SlideShare une entreprise Scribd logo
1  sur  39
Restoration/Rehabilitation Plan in
     Development Project Areas
Hit by Typhoon Pablo In Compostela
Valley and Davao Oriental Provinces
I. Extent of Damages Brought by Typhoon Pablo
   The onslaught of Typhoon Pablo resulted to loss of lives and
damage to properties including vast areas of forest cover. In
Compostela Valley Province, the severity of damage was aggravated
by the slope and elevation in the upstream of Andap Watershed.
(Shown in Annexes C and D). Thirty-eight percent of the total area
or 21,603.12 hectares has a slope of 50%. Forty-three percent or
23,955.37 hectares also belong to 1000masl elevation. The images
show the progression of water movement from upstream to
downstream.
Figure 1 .
Forty-three Percent of the
areas in New Bataan are
categorized to have an
elevation of more than
1,000masl. Also, 38.9% of
the total area has a slope
of more than 50% which
makes it susceptible to
erosion and flashfloods.
The image shown in Fig. 1
(note the blue arrows)
indicates water draining
from the mountain slopes
down to the gullies.
                             Figure 1
Figure 2.
From the mountains water
in the gullies flow toward
water tributaries and on
to Andap River, as
illustrated by the blue
arrow.      While     water
always follows its natural
course, the high volume of
rainfall in a certain period
aids in accelerating the
flow of water. In this case,
the excessive rain during
the typhoon accumulated
a volume of 200-250mm.
                               Figure 2
Figure 3.
Considering the factors that
accelerate the flow of
water, the high amount of
rain accumulated during
the typhoon resulted to the
overflowing of waterways
resulting to severe erosion
and flashfloods and in the
process carry with it
boulders, uprooted trees
and debris from the
mountain down to the main
river and continue on to
communities          settled
downstream.                    Figure 3
Facing East
Facing West
Facing South
A. Damage to Development Projects
  Based on the GIS Modeling on the
  damages caused by Typhoon
  Pablo, the illustration shows that
  the area colored in Red was
  severely damaged as it is also
  considered the center of Typhoon
  Pablo. The Pink area indicates
  areas moderately damaged while
  that in Yellow shows areas slightly
  damaged by Pablo.
 In Davao Oriental, the total project area constituted 2,167
  hectares and about 1,864 hectares were estimated to have
  been damaged amounting to P23,860,473.00.

 In Compostela Valley, of the total 3,821 hectares of project
  areas, 2,925 hectares have been damaged and estimated at a
  cost of P36,106,517.00.

 In all, from the 5,988 hectares of project areas, 4,324 hectares
  have been damaged with an equivalent estimate of
  P59,966,989.65.
Damage to Development Projects
SUMMARY OF ESTIMATED DAMAGE DURING TYPHOON PABLO
                                                     ESTIMATED
                          AREA                                     ESTIMATED
    NAME OF PROJECTS                 PROJECT COST     DAMAGE
                          (ha.)                                    DAMAGE (P)
                                                        (ha.)
PROVINCE OF DAVAO ORIENTAL
1   UDP 2009               136       2,843,805.00        96       1,990,663.50
2   UDP 2010               202       6,503,390.00       172       5,527,881.50
3   NGP 2011               700       8,050,000.00       627       7,210,500.00
4   NGP 2012               399       3,391,500.00       363       2,863,460.00
5   SOIL CONSERVATION      500       2,901,400.00       440       2,615,968.00
6   CARP 158               230       5,060,000.00       166       3,652,000.00
    SUB TOTAL        2,167           28,750,095.00     1,864      23,860,473.00
COMPOSTELA VALLEY PROVINCE
1   REGULAR REFO (2004-2008)236       2,290,625.00      196         660,000.00
2   UDP 2009                605      14,522,072.00      380        8,124,345.00
3   UDP 2010                133       4,281,935.00       55        1,770,725.00
4   NGP 2011              865.22      9,950,030.00     722.22     8,305,530.00
5   NGP 2012             1,614.63    13,365,083.00    1272.63     10,876,013.00
6   SOIL CONSERVATION       103       2,013,836.43       85        1,661,903.65
7   CARP 158                264       7,128,000.00      214        4,708,000.00
       SUB TOTAL          3,821       53,551,581       2,925       36,106,517
    GRAND TOTAL           5,988     82,301,676.43     4,789      59,966,989.65
B. Damage to Natural Forests
                    Natural Forest Damaged by Typhoon Pablo
            (GIS-generated data based from Year 2003 Satellite Image)

                               Severely Damaged
Province Davao Oriental
 Municipality   Close Canopy    Open Canopy Brush land   Mangrove   Total (has.)
Boston            3,944.67        8,796.71   5,577.31                18,318.69
Cateel            6,221.34       15,559.66  15,120.38     114.08     37,015.46
Baganga           7,617.95        3,331.03   8,696.79     964.86     20,610.63
    Total        17,783.96       27,687.40   29,394.48   1,078.94   75,944.78
Compostela Valley Province
                                 Open
Municipality   Close canopy     canopy    Brushland   Mangrove   Total (has.)
Monkayo           903.82      11,078.62   26,386.08               38,368.52
Compostela       1,375.41      1,810.72    6,601.41                9,787.54
Montevista                                 2,856.09                2,856.09
Laak             843.77       6,690.63    32,974.65               40,509.05
   Total         843.77       6,690.63    35,830.74      -       43,365.14
TOTAL OF SEVERELY DAMAGE
 Close Canopy: 8,627.73 ha.                Open Canopy: 34,378.03 ha.
 Brush Land: 65,225.22 ha.                 Mangrove: 1,078.94 ha.

                           Grand Total: 119,309.92 ha.
Moderately Damaged
Province Davao Oriental

Municipality   Close Canopy    Open Canopy   Brushland   Mangrove   Total (has.)
Boston           157.86          9,853.00    3,423.33               13,434.19
Cateel                           2,250.62    1,022.26                3,272.88
Baganga          8,517.12       11,807.53    5,769.87               26,094.52
Caraga           4,480.01       15,667.98    16,365.00
Manay                                        1,275.60
    Total       8,674.98        23,911.15    10,215.46      -       42,801.59
Compostela Valley Province
  Municipality   Close Canopy   Open Canopy     Brushland   Mangrove   Total (has.)
Monkayo                           1,695.72       1,708.37                3,404.09
Compostela                         925.73        3,144.04                4,069.77
Montevista                                       7,050.87                7,050.87
New Bataan        11,574.28      18,873.58      10,999.65               41,447.51
Laak                              1,264.40      14,496.15               15,760.55
Nabunturan                        2,532.45       7,456.99                9,989.44
Maragusan          390.44          182.60         419.87                  992.91
Mawab                                            1,055.35                1,055.35
     Total        11,574.28      20,137.98      32,546.67      -       64,258.93
                      TOTAL OF MODERATELY DAMAGE
 Close Canopy: 20,249.26 ha.                 Brush Land: 42,762.13 ha.
 Open Canopy: 44,049.13 ha.                  Grand Total: 107,060.52 ha.
Slightly Damaged
Province Davao Oriental

Municipality   Close Canopy   Open Canopy   Brushland    Mangrove   Total (has.)
Caraga         339.48         7,670.12      9,118.99                17,128.59
Manay          2,852.73       14,861.18     13,555.73               31,269.64
Tarragona      3,302.11       4,298.10      1,793.63                9,393.84
Mati City                     1,458.99      475.23
Lupon                         2,924.29      62.50
Banaybanay     2,012.25       5,132.26      1,527.16
     Total       6,494.32      26,829.40     24,468.35       -       57,792.07
Compostela Valley Province
               Close       Open
Municipality   Canopy      Canopy       Brushland    Mangrove Total (has.)
Pantukan       1,598.01    4,185.25     2,877.49              8,660.75
Mabini         2,187.54    2753.7       14,340.85             19,282.09
Maco           36.71       1,524.33     21,917.99             23,479.03
Maragusan      2,611.16    1,316.67     7,625.95              11,553.78
Mawab                                   2,238.92              2,238.92
Nabunturan                 809.38       2,257.07              3,066.45
     Total      2,647.87     2,841.00    31,782.86       -         37,271.73

                    TOTAL OF MODERATELY DAMAGE
 Close Canopy: 9,142.19 ha.              Brush Land: 56,251.21 ha.
 Open Canopy: 29,670.40 ha.              Grand Total: 95,063.80 ha.
C. Damage to Properties and Infrastructures
   An     estimated     total   cost   of
    P24,222,823,528.07 was determined
    by NDRRMC for the damages caused
    nationally by Typhon Pablo, as of its
    December 18, 2012 report. Of
    this, P7,822,986,310 was attributed to
    damages                             in
    infrastructures, P16,350,605,805.07 in
    agriculture and P48,959,413 worth of
    damages to private properties.
 In Region XI alone, gravely damaged
  included major bridges such as that
  in Caraga, Davao Oriental. Gov, T.
  Palma Bridge significantly connects
  the Municipalities of Caraga and
  Baganga, Davao Oriental and with
  the extent of its damage, the
  Municipalities of Boston, Cateel and
  Baganga were briefly cut-off as
  rescue, retrieval and relief operations
  ensued after the typhoon.
II. The Cash-For-Work Scheme

 The concept of Cash-for-Work scheme has been perceived to be
 suitable and beneficial for the rehabilitation and re-establishment of
 damaged development projects as well as provide economic
 opportunity to beneficiaries or partner-People’s Organization
 members. This was speculated on during several meetings
 conducted with the different PENROs and CENROs whose
 administrative jurisdictions were affected by the typhoon.
A.Underlying Principle
Being the most severely
damaged Provinces in Region
XI, PENROs Compostela Valley
and Davao Oriental has been
put under the Cash-For-Work
Scheme       in   implementing
rehabilitation/restoration plans
in    different    development
project areas.
The following considerations were determined as basis in
     the implementation of the cash-for-work scheme:
1.People in the affected areas cannot
  survive on relief goods alone;

2. The extent of damage in agriculture was
most severe in especially in the banana and
coconut industries, thus the government has
to provide for the livelihood and
employment to sustain the recovery of
affected municipalities.
3. Proclamation No. 522 declared a State of National Calamity in the
Provinces of Compostela Valley, Davao Oriental and Davao Del
Norte;
4. The extent of damages on forest resources particularly on NGP
plantations established in 2011 and 2012 was so severe and needed
to be rehabilitated;
5. The establishment of new plantations for 2013 shall be the main
source of employment for affected community members.
B. Expected Targets
• Replace damaged seedlings from NGP plantations established in
  2011 and 2012;

• 100% accomplishment of the 2013 NGP target for Davao Oriental
  and Compostela Valley Provinces;
• Hire people and their services from the affected areas as income
  generation;
• Fast tracking of planting activities within 60 days (2 months).
C. Target Municipalities for Rehabilitation
  • Baganga, Cateel, Boston, Caraga, and Manay in Davao Oriental
    Province;

  • New
    Bataan, Monkayo, Compostela, Maragusan, Monkayo, Mabini, N
    abunturan, Maco, Pantukan, Montevista and Laak town in
    Compostela Valley Province.
 Considering the magnitude of damage to these areas, Region XI
   came up with rehabilitation plans that would restore the
   environmental stability of damaged areas as well as come up with
   a system that would benefit not only the natural ecosystem but
   also the upland communities. With the Cash-for-Work
   scheme, rehabilitation of development projects would also
   enable upland communities earn a considerable income;

 Target areas to be prioritized in the scheme will be damaged
  areas of Peoples Organizations and may not necessarily be NGP
  participants. A contiguous area of at least 500 hectares for each
  PO shall be proposed for rehabilitation.
 For Compostela Valley, a total of 2,500 hectares for CY 2013 and
  an additional 1,900 hectares for CY 2014 will be the focus for
  rehabilitation. Davao Oriental, on the other hand, shall also set
  aside 4,600 hectares for CY 2013 and another 2,700 hectares for
  CY 2014. All in all, Region XI shall rehabilitate a total of 7,100
  hectares for CY 2013 and 4,600 hectares for CY 2014.
PEOPLES ORGANIZATION                      CENRO       MUNICIPALITY COMPONENT CY 2013 (ha.) CY 2014 (ha.)
PROVINCE OF DAVAO ORIENTAL
 1 Boston Mandaya Tribe                          CENRO Baganga Boston          Refo/Agro       500.00        500.00
 2 CFP Taytayan Multi-Purpose Coop.              CENRO Baganga Cateel          Refo/Agro       500.00        500.00
 3 Campawan Agro-Forestry Dvt. Assn.             CENRO Baganga Baganga         Refo/Agro                     500.00
 4 Binondo Upland Farmers Coop.                  CENRO Baganga Baganga         Refo/Agro       500.00        500.00
 5 Mandaya Tribal Council of Mahan-ub            CENRO Baganga Baganga         Refo/Agro       500.00        500.00
 6 LGU Baganga                                   CENRO Baganga Baganga         Mangrove        202.00        198.00
 7 LGU Baganga                                   CENRO Baganga Baganga         Mangrove                    1,200.00
 8 Lamiawan Forest Developers MPC                CENRO Manay Caraga            Refo/Agro       500.00        200.00
 9 Palma Gil Tree Planters Assn.                 CENRO Manay Caraga            Refo/Agro       704.00
10 Capasnan Development Coop.                    CENRO Manay Manay             Refo/Agro       500.00
                     Sub-Total                                                               3,906.00 4,098.00
COMPOSTELA VALLEY PROVINCE
 1 Awao Forestland Mgt. Agreement Beneficiaries CENRO Monkayo Monkayo Refo/Agro                700.00
 2 San Antonio, Candiis, Concepcion & Kidawa-FRDCCENRO Nabunturan Laak         Refo/Agro     1,500.00        500.00
 3 NPP-FRDC                                      CENRO Monkayo Compostela Refo/Agro            567.00        500.00
 4 Peoples Upland & Countryside Coop.            CENRO Monkayo New Bataan Refo/Agro            800.00        500.00
 5 Community Forest Consumers Coop.              CENRO Monkayo New Bataan Refo/Agro            500.00        400.00
 6 Nabunturan Tribal Multi-Purpose Coop.         CENRO Nabunturan Nabunturan Refo/Agro       1,074.00
                     Sub-Total                                                               5,141.00 1,900.00
                GRAND-TOTAL                                                                   9,047.00 5,998.00
PEOPLES ORGANIZATION           CENRO      MUNICIPALITY COMPONENT CY 2013 (ha.) CY 2014 (ha.)
PROVINCE OF DAVAO ORIENTAL
 1 Boston Mandaya Tribe                 CENRO Baganga Boston       Refo/Agro         500.00       500.00
 2 CFP Taytayan Multi-Purpose Coop.     CENRO Baganga Cateel       Refo/Agro         500.00       500.00
 3 Campawan Agro-Forestry Dvt. Assn.    CENRO Baganga Baganga      Refo/Agro                      500.00
 4 Binondo Upland Farmers Coop.         CENRO Baganga Baganga      Refo/Agro         500.00       500.00
 5 Mandaya Tribal Council of Mahan-ub   CENRO Baganga Baganga      Refo/Agro         500.00       500.00
 6 LGU Baganga                          CENRO Baganga Baganga      Mangrove          202.00       198.00
 7 LGU Baganga                          CENRO Baganga Baganga      Mangrove                     1,200.00
 8 Lamiawan Forest Developers MPC       CENRO Manay Caraga         Refo/Agro         500.00       200.00
 9 Palma Gil Tree Planters Assn.        CENRO Manay Caraga         Refo/Agro         704.00
10 Capasnan Development Coop.           CENRO Manay Manay          Refo/Agro         500.00
                     Sub-Total                                                     3,906.00    4,098.00
PEOPLES ORGANIZATION                      CENRO MUNICIPALITY COMPONENTCY 2013 (ha.) CY 2014 (ha.)
COMPOSTELA VALLEY PROVINCE
 1 Awao Forestland Mgt. Agreement Beneficiaries CENRO Monkayo Monkayo Refo/Agro          700.00
 2 San Antonio, Candiis, Concepcion & Kidawa-FRDCCENRO Nabunturan Laak       Refo/Agro 1,500.00 500.00
 3 NPP-FRDC                                      CENRO Monkayo Compostela Refo/Agro      567.00 500.00
 4 Peoples Upland & Countryside Coop.            CENRO Monkayo New Bataan Refo/Agro      800.00 500.00
 5 Community Forest Consumers Coop.              CENRO Monkayo New Bataan Refo/Agro      500.00 400.00
 6 Nabunturan Tribal Multi-Purpose Coop.         CENRO Nabunturan Nabunturan Refo/Agro 1,074.00
                   Sub-Total                                                           5,141.00 1,900.00
D. Mode of Implementation
 Affected head of the families shall be hired as plantation workers
 and shall receive a daily wage rate of P226.00. This modified
 employment scheme shall require the plantation worker to work
 on .10 hectares/manday or planted an equivalent of 50 trees per
 day. Hired workers shall participate in the site preparation and
 planting activities in the months of January to June 2013. The
 succeeding activity of maintenance and protection shall
 commence in the next six months or from July to December 2013.
 A total of 871 workers shall be hired to work in an area of
  13,054 hectares plantation establishment and forest
  rehabilitation under the National Greening Program for a
  period of 6 months.
 Areas subjected for the Cash-for-Work scheme shall also
  include Upland Development Program (UDP) and Soil
  Conservation Areas.

 The whole Program constitutes a total fund of P29,526,900.00
  to cover the targeted Municipalities of both Compostela Valley
  and Davao Oriental Provinces.
CASH FOR WORK PROGRAM
                                 CASH FOR WORK
     REGION XI                      TARGET
                        AREA (ha.)             COST
                                   (workforce
  REGIONAL TOTAL          13,054    871     29,552,040
DAVAO ORIENTAL             3,891    260      8,793,660
COMPOSTELA VALLEY          9,163    611     20,758,380
 Damage Area for
  Rehab.: 6,657.0 ha.

 NGP Regular Target:
  6,397.0 ha.
PROVINCE OF DAVAO ORIENTAL: 260
 Municipality Workforce     Cost
• Boston         65     2,203,500.00
• Cateel         65     2,203,500.00
• Baganga        60     2,034,000.00
• Caraga         40     1,356,000.00
• Manay          30     1,017,000.00
PROVINCE OF COMPOSTELA VALLEY: 611
 Municipality Workforce     Cost
• New Bataan    120     4,068,000.00
• Compostela     70     2,373,000.00
• Maragusan      15       508,500.00
• Monkayo        86     2,915,400.00
• Nabunturan     60     2,034,000.00
• Maco           45     1,525,500.00
• Pantukan       45     1,525,500.00
• Montevista     50     1,695,000.00
• Mawab          15       508,500.00
• Laak          105     3,559,500.00
SCHEDULE OF CASH FOR WORK LAUNCHING
Davao Oriental : February 12, 2013
Compostela Valley: February 13, 2013



Most importantly, coordination and necessary support from the
Department of Social Welfare and Development (DSWD) and
Local Government Units should be sustained to ensure efficient
and effective delivery of much needed services.
Cash for work

Contenu connexe

Tendances

Energy Conservation & Sustainability
Energy Conservation & Sustainability  Energy Conservation & Sustainability
Energy Conservation & Sustainability Meg Thompson
 
NJFuture Redevelopment Forum 13 Infrastructure Strickland
NJFuture Redevelopment Forum 13 Infrastructure StricklandNJFuture Redevelopment Forum 13 Infrastructure Strickland
NJFuture Redevelopment Forum 13 Infrastructure StricklandNew Jersey Future
 
Indonesia Emergency Response
Indonesia Emergency ResponseIndonesia Emergency Response
Indonesia Emergency Responsebenisuryadi
 
Mo Ti Presentation
Mo Ti PresentationMo Ti Presentation
Mo Ti Presentationxingjun78
 
Revolution happening in geothermal energy industry
Revolution happening in geothermal energy industryRevolution happening in geothermal energy industry
Revolution happening in geothermal energy industryRuchi Patel
 
Apresentação call tiete 2 q11_final
Apresentação call tiete 2 q11_finalApresentação call tiete 2 q11_final
Apresentação call tiete 2 q11_finalAES Tietê
 
4Q08 and 2008 Earnings Results
4Q08 and 2008 Earnings Results4Q08 and 2008 Earnings Results
4Q08 and 2008 Earnings ResultsAES Tietê
 
Integrated Refining & Gasification Rbc 9 2009
Integrated Refining & Gasification   Rbc 9 2009Integrated Refining & Gasification   Rbc 9 2009
Integrated Refining & Gasification Rbc 9 2009rcarpe
 

Tendances (10)

Energy Conservation & Sustainability
Energy Conservation & Sustainability  Energy Conservation & Sustainability
Energy Conservation & Sustainability
 
NJFuture Redevelopment Forum 13 Infrastructure Strickland
NJFuture Redevelopment Forum 13 Infrastructure StricklandNJFuture Redevelopment Forum 13 Infrastructure Strickland
NJFuture Redevelopment Forum 13 Infrastructure Strickland
 
Indonesia Emergency Response
Indonesia Emergency ResponseIndonesia Emergency Response
Indonesia Emergency Response
 
Mo Ti Presentation
Mo Ti PresentationMo Ti Presentation
Mo Ti Presentation
 
TIPRO: Legacy Lawsuit Update
TIPRO: Legacy Lawsuit UpdateTIPRO: Legacy Lawsuit Update
TIPRO: Legacy Lawsuit Update
 
Revolution happening in geothermal energy industry
Revolution happening in geothermal energy industryRevolution happening in geothermal energy industry
Revolution happening in geothermal energy industry
 
Apresentação call tiete 2 q11_final
Apresentação call tiete 2 q11_finalApresentação call tiete 2 q11_final
Apresentação call tiete 2 q11_final
 
4Q08 and 2008 Earnings Results
4Q08 and 2008 Earnings Results4Q08 and 2008 Earnings Results
4Q08 and 2008 Earnings Results
 
Toward a Net Zero World
Toward a  Net Zero WorldToward a  Net Zero World
Toward a Net Zero World
 
Integrated Refining & Gasification Rbc 9 2009
Integrated Refining & Gasification   Rbc 9 2009Integrated Refining & Gasification   Rbc 9 2009
Integrated Refining & Gasification Rbc 9 2009
 

En vedette

The “BENTO” (Lunch Box) Project: An alternative Cash for Work (CFW)?
The “BENTO” (Lunch Box) Project: An alternative Cash for Work (CFW)?The “BENTO” (Lunch Box) Project: An alternative Cash for Work (CFW)?
The “BENTO” (Lunch Box) Project: An alternative Cash for Work (CFW)?Global Risk Forum GRFDavos
 
Ra 9165 comprehensive dangerous drugs act
Ra 9165   comprehensive dangerous drugs actRa 9165   comprehensive dangerous drugs act
Ra 9165 comprehensive dangerous drugs actWingielyn Baldoza
 
Q4 lesson 31 gloria macapagal-arroyo
Q4 lesson 31 gloria macapagal-arroyoQ4 lesson 31 gloria macapagal-arroyo
Q4 lesson 31 gloria macapagal-arroyoRivera Arnel
 
Livelihood Program from DOLE
Livelihood Program from DOLELivelihood Program from DOLE
Livelihood Program from DOLEPflcw Secretariat
 

En vedette (6)

The “BENTO” (Lunch Box) Project: An alternative Cash for Work (CFW)?
The “BENTO” (Lunch Box) Project: An alternative Cash for Work (CFW)?The “BENTO” (Lunch Box) Project: An alternative Cash for Work (CFW)?
The “BENTO” (Lunch Box) Project: An alternative Cash for Work (CFW)?
 
Ra 9165 comprehensive dangerous drugs act
Ra 9165   comprehensive dangerous drugs actRa 9165   comprehensive dangerous drugs act
Ra 9165 comprehensive dangerous drugs act
 
Q4 lesson 31 gloria macapagal-arroyo
Q4 lesson 31 gloria macapagal-arroyoQ4 lesson 31 gloria macapagal-arroyo
Q4 lesson 31 gloria macapagal-arroyo
 
Ekonomiks aralin 5 and 6
Ekonomiks aralin 5 and 6Ekonomiks aralin 5 and 6
Ekonomiks aralin 5 and 6
 
Livelihood Program from DOLE
Livelihood Program from DOLELivelihood Program from DOLE
Livelihood Program from DOLE
 
Ra9165presentation
Ra9165presentationRa9165presentation
Ra9165presentation
 

Similaire à Cash for work

Dreoni - Input 2012
Dreoni   - Input 2012Dreoni   - Input 2012
Dreoni - Input 2012INPUT 2012
 
Presentation for cm 24.04.2012
Presentation for cm 24.04.2012Presentation for cm 24.04.2012
Presentation for cm 24.04.2012Rashid Ahmed
 
Mole xxiii presentation hawa
Mole xxiii presentation  hawaMole xxiii presentation  hawa
Mole xxiii presentation hawaconiwas
 
Withholding tax response 2011
Withholding tax response 2011Withholding tax response 2011
Withholding tax response 2011Mohammad Azam
 
2008- Useche’s Course - 2001 Impact Ven. Agrarian Reform
2008- Useche’s Course - 2001 Impact Ven. Agrarian Reform2008- Useche’s Course - 2001 Impact Ven. Agrarian Reform
2008- Useche’s Course - 2001 Impact Ven. Agrarian ReformAlfonso Sintjago
 
Advancing knowledge on the costs, risks and benefits of using carbon markets ...
Advancing knowledge on the costs, risks and benefits of using carbon markets ...Advancing knowledge on the costs, risks and benefits of using carbon markets ...
Advancing knowledge on the costs, risks and benefits of using carbon markets ...CIFOR-ICRAF
 
Piloting the global protocol for community scale greenhouse gas emissions in ...
Piloting the global protocol for community scale greenhouse gas emissions in ...Piloting the global protocol for community scale greenhouse gas emissions in ...
Piloting the global protocol for community scale greenhouse gas emissions in ...icarb
 
Población del cantón chone 2001
Población del cantón chone 2001Población del cantón chone 2001
Población del cantón chone 2001Josefa Aray Vera
 
SACHETANA Project Experience with recharge - BIRD-K
SACHETANA Project Experience with recharge - BIRD-KSACHETANA Project Experience with recharge - BIRD-K
SACHETANA Project Experience with recharge - BIRD-KIndia Water Portal
 
Workshop ghg mitigation bilbao (mohamed taher kahil)
Workshop ghg mitigation bilbao (mohamed taher kahil)Workshop ghg mitigation bilbao (mohamed taher kahil)
Workshop ghg mitigation bilbao (mohamed taher kahil)REMEDIAnetwork
 
Maiz grano para blog
Maiz grano para blogMaiz grano para blog
Maiz grano para blogMiguel Lopez
 
Calendario valorizado sistema de recreacion amotape
Calendario valorizado  sistema de recreacion amotapeCalendario valorizado  sistema de recreacion amotape
Calendario valorizado sistema de recreacion amotapeEdikson Soto
 
Targeting tanzania 13_march
Targeting tanzania 13_marchTargeting tanzania 13_march
Targeting tanzania 13_marchAmos Omore
 
Cronograma valorizado almacen
Cronograma valorizado almacenCronograma valorizado almacen
Cronograma valorizado almacenOMAR CHOQUEPATA
 
KA6564 Assignment 2
KA6564 Assignment 2KA6564 Assignment 2
KA6564 Assignment 2armada7000
 
2010 04 14 Proserv Mms Pocsr Rotac Presentation
2010 04 14 Proserv Mms Pocsr Rotac Presentation2010 04 14 Proserv Mms Pocsr Rotac Presentation
2010 04 14 Proserv Mms Pocsr Rotac PresentationRobert Byrd
 

Similaire à Cash for work (20)

Dreoni - Input 2012
Dreoni   - Input 2012Dreoni   - Input 2012
Dreoni - Input 2012
 
Presentation for cm 24.04.2012
Presentation for cm 24.04.2012Presentation for cm 24.04.2012
Presentation for cm 24.04.2012
 
Mole xxiii presentation hawa
Mole xxiii presentation  hawaMole xxiii presentation  hawa
Mole xxiii presentation hawa
 
Withholding tax response 2011
Withholding tax response 2011Withholding tax response 2011
Withholding tax response 2011
 
2008- Useche’s Course - 2001 Impact Ven. Agrarian Reform
2008- Useche’s Course - 2001 Impact Ven. Agrarian Reform2008- Useche’s Course - 2001 Impact Ven. Agrarian Reform
2008- Useche’s Course - 2001 Impact Ven. Agrarian Reform
 
Advancing knowledge on the costs, risks and benefits of using carbon markets ...
Advancing knowledge on the costs, risks and benefits of using carbon markets ...Advancing knowledge on the costs, risks and benefits of using carbon markets ...
Advancing knowledge on the costs, risks and benefits of using carbon markets ...
 
Frijol para blog
Frijol para blogFrijol para blog
Frijol para blog
 
Libya
LibyaLibya
Libya
 
Piloting the global protocol for community scale greenhouse gas emissions in ...
Piloting the global protocol for community scale greenhouse gas emissions in ...Piloting the global protocol for community scale greenhouse gas emissions in ...
Piloting the global protocol for community scale greenhouse gas emissions in ...
 
Recommendations of the Water Taskforce by Steve Davies, PSSP
Recommendations of the Water Taskforce by Steve Davies, PSSP  Recommendations of the Water Taskforce by Steve Davies, PSSP
Recommendations of the Water Taskforce by Steve Davies, PSSP
 
Mango para blog
Mango para blogMango para blog
Mango para blog
 
Población del cantón chone 2001
Población del cantón chone 2001Población del cantón chone 2001
Población del cantón chone 2001
 
SACHETANA Project Experience with recharge - BIRD-K
SACHETANA Project Experience with recharge - BIRD-KSACHETANA Project Experience with recharge - BIRD-K
SACHETANA Project Experience with recharge - BIRD-K
 
Workshop ghg mitigation bilbao (mohamed taher kahil)
Workshop ghg mitigation bilbao (mohamed taher kahil)Workshop ghg mitigation bilbao (mohamed taher kahil)
Workshop ghg mitigation bilbao (mohamed taher kahil)
 
Maiz grano para blog
Maiz grano para blogMaiz grano para blog
Maiz grano para blog
 
Calendario valorizado sistema de recreacion amotape
Calendario valorizado  sistema de recreacion amotapeCalendario valorizado  sistema de recreacion amotape
Calendario valorizado sistema de recreacion amotape
 
Targeting tanzania 13_march
Targeting tanzania 13_marchTargeting tanzania 13_march
Targeting tanzania 13_march
 
Cronograma valorizado almacen
Cronograma valorizado almacenCronograma valorizado almacen
Cronograma valorizado almacen
 
KA6564 Assignment 2
KA6564 Assignment 2KA6564 Assignment 2
KA6564 Assignment 2
 
2010 04 14 Proserv Mms Pocsr Rotac Presentation
2010 04 14 Proserv Mms Pocsr Rotac Presentation2010 04 14 Proserv Mms Pocsr Rotac Presentation
2010 04 14 Proserv Mms Pocsr Rotac Presentation
 

Cash for work

  • 1. Restoration/Rehabilitation Plan in Development Project Areas Hit by Typhoon Pablo In Compostela Valley and Davao Oriental Provinces
  • 2. I. Extent of Damages Brought by Typhoon Pablo The onslaught of Typhoon Pablo resulted to loss of lives and damage to properties including vast areas of forest cover. In Compostela Valley Province, the severity of damage was aggravated by the slope and elevation in the upstream of Andap Watershed. (Shown in Annexes C and D). Thirty-eight percent of the total area or 21,603.12 hectares has a slope of 50%. Forty-three percent or 23,955.37 hectares also belong to 1000masl elevation. The images show the progression of water movement from upstream to downstream.
  • 3. Figure 1 . Forty-three Percent of the areas in New Bataan are categorized to have an elevation of more than 1,000masl. Also, 38.9% of the total area has a slope of more than 50% which makes it susceptible to erosion and flashfloods. The image shown in Fig. 1 (note the blue arrows) indicates water draining from the mountain slopes down to the gullies. Figure 1
  • 4. Figure 2. From the mountains water in the gullies flow toward water tributaries and on to Andap River, as illustrated by the blue arrow. While water always follows its natural course, the high volume of rainfall in a certain period aids in accelerating the flow of water. In this case, the excessive rain during the typhoon accumulated a volume of 200-250mm. Figure 2
  • 5. Figure 3. Considering the factors that accelerate the flow of water, the high amount of rain accumulated during the typhoon resulted to the overflowing of waterways resulting to severe erosion and flashfloods and in the process carry with it boulders, uprooted trees and debris from the mountain down to the main river and continue on to communities settled downstream. Figure 3
  • 6.
  • 10.
  • 11. A. Damage to Development Projects Based on the GIS Modeling on the damages caused by Typhoon Pablo, the illustration shows that the area colored in Red was severely damaged as it is also considered the center of Typhoon Pablo. The Pink area indicates areas moderately damaged while that in Yellow shows areas slightly damaged by Pablo.
  • 12.  In Davao Oriental, the total project area constituted 2,167 hectares and about 1,864 hectares were estimated to have been damaged amounting to P23,860,473.00.  In Compostela Valley, of the total 3,821 hectares of project areas, 2,925 hectares have been damaged and estimated at a cost of P36,106,517.00.  In all, from the 5,988 hectares of project areas, 4,324 hectares have been damaged with an equivalent estimate of P59,966,989.65.
  • 13. Damage to Development Projects SUMMARY OF ESTIMATED DAMAGE DURING TYPHOON PABLO ESTIMATED AREA ESTIMATED NAME OF PROJECTS PROJECT COST DAMAGE (ha.) DAMAGE (P) (ha.) PROVINCE OF DAVAO ORIENTAL 1 UDP 2009 136 2,843,805.00 96 1,990,663.50 2 UDP 2010 202 6,503,390.00 172 5,527,881.50 3 NGP 2011 700 8,050,000.00 627 7,210,500.00 4 NGP 2012 399 3,391,500.00 363 2,863,460.00 5 SOIL CONSERVATION 500 2,901,400.00 440 2,615,968.00 6 CARP 158 230 5,060,000.00 166 3,652,000.00 SUB TOTAL 2,167 28,750,095.00 1,864 23,860,473.00 COMPOSTELA VALLEY PROVINCE 1 REGULAR REFO (2004-2008)236 2,290,625.00 196 660,000.00 2 UDP 2009 605 14,522,072.00 380 8,124,345.00 3 UDP 2010 133 4,281,935.00 55 1,770,725.00 4 NGP 2011 865.22 9,950,030.00 722.22 8,305,530.00 5 NGP 2012 1,614.63 13,365,083.00 1272.63 10,876,013.00 6 SOIL CONSERVATION 103 2,013,836.43 85 1,661,903.65 7 CARP 158 264 7,128,000.00 214 4,708,000.00 SUB TOTAL 3,821 53,551,581 2,925 36,106,517 GRAND TOTAL 5,988 82,301,676.43 4,789 59,966,989.65
  • 14. B. Damage to Natural Forests Natural Forest Damaged by Typhoon Pablo (GIS-generated data based from Year 2003 Satellite Image) Severely Damaged Province Davao Oriental Municipality Close Canopy Open Canopy Brush land Mangrove Total (has.) Boston 3,944.67 8,796.71 5,577.31 18,318.69 Cateel 6,221.34 15,559.66 15,120.38 114.08 37,015.46 Baganga 7,617.95 3,331.03 8,696.79 964.86 20,610.63 Total 17,783.96 27,687.40 29,394.48 1,078.94 75,944.78
  • 15. Compostela Valley Province Open Municipality Close canopy canopy Brushland Mangrove Total (has.) Monkayo 903.82 11,078.62 26,386.08 38,368.52 Compostela 1,375.41 1,810.72 6,601.41 9,787.54 Montevista 2,856.09 2,856.09 Laak 843.77 6,690.63 32,974.65 40,509.05 Total 843.77 6,690.63 35,830.74 - 43,365.14 TOTAL OF SEVERELY DAMAGE  Close Canopy: 8,627.73 ha.  Open Canopy: 34,378.03 ha.  Brush Land: 65,225.22 ha.  Mangrove: 1,078.94 ha.  Grand Total: 119,309.92 ha.
  • 16. Moderately Damaged Province Davao Oriental Municipality Close Canopy Open Canopy Brushland Mangrove Total (has.) Boston 157.86 9,853.00 3,423.33 13,434.19 Cateel 2,250.62 1,022.26 3,272.88 Baganga 8,517.12 11,807.53 5,769.87 26,094.52 Caraga 4,480.01 15,667.98 16,365.00 Manay 1,275.60 Total 8,674.98 23,911.15 10,215.46 - 42,801.59
  • 17. Compostela Valley Province Municipality Close Canopy Open Canopy Brushland Mangrove Total (has.) Monkayo 1,695.72 1,708.37 3,404.09 Compostela 925.73 3,144.04 4,069.77 Montevista 7,050.87 7,050.87 New Bataan 11,574.28 18,873.58 10,999.65 41,447.51 Laak 1,264.40 14,496.15 15,760.55 Nabunturan 2,532.45 7,456.99 9,989.44 Maragusan 390.44 182.60 419.87 992.91 Mawab 1,055.35 1,055.35 Total 11,574.28 20,137.98 32,546.67 - 64,258.93 TOTAL OF MODERATELY DAMAGE  Close Canopy: 20,249.26 ha.  Brush Land: 42,762.13 ha.  Open Canopy: 44,049.13 ha.  Grand Total: 107,060.52 ha.
  • 18. Slightly Damaged Province Davao Oriental Municipality Close Canopy Open Canopy Brushland Mangrove Total (has.) Caraga 339.48 7,670.12 9,118.99 17,128.59 Manay 2,852.73 14,861.18 13,555.73 31,269.64 Tarragona 3,302.11 4,298.10 1,793.63 9,393.84 Mati City 1,458.99 475.23 Lupon 2,924.29 62.50 Banaybanay 2,012.25 5,132.26 1,527.16 Total 6,494.32 26,829.40 24,468.35 - 57,792.07
  • 19. Compostela Valley Province Close Open Municipality Canopy Canopy Brushland Mangrove Total (has.) Pantukan 1,598.01 4,185.25 2,877.49 8,660.75 Mabini 2,187.54 2753.7 14,340.85 19,282.09 Maco 36.71 1,524.33 21,917.99 23,479.03 Maragusan 2,611.16 1,316.67 7,625.95 11,553.78 Mawab 2,238.92 2,238.92 Nabunturan 809.38 2,257.07 3,066.45 Total 2,647.87 2,841.00 31,782.86 - 37,271.73 TOTAL OF MODERATELY DAMAGE  Close Canopy: 9,142.19 ha.  Brush Land: 56,251.21 ha.  Open Canopy: 29,670.40 ha.  Grand Total: 95,063.80 ha.
  • 20. C. Damage to Properties and Infrastructures  An estimated total cost of P24,222,823,528.07 was determined by NDRRMC for the damages caused nationally by Typhon Pablo, as of its December 18, 2012 report. Of this, P7,822,986,310 was attributed to damages in infrastructures, P16,350,605,805.07 in agriculture and P48,959,413 worth of damages to private properties.
  • 21.  In Region XI alone, gravely damaged included major bridges such as that in Caraga, Davao Oriental. Gov, T. Palma Bridge significantly connects the Municipalities of Caraga and Baganga, Davao Oriental and with the extent of its damage, the Municipalities of Boston, Cateel and Baganga were briefly cut-off as rescue, retrieval and relief operations ensued after the typhoon.
  • 22. II. The Cash-For-Work Scheme The concept of Cash-for-Work scheme has been perceived to be suitable and beneficial for the rehabilitation and re-establishment of damaged development projects as well as provide economic opportunity to beneficiaries or partner-People’s Organization members. This was speculated on during several meetings conducted with the different PENROs and CENROs whose administrative jurisdictions were affected by the typhoon.
  • 23. A.Underlying Principle Being the most severely damaged Provinces in Region XI, PENROs Compostela Valley and Davao Oriental has been put under the Cash-For-Work Scheme in implementing rehabilitation/restoration plans in different development project areas.
  • 24. The following considerations were determined as basis in the implementation of the cash-for-work scheme: 1.People in the affected areas cannot survive on relief goods alone; 2. The extent of damage in agriculture was most severe in especially in the banana and coconut industries, thus the government has to provide for the livelihood and employment to sustain the recovery of affected municipalities.
  • 25. 3. Proclamation No. 522 declared a State of National Calamity in the Provinces of Compostela Valley, Davao Oriental and Davao Del Norte; 4. The extent of damages on forest resources particularly on NGP plantations established in 2011 and 2012 was so severe and needed to be rehabilitated; 5. The establishment of new plantations for 2013 shall be the main source of employment for affected community members.
  • 26. B. Expected Targets • Replace damaged seedlings from NGP plantations established in 2011 and 2012; • 100% accomplishment of the 2013 NGP target for Davao Oriental and Compostela Valley Provinces; • Hire people and their services from the affected areas as income generation; • Fast tracking of planting activities within 60 days (2 months).
  • 27. C. Target Municipalities for Rehabilitation • Baganga, Cateel, Boston, Caraga, and Manay in Davao Oriental Province; • New Bataan, Monkayo, Compostela, Maragusan, Monkayo, Mabini, N abunturan, Maco, Pantukan, Montevista and Laak town in Compostela Valley Province.
  • 28.  Considering the magnitude of damage to these areas, Region XI came up with rehabilitation plans that would restore the environmental stability of damaged areas as well as come up with a system that would benefit not only the natural ecosystem but also the upland communities. With the Cash-for-Work scheme, rehabilitation of development projects would also enable upland communities earn a considerable income;  Target areas to be prioritized in the scheme will be damaged areas of Peoples Organizations and may not necessarily be NGP participants. A contiguous area of at least 500 hectares for each PO shall be proposed for rehabilitation.
  • 29.  For Compostela Valley, a total of 2,500 hectares for CY 2013 and an additional 1,900 hectares for CY 2014 will be the focus for rehabilitation. Davao Oriental, on the other hand, shall also set aside 4,600 hectares for CY 2013 and another 2,700 hectares for CY 2014. All in all, Region XI shall rehabilitate a total of 7,100 hectares for CY 2013 and 4,600 hectares for CY 2014.
  • 30. PEOPLES ORGANIZATION CENRO MUNICIPALITY COMPONENT CY 2013 (ha.) CY 2014 (ha.) PROVINCE OF DAVAO ORIENTAL 1 Boston Mandaya Tribe CENRO Baganga Boston Refo/Agro 500.00 500.00 2 CFP Taytayan Multi-Purpose Coop. CENRO Baganga Cateel Refo/Agro 500.00 500.00 3 Campawan Agro-Forestry Dvt. Assn. CENRO Baganga Baganga Refo/Agro 500.00 4 Binondo Upland Farmers Coop. CENRO Baganga Baganga Refo/Agro 500.00 500.00 5 Mandaya Tribal Council of Mahan-ub CENRO Baganga Baganga Refo/Agro 500.00 500.00 6 LGU Baganga CENRO Baganga Baganga Mangrove 202.00 198.00 7 LGU Baganga CENRO Baganga Baganga Mangrove 1,200.00 8 Lamiawan Forest Developers MPC CENRO Manay Caraga Refo/Agro 500.00 200.00 9 Palma Gil Tree Planters Assn. CENRO Manay Caraga Refo/Agro 704.00 10 Capasnan Development Coop. CENRO Manay Manay Refo/Agro 500.00 Sub-Total 3,906.00 4,098.00 COMPOSTELA VALLEY PROVINCE 1 Awao Forestland Mgt. Agreement Beneficiaries CENRO Monkayo Monkayo Refo/Agro 700.00 2 San Antonio, Candiis, Concepcion & Kidawa-FRDCCENRO Nabunturan Laak Refo/Agro 1,500.00 500.00 3 NPP-FRDC CENRO Monkayo Compostela Refo/Agro 567.00 500.00 4 Peoples Upland & Countryside Coop. CENRO Monkayo New Bataan Refo/Agro 800.00 500.00 5 Community Forest Consumers Coop. CENRO Monkayo New Bataan Refo/Agro 500.00 400.00 6 Nabunturan Tribal Multi-Purpose Coop. CENRO Nabunturan Nabunturan Refo/Agro 1,074.00 Sub-Total 5,141.00 1,900.00 GRAND-TOTAL 9,047.00 5,998.00
  • 31. PEOPLES ORGANIZATION CENRO MUNICIPALITY COMPONENT CY 2013 (ha.) CY 2014 (ha.) PROVINCE OF DAVAO ORIENTAL 1 Boston Mandaya Tribe CENRO Baganga Boston Refo/Agro 500.00 500.00 2 CFP Taytayan Multi-Purpose Coop. CENRO Baganga Cateel Refo/Agro 500.00 500.00 3 Campawan Agro-Forestry Dvt. Assn. CENRO Baganga Baganga Refo/Agro 500.00 4 Binondo Upland Farmers Coop. CENRO Baganga Baganga Refo/Agro 500.00 500.00 5 Mandaya Tribal Council of Mahan-ub CENRO Baganga Baganga Refo/Agro 500.00 500.00 6 LGU Baganga CENRO Baganga Baganga Mangrove 202.00 198.00 7 LGU Baganga CENRO Baganga Baganga Mangrove 1,200.00 8 Lamiawan Forest Developers MPC CENRO Manay Caraga Refo/Agro 500.00 200.00 9 Palma Gil Tree Planters Assn. CENRO Manay Caraga Refo/Agro 704.00 10 Capasnan Development Coop. CENRO Manay Manay Refo/Agro 500.00 Sub-Total 3,906.00 4,098.00
  • 32. PEOPLES ORGANIZATION CENRO MUNICIPALITY COMPONENTCY 2013 (ha.) CY 2014 (ha.) COMPOSTELA VALLEY PROVINCE 1 Awao Forestland Mgt. Agreement Beneficiaries CENRO Monkayo Monkayo Refo/Agro 700.00 2 San Antonio, Candiis, Concepcion & Kidawa-FRDCCENRO Nabunturan Laak Refo/Agro 1,500.00 500.00 3 NPP-FRDC CENRO Monkayo Compostela Refo/Agro 567.00 500.00 4 Peoples Upland & Countryside Coop. CENRO Monkayo New Bataan Refo/Agro 800.00 500.00 5 Community Forest Consumers Coop. CENRO Monkayo New Bataan Refo/Agro 500.00 400.00 6 Nabunturan Tribal Multi-Purpose Coop. CENRO Nabunturan Nabunturan Refo/Agro 1,074.00 Sub-Total 5,141.00 1,900.00
  • 33. D. Mode of Implementation Affected head of the families shall be hired as plantation workers and shall receive a daily wage rate of P226.00. This modified employment scheme shall require the plantation worker to work on .10 hectares/manday or planted an equivalent of 50 trees per day. Hired workers shall participate in the site preparation and planting activities in the months of January to June 2013. The succeeding activity of maintenance and protection shall commence in the next six months or from July to December 2013.
  • 34.  A total of 871 workers shall be hired to work in an area of 13,054 hectares plantation establishment and forest rehabilitation under the National Greening Program for a period of 6 months.  Areas subjected for the Cash-for-Work scheme shall also include Upland Development Program (UDP) and Soil Conservation Areas.  The whole Program constitutes a total fund of P29,526,900.00 to cover the targeted Municipalities of both Compostela Valley and Davao Oriental Provinces.
  • 35. CASH FOR WORK PROGRAM CASH FOR WORK REGION XI TARGET AREA (ha.) COST (workforce REGIONAL TOTAL 13,054 871 29,552,040 DAVAO ORIENTAL 3,891 260 8,793,660 COMPOSTELA VALLEY 9,163 611 20,758,380  Damage Area for Rehab.: 6,657.0 ha.  NGP Regular Target: 6,397.0 ha.
  • 36. PROVINCE OF DAVAO ORIENTAL: 260 Municipality Workforce Cost • Boston 65 2,203,500.00 • Cateel 65 2,203,500.00 • Baganga 60 2,034,000.00 • Caraga 40 1,356,000.00 • Manay 30 1,017,000.00
  • 37. PROVINCE OF COMPOSTELA VALLEY: 611 Municipality Workforce Cost • New Bataan 120 4,068,000.00 • Compostela 70 2,373,000.00 • Maragusan 15 508,500.00 • Monkayo 86 2,915,400.00 • Nabunturan 60 2,034,000.00 • Maco 45 1,525,500.00 • Pantukan 45 1,525,500.00 • Montevista 50 1,695,000.00 • Mawab 15 508,500.00 • Laak 105 3,559,500.00
  • 38. SCHEDULE OF CASH FOR WORK LAUNCHING Davao Oriental : February 12, 2013 Compostela Valley: February 13, 2013 Most importantly, coordination and necessary support from the Department of Social Welfare and Development (DSWD) and Local Government Units should be sustained to ensure efficient and effective delivery of much needed services.