Deployment Plan for B2B Integrations
1. Now until Day 0
Task Details Begin Time End Time Owner Status
Soft Launch 1-Mar-09 Customer Dev Team
Load Dbacklog Orders
- Order Confirmed Date - 1/Nov/2008
- Backlog order
1-Mar-09 Customer Dev Team
DRAGONfx 2.0 Change Ticket Change Ticket
Preparation - Master CT
- MQ CT
- Control-M CT
- DB CT
Submit the CT - refer to CT & Contact tab 1-Mar-09 Customer Dev Team
Upstream/Downstream Change Ticket
Preparation
Review Deployment Plan 1-Mar-09 Customer
Review the Deployment Plan
- Webservice Project Team / Business (Upstream/downstream)
- Upstream/Downstream Systems Teams, IT
- LSPs
Day 1
Task Details Begin Time End Time Owner Status
Change Ticket Review 2-Mar-09 Customer
Change Ticket Review for Webservice Change Ticket and
Upstream/Downtream systems Change Ticket (Upstream/downstream)
Teams, IT
Day 2
Task Details Begin Time End Time Owner Status
Verify Webservice Connectivities LSP able to connect to Webservice thru https 9:00 AM 4:00 PM Customer IT, Vendor IT
Copy/Verify OMI Master Data 9:00 AM 4:00 PM Customer Bussiness Support
- Copy the OMI Master data from UAT
- Verify the OMI Master data
Pull/Verify DRAGON 1.0 Users Accounts 9:00 AM 4:00 PM Customer Logistics Business IT need to pull out now
- Pull out the old applicaton 1.0 user accounts
- Create the user accounts in application 2.0
Verify Master Data 9:00 AM 4:00 PM Customer Logistics / COM /
- Review all the master data (especially on Part, Vendor Pull all the master data
Part, etc) COC business, Logistics in xls file to the team.
Business,
Procurement, Customer IT
Day 2
Task Details Begin Time End Time Owner Status
Create User Accounts in Application 2.0 - Create the user accounts 9:00 AM 4:00 PM Customer Logistics
Load/Verify Application 1.0 Final Orders 9:00 AM 10:00 PM Customer Procurement
- Orders loaded up to that day same as Application 1.0
- Clear all the message fallout
- Keep deployment day feed in webservice transaction
table (example, SO / SOC / MN / etc) in case LSP
required
9:00 AM 1:00 PM Vendor Business / IT
Deploy LSP application ( no data interface - Deploy the changes in LSP system and point to Inventory quantity can
to within lsp and Dell) Application 2.0 webservices send to us on Day 0 if
- Physical inventory count for LSP (DMI / VMI) hub operation is stop
Stop Application 2.0 - Stop the application 2.0 weblogic 9:30 AM 10:00 AM Customer IT
2. 10:00 AM 12:00 PM Customer IT
Change Order Management batch jobs - Change the Order Management data feed to application
and LSP Feed-in folder 1.0 and application 2.0
- Change the LSP feed-in folder to another new folder
name
Adjust Inventory 10:00 AM 11:30 AM Customer Logistics/Customer Inventory quantity can
- Get the latest inventory info from Hub
send to us on Day 0 if
- Update/Adjust the Inventory table IT
hub operation is stop
Final turn application 2.0 orders - set the email account for application 2.0 email 10:00 AM 12:00 PM Customer IT
notification
- delete ETA_TMP table
- - Keep deployment day feed in webservice transaction
table (example, SO / SOC / MN / etc) in case LSP needed
Change vendor currency conversion setting 9:00 AM 12:00 PM Customer Logistics
Change vendor currency conversion
setting
Implement freight system changes Point to new application 2.0 DB view 9:00 AM 12:00 PM Customer IT
Deploy the application 2.0 build scripts Run the deployment build scripts with all the jobs enable 10:00 AM 12:00 PM Customer IT
11:00 AM 1:00 PM Customer Logistics / COM /
Confirm the master data and orders - Final verify all the master data and make sure non-
COC business, Logistics
intergrity. backlog orders set properly
- Make sure no records in webservice_transaction table Business,
Procurement, Customer IT
Start the Weblogic for Backend/Frontend services 12:00 PM 1:00 PM Customer IT
Turn on Application 2.0 application
services
Verify/Test order management Feed Files - Make sure application 1.0 and application 2.0 able to 12:00 PM 1:00 PM Customer IT
load/process the orders and master data
4:00 PM Customer IT, Vendor IT
Testing with LSP - Test with LSP on the webservices 1:00 PM
Day 3
Verify/Test freight system changes Able to pull the existing application 2.0 orders thru DB 9:00 AM 4:00 PM Customer IT
Implement Online Webfarm changes Point to new application 2.0 webservice 9:00 AM 4:00 PM Dell IT
Verify/Test Online Webfarm 9:00 AM 4:00 PM Customer IT
Able to pull the existing application 2.0 orders thru
webservice
Point to new application 2.0 DB 9:00 AM 4:00 PM Customer IT
Implement Customer Care system
changes
Implement Datamart changes Point to new application 2.0 share folder 9:00 AM 4:00 PM Customer IT
Implement Ebilling changes Point to new application 2.0 webservice 9:00 AM 4:00 PM Customer IT
Monitor Application logs Monitor application logs 9:00 AM 4:00 PM Customer IT
Verify/Test Customer Care system Able to pull the existing application 2.0 orders thru DB 9:00 AM 4:00 PM Customer IT
Verify TNT status Make sure the in-factory/ex-factory status is correct 9:00 AM 4:00 PM Customer Logistics
Verify OMI status Monitor the OMI calculated data and email status 9:00 AM 4:00 PM Customer Logistics / COM /
COC business, Logistics
Business,
Procurement, Customer IT
Verify Inventory Movement Able to perform Inventory movement from LSP 9:00 AM 4:00 PM Customer Logistics / COM /
COC business, Logistics
Business,
Procurement, Customer IT
3. Verify Reports Verify Fulfillment, TNT, Inventory, OMI reports 9:00 AM 4:00 PM Customer Logistics / COM /
COC business, Logistics
Business,
Procurement, Customer IT
Verify other downstream/upstream Able to pull the existing application 2.0 orders 9:00 AM 4:00 PM Customer Logistics / COM /
systems COC business, Logistics
Business,
Procurement, Customer IT
Final verification Final verify all the testing results before Go/No-Go 4:00 PM 4:30 PM Customer Logistics / COM /
COC business, Logistics
Business,
Procurement, Customer
IT/Vendor Business, Vendor IT
GO/NO-GO Meeting GO/NO-GO Meeting 4:30 PM 5:00 PM Customer Logistics / COM /
COC business, Logistics
Business,
Procurement, Customer
IT/Vendor Business, Vendor IT
Day 4 onward
Task Details Begin Time End Time Owner Status
Close the Change Ticket Update and close the Change Ticket 9:00 AM 4:00 PM Customer IT
Stabilization Start Monitor Trouble Ticket and route to project team 1-May-09 Customer Logistics/Customer
IT
4. Day 3
Task Details Begin Time End Time Owner Status
Stop application 2.0 6:30 PM 7:00 PM Customer IT
Stop the application 2.0 application and change back to soft launch
setting
7:00 PM 10:00 PM Customer IT
Copy upstream/downstream feed files back to Copy the upstream/downstream feed files from application 2.0
application 1.0 back to application 1.0
Copy the TNT status from application 2.0 tables to application 1.0 7:00 PM 10:00 PM Customer IT
Copy the TNT status / servicetag records from
application 2.0 DB to application 1.0 DB
Set the merge order in application 1.0 7:00 PM 10:00 PM Customer IT
Base on the application 2.0 merge order and set the application 1.0
fulfillment table
Adjust the Inventory 7:00 PM 10:00 PM Customer Logistics Business
Base on the application 2.0 inventory and adjust back on
application 1.0
Rollback MQ changes Change back to original MQ servers 7:00 PM 10:00 PM Customer IT
Rollback upstream/downstream/LSP changes Rollback to their original application settings 7:00 PM 10:00 PM Customer Change Owner
Verify back out result Verify back out result 10:00 PM 11:00 PM Customer Logistics/Customer IT
Day 4
Task Details Begin Time End Time Owner Status
Close the Change Ticket Update and close the Change Ticket 9:00 AM 4:00 PM Customer CT Implementer