SlideShare une entreprise Scribd logo
1  sur  26
Télécharger pour lire hors ligne
Compensation and transient studies on a long EHV
overhead line

     Illustration with the AGADIR-LAAYOUNE 400kV overhead line project
Study background
Issue
■   Very weak 225kV network                                                                                                        CHICHAOUA


       Long antenna (approx. 1200km)




                                                                                                                                     STEP A.MOMN
                                                   PE3                                                             AGADIR
       Low production
                                                                     LAAYOUNE




                                        Boujdour
       Low loads
       Low short-circuit power                                                                                                   Oed TEIMA
                                            Dakhla

                                                     PHOS .B                             GUELMIME   TIZNIT   IMI MKOURNE
                                                               PE2       PE1    TANTAN                                     Ait MELLOUL
■   Incoming generators in the
    southern part of the grid
        Winfarms (~ 800 MW) in the south
        Reversal of the usual power flow
        Heavy loaded 225 kV network                             Study:
        Distorted voltage profile
        Temporary disturbances                                  ■      Steady state analysis
                                                                ■      Transient overvoltage studies
■   Technical solution                                          ■      Transit capacity optimization
        Extension of the northern 400kV                                (series compensation)
        network to the south
        Double circuit 400kV overhead line
        between Agadir and Laâyoune
                                                                                                                                                   3
Modelling
Many different phenomena

■   Different frequencies
        Power frequency (50 Hz)
        Low frequency (~ 500 Hz)
        Transient disturbances (~ 5 kHz)


■   Different simulation cases
        Load flow
        Temporal
        Frequency scan


■   References:
        Guide CEI 60071-4: Computational guide to insulation co-ordination and modelling of electrical
        networks
        Brochure CIGRE n° GUIDELINES FOR REPRESENTATION OF NETWORK ELEMENTS
                         39:
        WHEN CALCULATING TRANSIENTS
One schematic for all cases…
                                                              2

■   Future network development
■   Border of the circuit:
        Propagation # 1/f                                              2

                                                          2

                                                  2                        1           2

                                                                               1



                                       LAAYOUNE                   AGADIR
                                                                                   1

        For low frequency studies:
        Thevenin equivalent at 50 Hz                                       1



                                       1                           2

                                                      1       1                            6



■   Completion with the southern           2
    225kV grid
Components modelling (1)

■   Basics models, non frequency-dependent: R, L et C




                                                 +
                                      +




                                                          ZnO +
                             +               +




■   Lines:
        FD model for temporal simulations            Geometrical
        PI-exact model for frequency scans           data


■   Generators:
Components modelling (2)

■ Transformers: standard low frequency model




                                                 Trans form er Data
                                                    BCTRAN
                                Coupling
                                considerations
Components modelling (3)

■ Specificity: auto-transformer
                                                                 ■ Modelling of magnetic
                                                                   saturation:




    HV            LV       Winding 1             Winding 2
parameters    parameters   parameters            parameters


   UHV            ULV       UHV – ULV                      ULV
                                                           2

         ZHV-LV                             U HV      
                              Z HV - LV   .
                                           U -U       
                                                       
                                            HV   LV   



 Validation by simulating the factory tests…
Validation of the model

■   Quite impossible to validate so complicated a network
        To many components
        Very simplified modelling
        Which data to compare to?


■   Load-flow simulations
        Compilation of the model
        No misconnections of the components
        Production / consumption configurations


■   Time domain simulations
        Compilation of the model
        Predicted behaviour
Shunt compensation
No-load compensation
■   Determination of the total reactive power needed
        Energization of the line (extremity disconnected): 800 Mvar needed


■   Which compensation scheme?
        Intermediary substations needed?
        Which repartition between substations?
        Reactors on the line or in the substation?
        Many steps needed?
        New specifications for reactors?
        Common mode?


■   10 cases studied:




                                                                             12
No-load compensation (2)
■   Observation of the voltage profile along the line
        Line connected at Agadir substation
        Line connected at Laâyoune substation
        Line connected to both substations




                                                        13
On-load compensation

■ Evolution of the compensation
  needs with the load
      Progressive increase of the
      generated power
      Adaptation of the compensation


■ Final compensation scheme:
      No intermediary substation
      Line reactors, all connected with
      circuit breaker
         =>new operation rules
      Minimal step = 40Mvar
Transient studies
Temporary overvoltage
■   Load drop
■   Windfarms power generation variation
■   Single phase fault




                                           overvoltage = 1.2 pu



■   Three phase fault



                                                                  16
Switching overvoltage (1)
■   Frequency scan
        Different configurations
          •   Substation analysed
          •   Lines configuration
          •   Compensation scheme
        Identification of potentially harmful
        situations


■   Statistical studies for each scenario
        Parameter variation
          •   Apparition of the fault
          •   Opening time of the circuit breakers
          •   Closing time of the circuit breakers
        Maximum overvoltage


■   Statistical studies have no ending…




                                                     17
Switching overvoltage (2)

    Examples of       Scenario                 Statistical             Mitigation
    study cases                                parameter                means
                   ■Single-phase fault        ■Closing time of the   ■Surge arresters in the
                   ■3-phase opening of        circuit breaker        substations
    Fault          the circuit breakers (1                           ■Insertion resistors in
                   circuit)                                          the circuit breakers
    clearing       ■3-phase reclosure of                             (R = 400 Ω, t = 10 ms)
                   the breaker
                   ■Single phase fault        ■Closing time of the   ■Neutral grounding
    Fault          ■Single phase opening
                   of the circuit breaker
                                              circuit breaker        reactor

    clearing       ■Single phase
                   reclosure of the breaker
                   ■One circuit of the        ■Closing time of the   ■Local loads
    Transformer    400kV line connected
                   ■One autotransformer
                                              circuit breaker


    energization   energization
                   ■Remanent flux




                                                                                               18
Series compensation
Series compensation

■   Why compensating?
        225kV => stability constraint


■   What solutions?
        Series capacitors
        Phase shifting transformer
        FACTS (UPFC, …)


■   Method:
        Amount of compensation
          •   Increase of the power generation
          •   Stability limit in faulty conditions
          •   Determination of the optimal compensation rate
               Objective: stability limit = thermal limit
        Compensation scheme




                                                               20
Impact of the localisation of the capacitors (1)

                                                 Vc                                V2
                                                                      I
                         line              I
                                                                                                 Vc
                                                                             V1
                                V1                    V2
                                                                                          ∆V
          800
                                                           V1
                                                           V2
          600                                              Vc
                                                           I
                                                                     Voltage profile along the 400 kV line
          400
Voltage




          200



             0



          -200



          -400



          -600



          -800
                 0   5          10    15         20   25        30
                                     time (ms)



                                                                                                             21
Impact of the localisation of the capacitors (2)

                                           Vc                                      V2
                         line        I
                                                                        I                 Vc
                                                                             V1
                                V1                    V2
                                                                                  ∆V

          600
                                                            V1
                                                            V2
                                                            Vc
          400                                               I         Voltage profile along the 400 kV line

          200
Voltage




            0



          -200



          -400



          -600
                 0   5          10    15         20    25        30
                                     time (ms)




                                                                                                              22
Impact of the localisation of the capacitors (3)
                                                  1,05
■   Voltage                                       1,00

        Low voltage if condensed                  0,95




                                   Voltage (pu)
        compensation
                                                  0,90
        Intermediary substation
                                                  0,85
        slightly interesting
                                                  0,80

                                                  0,75
■   Transmitted power                                -50
                                                     Laâyoune   50      150              250            350              450           550        650
                                                                                                                                             Agadir
                                                                                            Distance (km)
        ~ no impact
                                                                     Compensation at LAAYOUNE          Compensation at AGADIR
                                                                     Compensation at 2 substations     Compensation at 3 substations

■   Final compensation
    scheme:
        No intermediary
        substation
        Capacitors balanced
        between both the
        substations
Consequences on resonant phenomena
                                                                           Impedance at Laâyoune 225 kV substation
Impedance at Laâyoune 400 kV substation – transformers disconnected


                                                                      Y1

                                                                                                         D = (Y1-Y2) / Y1
                                                                                                              D > 5%
                                                                                                             (50-fR) = F0 ± 3 Hz
                                                                      Y2

                                                                                                  fR
                                                                            Impedance at Safi 400 kV substation




          No impact on transient
          overvoltage studies
          Further SSR studies needed
Conclusion
Main points

■ Definition of the simulation schematic
     Which phenomenon?
     What level of detail?
     Validation?

■ Operation usages
     Simulation cases based on operation usages
     Operation usages adapted to simulation results

■ Parametric studies
     Prior work is important
     Which end criteria?

Contenu connexe

Tendances

Published_Paper_TCASI
Published_Paper_TCASIPublished_Paper_TCASI
Published_Paper_TCASIXiaoLiang Tan
 
Power dissipation cmos
Power dissipation cmosPower dissipation cmos
Power dissipation cmosRajesh Tiwary
 
131 nerc pacific southwest disturbance presentation
131 nerc pacific southwest disturbance presentation131 nerc pacific southwest disturbance presentation
131 nerc pacific southwest disturbance presentationwmelis
 
Ee395 lab 2 - loren - victor - taylor
Ee395   lab 2 - loren - victor - taylorEe395   lab 2 - loren - victor - taylor
Ee395 lab 2 - loren - victor - taylorLoren Schwappach
 
Cn3210001005
Cn3210001005Cn3210001005
Cn3210001005IJMER
 
Ch2 lecture slides Chenming Hu Device for IC
Ch2 lecture slides Chenming Hu Device for ICCh2 lecture slides Chenming Hu Device for IC
Ch2 lecture slides Chenming Hu Device for ICChenming Hu
 
Low Power Design - PPT 1
Low Power Design - PPT 1 Low Power Design - PPT 1
Low Power Design - PPT 1 Varun Bansal
 
Neutralization Technique in EDC
Neutralization Technique in EDCNeutralization Technique in EDC
Neutralization Technique in EDCvimaladevi s
 
20GHz DQPSK Optical Modulator Electrical Bias Optimiser
20GHz DQPSK Optical Modulator Electrical Bias Optimiser20GHz DQPSK Optical Modulator Electrical Bias Optimiser
20GHz DQPSK Optical Modulator Electrical Bias OptimiserBen Larcombe
 
Transistors & Oscillators by Er. Swapnil Kaware
Transistors & Oscillators by Er. Swapnil KawareTransistors & Oscillators by Er. Swapnil Kaware
Transistors & Oscillators by Er. Swapnil KawareProf. Swapnil V. Kaware
 
Simulated Analysis of Resonant Frequency Converter Using Different Tank Circu...
Simulated Analysis of Resonant Frequency Converter Using Different Tank Circu...Simulated Analysis of Resonant Frequency Converter Using Different Tank Circu...
Simulated Analysis of Resonant Frequency Converter Using Different Tank Circu...IJERD Editor
 
11SETMVD_LDO
11SETMVD_LDO11SETMVD_LDO
11SETMVD_LDOprreiya
 

Tendances (19)

Published_Paper_TCASI
Published_Paper_TCASIPublished_Paper_TCASI
Published_Paper_TCASI
 
Power dissipation cmos
Power dissipation cmosPower dissipation cmos
Power dissipation cmos
 
Tuned amplifiers
Tuned amplifiersTuned amplifiers
Tuned amplifiers
 
131 nerc pacific southwest disturbance presentation
131 nerc pacific southwest disturbance presentation131 nerc pacific southwest disturbance presentation
131 nerc pacific southwest disturbance presentation
 
Mosfet 3
Mosfet 3Mosfet 3
Mosfet 3
 
Ee395 lab 2 - loren - victor - taylor
Ee395   lab 2 - loren - victor - taylorEe395   lab 2 - loren - victor - taylor
Ee395 lab 2 - loren - victor - taylor
 
17
1717
17
 
Cn3210001005
Cn3210001005Cn3210001005
Cn3210001005
 
Ep24889895
Ep24889895Ep24889895
Ep24889895
 
Ch2 lecture slides Chenming Hu Device for IC
Ch2 lecture slides Chenming Hu Device for ICCh2 lecture slides Chenming Hu Device for IC
Ch2 lecture slides Chenming Hu Device for IC
 
Low Power Design - PPT 1
Low Power Design - PPT 1 Low Power Design - PPT 1
Low Power Design - PPT 1
 
Neutralization Technique in EDC
Neutralization Technique in EDCNeutralization Technique in EDC
Neutralization Technique in EDC
 
20GHz DQPSK Optical Modulator Electrical Bias Optimiser
20GHz DQPSK Optical Modulator Electrical Bias Optimiser20GHz DQPSK Optical Modulator Electrical Bias Optimiser
20GHz DQPSK Optical Modulator Electrical Bias Optimiser
 
oscillators
oscillatorsoscillators
oscillators
 
Transistors & Oscillators by Er. Swapnil Kaware
Transistors & Oscillators by Er. Swapnil KawareTransistors & Oscillators by Er. Swapnil Kaware
Transistors & Oscillators by Er. Swapnil Kaware
 
Simulated Analysis of Resonant Frequency Converter Using Different Tank Circu...
Simulated Analysis of Resonant Frequency Converter Using Different Tank Circu...Simulated Analysis of Resonant Frequency Converter Using Different Tank Circu...
Simulated Analysis of Resonant Frequency Converter Using Different Tank Circu...
 
G0514551
G0514551G0514551
G0514551
 
11SETMVD_LDO
11SETMVD_LDO11SETMVD_LDO
11SETMVD_LDO
 
Hy2414011407
Hy2414011407Hy2414011407
Hy2414011407
 

En vedette

Rte Dufour Protection Systemforactives Substation
Rte Dufour Protection Systemforactives SubstationRte Dufour Protection Systemforactives Substation
Rte Dufour Protection Systemforactives Substationcorinne rocherieux
 
Furse transient overvoltage protection to BS 7671
Furse transient overvoltage protection to BS 7671Furse transient overvoltage protection to BS 7671
Furse transient overvoltage protection to BS 7671Furse
 
Rte Parisot Overview Of Emtp Studiesandmodel Devpt At Rte
Rte Parisot Overview Of Emtp Studiesandmodel Devpt At RteRte Parisot Overview Of Emtp Studiesandmodel Devpt At Rte
Rte Parisot Overview Of Emtp Studiesandmodel Devpt At Rtecorinne rocherieux
 
Edf R&D Xemard Coupling Between Transmission Underground Cables And Pipelines
Edf R&D Xemard Coupling Between Transmission Underground Cables And PipelinesEdf R&D Xemard Coupling Between Transmission Underground Cables And Pipelines
Edf R&D Xemard Coupling Between Transmission Underground Cables And Pipelinescorinne rocherieux
 
Univ Of Zagreb Uglesic Prevention Of Flashover
Univ Of Zagreb Uglesic Prevention Of FlashoverUniv Of Zagreb Uglesic Prevention Of Flashover
Univ Of Zagreb Uglesic Prevention Of Flashovercorinne rocherieux
 

En vedette (7)

Rte Dufour Protection Systemforactives Substation
Rte Dufour Protection Systemforactives SubstationRte Dufour Protection Systemforactives Substation
Rte Dufour Protection Systemforactives Substation
 
Rte Guerrier Lips Toolbox
Rte Guerrier Lips ToolboxRte Guerrier Lips Toolbox
Rte Guerrier Lips Toolbox
 
Emtp Mahseredjian R&D
Emtp Mahseredjian R&DEmtp Mahseredjian R&D
Emtp Mahseredjian R&D
 
Furse transient overvoltage protection to BS 7671
Furse transient overvoltage protection to BS 7671Furse transient overvoltage protection to BS 7671
Furse transient overvoltage protection to BS 7671
 
Rte Parisot Overview Of Emtp Studiesandmodel Devpt At Rte
Rte Parisot Overview Of Emtp Studiesandmodel Devpt At RteRte Parisot Overview Of Emtp Studiesandmodel Devpt At Rte
Rte Parisot Overview Of Emtp Studiesandmodel Devpt At Rte
 
Edf R&D Xemard Coupling Between Transmission Underground Cables And Pipelines
Edf R&D Xemard Coupling Between Transmission Underground Cables And PipelinesEdf R&D Xemard Coupling Between Transmission Underground Cables And Pipelines
Edf R&D Xemard Coupling Between Transmission Underground Cables And Pipelines
 
Univ Of Zagreb Uglesic Prevention Of Flashover
Univ Of Zagreb Uglesic Prevention Of FlashoverUniv Of Zagreb Uglesic Prevention Of Flashover
Univ Of Zagreb Uglesic Prevention Of Flashover
 

Similaire à Rte Lebranchu Compensation And Transient Studies Onalong Ehv Overheadline

J. A. P. Lopes, "Smart EV grid interfaces responding to frequency variations ...
J. A. P. Lopes, "Smart EV grid interfaces responding to frequency variations ...J. A. P. Lopes, "Smart EV grid interfaces responding to frequency variations ...
J. A. P. Lopes, "Smart EV grid interfaces responding to frequency variations ...Eamon Keane
 
FFC-MM Plantsite Power System Protection
FFC-MM Plantsite Power System ProtectionFFC-MM Plantsite Power System Protection
FFC-MM Plantsite Power System Protectionfarazrafi87
 
Development of underground line fault detector
Development of underground line fault detectorDevelopment of underground line fault detector
Development of underground line fault detectorDODDI NAGASAI
 
30, 31st July 2012 - The India Blackout
30, 31st July 2012 - The India Blackout30, 31st July 2012 - The India Blackout
30, 31st July 2012 - The India Blackoutgiridaran123
 
Dc power plants for telecom and data
Dc power plants for telecom and dataDc power plants for telecom and data
Dc power plants for telecom and dataAnil Upadhyay
 
EMVT 12 september - Pavol Bauer - TU Delft
EMVT 12 september - Pavol Bauer - TU DelftEMVT 12 september - Pavol Bauer - TU Delft
EMVT 12 september - Pavol Bauer - TU DelftDutch Power
 
Multi-KilowattFlybackConverters.pptx
Multi-KilowattFlybackConverters.pptxMulti-KilowattFlybackConverters.pptx
Multi-KilowattFlybackConverters.pptxRickMaity
 
Low Power Design Techniques for ASIC / SOC Design
Low Power Design Techniques for ASIC / SOC DesignLow Power Design Techniques for ASIC / SOC Design
Low Power Design Techniques for ASIC / SOC DesignRajesh_navandar
 
Automatic phase changer
Automatic phase changerAutomatic phase changer
Automatic phase changerviv3ksharma
 
ZVS Circuit based – Cockcroft Walton High Voltage DC Generator
ZVS Circuit based – Cockcroft Walton High Voltage DC GeneratorZVS Circuit based – Cockcroft Walton High Voltage DC Generator
ZVS Circuit based – Cockcroft Walton High Voltage DC GeneratorIRJET Journal
 
Master thesis presentation
Master thesis presentationMaster thesis presentation
Master thesis presentationMayur Sarode
 

Similaire à Rte Lebranchu Compensation And Transient Studies Onalong Ehv Overheadline (20)

Low Power Techniques
Low Power TechniquesLow Power Techniques
Low Power Techniques
 
12 low power techniques
12 low power techniques12 low power techniques
12 low power techniques
 
J. A. P. Lopes, "Smart EV grid interfaces responding to frequency variations ...
J. A. P. Lopes, "Smart EV grid interfaces responding to frequency variations ...J. A. P. Lopes, "Smart EV grid interfaces responding to frequency variations ...
J. A. P. Lopes, "Smart EV grid interfaces responding to frequency variations ...
 
Onyx Group Hv Test Report
Onyx Group   Hv Test ReportOnyx Group   Hv Test Report
Onyx Group Hv Test Report
 
Cmp0200 ieee
Cmp0200 ieeeCmp0200 ieee
Cmp0200 ieee
 
800%20k v%20paper
800%20k v%20paper800%20k v%20paper
800%20k v%20paper
 
FFC-MM Plantsite Power System Protection
FFC-MM Plantsite Power System ProtectionFFC-MM Plantsite Power System Protection
FFC-MM Plantsite Power System Protection
 
Development of underground line fault detector
Development of underground line fault detectorDevelopment of underground line fault detector
Development of underground line fault detector
 
30, 31st July 2012 - The India Blackout
30, 31st July 2012 - The India Blackout30, 31st July 2012 - The India Blackout
30, 31st July 2012 - The India Blackout
 
Bam Nuttall Hv Test Report
Bam Nuttall   Hv Test ReportBam Nuttall   Hv Test Report
Bam Nuttall Hv Test Report
 
Dc power plants for telecom and data
Dc power plants for telecom and dataDc power plants for telecom and data
Dc power plants for telecom and data
 
46584589 substation-design-data
46584589 substation-design-data46584589 substation-design-data
46584589 substation-design-data
 
Avalanche transit time devices
Avalanche transit time devicesAvalanche transit time devices
Avalanche transit time devices
 
EMVT 12 september - Pavol Bauer - TU Delft
EMVT 12 september - Pavol Bauer - TU DelftEMVT 12 september - Pavol Bauer - TU Delft
EMVT 12 september - Pavol Bauer - TU Delft
 
Multi-KilowattFlybackConverters.pptx
Multi-KilowattFlybackConverters.pptxMulti-KilowattFlybackConverters.pptx
Multi-KilowattFlybackConverters.pptx
 
Low Power Design Techniques for ASIC / SOC Design
Low Power Design Techniques for ASIC / SOC DesignLow Power Design Techniques for ASIC / SOC Design
Low Power Design Techniques for ASIC / SOC Design
 
kamal project ppt
kamal project pptkamal project ppt
kamal project ppt
 
Automatic phase changer
Automatic phase changerAutomatic phase changer
Automatic phase changer
 
ZVS Circuit based – Cockcroft Walton High Voltage DC Generator
ZVS Circuit based – Cockcroft Walton High Voltage DC GeneratorZVS Circuit based – Cockcroft Walton High Voltage DC Generator
ZVS Circuit based – Cockcroft Walton High Voltage DC Generator
 
Master thesis presentation
Master thesis presentationMaster thesis presentation
Master thesis presentation
 

Plus de corinne rocherieux

Sadovic Lighting Performance Computation
Sadovic Lighting Performance ComputationSadovic Lighting Performance Computation
Sadovic Lighting Performance Computationcorinne rocherieux
 
Hydro Quebec Roumy Interfacing Emtp Rv Withothersoftware Using C++
Hydro Quebec Roumy Interfacing Emtp Rv Withothersoftware Using C++Hydro Quebec Roumy Interfacing Emtp Rv Withothersoftware Using C++
Hydro Quebec Roumy Interfacing Emtp Rv Withothersoftware Using C++corinne rocherieux
 
Opal Rt Giroux Scrpting In Emtp Works
Opal Rt Giroux Scrpting In Emtp WorksOpal Rt Giroux Scrpting In Emtp Works
Opal Rt Giroux Scrpting In Emtp Workscorinne rocherieux
 
Emtp User Group092008 Supelec Stab Transitoire Web
Emtp User Group092008 Supelec Stab Transitoire WebEmtp User Group092008 Supelec Stab Transitoire Web
Emtp User Group092008 Supelec Stab Transitoire Webcorinne rocherieux
 
Emtp User Group092008 Sicae Raccordement Resau Web
Emtp User Group092008 Sicae Raccordement Resau WebEmtp User Group092008 Sicae Raccordement Resau Web
Emtp User Group092008 Sicae Raccordement Resau Webcorinne rocherieux
 
Emtp User Group092008 Sadovic Etudes Web
Emtp User Group092008 Sadovic Etudes WebEmtp User Group092008 Sadovic Etudes Web
Emtp User Group092008 Sadovic Etudes Webcorinne rocherieux
 
Emtp User Group092008 Rte Etudes Ttr Web
Emtp User Group092008 Rte Etudes Ttr WebEmtp User Group092008 Rte Etudes Ttr Web
Emtp User Group092008 Rte Etudes Ttr Webcorinne rocherieux
 
Emtp User Group092008 Polytechnique Montreal Nouveaux Dvpts Web
Emtp User Group092008 Polytechnique Montreal Nouveaux Dvpts WebEmtp User Group092008 Polytechnique Montreal Nouveaux Dvpts Web
Emtp User Group092008 Polytechnique Montreal Nouveaux Dvpts Webcorinne rocherieux
 
Emtp User Group092008 Idea P Vprotection Web
Emtp User Group092008 Idea P Vprotection WebEmtp User Group092008 Idea P Vprotection Web
Emtp User Group092008 Idea P Vprotection Webcorinne rocherieux
 
Emtp User Group092008 Idea P Vgeneration Web
Emtp User Group092008 Idea P Vgeneration WebEmtp User Group092008 Idea P Vgeneration Web
Emtp User Group092008 Idea P Vgeneration Webcorinne rocherieux
 
Emtp User Group092008 Edf Ttr Discordance Phase Web
Emtp User Group092008 Edf Ttr Discordance Phase WebEmtp User Group092008 Edf Ttr Discordance Phase Web
Emtp User Group092008 Edf Ttr Discordance Phase Webcorinne rocherieux
 
Emtp User Group092008 Edf Sectionneurs Web
Emtp User Group092008 Edf Sectionneurs WebEmtp User Group092008 Edf Sectionneurs Web
Emtp User Group092008 Edf Sectionneurs Webcorinne rocherieux
 
Emtp User Group092008 Edf Programme Web
Emtp User Group092008 Edf Programme WebEmtp User Group092008 Edf Programme Web
Emtp User Group092008 Edf Programme Webcorinne rocherieux
 
Etudes Raccordement Emtp 24092008
Etudes Raccordement Emtp   24092008Etudes Raccordement Emtp   24092008
Etudes Raccordement Emtp 24092008corinne rocherieux
 

Plus de corinne rocherieux (15)

Sadovic Lighting Performance Computation
Sadovic Lighting Performance ComputationSadovic Lighting Performance Computation
Sadovic Lighting Performance Computation
 
Hydro Quebec Roumy Interfacing Emtp Rv Withothersoftware Using C++
Hydro Quebec Roumy Interfacing Emtp Rv Withothersoftware Using C++Hydro Quebec Roumy Interfacing Emtp Rv Withothersoftware Using C++
Hydro Quebec Roumy Interfacing Emtp Rv Withothersoftware Using C++
 
Opal Rt Giroux Scrpting In Emtp Works
Opal Rt Giroux Scrpting In Emtp WorksOpal Rt Giroux Scrpting In Emtp Works
Opal Rt Giroux Scrpting In Emtp Works
 
Edf R&D Dennetiere Hvdc Emtp
Edf R&D Dennetiere Hvdc EmtpEdf R&D Dennetiere Hvdc Emtp
Edf R&D Dennetiere Hvdc Emtp
 
Emtp User Group092008 Supelec Stab Transitoire Web
Emtp User Group092008 Supelec Stab Transitoire WebEmtp User Group092008 Supelec Stab Transitoire Web
Emtp User Group092008 Supelec Stab Transitoire Web
 
Emtp User Group092008 Sicae Raccordement Resau Web
Emtp User Group092008 Sicae Raccordement Resau WebEmtp User Group092008 Sicae Raccordement Resau Web
Emtp User Group092008 Sicae Raccordement Resau Web
 
Emtp User Group092008 Sadovic Etudes Web
Emtp User Group092008 Sadovic Etudes WebEmtp User Group092008 Sadovic Etudes Web
Emtp User Group092008 Sadovic Etudes Web
 
Emtp User Group092008 Rte Etudes Ttr Web
Emtp User Group092008 Rte Etudes Ttr WebEmtp User Group092008 Rte Etudes Ttr Web
Emtp User Group092008 Rte Etudes Ttr Web
 
Emtp User Group092008 Polytechnique Montreal Nouveaux Dvpts Web
Emtp User Group092008 Polytechnique Montreal Nouveaux Dvpts WebEmtp User Group092008 Polytechnique Montreal Nouveaux Dvpts Web
Emtp User Group092008 Polytechnique Montreal Nouveaux Dvpts Web
 
Emtp User Group092008 Idea P Vprotection Web
Emtp User Group092008 Idea P Vprotection WebEmtp User Group092008 Idea P Vprotection Web
Emtp User Group092008 Idea P Vprotection Web
 
Emtp User Group092008 Idea P Vgeneration Web
Emtp User Group092008 Idea P Vgeneration WebEmtp User Group092008 Idea P Vgeneration Web
Emtp User Group092008 Idea P Vgeneration Web
 
Emtp User Group092008 Edf Ttr Discordance Phase Web
Emtp User Group092008 Edf Ttr Discordance Phase WebEmtp User Group092008 Edf Ttr Discordance Phase Web
Emtp User Group092008 Edf Ttr Discordance Phase Web
 
Emtp User Group092008 Edf Sectionneurs Web
Emtp User Group092008 Edf Sectionneurs WebEmtp User Group092008 Edf Sectionneurs Web
Emtp User Group092008 Edf Sectionneurs Web
 
Emtp User Group092008 Edf Programme Web
Emtp User Group092008 Edf Programme WebEmtp User Group092008 Edf Programme Web
Emtp User Group092008 Edf Programme Web
 
Etudes Raccordement Emtp 24092008
Etudes Raccordement Emtp   24092008Etudes Raccordement Emtp   24092008
Etudes Raccordement Emtp 24092008
 

Dernier

Histor y of HAM Radio presentation slide
Histor y of HAM Radio presentation slideHistor y of HAM Radio presentation slide
Histor y of HAM Radio presentation slidevu2urc
 
Handwritten Text Recognition for manuscripts and early printed texts
Handwritten Text Recognition for manuscripts and early printed textsHandwritten Text Recognition for manuscripts and early printed texts
Handwritten Text Recognition for manuscripts and early printed textsMaria Levchenko
 
What Are The Drone Anti-jamming Systems Technology?
What Are The Drone Anti-jamming Systems Technology?What Are The Drone Anti-jamming Systems Technology?
What Are The Drone Anti-jamming Systems Technology?Antenna Manufacturer Coco
 
A Domino Admins Adventures (Engage 2024)
A Domino Admins Adventures (Engage 2024)A Domino Admins Adventures (Engage 2024)
A Domino Admins Adventures (Engage 2024)Gabriella Davis
 
Understanding Discord NSFW Servers A Guide for Responsible Users.pdf
Understanding Discord NSFW Servers A Guide for Responsible Users.pdfUnderstanding Discord NSFW Servers A Guide for Responsible Users.pdf
Understanding Discord NSFW Servers A Guide for Responsible Users.pdfUK Journal
 
The 7 Things I Know About Cyber Security After 25 Years | April 2024
The 7 Things I Know About Cyber Security After 25 Years | April 2024The 7 Things I Know About Cyber Security After 25 Years | April 2024
The 7 Things I Know About Cyber Security After 25 Years | April 2024Rafal Los
 
Workshop - Best of Both Worlds_ Combine KG and Vector search for enhanced R...
Workshop - Best of Both Worlds_ Combine  KG and Vector search for  enhanced R...Workshop - Best of Both Worlds_ Combine  KG and Vector search for  enhanced R...
Workshop - Best of Both Worlds_ Combine KG and Vector search for enhanced R...Neo4j
 
Axa Assurance Maroc - Insurer Innovation Award 2024
Axa Assurance Maroc - Insurer Innovation Award 2024Axa Assurance Maroc - Insurer Innovation Award 2024
Axa Assurance Maroc - Insurer Innovation Award 2024The Digital Insurer
 
Powerful Google developer tools for immediate impact! (2023-24 C)
Powerful Google developer tools for immediate impact! (2023-24 C)Powerful Google developer tools for immediate impact! (2023-24 C)
Powerful Google developer tools for immediate impact! (2023-24 C)wesley chun
 
Raspberry Pi 5: Challenges and Solutions in Bringing up an OpenGL/Vulkan Driv...
Raspberry Pi 5: Challenges and Solutions in Bringing up an OpenGL/Vulkan Driv...Raspberry Pi 5: Challenges and Solutions in Bringing up an OpenGL/Vulkan Driv...
Raspberry Pi 5: Challenges and Solutions in Bringing up an OpenGL/Vulkan Driv...Igalia
 
Data Cloud, More than a CDP by Matt Robison
Data Cloud, More than a CDP by Matt RobisonData Cloud, More than a CDP by Matt Robison
Data Cloud, More than a CDP by Matt RobisonAnna Loughnan Colquhoun
 
Mastering MySQL Database Architecture: Deep Dive into MySQL Shell and MySQL R...
Mastering MySQL Database Architecture: Deep Dive into MySQL Shell and MySQL R...Mastering MySQL Database Architecture: Deep Dive into MySQL Shell and MySQL R...
Mastering MySQL Database Architecture: Deep Dive into MySQL Shell and MySQL R...Miguel Araújo
 
CNv6 Instructor Chapter 6 Quality of Service
CNv6 Instructor Chapter 6 Quality of ServiceCNv6 Instructor Chapter 6 Quality of Service
CNv6 Instructor Chapter 6 Quality of Servicegiselly40
 
How to convert PDF to text with Nanonets
How to convert PDF to text with NanonetsHow to convert PDF to text with Nanonets
How to convert PDF to text with Nanonetsnaman860154
 
Exploring the Future Potential of AI-Enabled Smartphone Processors
Exploring the Future Potential of AI-Enabled Smartphone ProcessorsExploring the Future Potential of AI-Enabled Smartphone Processors
Exploring the Future Potential of AI-Enabled Smartphone Processorsdebabhi2
 
[2024]Digital Global Overview Report 2024 Meltwater.pdf
[2024]Digital Global Overview Report 2024 Meltwater.pdf[2024]Digital Global Overview Report 2024 Meltwater.pdf
[2024]Digital Global Overview Report 2024 Meltwater.pdfhans926745
 
Apidays Singapore 2024 - Building Digital Trust in a Digital Economy by Veron...
Apidays Singapore 2024 - Building Digital Trust in a Digital Economy by Veron...Apidays Singapore 2024 - Building Digital Trust in a Digital Economy by Veron...
Apidays Singapore 2024 - Building Digital Trust in a Digital Economy by Veron...apidays
 
Boost Fertility New Invention Ups Success Rates.pdf
Boost Fertility New Invention Ups Success Rates.pdfBoost Fertility New Invention Ups Success Rates.pdf
Boost Fertility New Invention Ups Success Rates.pdfsudhanshuwaghmare1
 
A Call to Action for Generative AI in 2024
A Call to Action for Generative AI in 2024A Call to Action for Generative AI in 2024
A Call to Action for Generative AI in 2024Results
 
IAC 2024 - IA Fast Track to Search Focused AI Solutions
IAC 2024 - IA Fast Track to Search Focused AI SolutionsIAC 2024 - IA Fast Track to Search Focused AI Solutions
IAC 2024 - IA Fast Track to Search Focused AI SolutionsEnterprise Knowledge
 

Dernier (20)

Histor y of HAM Radio presentation slide
Histor y of HAM Radio presentation slideHistor y of HAM Radio presentation slide
Histor y of HAM Radio presentation slide
 
Handwritten Text Recognition for manuscripts and early printed texts
Handwritten Text Recognition for manuscripts and early printed textsHandwritten Text Recognition for manuscripts and early printed texts
Handwritten Text Recognition for manuscripts and early printed texts
 
What Are The Drone Anti-jamming Systems Technology?
What Are The Drone Anti-jamming Systems Technology?What Are The Drone Anti-jamming Systems Technology?
What Are The Drone Anti-jamming Systems Technology?
 
A Domino Admins Adventures (Engage 2024)
A Domino Admins Adventures (Engage 2024)A Domino Admins Adventures (Engage 2024)
A Domino Admins Adventures (Engage 2024)
 
Understanding Discord NSFW Servers A Guide for Responsible Users.pdf
Understanding Discord NSFW Servers A Guide for Responsible Users.pdfUnderstanding Discord NSFW Servers A Guide for Responsible Users.pdf
Understanding Discord NSFW Servers A Guide for Responsible Users.pdf
 
The 7 Things I Know About Cyber Security After 25 Years | April 2024
The 7 Things I Know About Cyber Security After 25 Years | April 2024The 7 Things I Know About Cyber Security After 25 Years | April 2024
The 7 Things I Know About Cyber Security After 25 Years | April 2024
 
Workshop - Best of Both Worlds_ Combine KG and Vector search for enhanced R...
Workshop - Best of Both Worlds_ Combine  KG and Vector search for  enhanced R...Workshop - Best of Both Worlds_ Combine  KG and Vector search for  enhanced R...
Workshop - Best of Both Worlds_ Combine KG and Vector search for enhanced R...
 
Axa Assurance Maroc - Insurer Innovation Award 2024
Axa Assurance Maroc - Insurer Innovation Award 2024Axa Assurance Maroc - Insurer Innovation Award 2024
Axa Assurance Maroc - Insurer Innovation Award 2024
 
Powerful Google developer tools for immediate impact! (2023-24 C)
Powerful Google developer tools for immediate impact! (2023-24 C)Powerful Google developer tools for immediate impact! (2023-24 C)
Powerful Google developer tools for immediate impact! (2023-24 C)
 
Raspberry Pi 5: Challenges and Solutions in Bringing up an OpenGL/Vulkan Driv...
Raspberry Pi 5: Challenges and Solutions in Bringing up an OpenGL/Vulkan Driv...Raspberry Pi 5: Challenges and Solutions in Bringing up an OpenGL/Vulkan Driv...
Raspberry Pi 5: Challenges and Solutions in Bringing up an OpenGL/Vulkan Driv...
 
Data Cloud, More than a CDP by Matt Robison
Data Cloud, More than a CDP by Matt RobisonData Cloud, More than a CDP by Matt Robison
Data Cloud, More than a CDP by Matt Robison
 
Mastering MySQL Database Architecture: Deep Dive into MySQL Shell and MySQL R...
Mastering MySQL Database Architecture: Deep Dive into MySQL Shell and MySQL R...Mastering MySQL Database Architecture: Deep Dive into MySQL Shell and MySQL R...
Mastering MySQL Database Architecture: Deep Dive into MySQL Shell and MySQL R...
 
CNv6 Instructor Chapter 6 Quality of Service
CNv6 Instructor Chapter 6 Quality of ServiceCNv6 Instructor Chapter 6 Quality of Service
CNv6 Instructor Chapter 6 Quality of Service
 
How to convert PDF to text with Nanonets
How to convert PDF to text with NanonetsHow to convert PDF to text with Nanonets
How to convert PDF to text with Nanonets
 
Exploring the Future Potential of AI-Enabled Smartphone Processors
Exploring the Future Potential of AI-Enabled Smartphone ProcessorsExploring the Future Potential of AI-Enabled Smartphone Processors
Exploring the Future Potential of AI-Enabled Smartphone Processors
 
[2024]Digital Global Overview Report 2024 Meltwater.pdf
[2024]Digital Global Overview Report 2024 Meltwater.pdf[2024]Digital Global Overview Report 2024 Meltwater.pdf
[2024]Digital Global Overview Report 2024 Meltwater.pdf
 
Apidays Singapore 2024 - Building Digital Trust in a Digital Economy by Veron...
Apidays Singapore 2024 - Building Digital Trust in a Digital Economy by Veron...Apidays Singapore 2024 - Building Digital Trust in a Digital Economy by Veron...
Apidays Singapore 2024 - Building Digital Trust in a Digital Economy by Veron...
 
Boost Fertility New Invention Ups Success Rates.pdf
Boost Fertility New Invention Ups Success Rates.pdfBoost Fertility New Invention Ups Success Rates.pdf
Boost Fertility New Invention Ups Success Rates.pdf
 
A Call to Action for Generative AI in 2024
A Call to Action for Generative AI in 2024A Call to Action for Generative AI in 2024
A Call to Action for Generative AI in 2024
 
IAC 2024 - IA Fast Track to Search Focused AI Solutions
IAC 2024 - IA Fast Track to Search Focused AI SolutionsIAC 2024 - IA Fast Track to Search Focused AI Solutions
IAC 2024 - IA Fast Track to Search Focused AI Solutions
 

Rte Lebranchu Compensation And Transient Studies Onalong Ehv Overheadline

  • 1. Compensation and transient studies on a long EHV overhead line Illustration with the AGADIR-LAAYOUNE 400kV overhead line project
  • 3. Issue ■ Very weak 225kV network CHICHAOUA Long antenna (approx. 1200km) STEP A.MOMN PE3 AGADIR Low production LAAYOUNE Boujdour Low loads Low short-circuit power Oed TEIMA Dakhla PHOS .B GUELMIME TIZNIT IMI MKOURNE PE2 PE1 TANTAN Ait MELLOUL ■ Incoming generators in the southern part of the grid Winfarms (~ 800 MW) in the south Reversal of the usual power flow Heavy loaded 225 kV network Study: Distorted voltage profile Temporary disturbances ■ Steady state analysis ■ Transient overvoltage studies ■ Technical solution ■ Transit capacity optimization Extension of the northern 400kV (series compensation) network to the south Double circuit 400kV overhead line between Agadir and Laâyoune 3
  • 5. Many different phenomena ■ Different frequencies Power frequency (50 Hz) Low frequency (~ 500 Hz) Transient disturbances (~ 5 kHz) ■ Different simulation cases Load flow Temporal Frequency scan ■ References: Guide CEI 60071-4: Computational guide to insulation co-ordination and modelling of electrical networks Brochure CIGRE n° GUIDELINES FOR REPRESENTATION OF NETWORK ELEMENTS 39: WHEN CALCULATING TRANSIENTS
  • 6. One schematic for all cases… 2 ■ Future network development ■ Border of the circuit: Propagation # 1/f 2 2 2 1 2 1 LAAYOUNE AGADIR 1 For low frequency studies: Thevenin equivalent at 50 Hz 1 1 2 1 1 6 ■ Completion with the southern 2 225kV grid
  • 7. Components modelling (1) ■ Basics models, non frequency-dependent: R, L et C + + ZnO + + + ■ Lines: FD model for temporal simulations Geometrical PI-exact model for frequency scans data ■ Generators:
  • 8. Components modelling (2) ■ Transformers: standard low frequency model Trans form er Data BCTRAN Coupling considerations
  • 9. Components modelling (3) ■ Specificity: auto-transformer ■ Modelling of magnetic saturation: HV LV Winding 1 Winding 2 parameters parameters parameters parameters UHV ULV UHV – ULV ULV 2 ZHV-LV  U HV  Z HV - LV . U -U    HV LV  Validation by simulating the factory tests…
  • 10. Validation of the model ■ Quite impossible to validate so complicated a network To many components Very simplified modelling Which data to compare to? ■ Load-flow simulations Compilation of the model No misconnections of the components Production / consumption configurations ■ Time domain simulations Compilation of the model Predicted behaviour
  • 12. No-load compensation ■ Determination of the total reactive power needed Energization of the line (extremity disconnected): 800 Mvar needed ■ Which compensation scheme? Intermediary substations needed? Which repartition between substations? Reactors on the line or in the substation? Many steps needed? New specifications for reactors? Common mode? ■ 10 cases studied: 12
  • 13. No-load compensation (2) ■ Observation of the voltage profile along the line Line connected at Agadir substation Line connected at Laâyoune substation Line connected to both substations 13
  • 14. On-load compensation ■ Evolution of the compensation needs with the load Progressive increase of the generated power Adaptation of the compensation ■ Final compensation scheme: No intermediary substation Line reactors, all connected with circuit breaker =>new operation rules Minimal step = 40Mvar
  • 16. Temporary overvoltage ■ Load drop ■ Windfarms power generation variation ■ Single phase fault overvoltage = 1.2 pu ■ Three phase fault 16
  • 17. Switching overvoltage (1) ■ Frequency scan Different configurations • Substation analysed • Lines configuration • Compensation scheme Identification of potentially harmful situations ■ Statistical studies for each scenario Parameter variation • Apparition of the fault • Opening time of the circuit breakers • Closing time of the circuit breakers Maximum overvoltage ■ Statistical studies have no ending… 17
  • 18. Switching overvoltage (2) Examples of Scenario Statistical Mitigation study cases parameter means ■Single-phase fault ■Closing time of the ■Surge arresters in the ■3-phase opening of circuit breaker substations Fault the circuit breakers (1 ■Insertion resistors in circuit) the circuit breakers clearing ■3-phase reclosure of (R = 400 Ω, t = 10 ms) the breaker ■Single phase fault ■Closing time of the ■Neutral grounding Fault ■Single phase opening of the circuit breaker circuit breaker reactor clearing ■Single phase reclosure of the breaker ■One circuit of the ■Closing time of the ■Local loads Transformer 400kV line connected ■One autotransformer circuit breaker energization energization ■Remanent flux 18
  • 20. Series compensation ■ Why compensating? 225kV => stability constraint ■ What solutions? Series capacitors Phase shifting transformer FACTS (UPFC, …) ■ Method: Amount of compensation • Increase of the power generation • Stability limit in faulty conditions • Determination of the optimal compensation rate Objective: stability limit = thermal limit Compensation scheme 20
  • 21. Impact of the localisation of the capacitors (1) Vc V2 I line I Vc V1 V1 V2 ∆V 800 V1 V2 600 Vc I Voltage profile along the 400 kV line 400 Voltage 200 0 -200 -400 -600 -800 0 5 10 15 20 25 30 time (ms) 21
  • 22. Impact of the localisation of the capacitors (2) Vc V2 line I I Vc V1 V1 V2 ∆V 600 V1 V2 Vc 400 I Voltage profile along the 400 kV line 200 Voltage 0 -200 -400 -600 0 5 10 15 20 25 30 time (ms) 22
  • 23. Impact of the localisation of the capacitors (3) 1,05 ■ Voltage 1,00 Low voltage if condensed 0,95 Voltage (pu) compensation 0,90 Intermediary substation 0,85 slightly interesting 0,80 0,75 ■ Transmitted power -50 Laâyoune 50 150 250 350 450 550 650 Agadir Distance (km) ~ no impact Compensation at LAAYOUNE Compensation at AGADIR Compensation at 2 substations Compensation at 3 substations ■ Final compensation scheme: No intermediary substation Capacitors balanced between both the substations
  • 24. Consequences on resonant phenomena Impedance at Laâyoune 225 kV substation Impedance at Laâyoune 400 kV substation – transformers disconnected Y1 D = (Y1-Y2) / Y1 D > 5% (50-fR) = F0 ± 3 Hz Y2 fR Impedance at Safi 400 kV substation No impact on transient overvoltage studies Further SSR studies needed
  • 26. Main points ■ Definition of the simulation schematic Which phenomenon? What level of detail? Validation? ■ Operation usages Simulation cases based on operation usages Operation usages adapted to simulation results ■ Parametric studies Prior work is important Which end criteria?