Trusted to deliver excellence
© 2013 Rolls-Royce plc
The information in this document is the property of Rolls-Royce plc and may not be copied or communicated to a third party, or used for any purpose other
than that for which it is supplied without the express written consent of Rolls-Royce plc.
This information is given in good faith based upon the latest information available to Rolls-Royce plc, no warranty or representation is given concerning
such information, which must not be taken as establishing any contractual or other commitment binding upon Rolls-Royce plc or any of its subsidiary or
associated companies.
Portfolio Management
APM Session– April 2014
Prepared by EIC Communications
John McGregor
Chief Of Delivery, EIC
Dean Hall
EIC PMO
Introductions
Integrated Production System
This session
• Portfolio
Management within
the Engineering
Improvement centre
• How we govern and
support our work
Rolls-Royce proprietary information
APM Defintion
“Portfolio management is the selection and management of all of an
organisation’s projects, programmes and related business-as-usual
activities taking into account resource constraints. A portfolio is a group
of projects and programmes carried out under the sponsorship of an
organisation.”
Portfolio management seeks to ensure that organisations:
1. Invest in the ‘right’ projects and programmes in the context of their
strategic objectives and subject to the constraints of risk and
affordability.
2. Manage their project and programmes ‘right’ – at a collective level, by
effective management of limited resources, dependencies and the
organisation’s capacity to absorb change.
3. Realise the full benefits from their investment in projects and
programmes
4. Capture lessons learned and use them to inform the development of
more efficient and effective management of their portfolios.
Rolls-Royce proprietary information
APM Defintion
“Portfolio management is the selection and management of all of an
organisation’s projects, programmes and related business-as-usual activities taking into account
resource constraints. A portfolio is a group of projects and
programmes carried out under the sponsorship of an
organisation.”
In summary, portfolio management seeks to ensure that organisations:
1. Invest in the ‘right’ projects and programmes in the context of their
strategic objectives and subject to the constraints of risk and
affordability.
2. Manage their project and programmes ‘right’ – at a collective level, by effective management of
limited resources, dependencies and the organisation’s
capacity to absorb change.
3. Realise the full benefits from their investment in projects and programmes
4. Capture lessons learned and use them to inform the development of
more efficient and effective management of their portfolios.
Rolls-Royce proprietary information
Portfolio Management
The continuous process of identification,
prioritisation, selection and delivery
management of projects that align to the
corporate strategy and business objectives
Rolls-Royce proprietary information
Portfolio and Project Management Impact
UNREALISED VALUE
Improve
Project
Management
Improve
Portfolio
Management
PortfolioManagement
“Doingthecorrectthings”
Programme & Project Management
“Doing things correctly”
0%
100%
100%
Portfolio Management acts as the commissioning body for
Programmes and Projects
Rolls-Royce proprietary information
REALISED PROJECT
VALUE
Rolls-Royce EIC
8
Transform
Standardise
Maintain
Rolls-Royce proprietary information
The current Portfolio
9
Rolls-Royce proprietary information
The EIC Portfolio
EIC Portfolio Delivery
TransformStandardise Maintain
Integrated Design,
Simulation and
Verification
--
Right first time
designs throughout
the product lifecycle
in the presence of
variation
Lean Engineering
and Functional
Maturity
--
Operating a mature
efficient and effective
function across the
engineering process
lifecycle
Enabling IT
--
Modern effective and
user friendly IT
enabling the
engineering process
and people
Product, Data &
Document
Management
Systems
--
Smooth transition of
data and documents
across the product
lifecycle
Rolls-Royce proprietary information
EIC
Product Data &
Document
Management
(PLM)
Knowledge
Management
Collaboration
TEDS
PLM Applications
Integrated Design
Simulation &
Verification
Virtual
Engine/Product
Design Automation
Mech System
Design
Tools & Methods
Performance/
Aero/Fluids
High Performance
Computing
Lean Engineering &
Functional Maturity
Product Family
Standards
Engineering
Process
Robust
Engineering
Global Specs &
Standards
Enabling IT
Architecture
Infrastructure
Corporate
Initiatives
HPC
Infrastructure
RRES
Architecture
EIC
Portfolio
Rolls-Royce proprietary information
EIC
DATA
Knowledge
Management
Collaboration
TEDS
PLM Applications
APPS
Virtual
Engine/Product
Design Automation
Mech System
Design
Tools & Methods
Performance/
Aero/Fluids
High Performance
Computing
PROCESS
Product Family
Standards
Engineering
Process
Robust
Engineering
Global Specs &
Standards
INFRASTRUCTURE
Architecture
Infrastructure
Corporate
Initiatives
HPC
Infrastructure
STRATEGY
EIC
Portfolio
Rolls-Royce proprietary information
The Engineering model
13
Central Engineering
and Technology
Energy Aerospace Marine Nuclear
Engineering
Functions
Customer
Develop and deploy capability
Construct and
deliver projects
Rolls-Royce proprietary information
EIC Organisation
Sector/function
Head of Engineering Business
Improvement
Portfolio Operations
Chief Engineer
Integrated design
simulation and
verification
Lean functional
operation and maturity
Enabling ITProduct, data &
doc management
systems
Chief of Delivery Chief of Strategy
Director
Chief of
Transformation
Transformation and Operations
Safety & Product Assurance
Systems Eng Development
Systems Design
Component Design
Engineering 4 Services/GTS
Controls & Electrical Eng
Test & Measurement
Manufacture
Materials
Technical Office
Portfolio
Management
Office
Finance & Quality
Business
Operations Office
Engineering
Functions
Theme Lead Theme Lead Theme Lead
Rolls-Royce proprietary information
Theme Lead
EIC
Product Data &
Document
Management
Knowledge
Management
Collaboration
TEDS
PLM Applications
Integrated Design
Simulation &
Verification
Virtual
Engine/Product
Design Automation
Mech System
Design
Tools & Methods
Performance/
Aero/Fluids
High Performance
Computing
Lean Engineering &
Functional Maturity
Product Family
Standards
Engineering
Process
Robust
Engineering
Global Specs &
Standards
Enabling IT
Architecture
Infrastructure
Corporate
Initiatives
HPC
Infrastructure
RRES
Architecture
Governing the Portfolio
Component Design
Controls / Electrical
Engineering
Engineering 4
Services / GTS
Materials
Safety
Systems Design
System Engineering
Development
Test and
Measurement
Transformation &
Operations
Tools & MethodsTools & MethodsTools & MethodsTools & Methods
Mech System
Design
Virtual
Engine/Product
Design Automation
Engineering
Process
Robust
Engineering
Global Specs &
Standards
Knowledge
Management
Engineering
Process
Knowledge
Management
Rolls-Royce proprietary information
How we govern and
track our work
16
EIC Portfolio Gates
Prioritise
Select
Launch
Baseline
Multi-Year
Assessment
Year-End
Review
Qualify
Quarterly
Portfolio
Hopper
Review
Project
Close
New
submission
Reject / Re -
submission
Rolls-Royce proprietary information
Active Project Governance
EIC PMO
Continuous
Review
Project
status
tracking
Cost
adherence
Benefit
realisation
review
Milestone
Delivery
Change
Control
Project
Health
Check
Risk
Rolls-Royce proprietary information
Supporting Tools
19
Rolls-Royce proprietary information
ForumPass
• Exostar’s ForumPass is a cloud-based, collaboration platform
• Specifically for communities with high security requirements.
• Built on the Microsoft SharePoint platform
• Desktop integration with Microsoft Office and Outlook
• Integration with SharePoint Designer, InfoPath, and Visio
• Automation workflows and business processes.
Rolls-Royce proprietary information
ForumPass for the EIC
• To improve how information is managed
• To facilitate collaboration
• To centralise critical data and information
• To enable automation of many aspects of reporting and
information dissemination
• Requires little intervention from IT.
Rolls-Royce proprietary information
PMIS
• A Portfolio Management Information System (PMIS) is a
standard set of automated tools available to an organisation
and integrated into a system. For the management of a
Portfolio of Projects.
• ForumPass provides a platform onto which a PMIS for the
EIC can be created
Rolls-Royce proprietary information
EIC PMIS Aims
• Centralise Project / Programme / Portfolio Information
- Storage of key artefacts
- Template management
- Version control, History and roll-back capability
- Traceability
- Remove double entry and duplication
• Facilitate collaboration and communication
- Easy sharing and group working
- Availability of information
- Automation of (some) communication
• Automate project and programme processes
- Change control, risk management, escalations and authorisations
- Reporting
Rolls-Royce proprietary information
To select projects that will deliver the greatest combined effect with
the least resources within defined risk constraints
Portfolio Hopper Management
Rolls-Royce proprietary information
Portfolio Hopper Management
• A collection of projects that the business would want the EIC to
fund.
• Projects provided to the EIC with core outline and requirements
• Pass through an assessment for validation, approval or rejection.
• After approval then the detailed project artefacts will be required
to generate standard RR business process documents for funding
and onward project management
• The Portfolio hopper will manage the authorisation (by EIC) of
projects and programmes to pass into the delivery model.
Rolls-Royce proprietary information
‘Doing the Correct Things’
Idea
New and On-going
Projects (for
subsequent years)
SUBMISSION
Load Project
requirements into
ForumPass EIC Portfolio
Hopper
QUALIFICATION
PMO Quality validation,
prioritisation, alignment
to Horizontals / Verticals
THEME REVIEW
Strategic review and
prioritisation / shortlist
EIC EXECUTIVE REVIEW
Final joint approval of
project portfolio to be
planned and delivered
Rejected Projects either
No-Go or ‘holding’ as
reserve projects
LAUNCH
Final projects budgeted
at Work Centre level and
Launch requirements
created
LIVE PROJECTS
Active Projects loaded
and managed for delivery
BASELINE
Detailed planning and
budgeting completed
(minimum @ Work
Centre level)
Rolls-Royce proprietary information
Key Data Hierarchy – ‘The Project’
PROJECT
All data centres
around the project
RISKS
BENEFITS
Schedule Milestones
Programme
Sub-
Function
EIC
Portfolio
Engineering
Portfolio
ISSUES
RESOURCES
Vertical
Alignment
Strategic
View
Function
Strategy
Engineering
Strategy
Benefit Area
Business
Function Benefit
Sector Benefit
Area
Business Area
Benefit
Rolls-Royce proprietary information
Creation of new
submission
Checklist
Project
Qualification
Gate
Determine project
relationships via
QFD2
Acquire & Rank
Sector
Requirements
Sector
Importance
Determine
relationships via
QFD1
Business
Prioritisation
Ranking of new
Projects
Director
Review
Baseline Project
Prioritisation
Project Portfolio
Selection
Baseline in-year
Portfolio
How to Prioritise
EIC Projects
How to Define &
Maintain a
Portfolio in the EIC
Gate
Statement To
Deliver
How to Deliver a
Project in the EIC
Checklist
Project Launch /
into Discovery
GateProject BaselineChecklist
Delivery &
Continuous
Review
Need for Change
Identified
Multi-Year
Project
Multi-Year Project
Ranking
Director
Review
How to Undertake
Change Control in
the EIC Portfolio
Gate
Change Request
Initiated
Gate
Change Impact
Assesment
Approval
Implement
Changes
Communicate
Completion
Change Rejected
Re-work?
Estimate RoM
Benefits and
Strategic Fit
How to Manage
Benefits in EIC
Programmes &
Projects
Refine Benefits
Estimate Based
on Agreed Scope
& Funding
Project Close
Categorise
Benefits & Obtain
Approval from
Benefit Owner
Baseline Benefits
in EIC PMIS
Verify Benefits
Delivered and
Report
3rd
April 2014
Process Key
EIC End 2 End Process for Portfolio Management and Delivery
Start
Review
Strategy
Strategy
Manage changes
to benefits as
project evolves
Load / Capacity
Balance
How to manage
EIC strategy
How to manage
Load / Capacity
Balance
Funding
How to manage
Funding
Rolls-Royce proprietary information
29
Rolls-Royce proprietary information

Contenu connexe

Tendances

SAFe (Scaled Agile Framework) 5 mins overview - Roni Tamari
SAFe (Scaled Agile Framework) 5 mins overview - Roni TamariSAFe (Scaled Agile Framework) 5 mins overview - Roni Tamari
SAFe (Scaled Agile Framework) 5 mins overview - Roni TamariAgileSparks
 
The People Model and Cloud Transformation | AWS Public Sector Summit 2016
The People Model and Cloud Transformation | AWS Public Sector Summit 2016The People Model and Cloud Transformation | AWS Public Sector Summit 2016
The People Model and Cloud Transformation | AWS Public Sector Summit 2016Amazon Web Services
 
DevOps Maturity Curve v5
DevOps Maturity Curve v5DevOps Maturity Curve v5
DevOps Maturity Curve v5Paul Peissner
 
Agile and Scrum Basics
Agile and Scrum BasicsAgile and Scrum Basics
Agile and Scrum BasicsMazhar Khan
 
Project management with kanban board
Project management with kanban boardProject management with kanban board
Project management with kanban boardProofHub
 
Introduction to Kong API Gateway
Introduction to Kong API GatewayIntroduction to Kong API Gateway
Introduction to Kong API GatewayYohann Ciurlik
 
Designing Event-Driven Applications with Apache NiFi, Apache Flink, Apache Sp...
Designing Event-Driven Applications with Apache NiFi, Apache Flink, Apache Sp...Designing Event-Driven Applications with Apache NiFi, Apache Flink, Apache Sp...
Designing Event-Driven Applications with Apache NiFi, Apache Flink, Apache Sp...Timothy Spann
 
MuleSoft Online Meetup - Salesforce Streaming APIs
MuleSoft Online Meetup - Salesforce Streaming APIsMuleSoft Online Meetup - Salesforce Streaming APIs
MuleSoft Online Meetup - Salesforce Streaming APIsRoyston Lobo
 
Agile Scrum Quick Reference Card
Agile Scrum Quick Reference CardAgile Scrum Quick Reference Card
Agile Scrum Quick Reference CardTechcanvass
 
Real-Life Use Cases & Architectures for Event Streaming with Apache Kafka
Real-Life Use Cases & Architectures for Event Streaming with Apache KafkaReal-Life Use Cases & Architectures for Event Streaming with Apache Kafka
Real-Life Use Cases & Architectures for Event Streaming with Apache KafkaKai Wähner
 
Agile, User Stories, Domain Driven Design
Agile, User Stories, Domain Driven DesignAgile, User Stories, Domain Driven Design
Agile, User Stories, Domain Driven DesignAraf Karsh Hamid
 
Set your Data in Motion with Confluent & Apache Kafka Tech Talk Series LME
Set your Data in Motion with Confluent & Apache Kafka Tech Talk Series LMESet your Data in Motion with Confluent & Apache Kafka Tech Talk Series LME
Set your Data in Motion with Confluent & Apache Kafka Tech Talk Series LMEconfluent
 
Agile Coaching Workshop
Agile Coaching WorkshopAgile Coaching Workshop
Agile Coaching WorkshopCraig Smith
 
Monitoring Kubernetes with Prometheus
Monitoring Kubernetes with PrometheusMonitoring Kubernetes with Prometheus
Monitoring Kubernetes with PrometheusGrafana Labs
 
LKCE14 Kanban at Scale, Scaling Kanban
LKCE14 Kanban at Scale, Scaling KanbanLKCE14 Kanban at Scale, Scaling Kanban
LKCE14 Kanban at Scale, Scaling KanbanKlaus Leopold
 

Tendances (20)

SAFe (Scaled Agile Framework) 5 mins overview - Roni Tamari
SAFe (Scaled Agile Framework) 5 mins overview - Roni TamariSAFe (Scaled Agile Framework) 5 mins overview - Roni Tamari
SAFe (Scaled Agile Framework) 5 mins overview - Roni Tamari
 
Professional Scrum Master I (PSM-I)
Professional Scrum Master I (PSM-I)Professional Scrum Master I (PSM-I)
Professional Scrum Master I (PSM-I)
 
The People Model and Cloud Transformation | AWS Public Sector Summit 2016
The People Model and Cloud Transformation | AWS Public Sector Summit 2016The People Model and Cloud Transformation | AWS Public Sector Summit 2016
The People Model and Cloud Transformation | AWS Public Sector Summit 2016
 
DevOps Maturity Curve v5
DevOps Maturity Curve v5DevOps Maturity Curve v5
DevOps Maturity Curve v5
 
Agile and Scrum Basics
Agile and Scrum BasicsAgile and Scrum Basics
Agile and Scrum Basics
 
Project management with kanban board
Project management with kanban boardProject management with kanban board
Project management with kanban board
 
Introduction to Kong API Gateway
Introduction to Kong API GatewayIntroduction to Kong API Gateway
Introduction to Kong API Gateway
 
Designing Event-Driven Applications with Apache NiFi, Apache Flink, Apache Sp...
Designing Event-Driven Applications with Apache NiFi, Apache Flink, Apache Sp...Designing Event-Driven Applications with Apache NiFi, Apache Flink, Apache Sp...
Designing Event-Driven Applications with Apache NiFi, Apache Flink, Apache Sp...
 
MuleSoft Online Meetup - Salesforce Streaming APIs
MuleSoft Online Meetup - Salesforce Streaming APIsMuleSoft Online Meetup - Salesforce Streaming APIs
MuleSoft Online Meetup - Salesforce Streaming APIs
 
Agile Scrum Quick Reference Card
Agile Scrum Quick Reference CardAgile Scrum Quick Reference Card
Agile Scrum Quick Reference Card
 
Scaled Agile Framework SAFe 4.0
Scaled Agile Framework SAFe 4.0Scaled Agile Framework SAFe 4.0
Scaled Agile Framework SAFe 4.0
 
Real-Life Use Cases & Architectures for Event Streaming with Apache Kafka
Real-Life Use Cases & Architectures for Event Streaming with Apache KafkaReal-Life Use Cases & Architectures for Event Streaming with Apache Kafka
Real-Life Use Cases & Architectures for Event Streaming with Apache Kafka
 
Salesforce Files Connect
Salesforce Files ConnectSalesforce Files Connect
Salesforce Files Connect
 
Agile, User Stories, Domain Driven Design
Agile, User Stories, Domain Driven DesignAgile, User Stories, Domain Driven Design
Agile, User Stories, Domain Driven Design
 
Set your Data in Motion with Confluent & Apache Kafka Tech Talk Series LME
Set your Data in Motion with Confluent & Apache Kafka Tech Talk Series LMESet your Data in Motion with Confluent & Apache Kafka Tech Talk Series LME
Set your Data in Motion with Confluent & Apache Kafka Tech Talk Series LME
 
Introduction to Agile and Scrum
Introduction to Agile and ScrumIntroduction to Agile and Scrum
Introduction to Agile and Scrum
 
Agile Coaching Workshop
Agile Coaching WorkshopAgile Coaching Workshop
Agile Coaching Workshop
 
Monitoring Kubernetes with Prometheus
Monitoring Kubernetes with PrometheusMonitoring Kubernetes with Prometheus
Monitoring Kubernetes with Prometheus
 
Scrum cheatsheet
Scrum cheatsheetScrum cheatsheet
Scrum cheatsheet
 
LKCE14 Kanban at Scale, Scaling Kanban
LKCE14 Kanban at Scale, Scaling KanbanLKCE14 Kanban at Scale, Scaling Kanban
LKCE14 Kanban at Scale, Scaling Kanban
 

En vedette

Rolls-Royce presentation FINAL PP
Rolls-Royce presentation FINAL PPRolls-Royce presentation FINAL PP
Rolls-Royce presentation FINAL PPEsra Bombaci
 
Andrew Bai's Engineering Portfolio
Andrew Bai's Engineering PortfolioAndrew Bai's Engineering Portfolio
Andrew Bai's Engineering PortfolioAndrew Bai
 
Myles Lynch Engineering portfolio
Myles Lynch Engineering portfolioMyles Lynch Engineering portfolio
Myles Lynch Engineering portfolioMyles Lynch
 
Rolls Royce Aerospace & Defense Digital Strategy
Rolls Royce Aerospace & Defense Digital StrategyRolls Royce Aerospace & Defense Digital Strategy
Rolls Royce Aerospace & Defense Digital StrategyKeegan Sapla
 
Placement Presentation
Placement PresentationPlacement Presentation
Placement PresentationHuw Griffin
 
Kevin Sherrington-Lodge, Customer Order Fulfilment Director at Rolls-Royce - ...
Kevin Sherrington-Lodge, Customer Order Fulfilment Director at Rolls-Royce - ...Kevin Sherrington-Lodge, Customer Order Fulfilment Director at Rolls-Royce - ...
Kevin Sherrington-Lodge, Customer Order Fulfilment Director at Rolls-Royce - ...Global Business Events
 
Value Chain Innovation Report
Value Chain Innovation ReportValue Chain Innovation Report
Value Chain Innovation ReportYuhao Xie
 
Rolls Royce Phantom.
Rolls Royce Phantom.Rolls Royce Phantom.
Rolls Royce Phantom.Saqlain Akram
 
Proposal for rolls royce to adapt an erp system
Proposal for rolls royce to adapt an erp systemProposal for rolls royce to adapt an erp system
Proposal for rolls royce to adapt an erp systemKunal Chadha
 
Modelo de acuerdo de nivel de servicios sla
Modelo de acuerdo de nivel de servicios  sla Modelo de acuerdo de nivel de servicios  sla
Modelo de acuerdo de nivel de servicios sla Leandro Be
 
Acuerdos de Niveles de Servicio
Acuerdos de Niveles de ServicioAcuerdos de Niveles de Servicio
Acuerdos de Niveles de ServicioJohn Ospina
 
Rolls Royce Brand Analysis
Rolls Royce Brand AnalysisRolls Royce Brand Analysis
Rolls Royce Brand AnalysisNerissa Marbury
 

En vedette (20)

Portfolio management in Rolls-Royce today
Portfolio management in Rolls-Royce todayPortfolio management in Rolls-Royce today
Portfolio management in Rolls-Royce today
 
Rolls-Royce presentation FINAL PP
Rolls-Royce presentation FINAL PPRolls-Royce presentation FINAL PP
Rolls-Royce presentation FINAL PP
 
Rolls_Royce
Rolls_RoyceRolls_Royce
Rolls_Royce
 
Andrew Bai's Engineering Portfolio
Andrew Bai's Engineering PortfolioAndrew Bai's Engineering Portfolio
Andrew Bai's Engineering Portfolio
 
ENGINEERING AND DESIGN PORTFOLIO
ENGINEERING AND DESIGN PORTFOLIOENGINEERING AND DESIGN PORTFOLIO
ENGINEERING AND DESIGN PORTFOLIO
 
Myles Lynch Engineering portfolio
Myles Lynch Engineering portfolioMyles Lynch Engineering portfolio
Myles Lynch Engineering portfolio
 
Rolls Royce Aerospace & Defense Digital Strategy
Rolls Royce Aerospace & Defense Digital StrategyRolls Royce Aerospace & Defense Digital Strategy
Rolls Royce Aerospace & Defense Digital Strategy
 
Placement Presentation
Placement PresentationPlacement Presentation
Placement Presentation
 
Kevin Sherrington-Lodge, Customer Order Fulfilment Director at Rolls-Royce - ...
Kevin Sherrington-Lodge, Customer Order Fulfilment Director at Rolls-Royce - ...Kevin Sherrington-Lodge, Customer Order Fulfilment Director at Rolls-Royce - ...
Kevin Sherrington-Lodge, Customer Order Fulfilment Director at Rolls-Royce - ...
 
Value Chain Innovation Report
Value Chain Innovation ReportValue Chain Innovation Report
Value Chain Innovation Report
 
Rolls Royce Phantom.
Rolls Royce Phantom.Rolls Royce Phantom.
Rolls Royce Phantom.
 
Prince2
Prince2Prince2
Prince2
 
Rolls royce
Rolls royceRolls royce
Rolls royce
 
Engineering design portfolio
Engineering design portfolioEngineering design portfolio
Engineering design portfolio
 
Proposal for rolls royce to adapt an erp system
Proposal for rolls royce to adapt an erp systemProposal for rolls royce to adapt an erp system
Proposal for rolls royce to adapt an erp system
 
Modelo de acuerdo de nivel de servicios sla
Modelo de acuerdo de nivel de servicios  sla Modelo de acuerdo de nivel de servicios  sla
Modelo de acuerdo de nivel de servicios sla
 
Acuerdo de nivel de servicio (ANS o SLA)
Acuerdo de nivel de servicio (ANS o SLA)Acuerdo de nivel de servicio (ANS o SLA)
Acuerdo de nivel de servicio (ANS o SLA)
 
Acuerdos de Niveles de Servicio
Acuerdos de Niveles de ServicioAcuerdos de Niveles de Servicio
Acuerdos de Niveles de Servicio
 
Rolls royce (2)
Rolls royce (2)Rolls royce (2)
Rolls royce (2)
 
Rolls Royce Brand Analysis
Rolls Royce Brand AnalysisRolls Royce Brand Analysis
Rolls Royce Brand Analysis
 

Similaire à Portfolio Management in the Rolls-Royce Engineering Improvements Centre

Simplifying it using a disciplined portfolio governance approach
Simplifying it using a disciplined portfolio governance approachSimplifying it using a disciplined portfolio governance approach
Simplifying it using a disciplined portfolio governance approachp6academy
 
Integrated Enterprise PPM, ALM and APM on force.com cloud
Integrated Enterprise PPM, ALM and APM on force.com cloudIntegrated Enterprise PPM, ALM and APM on force.com cloud
Integrated Enterprise PPM, ALM and APM on force.com cloudPoornima N
 
Conig® v1.5 Converged Information Governance
Conig® v1.5 Converged Information GovernanceConig® v1.5 Converged Information Governance
Conig® v1.5 Converged Information GovernanceYalcin Gerek
 
CONIG® v1.5 Converged Information Governance
CONIG® v1.5 Converged Information GovernanceCONIG® v1.5 Converged Information Governance
CONIG® v1.5 Converged Information GovernanceYalcin Gerek
 
Cloudbyz ppm, integrated enterprise ppm-alm-apm on force.com
Cloudbyz ppm,   integrated enterprise ppm-alm-apm on force.comCloudbyz ppm,   integrated enterprise ppm-alm-apm on force.com
Cloudbyz ppm, integrated enterprise ppm-alm-apm on force.comDinesh Sheshadri
 
6.18.2013 - 2013 - Prj & Port Mgmt SftDev - Portfolio Management - For the ...
6.18.2013 -  2013 - Prj & Port Mgmt SftDev - Portfolio Management -  For the ...6.18.2013 -  2013 - Prj & Port Mgmt SftDev - Portfolio Management -  For the ...
6.18.2013 - 2013 - Prj & Port Mgmt SftDev - Portfolio Management - For the ...IBM Rational
 
James Blance Resume_2016
James Blance Resume_2016James Blance Resume_2016
James Blance Resume_2016James Blance
 
Moving Up the PVC Maturity Curve in Industrial Manufacturing
Moving Up the PVC Maturity Curve in Industrial ManufacturingMoving Up the PVC Maturity Curve in Industrial Manufacturing
Moving Up the PVC Maturity Curve in Industrial ManufacturingZero Wait-State
 
Howard Kornblum Resume R12a[1]
Howard Kornblum Resume R12a[1]Howard Kornblum Resume R12a[1]
Howard Kornblum Resume R12a[1]west5812
 
205480 oracle primavera enterprise success at city of hope
205480 oracle primavera enterprise success at city of hope205480 oracle primavera enterprise success at city of hope
205480 oracle primavera enterprise success at city of hopep6academy
 
140101 Eclipsys Services - EN
140101 Eclipsys Services - EN140101 Eclipsys Services - EN
140101 Eclipsys Services - ENPeter Bissegger
 
Alliance session 4373 risk management from on premise to the cloud – a foc...
Alliance session 4373    risk management from on premise to the cloud – a foc...Alliance session 4373    risk management from on premise to the cloud – a foc...
Alliance session 4373 risk management from on premise to the cloud – a foc...Smart ERP Solutions, Inc.
 
HP's vision for an integrated IT Service Portfolio Management
HP's vision for an integrated IT Service Portfolio ManagementHP's vision for an integrated IT Service Portfolio Management
HP's vision for an integrated IT Service Portfolio ManagementHP Enterprise Italia
 
Building a Data Streaming Center of Excellence With Steve Gonzalez and Derek ...
Building a Data Streaming Center of Excellence With Steve Gonzalez and Derek ...Building a Data Streaming Center of Excellence With Steve Gonzalez and Derek ...
Building a Data Streaming Center of Excellence With Steve Gonzalez and Derek ...HostedbyConfluent
 

Similaire à Portfolio Management in the Rolls-Royce Engineering Improvements Centre (20)

Simplifying it using a disciplined portfolio governance approach
Simplifying it using a disciplined portfolio governance approachSimplifying it using a disciplined portfolio governance approach
Simplifying it using a disciplined portfolio governance approach
 
schofield_alan-CV
schofield_alan-CVschofield_alan-CV
schofield_alan-CV
 
Integrated Enterprise PPM, ALM and APM on force.com cloud
Integrated Enterprise PPM, ALM and APM on force.com cloudIntegrated Enterprise PPM, ALM and APM on force.com cloud
Integrated Enterprise PPM, ALM and APM on force.com cloud
 
Conig® v1.5 Converged Information Governance
Conig® v1.5 Converged Information GovernanceConig® v1.5 Converged Information Governance
Conig® v1.5 Converged Information Governance
 
CONIG® v1.5 Converged Information Governance
CONIG® v1.5 Converged Information GovernanceCONIG® v1.5 Converged Information Governance
CONIG® v1.5 Converged Information Governance
 
Cloudbyz ppm, integrated enterprise ppm-alm-apm on force.com
Cloudbyz ppm,   integrated enterprise ppm-alm-apm on force.comCloudbyz ppm,   integrated enterprise ppm-alm-apm on force.com
Cloudbyz ppm, integrated enterprise ppm-alm-apm on force.com
 
6.18.2013 - 2013 - Prj & Port Mgmt SftDev - Portfolio Management - For the ...
6.18.2013 -  2013 - Prj & Port Mgmt SftDev - Portfolio Management -  For the ...6.18.2013 -  2013 - Prj & Port Mgmt SftDev - Portfolio Management -  For the ...
6.18.2013 - 2013 - Prj & Port Mgmt SftDev - Portfolio Management - For the ...
 
Swapan's resume Aug 2017
Swapan's resume Aug 2017Swapan's resume Aug 2017
Swapan's resume Aug 2017
 
James Blance Resume_2016
James Blance Resume_2016James Blance Resume_2016
James Blance Resume_2016
 
Moving Up the PVC Maturity Curve in Industrial Manufacturing
Moving Up the PVC Maturity Curve in Industrial ManufacturingMoving Up the PVC Maturity Curve in Industrial Manufacturing
Moving Up the PVC Maturity Curve in Industrial Manufacturing
 
Unified PPM & Agile
Unified PPM & AgileUnified PPM & Agile
Unified PPM & Agile
 
Howard Kornblum Resume R12a[1]
Howard Kornblum Resume R12a[1]Howard Kornblum Resume R12a[1]
Howard Kornblum Resume R12a[1]
 
Disha Roy
Disha RoyDisha Roy
Disha Roy
 
205480 oracle primavera enterprise success at city of hope
205480 oracle primavera enterprise success at city of hope205480 oracle primavera enterprise success at city of hope
205480 oracle primavera enterprise success at city of hope
 
PMExpo2017slide Eureka Service - Oracle Prime
PMExpo2017slide Eureka Service - Oracle PrimePMExpo2017slide Eureka Service - Oracle Prime
PMExpo2017slide Eureka Service - Oracle Prime
 
140101 Eclipsys Services - EN
140101 Eclipsys Services - EN140101 Eclipsys Services - EN
140101 Eclipsys Services - EN
 
Alliance session 4373 risk management from on premise to the cloud – a foc...
Alliance session 4373    risk management from on premise to the cloud – a foc...Alliance session 4373    risk management from on premise to the cloud – a foc...
Alliance session 4373 risk management from on premise to the cloud – a foc...
 
HP's vision for an integrated IT Service Portfolio Management
HP's vision for an integrated IT Service Portfolio ManagementHP's vision for an integrated IT Service Portfolio Management
HP's vision for an integrated IT Service Portfolio Management
 
PW cv1602 03
PW cv1602 03PW cv1602 03
PW cv1602 03
 
Building a Data Streaming Center of Excellence With Steve Gonzalez and Derek ...
Building a Data Streaming Center of Excellence With Steve Gonzalez and Derek ...Building a Data Streaming Center of Excellence With Steve Gonzalez and Derek ...
Building a Data Streaming Center of Excellence With Steve Gonzalez and Derek ...
 

Plus de Association for Project Management

Making communications land - Are they received and understood as intended? we...
Making communications land - Are they received and understood as intended? we...Making communications land - Are they received and understood as intended? we...
Making communications land - Are they received and understood as intended? we...Association for Project Management
 
APM Welcome, APM North West Network Conference, Synergies Across Sectors
APM Welcome, APM North West Network Conference, Synergies Across SectorsAPM Welcome, APM North West Network Conference, Synergies Across Sectors
APM Welcome, APM North West Network Conference, Synergies Across SectorsAssociation for Project Management
 
Projecting for the Future: Harmonising Energy and Environment, APM North West...
Projecting for the Future: Harmonising Energy and Environment, APM North West...Projecting for the Future: Harmonising Energy and Environment, APM North West...
Projecting for the Future: Harmonising Energy and Environment, APM North West...Association for Project Management
 
New to Nuclear - Transition into nuclear from other sectors, APM North West N...
New to Nuclear - Transition into nuclear from other sectors, APM North West N...New to Nuclear - Transition into nuclear from other sectors, APM North West N...
New to Nuclear - Transition into nuclear from other sectors, APM North West N...Association for Project Management
 
Tell us what to do, not how to do it, APM North West Network Conference, Syne...
Tell us what to do, not how to do it, APM North West Network Conference, Syne...Tell us what to do, not how to do it, APM North West Network Conference, Syne...
Tell us what to do, not how to do it, APM North West Network Conference, Syne...Association for Project Management
 
The Future is Fractional, APM North West Network Conference, Synergies Across...
The Future is Fractional, APM North West Network Conference, Synergies Across...The Future is Fractional, APM North West Network Conference, Synergies Across...
The Future is Fractional, APM North West Network Conference, Synergies Across...Association for Project Management
 
Lessons learned across projects, APM North West Network Conference, Synergies...
Lessons learned across projects, APM North West Network Conference, Synergies...Lessons learned across projects, APM North West Network Conference, Synergies...
Lessons learned across projects, APM North West Network Conference, Synergies...Association for Project Management
 
Agile Adaptability: Navigating Project Management in a Dynamic World, APM Nor...
Agile Adaptability: Navigating Project Management in a Dynamic World, APM Nor...Agile Adaptability: Navigating Project Management in a Dynamic World, APM Nor...
Agile Adaptability: Navigating Project Management in a Dynamic World, APM Nor...Association for Project Management
 
Inclusive Practices in Project Management: Leveraging Digital Frameworks for ...
Inclusive Practices in Project Management: Leveraging Digital Frameworks for ...Inclusive Practices in Project Management: Leveraging Digital Frameworks for ...
Inclusive Practices in Project Management: Leveraging Digital Frameworks for ...Association for Project Management
 
Leadership - the project professionals secret weapon, 24 April 2024
Leadership - the project professionals secret weapon, 24 April 2024Leadership - the project professionals secret weapon, 24 April 2024
Leadership - the project professionals secret weapon, 24 April 2024Association for Project Management
 
APM Project Management Awards - Hints and tips for a winning award entry webi...
APM Project Management Awards - Hints and tips for a winning award entry webi...APM Project Management Awards - Hints and tips for a winning award entry webi...
APM Project Management Awards - Hints and tips for a winning award entry webi...Association for Project Management
 
The Vyrnwy Aqueduct Modernisation Programme webinar, 17 April 2024
The Vyrnwy Aqueduct Modernisation Programme webinar, 17 April 2024The Vyrnwy Aqueduct Modernisation Programme webinar, 17 April 2024
The Vyrnwy Aqueduct Modernisation Programme webinar, 17 April 2024Association for Project Management
 
Team Lead Succeed – Helping you and your team achieve high-performance teamwo...
Team Lead Succeed – Helping you and your team achieve high-performance teamwo...Team Lead Succeed – Helping you and your team achieve high-performance teamwo...
Team Lead Succeed – Helping you and your team achieve high-performance teamwo...Association for Project Management
 
AI in the project profession: examples of current use and roadmaps to adoptio...
AI in the project profession: examples of current use and roadmaps to adoptio...AI in the project profession: examples of current use and roadmaps to adoptio...
AI in the project profession: examples of current use and roadmaps to adoptio...Association for Project Management
 

Plus de Association for Project Management (20)

Making communications land - Are they received and understood as intended? we...
Making communications land - Are they received and understood as intended? we...Making communications land - Are they received and understood as intended? we...
Making communications land - Are they received and understood as intended? we...
 
Spatium Project Simulation student brief
Spatium Project Simulation student briefSpatium Project Simulation student brief
Spatium Project Simulation student brief
 
APM Welcome, APM North West Network Conference, Synergies Across Sectors
APM Welcome, APM North West Network Conference, Synergies Across SectorsAPM Welcome, APM North West Network Conference, Synergies Across Sectors
APM Welcome, APM North West Network Conference, Synergies Across Sectors
 
Projecting for the Future: Harmonising Energy and Environment, APM North West...
Projecting for the Future: Harmonising Energy and Environment, APM North West...Projecting for the Future: Harmonising Energy and Environment, APM North West...
Projecting for the Future: Harmonising Energy and Environment, APM North West...
 
New to Nuclear - Transition into nuclear from other sectors, APM North West N...
New to Nuclear - Transition into nuclear from other sectors, APM North West N...New to Nuclear - Transition into nuclear from other sectors, APM North West N...
New to Nuclear - Transition into nuclear from other sectors, APM North West N...
 
Tell us what to do, not how to do it, APM North West Network Conference, Syne...
Tell us what to do, not how to do it, APM North West Network Conference, Syne...Tell us what to do, not how to do it, APM North West Network Conference, Syne...
Tell us what to do, not how to do it, APM North West Network Conference, Syne...
 
The Future is Fractional, APM North West Network Conference, Synergies Across...
The Future is Fractional, APM North West Network Conference, Synergies Across...The Future is Fractional, APM North West Network Conference, Synergies Across...
The Future is Fractional, APM North West Network Conference, Synergies Across...
 
Lessons learned across projects, APM North West Network Conference, Synergies...
Lessons learned across projects, APM North West Network Conference, Synergies...Lessons learned across projects, APM North West Network Conference, Synergies...
Lessons learned across projects, APM North West Network Conference, Synergies...
 
Agile Adaptability: Navigating Project Management in a Dynamic World, APM Nor...
Agile Adaptability: Navigating Project Management in a Dynamic World, APM Nor...Agile Adaptability: Navigating Project Management in a Dynamic World, APM Nor...
Agile Adaptability: Navigating Project Management in a Dynamic World, APM Nor...
 
Inclusive Practices in Project Management: Leveraging Digital Frameworks for ...
Inclusive Practices in Project Management: Leveraging Digital Frameworks for ...Inclusive Practices in Project Management: Leveraging Digital Frameworks for ...
Inclusive Practices in Project Management: Leveraging Digital Frameworks for ...
 
Leadership - the project professionals secret weapon, 24 April 2024
Leadership - the project professionals secret weapon, 24 April 2024Leadership - the project professionals secret weapon, 24 April 2024
Leadership - the project professionals secret weapon, 24 April 2024
 
APM Project Management Awards - Hints and tips for a winning award entry webi...
APM Project Management Awards - Hints and tips for a winning award entry webi...APM Project Management Awards - Hints and tips for a winning award entry webi...
APM Project Management Awards - Hints and tips for a winning award entry webi...
 
The Vyrnwy Aqueduct Modernisation Programme webinar, 17 April 2024
The Vyrnwy Aqueduct Modernisation Programme webinar, 17 April 2024The Vyrnwy Aqueduct Modernisation Programme webinar, 17 April 2024
The Vyrnwy Aqueduct Modernisation Programme webinar, 17 April 2024
 
Team Lead Succeed – Helping you and your team achieve high-performance teamwo...
Team Lead Succeed – Helping you and your team achieve high-performance teamwo...Team Lead Succeed – Helping you and your team achieve high-performance teamwo...
Team Lead Succeed – Helping you and your team achieve high-performance teamwo...
 
Staurt Earl - ARCC Programme for APM Awards.pptx
Staurt Earl - ARCC Programme for APM Awards.pptxStaurt Earl - ARCC Programme for APM Awards.pptx
Staurt Earl - ARCC Programme for APM Awards.pptx
 
If AI changes everything – do feelings still matter?
If AI changes everything – do feelings still matter?If AI changes everything – do feelings still matter?
If AI changes everything – do feelings still matter?
 
AI in the project profession: examples of current use and roadmaps to adoptio...
AI in the project profession: examples of current use and roadmaps to adoptio...AI in the project profession: examples of current use and roadmaps to adoptio...
AI in the project profession: examples of current use and roadmaps to adoptio...
 
Katharine Fox, WRAP - Valuing sustainability
Katharine Fox, WRAP - Valuing sustainabilityKatharine Fox, WRAP - Valuing sustainability
Katharine Fox, WRAP - Valuing sustainability
 
The silent project disruptor: Building AI solutions
The silent project disruptor: Building AI solutionsThe silent project disruptor: Building AI solutions
The silent project disruptor: Building AI solutions
 
Personal Resilience in Project Management 2 - TV Edit 1a.pdf
Personal Resilience in Project Management 2 - TV Edit 1a.pdfPersonal Resilience in Project Management 2 - TV Edit 1a.pdf
Personal Resilience in Project Management 2 - TV Edit 1a.pdf
 

Dernier

Yaroslav Rozhankivskyy: Три складові і три передумови максимальної продуктивн...
Yaroslav Rozhankivskyy: Три складові і три передумови максимальної продуктивн...Yaroslav Rozhankivskyy: Три складові і три передумови максимальної продуктивн...
Yaroslav Rozhankivskyy: Три складові і три передумови максимальної продуктивн...Lviv Startup Club
 
Best VIP Call Girls Noida Sector 40 Call Me: 8448380779
Best VIP Call Girls Noida Sector 40 Call Me: 8448380779Best VIP Call Girls Noida Sector 40 Call Me: 8448380779
Best VIP Call Girls Noida Sector 40 Call Me: 8448380779Delhi Call girls
 
Regression analysis: Simple Linear Regression Multiple Linear Regression
Regression analysis:  Simple Linear Regression Multiple Linear RegressionRegression analysis:  Simple Linear Regression Multiple Linear Regression
Regression analysis: Simple Linear Regression Multiple Linear RegressionRavindra Nath Shukla
 
Call Girls In DLf Gurgaon ➥99902@11544 ( Best price)100% Genuine Escort In 24...
Call Girls In DLf Gurgaon ➥99902@11544 ( Best price)100% Genuine Escort In 24...Call Girls In DLf Gurgaon ➥99902@11544 ( Best price)100% Genuine Escort In 24...
Call Girls In DLf Gurgaon ➥99902@11544 ( Best price)100% Genuine Escort In 24...lizamodels9
 
VIP Call Girls In Saharaganj ( Lucknow ) 🔝 8923113531 🔝 Cash Payment (COD) 👒
VIP Call Girls In Saharaganj ( Lucknow  ) 🔝 8923113531 🔝  Cash Payment (COD) 👒VIP Call Girls In Saharaganj ( Lucknow  ) 🔝 8923113531 🔝  Cash Payment (COD) 👒
VIP Call Girls In Saharaganj ( Lucknow ) 🔝 8923113531 🔝 Cash Payment (COD) 👒anilsa9823
 
BEST ✨ Call Girls In Indirapuram Ghaziabad ✔️ 9871031762 ✔️ Escorts Service...
BEST ✨ Call Girls In  Indirapuram Ghaziabad  ✔️ 9871031762 ✔️ Escorts Service...BEST ✨ Call Girls In  Indirapuram Ghaziabad  ✔️ 9871031762 ✔️ Escorts Service...
BEST ✨ Call Girls In Indirapuram Ghaziabad ✔️ 9871031762 ✔️ Escorts Service...noida100girls
 
Monte Carlo simulation : Simulation using MCSM
Monte Carlo simulation : Simulation using MCSMMonte Carlo simulation : Simulation using MCSM
Monte Carlo simulation : Simulation using MCSMRavindra Nath Shukla
 
Progress Report - Oracle Database Analyst Summit
Progress  Report - Oracle Database Analyst SummitProgress  Report - Oracle Database Analyst Summit
Progress Report - Oracle Database Analyst SummitHolger Mueller
 
VIP Call Girl Jamshedpur Aashi 8250192130 Independent Escort Service Jamshedpur
VIP Call Girl Jamshedpur Aashi 8250192130 Independent Escort Service JamshedpurVIP Call Girl Jamshedpur Aashi 8250192130 Independent Escort Service Jamshedpur
VIP Call Girl Jamshedpur Aashi 8250192130 Independent Escort Service JamshedpurSuhani Kapoor
 
Mondelez State of Snacking and Future Trends 2023
Mondelez State of Snacking and Future Trends 2023Mondelez State of Snacking and Future Trends 2023
Mondelez State of Snacking and Future Trends 2023Neil Kimberley
 
Value Proposition canvas- Customer needs and pains
Value Proposition canvas- Customer needs and painsValue Proposition canvas- Customer needs and pains
Value Proposition canvas- Customer needs and painsP&CO
 
Cash Payment 9602870969 Escort Service in Udaipur Call Girls
Cash Payment 9602870969 Escort Service in Udaipur Call GirlsCash Payment 9602870969 Escort Service in Udaipur Call Girls
Cash Payment 9602870969 Escort Service in Udaipur Call GirlsApsara Of India
 
Tech Startup Growth Hacking 101 - Basics on Growth Marketing
Tech Startup Growth Hacking 101  - Basics on Growth MarketingTech Startup Growth Hacking 101  - Basics on Growth Marketing
Tech Startup Growth Hacking 101 - Basics on Growth MarketingShawn Pang
 
Sales & Marketing Alignment: How to Synergize for Success
Sales & Marketing Alignment: How to Synergize for SuccessSales & Marketing Alignment: How to Synergize for Success
Sales & Marketing Alignment: How to Synergize for SuccessAggregage
 
M.C Lodges -- Guest House in Jhang.
M.C Lodges --  Guest House in Jhang.M.C Lodges --  Guest House in Jhang.
M.C Lodges -- Guest House in Jhang.Aaiza Hassan
 
Call Girls Pune Just Call 9907093804 Top Class Call Girl Service Available
Call Girls Pune Just Call 9907093804 Top Class Call Girl Service AvailableCall Girls Pune Just Call 9907093804 Top Class Call Girl Service Available
Call Girls Pune Just Call 9907093804 Top Class Call Girl Service AvailableDipal Arora
 
Russian Faridabad Call Girls(Badarpur) : ☎ 8168257667, @4999
Russian Faridabad Call Girls(Badarpur) : ☎ 8168257667, @4999Russian Faridabad Call Girls(Badarpur) : ☎ 8168257667, @4999
Russian Faridabad Call Girls(Badarpur) : ☎ 8168257667, @4999Tina Ji
 
The Coffee Bean & Tea Leaf(CBTL), Business strategy case study
The Coffee Bean & Tea Leaf(CBTL), Business strategy case studyThe Coffee Bean & Tea Leaf(CBTL), Business strategy case study
The Coffee Bean & Tea Leaf(CBTL), Business strategy case studyEthan lee
 
GD Birla and his contribution in management
GD Birla and his contribution in managementGD Birla and his contribution in management
GD Birla and his contribution in managementchhavia330
 

Dernier (20)

Yaroslav Rozhankivskyy: Три складові і три передумови максимальної продуктивн...
Yaroslav Rozhankivskyy: Три складові і три передумови максимальної продуктивн...Yaroslav Rozhankivskyy: Три складові і три передумови максимальної продуктивн...
Yaroslav Rozhankivskyy: Три складові і три передумови максимальної продуктивн...
 
Best VIP Call Girls Noida Sector 40 Call Me: 8448380779
Best VIP Call Girls Noida Sector 40 Call Me: 8448380779Best VIP Call Girls Noida Sector 40 Call Me: 8448380779
Best VIP Call Girls Noida Sector 40 Call Me: 8448380779
 
Regression analysis: Simple Linear Regression Multiple Linear Regression
Regression analysis:  Simple Linear Regression Multiple Linear RegressionRegression analysis:  Simple Linear Regression Multiple Linear Regression
Regression analysis: Simple Linear Regression Multiple Linear Regression
 
Call Girls In DLf Gurgaon ➥99902@11544 ( Best price)100% Genuine Escort In 24...
Call Girls In DLf Gurgaon ➥99902@11544 ( Best price)100% Genuine Escort In 24...Call Girls In DLf Gurgaon ➥99902@11544 ( Best price)100% Genuine Escort In 24...
Call Girls In DLf Gurgaon ➥99902@11544 ( Best price)100% Genuine Escort In 24...
 
VIP Call Girls In Saharaganj ( Lucknow ) 🔝 8923113531 🔝 Cash Payment (COD) 👒
VIP Call Girls In Saharaganj ( Lucknow  ) 🔝 8923113531 🔝  Cash Payment (COD) 👒VIP Call Girls In Saharaganj ( Lucknow  ) 🔝 8923113531 🔝  Cash Payment (COD) 👒
VIP Call Girls In Saharaganj ( Lucknow ) 🔝 8923113531 🔝 Cash Payment (COD) 👒
 
BEST ✨ Call Girls In Indirapuram Ghaziabad ✔️ 9871031762 ✔️ Escorts Service...
BEST ✨ Call Girls In  Indirapuram Ghaziabad  ✔️ 9871031762 ✔️ Escorts Service...BEST ✨ Call Girls In  Indirapuram Ghaziabad  ✔️ 9871031762 ✔️ Escorts Service...
BEST ✨ Call Girls In Indirapuram Ghaziabad ✔️ 9871031762 ✔️ Escorts Service...
 
Monte Carlo simulation : Simulation using MCSM
Monte Carlo simulation : Simulation using MCSMMonte Carlo simulation : Simulation using MCSM
Monte Carlo simulation : Simulation using MCSM
 
Nepali Escort Girl Kakori \ 9548273370 Indian Call Girls Service Lucknow ₹,9517
Nepali Escort Girl Kakori \ 9548273370 Indian Call Girls Service Lucknow ₹,9517Nepali Escort Girl Kakori \ 9548273370 Indian Call Girls Service Lucknow ₹,9517
Nepali Escort Girl Kakori \ 9548273370 Indian Call Girls Service Lucknow ₹,9517
 
Progress Report - Oracle Database Analyst Summit
Progress  Report - Oracle Database Analyst SummitProgress  Report - Oracle Database Analyst Summit
Progress Report - Oracle Database Analyst Summit
 
VIP Call Girl Jamshedpur Aashi 8250192130 Independent Escort Service Jamshedpur
VIP Call Girl Jamshedpur Aashi 8250192130 Independent Escort Service JamshedpurVIP Call Girl Jamshedpur Aashi 8250192130 Independent Escort Service Jamshedpur
VIP Call Girl Jamshedpur Aashi 8250192130 Independent Escort Service Jamshedpur
 
Mondelez State of Snacking and Future Trends 2023
Mondelez State of Snacking and Future Trends 2023Mondelez State of Snacking and Future Trends 2023
Mondelez State of Snacking and Future Trends 2023
 
Value Proposition canvas- Customer needs and pains
Value Proposition canvas- Customer needs and painsValue Proposition canvas- Customer needs and pains
Value Proposition canvas- Customer needs and pains
 
Cash Payment 9602870969 Escort Service in Udaipur Call Girls
Cash Payment 9602870969 Escort Service in Udaipur Call GirlsCash Payment 9602870969 Escort Service in Udaipur Call Girls
Cash Payment 9602870969 Escort Service in Udaipur Call Girls
 
Tech Startup Growth Hacking 101 - Basics on Growth Marketing
Tech Startup Growth Hacking 101  - Basics on Growth MarketingTech Startup Growth Hacking 101  - Basics on Growth Marketing
Tech Startup Growth Hacking 101 - Basics on Growth Marketing
 
Sales & Marketing Alignment: How to Synergize for Success
Sales & Marketing Alignment: How to Synergize for SuccessSales & Marketing Alignment: How to Synergize for Success
Sales & Marketing Alignment: How to Synergize for Success
 
M.C Lodges -- Guest House in Jhang.
M.C Lodges --  Guest House in Jhang.M.C Lodges --  Guest House in Jhang.
M.C Lodges -- Guest House in Jhang.
 
Call Girls Pune Just Call 9907093804 Top Class Call Girl Service Available
Call Girls Pune Just Call 9907093804 Top Class Call Girl Service AvailableCall Girls Pune Just Call 9907093804 Top Class Call Girl Service Available
Call Girls Pune Just Call 9907093804 Top Class Call Girl Service Available
 
Russian Faridabad Call Girls(Badarpur) : ☎ 8168257667, @4999
Russian Faridabad Call Girls(Badarpur) : ☎ 8168257667, @4999Russian Faridabad Call Girls(Badarpur) : ☎ 8168257667, @4999
Russian Faridabad Call Girls(Badarpur) : ☎ 8168257667, @4999
 
The Coffee Bean & Tea Leaf(CBTL), Business strategy case study
The Coffee Bean & Tea Leaf(CBTL), Business strategy case studyThe Coffee Bean & Tea Leaf(CBTL), Business strategy case study
The Coffee Bean & Tea Leaf(CBTL), Business strategy case study
 
GD Birla and his contribution in management
GD Birla and his contribution in managementGD Birla and his contribution in management
GD Birla and his contribution in management
 

Portfolio Management in the Rolls-Royce Engineering Improvements Centre

  • 1. Trusted to deliver excellence © 2013 Rolls-Royce plc The information in this document is the property of Rolls-Royce plc and may not be copied or communicated to a third party, or used for any purpose other than that for which it is supplied without the express written consent of Rolls-Royce plc. This information is given in good faith based upon the latest information available to Rolls-Royce plc, no warranty or representation is given concerning such information, which must not be taken as establishing any contractual or other commitment binding upon Rolls-Royce plc or any of its subsidiary or associated companies. Portfolio Management APM Session– April 2014 Prepared by EIC Communications John McGregor Chief Of Delivery, EIC Dean Hall EIC PMO
  • 3. Integrated Production System This session • Portfolio Management within the Engineering Improvement centre • How we govern and support our work Rolls-Royce proprietary information
  • 4. APM Defintion “Portfolio management is the selection and management of all of an organisation’s projects, programmes and related business-as-usual activities taking into account resource constraints. A portfolio is a group of projects and programmes carried out under the sponsorship of an organisation.” Portfolio management seeks to ensure that organisations: 1. Invest in the ‘right’ projects and programmes in the context of their strategic objectives and subject to the constraints of risk and affordability. 2. Manage their project and programmes ‘right’ – at a collective level, by effective management of limited resources, dependencies and the organisation’s capacity to absorb change. 3. Realise the full benefits from their investment in projects and programmes 4. Capture lessons learned and use them to inform the development of more efficient and effective management of their portfolios. Rolls-Royce proprietary information
  • 5. APM Defintion “Portfolio management is the selection and management of all of an organisation’s projects, programmes and related business-as-usual activities taking into account resource constraints. A portfolio is a group of projects and programmes carried out under the sponsorship of an organisation.” In summary, portfolio management seeks to ensure that organisations: 1. Invest in the ‘right’ projects and programmes in the context of their strategic objectives and subject to the constraints of risk and affordability. 2. Manage their project and programmes ‘right’ – at a collective level, by effective management of limited resources, dependencies and the organisation’s capacity to absorb change. 3. Realise the full benefits from their investment in projects and programmes 4. Capture lessons learned and use them to inform the development of more efficient and effective management of their portfolios. Rolls-Royce proprietary information
  • 6. Portfolio Management The continuous process of identification, prioritisation, selection and delivery management of projects that align to the corporate strategy and business objectives Rolls-Royce proprietary information
  • 7. Portfolio and Project Management Impact UNREALISED VALUE Improve Project Management Improve Portfolio Management PortfolioManagement “Doingthecorrectthings” Programme & Project Management “Doing things correctly” 0% 100% 100% Portfolio Management acts as the commissioning body for Programmes and Projects Rolls-Royce proprietary information REALISED PROJECT VALUE
  • 9. The current Portfolio 9 Rolls-Royce proprietary information
  • 10. The EIC Portfolio EIC Portfolio Delivery TransformStandardise Maintain Integrated Design, Simulation and Verification -- Right first time designs throughout the product lifecycle in the presence of variation Lean Engineering and Functional Maturity -- Operating a mature efficient and effective function across the engineering process lifecycle Enabling IT -- Modern effective and user friendly IT enabling the engineering process and people Product, Data & Document Management Systems -- Smooth transition of data and documents across the product lifecycle Rolls-Royce proprietary information
  • 11. EIC Product Data & Document Management (PLM) Knowledge Management Collaboration TEDS PLM Applications Integrated Design Simulation & Verification Virtual Engine/Product Design Automation Mech System Design Tools & Methods Performance/ Aero/Fluids High Performance Computing Lean Engineering & Functional Maturity Product Family Standards Engineering Process Robust Engineering Global Specs & Standards Enabling IT Architecture Infrastructure Corporate Initiatives HPC Infrastructure RRES Architecture EIC Portfolio Rolls-Royce proprietary information
  • 12. EIC DATA Knowledge Management Collaboration TEDS PLM Applications APPS Virtual Engine/Product Design Automation Mech System Design Tools & Methods Performance/ Aero/Fluids High Performance Computing PROCESS Product Family Standards Engineering Process Robust Engineering Global Specs & Standards INFRASTRUCTURE Architecture Infrastructure Corporate Initiatives HPC Infrastructure STRATEGY EIC Portfolio Rolls-Royce proprietary information
  • 13. The Engineering model 13 Central Engineering and Technology Energy Aerospace Marine Nuclear Engineering Functions Customer Develop and deploy capability Construct and deliver projects Rolls-Royce proprietary information
  • 14. EIC Organisation Sector/function Head of Engineering Business Improvement Portfolio Operations Chief Engineer Integrated design simulation and verification Lean functional operation and maturity Enabling ITProduct, data & doc management systems Chief of Delivery Chief of Strategy Director Chief of Transformation Transformation and Operations Safety & Product Assurance Systems Eng Development Systems Design Component Design Engineering 4 Services/GTS Controls & Electrical Eng Test & Measurement Manufacture Materials Technical Office Portfolio Management Office Finance & Quality Business Operations Office Engineering Functions Theme Lead Theme Lead Theme Lead Rolls-Royce proprietary information Theme Lead
  • 15. EIC Product Data & Document Management Knowledge Management Collaboration TEDS PLM Applications Integrated Design Simulation & Verification Virtual Engine/Product Design Automation Mech System Design Tools & Methods Performance/ Aero/Fluids High Performance Computing Lean Engineering & Functional Maturity Product Family Standards Engineering Process Robust Engineering Global Specs & Standards Enabling IT Architecture Infrastructure Corporate Initiatives HPC Infrastructure RRES Architecture Governing the Portfolio Component Design Controls / Electrical Engineering Engineering 4 Services / GTS Materials Safety Systems Design System Engineering Development Test and Measurement Transformation & Operations Tools & MethodsTools & MethodsTools & MethodsTools & Methods Mech System Design Virtual Engine/Product Design Automation Engineering Process Robust Engineering Global Specs & Standards Knowledge Management Engineering Process Knowledge Management Rolls-Royce proprietary information
  • 16. How we govern and track our work 16
  • 18. Active Project Governance EIC PMO Continuous Review Project status tracking Cost adherence Benefit realisation review Milestone Delivery Change Control Project Health Check Risk Rolls-Royce proprietary information
  • 20. ForumPass • Exostar’s ForumPass is a cloud-based, collaboration platform • Specifically for communities with high security requirements. • Built on the Microsoft SharePoint platform • Desktop integration with Microsoft Office and Outlook • Integration with SharePoint Designer, InfoPath, and Visio • Automation workflows and business processes. Rolls-Royce proprietary information
  • 21. ForumPass for the EIC • To improve how information is managed • To facilitate collaboration • To centralise critical data and information • To enable automation of many aspects of reporting and information dissemination • Requires little intervention from IT. Rolls-Royce proprietary information
  • 22. PMIS • A Portfolio Management Information System (PMIS) is a standard set of automated tools available to an organisation and integrated into a system. For the management of a Portfolio of Projects. • ForumPass provides a platform onto which a PMIS for the EIC can be created Rolls-Royce proprietary information
  • 23. EIC PMIS Aims • Centralise Project / Programme / Portfolio Information - Storage of key artefacts - Template management - Version control, History and roll-back capability - Traceability - Remove double entry and duplication • Facilitate collaboration and communication - Easy sharing and group working - Availability of information - Automation of (some) communication • Automate project and programme processes - Change control, risk management, escalations and authorisations - Reporting Rolls-Royce proprietary information
  • 24. To select projects that will deliver the greatest combined effect with the least resources within defined risk constraints Portfolio Hopper Management Rolls-Royce proprietary information
  • 25. Portfolio Hopper Management • A collection of projects that the business would want the EIC to fund. • Projects provided to the EIC with core outline and requirements • Pass through an assessment for validation, approval or rejection. • After approval then the detailed project artefacts will be required to generate standard RR business process documents for funding and onward project management • The Portfolio hopper will manage the authorisation (by EIC) of projects and programmes to pass into the delivery model. Rolls-Royce proprietary information
  • 26. ‘Doing the Correct Things’ Idea New and On-going Projects (for subsequent years) SUBMISSION Load Project requirements into ForumPass EIC Portfolio Hopper QUALIFICATION PMO Quality validation, prioritisation, alignment to Horizontals / Verticals THEME REVIEW Strategic review and prioritisation / shortlist EIC EXECUTIVE REVIEW Final joint approval of project portfolio to be planned and delivered Rejected Projects either No-Go or ‘holding’ as reserve projects LAUNCH Final projects budgeted at Work Centre level and Launch requirements created LIVE PROJECTS Active Projects loaded and managed for delivery BASELINE Detailed planning and budgeting completed (minimum @ Work Centre level) Rolls-Royce proprietary information
  • 27. Key Data Hierarchy – ‘The Project’ PROJECT All data centres around the project RISKS BENEFITS Schedule Milestones Programme Sub- Function EIC Portfolio Engineering Portfolio ISSUES RESOURCES Vertical Alignment Strategic View Function Strategy Engineering Strategy Benefit Area Business Function Benefit Sector Benefit Area Business Area Benefit Rolls-Royce proprietary information
  • 28. Creation of new submission Checklist Project Qualification Gate Determine project relationships via QFD2 Acquire & Rank Sector Requirements Sector Importance Determine relationships via QFD1 Business Prioritisation Ranking of new Projects Director Review Baseline Project Prioritisation Project Portfolio Selection Baseline in-year Portfolio How to Prioritise EIC Projects How to Define & Maintain a Portfolio in the EIC Gate Statement To Deliver How to Deliver a Project in the EIC Checklist Project Launch / into Discovery GateProject BaselineChecklist Delivery & Continuous Review Need for Change Identified Multi-Year Project Multi-Year Project Ranking Director Review How to Undertake Change Control in the EIC Portfolio Gate Change Request Initiated Gate Change Impact Assesment Approval Implement Changes Communicate Completion Change Rejected Re-work? Estimate RoM Benefits and Strategic Fit How to Manage Benefits in EIC Programmes & Projects Refine Benefits Estimate Based on Agreed Scope & Funding Project Close Categorise Benefits & Obtain Approval from Benefit Owner Baseline Benefits in EIC PMIS Verify Benefits Delivered and Report 3rd April 2014 Process Key EIC End 2 End Process for Portfolio Management and Delivery Start Review Strategy Strategy Manage changes to benefits as project evolves Load / Capacity Balance How to manage EIC strategy How to manage Load / Capacity Balance Funding How to manage Funding Rolls-Royce proprietary information