91 Design Build Update
1. 91 DESIGN-BUILD PROJECT UPDATE
Riverside County Transportation Commission
David Thomas, Project Manager
American Public Works Association
May 28, 2015
3. Growing Need
• 91 is primary
east-west route
• 280,000 vehicles daily,
140,000 more by 2035
(a 50% increase)
• Afternoon eastbound
delays in top 5 in
nation – speeds drop
below 15 MPH
4. Multiple Benefits
• Fewer traffic delays
• Choice between lanes
• Faster emergency
response
• Reduced air pollution
• Improved surface
streets, connectivity
• 16,200 jobs created
7. Express Lanes
• Extend proven OC 91 Express Lanes
• RCTC to own/operate in Riv Co
• Replace carpool lanes; carpoolers
with 3+ and transponder ride free
94% of time
• Revenue reinvested in 91 corridor
• Without toll revenue, full widening
would not be possible, project would
be delayed for many years
8. Seamless Express Lanes
TollPolicySimilarities
Identical toll policy goals shared by OCTA and RCTC
Variable congestion pricing based on time-of-day and day-of-week
Pricing adjusted quarterly by pre-defined formula based
on tolled express lanes’ traffic volume
Tolls set to maximize corridor throughput
3+ carpoolers ride free during most periods
All electronic tolling using California interoperable transponders
11. Why Design-Build?
• Save 3-4 years over design-bid-build method by
overlapping design and build phases
• Shorter construction = Fewer impacts, lower cost
• Schedule and complexity ripe for innovations
• “Best Value” design-builder selected
• Price certainty needed for financial market
• Proper risk allocation reduces risk to RCTC
• Co-located project team = close coordination
14. Right of Way Acquisition
•62 commercial
•54 industrial
•28 multi-family residence
•53 single-family residence
Property
Type
•70 full acquisitions
•93 partial fee acquisitions
•34 other property interest
Acquisition
Type
•All in RCTC possession and 196 delivered to D-B
•85 closed through escrow
•7 currently in escrow
•105 condemnation actions approved
Acquisition
Status
197
Parcels
(by CPN)
as of
4/30/15
15. Right of Way Acquisition
Property Demolition
Property Mitigation
Property Demolition
16. Location: ROW Mitigation @ Z Corona – Facing East
Description: Wall forms installed for new building face at 1247 Bldg.
17. Location: ROW Mitigation @ Dvorak & Payne– Facing Northeast
Description: Site clean-up of the newly finished exterior of Dvorak and Payne property.
18. Location: ROW Demo @ Corona Town Center – Facing East
Description: Demolition of Dollar Tree building at Corona Town Center.
26. Location: Old EB SR-91 to NB/SB I-15 Connector at BR-27 – Facing West
Description: Existing bridge demolition over BNSF tracks.
27. Location: Bridge 25 (SB I-15 to WB SR91 Connector), Worksite – Facing West
Description: Bridge 25 soffit and stem installation.
28. Location: Bridge 23 (EB SR-91 to NB/SB I-15 Connector @ E Grand) – Facing Southeast
Description: Bridge 22-23 work area. CIDH pile installation at BR-23, Bent 2. Formwork for BR-22, Abut 2 wall stem.
BR-23,
BENT 2
BR-22, Abut
2
29. Location: Bridge 2 (WB 91/Green River Off-ramp) @ West Prado Rd. – Facing West
Description: Deck concrete placement between Abut 1 and Bent 4. Bent 5 column in foreground.
30. Location: Bridge 2 (WB 91/Green River Off-ramp) @ West Prado Rd. – Facing West
Description: Stem-soffit concrete pour between Abut 1 and Bent 4
31. Location: Bridge 2 (WB 91/Green River Off-ramp) @ West Prado Rd. – Facing North
Description: Deck concrete placement between Abut 1 and Bent 4.
32. Location: RW-103B (EB SR-91) @ Serfas Club Off-Ramp – Facing West
Description: Retaining wall footing rebar and formwork installation.
33. Location: RW-145 (New Frontage Rd Alignment) – Facing North
Description: RW-145 stem pour complete.
34. Location: RW-206A (WB SR-91) @ Wardlow Cir. – Facing West
Description: MSE Panel installation for RW-206A.
35.
36.
37. Location: I-15 Median @ Old Temescal Rd. – Facing North
Description: PCC pavement along I-15 median. Blockout for median sign structure foundation.
38. Location: EB SR-91 (Smith St. to Maple St.) – Facing Southwest
Description: Soundwall demolition.
39. Location: ROW Mitigation Demo. @ Northmoor Properties – Facing East
Description: Clearing and grubbing behind the Northmoor residential property.
40. Location: WB SR-91 @ SR-71 Interchange – Looking Northeast
Description: Earthwork for WB SR-91 widening between AutoCenter Dr. and SR-71.
41. Location: NB I-15 to WB SR-91 Temp Connector (Facing Southwest)
Description: Temp connector opened to traffic. Closure of existing NB I-15 to WB SR-91 connector for bridge construction.
42. Upcoming Milestones
RIVERSIDE COUNTY TRANSPORTATION COMMISSION
• 91 Corona Squeeze – June 1, 2015 - April 1, 2016
• ETTM Turnover – April 14, 2016
• New Lanes Open! – 2017
43. Stay Connected
RIVERSIDE COUNTY TRANSPORTATION COMMISSION
sr91project.info
877-770-9191
@sr91project
sr91project.com
Real-time traffic updates, ie511.org
Check out our mobile website!