Highway Projects - Evidence & Investigation
• 307 CCOs on 5 Projects were collected in March
2013
• 139 CCOs were identified as Design Related at a
cost of $6.4 M
• RCA performed on 85 Design Related CCO
28. 28
Improve Design Quality Management Plan
1. Identify QC Reviewers and provide Qualifications in DQMP
2. Strengthen use of checklists to improve Accuracy (QC Procedures)
3. Improve Coordination between disciplines & subconsultants
whenever design changes are made (Implement the Design
Control Log)
4. Ensure current reference files are utilized by all
disciplines/subconsultants to eliminate errors (EDMS)
5. Increase QA over subs (Prime conduct audits on subs)
29. 29
6. Engage construction professionals to perform Constructability
Reviews (Validate Qualifications)
7. Use Comment Response Log that Categorizes the Comments
(by Discipline then Engineering, CADD, Specifications, General)
8. DO NOT rely on As-Built data – Verify As-Built data (Assumptions)
• Request adequate surveys
• Perform thorough field investigations
9. Implement Risk Identification Log
– Document Risks and assumptions on a Risk ID Log
Improve Design Quality Management Plan
30. 30
Improve Construction Feedback
1. Use consistent Categories for CCOs for all Projects
2. CM/RE completes the RCA; then it’s Verified by PM/QM
31. 31
Implementation and Monitoring
Follow up Program
• Milestone QA Project Reviews at Consultants Office
– Surveillances
– Audits
• Project Performance Assessments
• Maintain the Continuous Improvement Program