SlideShare une entreprise Scribd logo
1  sur  11
Télécharger pour lire hors ligne
By Safi Qudsi
Realities of Business World
  New Satellite Program Major Delays

                          US Govt. faced
                          $3 billion in cost
                          overruns and a
                          three-year delay
                          in new satellite
                          program for
                          Hurricane &
                          severe weather
                          tracking.
Realities of Business World
               FoxMeyer Drugs Bankruptcy
In 1993, FoxMeyer Drugs was the
fourth largest distributor of
pharmaceuticals in the U.S., worth $5
billion. In an attempt to increase
efficiency, FoxMeyer purchased an SAP
system and a warehouse automation
system it what was supposed to be a
$35 million project. By 1996, due to
number of issues the company was
bankrupt; it was eventually sold to a
competitor for a mere $80 million.
RISK BASED QUALITY MANAGEMENT SYSTEM
              AUDITING
Definitions of Risk



Combination of the probability of an event and its consequence
(ISO DGUIDE 73)


The chance of something happening that will have an impact
upon objectives. It is measured in terms of consequences and
likelihood. (AS/NZS 4360)
Risk in Simple Words




Risk = Likelihood X Consequence
Risk Management
Acceptance/Tolerance: With or without planning of contingency.

Reduce likelihood or consequence: By establishing processes
and controls


  Analysis, evaluation and assessment
   of risk and its rational control in
   helping to promote the objectives
      and targets of the business
Risk Based Quality Management System
               Auditing

                        Auditor typical
                        role was limited
                        to documenting
                        audit findings
                        including non-
                        conformances
                        (if any)
Risk Based Quality Management System
                 Auditing


                                       VALUE ADDED
 Auditing     QMS         Risk    =       AUDIT



Management tool to prioritize the issues accordingly
SCORING TABLE: RISK BASED CONFORMANCE AUDIT & SCORING SYSTEM
               Quality Management System                                    Conformance
                                                                                                  Risk Classification
  Clause /                                                                      Score
Sub-Clauses    ISO 9001:2008 Standard Requirements                          Clause   Sub Clause
                                                                            Score      Score       H      M      L
7             Product Realization
    7.1       Planning of product realization
    7.2       Customer-related processes (Title)

      7.2.1          Determination of requirements related to product
      7.2.2         Review of the requirements related to the product
      7.2.3                                   Customer communication
    7.3     Design and Development (Title)
      7.3.1                         Design and Development Planning
      7.3.2                             Design and Development Input
      7.3.3                           Design and Development Output
      7.3.4                           Design and Development Review
      7.3.5                       Design and Development Verification
      7.3.6                        Design and Development Validation
      7.3.7                          Design and Development Changes
    7.4     Purchasing (Title)
      7.4.1                                          Purchasing Process
      7.4.2                                      Purchasing Information
      7.4.3                         Validation of Purchase Information
    7.5     Product and Service Provision (Title)
      7.5.1                    Control of product and service provision
                       Validation of processes for production and service
      7.5.2                                      provision Information
      7.5.3                             Identification and traceability
      7.5.4                                        Customer Property
      7.5.5                                   Preservation of product
    7.6     Control of monitoring and measuring equipment
Post Audit Activities

• Decisions based                  • Plan to reduce
  on analysis and                    Risks identified
  monitoring                         in audit.
  results.                           Improvement of
• Actions taken                      processes &
                                     controls

                     ACT    PLAN



                    CHECK   DO
• Indicators &                     • Implementation
  Measurement.                       of planned
• Audit                              actions

Contenu connexe

Tendances

Internal audit strategy for non-profits
Internal audit strategy for non-profitsInternal audit strategy for non-profits
Internal audit strategy for non-profitsDebashis Gupta
 
A Presentation on Risk Based Auditing
A Presentation on Risk Based AuditingA Presentation on Risk Based Auditing
A Presentation on Risk Based AuditingAmar Deep Ghimire
 
Internal Audit Methodology
Internal Audit MethodologyInternal Audit Methodology
Internal Audit MethodologyManoj Agarwal
 
Introduction to internal auditing
Introduction to internal auditingIntroduction to internal auditing
Introduction to internal auditingDavid Griffiths
 
Application Security Review 5 Dec 09 Final
Application Security Review 5 Dec 09 FinalApplication Security Review 5 Dec 09 Final
Application Security Review 5 Dec 09 FinalManoj Agarwal
 
Approach note on internal audit [compatibility mode]
Approach note on internal audit [compatibility mode]Approach note on internal audit [compatibility mode]
Approach note on internal audit [compatibility mode]Deep Kumar Mendiratta
 
Basic internal auditing
Basic internal auditingBasic internal auditing
Basic internal auditingKhalid Aziz
 
Ppt on risk based internal audit
Ppt on risk based internal auditPpt on risk based internal audit
Ppt on risk based internal auditAmitaMistry2
 
Eeoqms internal auditing
Eeoqms internal auditingEeoqms internal auditing
Eeoqms internal auditinghardeep singh
 
New approaches in internal audit
New approaches in internal auditNew approaches in internal audit
New approaches in internal auditSalih Islam
 
The state of ia pandemic plan
The state of ia  pandemic planThe state of ia  pandemic plan
The state of ia pandemic planManoj Agarwal
 
Integrating Data Analytics into a Risk-Based Audit Plan
Integrating Data Analytics into a Risk-Based Audit PlanIntegrating Data Analytics into a Risk-Based Audit Plan
Integrating Data Analytics into a Risk-Based Audit PlanCaseWare IDEA
 
Standards of Internal Audit
Standards of Internal AuditStandards of Internal Audit
Standards of Internal AuditKaran Puri
 
Measuring Institional Effectiveness by Performance Audit
Measuring Institional Effectiveness by Performance AuditMeasuring Institional Effectiveness by Performance Audit
Measuring Institional Effectiveness by Performance AuditShantanu Basu
 

Tendances (20)

Risk based internal auditing
 Risk based internal auditing Risk based internal auditing
Risk based internal auditing
 
Internal audit strategy for non-profits
Internal audit strategy for non-profitsInternal audit strategy for non-profits
Internal audit strategy for non-profits
 
A Presentation on Risk Based Auditing
A Presentation on Risk Based AuditingA Presentation on Risk Based Auditing
A Presentation on Risk Based Auditing
 
Internal audit
Internal auditInternal audit
Internal audit
 
Internal Audit Methodology
Internal Audit MethodologyInternal Audit Methodology
Internal Audit Methodology
 
Introduction to internal auditing
Introduction to internal auditingIntroduction to internal auditing
Introduction to internal auditing
 
Basics of internal audit
Basics of internal auditBasics of internal audit
Basics of internal audit
 
Application Security Review 5 Dec 09 Final
Application Security Review 5 Dec 09 FinalApplication Security Review 5 Dec 09 Final
Application Security Review 5 Dec 09 Final
 
Approach note on internal audit [compatibility mode]
Approach note on internal audit [compatibility mode]Approach note on internal audit [compatibility mode]
Approach note on internal audit [compatibility mode]
 
Internal Audit Manual
Internal Audit ManualInternal Audit Manual
Internal Audit Manual
 
SFC Plan of engagement
SFC Plan of engagementSFC Plan of engagement
SFC Plan of engagement
 
Presentation 6, Steps of system based auditing, Workshop on System-based audi...
Presentation 6, Steps of system based auditing, Workshop on System-based audi...Presentation 6, Steps of system based auditing, Workshop on System-based audi...
Presentation 6, Steps of system based auditing, Workshop on System-based audi...
 
Basic internal auditing
Basic internal auditingBasic internal auditing
Basic internal auditing
 
Ppt on risk based internal audit
Ppt on risk based internal auditPpt on risk based internal audit
Ppt on risk based internal audit
 
Eeoqms internal auditing
Eeoqms internal auditingEeoqms internal auditing
Eeoqms internal auditing
 
New approaches in internal audit
New approaches in internal auditNew approaches in internal audit
New approaches in internal audit
 
The state of ia pandemic plan
The state of ia  pandemic planThe state of ia  pandemic plan
The state of ia pandemic plan
 
Integrating Data Analytics into a Risk-Based Audit Plan
Integrating Data Analytics into a Risk-Based Audit PlanIntegrating Data Analytics into a Risk-Based Audit Plan
Integrating Data Analytics into a Risk-Based Audit Plan
 
Standards of Internal Audit
Standards of Internal AuditStandards of Internal Audit
Standards of Internal Audit
 
Measuring Institional Effectiveness by Performance Audit
Measuring Institional Effectiveness by Performance AuditMeasuring Institional Effectiveness by Performance Audit
Measuring Institional Effectiveness by Performance Audit
 

En vedette (18)

Risk Based Audit Approach
Risk Based Audit ApproachRisk Based Audit Approach
Risk Based Audit Approach
 
Proposal risk based internal audit 2013
Proposal risk based internal audit 2013Proposal risk based internal audit 2013
Proposal risk based internal audit 2013
 
Quality Risk Management
Quality Risk ManagementQuality Risk Management
Quality Risk Management
 
Quality Risk management Application of FMEA
Quality Risk management  Application of FMEAQuality Risk management  Application of FMEA
Quality Risk management Application of FMEA
 
Risk Management For Manufacturing
Risk Management For ManufacturingRisk Management For Manufacturing
Risk Management For Manufacturing
 
It 381 chap 7
It 381 chap 7It 381 chap 7
It 381 chap 7
 
Fmea Innovator - Step by Step
Fmea Innovator - Step by StepFmea Innovator - Step by Step
Fmea Innovator - Step by Step
 
Equipment audit
Equipment auditEquipment audit
Equipment audit
 
FMEA_BAL_Deepak_Sahoo
FMEA_BAL_Deepak_SahooFMEA_BAL_Deepak_Sahoo
FMEA_BAL_Deepak_Sahoo
 
Quality risk management
Quality risk managementQuality risk management
Quality risk management
 
Integrated quality and risk management
Integrated quality and risk managementIntegrated quality and risk management
Integrated quality and risk management
 
Fmea design la
Fmea design laFmea design la
Fmea design la
 
Fmea Presentation 2
Fmea Presentation 2Fmea Presentation 2
Fmea Presentation 2
 
Failure Mode and Effects Analysis WithAdrian™ FMEA 2013 Adrian Beale
Failure Mode and Effects Analysis WithAdrian™ FMEA 2013 Adrian BealeFailure Mode and Effects Analysis WithAdrian™ FMEA 2013 Adrian Beale
Failure Mode and Effects Analysis WithAdrian™ FMEA 2013 Adrian Beale
 
Who Guidance on Quality Risk Management
Who Guidance on Quality Risk ManagementWho Guidance on Quality Risk Management
Who Guidance on Quality Risk Management
 
Menyampaikan Kabar Buruk dengan Protokol SPIKES
Menyampaikan Kabar Buruk dengan Protokol SPIKESMenyampaikan Kabar Buruk dengan Protokol SPIKES
Menyampaikan Kabar Buruk dengan Protokol SPIKES
 
DEVELOPING AN ICT RISK REGISTER
DEVELOPING AN ICT RISK REGISTERDEVELOPING AN ICT RISK REGISTER
DEVELOPING AN ICT RISK REGISTER
 
QM-085-Design Andd Process Fmea
QM-085-Design Andd Process FmeaQM-085-Design Andd Process Fmea
QM-085-Design Andd Process Fmea
 

Similaire à Risk Based Quality Management System Auditing

Six sigma as foundation to cmmi
Six sigma as foundation to cmmiSix sigma as foundation to cmmi
Six sigma as foundation to cmmiKobi Vider
 
Skyward Erp Presentation
Skyward Erp PresentationSkyward Erp Presentation
Skyward Erp Presentationvishalnvora1
 
Quality Systems Investigation Technique
Quality Systems Investigation TechniqueQuality Systems Investigation Technique
Quality Systems Investigation TechniqueMitchell Manning Sr.
 
CA Quality Management System
CA Quality Management SystemCA Quality Management System
CA Quality Management SystemWahyu Prasetianto
 
Quality Management System ISO 9001 Interpretation and Internal Audit
Quality Management System ISO 9001 Interpretation and Internal AuditQuality Management System ISO 9001 Interpretation and Internal Audit
Quality Management System ISO 9001 Interpretation and Internal AuditDinar Surtikarani
 
Calibration of MMDs to meet QMS
Calibration of MMDs to meet QMSCalibration of MMDs to meet QMS
Calibration of MMDs to meet QMSAmsavel Vel
 
Best Practices Frameworks 101
Best Practices Frameworks 101Best Practices Frameworks 101
Best Practices Frameworks 101shailsood
 
Integrated methodology for testing and quality management.
Integrated methodology for testing and quality management.Integrated methodology for testing and quality management.
Integrated methodology for testing and quality management.Mindtree Ltd.
 
Agile and CMMI
Agile and CMMIAgile and CMMI
Agile and CMMIAgileee
 
Basic Internal Auditing Presentation
Basic Internal Auditing PresentationBasic Internal Auditing Presentation
Basic Internal Auditing PresentationVernon Benjamin
 
Transition to ISO 13485:2016
Transition to ISO 13485:2016Transition to ISO 13485:2016
Transition to ISO 13485:2016Carlin Jannine
 
Pmbok 4th edition chapter 8 - Project Quality Management
Pmbok 4th edition   chapter 8 - Project Quality Management Pmbok 4th edition   chapter 8 - Project Quality Management
Pmbok 4th edition chapter 8 - Project Quality Management Ahmad Maharma, PMP,RMP
 
Incorporate CPV and Continual Improvement into your Validation Plan
Incorporate CPV and Continual Improvement into your Validation PlanIncorporate CPV and Continual Improvement into your Validation Plan
Incorporate CPV and Continual Improvement into your Validation PlanInstitute of Validation Technology
 
Online PMP Training Material for PMP Exam - Quality Management Knowledge Area
Online PMP Training Material for PMP Exam - Quality Management Knowledge AreaOnline PMP Training Material for PMP Exam - Quality Management Knowledge Area
Online PMP Training Material for PMP Exam - Quality Management Knowledge AreaGlobalSkillup
 
Posecco clustering meeting
Posecco clustering meetingPosecco clustering meeting
Posecco clustering meetingfcleary
 

Similaire à Risk Based Quality Management System Auditing (20)

Six sigma as foundation to cmmi
Six sigma as foundation to cmmiSix sigma as foundation to cmmi
Six sigma as foundation to cmmi
 
Skyward Erp Presentation
Skyward Erp PresentationSkyward Erp Presentation
Skyward Erp Presentation
 
Quality Systems Investigation Technique
Quality Systems Investigation TechniqueQuality Systems Investigation Technique
Quality Systems Investigation Technique
 
Killing the Myth: Agile & CMMI
Killing the Myth: Agile & CMMIKilling the Myth: Agile & CMMI
Killing the Myth: Agile & CMMI
 
CA Quality Management System
CA Quality Management SystemCA Quality Management System
CA Quality Management System
 
Quality Management System ISO 9001 Interpretation and Internal Audit
Quality Management System ISO 9001 Interpretation and Internal AuditQuality Management System ISO 9001 Interpretation and Internal Audit
Quality Management System ISO 9001 Interpretation and Internal Audit
 
Calibration of MMDs to meet QMS
Calibration of MMDs to meet QMSCalibration of MMDs to meet QMS
Calibration of MMDs to meet QMS
 
Best Practices Frameworks 101
Best Practices Frameworks 101Best Practices Frameworks 101
Best Practices Frameworks 101
 
Quality in Software Testing
Quality in Software TestingQuality in Software Testing
Quality in Software Testing
 
Integrated methodology for testing and quality management.
Integrated methodology for testing and quality management.Integrated methodology for testing and quality management.
Integrated methodology for testing and quality management.
 
Agile and CMMI
Agile and CMMIAgile and CMMI
Agile and CMMI
 
Basic Internal Auditing Presentation
Basic Internal Auditing PresentationBasic Internal Auditing Presentation
Basic Internal Auditing Presentation
 
Transition to ISO 13485:2016
Transition to ISO 13485:2016Transition to ISO 13485:2016
Transition to ISO 13485:2016
 
Iso awarness
Iso awarnessIso awarness
Iso awarness
 
Pmbok 4th edition chapter 8 - Project Quality Management
Pmbok 4th edition   chapter 8 - Project Quality Management Pmbok 4th edition   chapter 8 - Project Quality Management
Pmbok 4th edition chapter 8 - Project Quality Management
 
Pmp an introduction
Pmp an introductionPmp an introduction
Pmp an introduction
 
Incorporate CPV and Continual Improvement into your Validation Plan
Incorporate CPV and Continual Improvement into your Validation PlanIncorporate CPV and Continual Improvement into your Validation Plan
Incorporate CPV and Continual Improvement into your Validation Plan
 
Online PMP Training Material for PMP Exam - Quality Management Knowledge Area
Online PMP Training Material for PMP Exam - Quality Management Knowledge AreaOnline PMP Training Material for PMP Exam - Quality Management Knowledge Area
Online PMP Training Material for PMP Exam - Quality Management Knowledge Area
 
Iso 9001 training
Iso 9001 trainingIso 9001 training
Iso 9001 training
 
Posecco clustering meeting
Posecco clustering meetingPosecco clustering meeting
Posecco clustering meeting
 

Dernier

Regression analysis: Simple Linear Regression Multiple Linear Regression
Regression analysis:  Simple Linear Regression Multiple Linear RegressionRegression analysis:  Simple Linear Regression Multiple Linear Regression
Regression analysis: Simple Linear Regression Multiple Linear RegressionRavindra Nath Shukla
 
Insurers' journeys to build a mastery in the IoT usage
Insurers' journeys to build a mastery in the IoT usageInsurers' journeys to build a mastery in the IoT usage
Insurers' journeys to build a mastery in the IoT usageMatteo Carbone
 
Best VIP Call Girls Noida Sector 40 Call Me: 8448380779
Best VIP Call Girls Noida Sector 40 Call Me: 8448380779Best VIP Call Girls Noida Sector 40 Call Me: 8448380779
Best VIP Call Girls Noida Sector 40 Call Me: 8448380779Delhi Call girls
 
VIP Kolkata Call Girl Howrah 👉 8250192130 Available With Room
VIP Kolkata Call Girl Howrah 👉 8250192130  Available With RoomVIP Kolkata Call Girl Howrah 👉 8250192130  Available With Room
VIP Kolkata Call Girl Howrah 👉 8250192130 Available With Roomdivyansh0kumar0
 
Cash Payment 9602870969 Escort Service in Udaipur Call Girls
Cash Payment 9602870969 Escort Service in Udaipur Call GirlsCash Payment 9602870969 Escort Service in Udaipur Call Girls
Cash Payment 9602870969 Escort Service in Udaipur Call GirlsApsara Of India
 
Lucknow 💋 Escorts in Lucknow - 450+ Call Girl Cash Payment 8923113531 Neha Th...
Lucknow 💋 Escorts in Lucknow - 450+ Call Girl Cash Payment 8923113531 Neha Th...Lucknow 💋 Escorts in Lucknow - 450+ Call Girl Cash Payment 8923113531 Neha Th...
Lucknow 💋 Escorts in Lucknow - 450+ Call Girl Cash Payment 8923113531 Neha Th...anilsa9823
 
MONA 98765-12871 CALL GIRLS IN LUDHIANA LUDHIANA CALL GIRL
MONA 98765-12871 CALL GIRLS IN LUDHIANA LUDHIANA CALL GIRLMONA 98765-12871 CALL GIRLS IN LUDHIANA LUDHIANA CALL GIRL
MONA 98765-12871 CALL GIRLS IN LUDHIANA LUDHIANA CALL GIRLSeo
 
0183760ssssssssssssssssssssssssssss00101011 (27).pdf
0183760ssssssssssssssssssssssssssss00101011 (27).pdf0183760ssssssssssssssssssssssssssss00101011 (27).pdf
0183760ssssssssssssssssssssssssssss00101011 (27).pdfRenandantas16
 
A DAY IN THE LIFE OF A SALESMAN / WOMAN
A DAY IN THE LIFE OF A  SALESMAN / WOMANA DAY IN THE LIFE OF A  SALESMAN / WOMAN
A DAY IN THE LIFE OF A SALESMAN / WOMANIlamathiKannappan
 
BEST ✨ Call Girls In Indirapuram Ghaziabad ✔️ 9871031762 ✔️ Escorts Service...
BEST ✨ Call Girls In  Indirapuram Ghaziabad  ✔️ 9871031762 ✔️ Escorts Service...BEST ✨ Call Girls In  Indirapuram Ghaziabad  ✔️ 9871031762 ✔️ Escorts Service...
BEST ✨ Call Girls In Indirapuram Ghaziabad ✔️ 9871031762 ✔️ Escorts Service...noida100girls
 
Monthly Social Media Update April 2024 pptx.pptx
Monthly Social Media Update April 2024 pptx.pptxMonthly Social Media Update April 2024 pptx.pptx
Monthly Social Media Update April 2024 pptx.pptxAndy Lambert
 
Call Girls In DLf Gurgaon ➥99902@11544 ( Best price)100% Genuine Escort In 24...
Call Girls In DLf Gurgaon ➥99902@11544 ( Best price)100% Genuine Escort In 24...Call Girls In DLf Gurgaon ➥99902@11544 ( Best price)100% Genuine Escort In 24...
Call Girls In DLf Gurgaon ➥99902@11544 ( Best price)100% Genuine Escort In 24...lizamodels9
 
Keppel Ltd. 1Q 2024 Business Update Presentation Slides
Keppel Ltd. 1Q 2024 Business Update  Presentation SlidesKeppel Ltd. 1Q 2024 Business Update  Presentation Slides
Keppel Ltd. 1Q 2024 Business Update Presentation SlidesKeppelCorporation
 
Call Girls Pune Just Call 9907093804 Top Class Call Girl Service Available
Call Girls Pune Just Call 9907093804 Top Class Call Girl Service AvailableCall Girls Pune Just Call 9907093804 Top Class Call Girl Service Available
Call Girls Pune Just Call 9907093804 Top Class Call Girl Service AvailableDipal Arora
 
Ensure the security of your HCL environment by applying the Zero Trust princi...
Ensure the security of your HCL environment by applying the Zero Trust princi...Ensure the security of your HCL environment by applying the Zero Trust princi...
Ensure the security of your HCL environment by applying the Zero Trust princi...Roland Driesen
 
The CMO Survey - Highlights and Insights Report - Spring 2024
The CMO Survey - Highlights and Insights Report - Spring 2024The CMO Survey - Highlights and Insights Report - Spring 2024
The CMO Survey - Highlights and Insights Report - Spring 2024christinemoorman
 
Call Girls In Panjim North Goa 9971646499 Genuine Service
Call Girls In Panjim North Goa 9971646499 Genuine ServiceCall Girls In Panjim North Goa 9971646499 Genuine Service
Call Girls In Panjim North Goa 9971646499 Genuine Serviceritikaroy0888
 

Dernier (20)

Regression analysis: Simple Linear Regression Multiple Linear Regression
Regression analysis:  Simple Linear Regression Multiple Linear RegressionRegression analysis:  Simple Linear Regression Multiple Linear Regression
Regression analysis: Simple Linear Regression Multiple Linear Regression
 
Insurers' journeys to build a mastery in the IoT usage
Insurers' journeys to build a mastery in the IoT usageInsurers' journeys to build a mastery in the IoT usage
Insurers' journeys to build a mastery in the IoT usage
 
Best VIP Call Girls Noida Sector 40 Call Me: 8448380779
Best VIP Call Girls Noida Sector 40 Call Me: 8448380779Best VIP Call Girls Noida Sector 40 Call Me: 8448380779
Best VIP Call Girls Noida Sector 40 Call Me: 8448380779
 
VIP Kolkata Call Girl Howrah 👉 8250192130 Available With Room
VIP Kolkata Call Girl Howrah 👉 8250192130  Available With RoomVIP Kolkata Call Girl Howrah 👉 8250192130  Available With Room
VIP Kolkata Call Girl Howrah 👉 8250192130 Available With Room
 
Forklift Operations: Safety through Cartoons
Forklift Operations: Safety through CartoonsForklift Operations: Safety through Cartoons
Forklift Operations: Safety through Cartoons
 
Cash Payment 9602870969 Escort Service in Udaipur Call Girls
Cash Payment 9602870969 Escort Service in Udaipur Call GirlsCash Payment 9602870969 Escort Service in Udaipur Call Girls
Cash Payment 9602870969 Escort Service in Udaipur Call Girls
 
Lucknow 💋 Escorts in Lucknow - 450+ Call Girl Cash Payment 8923113531 Neha Th...
Lucknow 💋 Escorts in Lucknow - 450+ Call Girl Cash Payment 8923113531 Neha Th...Lucknow 💋 Escorts in Lucknow - 450+ Call Girl Cash Payment 8923113531 Neha Th...
Lucknow 💋 Escorts in Lucknow - 450+ Call Girl Cash Payment 8923113531 Neha Th...
 
MONA 98765-12871 CALL GIRLS IN LUDHIANA LUDHIANA CALL GIRL
MONA 98765-12871 CALL GIRLS IN LUDHIANA LUDHIANA CALL GIRLMONA 98765-12871 CALL GIRLS IN LUDHIANA LUDHIANA CALL GIRL
MONA 98765-12871 CALL GIRLS IN LUDHIANA LUDHIANA CALL GIRL
 
0183760ssssssssssssssssssssssssssss00101011 (27).pdf
0183760ssssssssssssssssssssssssssss00101011 (27).pdf0183760ssssssssssssssssssssssssssss00101011 (27).pdf
0183760ssssssssssssssssssssssssssss00101011 (27).pdf
 
Nepali Escort Girl Kakori \ 9548273370 Indian Call Girls Service Lucknow ₹,9517
Nepali Escort Girl Kakori \ 9548273370 Indian Call Girls Service Lucknow ₹,9517Nepali Escort Girl Kakori \ 9548273370 Indian Call Girls Service Lucknow ₹,9517
Nepali Escort Girl Kakori \ 9548273370 Indian Call Girls Service Lucknow ₹,9517
 
A DAY IN THE LIFE OF A SALESMAN / WOMAN
A DAY IN THE LIFE OF A  SALESMAN / WOMANA DAY IN THE LIFE OF A  SALESMAN / WOMAN
A DAY IN THE LIFE OF A SALESMAN / WOMAN
 
BEST ✨ Call Girls In Indirapuram Ghaziabad ✔️ 9871031762 ✔️ Escorts Service...
BEST ✨ Call Girls In  Indirapuram Ghaziabad  ✔️ 9871031762 ✔️ Escorts Service...BEST ✨ Call Girls In  Indirapuram Ghaziabad  ✔️ 9871031762 ✔️ Escorts Service...
BEST ✨ Call Girls In Indirapuram Ghaziabad ✔️ 9871031762 ✔️ Escorts Service...
 
Monthly Social Media Update April 2024 pptx.pptx
Monthly Social Media Update April 2024 pptx.pptxMonthly Social Media Update April 2024 pptx.pptx
Monthly Social Media Update April 2024 pptx.pptx
 
Call Girls In DLf Gurgaon ➥99902@11544 ( Best price)100% Genuine Escort In 24...
Call Girls In DLf Gurgaon ➥99902@11544 ( Best price)100% Genuine Escort In 24...Call Girls In DLf Gurgaon ➥99902@11544 ( Best price)100% Genuine Escort In 24...
Call Girls In DLf Gurgaon ➥99902@11544 ( Best price)100% Genuine Escort In 24...
 
Keppel Ltd. 1Q 2024 Business Update Presentation Slides
Keppel Ltd. 1Q 2024 Business Update  Presentation SlidesKeppel Ltd. 1Q 2024 Business Update  Presentation Slides
Keppel Ltd. 1Q 2024 Business Update Presentation Slides
 
Call Girls Pune Just Call 9907093804 Top Class Call Girl Service Available
Call Girls Pune Just Call 9907093804 Top Class Call Girl Service AvailableCall Girls Pune Just Call 9907093804 Top Class Call Girl Service Available
Call Girls Pune Just Call 9907093804 Top Class Call Girl Service Available
 
Ensure the security of your HCL environment by applying the Zero Trust princi...
Ensure the security of your HCL environment by applying the Zero Trust princi...Ensure the security of your HCL environment by applying the Zero Trust princi...
Ensure the security of your HCL environment by applying the Zero Trust princi...
 
KestrelPro Flyer Japan IT Week 2024 (English)
KestrelPro Flyer Japan IT Week 2024 (English)KestrelPro Flyer Japan IT Week 2024 (English)
KestrelPro Flyer Japan IT Week 2024 (English)
 
The CMO Survey - Highlights and Insights Report - Spring 2024
The CMO Survey - Highlights and Insights Report - Spring 2024The CMO Survey - Highlights and Insights Report - Spring 2024
The CMO Survey - Highlights and Insights Report - Spring 2024
 
Call Girls In Panjim North Goa 9971646499 Genuine Service
Call Girls In Panjim North Goa 9971646499 Genuine ServiceCall Girls In Panjim North Goa 9971646499 Genuine Service
Call Girls In Panjim North Goa 9971646499 Genuine Service
 

Risk Based Quality Management System Auditing

  • 2. Realities of Business World New Satellite Program Major Delays US Govt. faced $3 billion in cost overruns and a three-year delay in new satellite program for Hurricane & severe weather tracking.
  • 3. Realities of Business World FoxMeyer Drugs Bankruptcy In 1993, FoxMeyer Drugs was the fourth largest distributor of pharmaceuticals in the U.S., worth $5 billion. In an attempt to increase efficiency, FoxMeyer purchased an SAP system and a warehouse automation system it what was supposed to be a $35 million project. By 1996, due to number of issues the company was bankrupt; it was eventually sold to a competitor for a mere $80 million.
  • 4. RISK BASED QUALITY MANAGEMENT SYSTEM AUDITING
  • 5. Definitions of Risk Combination of the probability of an event and its consequence (ISO DGUIDE 73) The chance of something happening that will have an impact upon objectives. It is measured in terms of consequences and likelihood. (AS/NZS 4360)
  • 6. Risk in Simple Words Risk = Likelihood X Consequence
  • 7. Risk Management Acceptance/Tolerance: With or without planning of contingency. Reduce likelihood or consequence: By establishing processes and controls Analysis, evaluation and assessment of risk and its rational control in helping to promote the objectives and targets of the business
  • 8. Risk Based Quality Management System Auditing Auditor typical role was limited to documenting audit findings including non- conformances (if any)
  • 9. Risk Based Quality Management System Auditing VALUE ADDED Auditing QMS Risk = AUDIT Management tool to prioritize the issues accordingly
  • 10. SCORING TABLE: RISK BASED CONFORMANCE AUDIT & SCORING SYSTEM Quality Management System Conformance Risk Classification Clause / Score Sub-Clauses ISO 9001:2008 Standard Requirements Clause Sub Clause Score Score H M L 7 Product Realization 7.1 Planning of product realization 7.2 Customer-related processes (Title) 7.2.1 Determination of requirements related to product 7.2.2 Review of the requirements related to the product 7.2.3 Customer communication 7.3 Design and Development (Title) 7.3.1 Design and Development Planning 7.3.2 Design and Development Input 7.3.3 Design and Development Output 7.3.4 Design and Development Review 7.3.5 Design and Development Verification 7.3.6 Design and Development Validation 7.3.7 Design and Development Changes 7.4 Purchasing (Title) 7.4.1 Purchasing Process 7.4.2 Purchasing Information 7.4.3 Validation of Purchase Information 7.5 Product and Service Provision (Title) 7.5.1 Control of product and service provision Validation of processes for production and service 7.5.2 provision Information 7.5.3 Identification and traceability 7.5.4 Customer Property 7.5.5 Preservation of product 7.6 Control of monitoring and measuring equipment
  • 11. Post Audit Activities • Decisions based • Plan to reduce on analysis and Risks identified monitoring in audit. results. Improvement of • Actions taken processes & controls ACT PLAN CHECK DO • Indicators & • Implementation Measurement. of planned • Audit actions