ISSUE:            NC International Terminal
Updated August 6, 2010

The North Carolina International Terminal (NCIT) is a megaport proposed by the North Carolina State Ports Authority, an agency of
the NC Department of Commerce. The Authority has purchased a 600-acre undeveloped industrial tract on the west bank of the
Cape Fear River in Brunswick County for the NCIT project. The proposed site is located four miles from the mouth of the Cape Fear
River and the Atlantic Ocean and only 17 miles from the Port of Wilmington. As envisioned, NCIT would greatly expand the capacity
of the Wilmington port.

According to the proposed plan, the NCIT would be a highly-automated, deep water container terminal capable of serving the most
advanced large vessels and handling two to three million TEUs* per year, a capacity similar to that of the ports at Charleston and
Savannah (* A TEU is a standard unit for describing a ship's cargo carrying capacity, or a shipping terminal's cargo handling capacity).

The Authority says the NCIT could be open for business in 2017 and reach its full capacity by 2030.

History
The concept for the NCIT began taking shape in 2005 when the Ports Authority learned that an undeveloped 600-acre site on the
Cape Fear River was on the market. On April 12, 2006, Ports Authority officials closed on the purchase of the $30 million property as
the proposed site for the NCIT.

After a comprehensive selection process during 2006, in July CH2M Hill, a global engineering and consulting firm was chosen to
manage the development process of the proposed NCIT. The Authority ultimately expanded the scope of CH2M Hill’s work in August
2006 to include the development of a business plan and financial strategy. Completed in March 2008, the plan portrays the project
in a very positive light, claiming that 461,000 jobs throughout the state will be related to the projected level of container operations
at the NCIT.

In June 2008, CenterPoint Properties, a Chicago-based company, became the Ports Authority’s partner in developing the NCIT.
However, in the midst of the economic downturn in the fall of 2008, the Ports Authority announced that CenterPoint would be
forced to withdraw from the project due to limited capital.

In 2009, the US Army Corps of Engineers began a Federally-funded reconnaissance study to determine if there is a Federal interest
for the deepening of the navigation channel to the NCIT. This study was due to be completed in June 2010, but a February 2010 draft
of this study recommends moving forward into the feasibility phase.

Meanwhile, the Ports Authority commissioned their own separate feasibility study by Moffatt & Nichol,a marine engineering firm,
for use in a revenue bond offering. This study was completed in February 2010 and concluded that the project was feasible.

In May 2010, the US Army Corps of Engineers asked the state to participate in the cost of a study to determine the feasibility of
dredging the Cape Fear River for the NCIT. The study would take about five years and cost $10 million, with the state being asked to
pay $4.7 million of this amount. The NC Department of Environment and Natural Resources (DENR) was prepared to sign a letter of
intent that would commit the state to share the cost of the feasibility study.

However, before a feasibility study could proceed, both Congress and the NC General Assembly would have to approve funding for
it. In June 2010, on a vote of 104-11, the state House overwhelmingly approved an amendment removing the proposed funding for
the feasibility study from the state’s 2010-11 budget, and they got no argument from the Senate. The final budget excluded all
funding for the study, placing the future of the NCIT in limbo, at least for the time being.

The Debate
SUPPORTERS say that the NCIT is destined to be “America’s Next Great Port.” According to the North Carolina State Ports Authority,
the project will:

    •    Support over 400,000 jobs.
    •    Provide an additional $1.2 billion in state and local tax revenues.
    •    Drive additional private investment and employment opportunities regionally as distribution centers and logistics facilities
         emerge across Southeastern North Carolina.
    •    Offer convenience to millions of U.S. consumers and businesses.
•    Supply valuable support to the region’s defense-related economy given proximity to the Military Ocean Terminal at Sunny
         Point, and the State’s military bases.
    •    Serve as the state's only deep-water port, allowing cargo shipping to bypass ports at Savannah, Charleston, & Hampton
         Roads and come directly into North Carolina.

In May 2010, the state Ports Authority CEO Tom Eager extolled the virtues of the project, stating, “There is no way this project will
fail. There is no way we can allow this project to fail.” He referred to the activist group No Port Southport, which opposes the
project, as a bunch of “know nothings and transplants.”

SUPPORTERS include:
Governor Beverly Perdue
North Carolina State Ports Authority
US Army Corps of Engineers
NC Department of Environment and Natural Resources (DENR) - Divisions of Coastal Management & Marine Fisheries

OPPONENTS question both the need and the cost for the NCIT. They assert that the Ports Authority's financial projections are based
on invalid assumptions and that the NCIT would lose approximately $25 million per year. Opponents also claim that:

    •    The current container terminal at the Port of Wilmington has sufficient capacity to handle projected shipping growth for the
         next 20 years and beyond.
    •    NCIT would not create new jobs. Since it would compete with the Port of Wilmington, a job at NCIT would at best simply
         replace a job lost at Wilmington, and automated container handling systems planned for NCIT will result in minimal
         personnel needs.
    •    Existing ports at Savannah, Charleston, and Hampton Roads are already expanding to handle the largest container vessels.
    •    Since the Cape Fear River is not a deepwater harbor, a new channel must be dredged, involving the removal of 68 million
         cubic yards of material and costing $1.35 billion.
    •    The nearest interstate highway, existing or planned, is over 20 miles from the NCIT site. A new four-lane highway costing
         $261 million would be necessary.
    •    The nearest trunk-line railroad is 23 miles from the NCIT site. The connecting spur is a single-track, crossing the property of
         a nuclear reactor (Progress Energy) and the largest ammunition depot in the Western Hemisphere (Military Ocean Terminal
         Sunny Point; MOTSU), and passing through the center of a residential community. Necessary improvements would cost $73
         million.
    •    The proposed private partner for NCIT terminated the agreement and no replacement has been found.
    •    The State Ports Authority’s model for NCIT is the new APM terminal in Virginia. Recently, the private company running that
         terminal asked the Virginia Ports Authority to take over, as the terminal has been consistently unprofitable.

Opponents also cite a number of environmental concerns, including:

    •    Building NCIT would require destroying 100 acres of coastal wetlands, depriving essential habitat for commercial &
         recreational fish populations, as well as many species of native and migrating birds.
    •    Dredging the NCIT shipping channel to the depth required for post-Panamax vessels will endanger the aquifer supplying
         drinking water to much of Brunswick County.
    •    Independent studies have shown that unemployment, poverty, and environmental hazards are substantially higher in port
         areas.
    •    Most container ships use bunker fuel, the dirtiest grade of diesel fuel, containing up to 45,000 ppm of sulfur. Ships using
         bunker fuel emit more sulfur dioxide than the entirety of the world’s cars, trucks and buses combined and up to 21 percent
         of the greenhouse gases from all transportation sources.
    •    An estimated 414 trucks per hour and 10-14 trains per day would move containers in and out of NCIT. Diesel fumes from
         this huge amount of traffic, in addition to that generated by the container ships, would dramatically increase local and
         regional air pollution.
    •    The Environmental Protection Agency says exposure to even low levels of diesel exhaust is likely to pose a risk of lung
         cancer and other respiratory diseases.
    •    A recent scientific study published in the medical journal Pediatrics demonstrated a positive correlation between exposure
         to air pollution and a lower IQ in children.
    •    The NC Ports Authority admits that its ports routinely handle shipments of highly dangerous materials, including PETN (the
         explosive favored by terrorists). In January 2010, the entire Morehead City, NC area was evacuated due to an accident
         involving a large shipment of PETN at the port.
•    NCIT will be located right next to the above-ground, spent nuclear fuel storage area of the Progress Energy plant and the
         huge ammunition storage sites of MOTSU. An accidental or terrorist explosion at NCIT could render a large swath of the
         U.S. Eastern Seaboard uninhabitable for decades.

OPPONENTS include:
No Port Southport
City of Southport
Caswell Beach
Boiling Springs Lakes
Town of Saint James
Town of Oak Island
Village of Bald Head Island
Bald Head Island Conservancy
Baptist State Convention of NC, Business Services Committee
US Fish and Wildlife Service

Finally, some members of the Council of State, who had voted unanimously in 2006 to allow the Ports Authority to borrow the
money to buy the land for NCIT, are having second thoughts. Then State Auditor Les Merritt, now admits his support of the
proposed port was an error in judgment.

"It's not my proudest moment that I voted for it," said Merritt. "It could be a bigger boondoggle than the Global TransPark or the
Randy Parton Theater."

"The risks outweigh the potential rewards in this case," Merritt continued. "The idea needs to be killed before so much is invested
that the powers-that-be feel obligated to keep on going."

OTHER INTERESTED PARTIES who are following the issue closely without publicly expressing support or opposition include:
Sen. R.C. Soles, NC Senate District 8
North Carolina Department of Cultural Resources
North Carolina Wildlife Resources Commission
US Environmental Protection Agency
US Marine Fisheries Service
Progress Energy

Summary
Governor Bev Perdue, who also served on the Council of State in 2006 as Lieutenant Governor, has stated through a spokeswoman
that she still has faith that NCIT can provide significant financial returns for North Carolina. But Progress Energy is concerned about a
port of this size next to its nuclear plant that could possibly interfere with nuclear operations.

In July 2010, the Ports Authority announced that in light of the refusal of the General Assembly to provide necessary funding and
Congressman Mike McIntyre’s opposition, all work on the project would be halted indefinitely. But at the July meeting, Board
Chairman Carl Stewart told members of the board that he remains committed to the project, and despite a loss of $6 million for the
budget year ending June 30, 2010, the Ports Authority inked a three-year, $375,000 contract with Capstrat, a Raleigh-based public
relations & lobbying firm, to represent them.

In the five years since the project’s inception, North Carolina taxpayers have invested $10.2 million on the project, including fees for
planning, engineering costs, legal & financial fees, and debt service on the property.

                                                            NCIT TIMELINE

                                NC Ports Authority learns that an undeveloped 600-acre site on the Cape Fear
                        2005
                                River is on the market.
                        Feb.    NC Council of State gives Ports Authority unanimous approval to borrow money
                        2006    to purchase the 600-acre site.
                        April   Ports Authority officials closes on the purchase of the proposed site for the
                        2006    NCIT.
July    CH2M Hill, a global engineering and consulting firm chosen to manage the
                      2006    development process of the proposed NCIT.

                      Aug.    The Authority expands the scope of CH2M Hill's work in to include a business
                      2006    plan and financial strategy.
                      2008    NoPort Southport formed to oppose NCIT, steering committee begins to meet.
                     March CH2M Hill's business plan for NCIT completed portraying the project in a very
                     2008 positive light.
                     March Town of Caswell Beach Board of Commissioners passes resolution opposing
                     2008 NCIT.

                      June    CenterPoint Properties becomes the Authority's partner in developing the NCIT,
                      2008    but withdraws later that year due to the "depressed economy."

                      Feb.    The US Army Corps of Engineers receives funding to determine Federal interest
                      2009    for the deepening of the navigation channel to the NCIT.

                      Feb.    Corps of Engineers asks the state to help fund a study to determine the
                      2010    feasibility of dredging the river for the NCIT.
                      June    Village of Bald Head Island, Bald Head Island Conservancy and City of Southport
                      2010    pass resolutions opposing NCIT.
                      June    Baptist State Convention of North Carolina's Business Services Committee
                      2010    sends letter to Gov. Bev Perdue opposing NCIT on environmental grounds.
                              NC final budget for 2010-11 excludes money for NCIT feasibility study. Though
                      June
                              supporters vow to search for funds elsewhere, Rep. Pricey Harrison declares
                      2010
                              that the project is "on life support."
                      June    U.S. Congressman Mike McIntyre expresses opposition to the port, placing
                      2010    future federal support in jeopardy.

                      July    NC Ports Authority announces that all work on the megaport will be halted
                      2010    indefinitely while they examine other options.
                      July    NC Ports Authority signs three-year, $375,000 contract with Capstrat to
                      2010    represent their future interests.


SURVEY QUESTION:

Yes         No        Should North Carolina taxpayers pay to build the proposed megaport in Brunswick County?

CONTACT YOUR LAWMAKERS:

Click here to share your views with your representatives in the North Carolina House & Senate.

Contenu connexe

En vedette

YouWeirdTube Top-100 Videos By Views
YouWeirdTube Top-100 Videos By ViewsYouWeirdTube Top-100 Videos By Views
YouWeirdTube Top-100 Videos By ViewsLimbs AndThings
 
B2B blogging trends 2011 feb11
B2B blogging trends 2011 feb11B2B blogging trends 2011 feb11
B2B blogging trends 2011 feb11Retelur Marketing
 
Media powerpoint evaulation
Media powerpoint evaulation Media powerpoint evaulation
Media powerpoint evaulation Kishan Ruda
 
Social Brand Experience
Social Brand ExperienceSocial Brand Experience
Social Brand ExperienceMarie_Estager
 
Audience research
Audience researchAudience research
Audience researchJordan2020
 
Moda e música uma fusão perfeita
Moda e  música uma fusão perfeitaModa e  música uma fusão perfeita
Moda e música uma fusão perfeitasalvadorbahiabrasil
 
Alresford music
Alresford musicAlresford music
Alresford musicMichael
 
Towards Zero Waste Newburyport
Towards Zero Waste NewburyportTowards Zero Waste Newburyport
Towards Zero Waste NewburyportMassRecycle .
 
Analyzing Large-Scale User Data with Hadoop and HBase
Analyzing Large-Scale User Data with Hadoop and HBaseAnalyzing Large-Scale User Data with Hadoop and HBase
Analyzing Large-Scale User Data with Hadoop and HBaseWibiData
 

En vedette (14)

Pinturas / Flôres
Pinturas / FlôresPinturas / Flôres
Pinturas / Flôres
 
YouWeirdTube Top-100 Videos By Views
YouWeirdTube Top-100 Videos By ViewsYouWeirdTube Top-100 Videos By Views
YouWeirdTube Top-100 Videos By Views
 
B2B blogging trends 2011 feb11
B2B blogging trends 2011 feb11B2B blogging trends 2011 feb11
B2B blogging trends 2011 feb11
 
Media powerpoint evaulation
Media powerpoint evaulation Media powerpoint evaulation
Media powerpoint evaulation
 
Social Brand Experience
Social Brand ExperienceSocial Brand Experience
Social Brand Experience
 
Consort catalogue
Consort catalogueConsort catalogue
Consort catalogue
 
Native upload 03
Native upload 03Native upload 03
Native upload 03
 
What Social Impact Bonds Really Mean for Philanthropy
What Social Impact Bonds Really Mean for PhilanthropyWhat Social Impact Bonds Really Mean for Philanthropy
What Social Impact Bonds Really Mean for Philanthropy
 
Audience research
Audience researchAudience research
Audience research
 
Moda e música uma fusão perfeita
Moda e  música uma fusão perfeitaModa e  música uma fusão perfeita
Moda e música uma fusão perfeita
 
Table
TableTable
Table
 
Alresford music
Alresford musicAlresford music
Alresford music
 
Towards Zero Waste Newburyport
Towards Zero Waste NewburyportTowards Zero Waste Newburyport
Towards Zero Waste Newburyport
 
Analyzing Large-Scale User Data with Hadoop and HBase
Analyzing Large-Scale User Data with Hadoop and HBaseAnalyzing Large-Scale User Data with Hadoop and HBase
Analyzing Large-Scale User Data with Hadoop and HBase
 

North Carolina International Terminal

  • 1. ISSUE: NC International Terminal Updated August 6, 2010 The North Carolina International Terminal (NCIT) is a megaport proposed by the North Carolina State Ports Authority, an agency of the NC Department of Commerce. The Authority has purchased a 600-acre undeveloped industrial tract on the west bank of the Cape Fear River in Brunswick County for the NCIT project. The proposed site is located four miles from the mouth of the Cape Fear River and the Atlantic Ocean and only 17 miles from the Port of Wilmington. As envisioned, NCIT would greatly expand the capacity of the Wilmington port. According to the proposed plan, the NCIT would be a highly-automated, deep water container terminal capable of serving the most advanced large vessels and handling two to three million TEUs* per year, a capacity similar to that of the ports at Charleston and Savannah (* A TEU is a standard unit for describing a ship's cargo carrying capacity, or a shipping terminal's cargo handling capacity). The Authority says the NCIT could be open for business in 2017 and reach its full capacity by 2030. History The concept for the NCIT began taking shape in 2005 when the Ports Authority learned that an undeveloped 600-acre site on the Cape Fear River was on the market. On April 12, 2006, Ports Authority officials closed on the purchase of the $30 million property as the proposed site for the NCIT. After a comprehensive selection process during 2006, in July CH2M Hill, a global engineering and consulting firm was chosen to manage the development process of the proposed NCIT. The Authority ultimately expanded the scope of CH2M Hill’s work in August 2006 to include the development of a business plan and financial strategy. Completed in March 2008, the plan portrays the project in a very positive light, claiming that 461,000 jobs throughout the state will be related to the projected level of container operations at the NCIT. In June 2008, CenterPoint Properties, a Chicago-based company, became the Ports Authority’s partner in developing the NCIT. However, in the midst of the economic downturn in the fall of 2008, the Ports Authority announced that CenterPoint would be forced to withdraw from the project due to limited capital. In 2009, the US Army Corps of Engineers began a Federally-funded reconnaissance study to determine if there is a Federal interest for the deepening of the navigation channel to the NCIT. This study was due to be completed in June 2010, but a February 2010 draft of this study recommends moving forward into the feasibility phase. Meanwhile, the Ports Authority commissioned their own separate feasibility study by Moffatt & Nichol,a marine engineering firm, for use in a revenue bond offering. This study was completed in February 2010 and concluded that the project was feasible. In May 2010, the US Army Corps of Engineers asked the state to participate in the cost of a study to determine the feasibility of dredging the Cape Fear River for the NCIT. The study would take about five years and cost $10 million, with the state being asked to pay $4.7 million of this amount. The NC Department of Environment and Natural Resources (DENR) was prepared to sign a letter of intent that would commit the state to share the cost of the feasibility study. However, before a feasibility study could proceed, both Congress and the NC General Assembly would have to approve funding for it. In June 2010, on a vote of 104-11, the state House overwhelmingly approved an amendment removing the proposed funding for the feasibility study from the state’s 2010-11 budget, and they got no argument from the Senate. The final budget excluded all funding for the study, placing the future of the NCIT in limbo, at least for the time being. The Debate SUPPORTERS say that the NCIT is destined to be “America’s Next Great Port.” According to the North Carolina State Ports Authority, the project will: • Support over 400,000 jobs. • Provide an additional $1.2 billion in state and local tax revenues. • Drive additional private investment and employment opportunities regionally as distribution centers and logistics facilities emerge across Southeastern North Carolina. • Offer convenience to millions of U.S. consumers and businesses.
  • 2. Supply valuable support to the region’s defense-related economy given proximity to the Military Ocean Terminal at Sunny Point, and the State’s military bases. • Serve as the state's only deep-water port, allowing cargo shipping to bypass ports at Savannah, Charleston, & Hampton Roads and come directly into North Carolina. In May 2010, the state Ports Authority CEO Tom Eager extolled the virtues of the project, stating, “There is no way this project will fail. There is no way we can allow this project to fail.” He referred to the activist group No Port Southport, which opposes the project, as a bunch of “know nothings and transplants.” SUPPORTERS include: Governor Beverly Perdue North Carolina State Ports Authority US Army Corps of Engineers NC Department of Environment and Natural Resources (DENR) - Divisions of Coastal Management & Marine Fisheries OPPONENTS question both the need and the cost for the NCIT. They assert that the Ports Authority's financial projections are based on invalid assumptions and that the NCIT would lose approximately $25 million per year. Opponents also claim that: • The current container terminal at the Port of Wilmington has sufficient capacity to handle projected shipping growth for the next 20 years and beyond. • NCIT would not create new jobs. Since it would compete with the Port of Wilmington, a job at NCIT would at best simply replace a job lost at Wilmington, and automated container handling systems planned for NCIT will result in minimal personnel needs. • Existing ports at Savannah, Charleston, and Hampton Roads are already expanding to handle the largest container vessels. • Since the Cape Fear River is not a deepwater harbor, a new channel must be dredged, involving the removal of 68 million cubic yards of material and costing $1.35 billion. • The nearest interstate highway, existing or planned, is over 20 miles from the NCIT site. A new four-lane highway costing $261 million would be necessary. • The nearest trunk-line railroad is 23 miles from the NCIT site. The connecting spur is a single-track, crossing the property of a nuclear reactor (Progress Energy) and the largest ammunition depot in the Western Hemisphere (Military Ocean Terminal Sunny Point; MOTSU), and passing through the center of a residential community. Necessary improvements would cost $73 million. • The proposed private partner for NCIT terminated the agreement and no replacement has been found. • The State Ports Authority’s model for NCIT is the new APM terminal in Virginia. Recently, the private company running that terminal asked the Virginia Ports Authority to take over, as the terminal has been consistently unprofitable. Opponents also cite a number of environmental concerns, including: • Building NCIT would require destroying 100 acres of coastal wetlands, depriving essential habitat for commercial & recreational fish populations, as well as many species of native and migrating birds. • Dredging the NCIT shipping channel to the depth required for post-Panamax vessels will endanger the aquifer supplying drinking water to much of Brunswick County. • Independent studies have shown that unemployment, poverty, and environmental hazards are substantially higher in port areas. • Most container ships use bunker fuel, the dirtiest grade of diesel fuel, containing up to 45,000 ppm of sulfur. Ships using bunker fuel emit more sulfur dioxide than the entirety of the world’s cars, trucks and buses combined and up to 21 percent of the greenhouse gases from all transportation sources. • An estimated 414 trucks per hour and 10-14 trains per day would move containers in and out of NCIT. Diesel fumes from this huge amount of traffic, in addition to that generated by the container ships, would dramatically increase local and regional air pollution. • The Environmental Protection Agency says exposure to even low levels of diesel exhaust is likely to pose a risk of lung cancer and other respiratory diseases. • A recent scientific study published in the medical journal Pediatrics demonstrated a positive correlation between exposure to air pollution and a lower IQ in children. • The NC Ports Authority admits that its ports routinely handle shipments of highly dangerous materials, including PETN (the explosive favored by terrorists). In January 2010, the entire Morehead City, NC area was evacuated due to an accident involving a large shipment of PETN at the port.
  • 3. NCIT will be located right next to the above-ground, spent nuclear fuel storage area of the Progress Energy plant and the huge ammunition storage sites of MOTSU. An accidental or terrorist explosion at NCIT could render a large swath of the U.S. Eastern Seaboard uninhabitable for decades. OPPONENTS include: No Port Southport City of Southport Caswell Beach Boiling Springs Lakes Town of Saint James Town of Oak Island Village of Bald Head Island Bald Head Island Conservancy Baptist State Convention of NC, Business Services Committee US Fish and Wildlife Service Finally, some members of the Council of State, who had voted unanimously in 2006 to allow the Ports Authority to borrow the money to buy the land for NCIT, are having second thoughts. Then State Auditor Les Merritt, now admits his support of the proposed port was an error in judgment. "It's not my proudest moment that I voted for it," said Merritt. "It could be a bigger boondoggle than the Global TransPark or the Randy Parton Theater." "The risks outweigh the potential rewards in this case," Merritt continued. "The idea needs to be killed before so much is invested that the powers-that-be feel obligated to keep on going." OTHER INTERESTED PARTIES who are following the issue closely without publicly expressing support or opposition include: Sen. R.C. Soles, NC Senate District 8 North Carolina Department of Cultural Resources North Carolina Wildlife Resources Commission US Environmental Protection Agency US Marine Fisheries Service Progress Energy Summary Governor Bev Perdue, who also served on the Council of State in 2006 as Lieutenant Governor, has stated through a spokeswoman that she still has faith that NCIT can provide significant financial returns for North Carolina. But Progress Energy is concerned about a port of this size next to its nuclear plant that could possibly interfere with nuclear operations. In July 2010, the Ports Authority announced that in light of the refusal of the General Assembly to provide necessary funding and Congressman Mike McIntyre’s opposition, all work on the project would be halted indefinitely. But at the July meeting, Board Chairman Carl Stewart told members of the board that he remains committed to the project, and despite a loss of $6 million for the budget year ending June 30, 2010, the Ports Authority inked a three-year, $375,000 contract with Capstrat, a Raleigh-based public relations & lobbying firm, to represent them. In the five years since the project’s inception, North Carolina taxpayers have invested $10.2 million on the project, including fees for planning, engineering costs, legal & financial fees, and debt service on the property. NCIT TIMELINE NC Ports Authority learns that an undeveloped 600-acre site on the Cape Fear 2005 River is on the market. Feb. NC Council of State gives Ports Authority unanimous approval to borrow money 2006 to purchase the 600-acre site. April Ports Authority officials closes on the purchase of the proposed site for the 2006 NCIT.
  • 4. July CH2M Hill, a global engineering and consulting firm chosen to manage the 2006 development process of the proposed NCIT. Aug. The Authority expands the scope of CH2M Hill's work in to include a business 2006 plan and financial strategy. 2008 NoPort Southport formed to oppose NCIT, steering committee begins to meet. March CH2M Hill's business plan for NCIT completed portraying the project in a very 2008 positive light. March Town of Caswell Beach Board of Commissioners passes resolution opposing 2008 NCIT. June CenterPoint Properties becomes the Authority's partner in developing the NCIT, 2008 but withdraws later that year due to the "depressed economy." Feb. The US Army Corps of Engineers receives funding to determine Federal interest 2009 for the deepening of the navigation channel to the NCIT. Feb. Corps of Engineers asks the state to help fund a study to determine the 2010 feasibility of dredging the river for the NCIT. June Village of Bald Head Island, Bald Head Island Conservancy and City of Southport 2010 pass resolutions opposing NCIT. June Baptist State Convention of North Carolina's Business Services Committee 2010 sends letter to Gov. Bev Perdue opposing NCIT on environmental grounds. NC final budget for 2010-11 excludes money for NCIT feasibility study. Though June supporters vow to search for funds elsewhere, Rep. Pricey Harrison declares 2010 that the project is "on life support." June U.S. Congressman Mike McIntyre expresses opposition to the port, placing 2010 future federal support in jeopardy. July NC Ports Authority announces that all work on the megaport will be halted 2010 indefinitely while they examine other options. July NC Ports Authority signs three-year, $375,000 contract with Capstrat to 2010 represent their future interests. SURVEY QUESTION: Yes No Should North Carolina taxpayers pay to build the proposed megaport in Brunswick County? CONTACT YOUR LAWMAKERS: Click here to share your views with your representatives in the North Carolina House & Senate.