SlideShare une entreprise Scribd logo
1  sur  3
Télécharger pour lire hors ligne
Page 1 of 3



Daily Progress Report for February 28, 2011
Whelan, Joseph
to:
Arlene Kabei, Steve Armann, Rich Vaille, Stephen Tyahla, Bret Moxley, Andrew Helmlinger, Steve
Wall, 'stuart.yamada@doh.hawaii.gov', 'Steven.chang@doh.hawaii.gov', 'alec.wong@doh.hawaii.gov'
02/28/2011 07:02 PM
Show Details

  
Greetings all. 
    Please find below the daily progress report on work items contained within the recently approved 
AOC.   
ACTIONS PERFORMED AND DEVELOPMENTS ANTICIPATED 
     Cell 6 Assessment: 
                             1. The QCA report documenting the evaluation and repair of the 
                                southwestern portion of the E6 liner system was submitted February 
                                25, 2011.  Approval to resume operations in this area is pending.  
                                  
                             2. The northwest section of the Cell E6 liner was also damaged in the 
                                January 13, 2011 storm.  This area is located directly below the 
                                section of the storm water diversion system where the open box 
                                culvert ties into the Hobas pipe.  Consequently, any rock and soil 
                                material generated from the construction of the diversion system in 
                                this area must be removed prior to the evaluation and repair of the 
                                liner.  This removal activity is ongoing and is expected to be 
                                completed within the next 2‐3 weeks, weather permitting.   
                                   
     Western Storm water Diversion Project (to render functional): 
                             1)  Diversion Structure:   The final wall section of the diversion structure is 
                             now in place.    
                             2)  Box Culvert:   The contractor has completed forming the transition 
                             structure from box culvert invert to pipe invert. This is scheduled to be 
                             poured next     week.  Rebar work on box culvert walls is ongoing.    
                             3)  Pipe:   Backfilling of the HOBAS pipe channel is now complete. 
                             4)  The diversion structure is functionally complete per the terms of 
                             Section 19.b. of the AOC. 
     Cell 6 Leachate Riser Restoration: 
                              1. 105,300 gallons was pumped from the Cell E6 leachate riser storage
                                 tank since Friday and transported to the waste water treatment plant.  
                                   
                              2. 33,200 gallons of water was pumped from the south pond area since
                                 Friday and transported to the local waste water treatment plant.  




file://C:Documents and SettingsstyahlaLocal SettingsTempnotesBAAA25~web6262.htm              3/1/2011
Page 2 of 3



           
                                      
                                3. 30,772 gallons of mud/water was pumped from the south pond area
                                   since Friday and placed within the onsite separation tanks.  
      Sediment Basin: 
                                1. Daily showers earlier this week have prevented removal of silt/rock 
                                   material from the northern portion of the sedimentation basin.   
                                      
                                2. The contractor pumped 8,700 gallons of storm water from the
                                   sedimentation basin since Friday and transported to the waste water
                                   treatment plant.  
        Evaluating possible hydraulic head below liner system: 
                                1. Per the work plan submitted to EPA on 2/1/2011, we have drilled to 
                                   depth at temporary piezometer locations PZ‐1, PZ‐5 and PZ‐6.  No 
                                   water was encountered  during the drilling process. Since no water 
                                   was observed, temporary piezometers were not installed.   The 
                                   documentation report was submitted on February 25, 2011.   
      Beach Assessment Update: 
                                1. The daily beach assessment phase of this task is complete. There were
                                   no calls received at the established beach waste siting hot line today.  
  
ANALYTICAL DATA RECEIVED DURING REPORTING PERIOD ‐ None 
ANTICIPATED PROBLEMS AND PLANNED RESOLUTIONS – None 
Please let me know if you have any questions.    
  
Best regards, 
  
  
Joe Whelan 
  
General Manager 
Waste Management of Hawaii 
808‐668‐2985, ext. 15 Office 
808‐668‐1366 Fax 
808‐479‐4610 Mobile 
  
Waste Management's landfills provide over 17,000 acres of
protected land for wildlife habitats and 15 landfills are certified
by the Wildlife Habitat Council.  

  
  
  




file://C:Documents and SettingsstyahlaLocal SettingsTempnotesBAAA25~web6262.htm              3/1/2011
Page 3 of 3



Waste Management recycles enough paper every year to save 41 million trees. Please
recycle any printed emails.




file://C:Documents and SettingsstyahlaLocal SettingsTempnotesBAAA25~web6262.htm     3/1/2011

Contenu connexe

Tendances

Feb. 3: Waste Management Progress Report
Feb. 3: Waste Management Progress ReportFeb. 3: Waste Management Progress Report
Feb. 3: Waste Management Progress ReportHonolulu Civil Beat
 
Feb. 21 Waste Management Daily Progress Report
Feb. 21 Waste Management Daily Progress ReportFeb. 21 Waste Management Daily Progress Report
Feb. 21 Waste Management Daily Progress ReportHonolulu Civil Beat
 
Feb. 2: Waste Management Daily Report
Feb. 2: Waste Management Daily ReportFeb. 2: Waste Management Daily Report
Feb. 2: Waste Management Daily ReportHonolulu Civil Beat
 
Feb. 1: Waste Management Daily Report
Feb. 1: Waste Management Daily ReportFeb. 1: Waste Management Daily Report
Feb. 1: Waste Management Daily ReportHonolulu Civil Beat
 
Feb. 4: Waste Management Progress Report
Feb. 4: Waste Management Progress ReportFeb. 4: Waste Management Progress Report
Feb. 4: Waste Management Progress ReportHonolulu Civil Beat
 
Feb. 8: Waste Management Progress Report
Feb. 8: Waste Management Progress ReportFeb. 8: Waste Management Progress Report
Feb. 8: Waste Management Progress ReportHonolulu Civil Beat
 
March 7 Waste Management Daily Progress Report
March 7 Waste Management Daily Progress ReportMarch 7 Waste Management Daily Progress Report
March 7 Waste Management Daily Progress ReportHonolulu Civil Beat
 
Feb. 14 Waste Management Daily Progress Report
Feb. 14 Waste Management Daily Progress ReportFeb. 14 Waste Management Daily Progress Report
Feb. 14 Waste Management Daily Progress ReportHonolulu Civil Beat
 
Jan. 31: Waste Management Daily Report
Jan. 31: Waste Management Daily ReportJan. 31: Waste Management Daily Report
Jan. 31: Waste Management Daily ReportHonolulu Civil Beat
 
020711 wgsl daily progress report aoc
020711 wgsl daily progress report aoc020711 wgsl daily progress report aoc
020711 wgsl daily progress report aocHonolulu Civil Beat
 
Feb. 9 waste management progress report
Feb. 9 waste management progress reportFeb. 9 waste management progress report
Feb. 9 waste management progress reportHonolulu Civil Beat
 
Jan. 28: Waste Management Daily Progress Report
Jan. 28: Waste Management Daily Progress ReportJan. 28: Waste Management Daily Progress Report
Jan. 28: Waste Management Daily Progress ReportHonolulu Civil Beat
 
Lenox Drive Outfall Restoration
Lenox Drive Outfall RestorationLenox Drive Outfall Restoration
Lenox Drive Outfall RestorationFairfax County
 
DRBC Docket: XTO Energy Application to Withdraw Surface Water at Oquaga Creek
DRBC Docket: XTO Energy Application to Withdraw Surface Water at Oquaga CreekDRBC Docket: XTO Energy Application to Withdraw Surface Water at Oquaga Creek
DRBC Docket: XTO Energy Application to Withdraw Surface Water at Oquaga CreekMarcellus Drilling News
 
Woodglen Lake Dredging and Restoration
Woodglen Lake Dredging and RestorationWoodglen Lake Dredging and Restoration
Woodglen Lake Dredging and RestorationFairfax County
 
Nottoway Park Stormwater and Water Quality Improvements Phases 1, 2, & 3
Nottoway Park Stormwater and Water Quality Improvements Phases 1, 2, & 3Nottoway Park Stormwater and Water Quality Improvements Phases 1, 2, & 3
Nottoway Park Stormwater and Water Quality Improvements Phases 1, 2, & 3Fairfax County
 
SLIPP All-Committee Meeting: Shoreline Update 12-April-2012
SLIPP All-Committee Meeting: Shoreline Update 12-April-2012SLIPP All-Committee Meeting: Shoreline Update 12-April-2012
SLIPP All-Committee Meeting: Shoreline Update 12-April-2012Erin Vieira
 
Woodglen Lake Dredging and Restoration
Woodglen Lake Dredging and Restoration Woodglen Lake Dredging and Restoration
Woodglen Lake Dredging and Restoration Fairfax County
 
Pohick Creek Watershed: Dam Rehabilitation Dredging and Lake Restoration
Pohick Creek Watershed: Dam Rehabilitation Dredging and Lake RestorationPohick Creek Watershed: Dam Rehabilitation Dredging and Lake Restoration
Pohick Creek Watershed: Dam Rehabilitation Dredging and Lake RestorationFairfax County
 

Tendances (20)

Feb. 3: Waste Management Progress Report
Feb. 3: Waste Management Progress ReportFeb. 3: Waste Management Progress Report
Feb. 3: Waste Management Progress Report
 
Feb. 21 Waste Management Daily Progress Report
Feb. 21 Waste Management Daily Progress ReportFeb. 21 Waste Management Daily Progress Report
Feb. 21 Waste Management Daily Progress Report
 
Feb. 2: Waste Management Daily Report
Feb. 2: Waste Management Daily ReportFeb. 2: Waste Management Daily Report
Feb. 2: Waste Management Daily Report
 
Feb. 1: Waste Management Daily Report
Feb. 1: Waste Management Daily ReportFeb. 1: Waste Management Daily Report
Feb. 1: Waste Management Daily Report
 
Feb. 4: Waste Management Progress Report
Feb. 4: Waste Management Progress ReportFeb. 4: Waste Management Progress Report
Feb. 4: Waste Management Progress Report
 
Feb. 8: Waste Management Progress Report
Feb. 8: Waste Management Progress ReportFeb. 8: Waste Management Progress Report
Feb. 8: Waste Management Progress Report
 
March 7 Waste Management Daily Progress Report
March 7 Waste Management Daily Progress ReportMarch 7 Waste Management Daily Progress Report
March 7 Waste Management Daily Progress Report
 
Feb. 14 Waste Management Daily Progress Report
Feb. 14 Waste Management Daily Progress ReportFeb. 14 Waste Management Daily Progress Report
Feb. 14 Waste Management Daily Progress Report
 
Jan. 31: Waste Management Daily Report
Jan. 31: Waste Management Daily ReportJan. 31: Waste Management Daily Report
Jan. 31: Waste Management Daily Report
 
020711 wgsl daily progress report aoc
020711 wgsl daily progress report aoc020711 wgsl daily progress report aoc
020711 wgsl daily progress report aoc
 
Feb. 9 waste management progress report
Feb. 9 waste management progress reportFeb. 9 waste management progress report
Feb. 9 waste management progress report
 
Jan. 28: Waste Management Daily Progress Report
Jan. 28: Waste Management Daily Progress ReportJan. 28: Waste Management Daily Progress Report
Jan. 28: Waste Management Daily Progress Report
 
Lenox Drive Outfall Restoration
Lenox Drive Outfall RestorationLenox Drive Outfall Restoration
Lenox Drive Outfall Restoration
 
DRBC Docket: XTO Energy Application to Withdraw Surface Water at Oquaga Creek
DRBC Docket: XTO Energy Application to Withdraw Surface Water at Oquaga CreekDRBC Docket: XTO Energy Application to Withdraw Surface Water at Oquaga Creek
DRBC Docket: XTO Energy Application to Withdraw Surface Water at Oquaga Creek
 
Woodglen Lake Dredging and Restoration
Woodglen Lake Dredging and RestorationWoodglen Lake Dredging and Restoration
Woodglen Lake Dredging and Restoration
 
Nottoway Park Stormwater and Water Quality Improvements Phases 1, 2, & 3
Nottoway Park Stormwater and Water Quality Improvements Phases 1, 2, & 3Nottoway Park Stormwater and Water Quality Improvements Phases 1, 2, & 3
Nottoway Park Stormwater and Water Quality Improvements Phases 1, 2, & 3
 
SLIPP All-Committee Meeting: Shoreline Update 12-April-2012
SLIPP All-Committee Meeting: Shoreline Update 12-April-2012SLIPP All-Committee Meeting: Shoreline Update 12-April-2012
SLIPP All-Committee Meeting: Shoreline Update 12-April-2012
 
Huntington Levee
Huntington LeveeHuntington Levee
Huntington Levee
 
Woodglen Lake Dredging and Restoration
Woodglen Lake Dredging and Restoration Woodglen Lake Dredging and Restoration
Woodglen Lake Dredging and Restoration
 
Pohick Creek Watershed: Dam Rehabilitation Dredging and Lake Restoration
Pohick Creek Watershed: Dam Rehabilitation Dredging and Lake RestorationPohick Creek Watershed: Dam Rehabilitation Dredging and Lake Restoration
Pohick Creek Watershed: Dam Rehabilitation Dredging and Lake Restoration
 

En vedette

En vedette (7)

Downtown exec summary
Downtown exec summaryDowntown exec summary
Downtown exec summary
 
Geothermal ad hoc committee report
Geothermal ad hoc committee reportGeothermal ad hoc committee report
Geothermal ad hoc committee report
 
Hawaii Office of Elections Response in Nader Case
Hawaii Office of Elections Response in Nader CaseHawaii Office of Elections Response in Nader Case
Hawaii Office of Elections Response in Nader Case
 
Letter to abercrombie
Letter to abercrombieLetter to abercrombie
Letter to abercrombie
 
Summary of Proposed Changes in CD1
Summary of Proposed Changes in CD1Summary of Proposed Changes in CD1
Summary of Proposed Changes in CD1
 
Robert Godbey Disclosure
Robert Godbey DisclosureRobert Godbey Disclosure
Robert Godbey Disclosure
 
August 2011 Federal Response to Lawsuit
August 2011 Federal Response to LawsuitAugust 2011 Federal Response to Lawsuit
August 2011 Federal Response to Lawsuit
 

Similaire à Daily Progress Report on Waste Management Work Items

Feb. 11 waste management daily progress report
Feb. 11 waste management daily progress reportFeb. 11 waste management daily progress report
Feb. 11 waste management daily progress reportHonolulu Civil Beat
 
Jan. 27: Waste Management Daily Report
Jan. 27: Waste Management Daily ReportJan. 27: Waste Management Daily Report
Jan. 27: Waste Management Daily ReportHonolulu Civil Beat
 
Feb. 10 Waste Management Daily Progress Report
Feb. 10 Waste Management Daily Progress ReportFeb. 10 Waste Management Daily Progress Report
Feb. 10 Waste Management Daily Progress ReportHonolulu Civil Beat
 
Stone Mill Court Project Completion
Stone Mill Court Project CompletionStone Mill Court Project Completion
Stone Mill Court Project CompletionFairfax County
 
Jan 26 Report Cell E6 and E4 Repair
Jan 26 Report Cell E6 and E4 RepairJan 26 Report Cell E6 and E4 Repair
Jan 26 Report Cell E6 and E4 RepairHonolulu Civil Beat
 
Green Hill Estates Emergency Sewer Repair
Green Hill Estates Emergency Sewer RepairGreen Hill Estates Emergency Sewer Repair
Green Hill Estates Emergency Sewer RepairFairfax County
 
Green Hill Estates Emergency Sewer Repair
Green Hill Estates Emergency Sewer RepairGreen Hill Estates Emergency Sewer Repair
Green Hill Estates Emergency Sewer RepairFairfax County
 
Launcelot Way Project Completion
Launcelot Way Project CompletionLauncelot Way Project Completion
Launcelot Way Project CompletionFairfax County
 
Flatlick Branch Phase II Stream Restoration Project
Flatlick Branch Phase II Stream Restoration ProjectFlatlick Branch Phase II Stream Restoration Project
Flatlick Branch Phase II Stream Restoration ProjectFairfax County
 
Pohick Stream Stabilization Phase II - Areas 2 and 3
Pohick Stream Stabilization Phase II - Areas 2 and 3Pohick Stream Stabilization Phase II - Areas 2 and 3
Pohick Stream Stabilization Phase II - Areas 2 and 3Fairfax County
 
Flatlick Sewer Rehabilitation Project Phase 1 and 2
Flatlick Sewer Rehabilitation Project Phase 1 and 2Flatlick Sewer Rehabilitation Project Phase 1 and 2
Flatlick Sewer Rehabilitation Project Phase 1 and 2Fairfax County
 
Robey Avenue Outfall Restoration
Robey Avenue Outfall RestorationRobey Avenue Outfall Restoration
Robey Avenue Outfall RestorationFairfax County
 
OC harbor brook wetlands stakeholder 6 15-11 final-1
OC harbor brook wetlands stakeholder 6 15-11 final-1OC harbor brook wetlands stakeholder 6 15-11 final-1
OC harbor brook wetlands stakeholder 6 15-11 final-1Onondaga County Save the Rain
 
Crestleigh Way Outfall Restoration
Crestleigh Way Outfall RestorationCrestleigh Way Outfall Restoration
Crestleigh Way Outfall RestorationFairfax County
 
Decommissioning Fukushima 20130306
Decommissioning Fukushima 20130306Decommissioning Fukushima 20130306
Decommissioning Fukushima 20130306dinomasch
 
Range Resources Voluntary Plan to Close Yeager Wastewater Impoundment in SWPA
Range Resources Voluntary Plan to Close Yeager Wastewater Impoundment in SWPARange Resources Voluntary Plan to Close Yeager Wastewater Impoundment in SWPA
Range Resources Voluntary Plan to Close Yeager Wastewater Impoundment in SWPAMarcellus Drilling News
 

Similaire à Daily Progress Report on Waste Management Work Items (18)

Feb. 11 waste management daily progress report
Feb. 11 waste management daily progress reportFeb. 11 waste management daily progress report
Feb. 11 waste management daily progress report
 
Jan. 27: Waste Management Daily Report
Jan. 27: Waste Management Daily ReportJan. 27: Waste Management Daily Report
Jan. 27: Waste Management Daily Report
 
Feb. 10 Waste Management Daily Progress Report
Feb. 10 Waste Management Daily Progress ReportFeb. 10 Waste Management Daily Progress Report
Feb. 10 Waste Management Daily Progress Report
 
Stone Mill Court Project Completion
Stone Mill Court Project CompletionStone Mill Court Project Completion
Stone Mill Court Project Completion
 
Jan 26 Report Cell E6 and E4 Repair
Jan 26 Report Cell E6 and E4 RepairJan 26 Report Cell E6 and E4 Repair
Jan 26 Report Cell E6 and E4 Repair
 
Green Hill Estates Emergency Sewer Repair
Green Hill Estates Emergency Sewer RepairGreen Hill Estates Emergency Sewer Repair
Green Hill Estates Emergency Sewer Repair
 
Green Hill Estates Emergency Sewer Repair
Green Hill Estates Emergency Sewer RepairGreen Hill Estates Emergency Sewer Repair
Green Hill Estates Emergency Sewer Repair
 
VSL_____(3190)
VSL_____(3190)VSL_____(3190)
VSL_____(3190)
 
Launcelot Way Project Completion
Launcelot Way Project CompletionLauncelot Way Project Completion
Launcelot Way Project Completion
 
Flatlick Branch Phase II Stream Restoration Project
Flatlick Branch Phase II Stream Restoration ProjectFlatlick Branch Phase II Stream Restoration Project
Flatlick Branch Phase II Stream Restoration Project
 
Pohick Stream Stabilization Phase II - Areas 2 and 3
Pohick Stream Stabilization Phase II - Areas 2 and 3Pohick Stream Stabilization Phase II - Areas 2 and 3
Pohick Stream Stabilization Phase II - Areas 2 and 3
 
Flatlick Sewer Rehabilitation Project Phase 1 and 2
Flatlick Sewer Rehabilitation Project Phase 1 and 2Flatlick Sewer Rehabilitation Project Phase 1 and 2
Flatlick Sewer Rehabilitation Project Phase 1 and 2
 
Robey Avenue Outfall Restoration
Robey Avenue Outfall RestorationRobey Avenue Outfall Restoration
Robey Avenue Outfall Restoration
 
OC harbor brook wetlands stakeholder 6 15-11 final-1
OC harbor brook wetlands stakeholder 6 15-11 final-1OC harbor brook wetlands stakeholder 6 15-11 final-1
OC harbor brook wetlands stakeholder 6 15-11 final-1
 
SFPUC-#377404v1.PDF
SFPUC-#377404v1.PDFSFPUC-#377404v1.PDF
SFPUC-#377404v1.PDF
 
Crestleigh Way Outfall Restoration
Crestleigh Way Outfall RestorationCrestleigh Way Outfall Restoration
Crestleigh Way Outfall Restoration
 
Decommissioning Fukushima 20130306
Decommissioning Fukushima 20130306Decommissioning Fukushima 20130306
Decommissioning Fukushima 20130306
 
Range Resources Voluntary Plan to Close Yeager Wastewater Impoundment in SWPA
Range Resources Voluntary Plan to Close Yeager Wastewater Impoundment in SWPARange Resources Voluntary Plan to Close Yeager Wastewater Impoundment in SWPA
Range Resources Voluntary Plan to Close Yeager Wastewater Impoundment in SWPA
 

Plus de Honolulu Civil Beat

Gov. David Ige response to U.S. Rep. Anna Eshoo
Gov. David Ige response to U.S. Rep. Anna EshooGov. David Ige response to U.S. Rep. Anna Eshoo
Gov. David Ige response to U.S. Rep. Anna EshooHonolulu Civil Beat
 
Audit of the Department of the Honolulu Prosecuting Attorney’s Policies, Proc...
Audit of the Department of the Honolulu Prosecuting Attorney’s Policies, Proc...Audit of the Department of the Honolulu Prosecuting Attorney’s Policies, Proc...
Audit of the Department of the Honolulu Prosecuting Attorney’s Policies, Proc...Honolulu Civil Beat
 
Audit of the Honolulu Police Department’s Policies, Procedures, and Controls
Audit of the Honolulu Police Department’s Policies, Procedures, and ControlsAudit of the Honolulu Police Department’s Policies, Procedures, and Controls
Audit of the Honolulu Police Department’s Policies, Procedures, and ControlsHonolulu Civil Beat
 
2019 Use of Force Annual Report HPD
2019 Use of Force Annual Report HPD 2019 Use of Force Annual Report HPD
2019 Use of Force Annual Report HPD Honolulu Civil Beat
 
Office of Health Equity Goals Draft 10
Office of Health Equity Goals Draft 10Office of Health Equity Goals Draft 10
Office of Health Equity Goals Draft 10Honolulu Civil Beat
 
ACLU Letter to HPD regarding racial profiling
ACLU Letter to HPD regarding racial profilingACLU Letter to HPD regarding racial profiling
ACLU Letter to HPD regarding racial profilingHonolulu Civil Beat
 
ACLU Letter to HPD regarding racial profiling
ACLU Letter to HPD regarding racial profilingACLU Letter to HPD regarding racial profiling
ACLU Letter to HPD regarding racial profilingHonolulu Civil Beat
 
Guam Governor's Letter to Pence
Guam Governor's Letter to Pence Guam Governor's Letter to Pence
Guam Governor's Letter to Pence Honolulu Civil Beat
 
List Of Pro Bono Legal Service Providers
List Of Pro Bono Legal Service ProvidersList Of Pro Bono Legal Service Providers
List Of Pro Bono Legal Service ProvidersHonolulu Civil Beat
 
Arbitration Hearing Transcript December 2018
Arbitration Hearing Transcript December 2018Arbitration Hearing Transcript December 2018
Arbitration Hearing Transcript December 2018Honolulu Civil Beat
 

Plus de Honolulu Civil Beat (20)

Gov. David Ige response to U.S. Rep. Anna Eshoo
Gov. David Ige response to U.S. Rep. Anna EshooGov. David Ige response to U.S. Rep. Anna Eshoo
Gov. David Ige response to U.S. Rep. Anna Eshoo
 
Audit of the Department of the Honolulu Prosecuting Attorney’s Policies, Proc...
Audit of the Department of the Honolulu Prosecuting Attorney’s Policies, Proc...Audit of the Department of the Honolulu Prosecuting Attorney’s Policies, Proc...
Audit of the Department of the Honolulu Prosecuting Attorney’s Policies, Proc...
 
Audit of the Honolulu Police Department’s Policies, Procedures, and Controls
Audit of the Honolulu Police Department’s Policies, Procedures, and ControlsAudit of the Honolulu Police Department’s Policies, Procedures, and Controls
Audit of the Honolulu Police Department’s Policies, Procedures, and Controls
 
2019 Use of Force Annual Report HPD
2019 Use of Force Annual Report HPD 2019 Use of Force Annual Report HPD
2019 Use of Force Annual Report HPD
 
Office of Health Equity Goals Draft 10
Office of Health Equity Goals Draft 10Office of Health Equity Goals Draft 10
Office of Health Equity Goals Draft 10
 
NHPI COVID-19 Statement
NHPI COVID-19 StatementNHPI COVID-19 Statement
NHPI COVID-19 Statement
 
DLIR Response Language Access
DLIR Response Language AccessDLIR Response Language Access
DLIR Response Language Access
 
Language Access Letter To DLIR
Language Access Letter To DLIRLanguage Access Letter To DLIR
Language Access Letter To DLIR
 
ACLU Letter to HPD regarding racial profiling
ACLU Letter to HPD regarding racial profilingACLU Letter to HPD regarding racial profiling
ACLU Letter to HPD regarding racial profiling
 
ACLU Letter to HPD regarding racial profiling
ACLU Letter to HPD regarding racial profilingACLU Letter to HPD regarding racial profiling
ACLU Letter to HPD regarding racial profiling
 
Jane Doe v. Rehab Hospital
Jane Doe v. Rehab HospitalJane Doe v. Rehab Hospital
Jane Doe v. Rehab Hospital
 
Coronavirus HPHA
Coronavirus HPHA Coronavirus HPHA
Coronavirus HPHA
 
OHA Data Request
OHA Data RequestOHA Data Request
OHA Data Request
 
Letter from Palau to Guam
Letter from Palau to GuamLetter from Palau to Guam
Letter from Palau to Guam
 
Guam Governor's Letter to Pence
Guam Governor's Letter to Pence Guam Governor's Letter to Pence
Guam Governor's Letter to Pence
 
OHA Analysis by Akina
OHA Analysis by AkinaOHA Analysis by Akina
OHA Analysis by Akina
 
Case COFA Letter
Case COFA LetterCase COFA Letter
Case COFA Letter
 
List Of Pro Bono Legal Service Providers
List Of Pro Bono Legal Service ProvidersList Of Pro Bono Legal Service Providers
List Of Pro Bono Legal Service Providers
 
Arbitration Hearing Transcript December 2018
Arbitration Hearing Transcript December 2018Arbitration Hearing Transcript December 2018
Arbitration Hearing Transcript December 2018
 
Caldwell Press Release
Caldwell Press ReleaseCaldwell Press Release
Caldwell Press Release
 

Dernier

Ensuring Technical Readiness For Copilot in Microsoft 365
Ensuring Technical Readiness For Copilot in Microsoft 365Ensuring Technical Readiness For Copilot in Microsoft 365
Ensuring Technical Readiness For Copilot in Microsoft 3652toLead Limited
 
Take control of your SAP testing with UiPath Test Suite
Take control of your SAP testing with UiPath Test SuiteTake control of your SAP testing with UiPath Test Suite
Take control of your SAP testing with UiPath Test SuiteDianaGray10
 
TrustArc Webinar - How to Build Consumer Trust Through Data Privacy
TrustArc Webinar - How to Build Consumer Trust Through Data PrivacyTrustArc Webinar - How to Build Consumer Trust Through Data Privacy
TrustArc Webinar - How to Build Consumer Trust Through Data PrivacyTrustArc
 
Are Multi-Cloud and Serverless Good or Bad?
Are Multi-Cloud and Serverless Good or Bad?Are Multi-Cloud and Serverless Good or Bad?
Are Multi-Cloud and Serverless Good or Bad?Mattias Andersson
 
Nell’iperspazio con Rocket: il Framework Web di Rust!
Nell’iperspazio con Rocket: il Framework Web di Rust!Nell’iperspazio con Rocket: il Framework Web di Rust!
Nell’iperspazio con Rocket: il Framework Web di Rust!Commit University
 
Use of FIDO in the Payments and Identity Landscape: FIDO Paris Seminar.pptx
Use of FIDO in the Payments and Identity Landscape: FIDO Paris Seminar.pptxUse of FIDO in the Payments and Identity Landscape: FIDO Paris Seminar.pptx
Use of FIDO in the Payments and Identity Landscape: FIDO Paris Seminar.pptxLoriGlavin3
 
Tampa BSides - Chef's Tour of Microsoft Security Adoption Framework (SAF)
Tampa BSides - Chef's Tour of Microsoft Security Adoption Framework (SAF)Tampa BSides - Chef's Tour of Microsoft Security Adoption Framework (SAF)
Tampa BSides - Chef's Tour of Microsoft Security Adoption Framework (SAF)Mark Simos
 
"Subclassing and Composition – A Pythonic Tour of Trade-Offs", Hynek Schlawack
"Subclassing and Composition – A Pythonic Tour of Trade-Offs", Hynek Schlawack"Subclassing and Composition – A Pythonic Tour of Trade-Offs", Hynek Schlawack
"Subclassing and Composition – A Pythonic Tour of Trade-Offs", Hynek SchlawackFwdays
 
Moving Beyond Passwords: FIDO Paris Seminar.pdf
Moving Beyond Passwords: FIDO Paris Seminar.pdfMoving Beyond Passwords: FIDO Paris Seminar.pdf
Moving Beyond Passwords: FIDO Paris Seminar.pdfLoriGlavin3
 
Gen AI in Business - Global Trends Report 2024.pdf
Gen AI in Business - Global Trends Report 2024.pdfGen AI in Business - Global Trends Report 2024.pdf
Gen AI in Business - Global Trends Report 2024.pdfAddepto
 
Merck Moving Beyond Passwords: FIDO Paris Seminar.pptx
Merck Moving Beyond Passwords: FIDO Paris Seminar.pptxMerck Moving Beyond Passwords: FIDO Paris Seminar.pptx
Merck Moving Beyond Passwords: FIDO Paris Seminar.pptxLoriGlavin3
 
Unleash Your Potential - Namagunga Girls Coding Club
Unleash Your Potential - Namagunga Girls Coding ClubUnleash Your Potential - Namagunga Girls Coding Club
Unleash Your Potential - Namagunga Girls Coding ClubKalema Edgar
 
Passkey Providers and Enabling Portability: FIDO Paris Seminar.pptx
Passkey Providers and Enabling Portability: FIDO Paris Seminar.pptxPasskey Providers and Enabling Portability: FIDO Paris Seminar.pptx
Passkey Providers and Enabling Portability: FIDO Paris Seminar.pptxLoriGlavin3
 
Digital Identity is Under Attack: FIDO Paris Seminar.pptx
Digital Identity is Under Attack: FIDO Paris Seminar.pptxDigital Identity is Under Attack: FIDO Paris Seminar.pptx
Digital Identity is Under Attack: FIDO Paris Seminar.pptxLoriGlavin3
 
The Fit for Passkeys for Employee and Consumer Sign-ins: FIDO Paris Seminar.pptx
The Fit for Passkeys for Employee and Consumer Sign-ins: FIDO Paris Seminar.pptxThe Fit for Passkeys for Employee and Consumer Sign-ins: FIDO Paris Seminar.pptx
The Fit for Passkeys for Employee and Consumer Sign-ins: FIDO Paris Seminar.pptxLoriGlavin3
 
DevoxxFR 2024 Reproducible Builds with Apache Maven
DevoxxFR 2024 Reproducible Builds with Apache MavenDevoxxFR 2024 Reproducible Builds with Apache Maven
DevoxxFR 2024 Reproducible Builds with Apache MavenHervé Boutemy
 
"Debugging python applications inside k8s environment", Andrii Soldatenko
"Debugging python applications inside k8s environment", Andrii Soldatenko"Debugging python applications inside k8s environment", Andrii Soldatenko
"Debugging python applications inside k8s environment", Andrii SoldatenkoFwdays
 
How AI, OpenAI, and ChatGPT impact business and software.
How AI, OpenAI, and ChatGPT impact business and software.How AI, OpenAI, and ChatGPT impact business and software.
How AI, OpenAI, and ChatGPT impact business and software.Curtis Poe
 
Hyperautomation and AI/ML: A Strategy for Digital Transformation Success.pdf
Hyperautomation and AI/ML: A Strategy for Digital Transformation Success.pdfHyperautomation and AI/ML: A Strategy for Digital Transformation Success.pdf
Hyperautomation and AI/ML: A Strategy for Digital Transformation Success.pdfPrecisely
 
Unraveling Multimodality with Large Language Models.pdf
Unraveling Multimodality with Large Language Models.pdfUnraveling Multimodality with Large Language Models.pdf
Unraveling Multimodality with Large Language Models.pdfAlex Barbosa Coqueiro
 

Dernier (20)

Ensuring Technical Readiness For Copilot in Microsoft 365
Ensuring Technical Readiness For Copilot in Microsoft 365Ensuring Technical Readiness For Copilot in Microsoft 365
Ensuring Technical Readiness For Copilot in Microsoft 365
 
Take control of your SAP testing with UiPath Test Suite
Take control of your SAP testing with UiPath Test SuiteTake control of your SAP testing with UiPath Test Suite
Take control of your SAP testing with UiPath Test Suite
 
TrustArc Webinar - How to Build Consumer Trust Through Data Privacy
TrustArc Webinar - How to Build Consumer Trust Through Data PrivacyTrustArc Webinar - How to Build Consumer Trust Through Data Privacy
TrustArc Webinar - How to Build Consumer Trust Through Data Privacy
 
Are Multi-Cloud and Serverless Good or Bad?
Are Multi-Cloud and Serverless Good or Bad?Are Multi-Cloud and Serverless Good or Bad?
Are Multi-Cloud and Serverless Good or Bad?
 
Nell’iperspazio con Rocket: il Framework Web di Rust!
Nell’iperspazio con Rocket: il Framework Web di Rust!Nell’iperspazio con Rocket: il Framework Web di Rust!
Nell’iperspazio con Rocket: il Framework Web di Rust!
 
Use of FIDO in the Payments and Identity Landscape: FIDO Paris Seminar.pptx
Use of FIDO in the Payments and Identity Landscape: FIDO Paris Seminar.pptxUse of FIDO in the Payments and Identity Landscape: FIDO Paris Seminar.pptx
Use of FIDO in the Payments and Identity Landscape: FIDO Paris Seminar.pptx
 
Tampa BSides - Chef's Tour of Microsoft Security Adoption Framework (SAF)
Tampa BSides - Chef's Tour of Microsoft Security Adoption Framework (SAF)Tampa BSides - Chef's Tour of Microsoft Security Adoption Framework (SAF)
Tampa BSides - Chef's Tour of Microsoft Security Adoption Framework (SAF)
 
"Subclassing and Composition – A Pythonic Tour of Trade-Offs", Hynek Schlawack
"Subclassing and Composition – A Pythonic Tour of Trade-Offs", Hynek Schlawack"Subclassing and Composition – A Pythonic Tour of Trade-Offs", Hynek Schlawack
"Subclassing and Composition – A Pythonic Tour of Trade-Offs", Hynek Schlawack
 
Moving Beyond Passwords: FIDO Paris Seminar.pdf
Moving Beyond Passwords: FIDO Paris Seminar.pdfMoving Beyond Passwords: FIDO Paris Seminar.pdf
Moving Beyond Passwords: FIDO Paris Seminar.pdf
 
Gen AI in Business - Global Trends Report 2024.pdf
Gen AI in Business - Global Trends Report 2024.pdfGen AI in Business - Global Trends Report 2024.pdf
Gen AI in Business - Global Trends Report 2024.pdf
 
Merck Moving Beyond Passwords: FIDO Paris Seminar.pptx
Merck Moving Beyond Passwords: FIDO Paris Seminar.pptxMerck Moving Beyond Passwords: FIDO Paris Seminar.pptx
Merck Moving Beyond Passwords: FIDO Paris Seminar.pptx
 
Unleash Your Potential - Namagunga Girls Coding Club
Unleash Your Potential - Namagunga Girls Coding ClubUnleash Your Potential - Namagunga Girls Coding Club
Unleash Your Potential - Namagunga Girls Coding Club
 
Passkey Providers and Enabling Portability: FIDO Paris Seminar.pptx
Passkey Providers and Enabling Portability: FIDO Paris Seminar.pptxPasskey Providers and Enabling Portability: FIDO Paris Seminar.pptx
Passkey Providers and Enabling Portability: FIDO Paris Seminar.pptx
 
Digital Identity is Under Attack: FIDO Paris Seminar.pptx
Digital Identity is Under Attack: FIDO Paris Seminar.pptxDigital Identity is Under Attack: FIDO Paris Seminar.pptx
Digital Identity is Under Attack: FIDO Paris Seminar.pptx
 
The Fit for Passkeys for Employee and Consumer Sign-ins: FIDO Paris Seminar.pptx
The Fit for Passkeys for Employee and Consumer Sign-ins: FIDO Paris Seminar.pptxThe Fit for Passkeys for Employee and Consumer Sign-ins: FIDO Paris Seminar.pptx
The Fit for Passkeys for Employee and Consumer Sign-ins: FIDO Paris Seminar.pptx
 
DevoxxFR 2024 Reproducible Builds with Apache Maven
DevoxxFR 2024 Reproducible Builds with Apache MavenDevoxxFR 2024 Reproducible Builds with Apache Maven
DevoxxFR 2024 Reproducible Builds with Apache Maven
 
"Debugging python applications inside k8s environment", Andrii Soldatenko
"Debugging python applications inside k8s environment", Andrii Soldatenko"Debugging python applications inside k8s environment", Andrii Soldatenko
"Debugging python applications inside k8s environment", Andrii Soldatenko
 
How AI, OpenAI, and ChatGPT impact business and software.
How AI, OpenAI, and ChatGPT impact business and software.How AI, OpenAI, and ChatGPT impact business and software.
How AI, OpenAI, and ChatGPT impact business and software.
 
Hyperautomation and AI/ML: A Strategy for Digital Transformation Success.pdf
Hyperautomation and AI/ML: A Strategy for Digital Transformation Success.pdfHyperautomation and AI/ML: A Strategy for Digital Transformation Success.pdf
Hyperautomation and AI/ML: A Strategy for Digital Transformation Success.pdf
 
Unraveling Multimodality with Large Language Models.pdf
Unraveling Multimodality with Large Language Models.pdfUnraveling Multimodality with Large Language Models.pdf
Unraveling Multimodality with Large Language Models.pdf
 

Daily Progress Report on Waste Management Work Items

  • 1. Page 1 of 3 Daily Progress Report for February 28, 2011 Whelan, Joseph to: Arlene Kabei, Steve Armann, Rich Vaille, Stephen Tyahla, Bret Moxley, Andrew Helmlinger, Steve Wall, 'stuart.yamada@doh.hawaii.gov', 'Steven.chang@doh.hawaii.gov', 'alec.wong@doh.hawaii.gov' 02/28/2011 07:02 PM Show Details    Greetings all.  Please find below the daily progress report on work items contained within the recently approved  AOC.    ACTIONS PERFORMED AND DEVELOPMENTS ANTICIPATED  Cell 6 Assessment:  1. The QCA report documenting the evaluation and repair of the  southwestern portion of the E6 liner system was submitted February  25, 2011.  Approval to resume operations in this area is pending.      2. The northwest section of the Cell E6 liner was also damaged in the  January 13, 2011 storm.  This area is located directly below the  section of the storm water diversion system where the open box  culvert ties into the Hobas pipe.  Consequently, any rock and soil  material generated from the construction of the diversion system in  this area must be removed prior to the evaluation and repair of the  liner.  This removal activity is ongoing and is expected to be  completed within the next 2‐3 weeks, weather permitting.       Western Storm water Diversion Project (to render functional):  1)  Diversion Structure:   The final wall section of the diversion structure is  now in place.     2)  Box Culvert:   The contractor has completed forming the transition  structure from box culvert invert to pipe invert. This is scheduled to be  poured next     week.  Rebar work on box culvert walls is ongoing.     3)  Pipe:   Backfilling of the HOBAS pipe channel is now complete.  4)  The diversion structure is functionally complete per the terms of  Section 19.b. of the AOC.  Cell 6 Leachate Riser Restoration:  1. 105,300 gallons was pumped from the Cell E6 leachate riser storage tank since Friday and transported to the waste water treatment plant.     2. 33,200 gallons of water was pumped from the south pond area since Friday and transported to the local waste water treatment plant.   file://C:Documents and SettingsstyahlaLocal SettingsTempnotesBAAA25~web6262.htm 3/1/2011
  • 2. Page 2 of 3      3. 30,772 gallons of mud/water was pumped from the south pond area since Friday and placed within the onsite separation tanks.   Sediment Basin:  1. Daily showers earlier this week have prevented removal of silt/rock  material from the northern portion of the sedimentation basin.      2. The contractor pumped 8,700 gallons of storm water from the sedimentation basin since Friday and transported to the waste water treatment plant.           Evaluating possible hydraulic head below liner system:  1. Per the work plan submitted to EPA on 2/1/2011, we have drilled to  depth at temporary piezometer locations PZ‐1, PZ‐5 and PZ‐6.  No  water was encountered  during the drilling process. Since no water  was observed, temporary piezometers were not installed.   The  documentation report was submitted on February 25, 2011.    Beach Assessment Update:  1. The daily beach assessment phase of this task is complete. There were no calls received at the established beach waste siting hot line today.     ANALYTICAL DATA RECEIVED DURING REPORTING PERIOD ‐ None  ANTICIPATED PROBLEMS AND PLANNED RESOLUTIONS – None  Please let me know if you have any questions.       Best regards,        Joe Whelan     General Manager  Waste Management of Hawaii  808‐668‐2985, ext. 15 Office  808‐668‐1366 Fax  808‐479‐4610 Mobile     Waste Management's landfills provide over 17,000 acres of protected land for wildlife habitats and 15 landfills are certified by the Wildlife Habitat Council.            file://C:Documents and SettingsstyahlaLocal SettingsTempnotesBAAA25~web6262.htm 3/1/2011
  • 3. Page 3 of 3 Waste Management recycles enough paper every year to save 41 million trees. Please recycle any printed emails. file://C:Documents and SettingsstyahlaLocal SettingsTempnotesBAAA25~web6262.htm 3/1/2011