2. CONTENTS:
Project Overview
Civil Construction and Fatima Fertilizer
My Working Areas
○ Roads and its Structures
○ Weigh Bridge
○ Nitro Phosphate (NP) Plant
3. Project Overview:
Salient Features:
Start of Land Acquiring in Year 2005.
Total Land Acquired 800 acres.
Estimated Cost in Rs. = 8,000 million
Start of project phase in April 2007 (NA plant).
Total no of plants/supporting areas are 50+.
Four Types of Fertilizer Products/Plants having design
capacity.
1. Urea 1500 MTPD
2. CAN 1400 MTPD
3. NP 1200 MTPD
4. NPK 1000 MTPD
4. Project Overview:
Salient Features:
Other Supporting Plants having design capacity
1. Ammonia 1500 MTPD
2. Nitric Acid 1500 MTPD
3. Offsite & Utilities 50 MW
Gas consumption of 75 MMCFD
Civil Contractors
1. CNCEC China
2. IPL Pakistan
Civil Designers
1. NESPAK Pakistan
2. A & A Pakistan
5. Civil Construction and Fatima Fertilizer:
Civil Engineering role in the establishment of any
kind of project is not ignorable.
The project like Fatima Fertilizer, its importance is
more.
Fatima Fertilizer have structures
From simple pumps foundations to complex pile
foundation under Prilling towers and Ammonia Tank.
From steel structures of Urea, CAN, Bulk Storage & Ware
houses to concrete structures of Cooling Tower, Raw water
Reservoir, Bagging, NA and NP plants.
From Technical building, CCR I & II, Substations to Strom
water drains, water pits, area development and network of
roads.
6. Civil Construction and Fatima Fertilizer:
In Fatima Fertilizer, basic form of structure is
frame structure .
Frame Structure is a combination of beams and
columns and load is transfer through this system
to design foundation.
Two types of frame structures are used.
1. Steel Structures
2. Concrete Structures
7. Steel Structures:
Steel structures are basically composite structures
having substructure of concrete and superstructure
of steel e.g.
• Ammonia & Urea Plants
• CAN & NPK Plants
• Bulk Storage (Phase-I)
• Ware houses, Pipe Racks etc.
8. Concrete Structures:
Concrete structures comprise of both substructure
and superstructure of concrete e.g.
• Raw Water Reservoir and Treatment Plant
• Cooling Tower & Urea Prilling Tower
• Bagging (Phase I & II)
• Bulk storage (Phase II)
• NP Plant
• Substations CCR I & II and Equalization Basin
• Workshop, Technical Building, Laboratory, etc
9. Pictorial View of Civil Construction in
FFCL:
Construction View of
Urea Prilling Tower and Plant
14. Bagging (Phase – II)
under construction
NP Plant
under construction
15. My Working Areas:
In Fatima Fertilizer during my Trainee period of
1 year, I worked on Roads and its Structures,
Construction of Weigh Bridge and also play a
vital role in the construction of NP plant.
16. Job Responsibilities:
Study of Drawings
Design Reviews
Survey of roads
Quality Control at site ( Formwork, Steel & Concrete)
Inspections before concrete
Checking of Bar Bending Schedule
Checking of Bills
17. Roads and its Structures:
Salient Features
Total length of Roads = 17.484 km
Completed Length of roads = 8.301 km
Remaining Length of roads = 9.183 km
Roads have Strom water drain and walkway on one
side, and shoulders on both sides.
Designer = Akbar & Associates
Contractors = IPL, Farhan Munir &
Company, AHCC
Type of Pavement = Rigid Pavement
Design Capacity = 90 Tons
18. What is Rigid Pavement?
Rigid pavements are generally constructed of a reinforced
concrete slab or more recently a continuously reinforced
concrete road base.
The pavement structure deflects very little under loading
due to the high modulus of elasticity of their surface
course.
A rigid pavement structure is typically composed of a PCC
or RCC surface course built on top of either
○ the sub-grade or
○ an underlying base course.
20. Why we (FFCL) preferred Rigid Pavement instead
of Flexible Pavement (Carpet Road)?
Rigid Pavement lasts much, much longer i.e. 30+ years compared
to 5-10 years of flexible pavements.
In the long run it is about half the cost to install and maintain.
But the initial costs are somewhat high.
Rigid pavement has the ability to bridge small imperfections in
the sub grade.
Less Maintenance cost and Continuous Traffic and Flow.
Low thermal variation as compared to Flexible Pavement.
Rigid Pavement has one draw back in terms of its repair i.e. we
have to remove 2-3 panels instead of damaged portion as in case
of Flexible pavements.
26. Nitro Phosphate (NP) Plant:
NP plant started from Prilling Tower in 2009.
Estimated Civil Cost in Rs. = 279.1 million
Civil Designer = NESPAK
Civil Contractor = IPL
80% of Civil work completed.
Remaining 20% include Refrigeration area
and Lime Drying unit, paints, brick masonry,
and finishing works.
27. Nitro Phosphate (NP) Plant:
NP Plant is divided into four parts
Prilling Tower & Lift Well
Main Building
Substation
CN & AN Section, Refrigeration Area, and Lime
Drying Unit
28. Salient Features:
Prilling Tower supported on 72 piles of length 27m.
Prilling Tower has height of 67.9m and diameter of 19m.
Lift Well has height of 70.1m, supported on 900mm thick
raft foundation.
Main Building has dimensions of 67.5m x 27.5m x 37.3m
supported on raft foundation.
Main Building comprise of 10 floors max on line 1-2.
Substation comprise of 2 floors supported on isolated
foundation.
29. Special Techniques adopted at NP Plant:
Prilling Tower and Lift Well concrete done by
using Slip Form Method.
Strengthening of Columns has to be decided.
30. Slip Form Method:
The most common method adopted for the construction of
an RCC outer shell/prilling tower is by using the ‘slip form
method’.
In this method the form work for the concrete literally slips
up cm by cm to produce an integrated concrete column in
the form of wall.
Continuous pouring of concrete ensures a joint free
construction.
At a rate of 0.3 meters per hour, this is consider as fast
construction method.
31. Components of Slip Form Method:
Slip form method is comprise of a complicated system of jacks
and radial screws.
Radial steel yokes, which have an inverted “U” at both ends,
support the slip form shuttering all around the shell/prilling
tower.
Walers strengthen and keep the shuttering in place.
The working deck and scaffolding is supported from the
walers and yokes.
The yokes are supported on hydraulic jacks, which move on
jack rods embedded in the concrete.
As the concrete pouring progresses the jacks lifts up the yokes,
together with the decks and slip form.
Screwed on pieces extend the jack rod as the work progresses.
The entire system of decks and shuttering appear as if floating
on top of the tower.
34. Strengthening of Columns:
To increase the capacity of NP Main Building columns
from 3500 Tons to 5500 Tons, the procedure that is used
called Strengthening of columns.
Why Strengthening of columns needed?
Continuous changing of mechanical design of Cfit of
NP main building, load on columns increased from
3500 Tons to 5500 Tons.
To counter this problem, columns has to be strengthened
by using concrete and steel jacketing.