Kitchen Remodel Risk Management and Mitigation Plan

Risk                                                    Likelihood   Impact    Risk response                                                           Responsibility
                                                        (H/M/L)      (H/M/L)   (Containment or contingency strategies)
Overall plan exceeds maximum budget costs               H            H         Would have to develop alternate solutions or cost saving ideas.         Project Manager
                                                                               Purchase cheaper items to meet the budget                               Project Team
Team members can’t participate                          L            M         Project Managers duty to locate more volunteers to participate on the   Project Manager
Lack of help on the project                                                    project
Appliances and products being unavailable               L            L         Project Manager would have to choose an alternate product to            Project Manager
                                                                               replace the unavailable appliance. Again, he would have to stay in
                                                                               the boundaries of the allowable budget
Problems with dismantling/installing the plumbing for   M            H         Project Manager would have to seek the services of a contractor or      Project Manager
the kitchen sink and faucet.                                                   plumber
Phases may exceed the timeline that was estimated       H            H         Project Manager may have to find other resources to help the team       Project Manager
due to installation problems and mistakes.                                     accomplish the task                                                     Project Team
Learning curve involved with the project team           H            H         Identify ways and ideas to help the project team attain their           Project Manager
members                                                                        knowledge quicker.
Damaged items that need to replaced and reordered       L            L         Project Manager would have to rearrange the completion order of the     Project Manager
                                                                               project phases.
Items that need to be readjusted or redone              H            H         This would impact whether the project will be done to meet the          Project Manager
                                                                               project deadline. Again, contractors may need to be used.

More Related Content

Viewers also liked

Project Risk Management (10)
 Project Risk Management (10) Project Risk Management (10)
Project Risk Management (10)
Serdar Temiz
 
Film production risk assessment form
Film production risk assessment formFilm production risk assessment form
Film production risk assessment form
cembitmead
 
New Microsoft Office PowerPoint Presentation
New Microsoft Office PowerPoint PresentationNew Microsoft Office PowerPoint Presentation
New Microsoft Office PowerPoint Presentation
Pragmatic Advisory
 
Final Presentation Ministry 2014-02-19
Final Presentation Ministry 2014-02-19Final Presentation Ministry 2014-02-19
Final Presentation Ministry 2014-02-19
Md. Abul Monsur
 
Company Profile PT. Keisi Indonesia-1
Company Profile PT. Keisi Indonesia-1Company Profile PT. Keisi Indonesia-1
Company Profile PT. Keisi Indonesia-1
christian kurniawan
 
Alaska Fly fishing
Alaska Fly fishing Alaska Fly fishing
Alaska Fly fishing
reeza fazily
 
Stephanie Orpurt-Ross Sample Business Proposal-Team Project
Stephanie Orpurt-Ross Sample Business Proposal-Team ProjectStephanie Orpurt-Ross Sample Business Proposal-Team Project
Stephanie Orpurt-Ross Sample Business Proposal-Team Project
stephross
 

Viewers also liked (13)

Project Risk Management (10)
 Project Risk Management (10) Project Risk Management (10)
Project Risk Management (10)
 
Film production risk assessment form
Film production risk assessment formFilm production risk assessment form
Film production risk assessment form
 
Risk Management Framework
Risk Management FrameworkRisk Management Framework
Risk Management Framework
 
New Microsoft Office PowerPoint Presentation
New Microsoft Office PowerPoint PresentationNew Microsoft Office PowerPoint Presentation
New Microsoft Office PowerPoint Presentation
 
Assumption infatuation
Assumption infatuationAssumption infatuation
Assumption infatuation
 
Stonehurst Student Housing Renovation 2012
Stonehurst Student Housing Renovation 2012Stonehurst Student Housing Renovation 2012
Stonehurst Student Housing Renovation 2012
 
So you want a new kitchen!
So you want a new kitchen!So you want a new kitchen!
So you want a new kitchen!
 
Final Presentation Ministry 2014-02-19
Final Presentation Ministry 2014-02-19Final Presentation Ministry 2014-02-19
Final Presentation Ministry 2014-02-19
 
Onions cultivation project - Project management
Onions cultivation project - Project managementOnions cultivation project - Project management
Onions cultivation project - Project management
 
Company Profile PT. Keisi Indonesia-1
Company Profile PT. Keisi Indonesia-1Company Profile PT. Keisi Indonesia-1
Company Profile PT. Keisi Indonesia-1
 
My Fire Risk Assessment Template
My Fire Risk Assessment TemplateMy Fire Risk Assessment Template
My Fire Risk Assessment Template
 
Alaska Fly fishing
Alaska Fly fishing Alaska Fly fishing
Alaska Fly fishing
 
Stephanie Orpurt-Ross Sample Business Proposal-Team Project
Stephanie Orpurt-Ross Sample Business Proposal-Team ProjectStephanie Orpurt-Ross Sample Business Proposal-Team Project
Stephanie Orpurt-Ross Sample Business Proposal-Team Project
 

More from brianbish10795 (9)

Life Of A Chinese Farmer In 2006
Life Of A Chinese Farmer In 2006Life Of A Chinese Farmer In 2006
Life Of A Chinese Farmer In 2006
 
Written Analysis Final Project[1]
Written Analysis Final Project[1]Written Analysis Final Project[1]
Written Analysis Final Project[1]
 
Personal Force Field Analysis
Personal Force Field AnalysisPersonal Force Field Analysis
Personal Force Field Analysis
 
Quality Management Presentation
Quality Management PresentationQuality Management Presentation
Quality Management Presentation
 
VoIP Project Request For Proposal Presentation
VoIP Project Request For Proposal PresentationVoIP Project Request For Proposal Presentation
VoIP Project Request For Proposal Presentation
 
Request For Proposal
Request For ProposalRequest For Proposal
Request For Proposal
 
Communications Management Presentation
Communications Management PresentationCommunications Management Presentation
Communications Management Presentation
 
E Commerce Project Charter
E Commerce Project CharterE Commerce Project Charter
E Commerce Project Charter
 
References
ReferencesReferences
References
 

Recently uploaded

EIS-Webinar-Prompt-Knowledge-Eng-2024-04-08.pptx
EIS-Webinar-Prompt-Knowledge-Eng-2024-04-08.pptxEIS-Webinar-Prompt-Knowledge-Eng-2024-04-08.pptx
EIS-Webinar-Prompt-Knowledge-Eng-2024-04-08.pptx
Earley Information Science
 

Recently uploaded (20)

Driving Behavioral Change for Information Management through Data-Driven Gree...
Driving Behavioral Change for Information Management through Data-Driven Gree...Driving Behavioral Change for Information Management through Data-Driven Gree...
Driving Behavioral Change for Information Management through Data-Driven Gree...
 
Boost PC performance: How more available memory can improve productivity
Boost PC performance: How more available memory can improve productivityBoost PC performance: How more available memory can improve productivity
Boost PC performance: How more available memory can improve productivity
 
08448380779 Call Girls In Civil Lines Women Seeking Men
08448380779 Call Girls In Civil Lines Women Seeking Men08448380779 Call Girls In Civil Lines Women Seeking Men
08448380779 Call Girls In Civil Lines Women Seeking Men
 
Strategize a Smooth Tenant-to-tenant Migration and Copilot Takeoff
Strategize a Smooth Tenant-to-tenant Migration and Copilot TakeoffStrategize a Smooth Tenant-to-tenant Migration and Copilot Takeoff
Strategize a Smooth Tenant-to-tenant Migration and Copilot Takeoff
 
Apidays Singapore 2024 - Building Digital Trust in a Digital Economy by Veron...
Apidays Singapore 2024 - Building Digital Trust in a Digital Economy by Veron...Apidays Singapore 2024 - Building Digital Trust in a Digital Economy by Veron...
Apidays Singapore 2024 - Building Digital Trust in a Digital Economy by Veron...
 
Axa Assurance Maroc - Insurer Innovation Award 2024
Axa Assurance Maroc - Insurer Innovation Award 2024Axa Assurance Maroc - Insurer Innovation Award 2024
Axa Assurance Maroc - Insurer Innovation Award 2024
 
04-2024-HHUG-Sales-and-Marketing-Alignment.pptx
04-2024-HHUG-Sales-and-Marketing-Alignment.pptx04-2024-HHUG-Sales-and-Marketing-Alignment.pptx
04-2024-HHUG-Sales-and-Marketing-Alignment.pptx
 
Scaling API-first – The story of a global engineering organization
Scaling API-first – The story of a global engineering organizationScaling API-first – The story of a global engineering organization
Scaling API-first – The story of a global engineering organization
 
Boost Fertility New Invention Ups Success Rates.pdf
Boost Fertility New Invention Ups Success Rates.pdfBoost Fertility New Invention Ups Success Rates.pdf
Boost Fertility New Invention Ups Success Rates.pdf
 
2024: Domino Containers - The Next Step. News from the Domino Container commu...
2024: Domino Containers - The Next Step. News from the Domino Container commu...2024: Domino Containers - The Next Step. News from the Domino Container commu...
2024: Domino Containers - The Next Step. News from the Domino Container commu...
 
08448380779 Call Girls In Friends Colony Women Seeking Men
08448380779 Call Girls In Friends Colony Women Seeking Men08448380779 Call Girls In Friends Colony Women Seeking Men
08448380779 Call Girls In Friends Colony Women Seeking Men
 
Bajaj Allianz Life Insurance Company - Insurer Innovation Award 2024
Bajaj Allianz Life Insurance Company - Insurer Innovation Award 2024Bajaj Allianz Life Insurance Company - Insurer Innovation Award 2024
Bajaj Allianz Life Insurance Company - Insurer Innovation Award 2024
 
ProductAnonymous-April2024-WinProductDiscovery-MelissaKlemke
ProductAnonymous-April2024-WinProductDiscovery-MelissaKlemkeProductAnonymous-April2024-WinProductDiscovery-MelissaKlemke
ProductAnonymous-April2024-WinProductDiscovery-MelissaKlemke
 
How to Troubleshoot Apps for the Modern Connected Worker
How to Troubleshoot Apps for the Modern Connected WorkerHow to Troubleshoot Apps for the Modern Connected Worker
How to Troubleshoot Apps for the Modern Connected Worker
 
EIS-Webinar-Prompt-Knowledge-Eng-2024-04-08.pptx
EIS-Webinar-Prompt-Knowledge-Eng-2024-04-08.pptxEIS-Webinar-Prompt-Knowledge-Eng-2024-04-08.pptx
EIS-Webinar-Prompt-Knowledge-Eng-2024-04-08.pptx
 
Strategies for Landing an Oracle DBA Job as a Fresher
Strategies for Landing an Oracle DBA Job as a FresherStrategies for Landing an Oracle DBA Job as a Fresher
Strategies for Landing an Oracle DBA Job as a Fresher
 
Raspberry Pi 5: Challenges and Solutions in Bringing up an OpenGL/Vulkan Driv...
Raspberry Pi 5: Challenges and Solutions in Bringing up an OpenGL/Vulkan Driv...Raspberry Pi 5: Challenges and Solutions in Bringing up an OpenGL/Vulkan Driv...
Raspberry Pi 5: Challenges and Solutions in Bringing up an OpenGL/Vulkan Driv...
 
Powerful Google developer tools for immediate impact! (2023-24 C)
Powerful Google developer tools for immediate impact! (2023-24 C)Powerful Google developer tools for immediate impact! (2023-24 C)
Powerful Google developer tools for immediate impact! (2023-24 C)
 
How to Troubleshoot Apps for the Modern Connected Worker
How to Troubleshoot Apps for the Modern Connected WorkerHow to Troubleshoot Apps for the Modern Connected Worker
How to Troubleshoot Apps for the Modern Connected Worker
 
Partners Life - Insurer Innovation Award 2024
Partners Life - Insurer Innovation Award 2024Partners Life - Insurer Innovation Award 2024
Partners Life - Insurer Innovation Award 2024
 

Kitchen Remodel Risk Management And Mitigation Plan

  • 1. Kitchen Remodel Risk Management and Mitigation Plan Risk Likelihood Impact Risk response Responsibility (H/M/L) (H/M/L) (Containment or contingency strategies) Overall plan exceeds maximum budget costs H H Would have to develop alternate solutions or cost saving ideas. Project Manager Purchase cheaper items to meet the budget Project Team Team members can’t participate L M Project Managers duty to locate more volunteers to participate on the Project Manager Lack of help on the project project Appliances and products being unavailable L L Project Manager would have to choose an alternate product to Project Manager replace the unavailable appliance. Again, he would have to stay in the boundaries of the allowable budget Problems with dismantling/installing the plumbing for M H Project Manager would have to seek the services of a contractor or Project Manager the kitchen sink and faucet. plumber Phases may exceed the timeline that was estimated H H Project Manager may have to find other resources to help the team Project Manager due to installation problems and mistakes. accomplish the task Project Team Learning curve involved with the project team H H Identify ways and ideas to help the project team attain their Project Manager members knowledge quicker. Damaged items that need to replaced and reordered L L Project Manager would have to rearrange the completion order of the Project Manager project phases. Items that need to be readjusted or redone H H This would impact whether the project will be done to meet the Project Manager project deadline. Again, contractors may need to be used.