Energy audit on site
V02
September 2011-2013
Andreas Iliou
TCS EEngineer

All rights reserved.
claim 1 – Power produced ,less than
expected
•
•

Client complains about less efficient system
(e.g inverter A towards B )
Check strings alone and compare with each other (with Ampmeter)

•

Check Voltage and current (mismatch-shortcut-bypassdiode still working ?)

•

Voltage ok ?! Uo
If Voltage is nearly the same –carry on with current

•

String with less voltage or current – probably shaded ?

•

Visual inspection of string wether shaded or not – probably dirty (birddrops)
claim 1 – Power produced ,less than
expected

•

Check layout of inverters

•

change the two inverters and check again current and voltage

•

If value still the same …check inverter temperature

•
•
•

if value changed , check air vent of 2nd inverter – clean if necessary
Rearrange position of inverter if it gets pre heated air
Change the position of the inverter and….. – check again

•
•
•

If still less efficient check cable size –keep in mind max drop < 1 %
If everything ok , check loop of system and change supply line
If not satisfied with measurement
claim 1 – Power produced ,less than
expected
Measurements :
1) Visual Inspection cells or cracks – if ok
2) Check voltage of different strings e.g 80V DC less ??
3) Measure current: module is producing 1,5A other strings produce 2,3-2,4A instead

….check with label – backside

If the system is not shaded , carry on with thermal image
claim 1 – Power produced ,less than
expected
Hotspot issue:
4) Thermal image from the front view

5) If it s problematic- clean surface and make another pic from the back
claim 1 – Power produced ,less than
expected
Solution :
6) Visual inspection if the module shows same hotspot from back and front view:

No visual crack or hotspot to be seen

Outcome of inspection e.g:
-

J-boxes show hotspots as well
More than one cell shows hotspot issues
E.g Voltage measured is only 2/3 of Uo (28V actual reading <-> 44V DC labelled)
Diode is defect j-box must be changed
claim 2 – Power produced ,less than
previous years
Claim 2:
check if the system is shaded or dirty – if not ?!
are the cables damaged or defect- if not?!
check with Tool like ( Tri Ka )
and compare with existing datas from prev. years
check corrosion or weak connections
are their any shortcuts ( modules or bypassdiodes )- if not ?!
cell damage in the module- cracks
shortcut inside j-box ( water ) – if not ?!
problem of degradation ?!
how old is the system- output power still as expected ?!
claim 3 –No power produced during
daytime
Claim 3:
meter not turning at all
is it still cloudy or dark outside ?!
check dc switch – or + broken – if not ?!

check AC breaker or earth leakage tester – if not ?!
check over protection unit -> shortcut – if not ?!
measure strings seperately
problem with frequency –if not ?!
check voltage of each phase –if not ?!
No DC supply:
Probaly to dark or less starting voltage
Inverter or tracker damaged
Fault on iso, check each string individually

Contenu connexe

Tendances

Fluke India - Digital Multimeter
Fluke India - Digital MultimeterFluke India - Digital Multimeter
Fluke India - Digital MultimeterMithila6190
 
Electrical measuring instruments
Electrical measuring instrumentsElectrical measuring instruments
Electrical measuring instrumentsSuhail Ahmed
 
Analog and Digital Multimeters
Analog and Digital MultimetersAnalog and Digital Multimeters
Analog and Digital MultimetersDinesh Sharma
 
Cdi t1 10_gen_unit3_revision_notes_eot
Cdi t1 10_gen_unit3_revision_notes_eotCdi t1 10_gen_unit3_revision_notes_eot
Cdi t1 10_gen_unit3_revision_notes_eotCDI Aljeer
 
L41 instruments
L41 instrumentsL41 instruments
L41 instrumentsSatyakam
 
Analog multimeter and ohmmeter
Analog multimeter and ohmmeterAnalog multimeter and ohmmeter
Analog multimeter and ohmmeterRahul Ranjan
 
TESCO Tuesday: Traditional Ratio, Burden, Admittance and Demag Testing – Part II
TESCO Tuesday: Traditional Ratio, Burden, Admittance and Demag Testing – Part IITESCO Tuesday: Traditional Ratio, Burden, Admittance and Demag Testing – Part II
TESCO Tuesday: Traditional Ratio, Burden, Admittance and Demag Testing – Part IITESCO - The Eastern Specialty Company
 
Digital Multimeters- Basic Guide
Digital Multimeters- Basic GuideDigital Multimeters- Basic Guide
Digital Multimeters- Basic GuideMithila6190
 
Cdi t1 11_gen_unit1&amp;2_revision_notes_eot
Cdi t1 11_gen_unit1&amp;2_revision_notes_eotCdi t1 11_gen_unit1&amp;2_revision_notes_eot
Cdi t1 11_gen_unit1&amp;2_revision_notes_eotCDI Aljeer
 
4. Test instruments and their connections
4. Test instruments and their connections4. Test instruments and their connections
4. Test instruments and their connectionssanewton
 
Vom reading
Vom  readingVom  reading
Vom readingEMEC101
 
Cdi t1 12_gen_unit1&amp;2_revision_notes_eot
Cdi t1 12_gen_unit1&amp;2_revision_notes_eotCdi t1 12_gen_unit1&amp;2_revision_notes_eot
Cdi t1 12_gen_unit1&amp;2_revision_notes_eotCDI Aljeer
 

Tendances (20)

The Multitester
The MultitesterThe Multitester
The Multitester
 
Fluke India - Digital Multimeter
Fluke India - Digital MultimeterFluke India - Digital Multimeter
Fluke India - Digital Multimeter
 
Electrical measuring instruments
Electrical measuring instrumentsElectrical measuring instruments
Electrical measuring instruments
 
Analog and Digital Multimeters
Analog and Digital MultimetersAnalog and Digital Multimeters
Analog and Digital Multimeters
 
Cdi t1 10_gen_unit3_revision_notes_eot
Cdi t1 10_gen_unit3_revision_notes_eotCdi t1 10_gen_unit3_revision_notes_eot
Cdi t1 10_gen_unit3_revision_notes_eot
 
Lab 2 multimeter
Lab 2 multimeterLab 2 multimeter
Lab 2 multimeter
 
Digital voltmeter
Digital voltmeterDigital voltmeter
Digital voltmeter
 
MULTITESTER
MULTITESTERMULTITESTER
MULTITESTER
 
L41 instruments
L41 instrumentsL41 instruments
L41 instruments
 
Analog multimeter and ohmmeter
Analog multimeter and ohmmeterAnalog multimeter and ohmmeter
Analog multimeter and ohmmeter
 
TESCO Tuesday: Traditional Ratio, Burden, Admittance and Demag Testing – Part II
TESCO Tuesday: Traditional Ratio, Burden, Admittance and Demag Testing – Part IITESCO Tuesday: Traditional Ratio, Burden, Admittance and Demag Testing – Part II
TESCO Tuesday: Traditional Ratio, Burden, Admittance and Demag Testing – Part II
 
Section 6
Section 6 Section 6
Section 6
 
Digital Multimeters- Basic Guide
Digital Multimeters- Basic GuideDigital Multimeters- Basic Guide
Digital Multimeters- Basic Guide
 
Cdi t1 11_gen_unit1&amp;2_revision_notes_eot
Cdi t1 11_gen_unit1&amp;2_revision_notes_eotCdi t1 11_gen_unit1&amp;2_revision_notes_eot
Cdi t1 11_gen_unit1&amp;2_revision_notes_eot
 
4. Test instruments and their connections
4. Test instruments and their connections4. Test instruments and their connections
4. Test instruments and their connections
 
Ac meters-part-1
Ac meters-part-1Ac meters-part-1
Ac meters-part-1
 
type of ohmmeter
type of ohmmetertype of ohmmeter
type of ohmmeter
 
Vom reading
Vom  readingVom  reading
Vom reading
 
Cdi t1 12_gen_unit1&amp;2_revision_notes_eot
Cdi t1 12_gen_unit1&amp;2_revision_notes_eotCdi t1 12_gen_unit1&amp;2_revision_notes_eot
Cdi t1 12_gen_unit1&amp;2_revision_notes_eot
 
Voltmeter
VoltmeterVoltmeter
Voltmeter
 

En vedette

En vedette (7)

Danfoss thin film and pid related topic
Danfoss thin film and pid related topicDanfoss thin film and pid related topic
Danfoss thin film and pid related topic
 
103201211214516440000
103201211214516440000103201211214516440000
103201211214516440000
 
Blogger for-beginners-pdf-version
Blogger for-beginners-pdf-versionBlogger for-beginners-pdf-version
Blogger for-beginners-pdf-version
 
Portfolio Ideaal
Portfolio IdeaalPortfolio Ideaal
Portfolio Ideaal
 
Pid-degradation of solarcells- solon in englisch
 Pid-degradation of solarcells- solon  in englisch Pid-degradation of solarcells- solon  in englisch
Pid-degradation of solarcells- solon in englisch
 
Site visit as discussed
Site visit  as discussedSite visit  as discussed
Site visit as discussed
 
Li gen vis1
Li gen vis1Li gen vis1
Li gen vis1
 

Similaire à Energy Audit Findings and Solutions

Practical Power Quality Measurements and Fixes Presented by Fluke and Transcat
Practical Power Quality Measurements and Fixes Presented by Fluke and TranscatPractical Power Quality Measurements and Fixes Presented by Fluke and Transcat
Practical Power Quality Measurements and Fixes Presented by Fluke and TranscatTranscat
 
Achieving Compliance to Small Format Battery Standards
Achieving Compliance to Small Format Battery StandardsAchieving Compliance to Small Format Battery Standards
Achieving Compliance to Small Format Battery StandardsEnergy Assurance LLC
 
Unit 06 - Substation and maintenance
Unit 06 - Substation and maintenanceUnit 06 - Substation and maintenance
Unit 06 - Substation and maintenancePremanandDesai
 
Chapter 1 Introduction to power Electronic Devices.pdf
Chapter 1 Introduction to power Electronic Devices.pdfChapter 1 Introduction to power Electronic Devices.pdf
Chapter 1 Introduction to power Electronic Devices.pdfLiewChiaPing
 
Michael Wood - Loader electric shocks, a case study
Michael Wood - Loader electric shocks, a case studyMichael Wood - Loader electric shocks, a case study
Michael Wood - Loader electric shocks, a case studyNSW Environment and Planning
 
BEC 26 control-Systems_unit-I_pdf
BEC 26 control-Systems_unit-I_pdfBEC 26 control-Systems_unit-I_pdf
BEC 26 control-Systems_unit-I_pdfShadab Siddiqui
 
Tools and Techniques for Commissioning and Maintaining PV Systems
Tools and Techniques for Commissioning and Maintaining PV SystemsTools and Techniques for Commissioning and Maintaining PV Systems
Tools and Techniques for Commissioning and Maintaining PV SystemsTranscat
 
Basics Of Energy Matering And Fraud Detection
Basics Of Energy Matering And Fraud DetectionBasics Of Energy Matering And Fraud Detection
Basics Of Energy Matering And Fraud DetectionAbhisek Swain
 

Similaire à Energy Audit Findings and Solutions (20)

Practical Power Quality Measurements and Fixes Presented by Fluke and Transcat
Practical Power Quality Measurements and Fixes Presented by Fluke and TranscatPractical Power Quality Measurements and Fixes Presented by Fluke and Transcat
Practical Power Quality Measurements and Fixes Presented by Fluke and Transcat
 
Introduction to PLC
Introduction to PLCIntroduction to PLC
Introduction to PLC
 
Meduim Voltage Switchgear.pptx
Meduim Voltage Switchgear.pptxMeduim Voltage Switchgear.pptx
Meduim Voltage Switchgear.pptx
 
Achieving Compliance to Small Format Battery Standards
Achieving Compliance to Small Format Battery StandardsAchieving Compliance to Small Format Battery Standards
Achieving Compliance to Small Format Battery Standards
 
Meduim Voltage Switchgear.pptx
Meduim Voltage Switchgear.pptxMeduim Voltage Switchgear.pptx
Meduim Voltage Switchgear.pptx
 
Unit 06 - Substation and maintenance
Unit 06 - Substation and maintenanceUnit 06 - Substation and maintenance
Unit 06 - Substation and maintenance
 
Chapter 1 Introduction to power Electronic Devices.pdf
Chapter 1 Introduction to power Electronic Devices.pdfChapter 1 Introduction to power Electronic Devices.pdf
Chapter 1 Introduction to power Electronic Devices.pdf
 
Introduction to Transformer Rated Metering
Introduction to Transformer Rated Metering Introduction to Transformer Rated Metering
Introduction to Transformer Rated Metering
 
Introduction to Transformer Rated Metering
Introduction to Transformer Rated MeteringIntroduction to Transformer Rated Metering
Introduction to Transformer Rated Metering
 
Introduction to Transformer Rated Metering
Introduction to Transformer Rated MeteringIntroduction to Transformer Rated Metering
Introduction to Transformer Rated Metering
 
Site Verification for Self-Contained Hot Socket Detection
Site Verification for Self-Contained Hot Socket DetectionSite Verification for Self-Contained Hot Socket Detection
Site Verification for Self-Contained Hot Socket Detection
 
EIT_Presentation
EIT_PresentationEIT_Presentation
EIT_Presentation
 
Transformer Rated Metering Site Verification
Transformer Rated Metering Site VerificationTransformer Rated Metering Site Verification
Transformer Rated Metering Site Verification
 
Michael Wood - Loader electric shocks, a case study
Michael Wood - Loader electric shocks, a case studyMichael Wood - Loader electric shocks, a case study
Michael Wood - Loader electric shocks, a case study
 
BEC 26 control-Systems_unit-I_pdf
BEC 26 control-Systems_unit-I_pdfBEC 26 control-Systems_unit-I_pdf
BEC 26 control-Systems_unit-I_pdf
 
Tools and Techniques for Commissioning and Maintaining PV Systems
Tools and Techniques for Commissioning and Maintaining PV SystemsTools and Techniques for Commissioning and Maintaining PV Systems
Tools and Techniques for Commissioning and Maintaining PV Systems
 
Basics Of Energy Matering And Fraud Detection
Basics Of Energy Matering And Fraud DetectionBasics Of Energy Matering And Fraud Detection
Basics Of Energy Matering And Fraud Detection
 
CircuitDebugging
CircuitDebuggingCircuitDebugging
CircuitDebugging
 
Transformer Rated Metering
Transformer Rated MeteringTransformer Rated Metering
Transformer Rated Metering
 
Learning the Language (Meter Testing 101)
Learning the Language (Meter Testing 101)Learning the Language (Meter Testing 101)
Learning the Language (Meter Testing 101)
 

Plus de Andreas ILIOU - Elektro- Solar (11)

Report earthing grounding pv with shielded, armoured dc cabling (worldwide)
Report earthing grounding pv with shielded, armoured dc cabling (worldwide)Report earthing grounding pv with shielded, armoured dc cabling (worldwide)
Report earthing grounding pv with shielded, armoured dc cabling (worldwide)
 
Report uk pv plants part 1
Report  uk pv plants part 1Report  uk pv plants part 1
Report uk pv plants part 1
 
Uwe linder reference
Uwe linder referenceUwe linder reference
Uwe linder reference
 
Untitled Presentation
Untitled PresentationUntitled Presentation
Untitled Presentation
 
Leakage current per inverter recorded
Leakage current per inverter recordedLeakage current per inverter recorded
Leakage current per inverter recorded
 
20110711 blitzschutz spezifikationen
20110711 blitzschutz spezifikationen20110711 blitzschutz spezifikationen
20110711 blitzschutz spezifikationen
 
80 MW Stringwechselrichter Lösung
80 MW Stringwechselrichter Lösung80 MW Stringwechselrichter Lösung
80 MW Stringwechselrichter Lösung
 
Transformerless inverters with thin film technology-Danfoss thin film and pid...
Transformerless inverters with thin film technology-Danfoss thin film and pid...Transformerless inverters with thin film technology-Danfoss thin film and pid...
Transformerless inverters with thin film technology-Danfoss thin film and pid...
 
Shading v02
Shading v02Shading v02
Shading v02
 
Energy Audits 2011....2018
Energy Audits 2011....2018Energy Audits 2011....2018
Energy Audits 2011....2018
 
Suntech ppt 2011 new vi template.ppt1.ppt.engl
Suntech ppt 2011 new vi template.ppt1.ppt.englSuntech ppt 2011 new vi template.ppt1.ppt.engl
Suntech ppt 2011 new vi template.ppt1.ppt.engl
 

Dernier

Unraveling Multimodality with Large Language Models.pdf
Unraveling Multimodality with Large Language Models.pdfUnraveling Multimodality with Large Language Models.pdf
Unraveling Multimodality with Large Language Models.pdfAlex Barbosa Coqueiro
 
"LLMs for Python Engineers: Advanced Data Analysis and Semantic Kernel",Oleks...
"LLMs for Python Engineers: Advanced Data Analysis and Semantic Kernel",Oleks..."LLMs for Python Engineers: Advanced Data Analysis and Semantic Kernel",Oleks...
"LLMs for Python Engineers: Advanced Data Analysis and Semantic Kernel",Oleks...Fwdays
 
Hyperautomation and AI/ML: A Strategy for Digital Transformation Success.pdf
Hyperautomation and AI/ML: A Strategy for Digital Transformation Success.pdfHyperautomation and AI/ML: A Strategy for Digital Transformation Success.pdf
Hyperautomation and AI/ML: A Strategy for Digital Transformation Success.pdfPrecisely
 
Ensuring Technical Readiness For Copilot in Microsoft 365
Ensuring Technical Readiness For Copilot in Microsoft 365Ensuring Technical Readiness For Copilot in Microsoft 365
Ensuring Technical Readiness For Copilot in Microsoft 3652toLead Limited
 
Advanced Computer Architecture – An Introduction
Advanced Computer Architecture – An IntroductionAdvanced Computer Architecture – An Introduction
Advanced Computer Architecture – An IntroductionDilum Bandara
 
"Debugging python applications inside k8s environment", Andrii Soldatenko
"Debugging python applications inside k8s environment", Andrii Soldatenko"Debugging python applications inside k8s environment", Andrii Soldatenko
"Debugging python applications inside k8s environment", Andrii SoldatenkoFwdays
 
Streamlining Python Development: A Guide to a Modern Project Setup
Streamlining Python Development: A Guide to a Modern Project SetupStreamlining Python Development: A Guide to a Modern Project Setup
Streamlining Python Development: A Guide to a Modern Project SetupFlorian Wilhelm
 
Anypoint Exchange: It’s Not Just a Repo!
Anypoint Exchange: It’s Not Just a Repo!Anypoint Exchange: It’s Not Just a Repo!
Anypoint Exchange: It’s Not Just a Repo!Manik S Magar
 
Dev Dives: Streamline document processing with UiPath Studio Web
Dev Dives: Streamline document processing with UiPath Studio WebDev Dives: Streamline document processing with UiPath Studio Web
Dev Dives: Streamline document processing with UiPath Studio WebUiPathCommunity
 
Artificial intelligence in cctv survelliance.pptx
Artificial intelligence in cctv survelliance.pptxArtificial intelligence in cctv survelliance.pptx
Artificial intelligence in cctv survelliance.pptxhariprasad279825
 
Merck Moving Beyond Passwords: FIDO Paris Seminar.pptx
Merck Moving Beyond Passwords: FIDO Paris Seminar.pptxMerck Moving Beyond Passwords: FIDO Paris Seminar.pptx
Merck Moving Beyond Passwords: FIDO Paris Seminar.pptxLoriGlavin3
 
CloudStudio User manual (basic edition):
CloudStudio User manual (basic edition):CloudStudio User manual (basic edition):
CloudStudio User manual (basic edition):comworks
 
Leverage Zilliz Serverless - Up to 50X Saving for Your Vector Storage Cost
Leverage Zilliz Serverless - Up to 50X Saving for Your Vector Storage CostLeverage Zilliz Serverless - Up to 50X Saving for Your Vector Storage Cost
Leverage Zilliz Serverless - Up to 50X Saving for Your Vector Storage CostZilliz
 
Take control of your SAP testing with UiPath Test Suite
Take control of your SAP testing with UiPath Test SuiteTake control of your SAP testing with UiPath Test Suite
Take control of your SAP testing with UiPath Test SuiteDianaGray10
 
WordPress Websites for Engineers: Elevate Your Brand
WordPress Websites for Engineers: Elevate Your BrandWordPress Websites for Engineers: Elevate Your Brand
WordPress Websites for Engineers: Elevate Your Brandgvaughan
 
Human Factors of XR: Using Human Factors to Design XR Systems
Human Factors of XR: Using Human Factors to Design XR SystemsHuman Factors of XR: Using Human Factors to Design XR Systems
Human Factors of XR: Using Human Factors to Design XR SystemsMark Billinghurst
 
SIP trunking in Janus @ Kamailio World 2024
SIP trunking in Janus @ Kamailio World 2024SIP trunking in Janus @ Kamailio World 2024
SIP trunking in Janus @ Kamailio World 2024Lorenzo Miniero
 
Transcript: New from BookNet Canada for 2024: BNC CataList - Tech Forum 2024
Transcript: New from BookNet Canada for 2024: BNC CataList - Tech Forum 2024Transcript: New from BookNet Canada for 2024: BNC CataList - Tech Forum 2024
Transcript: New from BookNet Canada for 2024: BNC CataList - Tech Forum 2024BookNet Canada
 
Powerpoint exploring the locations used in television show Time Clash
Powerpoint exploring the locations used in television show Time ClashPowerpoint exploring the locations used in television show Time Clash
Powerpoint exploring the locations used in television show Time Clashcharlottematthew16
 

Dernier (20)

E-Vehicle_Hacking_by_Parul Sharma_null_owasp.pptx
E-Vehicle_Hacking_by_Parul Sharma_null_owasp.pptxE-Vehicle_Hacking_by_Parul Sharma_null_owasp.pptx
E-Vehicle_Hacking_by_Parul Sharma_null_owasp.pptx
 
Unraveling Multimodality with Large Language Models.pdf
Unraveling Multimodality with Large Language Models.pdfUnraveling Multimodality with Large Language Models.pdf
Unraveling Multimodality with Large Language Models.pdf
 
"LLMs for Python Engineers: Advanced Data Analysis and Semantic Kernel",Oleks...
"LLMs for Python Engineers: Advanced Data Analysis and Semantic Kernel",Oleks..."LLMs for Python Engineers: Advanced Data Analysis and Semantic Kernel",Oleks...
"LLMs for Python Engineers: Advanced Data Analysis and Semantic Kernel",Oleks...
 
Hyperautomation and AI/ML: A Strategy for Digital Transformation Success.pdf
Hyperautomation and AI/ML: A Strategy for Digital Transformation Success.pdfHyperautomation and AI/ML: A Strategy for Digital Transformation Success.pdf
Hyperautomation and AI/ML: A Strategy for Digital Transformation Success.pdf
 
Ensuring Technical Readiness For Copilot in Microsoft 365
Ensuring Technical Readiness For Copilot in Microsoft 365Ensuring Technical Readiness For Copilot in Microsoft 365
Ensuring Technical Readiness For Copilot in Microsoft 365
 
Advanced Computer Architecture – An Introduction
Advanced Computer Architecture – An IntroductionAdvanced Computer Architecture – An Introduction
Advanced Computer Architecture – An Introduction
 
"Debugging python applications inside k8s environment", Andrii Soldatenko
"Debugging python applications inside k8s environment", Andrii Soldatenko"Debugging python applications inside k8s environment", Andrii Soldatenko
"Debugging python applications inside k8s environment", Andrii Soldatenko
 
Streamlining Python Development: A Guide to a Modern Project Setup
Streamlining Python Development: A Guide to a Modern Project SetupStreamlining Python Development: A Guide to a Modern Project Setup
Streamlining Python Development: A Guide to a Modern Project Setup
 
Anypoint Exchange: It’s Not Just a Repo!
Anypoint Exchange: It’s Not Just a Repo!Anypoint Exchange: It’s Not Just a Repo!
Anypoint Exchange: It’s Not Just a Repo!
 
Dev Dives: Streamline document processing with UiPath Studio Web
Dev Dives: Streamline document processing with UiPath Studio WebDev Dives: Streamline document processing with UiPath Studio Web
Dev Dives: Streamline document processing with UiPath Studio Web
 
Artificial intelligence in cctv survelliance.pptx
Artificial intelligence in cctv survelliance.pptxArtificial intelligence in cctv survelliance.pptx
Artificial intelligence in cctv survelliance.pptx
 
Merck Moving Beyond Passwords: FIDO Paris Seminar.pptx
Merck Moving Beyond Passwords: FIDO Paris Seminar.pptxMerck Moving Beyond Passwords: FIDO Paris Seminar.pptx
Merck Moving Beyond Passwords: FIDO Paris Seminar.pptx
 
CloudStudio User manual (basic edition):
CloudStudio User manual (basic edition):CloudStudio User manual (basic edition):
CloudStudio User manual (basic edition):
 
Leverage Zilliz Serverless - Up to 50X Saving for Your Vector Storage Cost
Leverage Zilliz Serverless - Up to 50X Saving for Your Vector Storage CostLeverage Zilliz Serverless - Up to 50X Saving for Your Vector Storage Cost
Leverage Zilliz Serverless - Up to 50X Saving for Your Vector Storage Cost
 
Take control of your SAP testing with UiPath Test Suite
Take control of your SAP testing with UiPath Test SuiteTake control of your SAP testing with UiPath Test Suite
Take control of your SAP testing with UiPath Test Suite
 
WordPress Websites for Engineers: Elevate Your Brand
WordPress Websites for Engineers: Elevate Your BrandWordPress Websites for Engineers: Elevate Your Brand
WordPress Websites for Engineers: Elevate Your Brand
 
Human Factors of XR: Using Human Factors to Design XR Systems
Human Factors of XR: Using Human Factors to Design XR SystemsHuman Factors of XR: Using Human Factors to Design XR Systems
Human Factors of XR: Using Human Factors to Design XR Systems
 
SIP trunking in Janus @ Kamailio World 2024
SIP trunking in Janus @ Kamailio World 2024SIP trunking in Janus @ Kamailio World 2024
SIP trunking in Janus @ Kamailio World 2024
 
Transcript: New from BookNet Canada for 2024: BNC CataList - Tech Forum 2024
Transcript: New from BookNet Canada for 2024: BNC CataList - Tech Forum 2024Transcript: New from BookNet Canada for 2024: BNC CataList - Tech Forum 2024
Transcript: New from BookNet Canada for 2024: BNC CataList - Tech Forum 2024
 
Powerpoint exploring the locations used in television show Time Clash
Powerpoint exploring the locations used in television show Time ClashPowerpoint exploring the locations used in television show Time Clash
Powerpoint exploring the locations used in television show Time Clash
 

Energy Audit Findings and Solutions

  • 1. Energy audit on site V02 September 2011-2013 Andreas Iliou TCS EEngineer All rights reserved.
  • 2. claim 1 – Power produced ,less than expected • • Client complains about less efficient system (e.g inverter A towards B ) Check strings alone and compare with each other (with Ampmeter) • Check Voltage and current (mismatch-shortcut-bypassdiode still working ?) • Voltage ok ?! Uo If Voltage is nearly the same –carry on with current • String with less voltage or current – probably shaded ? • Visual inspection of string wether shaded or not – probably dirty (birddrops)
  • 3. claim 1 – Power produced ,less than expected • Check layout of inverters • change the two inverters and check again current and voltage • If value still the same …check inverter temperature • • • if value changed , check air vent of 2nd inverter – clean if necessary Rearrange position of inverter if it gets pre heated air Change the position of the inverter and….. – check again • • • If still less efficient check cable size –keep in mind max drop < 1 % If everything ok , check loop of system and change supply line If not satisfied with measurement
  • 4. claim 1 – Power produced ,less than expected Measurements : 1) Visual Inspection cells or cracks – if ok 2) Check voltage of different strings e.g 80V DC less ?? 3) Measure current: module is producing 1,5A other strings produce 2,3-2,4A instead ….check with label – backside If the system is not shaded , carry on with thermal image
  • 5. claim 1 – Power produced ,less than expected Hotspot issue: 4) Thermal image from the front view 5) If it s problematic- clean surface and make another pic from the back
  • 6. claim 1 – Power produced ,less than expected Solution : 6) Visual inspection if the module shows same hotspot from back and front view: No visual crack or hotspot to be seen Outcome of inspection e.g: - J-boxes show hotspots as well More than one cell shows hotspot issues E.g Voltage measured is only 2/3 of Uo (28V actual reading <-> 44V DC labelled) Diode is defect j-box must be changed
  • 7. claim 2 – Power produced ,less than previous years Claim 2: check if the system is shaded or dirty – if not ?! are the cables damaged or defect- if not?! check with Tool like ( Tri Ka ) and compare with existing datas from prev. years check corrosion or weak connections are their any shortcuts ( modules or bypassdiodes )- if not ?! cell damage in the module- cracks shortcut inside j-box ( water ) – if not ?! problem of degradation ?! how old is the system- output power still as expected ?!
  • 8. claim 3 –No power produced during daytime Claim 3: meter not turning at all is it still cloudy or dark outside ?! check dc switch – or + broken – if not ?! check AC breaker or earth leakage tester – if not ?! check over protection unit -> shortcut – if not ?! measure strings seperately problem with frequency –if not ?! check voltage of each phase –if not ?! No DC supply: Probaly to dark or less starting voltage Inverter or tracker damaged Fault on iso, check each string individually