SlideShare une entreprise Scribd logo
1  sur  3
Télécharger pour lire hors ligne
Daily Progress Report for 2-7-11                                                          Page 1 of 3



Daily Progress Report for 2-7-11
Whelan, Joseph
to:
Arlene Kabei, Steve Armann, Rich Vaille, Stephen Tyahla, Bret Moxley, Andrew Helmlinger, Steve
Wall, Katherine Baylor, stuart.yamada, Steven.chang, alec.wong
02/07/2011 07:21 PM
Show Details

Greetings all.

    Please find below the daily progress report on work items contained within the recently approved
AOC.

ACTIONS PERFORMED AND DEVELOPMENTS ANTICIPATED

     Cell 6 assessment:

                                               1) The south portion of the west side assessment of
                                               cell E6 is ongoing. The operations layer of protective
                                               stone located above the anchor trench has been
                                               removed to allow the liner material to be further
                                               investigated. Rains on Sunday kept the liner crew
                                               from re-installing the liner in this area within the
                                               anchor trench. This work will be addressed on
                                               Wednesday, weather permitting. A temporary fill
                                               road was placed to allow an excavator to remove over
                                               burden from the storm in order to access the side wall
                                               liner, which was exposed Friday and Saturday.
                                               Operations layer sand will be placed on Wednesday.


     Western Storm water Diversion Project (to render functional):

                                               1) Diversion Structure: The contractor closed all
                                               remaining forms in anticipation of the final wall pour
                                               on February 8th. Sunday rains prevented work in this
                                               area on Monday due to muddy conditions.

                                               2) Box Culvert: The contractor completed pouring
                                               the channel invert on Friday. This weeks efforts will
                                               concentrate on forming the transition structure from
                                               box culvert invert to pipe invert.

                                                3) Pipe: The contractor completed laying the Hobas
                                               Pipe on Friday, and completed pressure testing the
                                               joints of placed pipe. Backfilling of the pipe trench
                                               will continue thru this week.




file://C:Documents and SettingsstyahlaLocal SettingsTempnotesBAAA25~web5203.htm        2/8/2011
Daily Progress Report for 2-7-11                                                                Page 2 of 3



     Cell 6 Leachate Riser Restoration:

                                                         We anticipate Cell E6 riser connections to
                                                      commence on Tuesday and Wednesday.

                                                      2) The contractor removed 2500 gallons of mud and
                                                      water mixture from the area south of Cell E6 today,
                                                      and placed into frac tanks in order to allow them to
                                                      separate. These activities are ongoing. Rain all day
                                                      Sunday hampered removal activity in this area.


     Sediment Basin:

1) The contractor pumped 24,700 gallons of storm water from the sedimentation basin today,
which was sent to the WWTP for treatment and disposal. These activities are ongoing.

     Evaluating possible hydraulic head below liner system:

1) Per the work plan submitted to EPA on 2/1/2011, we have drilled to depth at temporary
piezometer locations PZ 5 and PZ 6. No water was encountered at any time during the drilling. Since
no water was observed, temporary piezometers were not installed.

ANALYTICAL DATA RECEIVED DURING REPORTING PERIOD None

ANTICIPATED PROBLEMS AND PLANNED RESOLUTIONS –– None

Please let me know if you have any questions.

Best regards,

Joe Whelan

General Manager

Waste Management of Hawaii

808-668-2985, ext. 15 Office

808-668-1366 Fax

808-479-4610 Mobile

Waste Management's landfills provide over 17,000 acres of
protected land for wildlife habitats and 15 landfills are certified
by the Wildlife Habitat Council.




file://C:Documents and SettingsstyahlaLocal SettingsTempnotesBAAA25~web5203.htm             2/8/2011
Daily Progress Report for 2-7-11                                                        Page 3 of 3




Waste Management recycles enough paper every year to save 41 million trees. Please
recycle any printed emails.




file://C:Documents and SettingsstyahlaLocal SettingsTempnotesBAAA25~web5203.htm     2/8/2011

Contenu connexe

Tendances

Feb. 15 Waste Management Daily Progress Report
Feb. 15 Waste Management Daily Progress Report Feb. 15 Waste Management Daily Progress Report
Feb. 15 Waste Management Daily Progress Report
Honolulu Civil Beat
 
Feb. 18 Waste Management Daily Progress Report
Feb. 18 Waste Management Daily Progress ReportFeb. 18 Waste Management Daily Progress Report
Feb. 18 Waste Management Daily Progress Report
Honolulu Civil Beat
 
Feb. 15 waste management daily progress report
Feb. 15 waste management daily progress reportFeb. 15 waste management daily progress report
Feb. 15 waste management daily progress report
Honolulu Civil Beat
 
Project Description - Riverside High School
Project Description - Riverside High SchoolProject Description - Riverside High School
Project Description - Riverside High School
Jahonn Naimi
 

Tendances (14)

Feb. 15 Waste Management Daily Progress Report
Feb. 15 Waste Management Daily Progress Report Feb. 15 Waste Management Daily Progress Report
Feb. 15 Waste Management Daily Progress Report
 
Feb. 18 Waste Management Daily Progress Report
Feb. 18 Waste Management Daily Progress ReportFeb. 18 Waste Management Daily Progress Report
Feb. 18 Waste Management Daily Progress Report
 
Feb. 15 waste management daily progress report
Feb. 15 waste management daily progress reportFeb. 15 waste management daily progress report
Feb. 15 waste management daily progress report
 
Lanchkhuti City / Lashis Gele RC Tank (500m3)
Lanchkhuti City / Lashis Gele RC Tank (500m3)Lanchkhuti City / Lashis Gele RC Tank (500m3)
Lanchkhuti City / Lashis Gele RC Tank (500m3)
 
Turnkey total swimming pool refurbishment project to prestigious school in th...
Turnkey total swimming pool refurbishment project to prestigious school in th...Turnkey total swimming pool refurbishment project to prestigious school in th...
Turnkey total swimming pool refurbishment project to prestigious school in th...
 
Launcelot Way Project Completion
Launcelot Way Project CompletionLauncelot Way Project Completion
Launcelot Way Project Completion
 
SFPR-Project-Profile_0
SFPR-Project-Profile_0SFPR-Project-Profile_0
SFPR-Project-Profile_0
 
Dead Run Drive Outfall Restoration
Dead Run Drive Outfall RestorationDead Run Drive Outfall Restoration
Dead Run Drive Outfall Restoration
 
Quay failure in barcelona harbour
Quay failure in barcelona harbourQuay failure in barcelona harbour
Quay failure in barcelona harbour
 
Energy Piles® Datasheet
Energy Piles® DatasheetEnergy Piles® Datasheet
Energy Piles® Datasheet
 
H&L Remediation 2011
H&L Remediation 2011H&L Remediation 2011
H&L Remediation 2011
 
Project Description - Riverside High School
Project Description - Riverside High SchoolProject Description - Riverside High School
Project Description - Riverside High School
 
Escravos
EscravosEscravos
Escravos
 
A4 Long CV
A4 Long CVA4 Long CV
A4 Long CV
 

En vedette

En vedette (9)

Sister City Program
Sister City ProgramSister City Program
Sister City Program
 
JavaScript aussi sur le serveur et jusque dans le cloud?
JavaScript aussi sur le serveur et jusque dans le cloud?JavaScript aussi sur le serveur et jusque dans le cloud?
JavaScript aussi sur le serveur et jusque dans le cloud?
 
2010 12-11 thru2011-01-11
2010 12-11 thru2011-01-112010 12-11 thru2011-01-11
2010 12-11 thru2011-01-11
 
Matayoshi contract 062111
Matayoshi contract 062111Matayoshi contract 062111
Matayoshi contract 062111
 
2011 01-28
2011 01-282011 01-28
2011 01-28
 
Hsta complaint
Hsta complaintHsta complaint
Hsta complaint
 
Uwp + Xamarin : Du nouveau en terre du milieu
Uwp + Xamarin : Du nouveau en terre du milieuUwp + Xamarin : Du nouveau en terre du milieu
Uwp + Xamarin : Du nouveau en terre du milieu
 
Techniques d’accélération des pages Web
Techniques d’accélération des pages WebTechniques d’accélération des pages Web
Techniques d’accélération des pages Web
 
Comment Microsoft gère la sécurité de ses offres de Cloud public
Comment Microsoft gère la sécurité de ses offres de Cloud publicComment Microsoft gère la sécurité de ses offres de Cloud public
Comment Microsoft gère la sécurité de ses offres de Cloud public
 

Similaire à 020711 wgsl daily progress report aoc

Feb. 9 waste management progress report
Feb. 9 waste management progress reportFeb. 9 waste management progress report
Feb. 9 waste management progress report
Honolulu Civil Beat
 
Jan. 31: Waste Management Daily Report
Jan. 31: Waste Management Daily ReportJan. 31: Waste Management Daily Report
Jan. 31: Waste Management Daily Report
Honolulu Civil Beat
 
Feb. 10 Waste Management Daily Progress Report
Feb. 10 Waste Management Daily Progress ReportFeb. 10 Waste Management Daily Progress Report
Feb. 10 Waste Management Daily Progress Report
Honolulu Civil Beat
 
Feb. 14 Waste Management Daily Progress Report
Feb. 14 Waste Management Daily Progress ReportFeb. 14 Waste Management Daily Progress Report
Feb. 14 Waste Management Daily Progress Report
Honolulu Civil Beat
 
Feb. 28 Waste Management Daily Progress Report
Feb. 28 Waste Management Daily Progress Report Feb. 28 Waste Management Daily Progress Report
Feb. 28 Waste Management Daily Progress Report
Honolulu Civil Beat
 
Feb. 25 Waste Management Daily Progress Report
Feb. 25 Waste Management Daily Progress ReportFeb. 25 Waste Management Daily Progress Report
Feb. 25 Waste Management Daily Progress Report
Honolulu Civil Beat
 
Jan. 28: Waste Management Daily Progress Report
Jan. 28: Waste Management Daily Progress ReportJan. 28: Waste Management Daily Progress Report
Jan. 28: Waste Management Daily Progress Report
Honolulu Civil Beat
 
March 3, 2011 Waste Management Daily Progress Report
March 3, 2011 Waste Management Daily Progress ReportMarch 3, 2011 Waste Management Daily Progress Report
March 3, 2011 Waste Management Daily Progress Report
Honolulu Civil Beat
 
Feb. 21 Waste Management Daily Progress Report
Feb. 21 Waste Management Daily Progress ReportFeb. 21 Waste Management Daily Progress Report
Feb. 21 Waste Management Daily Progress Report
Honolulu Civil Beat
 
Feb. 11 waste management daily progress report
Feb. 11 waste management daily progress reportFeb. 11 waste management daily progress report
Feb. 11 waste management daily progress report
Honolulu Civil Beat
 
Jan. 27: Waste Management Daily Report
Jan. 27: Waste Management Daily ReportJan. 27: Waste Management Daily Report
Jan. 27: Waste Management Daily Report
Honolulu Civil Beat
 
March 7 Waste Management Daily Progress Report
March 7 Waste Management Daily Progress ReportMarch 7 Waste Management Daily Progress Report
March 7 Waste Management Daily Progress Report
Honolulu Civil Beat
 
Jan 26 Report Cell E6 and E4 Repair
Jan 26 Report Cell E6 and E4 RepairJan 26 Report Cell E6 and E4 Repair
Jan 26 Report Cell E6 and E4 Repair
Honolulu Civil Beat
 
20220817 Presentation wapda.pptx
20220817 Presentation wapda.pptx20220817 Presentation wapda.pptx
20220817 Presentation wapda.pptx
AmirShafiq25
 
UKWP Case study - Mauchline Final copy 23 06 15
UKWP Case study - Mauchline Final copy 23 06 15UKWP Case study - Mauchline Final copy 23 06 15
UKWP Case study - Mauchline Final copy 23 06 15
ADAM DUKE
 
Jan 26 Waimanalo Gulch Storm Water Contingency Plan
Jan 26 Waimanalo Gulch Storm Water Contingency PlanJan 26 Waimanalo Gulch Storm Water Contingency Plan
Jan 26 Waimanalo Gulch Storm Water Contingency Plan
Honolulu Civil Beat
 

Similaire à 020711 wgsl daily progress report aoc (20)

Feb. 9 waste management progress report
Feb. 9 waste management progress reportFeb. 9 waste management progress report
Feb. 9 waste management progress report
 
Jan. 31: Waste Management Daily Report
Jan. 31: Waste Management Daily ReportJan. 31: Waste Management Daily Report
Jan. 31: Waste Management Daily Report
 
Feb. 10 Waste Management Daily Progress Report
Feb. 10 Waste Management Daily Progress ReportFeb. 10 Waste Management Daily Progress Report
Feb. 10 Waste Management Daily Progress Report
 
Feb. 14 Waste Management Daily Progress Report
Feb. 14 Waste Management Daily Progress ReportFeb. 14 Waste Management Daily Progress Report
Feb. 14 Waste Management Daily Progress Report
 
Feb. 28 Waste Management Daily Progress Report
Feb. 28 Waste Management Daily Progress Report Feb. 28 Waste Management Daily Progress Report
Feb. 28 Waste Management Daily Progress Report
 
Feb. 25 Waste Management Daily Progress Report
Feb. 25 Waste Management Daily Progress ReportFeb. 25 Waste Management Daily Progress Report
Feb. 25 Waste Management Daily Progress Report
 
Jan. 28: Waste Management Daily Progress Report
Jan. 28: Waste Management Daily Progress ReportJan. 28: Waste Management Daily Progress Report
Jan. 28: Waste Management Daily Progress Report
 
March 3, 2011 Waste Management Daily Progress Report
March 3, 2011 Waste Management Daily Progress ReportMarch 3, 2011 Waste Management Daily Progress Report
March 3, 2011 Waste Management Daily Progress Report
 
Feb. 21 Waste Management Daily Progress Report
Feb. 21 Waste Management Daily Progress ReportFeb. 21 Waste Management Daily Progress Report
Feb. 21 Waste Management Daily Progress Report
 
Feb. 11 waste management daily progress report
Feb. 11 waste management daily progress reportFeb. 11 waste management daily progress report
Feb. 11 waste management daily progress report
 
Jan. 27: Waste Management Daily Report
Jan. 27: Waste Management Daily ReportJan. 27: Waste Management Daily Report
Jan. 27: Waste Management Daily Report
 
March 7 Waste Management Daily Progress Report
March 7 Waste Management Daily Progress ReportMarch 7 Waste Management Daily Progress Report
March 7 Waste Management Daily Progress Report
 
Jan 26 Report Cell E6 and E4 Repair
Jan 26 Report Cell E6 and E4 RepairJan 26 Report Cell E6 and E4 Repair
Jan 26 Report Cell E6 and E4 Repair
 
Stone Mill Court Project Completion
Stone Mill Court Project CompletionStone Mill Court Project Completion
Stone Mill Court Project Completion
 
Project Analysis - PPT
Project Analysis - PPTProject Analysis - PPT
Project Analysis - PPT
 
20220817 Presentation wapda.pptx
20220817 Presentation wapda.pptx20220817 Presentation wapda.pptx
20220817 Presentation wapda.pptx
 
UKWP Case study - Mauchline Final copy 23 06 15
UKWP Case study - Mauchline Final copy 23 06 15UKWP Case study - Mauchline Final copy 23 06 15
UKWP Case study - Mauchline Final copy 23 06 15
 
South Jetty
South JettySouth Jetty
South Jetty
 
Pohick Stream Stabilization Phase II - Areas 2 and 3
Pohick Stream Stabilization Phase II - Areas 2 and 3Pohick Stream Stabilization Phase II - Areas 2 and 3
Pohick Stream Stabilization Phase II - Areas 2 and 3
 
Jan 26 Waimanalo Gulch Storm Water Contingency Plan
Jan 26 Waimanalo Gulch Storm Water Contingency PlanJan 26 Waimanalo Gulch Storm Water Contingency Plan
Jan 26 Waimanalo Gulch Storm Water Contingency Plan
 

Plus de Honolulu Civil Beat

Plus de Honolulu Civil Beat (20)

Gov. David Ige response to U.S. Rep. Anna Eshoo
Gov. David Ige response to U.S. Rep. Anna EshooGov. David Ige response to U.S. Rep. Anna Eshoo
Gov. David Ige response to U.S. Rep. Anna Eshoo
 
Audit of the Department of the Honolulu Prosecuting Attorney’s Policies, Proc...
Audit of the Department of the Honolulu Prosecuting Attorney’s Policies, Proc...Audit of the Department of the Honolulu Prosecuting Attorney’s Policies, Proc...
Audit of the Department of the Honolulu Prosecuting Attorney’s Policies, Proc...
 
Audit of the Honolulu Police Department’s Policies, Procedures, and Controls
Audit of the Honolulu Police Department’s Policies, Procedures, and ControlsAudit of the Honolulu Police Department’s Policies, Procedures, and Controls
Audit of the Honolulu Police Department’s Policies, Procedures, and Controls
 
2019 Use of Force Annual Report HPD
2019 Use of Force Annual Report HPD 2019 Use of Force Annual Report HPD
2019 Use of Force Annual Report HPD
 
Office of Health Equity Goals Draft 10
Office of Health Equity Goals Draft 10Office of Health Equity Goals Draft 10
Office of Health Equity Goals Draft 10
 
NHPI COVID-19 Statement
NHPI COVID-19 StatementNHPI COVID-19 Statement
NHPI COVID-19 Statement
 
DLIR Response Language Access
DLIR Response Language AccessDLIR Response Language Access
DLIR Response Language Access
 
Language Access Letter To DLIR
Language Access Letter To DLIRLanguage Access Letter To DLIR
Language Access Letter To DLIR
 
ACLU Letter to HPD regarding racial profiling
ACLU Letter to HPD regarding racial profilingACLU Letter to HPD regarding racial profiling
ACLU Letter to HPD regarding racial profiling
 
ACLU Letter to HPD regarding racial profiling
ACLU Letter to HPD regarding racial profilingACLU Letter to HPD regarding racial profiling
ACLU Letter to HPD regarding racial profiling
 
Jane Doe v. Rehab Hospital
Jane Doe v. Rehab HospitalJane Doe v. Rehab Hospital
Jane Doe v. Rehab Hospital
 
Coronavirus HPHA
Coronavirus HPHA Coronavirus HPHA
Coronavirus HPHA
 
OHA Data Request
OHA Data RequestOHA Data Request
OHA Data Request
 
Letter from Palau to Guam
Letter from Palau to GuamLetter from Palau to Guam
Letter from Palau to Guam
 
Guam Governor's Letter to Pence
Guam Governor's Letter to Pence Guam Governor's Letter to Pence
Guam Governor's Letter to Pence
 
OHA Analysis by Akina
OHA Analysis by AkinaOHA Analysis by Akina
OHA Analysis by Akina
 
Case COFA Letter
Case COFA LetterCase COFA Letter
Case COFA Letter
 
List Of Pro Bono Legal Service Providers
List Of Pro Bono Legal Service ProvidersList Of Pro Bono Legal Service Providers
List Of Pro Bono Legal Service Providers
 
Arbitration Hearing Transcript December 2018
Arbitration Hearing Transcript December 2018Arbitration Hearing Transcript December 2018
Arbitration Hearing Transcript December 2018
 
Caldwell Press Release
Caldwell Press ReleaseCaldwell Press Release
Caldwell Press Release
 

020711 wgsl daily progress report aoc

  • 1. Daily Progress Report for 2-7-11 Page 1 of 3 Daily Progress Report for 2-7-11 Whelan, Joseph to: Arlene Kabei, Steve Armann, Rich Vaille, Stephen Tyahla, Bret Moxley, Andrew Helmlinger, Steve Wall, Katherine Baylor, stuart.yamada, Steven.chang, alec.wong 02/07/2011 07:21 PM Show Details Greetings all. Please find below the daily progress report on work items contained within the recently approved AOC. ACTIONS PERFORMED AND DEVELOPMENTS ANTICIPATED Cell 6 assessment: 1) The south portion of the west side assessment of cell E6 is ongoing. The operations layer of protective stone located above the anchor trench has been removed to allow the liner material to be further investigated. Rains on Sunday kept the liner crew from re-installing the liner in this area within the anchor trench. This work will be addressed on Wednesday, weather permitting. A temporary fill road was placed to allow an excavator to remove over burden from the storm in order to access the side wall liner, which was exposed Friday and Saturday. Operations layer sand will be placed on Wednesday. Western Storm water Diversion Project (to render functional): 1) Diversion Structure: The contractor closed all remaining forms in anticipation of the final wall pour on February 8th. Sunday rains prevented work in this area on Monday due to muddy conditions. 2) Box Culvert: The contractor completed pouring the channel invert on Friday. This weeks efforts will concentrate on forming the transition structure from box culvert invert to pipe invert. 3) Pipe: The contractor completed laying the Hobas Pipe on Friday, and completed pressure testing the joints of placed pipe. Backfilling of the pipe trench will continue thru this week. file://C:Documents and SettingsstyahlaLocal SettingsTempnotesBAAA25~web5203.htm 2/8/2011
  • 2. Daily Progress Report for 2-7-11 Page 2 of 3 Cell 6 Leachate Riser Restoration: We anticipate Cell E6 riser connections to commence on Tuesday and Wednesday. 2) The contractor removed 2500 gallons of mud and water mixture from the area south of Cell E6 today, and placed into frac tanks in order to allow them to separate. These activities are ongoing. Rain all day Sunday hampered removal activity in this area. Sediment Basin: 1) The contractor pumped 24,700 gallons of storm water from the sedimentation basin today, which was sent to the WWTP for treatment and disposal. These activities are ongoing. Evaluating possible hydraulic head below liner system: 1) Per the work plan submitted to EPA on 2/1/2011, we have drilled to depth at temporary piezometer locations PZ 5 and PZ 6. No water was encountered at any time during the drilling. Since no water was observed, temporary piezometers were not installed. ANALYTICAL DATA RECEIVED DURING REPORTING PERIOD None ANTICIPATED PROBLEMS AND PLANNED RESOLUTIONS –– None Please let me know if you have any questions. Best regards, Joe Whelan General Manager Waste Management of Hawaii 808-668-2985, ext. 15 Office 808-668-1366 Fax 808-479-4610 Mobile Waste Management's landfills provide over 17,000 acres of protected land for wildlife habitats and 15 landfills are certified by the Wildlife Habitat Council. file://C:Documents and SettingsstyahlaLocal SettingsTempnotesBAAA25~web5203.htm 2/8/2011
  • 3. Daily Progress Report for 2-7-11 Page 3 of 3 Waste Management recycles enough paper every year to save 41 million trees. Please recycle any printed emails. file://C:Documents and SettingsstyahlaLocal SettingsTempnotesBAAA25~web5203.htm 2/8/2011