17. City of Beaufort Goals for Boundary Street
Create Livable Communities through Strategic
Infrastructure Investments
Encourage Economic Development on the Corridor
Improve Safety and Traffic Flow for Pedestrians,
Cyclists and Automobiles
34. Improved Mobility Options
Trailhead Park and Multi-Use Path
Trailhead 1 Acre Park at Rail-Trail Connection
Over 1 Mile in Trail Parallel to Boundary Street
Marsh Repair along Trail Route
36. Parallel Street – Polk Street
Street Trees, Lighting and Sidewalks
Power Lines Underground
On-street Parking
37. The Big Moves – Completed and Planned
1. Parallel Road Network
2. Street Trees & Proper Sidewalks
3. “Boulevard-style” Slow Lane + Parking
4. Special Intersections at 2 Key Spots
5. Greenspace: “window” squares, marsh-front,
possible central park
6. Civic Buildings Positioned Correctly
7. Strip Centers Converted to Town Blocks
39. Next Steps
Design Phase: Feb 2012 – March 2013
Permitting: April 2012 – Oct 2012
NEPA Documentation: Feb 2012 – Oct 2012
ROW Acquisition: Aug 2012 – April 2013
Bidding: April 2013 – May 2013
Construction: June 2012 – Jan 2015