PLUG N’ PLAY NETWORK 
SOLUTIONS 
EST. 2014
Brandon Waymire- Project Leader 
Andrew Stefan- Support Specialist 
Rafael Cortes- Support Specialist
We were recently approached by a local car 
dealership, Roman Motors Inc. Mr. Roman 
informed us that he feels it is time to take 
the steps, to expand his business by adding 
the network tools he desperately needs.
Using technology to maximize your business 
productivity creates the platform to realize true 
business success. Business productivity through 
technology ensures organizations have the tools to 
overcome the challenges of executing on strategy 
every day and prospering in today's economic times
What can technology do for 
your business? 
Create an open and 
communicative environment. 
Connect teams virtually within 
the company. 
Motivate your employees using 
technology. 
Monitor business productivity 
and employee progress on goals. 
Analyze performance
 Clarity, poise, enthusiasm, connection with the 
audience.
Scope Of Project 
• Meet with Mr. Roman to discuss recommendation of the 
best business package from his local Internet Service 
Provider. 
• Design a WAN infrastructure that will connect Roman 
motors main site to each of the other two sites, securely. 
• Configuration of media room components. 
• Training for up to 10 employees for 2 hours, on how to 
operate all equipment we have installed. I.E. Kiosk 
operation, connecting to each site through media room 
live streaming, basic file sharing software operation. 
(More training can be provided upon implementation of 
separate contract.) 
• Install software and OS’s on all machines purchased 
through Plug N’ Play, including hypervisors. 
• Installation of wireless access points at all 3 sites.
 Have multiple bundle packages to pick from for 
future IT management by our company. Provide 
backup options, disaster recovery solutions, and 
24 hour emergency on-site response, are some of 
the packages we would like offer to you. 
 . Monitoring security camera’s depends on 
package selection. 
 Physical cabling by 3rd party company for 
infrared installation. 
 Media room cable, and physical screen 
installation. 
Out of Scope
Key Stakeholders 
 Mr. Henk Robinson-Chairman/Head IT @ Itt Tech West 
Palm Beach 
 Mr. Roman- Owner Roman Motors Inc. 
 ISP- Comcast Business Class 
 Lorex security cameras 
 Printers/Cpus—Gateway 
 Wireless Access Point 
--Retailers
Net Work Simulation
Cost Summary 
Main Office: 
 -Main firewall (additional back up firewall pre 
configured for redundancy) (565) 2=1130$ 
-50 slots (POE if VOIP or security cameras need to be) 
(700$) 
 -Hypervisor x 2 (rack mountable or towers) (1500$) 
x2=3000.00 
-Wireless access point. (75-115$) 
-Server size Battery backup 2-3 (97$) x2= 194 
-Workstation Battery Backups. 20 (58$ each) 
x20=1,160.00 
-workstations 20 (470$) x20 9,400.00 
-Workstations /Monitors dual or single 20 single(47$) 
x20=940.00 
-Kiosks stations 3-4. (300$) x4=1,200.00 
-Camera system (1k-2k) 
-Printers 2-3 (200-500$) 
 Media room screen and components $3,000*3 sites 
=30,000.00 rough est.
 
Office 1 
Office 1 
-Main firewall (additional back up firewall pre configured 
for redundancy) (565) 
-16 slots (POE if VOIP or security cameras need to be) 
(190$) 
 -Hypervisor x 2 (rack mountable or towers) (1500$) 
-Wireless access point. (75-115$) 
-Server size Battery backup 2-3 (97$) 
-Workstation Battery Backups. 7 (58$ each) 
-Workstations /Monitors dual or single 7 single(47$) 
-Kiosks stations 3-4. (300$) 
-workstations 7 (470$) 
-Camera system (1k-2k) -Printers 2-3 (200-500$) 
 =14000.00 rough est. 
Software Office 365 9$ per computer 
 Microsoft hosted outlook 5$ per person
Office 2 
Office 2 
-Main firewall (additional back up firewall pre configured 
for redundancy) (565$) 
-16 slots (POE if VOIP or security cameras need to be) 
(190$) 
-Hypervisor x 2 (rack mountable or towers) (1500$) 
-Wireless access point. (75-115$) 
-Server size Battery backup 2-3 (97$) 
-Workstation Battery Backups. 7 (58$ each) 
-Workstations /Monitors dual or single 7 single(47$) 
-Kiosks stations 3-4. (300$) 
-Camera system (1k-2k) 
-Printers 2-3 (200-500$) 
-workstations 7 (470$) 
=14000.00 rough est
Available Packages 
 Gold -1,475.00 
All monitoring and backups included Service 
calls are paid per month instead of hourly. 
And after hours support is included within the 
monthly rate. 
And free bi monthly security audit, with one 
onsite security check, twice a year. 
 Silver- 1,150.00 
All monitoring and backups included Service 
calls are paid per month instead of hourly. 
After hours tech support fee still required. 
 Bronze –Pay as you go services. 
Backups 200$ per site 
Monitoring 5$ per workstation. 
10$ per server 
830$ a month service calls 115$ per hour 
minimum hour per onsite time per call.
Risk Management 
Completing physical cabling by 
configuration of software start 
date. 
Kiosk, printer, computer, security 
camera, delivery times. 
Secure contracts through vendors 
to ensure costs and materials are 
definitive. 
Allow adequate time for damaged 
goods to be expedited.
Majority of work and install 
needs to be completed during the 
stores “off hours.” 
Cost 
Time 
Manpower 
Building codes & regulations 
Constraints
Task Mode Task Name Duration Start Finish 
Auto Scheduled Roman Motors Site Proposal 28 days Sat 11/15/14 Wed 12/24/14 
Manually Scheduled Customer Contact 0 days Sat 11/15/14 Sat 11/15/14 
Manually Scheduled ISP RECCOMENDATION/ INITIAL MEET AND GREET 1 day Sat 11/15/14 Sat 11/15/14 
Manually Scheduled VISIT PHYSICAL LOCATIONS 5 days Mon 11/17/14 Fri 11/21/14 
Manually Scheduled CREATE LOGICAL DESIGN 3 days Mon 11/24/14 Wed 11/26/14 
Manually Scheduled Customer Agreement 0 days Thu 11/27/14 Thu 11/27/14 
Manually Scheduled ALL STAKEHOLDERS SIGN OFF ON DESIGN 1 day Thu 11/27/14 Thu 11/27/14 
Manually Scheduled CREATE STATEMENT OF SALES INVENTORY REPORT 1 day Thu 11/27/14 Thu 11/27/14 
Manually Scheduled MEETING FOR ANY COST CHANGES 0 days Fri 11/28/14 Fri 11/28/14 
Manually Scheduled STAKEHOLDER FINAL COST APPROVAL ON HARDWARE 0 days Fri 11/28/14 Fri 11/28/14 
Manually Scheduled Initial Setup 10 days Mon 12/1/14 Fri 12/12/14 
Manually Scheduled PURCHASE EQUIPMENT 11 days Mon 12/1/14 Sat 12/13/14 
Manually Scheduled CABLING INSTALLATION 11 days Mon 12/1/14 Sat 12/13/14 
Manually Scheduled SOFTWARE INSTALLATION 11 days Mon 12/1/14 Sat 12/13/14 
Manually Scheduled MEDIA ROOM INSTALL 1 day Sat 12/13/14 Sat 12/13/14 
Manually Scheduled HARDWARE SETUP AND INSTALL 1 day Sat 12/13/14 Sat 12/13/14 
Manually Scheduled WAP INSTALL 1 day Sat 12/13/14 Sat 12/13/14 
Manually Scheduled NETWORK RESOLUTION AND SYSTEM INITIAL TESTING 9 days Sat 12/13/14 Wed 12/24/14 
Manually Scheduled Training 1 day Wed 11/26/14 Wed 11/26/14 
Manually Scheduled TRAINING I--MAIN OFFICE 1 day Wed 11/26/14 Wed 11/26/14 
Manually Scheduled TRAINING II--SITE 1 1 day Wed 11/26/14 Wed 11/26/14 
Manually Scheduled TRAINING III--SITE 2 1 day Wed 11/26/14 Wed 11/26/14 
Manually Scheduled FINAL CUSTOMER SATISFACTION MEETING 1 day Tue 12/30/14 Tue 12/30/14 
Manually Scheduled countining service(Goldpackage) Tue 12/30/14
PREPARED BY ANDREW STEFAN 
10/20/2014

Contenu connexe

En vedette

18 листопада
18 листопада18 листопада
18 листопадаYura8222
 
NSC2015 - my pitstop & your kickoff
NSC2015 - my pitstop & your kickoffNSC2015 - my pitstop & your kickoff
NSC2015 - my pitstop & your kickoffAIESEC UNDIP
 
Intranet Strategy and Design Presentation
Intranet Strategy and Design PresentationIntranet Strategy and Design Presentation
Intranet Strategy and Design PresentationMark Waldo
 
Navigating the SAP HR Technology Landscape
Navigating the SAP HR Technology LandscapeNavigating the SAP HR Technology Landscape
Navigating the SAP HR Technology LandscapeNGA Human Resources
 
Design Thinking Workshop - By the people for the people
Design Thinking Workshop - By the people for the peopleDesign Thinking Workshop - By the people for the people
Design Thinking Workshop - By the people for the peopleRafael Citadella Daron
 
Penn personas v2.2
Penn personas v2.2Penn personas v2.2
Penn personas v2.2Mark Waldo
 

En vedette (9)

18 листопада
18 листопада18 листопада
18 листопада
 
NSC2015 - my pitstop & your kickoff
NSC2015 - my pitstop & your kickoffNSC2015 - my pitstop & your kickoff
NSC2015 - my pitstop & your kickoff
 
MS Outlook Training 2007
MS Outlook Training 2007MS Outlook Training 2007
MS Outlook Training 2007
 
Intranet Strategy and Design Presentation
Intranet Strategy and Design PresentationIntranet Strategy and Design Presentation
Intranet Strategy and Design Presentation
 
Navigating the SAP HR Technology Landscape
Navigating the SAP HR Technology LandscapeNavigating the SAP HR Technology Landscape
Navigating the SAP HR Technology Landscape
 
40 Ict Ideas In 40 Minutes
40 Ict Ideas In 40 Minutes40 Ict Ideas In 40 Minutes
40 Ict Ideas In 40 Minutes
 
71 ICT Ideas in Education
71 ICT Ideas in Education71 ICT Ideas in Education
71 ICT Ideas in Education
 
Design Thinking Workshop - By the people for the people
Design Thinking Workshop - By the people for the peopleDesign Thinking Workshop - By the people for the people
Design Thinking Workshop - By the people for the people
 
Penn personas v2.2
Penn personas v2.2Penn personas v2.2
Penn personas v2.2
 

Similaire à PLUG N’ PLAY NETWORK SOLUTIONS PRESENTATION 1

Adi telecom digital notice boards and hs reporting solution - v2 jan 2016
Adi telecom   digital notice boards and hs reporting solution - v2 jan 2016Adi telecom   digital notice boards and hs reporting solution - v2 jan 2016
Adi telecom digital notice boards and hs reporting solution - v2 jan 2016Steve Farmer MBA
 
Cyberdyne systems (2)
Cyberdyne systems (2)Cyberdyne systems (2)
Cyberdyne systems (2)Bryan Moss
 
Ahmed Hosny Resume
Ahmed Hosny ResumeAhmed Hosny Resume
Ahmed Hosny ResumeAhmed Hosni
 
David Schaal oct 14 word doc
David Schaal oct 14 word docDavid Schaal oct 14 word doc
David Schaal oct 14 word docDavid Schaal
 
This is my test slideshare
This is my test slideshareThis is my test slideshare
This is my test slidesharepapdev
 
DR Planning and Testing
DR Planning and TestingDR Planning and Testing
DR Planning and TestingJason Dea
 
Wong Kien Hoe Resume
Wong Kien Hoe ResumeWong Kien Hoe Resume
Wong Kien Hoe ResumeKien Hoe Wong
 
N-able webinar:Build recurring revenue in 45 days
N-able webinar:Build recurring revenue in 45 daysN-able webinar:Build recurring revenue in 45 days
N-able webinar:Build recurring revenue in 45 daysSolarwinds N-able
 
Network & System Engineer
Network & System EngineerNetwork & System Engineer
Network & System EngineerPinki Rajput
 

Similaire à PLUG N’ PLAY NETWORK SOLUTIONS PRESENTATION 1 (20)

RussellMannResume
RussellMannResumeRussellMannResume
RussellMannResume
 
cv
cv cv
cv
 
Mohamed A Barakat CV -
Mohamed A Barakat CV -Mohamed A Barakat CV -
Mohamed A Barakat CV -
 
Adi telecom digital notice boards and hs reporting solution - v2 jan 2016
Adi telecom   digital notice boards and hs reporting solution - v2 jan 2016Adi telecom   digital notice boards and hs reporting solution - v2 jan 2016
Adi telecom digital notice boards and hs reporting solution - v2 jan 2016
 
SHABAB`S RESUME
SHABAB`S RESUMESHABAB`S RESUME
SHABAB`S RESUME
 
CV_RomRes_2015_V9
CV_RomRes_2015_V9CV_RomRes_2015_V9
CV_RomRes_2015_V9
 
Cyberdyne systems (2)
Cyberdyne systems (2)Cyberdyne systems (2)
Cyberdyne systems (2)
 
Ahmed Hosny Resume
Ahmed Hosny ResumeAhmed Hosny Resume
Ahmed Hosny Resume
 
resume2017
resume2017resume2017
resume2017
 
Willie Campbell III (1)
Willie Campbell III (1)Willie Campbell III (1)
Willie Campbell III (1)
 
David Schaal oct 14 word doc
David Schaal oct 14 word docDavid Schaal oct 14 word doc
David Schaal oct 14 word doc
 
This is my test slideshare
This is my test slideshareThis is my test slideshare
This is my test slideshare
 
Maninder_singh
Maninder_singhManinder_singh
Maninder_singh
 
Maninder_singh
Maninder_singhManinder_singh
Maninder_singh
 
DR Planning and Testing
DR Planning and TestingDR Planning and Testing
DR Planning and Testing
 
ENG-Islam-CV
ENG-Islam-CV ENG-Islam-CV
ENG-Islam-CV
 
ramyelkady
ramyelkadyramyelkady
ramyelkady
 
Wong Kien Hoe Resume
Wong Kien Hoe ResumeWong Kien Hoe Resume
Wong Kien Hoe Resume
 
N-able webinar:Build recurring revenue in 45 days
N-able webinar:Build recurring revenue in 45 daysN-able webinar:Build recurring revenue in 45 days
N-able webinar:Build recurring revenue in 45 days
 
Network & System Engineer
Network & System EngineerNetwork & System Engineer
Network & System Engineer
 

PLUG N’ PLAY NETWORK SOLUTIONS PRESENTATION 1

  • 1.
  • 2. { PLUG N’ PLAY NETWORK SOLUTIONS EST. 2014
  • 3. Brandon Waymire- Project Leader Andrew Stefan- Support Specialist Rafael Cortes- Support Specialist
  • 4. We were recently approached by a local car dealership, Roman Motors Inc. Mr. Roman informed us that he feels it is time to take the steps, to expand his business by adding the network tools he desperately needs.
  • 5. Using technology to maximize your business productivity creates the platform to realize true business success. Business productivity through technology ensures organizations have the tools to overcome the challenges of executing on strategy every day and prospering in today's economic times
  • 6. What can technology do for your business? Create an open and communicative environment. Connect teams virtually within the company. Motivate your employees using technology. Monitor business productivity and employee progress on goals. Analyze performance
  • 7.  Clarity, poise, enthusiasm, connection with the audience.
  • 8. Scope Of Project • Meet with Mr. Roman to discuss recommendation of the best business package from his local Internet Service Provider. • Design a WAN infrastructure that will connect Roman motors main site to each of the other two sites, securely. • Configuration of media room components. • Training for up to 10 employees for 2 hours, on how to operate all equipment we have installed. I.E. Kiosk operation, connecting to each site through media room live streaming, basic file sharing software operation. (More training can be provided upon implementation of separate contract.) • Install software and OS’s on all machines purchased through Plug N’ Play, including hypervisors. • Installation of wireless access points at all 3 sites.
  • 9.  Have multiple bundle packages to pick from for future IT management by our company. Provide backup options, disaster recovery solutions, and 24 hour emergency on-site response, are some of the packages we would like offer to you.  . Monitoring security camera’s depends on package selection.  Physical cabling by 3rd party company for infrared installation.  Media room cable, and physical screen installation. Out of Scope
  • 10. Key Stakeholders  Mr. Henk Robinson-Chairman/Head IT @ Itt Tech West Palm Beach  Mr. Roman- Owner Roman Motors Inc.  ISP- Comcast Business Class  Lorex security cameras  Printers/Cpus—Gateway  Wireless Access Point --Retailers
  • 11.
  • 13. Cost Summary Main Office:  -Main firewall (additional back up firewall pre configured for redundancy) (565) 2=1130$ -50 slots (POE if VOIP or security cameras need to be) (700$)  -Hypervisor x 2 (rack mountable or towers) (1500$) x2=3000.00 -Wireless access point. (75-115$) -Server size Battery backup 2-3 (97$) x2= 194 -Workstation Battery Backups. 20 (58$ each) x20=1,160.00 -workstations 20 (470$) x20 9,400.00 -Workstations /Monitors dual or single 20 single(47$) x20=940.00 -Kiosks stations 3-4. (300$) x4=1,200.00 -Camera system (1k-2k) -Printers 2-3 (200-500$)  Media room screen and components $3,000*3 sites =30,000.00 rough est.
  • 14.  Office 1 Office 1 -Main firewall (additional back up firewall pre configured for redundancy) (565) -16 slots (POE if VOIP or security cameras need to be) (190$)  -Hypervisor x 2 (rack mountable or towers) (1500$) -Wireless access point. (75-115$) -Server size Battery backup 2-3 (97$) -Workstation Battery Backups. 7 (58$ each) -Workstations /Monitors dual or single 7 single(47$) -Kiosks stations 3-4. (300$) -workstations 7 (470$) -Camera system (1k-2k) -Printers 2-3 (200-500$)  =14000.00 rough est. Software Office 365 9$ per computer  Microsoft hosted outlook 5$ per person
  • 15. Office 2 Office 2 -Main firewall (additional back up firewall pre configured for redundancy) (565$) -16 slots (POE if VOIP or security cameras need to be) (190$) -Hypervisor x 2 (rack mountable or towers) (1500$) -Wireless access point. (75-115$) -Server size Battery backup 2-3 (97$) -Workstation Battery Backups. 7 (58$ each) -Workstations /Monitors dual or single 7 single(47$) -Kiosks stations 3-4. (300$) -Camera system (1k-2k) -Printers 2-3 (200-500$) -workstations 7 (470$) =14000.00 rough est
  • 16. Available Packages  Gold -1,475.00 All monitoring and backups included Service calls are paid per month instead of hourly. And after hours support is included within the monthly rate. And free bi monthly security audit, with one onsite security check, twice a year.  Silver- 1,150.00 All monitoring and backups included Service calls are paid per month instead of hourly. After hours tech support fee still required.  Bronze –Pay as you go services. Backups 200$ per site Monitoring 5$ per workstation. 10$ per server 830$ a month service calls 115$ per hour minimum hour per onsite time per call.
  • 17.
  • 18.
  • 19. Risk Management Completing physical cabling by configuration of software start date. Kiosk, printer, computer, security camera, delivery times. Secure contracts through vendors to ensure costs and materials are definitive. Allow adequate time for damaged goods to be expedited.
  • 20. Majority of work and install needs to be completed during the stores “off hours.” Cost Time Manpower Building codes & regulations Constraints
  • 21. Task Mode Task Name Duration Start Finish Auto Scheduled Roman Motors Site Proposal 28 days Sat 11/15/14 Wed 12/24/14 Manually Scheduled Customer Contact 0 days Sat 11/15/14 Sat 11/15/14 Manually Scheduled ISP RECCOMENDATION/ INITIAL MEET AND GREET 1 day Sat 11/15/14 Sat 11/15/14 Manually Scheduled VISIT PHYSICAL LOCATIONS 5 days Mon 11/17/14 Fri 11/21/14 Manually Scheduled CREATE LOGICAL DESIGN 3 days Mon 11/24/14 Wed 11/26/14 Manually Scheduled Customer Agreement 0 days Thu 11/27/14 Thu 11/27/14 Manually Scheduled ALL STAKEHOLDERS SIGN OFF ON DESIGN 1 day Thu 11/27/14 Thu 11/27/14 Manually Scheduled CREATE STATEMENT OF SALES INVENTORY REPORT 1 day Thu 11/27/14 Thu 11/27/14 Manually Scheduled MEETING FOR ANY COST CHANGES 0 days Fri 11/28/14 Fri 11/28/14 Manually Scheduled STAKEHOLDER FINAL COST APPROVAL ON HARDWARE 0 days Fri 11/28/14 Fri 11/28/14 Manually Scheduled Initial Setup 10 days Mon 12/1/14 Fri 12/12/14 Manually Scheduled PURCHASE EQUIPMENT 11 days Mon 12/1/14 Sat 12/13/14 Manually Scheduled CABLING INSTALLATION 11 days Mon 12/1/14 Sat 12/13/14 Manually Scheduled SOFTWARE INSTALLATION 11 days Mon 12/1/14 Sat 12/13/14 Manually Scheduled MEDIA ROOM INSTALL 1 day Sat 12/13/14 Sat 12/13/14 Manually Scheduled HARDWARE SETUP AND INSTALL 1 day Sat 12/13/14 Sat 12/13/14 Manually Scheduled WAP INSTALL 1 day Sat 12/13/14 Sat 12/13/14 Manually Scheduled NETWORK RESOLUTION AND SYSTEM INITIAL TESTING 9 days Sat 12/13/14 Wed 12/24/14 Manually Scheduled Training 1 day Wed 11/26/14 Wed 11/26/14 Manually Scheduled TRAINING I--MAIN OFFICE 1 day Wed 11/26/14 Wed 11/26/14 Manually Scheduled TRAINING II--SITE 1 1 day Wed 11/26/14 Wed 11/26/14 Manually Scheduled TRAINING III--SITE 2 1 day Wed 11/26/14 Wed 11/26/14 Manually Scheduled FINAL CUSTOMER SATISFACTION MEETING 1 day Tue 12/30/14 Tue 12/30/14 Manually Scheduled countining service(Goldpackage) Tue 12/30/14
  • 22. PREPARED BY ANDREW STEFAN 10/20/2014

Notes de l'éditeur

  1. Introduction
  2. Business Case The reason for pursuing the project. This should include the background, history, stakeholders, etc.
  3. Verbal communication
  4. Scope
  5. Solution approach
  6. Slide Quality