4. Overview of the park
• Natural setting, integrate to what is there, minimal
construction and minimal disturbance
• Rotating sculptural displays donated by artists, combined
with permanent pieces acquired over time
• Integrate education, physical activities and deeper
community engagement to open up more grant
opportunities and create a unique experience for kids and
adults alike
– Ideas: Rubbings, Community Garden, Interactive elements
(Whisper bench), Community Built Art
5. EXISTING LANDSCAPE
DRAINAGE EASEMENT
WATERQUALITYBUFFERZONE
FLOODPLAIN 100 YEAR
FLOODPLAIN 2 YEAR
Teresa Stephens
Organic teresa@pollydog.com
Landscapes 512-296-4195
9. Over 20 species of trees, shrubs,
perennials, grasses and wildflowers
10.
11.
12. Bee Cave Sculpture Park Phase 1 Budget
Design/Site Preparation Hotel/Motel Tax Funds City Beautification Funds Bee Cave Arts Foundation
Landscape/Park Design $0.00 $0.00 $2,500.00
Underbrush clearing/tree removal $0.00 $0.00 Volunteer Effort
Granite Path (granite & labor) $0.00 $1,575.00 $0.00
Granite path borders (stones on site) $0.00 $0.00 Volunteer Effort
Total $0.00 $1,575.00 $2,500.00
Drainage Hotel/Motel Tax Funds City Beautification Funds Bee Cave Arts Foundation
Re-grade for drainage & paths $0.00 $985.00 $0.00
Fill drainage areas with river rock $0.00 $3,500.00 $0.00
Add large boulder stepping stones $0.00 $875.00 $0.00
Total $0.00 $5,360.00 $0.00
Sculpture Installations Hotel/Motel Tax Funds City Beautification Funds Bee Cave Arts Foundation
10 4x4 Concrete Sculpture Pads $2,000.00 $0.00 $0.00
Sculpture sourcing $0.00 $0.00 $250.00
Installation of sculptures $0.00 $0.00 $500.00
Payment for leased sculptures $0.00 $0.00 $1,600.00
Acquisition of 2 permanent sculptures $0.00 $0.00 $4,000.00
Total $2,000.00 $0.00 $6,350.00
Miscellaneous Hotel/Motel Tax Funds City Beautification Funds Bee Cave Arts Foundation
TML Insurance $500.00 $0.00 $0.00
Ongoing landscape maintenance $0.00 $1,000.00 Volunteer Effort
New Sign $0.00 $0.00 $500.00
Total $500.00 $1,000.00 $0.00
Total Expenses Hotel/Motel Tax Funds City Beautification Funds Bee Cave Arts Foundation
Totals $2,500.00 $7,935.00 $8,850.00
Phase 1 (Optional)
Front Entry Beds Hotel/Motel Tax Funds City Beautification Funds Bee Cave Arts Foundation
Retaining wall for entry beds $0.00 $3,800.00 $0.00
Soli for entry beds $0.00 $855.00 $0.00
Plants for entry beds $0.00 $660.00 $0.00
Mulch for entry beds $0.00 $375.00 $0.00
Irrigation (optional) $0.00 $1,000.00 $0.00
Total $0.00 $6,690.00 $0.00
13. Bee Cave Sculpture Park Timeline
COUNCIL UPDATE AND APPROVAL SCULPTURE INSTALLATION
PARK CLEAN-UP DAY
OAK TREE PRUNING
CALL TO ARTISTS SCULPTURE SELECTION
9 Apr 9 May 9 Jun 9 Jul 9 Aug 9 Sep 9 Oct
SCULPTURE PADS INSTALLED SCULPTURE PARK OPENING
DRAINAGE WORK COMPLETE
GRANITE PATH INSTALLATION
PROJECT DETAILS
DATE MILESTONE
9-Apr Council update and approval
20-Apr Park clean-up day
1-May Call to artists
1-Jun Sculpture pads installed
30-Jun Drainage work complete
13-Jul Granite path installation
15-Jul Sculpture selection
1-Aug Oak tree pruning
30-Sep Sculpture Installation
12-Oct Sculpture Park Opening
Notes de l'éditeur
Large TreesUlmuscrassifolia- Cedar elmQuercusfusiformis- Texas live oakFraxinusamericana- White ashPlatanusoccidentalis- American sycamoreSmall Trees and ShrubsSophorasecundiflora- Texas mountain laurelDiospyrostexana- Texas persimmonMahoniatrifoliolata- AgaritaSabal minor - Dwarf palmettoOpuntiasp. - PricklypearPerennials and Grasses*Iris sp. - Wild IrisHilariabelangeri- Curly mesquite grassSchizachyriumscoparium- Little bluestem*There are many more perennial wild flowers and grasses on site, but they are justwaking up for spring and I have not identified them all.