management
      Increase Access control and security
      Facilitates efficient Market Research
      Centralized Control for Managers
      Efficiency in Decision Making
      Increase profitability
   Balance market competition
   Assured return on investment (ROI)
   Increase Brand Value in terms of quality and quantity.


    BIBLIOGRAPHY
        http://www.bp.com/liveassets/bp_internet/globalbp/STAGING/global_assets/
           V/verfied_site_reports/Middle_east_SE_asia/Vietnam_NCSP_2006_verified
        http://www.csmpl.com/Project%20Monitoring%20System%20for%20Nam
           %20Con%20Son%20Gas%20Project%20of%20British%20Petroleum,%20
           Vietnam

Contenu connexe

Tendances

Europeana Sounds: Project Governance, Reporting and Administration
Europeana Sounds: Project Governance, Reporting and AdministrationEuropeana Sounds: Project Governance, Reporting and Administration
Europeana Sounds: Project Governance, Reporting and AdministrationEuropeana_Sounds
 
Construction Planing & Schedule
Construction Planing & ScheduleConstruction Planing & Schedule
Construction Planing & ScheduleVîñõđ Kůmåř
 
160155061 project-monitoring-control
160155061 project-monitoring-control160155061 project-monitoring-control
160155061 project-monitoring-controleidalin95
 
Construction planning - Construction Technology and Project Management
Construction planning - Construction Technology and Project ManagementConstruction planning - Construction Technology and Project Management
Construction planning - Construction Technology and Project Managementsrinivas2036
 
Planning and Scheduling Construction Projects using Primavera Software A Case...
Planning and Scheduling Construction Projects using Primavera Software A Case...Planning and Scheduling Construction Projects using Primavera Software A Case...
Planning and Scheduling Construction Projects using Primavera Software A Case...ijtsrd
 
Project planning and scheduling
Project planning and schedulingProject planning and scheduling
Project planning and schedulingadeel hamid
 
CPM Scheduling best practicies within the Construction Indistry
CPM Scheduling best practicies within the Construction IndistryCPM Scheduling best practicies within the Construction Indistry
CPM Scheduling best practicies within the Construction IndistryMichael Pink
 
Construction Planning and Scheduling of Residential Building by MS Project by...
Construction Planning and Scheduling of Residential Building by MS Project by...Construction Planning and Scheduling of Residential Building by MS Project by...
Construction Planning and Scheduling of Residential Building by MS Project by...Shabaz Khan
 
Coonce.tom
Coonce.tomCoonce.tom
Coonce.tomNASAPMC
 
Strategic direction of cambodia budget system reform 2013-2020 - Ratanak Hav,...
Strategic direction of cambodia budget system reform 2013-2020 - Ratanak Hav,...Strategic direction of cambodia budget system reform 2013-2020 - Ratanak Hav,...
Strategic direction of cambodia budget system reform 2013-2020 - Ratanak Hav,...OECD Governance
 
Smith.donnie
Smith.donnieSmith.donnie
Smith.donnieNASAPMC
 
Cambodia's perspective on program/performance budgeting - Ratanak Hav - Cambodia
Cambodia's perspective on program/performance budgeting - Ratanak Hav - CambodiaCambodia's perspective on program/performance budgeting - Ratanak Hav - Cambodia
Cambodia's perspective on program/performance budgeting - Ratanak Hav - CambodiaOECD Governance
 
Recent budgeting developments - Sokkheang Lay, Cambodia
Recent budgeting developments - Sokkheang Lay, CambodiaRecent budgeting developments - Sokkheang Lay, Cambodia
Recent budgeting developments - Sokkheang Lay, CambodiaOECD Governance
 

Tendances (20)

Europeana Sounds: Project Governance, Reporting and Administration
Europeana Sounds: Project Governance, Reporting and AdministrationEuropeana Sounds: Project Governance, Reporting and Administration
Europeana Sounds: Project Governance, Reporting and Administration
 
Construction Planing & Schedule
Construction Planing & ScheduleConstruction Planing & Schedule
Construction Planing & Schedule
 
160155061 project-monitoring-control
160155061 project-monitoring-control160155061 project-monitoring-control
160155061 project-monitoring-control
 
Cost value reconciliation (cvr)
Cost value reconciliation (cvr)Cost value reconciliation (cvr)
Cost value reconciliation (cvr)
 
C1 audit planning summary
C1 audit planning summaryC1 audit planning summary
C1 audit planning summary
 
Performing against the wall - SPI after completion
Performing against the wall - SPI after completionPerforming against the wall - SPI after completion
Performing against the wall - SPI after completion
 
Construction planning - Construction Technology and Project Management
Construction planning - Construction Technology and Project ManagementConstruction planning - Construction Technology and Project Management
Construction planning - Construction Technology and Project Management
 
Planning and Scheduling Construction Projects using Primavera Software A Case...
Planning and Scheduling Construction Projects using Primavera Software A Case...Planning and Scheduling Construction Projects using Primavera Software A Case...
Planning and Scheduling Construction Projects using Primavera Software A Case...
 
Project planning and scheduling
Project planning and schedulingProject planning and scheduling
Project planning and scheduling
 
Construction Planning
Construction PlanningConstruction Planning
Construction Planning
 
CPM Scheduling best practicies within the Construction Indistry
CPM Scheduling best practicies within the Construction IndistryCPM Scheduling best practicies within the Construction Indistry
CPM Scheduling best practicies within the Construction Indistry
 
Construction Planning and Scheduling of Residential Building by MS Project by...
Construction Planning and Scheduling of Residential Building by MS Project by...Construction Planning and Scheduling of Residential Building by MS Project by...
Construction Planning and Scheduling of Residential Building by MS Project by...
 
Coonce.tom
Coonce.tomCoonce.tom
Coonce.tom
 
005 benchmarking-kpi's
005 benchmarking-kpi's005 benchmarking-kpi's
005 benchmarking-kpi's
 
012 bussiness planning process
012 bussiness planning process012 bussiness planning process
012 bussiness planning process
 
Strategic direction of cambodia budget system reform 2013-2020 - Ratanak Hav,...
Strategic direction of cambodia budget system reform 2013-2020 - Ratanak Hav,...Strategic direction of cambodia budget system reform 2013-2020 - Ratanak Hav,...
Strategic direction of cambodia budget system reform 2013-2020 - Ratanak Hav,...
 
Project Scheduling & Controls
Project Scheduling & ControlsProject Scheduling & Controls
Project Scheduling & Controls
 
Smith.donnie
Smith.donnieSmith.donnie
Smith.donnie
 
Cambodia's perspective on program/performance budgeting - Ratanak Hav - Cambodia
Cambodia's perspective on program/performance budgeting - Ratanak Hav - CambodiaCambodia's perspective on program/performance budgeting - Ratanak Hav - Cambodia
Cambodia's perspective on program/performance budgeting - Ratanak Hav - Cambodia
 
Recent budgeting developments - Sokkheang Lay, Cambodia
Recent budgeting developments - Sokkheang Lay, CambodiaRecent budgeting developments - Sokkheang Lay, Cambodia
Recent budgeting developments - Sokkheang Lay, Cambodia
 

En vedette

Project Portfolio Strategic Planning
Project Portfolio Strategic PlanningProject Portfolio Strategic Planning
Project Portfolio Strategic Planningvmakarov
 
A project on mc donalds
A project on mc donaldsA project on mc donalds
A project on mc donaldsProjects Kart
 
CA Project and Portfolio Management (CA PPM) for Business Transformation at P...
CA Project and Portfolio Management (CA PPM) for Business Transformation at P...CA Project and Portfolio Management (CA PPM) for Business Transformation at P...
CA Project and Portfolio Management (CA PPM) for Business Transformation at P...CA Technologies
 

En vedette (6)

Project Portfolio Strategic Planning
Project Portfolio Strategic PlanningProject Portfolio Strategic Planning
Project Portfolio Strategic Planning
 
A project on mc donalds
A project on mc donaldsA project on mc donalds
A project on mc donalds
 
CA Project and Portfolio Management (CA PPM) for Business Transformation at P...
CA Project and Portfolio Management (CA PPM) for Business Transformation at P...CA Project and Portfolio Management (CA PPM) for Business Transformation at P...
CA Project and Portfolio Management (CA PPM) for Business Transformation at P...
 
Guide to Project Portfolio Management
Guide to Project Portfolio ManagementGuide to Project Portfolio Management
Guide to Project Portfolio Management
 
MNC
MNCMNC
MNC
 
Slideshare ppt
Slideshare pptSlideshare ppt
Slideshare ppt
 

Similaire à Project Management

CPM lecture note 4,5,6&7.pdf
CPM lecture note 4,5,6&7.pdfCPM lecture note 4,5,6&7.pdf
CPM lecture note 4,5,6&7.pdfDejeneTsegaye6
 
CPM lecture note 4,5,6&7.pdf
CPM lecture note 4,5,6&7.pdfCPM lecture note 4,5,6&7.pdf
CPM lecture note 4,5,6&7.pdfDejeneTsegaye6
 
Construction company business plan
Construction company business planConstruction company business plan
Construction company business planfarouq umar
 
7 cost managmenet
7 cost managmenet7 cost managmenet
7 cost managmenetAla Ibrahim
 
Software Project Management: Budget
Software Project Management: BudgetSoftware Project Management: Budget
Software Project Management: BudgetMinhas Kamal
 
Pmp t09 project_execution_plan_rev_a
Pmp t09 project_execution_plan_rev_aPmp t09 project_execution_plan_rev_a
Pmp t09 project_execution_plan_rev_aForbes Chanakira
 
07.cost management updated
07.cost management updated07.cost management updated
07.cost management updatedShraddha PMP
 
PM_Assignment3_Group1 (2).pptx
PM_Assignment3_Group1 (2).pptxPM_Assignment3_Group1 (2).pptx
PM_Assignment3_Group1 (2).pptxvanna37
 
A brief on project cost management
A brief on project cost managementA brief on project cost management
A brief on project cost managementImran Jamil
 
Monitor and control process group part two
Monitor and control process group part twoMonitor and control process group part two
Monitor and control process group part twoHossam Maghrabi
 
Project Budget.pptx.ppt
Project Budget.pptx.pptProject Budget.pptx.ppt
Project Budget.pptx.pptDejeneTsegaye6
 
2.07 cost management 1
2.07 cost management 12.07 cost management 1
2.07 cost management 1reddvise
 
Project Management.pptx
Project Management.pptxProject Management.pptx
Project Management.pptxYogesh Singh
 
Cost management plan tyre recycling plant
Cost management plan  tyre recycling plantCost management plan  tyre recycling plant
Cost management plan tyre recycling plantabhishekthakur309
 
EPC Group's Project Management Organization’s Methodology
EPC Group's Project Management Organization’s MethodologyEPC Group's Project Management Organization’s Methodology
EPC Group's Project Management Organization’s MethodologyEPC Group
 
EPC Group's PMO Methodology to Ensure On Time and On Budget Initiatives
EPC Group's PMO Methodology to Ensure On Time and On Budget InitiativesEPC Group's PMO Methodology to Ensure On Time and On Budget Initiatives
EPC Group's PMO Methodology to Ensure On Time and On Budget InitiativesEPC Group
 
Running head Quality Plan Analysis1Quality Plan Analysis3.docx
Running head Quality Plan Analysis1Quality Plan Analysis3.docxRunning head Quality Plan Analysis1Quality Plan Analysis3.docx
Running head Quality Plan Analysis1Quality Plan Analysis3.docxcharisellington63520
 
Topic 12 - Project Cost Management.pdf
Topic 12 - Project Cost Management.pdfTopic 12 - Project Cost Management.pdf
Topic 12 - Project Cost Management.pdfHuyNguyen657394
 
Understanding Work in Progress (WIP) Schedules in Construction Accounting.docx
Understanding Work in Progress (WIP) Schedules in Construction Accounting.docxUnderstanding Work in Progress (WIP) Schedules in Construction Accounting.docx
Understanding Work in Progress (WIP) Schedules in Construction Accounting.docxConstruction Company
 
Cert iv cost part 2
Cert iv  cost part 2Cert iv  cost part 2
Cert iv cost part 2Skript
 

Similaire à Project Management (20)

CPM lecture note 4,5,6&7.pdf
CPM lecture note 4,5,6&7.pdfCPM lecture note 4,5,6&7.pdf
CPM lecture note 4,5,6&7.pdf
 
CPM lecture note 4,5,6&7.pdf
CPM lecture note 4,5,6&7.pdfCPM lecture note 4,5,6&7.pdf
CPM lecture note 4,5,6&7.pdf
 
Construction company business plan
Construction company business planConstruction company business plan
Construction company business plan
 
7 cost managmenet
7 cost managmenet7 cost managmenet
7 cost managmenet
 
Software Project Management: Budget
Software Project Management: BudgetSoftware Project Management: Budget
Software Project Management: Budget
 
Pmp t09 project_execution_plan_rev_a
Pmp t09 project_execution_plan_rev_aPmp t09 project_execution_plan_rev_a
Pmp t09 project_execution_plan_rev_a
 
07.cost management updated
07.cost management updated07.cost management updated
07.cost management updated
 
PM_Assignment3_Group1 (2).pptx
PM_Assignment3_Group1 (2).pptxPM_Assignment3_Group1 (2).pptx
PM_Assignment3_Group1 (2).pptx
 
A brief on project cost management
A brief on project cost managementA brief on project cost management
A brief on project cost management
 
Monitor and control process group part two
Monitor and control process group part twoMonitor and control process group part two
Monitor and control process group part two
 
Project Budget.pptx.ppt
Project Budget.pptx.pptProject Budget.pptx.ppt
Project Budget.pptx.ppt
 
2.07 cost management 1
2.07 cost management 12.07 cost management 1
2.07 cost management 1
 
Project Management.pptx
Project Management.pptxProject Management.pptx
Project Management.pptx
 
Cost management plan tyre recycling plant
Cost management plan  tyre recycling plantCost management plan  tyre recycling plant
Cost management plan tyre recycling plant
 
EPC Group's Project Management Organization’s Methodology
EPC Group's Project Management Organization’s MethodologyEPC Group's Project Management Organization’s Methodology
EPC Group's Project Management Organization’s Methodology
 
EPC Group's PMO Methodology to Ensure On Time and On Budget Initiatives
EPC Group's PMO Methodology to Ensure On Time and On Budget InitiativesEPC Group's PMO Methodology to Ensure On Time and On Budget Initiatives
EPC Group's PMO Methodology to Ensure On Time and On Budget Initiatives
 
Running head Quality Plan Analysis1Quality Plan Analysis3.docx
Running head Quality Plan Analysis1Quality Plan Analysis3.docxRunning head Quality Plan Analysis1Quality Plan Analysis3.docx
Running head Quality Plan Analysis1Quality Plan Analysis3.docx
 
Topic 12 - Project Cost Management.pdf
Topic 12 - Project Cost Management.pdfTopic 12 - Project Cost Management.pdf
Topic 12 - Project Cost Management.pdf
 
Understanding Work in Progress (WIP) Schedules in Construction Accounting.docx
Understanding Work in Progress (WIP) Schedules in Construction Accounting.docxUnderstanding Work in Progress (WIP) Schedules in Construction Accounting.docx
Understanding Work in Progress (WIP) Schedules in Construction Accounting.docx
 
Cert iv cost part 2
Cert iv  cost part 2Cert iv  cost part 2
Cert iv cost part 2
 

Plus de amit soni

graphic tool
graphic toolgraphic tool
graphic toolamit soni
 
Graphical Tool Term Paper
Graphical Tool Term PaperGraphical Tool Term Paper
Graphical Tool Term Paperamit soni
 
design of web page(home page)
design of web page(home page)design of web page(home page)
design of web page(home page)amit soni
 
Term Paper Of Ifs
Term Paper Of IfsTerm Paper Of Ifs
Term Paper Of Ifsamit soni
 
Honda Motors
Honda MotorsHonda Motors
Honda Motorsamit soni
 
Significance Of Emotional Intelligence And Its Impact On Job Satisfaction
Significance Of Emotional Intelligence And Its Impact On Job SatisfactionSignificance Of Emotional Intelligence And Its Impact On Job Satisfaction
Significance Of Emotional Intelligence And Its Impact On Job Satisfactionamit soni
 
Coca Cola Pre..
Coca Cola Pre..Coca Cola Pre..
Coca Cola Pre..amit soni
 
Ppt State Bank Group 1226349742695851 9
Ppt State Bank Group 1226349742695851 9Ppt State Bank Group 1226349742695851 9
Ppt State Bank Group 1226349742695851 9amit soni
 
Aegon religare
Aegon religareAegon religare
Aegon religareamit soni
 
financial analysis of icici prudential life insurance
financial analysis of icici prudential life insurancefinancial analysis of icici prudential life insurance
financial analysis of icici prudential life insuranceamit soni
 
Club Mahindra111
Club Mahindra111Club Mahindra111
Club Mahindra111amit soni
 

Plus de amit soni (13)

graphic tool
graphic toolgraphic tool
graphic tool
 
Graphical Tool Term Paper
Graphical Tool Term PaperGraphical Tool Term Paper
Graphical Tool Term Paper
 
Honda city
Honda cityHonda city
Honda city
 
design of web page(home page)
design of web page(home page)design of web page(home page)
design of web page(home page)
 
Term Paper Of Ifs
Term Paper Of IfsTerm Paper Of Ifs
Term Paper Of Ifs
 
Honda Motors
Honda MotorsHonda Motors
Honda Motors
 
Significance Of Emotional Intelligence And Its Impact On Job Satisfaction
Significance Of Emotional Intelligence And Its Impact On Job SatisfactionSignificance Of Emotional Intelligence And Its Impact On Job Satisfaction
Significance Of Emotional Intelligence And Its Impact On Job Satisfaction
 
Coca Cola Pre..
Coca Cola Pre..Coca Cola Pre..
Coca Cola Pre..
 
Ppt State Bank Group 1226349742695851 9
Ppt State Bank Group 1226349742695851 9Ppt State Bank Group 1226349742695851 9
Ppt State Bank Group 1226349742695851 9
 
Aegon religare
Aegon religareAegon religare
Aegon religare
 
financial analysis of icici prudential life insurance
financial analysis of icici prudential life insurancefinancial analysis of icici prudential life insurance
financial analysis of icici prudential life insurance
 
Club Mahindra111
Club Mahindra111Club Mahindra111
Club Mahindra111
 
Hdfc Bank
Hdfc BankHdfc Bank
Hdfc Bank
 

Dernier

Transaction Management in Database Management System
Transaction Management in Database Management SystemTransaction Management in Database Management System
Transaction Management in Database Management SystemChristalin Nelson
 
Q-Factor HISPOL Quiz-6th April 2024, Quiz Club NITW
Q-Factor HISPOL Quiz-6th April 2024, Quiz Club NITWQ-Factor HISPOL Quiz-6th April 2024, Quiz Club NITW
Q-Factor HISPOL Quiz-6th April 2024, Quiz Club NITWQuiz Club NITW
 
Textual Evidence in Reading and Writing of SHS
Textual Evidence in Reading and Writing of SHSTextual Evidence in Reading and Writing of SHS
Textual Evidence in Reading and Writing of SHSMae Pangan
 
How to Make a Duplicate of Your Odoo 17 Database
How to Make a Duplicate of Your Odoo 17 DatabaseHow to Make a Duplicate of Your Odoo 17 Database
How to Make a Duplicate of Your Odoo 17 DatabaseCeline George
 
Active Learning Strategies (in short ALS).pdf
Active Learning Strategies (in short ALS).pdfActive Learning Strategies (in short ALS).pdf
Active Learning Strategies (in short ALS).pdfPatidar M
 
Decoding the Tweet _ Practical Criticism in the Age of Hashtag.pptx
Decoding the Tweet _ Practical Criticism in the Age of Hashtag.pptxDecoding the Tweet _ Practical Criticism in the Age of Hashtag.pptx
Decoding the Tweet _ Practical Criticism in the Age of Hashtag.pptxDhatriParmar
 
Unraveling Hypertext_ Analyzing Postmodern Elements in Literature.pptx
Unraveling Hypertext_ Analyzing  Postmodern Elements in  Literature.pptxUnraveling Hypertext_ Analyzing  Postmodern Elements in  Literature.pptx
Unraveling Hypertext_ Analyzing Postmodern Elements in Literature.pptxDhatriParmar
 
Blowin' in the Wind of Caste_ Bob Dylan's Song as a Catalyst for Social Justi...
Blowin' in the Wind of Caste_ Bob Dylan's Song as a Catalyst for Social Justi...Blowin' in the Wind of Caste_ Bob Dylan's Song as a Catalyst for Social Justi...
Blowin' in the Wind of Caste_ Bob Dylan's Song as a Catalyst for Social Justi...DhatriParmar
 
Oppenheimer Film Discussion for Philosophy and Film
Oppenheimer Film Discussion for Philosophy and FilmOppenheimer Film Discussion for Philosophy and Film
Oppenheimer Film Discussion for Philosophy and FilmStan Meyer
 
Mythology Quiz-4th April 2024, Quiz Club NITW
Mythology Quiz-4th April 2024, Quiz Club NITWMythology Quiz-4th April 2024, Quiz Club NITW
Mythology Quiz-4th April 2024, Quiz Club NITWQuiz Club NITW
 
Multi Domain Alias In the Odoo 17 ERP Module
Multi Domain Alias In the Odoo 17 ERP ModuleMulti Domain Alias In the Odoo 17 ERP Module
Multi Domain Alias In the Odoo 17 ERP ModuleCeline George
 
Mental Health Awareness - a toolkit for supporting young minds
Mental Health Awareness - a toolkit for supporting young mindsMental Health Awareness - a toolkit for supporting young minds
Mental Health Awareness - a toolkit for supporting young mindsPooky Knightsmith
 
ClimART Action | eTwinning Project
ClimART Action    |    eTwinning ProjectClimART Action    |    eTwinning Project
ClimART Action | eTwinning Projectjordimapav
 
Student Profile Sample - We help schools to connect the data they have, with ...
Student Profile Sample - We help schools to connect the data they have, with ...Student Profile Sample - We help schools to connect the data they have, with ...
Student Profile Sample - We help schools to connect the data they have, with ...Seán Kennedy
 
ESP 4-EDITED.pdfmmcncncncmcmmnmnmncnmncmnnjvnnv
ESP 4-EDITED.pdfmmcncncncmcmmnmnmncnmncmnnjvnnvESP 4-EDITED.pdfmmcncncncmcmmnmnmncnmncmnnjvnnv
ESP 4-EDITED.pdfmmcncncncmcmmnmnmncnmncmnnjvnnvRicaMaeCastro1
 
Congestive Cardiac Failure..presentation
Congestive Cardiac Failure..presentationCongestive Cardiac Failure..presentation
Congestive Cardiac Failure..presentationdeepaannamalai16
 
4.11.24 Mass Incarceration and the New Jim Crow.pptx
4.11.24 Mass Incarceration and the New Jim Crow.pptx4.11.24 Mass Incarceration and the New Jim Crow.pptx
4.11.24 Mass Incarceration and the New Jim Crow.pptxmary850239
 
Q-Factor General Quiz-7th April 2024, Quiz Club NITW
Q-Factor General Quiz-7th April 2024, Quiz Club NITWQ-Factor General Quiz-7th April 2024, Quiz Club NITW
Q-Factor General Quiz-7th April 2024, Quiz Club NITWQuiz Club NITW
 

Dernier (20)

Transaction Management in Database Management System
Transaction Management in Database Management SystemTransaction Management in Database Management System
Transaction Management in Database Management System
 
Q-Factor HISPOL Quiz-6th April 2024, Quiz Club NITW
Q-Factor HISPOL Quiz-6th April 2024, Quiz Club NITWQ-Factor HISPOL Quiz-6th April 2024, Quiz Club NITW
Q-Factor HISPOL Quiz-6th April 2024, Quiz Club NITW
 
Textual Evidence in Reading and Writing of SHS
Textual Evidence in Reading and Writing of SHSTextual Evidence in Reading and Writing of SHS
Textual Evidence in Reading and Writing of SHS
 
How to Make a Duplicate of Your Odoo 17 Database
How to Make a Duplicate of Your Odoo 17 DatabaseHow to Make a Duplicate of Your Odoo 17 Database
How to Make a Duplicate of Your Odoo 17 Database
 
Active Learning Strategies (in short ALS).pdf
Active Learning Strategies (in short ALS).pdfActive Learning Strategies (in short ALS).pdf
Active Learning Strategies (in short ALS).pdf
 
Decoding the Tweet _ Practical Criticism in the Age of Hashtag.pptx
Decoding the Tweet _ Practical Criticism in the Age of Hashtag.pptxDecoding the Tweet _ Practical Criticism in the Age of Hashtag.pptx
Decoding the Tweet _ Practical Criticism in the Age of Hashtag.pptx
 
Unraveling Hypertext_ Analyzing Postmodern Elements in Literature.pptx
Unraveling Hypertext_ Analyzing  Postmodern Elements in  Literature.pptxUnraveling Hypertext_ Analyzing  Postmodern Elements in  Literature.pptx
Unraveling Hypertext_ Analyzing Postmodern Elements in Literature.pptx
 
Blowin' in the Wind of Caste_ Bob Dylan's Song as a Catalyst for Social Justi...
Blowin' in the Wind of Caste_ Bob Dylan's Song as a Catalyst for Social Justi...Blowin' in the Wind of Caste_ Bob Dylan's Song as a Catalyst for Social Justi...
Blowin' in the Wind of Caste_ Bob Dylan's Song as a Catalyst for Social Justi...
 
Oppenheimer Film Discussion for Philosophy and Film
Oppenheimer Film Discussion for Philosophy and FilmOppenheimer Film Discussion for Philosophy and Film
Oppenheimer Film Discussion for Philosophy and Film
 
prashanth updated resume 2024 for Teaching Profession
prashanth updated resume 2024 for Teaching Professionprashanth updated resume 2024 for Teaching Profession
prashanth updated resume 2024 for Teaching Profession
 
Mythology Quiz-4th April 2024, Quiz Club NITW
Mythology Quiz-4th April 2024, Quiz Club NITWMythology Quiz-4th April 2024, Quiz Club NITW
Mythology Quiz-4th April 2024, Quiz Club NITW
 
Multi Domain Alias In the Odoo 17 ERP Module
Multi Domain Alias In the Odoo 17 ERP ModuleMulti Domain Alias In the Odoo 17 ERP Module
Multi Domain Alias In the Odoo 17 ERP Module
 
Mental Health Awareness - a toolkit for supporting young minds
Mental Health Awareness - a toolkit for supporting young mindsMental Health Awareness - a toolkit for supporting young minds
Mental Health Awareness - a toolkit for supporting young minds
 
Faculty Profile prashantha K EEE dept Sri Sairam college of Engineering
Faculty Profile prashantha K EEE dept Sri Sairam college of EngineeringFaculty Profile prashantha K EEE dept Sri Sairam college of Engineering
Faculty Profile prashantha K EEE dept Sri Sairam college of Engineering
 
ClimART Action | eTwinning Project
ClimART Action    |    eTwinning ProjectClimART Action    |    eTwinning Project
ClimART Action | eTwinning Project
 
Student Profile Sample - We help schools to connect the data they have, with ...
Student Profile Sample - We help schools to connect the data they have, with ...Student Profile Sample - We help schools to connect the data they have, with ...
Student Profile Sample - We help schools to connect the data they have, with ...
 
ESP 4-EDITED.pdfmmcncncncmcmmnmnmncnmncmnnjvnnv
ESP 4-EDITED.pdfmmcncncncmcmmnmnmncnmncmnnjvnnvESP 4-EDITED.pdfmmcncncncmcmmnmnmncnmncmnnjvnnv
ESP 4-EDITED.pdfmmcncncncmcmmnmnmncnmncmnnjvnnv
 
Congestive Cardiac Failure..presentation
Congestive Cardiac Failure..presentationCongestive Cardiac Failure..presentation
Congestive Cardiac Failure..presentation
 
4.11.24 Mass Incarceration and the New Jim Crow.pptx
4.11.24 Mass Incarceration and the New Jim Crow.pptx4.11.24 Mass Incarceration and the New Jim Crow.pptx
4.11.24 Mass Incarceration and the New Jim Crow.pptx
 
Q-Factor General Quiz-7th April 2024, Quiz Club NITW
Q-Factor General Quiz-7th April 2024, Quiz Club NITWQ-Factor General Quiz-7th April 2024, Quiz Club NITW
Q-Factor General Quiz-7th April 2024, Quiz Club NITW
 

Project Management

  • 1. TERM PAPER OF PROJECT MANAGEMENT Project: Nam Con Son Gas Project of British Petroleum, Vietnam Topic: various controlling procedures, progress control, & project monitoring system in this project. Submitted by: Submitted to: Amit Kumar Ms. Tejbir Kaur 3020070044 RR1709B34 Sec: 1709
  • 2. Objective of this term paper The objectives of my term paper are……..  To get knowledge about the project Nam Con Son project of British petroleum, Vietnam.  What are the various investors investing in this project?  To study about the various control procedures in a project.  Various scheduled planning procedures.  Various cost planning procedures.  Performance reporting procedures.  Change control procedures.  To study about the progress control of the project.  To study about the monitoring system used in the project.
  • 3. Nam Con Son Gas Project of British Petroleum, Vietnam INTRODUCTION TO PROJECT The Nam Con Son project is Vietnam's largest foreign investment project of $1.3 billion, having investors like the Vietnam Oil and Gas Corporation (Petro-Vietnam), the UK's BP Group, India's Oil and Natural Gas Company (ONGC Videsh) and the US's Conoco-Philips. Over the past 14 months, the $1.3 billion Nam Con Son Gas project, operated by BPEOC, has shown outstanding reliability by meeting almost 100 percent the gas nomination of its customers in the Phu My power complex in the southern province of Ba Ria-Vung Tau, the largest power complex in Vietnam so far. The Project center based in Vietnam needed to update the partners with the latest progress of the project and accordingly plan/reschedule jobs. The Project partners located at various locations required to track progress at the earliest and plan or reschedule further progress with immediate effect. The Project Information was being disseminated through manually printed journals, generated once in a fortnight, and electronic mails. This method of information dissemination involved high costs and delayed the planning process. Various control procedures  Schedule Planning Procedure: This defines the procedures and responsibilities for developing this project baseline schedule. In cooperation with the Project Customer, all levels of the project management team are involved in the process of establishing a timetable of milestones and activities that will lead to a successful project outcome. These following are Schedule Planning procedures:
  • 4. 1. The Project Customer and the Project Manager jointly determine the Baseline Milestones.  The Project Manager, collaborating with the Project Customer, selects the project key events and decision points that constitute the master schedule. Titles, definitions and planned dates are determined for each Baseline Milestone. 2. The Project Management & Integrated Planning Division develops the Baseline Milestones Schedule.  Project management & integrated planning division load the Baseline Milestones (Level 1 and 2) with their associated planned dates into the Schedule Management System forming a Baseline Milestones Schedule. 3. The Project Management & Integrated Planning Division, the Associate Project Manager, and the Control Account Manager identify the Intermediate Milestones.  Based on the defined Baseline Milestones, Project Management & Integrated planning division, the Associate Project Manager, and the Control Account Manager identify the important Level 3 and 4 milestones of the project. 4. The Project Management & Integrated Planning Division develops the Intermediate Milestone Schedule.  PM&I loads the Intermediate Milestones with their associated planned dates into the Schedule Management System forming an Intermediate Milestones Schedule.  Cost Planning Procedure: The cost planning procedure defines the procedures and responsibilities for developing a project cost baseline. With funding guidance from the Project Customer, all levels of the project management team are involved in the process of producing a project cost estimate. When combined with the project schedule, a timed- phase budget will be established against which project performance can be measured.
  • 5. 1. The Project Customer provides funding guidance.  Based on the desired final product and the expected funding availability, the Project Customer will usually provide the Project Manager with a funding profile for the project. 2. The Project Manager determines an initial project budget target.  Taking the funding guidance provided by the Project Customer, the Project Manager establishes initial budget targets for the project. With a preliminary BS framework, proposed budgets may be prescribed as well as a fiscal year breakouts. 3. The Control Account Manager develops the Control Account Plan.  The Control Account Manager develops an initial Control Account Plan that will be used to establish the initial cost estimate. 4. The Associate Project Manager reviews the Control Account Plan.  The Associate Project Manager reviews the Control Account Plan(s) within his area of responsibility. Plans that are not complete are returned to the appropriate Control Account Manager for revision. Once satisfactory, the Control Account Plan(s) is/are forwarded to the Project Management & Integrated Planning Division. 5. The Project Management & Integrated Planning Division reviews the Control Account Plans.  PM&I reviews the Control Account Plans to ensure that the project cost estimate does not exceed any pre-established funding constraints. 6. The Project Management & Integrated Planning Division establishes the initial cost estimate.  The costs from each Control Account Plan are summarized to establish an initial cost estimate.
  • 6. 7. The Project Management team reviews and finalizes the cost estimate.  The Project Management team reviews the consolidated cost estimate for the project, and through negotiation, finalize the estimate. The Control Account Manager revises the Control Account Plan for each relevant control account based on the final negotiated cost estimate for the project. 8. The Project Management & Integrated Planning Division establishes the cost Baseline.  With approved Control Account Plans, the project cost baseline is established. This cost baseline is then integrated with the schedule baseline to produce the project Time-Phased Budget.  Performance Reporting Procedure: This defines the procedures and responsibilities for collecting and reporting cost and schedule performance data and analyzing these data to assess current and projected future project status. Cost and schedule performance is measured and reported monthly for each control account and WBS element, as appropriate. 1. The Project Manager determines the variance thresholds.  The Project Manager determines the thresholds used to flag variances for each control account and WBS element, as appropriate. 2. The Control Account Manager prepares the Status Update Report.  At the end of the accounting period, the Control Account Manager reports the control account work progress and accomplishments by providing input on the Status Update Report. 3. The Associate Project Manager reviews the Status Update Report.  The Associate Project Manager validates work activity completions and makes assessment of interim progress.
  • 7. 4. The Project Management & Integrated Planning Division determines the Budgeted Cost of Work Performed.  Exporting the data from the Status Update Reports to the Scheduling Management System, PM&I calculates BCWP (Earned Value) by summing the budgets of work accomplished and completed portions of work in progress for each control account. 5. The performing organizations report expenses incurred.  Performing organizations charge actual costs incurred throughout the reporting period using the Jefferson Lab accounting system. 6. The Chief Financial Officer prepares the cost reports.  The Chief Financial Officer converts time sheets, purchase orders, receipts and invoices, travel expense vouchers, and other entry documents into costs and commitments for each control account. Labor and cost reports are prepared by the Chief Financial Officer and are available to the Control Account Managers and Associate Project Managers for review and to Project Management & Integrated planning division for entering into the performance database. 7. The Control Account Manager reviews the cost reports.  The Control Account Manager reviews the cost reports for accuracy and control of costs. Unusual or excessive charges are investigated and errors are reported to the Chief Financial Officer. 8. The Associate Project Manager reviews the cost reports.  Each Associate Project Manager reviews actual costs with the Control Account Manager directing the effort.
  • 8. 9. The Project Management & Integrated Planning Division prepares the performance reports.  PM&I combines ACWP (Actual Costs) data from accounting, BCWS (Planned Value), and Budget At Completion from the Performance Measurement Baseline, BCWP (Earned Value) as determined in step 4 above, and Estimate At Completion to calculate cost, schedule, and at completion variances. Results are published in monthly performance reports (Project Analysis Reports) and charts (Earned Value Management Performance Charts/Performance Indicator Charts). The Red Flag Report is also generated where significant variances are flagged in accordance with the thresholds established by the Project Manager. 10. The Project Management team reviews the Control Account Performance Report.  The Control Account Performance Report consists of those combined performance reports available to the Control Account Manager from the financial management system and the schedule/cost management systems. Each Control Account Manager reviews the Control Account Performance Report, notes variances, and determines reasons for above or below planned performance. Each Associate Project Manager reviews the Control Account Performance Reports and the technical progress for their area of responsibility and discusses the work, cost, and schedule status with the responsible Control Account Manager. The Project Manager reviews the all reports and identifies reporting elements of the WBS for which formal Variance Analysis Reports are required. 11. The Project Management & Integrated Planning Division issues the Variance Analysis Report form.  PM&I issues a Variance Analysis Report form for each reporting element requiring a Variance Analysis Report.
  • 9. 12. The Control Account Manager completes the Variance Analysis Report.  The Control Account Manager conducts a variance analysis to include the reasons for the variances, the anticipated effect on the project cost, schedule or technical parameters, and proposed corrective action. 13. The Project Manager reviews the Variance Analysis Reports with the Control Account Managers and Associate Project Managers.  The Project Manager reviews the Variance Analysis Reports with the Control Account Managers and Associate Project Managers to ensure accurate variance causes are identified and adequate corrective plans are established. The Variance Analysis Report form is signed by the Control Account Manager and the Associate Project Manager/Project Manager. 14. The Project Management & Integrated Planning Division prepares the monthly project report.  PM&I collects all pertinent project performance data and summarizes it for the monthly report. PM&I forwards the monthly report, including the revised Estimates at Completion, to the Project Manager. 15. The Project Manager submits the monthly report to the Project Customer.  The Project Manager reviews the monthly report and submits it to the Project Customer.  Change Control Procedure: The Project Nam Con Son has the approved technical, schedule and cost plan for accomplishing all project activities. As the project progresses, this baseline may change due to Project Customer redirection, internal replanning, or redesign. Changes are classified according to the extent that they impact the Integrated Project Baseline. The review process and the approval authority required for a proposed change depend upon its classification. This defines the procedures and responsibilities for requesting, reviewing, and documenting changes to the Integrated Project Baseline, and
  • 10. to assure timely implementation of changes once they are approved. The change control procedure contains various phases in it. These phases are: 1. Request Phase Any project team member may request a change to the technical, schedule, and cost baselines by generating a Change Request form and submitting it to a member of the Change Control Board for concurrence. a. The Originator prepares the Change Request.  The originator prepares the Change Request form in accordance with the document instructions. Change Request status at this stage is “New.” b. The Change Control Board member concurs with the Change Request.  The originator must then obtain the concurrence of one member of the Change Control Board in order for the request to be accepted for consideration. The concurring member signs the Change Request in the „Concurrence‟ block. c. The Change Control Board member initiates the Change Impact Assessment process.  If the Change Impact Assessment has not been completed on the Change Request form, the Change Control Board member assigns actions for analyses of potential technical, schedule, cost and quality/safety effects of the proposed change. Primary responsibility is typically assigned to a Control Account Manager. d. The Project Management & Integrated Planning Division enters the Change Request in the Change Request Log.  After Change Control Board member concurrence is obtained, PM&I assigns a number (scheme: FY - sequence #, e.g., 05-001) to the Change Request and enters it in the Change Request Log as “Open.” PM&I maintains this log as a database, updating information each time there is a change to the status of a Change Request. For Class 1-2 and Class 3 changes, PM&I distributes the Change Request to members of the Change Control Board, and places the Change Request on the agenda for the next Change Control Board meeting.
  • 11. e. The Control Account Manager coordinates inputs to the Change Impact Assessment.  The assigned Control Account Manager completes the Change Impact Assessment. The Change Impact Assessment records the potential impacts of the proposed change to the technical, schedule and cost baselines and also to safety and quality. The impacts of not approving the change are also documented. The Control Account Manager coordinates inputs from relevant parties, such as scientists, engineers, contractors, and quality and safety personnel, to document these potential impacts. Continuation pages are attached to the Change Request form where space is insufficient. Where drawings, specifications, purchase orders, Control Account Plans, etc., are affected, changes are marked on copies and attached. f. The Control Account Manager establishes the classification of the Change Request.  After reviewing the Change Impact Assessment and exhibits, the Control Account Manager establishes the Change Request classification. The Control Account Manager selects the appropriate class and signs the appropriate block on the Change Request form. g. The Associate Project Manager concurs with the classification of the Change Request.  The Associate Project Manager reviews the classification assigned by the Control Account Manager and, if he concurs, signs the adjacent block. h. The Project Management & Integrated Planning Division approves the classification of the Change Request.  The PM&I Manager reviews the classification assigned by the Control Account Manager and, if he concurs, signs the next block on the Change Request form. The classification may also be reviewed and changed by the Change Control Board.
  • 12. 2. Review Phase After the Change Request has been generated, impacts have been assessed, and an approved classification level has been established, it enters the Review Phase where the proposed change is evaluated and approved by an appropriate authority. For Class 1-2 Change Requests that will go to the Project Customer, this will be an external approval process. Class 3-5 Change Requests follow an internal approval process.  External Approval 1. The Project Management & Integrated Planning Division updates the Change Request Log.  Once PM&I has approved the classification level, the Change Request enters the Review Phase. PM&I monitors the status of Change Requests awaiting action. 2. The Change Control Board evaluates the Class 1-2 Change Request.  For Class 1-2 Change Requests, PM&I distributes the Change Request to members of the Change Control Board and places the Change Request on the agenda for the next board meeting. The Change Control Board evaluates the Class 1-2 Change Request package and recommends action to the Project Manager. 3. The Project Manager reviews the Class 1-2 Change Request.  The Project Manager reviews the Class 1-2 Change Request package and Change Control Board recommendations. The Project Manager prepares a submission to the Project Customer in accordance with customer procedures which may include a Baseline Change Control Board. This may include the Change Request as received, with some or all of the exhibits, or it may be a letter extracted from the Change Request material with additional amplification where necessary.
  • 13. 4. The Project Customer approves/disapproves the Class 1-2 Change Request.  For Class 1-2 Change Requests, the Project Customer is the final approving authority. Approval is indicated by signature in the appropriate 'Final Approval' block on the Change Request form. The approved Class 1-2 Change Request package is then returned to the Project Manager. 5. The Project Manager reviews the Project Customer Change Request actions.  The Project Manager reviews the decisions of the Project Customer and documents any impacts to the project plans in the Recommendation and Disposition section of the Change Request. 6. The Project Management & Integrated Planning Division determines the approval status of the Change Request.  PM&I updates the Change Request Log after the review process has been completed. At this stage, the Change Request can be deferred, approved, disapproved or determined to be a duplicate of a previously submitted Change Request. Any disapproved CR is sent back to the affected Control Account Manager who will consult with the originator to determine any further action.  Internal Approval 1. The Project Management & Integrated Planning Division updates the Change Request Log.  Once PM&I has approved the classification level, the Change Request enters the Review Phase. PM&I monitors the status of Change Requests awaiting action. 2. The Change Control Board evaluates the Class 3 Change Request.  For Class 3 Change Requests, PM&I distributes the Change Request to members of the Change Control Board and places the Change Request on the agenda for the next board meeting. The Change Control Board evaluates the Class 3 Change Request package and recommends action to the Project Manager.
  • 14. 3. The Project Manager reviews the Class 3 Change Request.  The Project Manager reviews the Class 3 Change Request package and Change Control Board recommendations. 4. The Project Manager approves/disapproves the Class 3 Change Requests.  For Class 3 Change Requests, the Project Manager is the final approving authority. Approval is indicated by signature in the appropriate 'Final Approval' block on the Change Request form. The approved Class 3 Change Request package is forwarded to PM&I. 5. The Associate Project Manager evaluates the Class 4 Change Request. 6. The Associate Project Manager approves/disapproves the Class 4 Change Request.  For Class 4 Change Requests, the Associate Project Manager is the final approving authority. Approval is indicated by signature in the appropriate 'Final Approval' block on the Change Request form. The approved Class 4 Change Request package is forwarded to PM&I. 7. The Control Account Manager evaluates the Class 5 Change Request. 8. The Control Account Manager approves/disapproves the Class 5 Change Request.  For Class 5 Change Requests, the Control Account Manager is the final approving authority. Approval is indicated by signature in the appropriate 'Final Approval' block on the Change Request form. The approved Class 5 Change Request package is forwarded to PM&I. 9. The Project Management & Integrated Planning Division determines the approval status of the Change Request.  PM&I updates the Change Request Log after the review process has been completed. At this stage, the Change Request can be deferred, approved, disapproved or determined to be a duplicate of a previously submitted Change Request. Any disapproved CR is sent
  • 15. back to the affected Control Account Manager who will consult with the originator to determine any further action.  Documentation Phase After the Change Request has been reviewed and approved by the appropriate authority, it enters the Documentation Phase where the proposed change is fully documented and implemented. 1. The Project Management & Integrated Planning Division issues the Change Order.  PM&I issues a Change Order for the approved Change Request. The Change Order is a completed, approved Change Request. 2. The Associate Project Manager updates the technical documentation.  Upon receipt of a Change Order, the affected Associate Project Manager ensures any relevant technical documentation (drawings, specifications, etc.) is revised. 3. The Project Management & Integrated Planning Division updates the Performance Measurement Baseline and Working Detail Schedule.  PM&I updates the Performance Measurement Baseline, the Working Detail Schedule and the associated Earned Value data. Historical EV data will not be revised. To improve document traceability, a new project baseline will be generated for each approved Change Request. 4. The Control Account Manager implements the approved Control Account Plan.  The Control Account Manager performs the effort in accordance with the updated Control Account Plan.
  • 16. Project Monitoring System for Nam Con Son Gas Project of British Petroleum, Vietnam To formulate and sustain the operations of this Gas project operating in 7 geographic locations, a project monitoring services were required to help to minimize project risk, controlling costs and providing expert advice on multinational projects. Areas that needed to be covered included • Permanent milestone monitoring • Budget control • Progress Documents management • Project specialists‟ onsite. The monitoring system developed in this project is based on the very latest commercial enterprise detection and correlation technologies adapted to monitor control networks, providing asset owners with dramatically improved situational awareness. The application has been conceptualized to increase the visibility about the progress of the Project. The objectives were to: 1. Meeting the project team requirements o What the project is seeking to achieve - the challenge o Who is involved in the project – project organization? o How the project is being run - the approach o Where the project is being run – map of organization o Monthly progress reporting – schedules and keys measures see below o HSE approach – statistics, slogans, awareness etc. o Latest news – highlighting people or project developments 2. Timely process to post Monthly Progress Reports o These contain a variety of information: progress against time schedule, key measures such as procurement status, approvals status, contract awards and progress or “Scurves” current electronic format is a mixture of Excel, Power point & Primavera. 3. BP A common processes and latest technology applied for Web building, including web tools, engines, server instances etc.
  • 17. 4. Simple process for maintenance of the site in the future. British Petroleum used Virtual Private Network (VPN) as the medium of communication between its partners except one, who was placed beyond the network. An information base within the VPN was set which, contained all the project related data, which was sent from the work sites through a common protocol router shared by the VPN and work site networks. This data was then electronically published in a HTML format and hosted in a web server which enabled easy client access through the TCP/IP network protocol .The information base can contain project data in any format which could automatically be converted to the browser recognizable MIME. This was collaborated with an online communication component, which enabled desktop meetings for the managers to track the project progress and reschedule the tasks. A security system was built into the middle tier to ensure that the data was secure during transaction, for partners outside the VPN network. The security layer was provided through encryption. Such data relating to work progress and technology in the Exploration and Projects is much classified and has a lot of commercial value. The following benefits will be achieved by implementing the project.  Bridge the gap between the customer‟s needs and available products  Use of cutting edge technology to benefit BOYANIKA  Delivery of best in class services to customers.  Increase Online Transaction  Increase customer‟s satisfaction  Increase productivity  Reduced operating costs  Efficient Master data maintenance  Efficient Event Management  Increase Access control and security  Facilitates efficient Market Research  Centralized Control for Managers  Efficiency in Decision Making  Increase profitability
  • 18. Balance market competition  Assured return on investment (ROI)  Increase Brand Value in terms of quality and quantity. BIBLIOGRAPHY  http://www.bp.com/liveassets/bp_internet/globalbp/STAGING/global_assets/ V/verfied_site_reports/Middle_east_SE_asia/Vietnam_NCSP_2006_verified  http://www.csmpl.com/Project%20Monitoring%20System%20for%20Nam %20Con%20Son%20Gas%20Project%20of%20British%20Petroleum,%20 Vietnam