Objectives
The objective of the present report is
 to summarize the experience available today in the field of
post-tensioning in building construction and in particular to
discuss the design and construction of post tensioned slab
structures, especially post tensioned flat slabs*
 A detailed explanation will be given of the checks to be carried
out, the aspects to be considered in the design and the
construction procedures and sequences of a post-tensioned
slab. The execution of the design will be explained.
Prestressed concrete
 PRINCIPLE – Using high tensile strength
steel alloys producing permanent pre-
compression in areas subjected to Tension.
 A portion of tensile stress is counteracted
thereby reducing the cross-sectional area of
the steel reinforcement .
 METHODS :- a) Pretensioning
b)Post-tensioning
 PRETENSIONING :- Placing of concrete
around reinforcing tendons that have been
stressed to the desired degree.
 POST-TENSIONING :- Reinforcing tendons
are stretched by jacks whilst keeping them in
serted in voids left pre-hand during curing of
concrete.
 These spaces are then pumped full of grout
to bond steel tightly to the concrete.
STEEL BARS BEING
STRETCHED BY JACKS
Introduction
Methods of Pre-stressing
Pre-tensioning
Post-tensioning
Introduction
Pre-tensioning
• Steel tendons are stressed before the concrete is placed
at a precast plant remote from the construction site.
Introduction
Post-tensioning
• Steel tendon are stressed after the concrete has
been placed and gained sufficient strength at
the construction site.
Introduction
Post-tensioning Systems
Un-bonded Post-tensioning System
Bonded Post-tensioning Systems
Single strand
Multi strands flat duct
Multi strands round duct
Single strand
Design of PT Slabs
Flat Plate with Drop Panels
Common geometries*
• Two-way system
• Suitable span: 12.2 m
• Limiting criterion: Deflection
• Rebar**: 2.94 kg/m2
• PT: 3.87 kg/m2
* for typical office/residential buildings using
ACI/UBC requirements
** quantity assume no bottom reinforcement
post tensioning slabs
Materiel properties
CONCRETE:
Fc^28 → Compressive strength of concrete 28 days.
Fcd → Design value for compressive strength on concrete.
→ 0.6 × fc^28 = 21 N/MM^2
PRE STRESSING STEEL:
Ap → cross sectional area of pj steel 146 mm^2
Fpy →yield strength of PT steel 1570 N/MM^2
Fpu → characteristic strength of PT steel 1770 N/MM^2
PRE-TENSIONING STEEL:
Ep → modulus of elasticity of pre stressing steel 1.95 × 10^5 N/MM^2
(very low relaxation (3%)
Admissible stressing 0.75 fpu
Reinforcing steel:
Fsy →yield strength of reinforcing steel is 460 N/MM^2
Long-term losses (assumed to be 10%)
Details of building
Type of structure: commercial building
- Loadings:
Live load p = 2.5 kN/m2
Floor finishes gB = 1.OkN/m2
Walls g w = 1.5 kN/m2
q = 5.0 kN/m2
Plan showing dimensions
Design
Determination of slab thickness:
Assumption l/h = 35
Self wt of slab g = yc × h
L → length of span 8.4
h → 0.24 mt
h → thickness of slab.
Yc → volumetric wt.of concrete →2.5 KN/M^3
→ g=6KN/M^3
→ q =5 KN/M^3
→ (g+q)/g) = 6+5/6 = 1.83 ((g+q) –service load
g→ self wt )
(l/h as a function of (g+q/g))
→ For a value of 1.83 on y- axis l/h is coming to 36
→ 0.233 which is approximately (0.24)
Determination of prestress
µ → it is transfer component from pre stressing / unit length
(g+q/g) → 1.83 based on previous caluculation
Pre stress in longitudinal direction
→ for 1.83 the u/g value in is 1.39
→ u = 8.34 KN/m^2
K → woober’s coefficient =(0.24×10^3)/(8.4^2×25) = 0.136
→h = 0.24
→length of slab = 8.4
→yc =25
£c =concrete tensile stress=1000
Pre tensioning force
→ P = 4×l^2/8×hp
→sag of tendon parabola
Hp →0.178mt (p=8.34× 8.4^2/8×0.178)
P =413 KN/M
P =7.8 × 413 for a width of 78 mt
P = 3221 KN/strand
Pl → pre tensioning force per strand
Pl → Ap × fpu × 0.7 ×10^-3
Ap =416 mm^2
Fpu = 1770 N/mm^2
Pl = 181 KN
strands
No.of strands = p/ pl =413/pl =17.8 =͠ 18
18 strands of dia 15mm on 78 mt width.
For 7.4 mt width =7.4/7.8 ×17.8 =16.88
17 mono strands of dia 15 mm of 7.4 mt width.
On 6.6 mt width = 6.6/7.8 ×17.8 =15.1
16 mono strands of dia 15 mm of 6.6 mt width.
For 2.4 mt width =2.4/7.8 ×17.8 =5.5
6 mono strand of dia of 15mm on 2.4 mt width
Transverse direction:
g+q/g = 1.83
k = 0.24 × 1000/ 7.8 m^2×25
k = 0.158
on design chart 2 for a k value of 0.158 & (g+q/g) value of 1.83 the value of u/g is found be 1.41
→ u= 8.46 kn/m^2
P = (u×l^2/8×hp ) →8.46 ×7.8^2/( 8× 0.167)
P = 3.85 kn/m
On 8.4 mt width p=8.4×385
P =3234 kn
Pc 181 kn
No. Of strands Np = p/pl =3234/181 = 17.9
18 mono strands of dia 15mm on 8.4 mt width
On 7.2 mt width np = 7.2/8.4× 7.9 = 15.3
16 mono strands of dia 15mm on 7.2 mt width.
Execution
Materials & Equipment
Anchorage Markings
Laying of Tendon
Concrete pouring
Pre stressing
grouting
MATERIALS AND EQUIPMENT
a) FORMWORK
b) CONCRETE
c) STRANDS
d) TENDONS
e) DUCTS
f) ANCHORAGES
g) WEDGES
Formwork
strands
Wedges
POST –TENSIONING METHOD
Anchorage marking
Laying of tendons
Concrete pourig
 Mix design of M35
 Grade of Concrete : M35
 Characteristic Strength (Fck) : 35 Mpa
 Standard Deviation : 1.91 Mpa*
 Target Mean Strength : T.M.S.= Fck +1.65 x S.D.
 (from I.S 456-2000) = 35+ 1.65×1.91
 = 38.15 Mpa
 Test Data For Material:
 Aggregate Type : Crushed
 Specific Gravity Cement : 3.15
 Coarse Aggregate : 2.67
 Fine Aggregate : 2.62
 Water Absorption
 Coarse Aggregate : 0.5%
 Fine Aggregate : 1.0 %
Concrete pouring
Mix Design:
 Take Sand content as percentage of total aggregates = 36%
 Select Water Cement Ratio = 0.43 for concrete grade M35
 Select Water Content = 172 Kg
 (From IS: 10262 for 20 mm nominal size of aggregates Maximum Water Content = 186 Kg/m 3 )
Hence, Cement Content= 172 / 0.43 = 400 Kg /m 3
 Formula for Mix Proportion of Fine and Coarse Aggregate:
 1000(1-a 0 )= {(Cement Content / Sp. Gr. Of Cement) + Water Content +(F a / Sp. Gr.* P f )} 1000(1-
a 0 )= {(Cement Content / Sp. Gr. Of Cement) + Water Content +C a / Sp. Gr.* Pc )}
 Where
 C a = Coarse Aggregate Content
 F a = Fine Aggregate Content
 P f = Sand Content as percentage of total Aggregates = 0.36
 P c = Coarse Aggregate Content as percentage of total Aggregates.
 = 0.64
 a 0 = Percentage air content in concrete (As per IS :10262 for 20 mm nominal size of
 aggregates air content is 2 %) = 0.02
 Hence, 1000(1-0.02) = {(400 /3.15) + 172 +(F a / 2.62 x 0.36)}
 Fa = 642 Kg/ Cum
 As the sand is of Zone II no adjustment is required for sand.
 Sand Content = 642 Kg/ Cum
 1000(1-0.02)= {(400 /3.15) + 172 +(C a / 2.67 x 0.64)}
 Hence, Ca = 1165 Kg/ Cum
Prestressing jack
 For prestressing, mono strand stressing jack is used and pressure is
applied in a controlled way with the help of prestressing power pack.
Initially, a gradual pressure of about 5 kg/cm 2 is applied.
 anchorage bursting when prestressing is applied and also to check
anchorage slip. The perimeter of the rod is then marked with paint and
then once the anchorage is known to be stable, the pressure is
increasing up to 430 kg/cm 2 .
Jacks
Prestressing powerpack
Mono strandstressing jack
Grouting
 Grouting is done with the help of grout pump. The mixture of cement,
water and admixtures must be done under a strict mixing time and
velocity control and must not contain lumps nor any air bubbles during
injection into the ducts
EQUIPMENTS :-
 T6Z-08 Air Powered Grout Pump
 Pumps cement grout only, no sand. 32 Gallon Mixing
Tank. Mixes up to 2 sacks of material at once and allows
for grout to be pumped during mixing or mixed without
pumping.
Approximate size 50" long
30.5" high
52" wide
Weight 560 lbs.
Production Rate 8 gallons per
minute
at 150 psi
ADVANTAGES OF POST-TENSIONING
• Longer clear spans
• Thinner slabs
• Lesser floor-to-floor heights
• Shorter building height
• Lesser weight
• Improved seismic performance
• Faster construction cycle
Conclusions
 Prestressed concrete offers great technical advantages in comparison with
other forms of construction such as reinforced concrete and steel. They
possess improved resistance to shearing forces, due to the effect of
compressive prestress, which reduces the principles tensile stress
 Prestressing of concrete helps in improving the ability of the material for
energy absorption under impact loads. The economy of prestressed concrete
is well established for long span structures. Standardized precast bridge
beams between 10m and 30 m long and precast prestressed piles have
proved to be more economical than steel and reinforced concrete.
 Due to utilization of concrete in the tension zone, an extra saving of 15 to 30%
in concrete is possible in comparison with reinforced concrete
Thank You!

Contenu connexe

Tendances

Post-tensioning in Prestressed Concrete
Post-tensioning in Prestressed ConcretePost-tensioning in Prestressed Concrete
Post-tensioning in Prestressed ConcreteDavinderpal Singh
 
Post tensioned (PT) slabs
Post tensioned (PT) slabsPost tensioned (PT) slabs
Post tensioned (PT) slabsFOYSOLMAHMUD1
 
Basic principles of design for rcc building
Basic principles of design for rcc buildingBasic principles of design for rcc building
Basic principles of design for rcc buildinghlksd
 
Chapter 3 materials & techniques for repairs
Chapter 3 materials & techniques for repairsChapter 3 materials & techniques for repairs
Chapter 3 materials & techniques for repairsAnkit Patel
 
Introduction to prestressed concrete
Introduction to prestressed concreteIntroduction to prestressed concrete
Introduction to prestressed concrete9833356555
 
Retrofitting of concrete structure
Retrofitting of concrete structureRetrofitting of concrete structure
Retrofitting of concrete structureshlok patel
 
PRESTRESSED CONCRETE STRUCTURES
PRESTRESSED CONCRETE STRUCTURESPRESTRESSED CONCRETE STRUCTURES
PRESTRESSED CONCRETE STRUCTURESTarun kumar
 
Special Concreting Techniques
Special Concreting Techniques Special Concreting Techniques
Special Concreting Techniques GAURAV. H .TANDON
 
Creep and shrinkage
Creep and shrinkageCreep and shrinkage
Creep and shrinkageAsad Rehman
 
Prestressed concrete structures and its applications By Mukesh Singh Ghuraiya
Prestressed concrete structures and its applications By Mukesh Singh GhuraiyaPrestressed concrete structures and its applications By Mukesh Singh Ghuraiya
Prestressed concrete structures and its applications By Mukesh Singh GhuraiyaMukesh Singh Ghuraiya
 
Prestressed concrete
Prestressed concretePrestressed concrete
Prestressed concreteRajesh Burde
 
DEEP FOUNDATION
DEEP FOUNDATIONDEEP FOUNDATION
DEEP FOUNDATIONaframawal
 
Techniques for various structural repair
Techniques for various  structural repairTechniques for various  structural repair
Techniques for various structural repairUdayram Patil
 

Tendances (20)

Pile foundations
Pile foundationsPile foundations
Pile foundations
 
Repair and Rehabilitation
Repair and RehabilitationRepair and Rehabilitation
Repair and Rehabilitation
 
Post-tensioning in Prestressed Concrete
Post-tensioning in Prestressed ConcretePost-tensioning in Prestressed Concrete
Post-tensioning in Prestressed Concrete
 
Post tensioned (PT) slabs
Post tensioned (PT) slabsPost tensioned (PT) slabs
Post tensioned (PT) slabs
 
Basic principles of design for rcc building
Basic principles of design for rcc buildingBasic principles of design for rcc building
Basic principles of design for rcc building
 
Chapter 3 materials & techniques for repairs
Chapter 3 materials & techniques for repairsChapter 3 materials & techniques for repairs
Chapter 3 materials & techniques for repairs
 
Introduction to prestressed concrete
Introduction to prestressed concreteIntroduction to prestressed concrete
Introduction to prestressed concrete
 
Retrofitting of concrete structure
Retrofitting of concrete structureRetrofitting of concrete structure
Retrofitting of concrete structure
 
Post Tension
Post TensionPost Tension
Post Tension
 
PRESTRESSED CONCRETE STRUCTURES
PRESTRESSED CONCRETE STRUCTURESPRESTRESSED CONCRETE STRUCTURES
PRESTRESSED CONCRETE STRUCTURES
 
Special Concreting Techniques
Special Concreting Techniques Special Concreting Techniques
Special Concreting Techniques
 
Creep and shrinkage
Creep and shrinkageCreep and shrinkage
Creep and shrinkage
 
Prestressed concrete structures and its applications By Mukesh Singh Ghuraiya
Prestressed concrete structures and its applications By Mukesh Singh GhuraiyaPrestressed concrete structures and its applications By Mukesh Singh Ghuraiya
Prestressed concrete structures and its applications By Mukesh Singh Ghuraiya
 
Prestressed concrete
Prestressed concretePrestressed concrete
Prestressed concrete
 
Pre-stressed Concrete
Pre-stressed ConcretePre-stressed Concrete
Pre-stressed Concrete
 
Epoxy injection crack repair
Epoxy injection crack repairEpoxy injection crack repair
Epoxy injection crack repair
 
DEEP FOUNDATION
DEEP FOUNDATIONDEEP FOUNDATION
DEEP FOUNDATION
 
Concrete repair
Concrete repairConcrete repair
Concrete repair
 
Cracks in Buildings
Cracks in BuildingsCracks in Buildings
Cracks in Buildings
 
Techniques for various structural repair
Techniques for various  structural repairTechniques for various  structural repair
Techniques for various structural repair
 

En vedette

En vedette (7)

Gyproc
GyprocGyproc
Gyproc
 
Final Construction Documents
Final Construction DocumentsFinal Construction Documents
Final Construction Documents
 
Post-Tension Concrete - Info session for Contractors
Post-Tension Concrete - Info session for ContractorsPost-Tension Concrete - Info session for Contractors
Post-Tension Concrete - Info session for Contractors
 
Partition walls
Partition wallsPartition walls
Partition walls
 
Partition wall
Partition wallPartition wall
Partition wall
 
Partitions
PartitionsPartitions
Partitions
 
prestressed concrete
prestressed concreteprestressed concrete
prestressed concrete
 

Similaire à post tensioning slabs

350 kl overhead water intze tank design
350 kl overhead water intze tank design350 kl overhead water intze tank design
350 kl overhead water intze tank designHarish Mahavar
 
Structural design of 350 kl overhead water tank at telibagh,lucknow
Structural design of 350 kl overhead water tank at telibagh,lucknowStructural design of 350 kl overhead water tank at telibagh,lucknow
Structural design of 350 kl overhead water tank at telibagh,lucknowAnchit Agrawal
 
Comparative Study on Flexural Strength of M20 Grade Beam with Lapping of Bars
Comparative Study on Flexural Strength of M20 Grade Beam with Lapping of BarsComparative Study on Flexural Strength of M20 Grade Beam with Lapping of Bars
Comparative Study on Flexural Strength of M20 Grade Beam with Lapping of BarsIRJET Journal
 
Design of composite steel and concrete structures.pptx
Design of composite steel and concrete structures.pptxDesign of composite steel and concrete structures.pptx
Design of composite steel and concrete structures.pptxSharpEyu
 
Design of Steel Grillage Foundation for an Auditorium
Design of Steel Grillage Foundation for an AuditoriumDesign of Steel Grillage Foundation for an Auditorium
Design of Steel Grillage Foundation for an AuditoriumIRJET Journal
 
IRJET- Design of the Support Structure for the Pipe Line System
IRJET- Design of the Support Structure for the Pipe Line SystemIRJET- Design of the Support Structure for the Pipe Line System
IRJET- Design of the Support Structure for the Pipe Line SystemIRJET Journal
 
Chap-5-T-Girder Example-1.pdf
Chap-5-T-Girder Example-1.pdfChap-5-T-Girder Example-1.pdf
Chap-5-T-Girder Example-1.pdfAberaMamoJaleta
 
Construction Aspects of Rigid Pavements.ppt
Construction Aspects of Rigid Pavements.pptConstruction Aspects of Rigid Pavements.ppt
Construction Aspects of Rigid Pavements.pptbala506586
 
Important Technical Terms in Concrete Design
Important Technical Terms in Concrete DesignImportant Technical Terms in Concrete Design
Important Technical Terms in Concrete DesignRoshni Ramakrishnan
 
Structural Design
Structural DesignStructural Design
Structural DesignVj NiroSh
 
Qualification under hypothetical accident conditions during transport-R Pal
Qualification under hypothetical accident conditions during transport-R PalQualification under hypothetical accident conditions during transport-R Pal
Qualification under hypothetical accident conditions during transport-R PalProSIM R & D Pvt. Ltd.
 
Experimental Study on Soil Nailing.pptx
Experimental Study on Soil Nailing.pptxExperimental Study on Soil Nailing.pptx
Experimental Study on Soil Nailing.pptxSamirsinh Parmar
 
New Microsoft PowerPoint Presentation.pptx
New Microsoft PowerPoint Presentation.pptxNew Microsoft PowerPoint Presentation.pptx
New Microsoft PowerPoint Presentation.pptxRajeshKumar25548
 
fiber feinforced concrete.pptx
fiber feinforced concrete.pptxfiber feinforced concrete.pptx
fiber feinforced concrete.pptxAnujKumarShukla8
 
Experimental behaviour and analysis of stress in rigid pavement
Experimental behaviour and analysis of stress in rigid pavementExperimental behaviour and analysis of stress in rigid pavement
Experimental behaviour and analysis of stress in rigid pavementVivek Loyola
 
DESIGN OF CIRCULAR OVERHEAD WATER TANK.pptx
DESIGN OF CIRCULAR OVERHEAD WATER TANK.pptxDESIGN OF CIRCULAR OVERHEAD WATER TANK.pptx
DESIGN OF CIRCULAR OVERHEAD WATER TANK.pptxsubhashini214160
 

Similaire à post tensioning slabs (20)

Design of Composite Pressure Vessel
Design of Composite Pressure VesselDesign of Composite Pressure Vessel
Design of Composite Pressure Vessel
 
350 kl overhead water intze tank design
350 kl overhead water intze tank design350 kl overhead water intze tank design
350 kl overhead water intze tank design
 
Structural design of 350 kl overhead water tank at telibagh,lucknow
Structural design of 350 kl overhead water tank at telibagh,lucknowStructural design of 350 kl overhead water tank at telibagh,lucknow
Structural design of 350 kl overhead water tank at telibagh,lucknow
 
Jury Presenatation.pptx
Jury Presenatation.pptxJury Presenatation.pptx
Jury Presenatation.pptx
 
Comparative Study on Flexural Strength of M20 Grade Beam with Lapping of Bars
Comparative Study on Flexural Strength of M20 Grade Beam with Lapping of BarsComparative Study on Flexural Strength of M20 Grade Beam with Lapping of Bars
Comparative Study on Flexural Strength of M20 Grade Beam with Lapping of Bars
 
Design of composite steel and concrete structures.pptx
Design of composite steel and concrete structures.pptxDesign of composite steel and concrete structures.pptx
Design of composite steel and concrete structures.pptx
 
Design of Steel Grillage Foundation for an Auditorium
Design of Steel Grillage Foundation for an AuditoriumDesign of Steel Grillage Foundation for an Auditorium
Design of Steel Grillage Foundation for an Auditorium
 
IRJET- Design of the Support Structure for the Pipe Line System
IRJET- Design of the Support Structure for the Pipe Line SystemIRJET- Design of the Support Structure for the Pipe Line System
IRJET- Design of the Support Structure for the Pipe Line System
 
Prestressed pipes,tanks,poles
Prestressed pipes,tanks,polesPrestressed pipes,tanks,poles
Prestressed pipes,tanks,poles
 
Chap-5-T-Girder Example-1.pdf
Chap-5-T-Girder Example-1.pdfChap-5-T-Girder Example-1.pdf
Chap-5-T-Girder Example-1.pdf
 
Construction Aspects of Rigid Pavements.ppt
Construction Aspects of Rigid Pavements.pptConstruction Aspects of Rigid Pavements.ppt
Construction Aspects of Rigid Pavements.ppt
 
Important Technical Terms in Concrete Design
Important Technical Terms in Concrete DesignImportant Technical Terms in Concrete Design
Important Technical Terms in Concrete Design
 
Structural Design
Structural DesignStructural Design
Structural Design
 
bridge final ppt.pptx
bridge final ppt.pptxbridge final ppt.pptx
bridge final ppt.pptx
 
Qualification under hypothetical accident conditions during transport-R Pal
Qualification under hypothetical accident conditions during transport-R PalQualification under hypothetical accident conditions during transport-R Pal
Qualification under hypothetical accident conditions during transport-R Pal
 
Experimental Study on Soil Nailing.pptx
Experimental Study on Soil Nailing.pptxExperimental Study on Soil Nailing.pptx
Experimental Study on Soil Nailing.pptx
 
New Microsoft PowerPoint Presentation.pptx
New Microsoft PowerPoint Presentation.pptxNew Microsoft PowerPoint Presentation.pptx
New Microsoft PowerPoint Presentation.pptx
 
fiber feinforced concrete.pptx
fiber feinforced concrete.pptxfiber feinforced concrete.pptx
fiber feinforced concrete.pptx
 
Experimental behaviour and analysis of stress in rigid pavement
Experimental behaviour and analysis of stress in rigid pavementExperimental behaviour and analysis of stress in rigid pavement
Experimental behaviour and analysis of stress in rigid pavement
 
DESIGN OF CIRCULAR OVERHEAD WATER TANK.pptx
DESIGN OF CIRCULAR OVERHEAD WATER TANK.pptxDESIGN OF CIRCULAR OVERHEAD WATER TANK.pptx
DESIGN OF CIRCULAR OVERHEAD WATER TANK.pptx
 

Dernier

Popular-NO1 Kala Jadu Expert Specialist In Germany Kala Jadu Expert Specialis...
Popular-NO1 Kala Jadu Expert Specialist In Germany Kala Jadu Expert Specialis...Popular-NO1 Kala Jadu Expert Specialist In Germany Kala Jadu Expert Specialis...
Popular-NO1 Kala Jadu Expert Specialist In Germany Kala Jadu Expert Specialis...Amil baba
 
IT3401-WEB ESSENTIALS PRESENTATIONS.pptx
IT3401-WEB ESSENTIALS PRESENTATIONS.pptxIT3401-WEB ESSENTIALS PRESENTATIONS.pptx
IT3401-WEB ESSENTIALS PRESENTATIONS.pptxSAJITHABANUS
 
solar wireless electric vechicle charging system
solar wireless electric vechicle charging systemsolar wireless electric vechicle charging system
solar wireless electric vechicle charging systemgokuldongala
 
Strategies of Urban Morphologyfor Improving Outdoor Thermal Comfort and Susta...
Strategies of Urban Morphologyfor Improving Outdoor Thermal Comfort and Susta...Strategies of Urban Morphologyfor Improving Outdoor Thermal Comfort and Susta...
Strategies of Urban Morphologyfor Improving Outdoor Thermal Comfort and Susta...amrabdallah9
 
Lecture 1: Basics of trigonometry (surveying)
Lecture 1: Basics of trigonometry (surveying)Lecture 1: Basics of trigonometry (surveying)
Lecture 1: Basics of trigonometry (surveying)Bahzad5
 
ChatGPT-and-Generative-AI-Landscape Working of generative ai search
ChatGPT-and-Generative-AI-Landscape Working of generative ai searchChatGPT-and-Generative-AI-Landscape Working of generative ai search
ChatGPT-and-Generative-AI-Landscape Working of generative ai searchrohitcse52
 
Gender Bias in Engineer, Honors 203 Project
Gender Bias in Engineer, Honors 203 ProjectGender Bias in Engineer, Honors 203 Project
Gender Bias in Engineer, Honors 203 Projectreemakb03
 
SUMMER TRAINING REPORT ON BUILDING CONSTRUCTION.docx
SUMMER TRAINING REPORT ON BUILDING CONSTRUCTION.docxSUMMER TRAINING REPORT ON BUILDING CONSTRUCTION.docx
SUMMER TRAINING REPORT ON BUILDING CONSTRUCTION.docxNaveenVerma126
 
Phase noise transfer functions.pptx
Phase noise transfer      functions.pptxPhase noise transfer      functions.pptx
Phase noise transfer functions.pptxSaiGouthamSunkara
 
ASME BPVC 2023 Section I para leer y entender
ASME BPVC 2023 Section I para leer y entenderASME BPVC 2023 Section I para leer y entender
ASME BPVC 2023 Section I para leer y entenderjuancarlos286641
 
UNIT4_ESD_wfffffggggggggggggith_ARM.pptx
UNIT4_ESD_wfffffggggggggggggith_ARM.pptxUNIT4_ESD_wfffffggggggggggggith_ARM.pptx
UNIT4_ESD_wfffffggggggggggggith_ARM.pptxrealme6igamerr
 
nvidia AI-gtc 2024 partial slide deck.pptx
nvidia AI-gtc 2024 partial slide deck.pptxnvidia AI-gtc 2024 partial slide deck.pptx
nvidia AI-gtc 2024 partial slide deck.pptxjasonsedano2
 
A Seminar on Electric Vehicle Software Simulation
A Seminar on Electric Vehicle Software SimulationA Seminar on Electric Vehicle Software Simulation
A Seminar on Electric Vehicle Software SimulationMohsinKhanA
 
Guardians and Glitches: Navigating the Duality of Gen AI in AppSec
Guardians and Glitches: Navigating the Duality of Gen AI in AppSecGuardians and Glitches: Navigating the Duality of Gen AI in AppSec
Guardians and Glitches: Navigating the Duality of Gen AI in AppSecTrupti Shiralkar, CISSP
 
دليل تجارب الاسفلت المختبرية - Asphalt Experiments Guide Laboratory
دليل تجارب الاسفلت المختبرية - Asphalt Experiments Guide Laboratoryدليل تجارب الاسفلت المختبرية - Asphalt Experiments Guide Laboratory
دليل تجارب الاسفلت المختبرية - Asphalt Experiments Guide LaboratoryBahzad5
 
How to Write a Good Scientific Paper.pdf
How to Write a Good Scientific Paper.pdfHow to Write a Good Scientific Paper.pdf
How to Write a Good Scientific Paper.pdfRedhwan Qasem Shaddad
 
cloud computing notes for anna university syllabus
cloud computing notes for anna university syllabuscloud computing notes for anna university syllabus
cloud computing notes for anna university syllabusViolet Violet
 
Transforming Process Safety Management: Challenges, Benefits, and Transition ...
Transforming Process Safety Management: Challenges, Benefits, and Transition ...Transforming Process Safety Management: Challenges, Benefits, and Transition ...
Transforming Process Safety Management: Challenges, Benefits, and Transition ...soginsider
 

Dernier (20)

Popular-NO1 Kala Jadu Expert Specialist In Germany Kala Jadu Expert Specialis...
Popular-NO1 Kala Jadu Expert Specialist In Germany Kala Jadu Expert Specialis...Popular-NO1 Kala Jadu Expert Specialist In Germany Kala Jadu Expert Specialis...
Popular-NO1 Kala Jadu Expert Specialist In Germany Kala Jadu Expert Specialis...
 
IT3401-WEB ESSENTIALS PRESENTATIONS.pptx
IT3401-WEB ESSENTIALS PRESENTATIONS.pptxIT3401-WEB ESSENTIALS PRESENTATIONS.pptx
IT3401-WEB ESSENTIALS PRESENTATIONS.pptx
 
solar wireless electric vechicle charging system
solar wireless electric vechicle charging systemsolar wireless electric vechicle charging system
solar wireless electric vechicle charging system
 
Strategies of Urban Morphologyfor Improving Outdoor Thermal Comfort and Susta...
Strategies of Urban Morphologyfor Improving Outdoor Thermal Comfort and Susta...Strategies of Urban Morphologyfor Improving Outdoor Thermal Comfort and Susta...
Strategies of Urban Morphologyfor Improving Outdoor Thermal Comfort and Susta...
 
Lecture 1: Basics of trigonometry (surveying)
Lecture 1: Basics of trigonometry (surveying)Lecture 1: Basics of trigonometry (surveying)
Lecture 1: Basics of trigonometry (surveying)
 
ChatGPT-and-Generative-AI-Landscape Working of generative ai search
ChatGPT-and-Generative-AI-Landscape Working of generative ai searchChatGPT-and-Generative-AI-Landscape Working of generative ai search
ChatGPT-and-Generative-AI-Landscape Working of generative ai search
 
Gender Bias in Engineer, Honors 203 Project
Gender Bias in Engineer, Honors 203 ProjectGender Bias in Engineer, Honors 203 Project
Gender Bias in Engineer, Honors 203 Project
 
SUMMER TRAINING REPORT ON BUILDING CONSTRUCTION.docx
SUMMER TRAINING REPORT ON BUILDING CONSTRUCTION.docxSUMMER TRAINING REPORT ON BUILDING CONSTRUCTION.docx
SUMMER TRAINING REPORT ON BUILDING CONSTRUCTION.docx
 
Phase noise transfer functions.pptx
Phase noise transfer      functions.pptxPhase noise transfer      functions.pptx
Phase noise transfer functions.pptx
 
ASME BPVC 2023 Section I para leer y entender
ASME BPVC 2023 Section I para leer y entenderASME BPVC 2023 Section I para leer y entender
ASME BPVC 2023 Section I para leer y entender
 
UNIT4_ESD_wfffffggggggggggggith_ARM.pptx
UNIT4_ESD_wfffffggggggggggggith_ARM.pptxUNIT4_ESD_wfffffggggggggggggith_ARM.pptx
UNIT4_ESD_wfffffggggggggggggith_ARM.pptx
 
nvidia AI-gtc 2024 partial slide deck.pptx
nvidia AI-gtc 2024 partial slide deck.pptxnvidia AI-gtc 2024 partial slide deck.pptx
nvidia AI-gtc 2024 partial slide deck.pptx
 
A Seminar on Electric Vehicle Software Simulation
A Seminar on Electric Vehicle Software SimulationA Seminar on Electric Vehicle Software Simulation
A Seminar on Electric Vehicle Software Simulation
 
Guardians and Glitches: Navigating the Duality of Gen AI in AppSec
Guardians and Glitches: Navigating the Duality of Gen AI in AppSecGuardians and Glitches: Navigating the Duality of Gen AI in AppSec
Guardians and Glitches: Navigating the Duality of Gen AI in AppSec
 
دليل تجارب الاسفلت المختبرية - Asphalt Experiments Guide Laboratory
دليل تجارب الاسفلت المختبرية - Asphalt Experiments Guide Laboratoryدليل تجارب الاسفلت المختبرية - Asphalt Experiments Guide Laboratory
دليل تجارب الاسفلت المختبرية - Asphalt Experiments Guide Laboratory
 
How to Write a Good Scientific Paper.pdf
How to Write a Good Scientific Paper.pdfHow to Write a Good Scientific Paper.pdf
How to Write a Good Scientific Paper.pdf
 
Présentation IIRB 2024 Chloe Dufrane.pdf
Présentation IIRB 2024 Chloe Dufrane.pdfPrésentation IIRB 2024 Chloe Dufrane.pdf
Présentation IIRB 2024 Chloe Dufrane.pdf
 
cloud computing notes for anna university syllabus
cloud computing notes for anna university syllabuscloud computing notes for anna university syllabus
cloud computing notes for anna university syllabus
 
Lecture 4 .pdf
Lecture 4                              .pdfLecture 4                              .pdf
Lecture 4 .pdf
 
Transforming Process Safety Management: Challenges, Benefits, and Transition ...
Transforming Process Safety Management: Challenges, Benefits, and Transition ...Transforming Process Safety Management: Challenges, Benefits, and Transition ...
Transforming Process Safety Management: Challenges, Benefits, and Transition ...
 

post tensioning slabs

  • 1. Project on Design and construction of post tensioning slab PRESENTING BY:- CH .Gopichand (10631A0110) D.Nagender (10631A0120) J.Paramesh (10631A0126) N.Prudhviraj (10631A0129) S.Sathyanarayana(10631A0147) CIVIL ENGINEERING 4th YEAR SRI VENKATESWARA ENGINEERING COLLEGE INTERNAL GUIDE: Mrs.P.Jhansi
  • 2. Objectives The objective of the present report is  to summarize the experience available today in the field of post-tensioning in building construction and in particular to discuss the design and construction of post tensioned slab structures, especially post tensioned flat slabs*  A detailed explanation will be given of the checks to be carried out, the aspects to be considered in the design and the construction procedures and sequences of a post-tensioned slab. The execution of the design will be explained.
  • 3. Prestressed concrete  PRINCIPLE – Using high tensile strength steel alloys producing permanent pre- compression in areas subjected to Tension.  A portion of tensile stress is counteracted thereby reducing the cross-sectional area of the steel reinforcement .  METHODS :- a) Pretensioning b)Post-tensioning  PRETENSIONING :- Placing of concrete around reinforcing tendons that have been stressed to the desired degree.  POST-TENSIONING :- Reinforcing tendons are stretched by jacks whilst keeping them in serted in voids left pre-hand during curing of concrete.  These spaces are then pumped full of grout to bond steel tightly to the concrete. STEEL BARS BEING STRETCHED BY JACKS
  • 5. Introduction Pre-tensioning • Steel tendons are stressed before the concrete is placed at a precast plant remote from the construction site.
  • 6. Introduction Post-tensioning • Steel tendon are stressed after the concrete has been placed and gained sufficient strength at the construction site.
  • 7. Introduction Post-tensioning Systems Un-bonded Post-tensioning System Bonded Post-tensioning Systems Single strand Multi strands flat duct Multi strands round duct Single strand
  • 8. Design of PT Slabs Flat Plate with Drop Panels Common geometries* • Two-way system • Suitable span: 12.2 m • Limiting criterion: Deflection • Rebar**: 2.94 kg/m2 • PT: 3.87 kg/m2 * for typical office/residential buildings using ACI/UBC requirements ** quantity assume no bottom reinforcement
  • 10. Materiel properties CONCRETE: Fc^28 → Compressive strength of concrete 28 days. Fcd → Design value for compressive strength on concrete. → 0.6 × fc^28 = 21 N/MM^2 PRE STRESSING STEEL: Ap → cross sectional area of pj steel 146 mm^2 Fpy →yield strength of PT steel 1570 N/MM^2 Fpu → characteristic strength of PT steel 1770 N/MM^2 PRE-TENSIONING STEEL: Ep → modulus of elasticity of pre stressing steel 1.95 × 10^5 N/MM^2 (very low relaxation (3%) Admissible stressing 0.75 fpu Reinforcing steel: Fsy →yield strength of reinforcing steel is 460 N/MM^2 Long-term losses (assumed to be 10%)
  • 11. Details of building Type of structure: commercial building - Loadings: Live load p = 2.5 kN/m2 Floor finishes gB = 1.OkN/m2 Walls g w = 1.5 kN/m2 q = 5.0 kN/m2
  • 13. Design Determination of slab thickness: Assumption l/h = 35 Self wt of slab g = yc × h L → length of span 8.4 h → 0.24 mt h → thickness of slab. Yc → volumetric wt.of concrete →2.5 KN/M^3 → g=6KN/M^3 → q =5 KN/M^3 → (g+q)/g) = 6+5/6 = 1.83 ((g+q) –service load g→ self wt )
  • 14. (l/h as a function of (g+q/g)) → For a value of 1.83 on y- axis l/h is coming to 36 → 0.233 which is approximately (0.24)
  • 15. Determination of prestress µ → it is transfer component from pre stressing / unit length (g+q/g) → 1.83 based on previous caluculation
  • 16. Pre stress in longitudinal direction → for 1.83 the u/g value in is 1.39 → u = 8.34 KN/m^2 K → woober’s coefficient =(0.24×10^3)/(8.4^2×25) = 0.136 →h = 0.24 →length of slab = 8.4 →yc =25 £c =concrete tensile stress=1000 Pre tensioning force → P = 4×l^2/8×hp →sag of tendon parabola Hp →0.178mt (p=8.34× 8.4^2/8×0.178) P =413 KN/M P =7.8 × 413 for a width of 78 mt P = 3221 KN/strand Pl → pre tensioning force per strand Pl → Ap × fpu × 0.7 ×10^-3 Ap =416 mm^2 Fpu = 1770 N/mm^2 Pl = 181 KN
  • 17. strands No.of strands = p/ pl =413/pl =17.8 =͠ 18 18 strands of dia 15mm on 78 mt width. For 7.4 mt width =7.4/7.8 ×17.8 =16.88 17 mono strands of dia 15 mm of 7.4 mt width. On 6.6 mt width = 6.6/7.8 ×17.8 =15.1 16 mono strands of dia 15 mm of 6.6 mt width. For 2.4 mt width =2.4/7.8 ×17.8 =5.5 6 mono strand of dia of 15mm on 2.4 mt width Transverse direction: g+q/g = 1.83 k = 0.24 × 1000/ 7.8 m^2×25 k = 0.158 on design chart 2 for a k value of 0.158 & (g+q/g) value of 1.83 the value of u/g is found be 1.41 → u= 8.46 kn/m^2 P = (u×l^2/8×hp ) →8.46 ×7.8^2/( 8× 0.167) P = 3.85 kn/m On 8.4 mt width p=8.4×385 P =3234 kn Pc 181 kn No. Of strands Np = p/pl =3234/181 = 17.9 18 mono strands of dia 15mm on 8.4 mt width On 7.2 mt width np = 7.2/8.4× 7.9 = 15.3 16 mono strands of dia 15mm on 7.2 mt width.
  • 18. Execution Materials & Equipment Anchorage Markings Laying of Tendon Concrete pouring Pre stressing grouting
  • 19. MATERIALS AND EQUIPMENT a) FORMWORK b) CONCRETE c) STRANDS d) TENDONS e) DUCTS f) ANCHORAGES g) WEDGES
  • 26. Concrete pourig  Mix design of M35  Grade of Concrete : M35  Characteristic Strength (Fck) : 35 Mpa  Standard Deviation : 1.91 Mpa*  Target Mean Strength : T.M.S.= Fck +1.65 x S.D.  (from I.S 456-2000) = 35+ 1.65×1.91  = 38.15 Mpa  Test Data For Material:  Aggregate Type : Crushed  Specific Gravity Cement : 3.15  Coarse Aggregate : 2.67  Fine Aggregate : 2.62  Water Absorption  Coarse Aggregate : 0.5%  Fine Aggregate : 1.0 %
  • 28. Mix Design:  Take Sand content as percentage of total aggregates = 36%  Select Water Cement Ratio = 0.43 for concrete grade M35  Select Water Content = 172 Kg  (From IS: 10262 for 20 mm nominal size of aggregates Maximum Water Content = 186 Kg/m 3 ) Hence, Cement Content= 172 / 0.43 = 400 Kg /m 3  Formula for Mix Proportion of Fine and Coarse Aggregate:  1000(1-a 0 )= {(Cement Content / Sp. Gr. Of Cement) + Water Content +(F a / Sp. Gr.* P f )} 1000(1- a 0 )= {(Cement Content / Sp. Gr. Of Cement) + Water Content +C a / Sp. Gr.* Pc )}  Where  C a = Coarse Aggregate Content  F a = Fine Aggregate Content  P f = Sand Content as percentage of total Aggregates = 0.36  P c = Coarse Aggregate Content as percentage of total Aggregates.  = 0.64  a 0 = Percentage air content in concrete (As per IS :10262 for 20 mm nominal size of  aggregates air content is 2 %) = 0.02  Hence, 1000(1-0.02) = {(400 /3.15) + 172 +(F a / 2.62 x 0.36)}  Fa = 642 Kg/ Cum  As the sand is of Zone II no adjustment is required for sand.  Sand Content = 642 Kg/ Cum  1000(1-0.02)= {(400 /3.15) + 172 +(C a / 2.67 x 0.64)}  Hence, Ca = 1165 Kg/ Cum
  • 29. Prestressing jack  For prestressing, mono strand stressing jack is used and pressure is applied in a controlled way with the help of prestressing power pack. Initially, a gradual pressure of about 5 kg/cm 2 is applied.  anchorage bursting when prestressing is applied and also to check anchorage slip. The perimeter of the rod is then marked with paint and then once the anchorage is known to be stable, the pressure is increasing up to 430 kg/cm 2 .
  • 31. Grouting  Grouting is done with the help of grout pump. The mixture of cement, water and admixtures must be done under a strict mixing time and velocity control and must not contain lumps nor any air bubbles during injection into the ducts
  • 32. EQUIPMENTS :-  T6Z-08 Air Powered Grout Pump  Pumps cement grout only, no sand. 32 Gallon Mixing Tank. Mixes up to 2 sacks of material at once and allows for grout to be pumped during mixing or mixed without pumping. Approximate size 50" long 30.5" high 52" wide Weight 560 lbs. Production Rate 8 gallons per minute at 150 psi
  • 33. ADVANTAGES OF POST-TENSIONING • Longer clear spans • Thinner slabs • Lesser floor-to-floor heights • Shorter building height • Lesser weight • Improved seismic performance • Faster construction cycle
  • 34. Conclusions  Prestressed concrete offers great technical advantages in comparison with other forms of construction such as reinforced concrete and steel. They possess improved resistance to shearing forces, due to the effect of compressive prestress, which reduces the principles tensile stress  Prestressing of concrete helps in improving the ability of the material for energy absorption under impact loads. The economy of prestressed concrete is well established for long span structures. Standardized precast bridge beams between 10m and 30 m long and precast prestressed piles have proved to be more economical than steel and reinforced concrete.  Due to utilization of concrete in the tension zone, an extra saving of 15 to 30% in concrete is possible in comparison with reinforced concrete