SlideShare a Scribd company logo
1 of 48
Download to read offline
Verbus System Design Manual
   issue 003: March 2009
overview


                                                        VERBUS




> Significantly improved programme times compared to
traditional construction.

> Improved project costs.

> Deliverable anywhere in the world.

> Up to 16 stories achievable with a standard module.

> Reduced on site project and commercial management
required by Main Contractor.
CONTENTS




                                         1     Verbus System
>   What is Modular Construction?
>   Why use Modular Construction?
>   How does Verbus differ from other systems?
>   Verbus Cycle




                                         2     Verbus Process
>   The Team
>   The Design Process
>   Limitless Solutions
>   Modular Building Concept




                                         3     Verbus Technology
>   Construction
>   Geometries
>   Structure
>   Assembly and H&S
>   Robustness & Durability
>   Fire
>   Acoustics
>   Thermal Performance
>   Heat & Ventilation
>   Sustainability
>   Standard Details

                                         4     Verbus FAQ’s
>   Structure
>   Manufacture & Delivery
>   External Treatment: Roofing Facade/ Cladding
>   Glazing
>   Acoustic Design
>   Conservation of Fuel & Power - Thermal
>   Fire Safety
>   Drainage
>   Mechanical & Electrical
>   Internal FF&E
>   Resistance to Contaminants & Moisture
>   Toxic Substances
>   Stairs Lifts & Protection from Failing
>   Certification & Design Life
1 Verbus System
>   What is Modular Construction?
>   Why use Modular Construction?
>   How does Verbus differ from other systems?
>   Verbus Cycle
VERBUS SYSTEM


                                                                                                                  Modular Construction


WHAT is modular                      WHY use modular construction?
construction?                        Modular technology considerably reduces construction time. It is safer, quieter and cleaner than traditional methods of
                                     construction. It reduces the likelihood of defects and allows easy and low cost maintenance. It also offers designers
The term modular construction        and architects flexibility which is cost-effective.
is used where a building is
                                     Modular construction has many benefits in terms of labour skills, programme and quality. National Audit Office
assembled from a series of           statistics:
volumetric modules, linked
together to form a complete          1.Construction times can be reduced by 60%, saving both programme time and associated preliminary costs.
structure. The modules, which
are manufactured, finished and       2.On-site Labour is typically reduced by 70% compared to traditional construction techniques, which leads to
                                     considerable benefits on site for access, storage of materials and Health & Safety issues in general.
fitted-out off-site, under factory
conditions, are then                 3.The building envelope can be made water tight up to 80% faster than through traditional construction techniques,
transported to the construction      leading to reduced risks due to weather.
site and lifted into place.
                                     All which lead to greater speed, productivity, quality and safety thus ensuring earlier completion and greater revenue
                                     generation.

                                     HOW does Verbus differ from other systems?

                                     The Verbus system is built around newly developed, patented technology, and is far more robust than any other
                                     system on the market.

                                     The Verbus system is based on the fittings and transportation characteristics of the universal shipping container
                                     hence Verbus modules are not only highly robust, versatile and economic but they are also highly suitable for both
                                     international and national sea and road transportation using conventional vehicle logistics.

                                     The Verbus system with its steel frame and panelised lightweight wall construction are particularly suitable for use
                                     as structural modules making additional steel framing unnecessary.

                                     The robustness and rigidity of Verbus modules also allows far greater variety in the type of finishing that can be
                                     applied to the exterior of the building and the quality and level of fit-out that can be introduced to the interior

                                     The Verbus system is generally self stabilising and does not require support from the staircases or riser cores,
                                     removing the construction of these items from the critical path.

                                     Finally the close integration and vast experience of the Verbus design team, logistics department and module
                                     manufacturer, mean that when initial concept schemes are considered, total optimisation can be built-in at an early
                                     stage.
VERBUS SYSTEM


                                                                                                        Verbus Building Cycle




                              fabrication                       fitout                       shipping                 docking

                             The Verbus System utilises established production techniques and
                             capacity to manufacture quality accommodation solutions at high volume. The
                             basis of the system is a range of High Strength, corrosion resistant steel
                             manufactured modules fully certified, tested and approved that can be
                             fully fitted out and combined to create a wide variety of building shapes and be
                             adapted to suit any planning or end user needs.

                             The Verbus System is also revolutionary in that it is fully de-mountable and
                             re-usable.

                                                                                                                   road transport



             dismantle




                                                       completion                          connection                installation




re-furbish               re-assabmle
2 Verbus Process
>   The Team
>   The Design Process
>   Limitless Solutions
>   Modular Building Concept
VERBUS PROCESS


                                                                                                                                        The Team


                                                                                         The Verbus Team provides full
                                                                                         technical support and detailed information
                                                                                         on all aspects of the Verbus Systems
                                                                                         solution. Working closely with Client’s Team
                                                                                         to ensure a seamless interface and a fully
                                                                                         integrated building solution.


Verbus Systems have worked closely with industry
professionals to develop a highly versatile, efficient and
r o b u s t m o d u l a r b u i l d i n g s y s t e m . Ve r b u s S y s t e m s c a n
provide a full design and service to clients ranging
from foundations to finishes. Working with contractors they can deliver and
erect their patented volumetric modular system as a shell
or fully fitted finish.



Buro Happold have helped develop Verbus Systems design and
technology over the last 3 years. This has been achieved through detailed
design development of the structural engineering, fire, thermal and acoustic
performance of the units in order to gain compliance with local building
regulations. Initially the projects have been in the UK, but they are now being
developed further for approval in other European countries as well as North
America and the Middle East



K KA h a v e a s s i s t e d i n t h e d e s i g n a n d d e l i v e r y o f
numerous Verbus Systems projects throughout the UK and
other worldwide locations. From inception to completion,
through in depth understanding of the system, KKA can
provide full design solutions or simply advise on developing
the most economical Verbus solution.
VERBUS PROCESS


                                                                                                                             The Design Process


The Design Process                         Verbus Design Stages

                                           Stage 1A: Initial Viability Appraisal
The Verbus Team provides full
technical support and detailed             Identify Client's requirements, propose multiple options to maximise use of Verbus Modular Units within the scheme.
information on all aspects of the          Demonstrate the flexibility with which the Verbus Modular Units can accommodate diverse layouts and multiple
Ve r b u s S y s t e m s s o l u t i o n   building types.
ensuring a seamless interface
between the Verbus System                  Stage 1B: Preliminary Unit Types and Layouts
and all other building                     Prepare outline proposals based on clients preferred options including basic schedule on Units Types and Sizes.
components.                                Liaise with Client Team to explain the fundamental principals of the Verbus System and its integration into a complete
                                           building solution.
The Verbus Design Team can
offer a full building design               Stage 2: Detailed Unit Types and Layouts
service, but where required will
                                           Prepare initial GA drawings including all setting out and structural parameters .
work alongside the Client's Team           Liaise with Client Design Team on all building interface issues and prepare generic information on Structural, M&E,
through every stage of the                 Thermal, Fire and Acoustic performance of Verbus components.
design process to ensure a fully           Prepare detailed schedule of Unit Types, Sizes and Fit-out.
integrated, optimised and
statutory compliant building               Stage 3A – C: Unit Shell and Structure Plans, Sections & Elevations
solution is achieved.
                                           Prepare detailed Unit Shell fabrication drawings and carry out all structural calculations etc. in conjunction with Unit
                                           Shell.
Early involvement of the Verbus            Liaise with manufacturer to ensure fabrication drawings / specifications are optimized for Unit Shell construction and
Team in the design of a building           economy.
leads to greater flexibility and
greater economic and                       Stage 4A – D: Unit Fit-out Plans, Sections, Elevations & Schedules
programme benefits.
                                           Prepare detailed internal fit-out drawings and schedules based on the clients Employers Requirements Documents
                                           for client approval and fabrication.
The Verbus Team becomes a                  Liaise with manufacturer to ensure fit-out drawings / specifications are optimized for Unit Shell construction and
fully integrated part of the overall       economy.
Project Team attending briefing,           Prepare detailed M&E drawings and specifications for all services to be provided in Verbus fit-out
design, and contractor / site
                                           Stage 5: Unit Interface / Co-ordination Remaining Building Fabric.
meetings and ensuring a
continuous flow of information             Prepare all information necessary to ensure Verbus System can be integrated by Client Design team with all
between all parties.                       remaining building fabric.
VERBUS PROCESS


                                                Case Study 1: The Design Process


    PROPOSED HOTEL
    VERBUS STAGE 1A OPTIMISATION STUDY                                           VERBUS PROPOSALS
    TOTAL NUMBER OF BEDROOMS: 80
    TOTAL NUMBER OF VERBUS STOREYS: 3




                                                                                            Staircase could be provided
                                                                                            in Verbus unit. Note: careful
                                                                                            co-ordination required.
                                                    Traditional steel frame
                                                    podium structure




                                                                                                                  LEVEL 1
                                                                                             Corner could be provided
                                                                                             in Verbus or traditional.




                                                       Note: Half units are                 Option2: Greater economy as
     ORIGINAL PROPOSALS                                less economical than                 units are the same
                                                        full units. To achieve
                                                       greater economics,                   Junction will need consideration
                                                       reduce number of                     where Verbus units intersect.
                                                       types.


Module
Module
Module
Module




                                         OPTION 1                                OPTION 2                 LEVEL 2 - 3
VERBUS PROCESS


                                                                      Case Study 2: The Design Process

                                                                                 VERBUS PROPOSALS
                                                                                                    Line of original tower.




PROPOSED HOTEL
VERBUS STAGE 1A OPTIMISATION STUDY
TOTAL NUMBER OF BEDROOMS: 230
TOTAL NUMBER OF VERBUS STOREYS: 9


                                                                                                              LEVEL 1
                                                                                                    Building extended to rationalise
                                                                                                    the use of Verbus units.



                                                                                                    Keep corridor central if possible
                                                                                                    to maximise economy.
                                     All elevational modelling as “decorative”
                                     cladding/balconies etc. This ensures
                                     maximum off site fit out.




ORIGINAL PROPOSALS


                                                                                                        LEVEL 2-6


                                     Mix of rooms depandant on width of site.




                                     All elevational modelling as “decorative”
                                     cladding/balconies etc. This ensures
                                     maximum off site fit out.




                                                                                                             LEVEL 7
VERBUS PROCESS


                                                             Case Study 3: The Design Process

                                                   VERBUS PROPOSALS
                                                                                                     Ground and mezzanine floor levels to be
                                                                                                     traditionally constructed

                                                                                                     Dashed line indicates outline of upper floors.

                                                                                                     Extent of Bedroom accommodation over.
PROPOSED HOTEL
VERBUS STAGE 1A OPTIMISATION STUDY
TOTAL NUMBER OF BEDROOMS: 70
TOTAL NUMBER OF VERBUS STOREYS: 5



ORIGINAL PROPOSALS



                                                                                                   GROUND & MEZZ LEVEL
                                                     Proposed void space, will require fire
                                                     stopping.
                                                     Traditionally constructed bridging infill.
                                                     Continuity of finishes maintained by
                                                     lining of corridor wall face on site/
                                                     typical ‘zip-up’ detail.




                                                     External cladding to face of all units
                                                     by contractor.
                                                     Standard Units arranged radially.

                                                                                                                          LEVEL 1 - 4
      RESIDENTIAL BY OTHERS      HOTEL BY VERBUS
                                                      Module can be delivered with
                                                      staircase insitu.



  Module
  Module
  Module




                                                     Voids for lift shafts.

                                                                                                                          LEVEL 5
VERBUS PROCESS


                                                                                             Case Study 4: The Design Process

                                                     VERBUS PROPOSALS                                                           Traditional Frame
                                                                                                                                Structure & Fit Out
                                                                                                                                will be required to
                                                                                                                                corners.


   PROPOSED STUDENT ACCOMMODATION:
   VERBUS STAGE 1A OPTIMISATION STUDY
   TOTAL NUMBER OF BEDROOMS: 740
   TOTAL NUMBER OF VERBUS STOREYS: 20
                                                                                                                                Traditional Frame
                                                                                                                                Structure & Fit Out
                                                                                                                                will be required to
                                                                                                                                corners and Braced
                                   Slightly Larger Units                                                                        Corners.
                                   to accommodate Stair
                                   approx 200-300 mm
                                   wider than Standard
                                   Room. Thus Structure
                                   “Lines” through.
                                                                                   Traditional Frame
                                                                                   Structure & Fit Out
                                                                                   will be required to
                                                                                   corners.




                                          Possible Extra Rooms
                                          could be achieved.               LEVEL 1-6                             LEVEL 7                                     LEVEL 8
                                          However Implication is
                                          2no. 6 Bed Clusters.


                                                             Traditional Frame
                                                             Structure & Fit Out
                                                             will be required to
                                                             corners.




  ORIGINAL PROPOSALS                                                                                          Traditional Frame
                                                                                                              Structure & Fit Out
                                                                                                              will be required to
                                                                                                              corners and Braced
Module                                                                                                        Corners.




                                                                                                         LEVEL 9,10                                   LEVEL 11- 20
VERBUS PROCESS


                                                             Limitless Solutions



Variable length, height, width, orientation, juxtaposition, layout and finish
construct endless design solutions and building layouts.

Modular construction need not be limited by a single solution only your
imagination.


consider the time, cost & quality benefits of a fully
finished modular building solution.


1 pre-fabricated frame
pre-fabricated ground floor podium structure delivered to site for rapid assembly

2 building blocks
fully fitted & finished room modules containing bedrooms, circulation & services
accommodation “stacked” up to 15 storeys without the need for additional framing

3 modular roof
fully finished roof modules pre-laid to fall & complete with gutter system fitted to
the upper storey and integrated with pre-installed plant modules if required

4 “clip on” cladding
modules are designed to be clad with an external skin, but can be delivered fully
insulated and glazed, ready for habitation
VERBUS PROCESS


                                          Modular Building Concept


                                                 pre- fabricated roof modules utilize
 modules lowered and bolted                      Verbus connection technology shipped in
 into place                                      “batches” in the volume of a shipping module




                                                 upper circulation module pre-fitted with lifts
 stairs pre-fitted in circulation                ready to “drop” upon completion of vertical
 modules                                         core




modular cladding system
as single component (where required)             enhancement features
can be attached before module is lifted
 into place

option A.
ground floor structure
provided as traditional construction




 complete modular units craned
 into position




option B.
ground floor structure
provided as a ready to assemble
prefabricated “kit of parts”
                                                option C.
                                                ground floor podium structure
                                                provided in Verbus units with Verbus spacer
signature cladding                              frames providing extra height if required
system can be attached in module
size sections before module is lifted
into place
3 Verbus Technology
>   Construction
>   Geometries
>   Structure
>   Assembly and H&S
>   Fire
>   Acoustics
>   Thermal Performance
>   Heat & Ventilation
>   Sustainability
>   Standard Details
VERBUS TECHNOLOGY


                       Construction: The Basic Verbus Module




The basic Verbus module comprises a “shell” of high tensile
corrosion resistant steel components with composite wall,
floor and roof structure that provides superior insulation for
sound, thermal & fire performance.
VERBUS TECHNOLOGY


                                                                                                 Construction: The Basic Verbus Shell
                                                                                                                    intermediate castings are
                                                                                                                    introduced depending on unit size to
                                                                                                                    ensure maximum flexibility for
                                                                                                                    transportation lifting stacking & docking


                                                                                                                    the module frame comprises
                                                                                                                    lightweight folded plate rails and posts

Composite roof comprises:
- 1.6mm Corten steel flat outer sheet                                                                               units are permanentlybolted/
- 100mm mineral wool insulation
                                                                                                                    secured once on site via a simple bolt
- “C” channel steel joists
                                                                                                                    box
- 9mm plywood
- 2 layers of 12.5mm plasterboard




                                                                                                                    openings are framed with closure
                                                                                                                    posts & head & sill rails




                                                                                                                    the frame is stiffened by lightweight
                                                                                                                    1.6mm gauge corrugated steel sheets i.e.
                                                                                                                    the frame and outer sheet act as a
                                                                                                                    lightweight diaphragm structure

                                                                                                                    a grid of simple plates &
                                                                                                                    standard industry connections are installed
                                                                                                                    to ensure a perfect fit & interface with other
                                                                                                                    building components




Composite wall comprises:
- 1.6mm Corten Steel profiled outer sheet
                                                                                  plasterboard




- 40mm insulation
                                              outersheet




- lining support rails
                                                           insulation



                                                                        plywood




- 9mm plywood primary lining
- 2 layers of plasterboard secondary lining
                                                           rails




standard shipping “castings” - used
for lifting docking & securing


Composite floor comprises:
- 28mm plywood
- 100mm mineral wool insulation
- rubber separation gaskets
- “C” channel steel joists
- 1.6mm Corten steel flat outer sheet
VERBUS TECHNOLOGY


                                                                                                      Geometries




                      Verbus Module dimensions can be a range of sizes. The most common
                      dimensions of which are 6ft or 8ft x 40ft (2,438mm or 3660 mm x 12,192mm).

                      The adjacent Matrix highlights how Verbus Modules which harmonize with multiples of these
                      dimensions to give greater economies.

                      Longer units combining more volumes into a single module will provide greater savings
                      than a series of smaller modules containing the same independent spaces.

                      Projects are not limited to 'standard' sizes and a full range of
                      Module sizes can be provided.

                                    Geometry ‘V’ Economy Matrix:
                                    minimum          optimum            maximum
                                     6058     to     12192       to      14273


                   minimum   2438




                                                                                    variable widths
                              to




                   optimum   3660




                              to


     Good Value
Very Good Value    maximum 4022
 Excellent Value

                                              variable lengths
VERBUS TECHNOLOGY


                                                                                               Structure




                                                                                      stability
                                                                                       side & end unit walls to provide
Verbus Modules are high strength                                                       building stability
steel frame and metal plate diaphragm
structures based on universal shipping
container design, revised to suit the
requirements and demands of the
construction industry.
The units are fabricated from rolled
steel sections, with the wall structure of the
shipping container acting as a load bearing
structural element and floor and roof
construction designed to satisfy the loading
and dynamic response conditions of a multi-
storey building.
Because of their inherent
strength, the units can be stacked as
high as high as 15 to 20 storeys. For
stability, the units laid side by side are
connected to each other using spigots and
sockets, and bolted plates. When fully
connected the units are mostly self              load paths
stabilising and do not require the support of    corner + intermediate posts
                                                 support vertical loads
independent steel frames or cores.
VERBUS TECHNOLOGY


                                                    Assembly and H&S




Assembly is simple, fast and safe. The
Verbus System can be provided on a simple
foundation solution or on a steel or concrete
podium. The design allows for rapid
erection with low-technology, fail safe
bolted connections.         The units are
weatherproof so that interiors remain
protected during the assembly process.
Modules are fully fitted out before arrival on
site.

Modules can be erected and bolted
together internally without external
scaffolding.   The installation process
includes a temporary barrier system which
in conjunction with man-safes and safety
harnesses provides a rapid and safe
method of construction.

Due to the small number of large lifts
and the absence of traditional materials on
site, this modular construction method
offers the opportunity for a significant
reduction in the number of hazards on site.
VERBUS TECHNOLOGY


                                                                                 Robustness & Durability



                                                  boxes
                                                   high yield structural steel
                                                   boxes




                                                                                           bolting phase 1
The Verbus units are manufactured                                                           internal corridor bolting
from weather-resistant Corten A steel. This
is a material with a yield stress of at least
375N/mm2. The Corten A steel is used for
the corrugated walls of the unit and also for
rolled steel sections including perimeter
beams and load bearing posts.
When bolted together, the boxes form a
continuous tied structure which prevents
disproportionate collapse of the building
should a single unit become damaged and
fail.
The external steel box also
provides a vapour barrier, and allows the
individual building elements to be weather-
tight during transportation and construction
The units have been prototyped and
load tested, and all materials are certified by
testing.                                          corrosion
                                                  protection

Workmanship in the factory is                     painted corten steel
                                                  (anti-rust) protection                   bolting phase 2
independently monitored and controlled by                                                  external vertical and horizontal
                                                                                           bolting ties to prevent
Lloyds Insurance.                                                                          disproportionate collapse
VERBUS TECHNOLOGY


                                                                                      Fire Strategy



                                                fire protected riser shaft

                                                                                      cavity between units: class 0 fire
                                                                                      sterile environment




The building system is designed                                                       fire resistance of unit is 1 - 2 hours
to meet Building Regulations for Fire Safety,
which covers means of escape, spread of
flame, fire performance and access for fire-
fighting.
The modular units can be built to
resist a fire for up to 2 hours. Spread of
flame through the corridors or via the
windows is prevented by conventional fire
stopping. The spaces between the units
are treated as fire sterile areas and are
sealed off from the other spaces in the
building. In the event that a module is
damaged during a fire the surrounding units
remain tied together and fully supported.
Escape stairs and corridors
can be treated in a similar way to a
conventional building.


                                                corridor “zip-up” linings
                                                provide cavity fire barriers
                                                                                      external envelope insulation
                                                                                      provides fire barrier in cladding
                                                                                      zone
VERBUS TECHNOLOGY


                                                                                   Acoustic Performance



                                                >54 Dntw Ctr dB Floor/ceiling
                                                noise reduction




The modular units meet and                                                              floor to ceiling impact noise
                                                                                        transfer < 55Lntw dB
exceed minimum building regulation noise
reduction levels, and can accommodate
sound isolation requirements for residential
and hotel buildings. Air borne noise and
structure borne sounds are successfully
isolated by the layers of plasterboard,
insulation and air gaps between the units.
A range of external noise isolation
measures can be achieved through the
specification of appropriate cladding
working in conjunction with the noise
reduction of the units themselves.




                                               >50Dntw + Ctr dB noise reduction
                                               between rooms

                                                                                        units + external cladding provide noise
                                                                                        reduction
VERBUS TECHNOLOGY


                                                                                            Thermal Performance




                                                                                             it should be noted that the outer
                                                                                             steel sheet of the Verbus unit is
The Building Regulations will                                                                considered as the vapour barrier. In order
specify minimum standards to be achieved                                                     for this to be successful, and to mitigate
                                                                                             the risk of interstitial condensation,
for thermal performance of the building                                                      additional insulation must be provided
                                                                                             against the external steel face of the unit.
design, including the building fabric. The
assessment method usually requires the
performance of the entire building to be      composite roof: R=1.31m2K/W
measured against standard criteria for
carbon emissions.

The thermal performance of
the Verbus System is measured in
conjunction with the external wall and
insulation, plywood and minimum 2 layers                    composite wall: R=1.09m2K/W

plasterboard for combined optimum
thermal and acoustic performance,
                                                composite floor: R=1.31m2K/W
achieving the best possible elemental value
without compromising the available floor
area.

The adjacent diagram provides indicative
elemental Thermal Resistance Values (R -
Value) for the wall, floor and roof of the
Verbus Systems Shell. These values can of
course be increased, with a small loss of
floor area, by increasing insulation
thickness and lining specification.
VERBUS TECHNOLOGY


                                                                                      Heat & Ventilation


                                                   extract via bathroom riser

                                                                                       heat & ventilation
                                                                                       option 2:
                                                                                         supply & extract temperature controlled
                                                                                        air ducted from roof to fan coil units in
                                                                                         bedroom ceilings



The units can meet current Building
Regulations standards for thermal
performance, air-tightness and general
building servicing requirements with an
appropriate specification for the building
fabric.
Heat and ventilation can be
provided locally in the modules or if a sealed
façade and ducted air solution is required,
via temperature controlled ventilation
fancoil units.
The modules are pre-fabricated with
pre-formed service riser positions to allow
the installation of ductwork both horizontally
and vertically. Plant and equipment outside
the modules will be installed on site, with the
pre-fabrication concentrated within the           heat & ventilation
                                                  option 1:
modules and local risers.                         external trickle ventilation

The level of pre-fabrication
                                                  local heater unit in the room
will vary between the different types of
building and there will be connections of
ductwork and services to be made between
the units horizontally and vertically
dependant on the design strategy for the
ventilation system of the modules.
VERBUS TECHNOLOGY


                                                                                                                                                     Sustainability


                                                                                                          40 year life cycle


                                                                        Material
                                                                                        Transport                                          Dismantling
                                                                       Extraction                                                                               Second
                                                                                            to          Construction       Operation        & rebuild/
                                                                          and                                                                                  operation
                                                                                           site                                              Rebuild
                                                                       processing




The Verbus building system brings the
following    benefits  in terms    of                                                               Stage 1                                          Stage 2

sustainability:

1.        Minimised transport and CO2
                                                                     Stage One & Stage Two: Impact of Reuse                              Summary of Verbus Building
emissions.                                                                                                                                (over 40 year Design Life)
 Materials are sourced close to the factory. The steel used
contains re-cycled material. The amount of fossil fuels used
for shipping and transportation is less than the fuels used for
deliveries by traditional on-site construction techniques.

2.         Re-use of the units.
The units can be unbolted and refurbished for re-use. They
are also flexible and adaptable for modification.

3.       Minimised use of Materials and
Waste.
The prefabrication process maximises the use of material in
manufacture, and minimises waste created on site.

4.        Good Air-tightness and thermal
performance.
The continuous outer steel box prevents air leakage allowing
venting to be carefully controlled through trickle vents. The     Alternative technologies can be incorporated into the Verbus
box is insulated inside and out providing good thermal and        system to reduce external power and water consumption, such as:
acoustic performance.

5.       Shading devices and other façade                         Solar thermal collectors, Photo-voltaics, Ground source Heat pumps, Biomass boiler, Greywater
elements: These can be modularised and fixed to the               Recycling.
outside of the Verbus boxes without additional
strengthening.
                                                                  The other measures that can be taken to reduce the environmental impact of the building include good
                                                                  building orientation and use of daylight, natural ventilation and cooling, efficient land use, respect to
                                                                  ecology, efficient water usage, good operation management, and low energy services such as lighting.
VERBUS TECHNOLOGY


                                                      Standard Details




                      wall construction (plan)




roof construction (section)




floor construction (section)
5 Verbus FAQ’s
>   Structure
>   Manufacture & Delivery
>   External Treatment: Roofing Facade/ Cladding
>   Glazing
>   Acoustic Design
>   Conservation of Fuel & Power - Thermal
>   Fire Safety
>   Drainage
>   Mechanical & Electrical
>   Internal FF&E
>   Resistance to Contaminants & Moisture
>   Toxic Substances
>   Stairs Lifts & Protection from Falling
>   Certification & Design Life
Verbus FAQ


                                                                                                        STRUCTURE

1. What is the wall make-up between units for wall acting as party wall?

Standard Verbus detail would be two layers 12.5mm fireline, 1 layer of 10mm plywood, 40mm metal stud with rockwool
insulation 1.6mm Corten steel folded to give a 20.5mm corrugation. There would be an air gap of approximately 28m before
adjacent unit provides an identical wall build up. Typical overall thickness 220mm.

2. What is the wall make-up for an external wall?

As detailed above, but Corten steel wall would then have additional insulation, a cavity then the external facade (brick,
rendered panel , timber, aluminium cladding etc.)

3. There appear to be a number of posts in the front elevation: is this
standard or is this due to opening that is created?

There are some posts required in the end walls to give the unit robustness during shipping and stacking on a vessel. Some
of these posts can be removed once the unit is in its permanent state (i.e. erected as a building). Some Posts are to form
window/ door apertures as required.

4. Is it possible to completely remove the front of a unit?

Dependant on width of unit and adjacent structure. The top, bottom & end joists will always be required as will the columns
on the corners of the unit. The remainder of the end wall could be removed in the right situation.

5. Will our openings require similar framing?

Yes. All openings will need to be framed. There is an opportunity to use the essential elements of structure for this framing
(as mentioned above) or an additional frame would be required.
Verbus FAQ


                                                                                                         STRUCTURE

6. Do Verbus design and warrant the overall building stability including core?

Verbus will warrant the design of the structure of the Verbus elements of a building. Where a building contains elements of
steel / concrete frame (i.e. cores or large open span areas) these elements may designed by the Verbus project engineer. It
is the project engineer who takes overall responsibility for the building as a whole.

7. Do Verbus provide wind loading design?

Verbus units will be designed for wind loading pressures provided by the structural engineer.

8. Do Verbus provide load bearing design including cladding loads?

Dead and live loads would be agreed with the structural engineer. Verbus can provide loadings for interface with supporting
structures (e.g. Transfer decks and cores.)

9. Do Verbus provide disproportionate collapse safeguard design?

The units are designed and detailed to transmit tie forces to BS 5950 in the event of loss of support.

10. Do Verbus provide loadings for ground slab design?

Loads due to Verbus units in contact with the ground slab would be provided by Verbus to the structural engineer designing
the ground floor slab.

11. Do Verbus provide loadings for design of foundations?

Verbus provides unit loads for incorporation into foundation designs. Note that weight of cladding, roof top plant and other
loadings to be provided by the structural engineer.
Verbus FAQ


                                                                          MANUFACTURE & DELIVERY

1. What would be the period required for Verbus to prepare drawings, issue
for comment, amend and re-issue for construction?

Very much dependent on the size of project and variation of unit types. Typically 6-8 weeks from order being placed to
Verbus Design Freeze being achieved assuming the Clients Design is “frozen”.

2. What period would be required for manufacture and despatch from factory
from the date of construction issued drawings?

Typically twelve weeks.

3. What period would be required from factory despatch date for shipping and
delivery to site, including time to negotiate exit and entry ports?

Typically four weeks.

4. What holding/ storage or other arrangement is provided by Verbus to
facilitate a phased delivery to meet the site programme of erection?

As required we use a national road haulier with storage facilities throughout the UK

5. Given a clear run, what average site erection rate would Verbus expect to
achieve per week – (modules delivered, placed and structurally connected.)

Verbus could achieve a rate of ten units per day

6. Will Verbus inspect / accept foundations and erect modules, and attach
structurally to the cores and foundations.

This is subject to contract conditions. Verbus can carry out these procedures if required
Verbus FAQ


                                                                          MANUFACTURE & DELIVERY

7. What protection do units have in transit?

The outer skin of the units is 1.6mm Corten Steel. This requires no additional protection.

8. What happens if the boat sinks or a unit falls off the side of the vessel?

Verbus provide insurance to cover any such transit related issues. This insurance is valid from the manufacturing
facility through to delivery to site.
Verbus FAQ


                              EXTERNAL TREATMENT: ROOFING FACADE/ CLADDING

1. Have you ever used a bespoke metal cladding solution externally?

There are currently two live projects which utilise metal cladding in part of the external façade system. However the
outer face of the unit must be insulated.
2. What rules have to be followed for the fixings / spacing of cleats etc. which
cladding rails, trims and flashings can be fixed to?

The Verbus units provide fixing points for cladding rails at the top and bottom of the side and end walls. Should brick
ties or similar be required then plates are welded to the external skin as required.
3. Cladding connection provision

The Verbus units have a steel structure allowing different cladding systems to be fixed to the outside of the units. Flat
plates, “Ancon” brackets and other fixing points are provided on the unit for cladding attachments to be added.

4. What types of cladding can be applied to the module and what provision do
Verbus make in each case for fixing.

Any cladding system can be fixed to a Verbus unit. The standard provision is either brick tie plates welded to the
external skin of the unit plus “Ancon” brackets along top and bottom rails to take vertical cladding rails. We would have
early discussions with the cladding contractor to ensure that the interfaces are known.

5. Do Verbus normally provide external doorsets and/ or windows factory fitted
and glazed?

No, not normally. If the employer requires such items they can be supplied loose inside modules. However windows &
doors could be pre-installed in the right situation.
6. Can a parapet detail be added to the Verbus units by means of a standard
Verbus connection detail?

Previous projects have had parapets formed in situ from a timber construction fixed through into the top rail of the units.
However in the right situation yes this could be achieved.
Verbus FAQ


                                                                                                             GLAZING

1. How do you deal with window penetrations in a UK brick clad scheme? With
particular interest in what the sequence / detail is once the opening has been
'knocked out'. Is the reveal of the Verbus unit simply dry lined from within on site?

The window reveal has straps or brackets fixed to it to support the window (which is primarily in the wall cavity).
Once the window is fitted the reveal is lined with 1 layer 12.5mm vapour check plasterboard and 1 layer 12.5mm
soundbloc plasterboard as standard


2. If the reveal is dry lined on site, how is fixing achieved into the steel surround?
Are grounds required first?

Grounds are not required first. The plasterboard can be fixed directly to the steel frame of the window aperture.
Alternatively a plywood lined reveal could be provided.
3. Is the window normally fixed into the Verbus unit rather than the outer
cladding system? This would replace the need for a lined reveal with a simple
finish like an architrave.

Both are possible. The client usually prefers to have an internal cill detail as a more traditional construction would
provide, therefore the window is fitted in the cavity between Verbus wall and external façade.
However if there is no requirement for an internal cill or reveal the window can be pre-installed in the unit providing it
does not protrude beyond the face of the outer sheet.
Verbus FAQ


                                                                                            ACOUSTIC DESIGN

1. What sound insulation value does the unit have without additional insulation?

Results of theoretical predictions and model constructions
For single external wall:
Assumptions:
Plasterboard 2 layers of 12.5mm board with mass
17.3kg/m2
Plywood 1 layer of 10mm plywood with mass
5.6kg/m2
Void 50mm with 40mm of mineral wool
Steel 1.6mm flat steel 12.5kg/m2

Sound reduction index Rw - 51

2. Vibration: To meet design code and Employer's requirements.
<= 55Lntw dB



3. Acoustic Design: To meet both Employer's requirements and Building
Regulations – impact and airborne sound walls and floors.

The design of a standard Verbus unit is such that previous test data confirms it easily attains those targets set by Building
Regulations. Acoustic performance measured as a combination of Verbus build-up and external walls. Room to room
acoustic performance measured on previous Verbus buildings.
Room to room noise reduction:
>= 50Dntw +Ctr dB
Floor to ceiling noise reduction:
>= 54Dntw +Ctr dB
Verbus FAQ


                                            CONSERVATION OF FUEL & POWER - THERMAL

1. What U value does the unit provide without additional insulation?

The unit has the following thermal resistance, which when combined with external cladding and insulation provides a U-
value:
- wall: R=1.09 m2K/W
- roof: R=1.31 m2K/W
- floor: R=1.05 m2K/W

2. Does the external insulation need to be positioned tight against the outer face
of the unit? Can an air gap be provided with a composite, Kingspan type,
insulation or does this cause problems with interstitial condensation?

No requirement to place insulation against outer face of unit.

3. Air Tightness Design: To meet both Employer's requirements and Building
Regulations including interstitial condensation calculation check.

Part L calculations normally carried out by project building services engineer or architect. Construction details of the
Verbus units provided by Verbus.

4. Thermal Design: To meet both Employer's requirements and                                                    Building
Regulations including interstitial condensation calculation check.

The thermal properties of the Verbus units are such that additional insulation is required outside of the units in the
cavity behind the external cladding / façade. Part L calculations normally carried out by project building services
engineer.
Verbus FAQ


                                                                                                        FIRE SAFETY

1. What is the Fire rating for a Verbus Unit and what level of protection is
given to its structural elements?

90 minutes standard. Verbus units are fire rated as specified by the architect. Up to 2 hours protection possible.
Verbus FAQ


                                                                                                         DRAINAGE

1. Services Design: Provision of service risers as shown, to meet needs of M&E
and Building Regulations

Apertures in floor and roof of Verbus units are provided to give vertical access through the building for services. Sizes
of these apertures vary dependant on services required and height of building. Risers are generally sized by M&E
consultant.
Verbus FAQ


                                                                           MECHANICAL & ELECTRICAL

1. Are power and data services run within the wall cavity?

Yes. Where certain specialist cabling cannot be supplied (i.e. data or fire) then containment is provided within wall
construction with draw wires.

2. What electrics would be included and how would they interface with
distribution mains – plug and play or traditional connections?

Units will have first fix electrics with regard cabling and containment. Where cabling cannot be supplied (i.e. fire)
conduit will be provided with draw wires.
3. How is electrical / mechanical certification achieved?

M&E services are tested and certification provided at the point of manufacture, under the supervision of an
independent representative.
Verbus FAQ


                                                                                                    INTERNAL FF&E

1. For surface mounted items, such as shelves, are additional studs added to
the wall construction or is the plywood sufficient?

Typically the standard 10mm plywood behind the plasterboard provides sufficient grounds to fix into. Should a more
substantial substrate be required this plywood can be increased.

2. Will Verbus fit out internally to a specification to meet the Employer's
Requirements or a pre-determined specification used previously that may not
align with Employer's specification?

Each project is treated on its own merit, however Verbus. units will be fitted out to the employer's requirements as detailed in
the terms of contract unless otherwise agreed.

3. Which components would be sourced from UK?

Those which cannot be sourced in China. Typically these are reasonably few but can include specific data cabling or
fire detection systems.

4. Which components would be sourced from Europe?

Only those which cannot be sourced in China or UK.

5. Which components would be sourced from China?

The majority of the components will be sourced in China as quite often the specified components are made in China. These
can include sanitary ware, doors and door furniture, beds, light fittings etc.

6. Would bathrooms be 'podded'? Would connections be to UK standard?

Verbus have provided both bathroom pods and built-in bathrooms. It has proved more productive to construct the
bathrooms in the units in the factory rather than use pods. All connections will be to UK standard.
Verbus FAQ


                                                                                             INTERNAL FF&E

7. What happens any of the goods supplied are defective?

Verbus ensures that replacement products are available in the country of the site and will arrange for replacement to be
made where appropriate
Verbus FAQ


                                            RESISTANCE TO CONTAMINANTS & MOISTURE

1. How are DPCs dealt with where they are required at opening positions?

As with traditional construction a Thermabate or similar would be incorporated into the external wall construction around the
openings.
Verbus FAQ


                                                                         TOXIC SUBSTANCES

1. Does the standard Verbus wall insulation contain Urea-formaldehyde foam of
any other substance which could be hazardous to health? If so, how is this
managed?

No. The insulation in the Verbus wall is an approved Rockwool product.
Verbus FAQ


                                                STAIRS LIFTS & PROTECTION FROM FALLING

1. Do Verbus have a solution for a staircase within a Unit?

A staircase solution, although not offered yet, is in design stage.

2. Design of interface connection of modules with stair/lift shaft cores etc.

Verbus provides loads and recommended connection details between the units and stair/lift cores
Verbus FAQ


                                               CERTIFICATION & DESIGN LIFE

1. Longevity

60 year design life.

2. Do the Verbus units carry any recognised certification? (Eg BBA; BRE;
Warrington Fire; ETA; BS or ISO compliance.)

Designed to meet UK standards, BS codes etc.
Verbus System Design Manual
Verbus System Design Manual

More Related Content

What's hot

Design 3 2011 - Design Lecture Structures
Design 3 2011 - Design Lecture  StructuresDesign 3 2011 - Design Lecture  Structures
Design 3 2011 - Design Lecture StructuresGalala University
 
Vierendeel truss bs5
Vierendeel truss bs5Vierendeel truss bs5
Vierendeel truss bs5Sandhya Singh
 
high rise building construction
high rise building constructionhigh rise building construction
high rise building constructionAditya Sanyal
 
Analysis and Design of G+3 shopping complex
Analysis and Design of G+3 shopping complexAnalysis and Design of G+3 shopping complex
Analysis and Design of G+3 shopping complexDhananjay Singh
 
MODERN CONSTRUCTION TECHNOLOGIES IN ENGINEERING PERSPECTIVE
MODERN CONSTRUCTION TECHNOLOGIES IN ENGINEERING PERSPECTIVEMODERN CONSTRUCTION TECHNOLOGIES IN ENGINEERING PERSPECTIVE
MODERN CONSTRUCTION TECHNOLOGIES IN ENGINEERING PERSPECTIVEDr K M SONI
 
Hearst Tower, Manhattan, Dubai.
Hearst Tower, Manhattan, Dubai.Hearst Tower, Manhattan, Dubai.
Hearst Tower, Manhattan, Dubai.Mayur Waghulde
 
Pre fabricated structures
Pre fabricated structuresPre fabricated structures
Pre fabricated structuresjamali husain
 
Spanning Space, Horizontal-span Building Structures, Wolfgang Schueller
Spanning Space, Horizontal-span Building Structures, Wolfgang SchuellerSpanning Space, Horizontal-span Building Structures, Wolfgang Schueller
Spanning Space, Horizontal-span Building Structures, Wolfgang SchuellerWolfgang Schueller
 
150316 high rise design
150316 high rise design150316 high rise design
150316 high rise designTieng Wei
 
High Rise Building Research Document
High Rise Building Research DocumentHigh Rise Building Research Document
High Rise Building Research DocumentNicholas Socrates
 
Slipform construction
Slipform constructionSlipform construction
Slipform constructiontivar rose
 
Chapter 12 Light Gauge Steel Frame Construction
Chapter 12 Light Gauge Steel Frame ConstructionChapter 12 Light Gauge Steel Frame Construction
Chapter 12 Light Gauge Steel Frame ConstructionDouglas Vail
 
Form active structure system (1)
 Form active structure system (1) Form active structure system (1)
Form active structure system (1)Prince Pathania
 

What's hot (20)

Design 3 2011 - Design Lecture Structures
Design 3 2011 - Design Lecture  StructuresDesign 3 2011 - Design Lecture  Structures
Design 3 2011 - Design Lecture Structures
 
Vierendeel truss bs5
Vierendeel truss bs5Vierendeel truss bs5
Vierendeel truss bs5
 
high rise building construction
high rise building constructionhigh rise building construction
high rise building construction
 
Structural System in High Rise building
Structural System in High Rise buildingStructural System in High Rise building
Structural System in High Rise building
 
Analysis and Design of G+3 shopping complex
Analysis and Design of G+3 shopping complexAnalysis and Design of G+3 shopping complex
Analysis and Design of G+3 shopping complex
 
MODERN CONSTRUCTION TECHNOLOGIES IN ENGINEERING PERSPECTIVE
MODERN CONSTRUCTION TECHNOLOGIES IN ENGINEERING PERSPECTIVEMODERN CONSTRUCTION TECHNOLOGIES IN ENGINEERING PERSPECTIVE
MODERN CONSTRUCTION TECHNOLOGIES IN ENGINEERING PERSPECTIVE
 
Hearst Tower, Manhattan, Dubai.
Hearst Tower, Manhattan, Dubai.Hearst Tower, Manhattan, Dubai.
Hearst Tower, Manhattan, Dubai.
 
Pre fabricated structures
Pre fabricated structuresPre fabricated structures
Pre fabricated structures
 
Spanning Space, Horizontal-span Building Structures, Wolfgang Schueller
Spanning Space, Horizontal-span Building Structures, Wolfgang SchuellerSpanning Space, Horizontal-span Building Structures, Wolfgang Schueller
Spanning Space, Horizontal-span Building Structures, Wolfgang Schueller
 
150316 high rise design
150316 high rise design150316 high rise design
150316 high rise design
 
Steel Roof Truss
Steel Roof TrussSteel Roof Truss
Steel Roof Truss
 
High Rise Building Research Document
High Rise Building Research DocumentHigh Rise Building Research Document
High Rise Building Research Document
 
Concrete
ConcreteConcrete
Concrete
 
Slipform construction
Slipform constructionSlipform construction
Slipform construction
 
Architectural details
Architectural detailsArchitectural details
Architectural details
 
Chapter 12 Light Gauge Steel Frame Construction
Chapter 12 Light Gauge Steel Frame ConstructionChapter 12 Light Gauge Steel Frame Construction
Chapter 12 Light Gauge Steel Frame Construction
 
Folded plates
Folded platesFolded plates
Folded plates
 
Form active structure system (1)
 Form active structure system (1) Form active structure system (1)
Form active structure system (1)
 
Shell structure.pdf
Shell structure.pdfShell structure.pdf
Shell structure.pdf
 
Pragati towers
Pragati towersPragati towers
Pragati towers
 

Viewers also liked

Shipping Container Architecture Research
Shipping Container Architecture ResearchShipping Container Architecture Research
Shipping Container Architecture ResearchPB4000XL
 
2015 03 23 SPS Floors - Generic Presentation
2015 03 23 SPS Floors - Generic Presentation2015 03 23 SPS Floors - Generic Presentation
2015 03 23 SPS Floors - Generic PresentationQipei Mei
 
INNOVATIVE TECHNOLOGY FOR LIGHTWEIGHT CONSTRUCTION
INNOVATIVE TECHNOLOGY FOR LIGHTWEIGHT CONSTRUCTIONINNOVATIVE TECHNOLOGY FOR LIGHTWEIGHT CONSTRUCTION
INNOVATIVE TECHNOLOGY FOR LIGHTWEIGHT CONSTRUCTIONСергей Власкин
 
STRENGTHENING OF RC BEAMS USING FRP SHEET
STRENGTHENING OF RC BEAMS USING FRP SHEETSTRENGTHENING OF RC BEAMS USING FRP SHEET
STRENGTHENING OF RC BEAMS USING FRP SHEETIjripublishers Ijri
 
Building construction 1 experiencing construction (zone innovation park klang)
Building construction 1 experiencing construction (zone innovation park klang)Building construction 1 experiencing construction (zone innovation park klang)
Building construction 1 experiencing construction (zone innovation park klang)Darshiini Vig
 
Building construction 1 experiencing construction (zone innovation park klang)
Building construction 1 experiencing construction (zone innovation park klang)Building construction 1 experiencing construction (zone innovation park klang)
Building construction 1 experiencing construction (zone innovation park klang)Chow Hong Da
 
Prefab Container House
Prefab Container HousePrefab Container House
Prefab Container Housesoodkartik
 
Sustainable Building Design with Shipping Containers
Sustainable Building Design with Shipping ContainersSustainable Building Design with Shipping Containers
Sustainable Building Design with Shipping ContainersDallas College
 
Production Management
Production ManagementProduction Management
Production ManagementUmar Khan
 
Lean presentation ppt
Lean presentation pptLean presentation ppt
Lean presentation pptbwu.nl
 

Viewers also liked (12)

Shipping Container Architecture Research
Shipping Container Architecture ResearchShipping Container Architecture Research
Shipping Container Architecture Research
 
архитектура Prefab city
архитектура Prefab city архитектура Prefab city
архитектура Prefab city
 
2015 03 23 SPS Floors - Generic Presentation
2015 03 23 SPS Floors - Generic Presentation2015 03 23 SPS Floors - Generic Presentation
2015 03 23 SPS Floors - Generic Presentation
 
INNOVATIVE TECHNOLOGY FOR LIGHTWEIGHT CONSTRUCTION
INNOVATIVE TECHNOLOGY FOR LIGHTWEIGHT CONSTRUCTIONINNOVATIVE TECHNOLOGY FOR LIGHTWEIGHT CONSTRUCTION
INNOVATIVE TECHNOLOGY FOR LIGHTWEIGHT CONSTRUCTION
 
STRENGTHENING OF RC BEAMS USING FRP SHEET
STRENGTHENING OF RC BEAMS USING FRP SHEETSTRENGTHENING OF RC BEAMS USING FRP SHEET
STRENGTHENING OF RC BEAMS USING FRP SHEET
 
Building construction 1 experiencing construction (zone innovation park klang)
Building construction 1 experiencing construction (zone innovation park klang)Building construction 1 experiencing construction (zone innovation park klang)
Building construction 1 experiencing construction (zone innovation park klang)
 
Building construction 1 experiencing construction (zone innovation park klang)
Building construction 1 experiencing construction (zone innovation park klang)Building construction 1 experiencing construction (zone innovation park klang)
Building construction 1 experiencing construction (zone innovation park klang)
 
Prefab Container House
Prefab Container HousePrefab Container House
Prefab Container House
 
Sustainable Building Design with Shipping Containers
Sustainable Building Design with Shipping ContainersSustainable Building Design with Shipping Containers
Sustainable Building Design with Shipping Containers
 
Production Management
Production ManagementProduction Management
Production Management
 
INDUSTRIALISED BUILDING SYSTEMS & MODULAR COORDINATION
INDUSTRIALISED BUILDING SYSTEMS & MODULAR COORDINATIONINDUSTRIALISED BUILDING SYSTEMS & MODULAR COORDINATION
INDUSTRIALISED BUILDING SYSTEMS & MODULAR COORDINATION
 
Lean presentation ppt
Lean presentation pptLean presentation ppt
Lean presentation ppt
 

Similar to Verbus System Design Manual

Verrex Global Portfolio 01 12 A4
Verrex Global Portfolio 01 12 A4Verrex Global Portfolio 01 12 A4
Verrex Global Portfolio 01 12 A4jamesjshanks
 
Verrex Global Portfolio
Verrex Global PortfolioVerrex Global Portfolio
Verrex Global Portfoliojmakverrex
 
Verrex Global Portfolio
Verrex Global PortfolioVerrex Global Portfolio
Verrex Global Portfoliosarbar1030
 
Verrex Global Portfolio
Verrex Global PortfolioVerrex Global Portfolio
Verrex Global Portfoliodkwok
 
Verrex Global Portfolio
Verrex Global PortfolioVerrex Global Portfolio
Verrex Global Portfoliosarbar1030
 
Verrex Global Portfolio
Verrex Global PortfolioVerrex Global Portfolio
Verrex Global Portfoliolynnsaccone
 
Verrex Global Portfolio
Verrex Global PortfolioVerrex Global Portfolio
Verrex Global Portfoliotberryjr
 
Verrex Global Portfolio
Verrex Global PortfolioVerrex Global Portfolio
Verrex Global Portfolioevanscottsmith
 
Verrex Global Portfolio
Verrex Global PortfolioVerrex Global Portfolio
Verrex Global PortfolioSabinop
 
Verrex Global Portfolio
Verrex Global PortfolioVerrex Global Portfolio
Verrex Global Portfoliolhense
 
Verrex Global Portfolio
Verrex Global PortfolioVerrex Global Portfolio
Verrex Global Portfoliomsidarous
 
Verrexglobalportfolio0311 13039310810099 Phpapp02
Verrexglobalportfolio0311 13039310810099 Phpapp02Verrexglobalportfolio0311 13039310810099 Phpapp02
Verrexglobalportfolio0311 13039310810099 Phpapp02FiDRaT
 
Verrex E Portfolio 2011
Verrex E Portfolio 2011Verrex E Portfolio 2011
Verrex E Portfolio 2011wchivil
 
Verrex Global Portfolio
Verrex Global PortfolioVerrex Global Portfolio
Verrex Global Portfoliosarbar1030
 
Verrex E Portfolio 2011
Verrex E Portfolio 2011Verrex E Portfolio 2011
Verrex E Portfolio 2011wchivil
 
Verrex Global Portfolio
Verrex Global PortfolioVerrex Global Portfolio
Verrex Global Portfoliojhealy8270
 
Verrex Global Portfolio
Verrex Global PortfolioVerrex Global Portfolio
Verrex Global Portfoliobbaretz
 
Verrex Global Portfolio
Verrex Global PortfolioVerrex Global Portfolio
Verrex Global Portfoliocraadverrex
 

Similar to Verbus System Design Manual (20)

Verrex portfolio 2012
Verrex portfolio 2012Verrex portfolio 2012
Verrex portfolio 2012
 
Verrex Global Portfolio 01 12 A4
Verrex Global Portfolio 01 12 A4Verrex Global Portfolio 01 12 A4
Verrex Global Portfolio 01 12 A4
 
Verrex Global Portfolio
Verrex Global PortfolioVerrex Global Portfolio
Verrex Global Portfolio
 
Verrex Global Portfolio
Verrex Global PortfolioVerrex Global Portfolio
Verrex Global Portfolio
 
Verrex Global Portfolio
Verrex Global PortfolioVerrex Global Portfolio
Verrex Global Portfolio
 
Verrex Global Portfolio
Verrex Global PortfolioVerrex Global Portfolio
Verrex Global Portfolio
 
Verrex Global Portfolio
Verrex Global PortfolioVerrex Global Portfolio
Verrex Global Portfolio
 
Verrex Global Portfolio
Verrex Global PortfolioVerrex Global Portfolio
Verrex Global Portfolio
 
Verrex Global Portfolio
Verrex Global PortfolioVerrex Global Portfolio
Verrex Global Portfolio
 
Verrex Global Portfolio
Verrex Global PortfolioVerrex Global Portfolio
Verrex Global Portfolio
 
Verrex Global Portfolio
Verrex Global PortfolioVerrex Global Portfolio
Verrex Global Portfolio
 
Verrex Global Portfolio
Verrex Global PortfolioVerrex Global Portfolio
Verrex Global Portfolio
 
Verrex Global Portfolio
Verrex Global PortfolioVerrex Global Portfolio
Verrex Global Portfolio
 
Verrexglobalportfolio0311 13039310810099 Phpapp02
Verrexglobalportfolio0311 13039310810099 Phpapp02Verrexglobalportfolio0311 13039310810099 Phpapp02
Verrexglobalportfolio0311 13039310810099 Phpapp02
 
Verrex E Portfolio 2011
Verrex E Portfolio 2011Verrex E Portfolio 2011
Verrex E Portfolio 2011
 
Verrex Global Portfolio
Verrex Global PortfolioVerrex Global Portfolio
Verrex Global Portfolio
 
Verrex E Portfolio 2011
Verrex E Portfolio 2011Verrex E Portfolio 2011
Verrex E Portfolio 2011
 
Verrex Global Portfolio
Verrex Global PortfolioVerrex Global Portfolio
Verrex Global Portfolio
 
Verrex Global Portfolio
Verrex Global PortfolioVerrex Global Portfolio
Verrex Global Portfolio
 
Verrex Global Portfolio
Verrex Global PortfolioVerrex Global Portfolio
Verrex Global Portfolio
 

Verbus System Design Manual

  • 1. Verbus System Design Manual issue 003: March 2009
  • 2. overview VERBUS > Significantly improved programme times compared to traditional construction. > Improved project costs. > Deliverable anywhere in the world. > Up to 16 stories achievable with a standard module. > Reduced on site project and commercial management required by Main Contractor.
  • 3. CONTENTS 1 Verbus System > What is Modular Construction? > Why use Modular Construction? > How does Verbus differ from other systems? > Verbus Cycle 2 Verbus Process > The Team > The Design Process > Limitless Solutions > Modular Building Concept 3 Verbus Technology > Construction > Geometries > Structure > Assembly and H&S > Robustness & Durability > Fire > Acoustics > Thermal Performance > Heat & Ventilation > Sustainability > Standard Details 4 Verbus FAQ’s > Structure > Manufacture & Delivery > External Treatment: Roofing Facade/ Cladding > Glazing > Acoustic Design > Conservation of Fuel & Power - Thermal > Fire Safety > Drainage > Mechanical & Electrical > Internal FF&E > Resistance to Contaminants & Moisture > Toxic Substances > Stairs Lifts & Protection from Failing > Certification & Design Life
  • 4. 1 Verbus System > What is Modular Construction? > Why use Modular Construction? > How does Verbus differ from other systems? > Verbus Cycle
  • 5. VERBUS SYSTEM Modular Construction WHAT is modular WHY use modular construction? construction? Modular technology considerably reduces construction time. It is safer, quieter and cleaner than traditional methods of construction. It reduces the likelihood of defects and allows easy and low cost maintenance. It also offers designers The term modular construction and architects flexibility which is cost-effective. is used where a building is Modular construction has many benefits in terms of labour skills, programme and quality. National Audit Office assembled from a series of statistics: volumetric modules, linked together to form a complete 1.Construction times can be reduced by 60%, saving both programme time and associated preliminary costs. structure. The modules, which are manufactured, finished and 2.On-site Labour is typically reduced by 70% compared to traditional construction techniques, which leads to considerable benefits on site for access, storage of materials and Health & Safety issues in general. fitted-out off-site, under factory conditions, are then 3.The building envelope can be made water tight up to 80% faster than through traditional construction techniques, transported to the construction leading to reduced risks due to weather. site and lifted into place. All which lead to greater speed, productivity, quality and safety thus ensuring earlier completion and greater revenue generation. HOW does Verbus differ from other systems? The Verbus system is built around newly developed, patented technology, and is far more robust than any other system on the market. The Verbus system is based on the fittings and transportation characteristics of the universal shipping container hence Verbus modules are not only highly robust, versatile and economic but they are also highly suitable for both international and national sea and road transportation using conventional vehicle logistics. The Verbus system with its steel frame and panelised lightweight wall construction are particularly suitable for use as structural modules making additional steel framing unnecessary. The robustness and rigidity of Verbus modules also allows far greater variety in the type of finishing that can be applied to the exterior of the building and the quality and level of fit-out that can be introduced to the interior The Verbus system is generally self stabilising and does not require support from the staircases or riser cores, removing the construction of these items from the critical path. Finally the close integration and vast experience of the Verbus design team, logistics department and module manufacturer, mean that when initial concept schemes are considered, total optimisation can be built-in at an early stage.
  • 6. VERBUS SYSTEM Verbus Building Cycle fabrication fitout shipping docking The Verbus System utilises established production techniques and capacity to manufacture quality accommodation solutions at high volume. The basis of the system is a range of High Strength, corrosion resistant steel manufactured modules fully certified, tested and approved that can be fully fitted out and combined to create a wide variety of building shapes and be adapted to suit any planning or end user needs. The Verbus System is also revolutionary in that it is fully de-mountable and re-usable. road transport dismantle completion connection installation re-furbish re-assabmle
  • 7. 2 Verbus Process > The Team > The Design Process > Limitless Solutions > Modular Building Concept
  • 8. VERBUS PROCESS The Team The Verbus Team provides full technical support and detailed information on all aspects of the Verbus Systems solution. Working closely with Client’s Team to ensure a seamless interface and a fully integrated building solution. Verbus Systems have worked closely with industry professionals to develop a highly versatile, efficient and r o b u s t m o d u l a r b u i l d i n g s y s t e m . Ve r b u s S y s t e m s c a n provide a full design and service to clients ranging from foundations to finishes. Working with contractors they can deliver and erect their patented volumetric modular system as a shell or fully fitted finish. Buro Happold have helped develop Verbus Systems design and technology over the last 3 years. This has been achieved through detailed design development of the structural engineering, fire, thermal and acoustic performance of the units in order to gain compliance with local building regulations. Initially the projects have been in the UK, but they are now being developed further for approval in other European countries as well as North America and the Middle East K KA h a v e a s s i s t e d i n t h e d e s i g n a n d d e l i v e r y o f numerous Verbus Systems projects throughout the UK and other worldwide locations. From inception to completion, through in depth understanding of the system, KKA can provide full design solutions or simply advise on developing the most economical Verbus solution.
  • 9. VERBUS PROCESS The Design Process The Design Process Verbus Design Stages Stage 1A: Initial Viability Appraisal The Verbus Team provides full technical support and detailed Identify Client's requirements, propose multiple options to maximise use of Verbus Modular Units within the scheme. information on all aspects of the Demonstrate the flexibility with which the Verbus Modular Units can accommodate diverse layouts and multiple Ve r b u s S y s t e m s s o l u t i o n building types. ensuring a seamless interface between the Verbus System Stage 1B: Preliminary Unit Types and Layouts and all other building Prepare outline proposals based on clients preferred options including basic schedule on Units Types and Sizes. components. Liaise with Client Team to explain the fundamental principals of the Verbus System and its integration into a complete building solution. The Verbus Design Team can offer a full building design Stage 2: Detailed Unit Types and Layouts service, but where required will Prepare initial GA drawings including all setting out and structural parameters . work alongside the Client's Team Liaise with Client Design Team on all building interface issues and prepare generic information on Structural, M&E, through every stage of the Thermal, Fire and Acoustic performance of Verbus components. design process to ensure a fully Prepare detailed schedule of Unit Types, Sizes and Fit-out. integrated, optimised and statutory compliant building Stage 3A – C: Unit Shell and Structure Plans, Sections & Elevations solution is achieved. Prepare detailed Unit Shell fabrication drawings and carry out all structural calculations etc. in conjunction with Unit Shell. Early involvement of the Verbus Liaise with manufacturer to ensure fabrication drawings / specifications are optimized for Unit Shell construction and Team in the design of a building economy. leads to greater flexibility and greater economic and Stage 4A – D: Unit Fit-out Plans, Sections, Elevations & Schedules programme benefits. Prepare detailed internal fit-out drawings and schedules based on the clients Employers Requirements Documents for client approval and fabrication. The Verbus Team becomes a Liaise with manufacturer to ensure fit-out drawings / specifications are optimized for Unit Shell construction and fully integrated part of the overall economy. Project Team attending briefing, Prepare detailed M&E drawings and specifications for all services to be provided in Verbus fit-out design, and contractor / site Stage 5: Unit Interface / Co-ordination Remaining Building Fabric. meetings and ensuring a continuous flow of information Prepare all information necessary to ensure Verbus System can be integrated by Client Design team with all between all parties. remaining building fabric.
  • 10. VERBUS PROCESS Case Study 1: The Design Process PROPOSED HOTEL VERBUS STAGE 1A OPTIMISATION STUDY VERBUS PROPOSALS TOTAL NUMBER OF BEDROOMS: 80 TOTAL NUMBER OF VERBUS STOREYS: 3 Staircase could be provided in Verbus unit. Note: careful co-ordination required. Traditional steel frame podium structure LEVEL 1 Corner could be provided in Verbus or traditional. Note: Half units are Option2: Greater economy as ORIGINAL PROPOSALS less economical than units are the same full units. To achieve greater economics, Junction will need consideration reduce number of where Verbus units intersect. types. Module Module Module Module OPTION 1 OPTION 2 LEVEL 2 - 3
  • 11. VERBUS PROCESS Case Study 2: The Design Process VERBUS PROPOSALS Line of original tower. PROPOSED HOTEL VERBUS STAGE 1A OPTIMISATION STUDY TOTAL NUMBER OF BEDROOMS: 230 TOTAL NUMBER OF VERBUS STOREYS: 9 LEVEL 1 Building extended to rationalise the use of Verbus units. Keep corridor central if possible to maximise economy. All elevational modelling as “decorative” cladding/balconies etc. This ensures maximum off site fit out. ORIGINAL PROPOSALS LEVEL 2-6 Mix of rooms depandant on width of site. All elevational modelling as “decorative” cladding/balconies etc. This ensures maximum off site fit out. LEVEL 7
  • 12. VERBUS PROCESS Case Study 3: The Design Process VERBUS PROPOSALS Ground and mezzanine floor levels to be traditionally constructed Dashed line indicates outline of upper floors. Extent of Bedroom accommodation over. PROPOSED HOTEL VERBUS STAGE 1A OPTIMISATION STUDY TOTAL NUMBER OF BEDROOMS: 70 TOTAL NUMBER OF VERBUS STOREYS: 5 ORIGINAL PROPOSALS GROUND & MEZZ LEVEL Proposed void space, will require fire stopping. Traditionally constructed bridging infill. Continuity of finishes maintained by lining of corridor wall face on site/ typical ‘zip-up’ detail. External cladding to face of all units by contractor. Standard Units arranged radially. LEVEL 1 - 4 RESIDENTIAL BY OTHERS HOTEL BY VERBUS Module can be delivered with staircase insitu. Module Module Module Voids for lift shafts. LEVEL 5
  • 13. VERBUS PROCESS Case Study 4: The Design Process VERBUS PROPOSALS Traditional Frame Structure & Fit Out will be required to corners. PROPOSED STUDENT ACCOMMODATION: VERBUS STAGE 1A OPTIMISATION STUDY TOTAL NUMBER OF BEDROOMS: 740 TOTAL NUMBER OF VERBUS STOREYS: 20 Traditional Frame Structure & Fit Out will be required to corners and Braced Slightly Larger Units Corners. to accommodate Stair approx 200-300 mm wider than Standard Room. Thus Structure “Lines” through. Traditional Frame Structure & Fit Out will be required to corners. Possible Extra Rooms could be achieved. LEVEL 1-6 LEVEL 7 LEVEL 8 However Implication is 2no. 6 Bed Clusters. Traditional Frame Structure & Fit Out will be required to corners. ORIGINAL PROPOSALS Traditional Frame Structure & Fit Out will be required to corners and Braced Module Corners. LEVEL 9,10 LEVEL 11- 20
  • 14. VERBUS PROCESS Limitless Solutions Variable length, height, width, orientation, juxtaposition, layout and finish construct endless design solutions and building layouts. Modular construction need not be limited by a single solution only your imagination. consider the time, cost & quality benefits of a fully finished modular building solution. 1 pre-fabricated frame pre-fabricated ground floor podium structure delivered to site for rapid assembly 2 building blocks fully fitted & finished room modules containing bedrooms, circulation & services accommodation “stacked” up to 15 storeys without the need for additional framing 3 modular roof fully finished roof modules pre-laid to fall & complete with gutter system fitted to the upper storey and integrated with pre-installed plant modules if required 4 “clip on” cladding modules are designed to be clad with an external skin, but can be delivered fully insulated and glazed, ready for habitation
  • 15. VERBUS PROCESS Modular Building Concept pre- fabricated roof modules utilize modules lowered and bolted Verbus connection technology shipped in into place “batches” in the volume of a shipping module upper circulation module pre-fitted with lifts stairs pre-fitted in circulation ready to “drop” upon completion of vertical modules core modular cladding system as single component (where required) enhancement features can be attached before module is lifted into place option A. ground floor structure provided as traditional construction complete modular units craned into position option B. ground floor structure provided as a ready to assemble prefabricated “kit of parts” option C. ground floor podium structure provided in Verbus units with Verbus spacer signature cladding frames providing extra height if required system can be attached in module size sections before module is lifted into place
  • 16. 3 Verbus Technology > Construction > Geometries > Structure > Assembly and H&S > Fire > Acoustics > Thermal Performance > Heat & Ventilation > Sustainability > Standard Details
  • 17. VERBUS TECHNOLOGY Construction: The Basic Verbus Module The basic Verbus module comprises a “shell” of high tensile corrosion resistant steel components with composite wall, floor and roof structure that provides superior insulation for sound, thermal & fire performance.
  • 18. VERBUS TECHNOLOGY Construction: The Basic Verbus Shell intermediate castings are introduced depending on unit size to ensure maximum flexibility for transportation lifting stacking & docking the module frame comprises lightweight folded plate rails and posts Composite roof comprises: - 1.6mm Corten steel flat outer sheet units are permanentlybolted/ - 100mm mineral wool insulation secured once on site via a simple bolt - “C” channel steel joists box - 9mm plywood - 2 layers of 12.5mm plasterboard openings are framed with closure posts & head & sill rails the frame is stiffened by lightweight 1.6mm gauge corrugated steel sheets i.e. the frame and outer sheet act as a lightweight diaphragm structure a grid of simple plates & standard industry connections are installed to ensure a perfect fit & interface with other building components Composite wall comprises: - 1.6mm Corten Steel profiled outer sheet plasterboard - 40mm insulation outersheet - lining support rails insulation plywood - 9mm plywood primary lining - 2 layers of plasterboard secondary lining rails standard shipping “castings” - used for lifting docking & securing Composite floor comprises: - 28mm plywood - 100mm mineral wool insulation - rubber separation gaskets - “C” channel steel joists - 1.6mm Corten steel flat outer sheet
  • 19. VERBUS TECHNOLOGY Geometries Verbus Module dimensions can be a range of sizes. The most common dimensions of which are 6ft or 8ft x 40ft (2,438mm or 3660 mm x 12,192mm). The adjacent Matrix highlights how Verbus Modules which harmonize with multiples of these dimensions to give greater economies. Longer units combining more volumes into a single module will provide greater savings than a series of smaller modules containing the same independent spaces. Projects are not limited to 'standard' sizes and a full range of Module sizes can be provided. Geometry ‘V’ Economy Matrix: minimum optimum maximum 6058 to 12192 to 14273 minimum 2438 variable widths to optimum 3660 to Good Value Very Good Value maximum 4022 Excellent Value variable lengths
  • 20. VERBUS TECHNOLOGY Structure stability side & end unit walls to provide Verbus Modules are high strength building stability steel frame and metal plate diaphragm structures based on universal shipping container design, revised to suit the requirements and demands of the construction industry. The units are fabricated from rolled steel sections, with the wall structure of the shipping container acting as a load bearing structural element and floor and roof construction designed to satisfy the loading and dynamic response conditions of a multi- storey building. Because of their inherent strength, the units can be stacked as high as high as 15 to 20 storeys. For stability, the units laid side by side are connected to each other using spigots and sockets, and bolted plates. When fully connected the units are mostly self load paths stabilising and do not require the support of corner + intermediate posts support vertical loads independent steel frames or cores.
  • 21. VERBUS TECHNOLOGY Assembly and H&S Assembly is simple, fast and safe. The Verbus System can be provided on a simple foundation solution or on a steel or concrete podium. The design allows for rapid erection with low-technology, fail safe bolted connections. The units are weatherproof so that interiors remain protected during the assembly process. Modules are fully fitted out before arrival on site. Modules can be erected and bolted together internally without external scaffolding. The installation process includes a temporary barrier system which in conjunction with man-safes and safety harnesses provides a rapid and safe method of construction. Due to the small number of large lifts and the absence of traditional materials on site, this modular construction method offers the opportunity for a significant reduction in the number of hazards on site.
  • 22. VERBUS TECHNOLOGY Robustness & Durability boxes high yield structural steel boxes bolting phase 1 The Verbus units are manufactured internal corridor bolting from weather-resistant Corten A steel. This is a material with a yield stress of at least 375N/mm2. The Corten A steel is used for the corrugated walls of the unit and also for rolled steel sections including perimeter beams and load bearing posts. When bolted together, the boxes form a continuous tied structure which prevents disproportionate collapse of the building should a single unit become damaged and fail. The external steel box also provides a vapour barrier, and allows the individual building elements to be weather- tight during transportation and construction The units have been prototyped and load tested, and all materials are certified by testing. corrosion protection Workmanship in the factory is painted corten steel (anti-rust) protection bolting phase 2 independently monitored and controlled by external vertical and horizontal bolting ties to prevent Lloyds Insurance. disproportionate collapse
  • 23. VERBUS TECHNOLOGY Fire Strategy fire protected riser shaft cavity between units: class 0 fire sterile environment The building system is designed fire resistance of unit is 1 - 2 hours to meet Building Regulations for Fire Safety, which covers means of escape, spread of flame, fire performance and access for fire- fighting. The modular units can be built to resist a fire for up to 2 hours. Spread of flame through the corridors or via the windows is prevented by conventional fire stopping. The spaces between the units are treated as fire sterile areas and are sealed off from the other spaces in the building. In the event that a module is damaged during a fire the surrounding units remain tied together and fully supported. Escape stairs and corridors can be treated in a similar way to a conventional building. corridor “zip-up” linings provide cavity fire barriers external envelope insulation provides fire barrier in cladding zone
  • 24. VERBUS TECHNOLOGY Acoustic Performance >54 Dntw Ctr dB Floor/ceiling noise reduction The modular units meet and floor to ceiling impact noise transfer < 55Lntw dB exceed minimum building regulation noise reduction levels, and can accommodate sound isolation requirements for residential and hotel buildings. Air borne noise and structure borne sounds are successfully isolated by the layers of plasterboard, insulation and air gaps between the units. A range of external noise isolation measures can be achieved through the specification of appropriate cladding working in conjunction with the noise reduction of the units themselves. >50Dntw + Ctr dB noise reduction between rooms units + external cladding provide noise reduction
  • 25. VERBUS TECHNOLOGY Thermal Performance it should be noted that the outer steel sheet of the Verbus unit is The Building Regulations will considered as the vapour barrier. In order specify minimum standards to be achieved for this to be successful, and to mitigate the risk of interstitial condensation, for thermal performance of the building additional insulation must be provided against the external steel face of the unit. design, including the building fabric. The assessment method usually requires the performance of the entire building to be composite roof: R=1.31m2K/W measured against standard criteria for carbon emissions. The thermal performance of the Verbus System is measured in conjunction with the external wall and insulation, plywood and minimum 2 layers composite wall: R=1.09m2K/W plasterboard for combined optimum thermal and acoustic performance, composite floor: R=1.31m2K/W achieving the best possible elemental value without compromising the available floor area. The adjacent diagram provides indicative elemental Thermal Resistance Values (R - Value) for the wall, floor and roof of the Verbus Systems Shell. These values can of course be increased, with a small loss of floor area, by increasing insulation thickness and lining specification.
  • 26. VERBUS TECHNOLOGY Heat & Ventilation extract via bathroom riser heat & ventilation option 2: supply & extract temperature controlled air ducted from roof to fan coil units in bedroom ceilings The units can meet current Building Regulations standards for thermal performance, air-tightness and general building servicing requirements with an appropriate specification for the building fabric. Heat and ventilation can be provided locally in the modules or if a sealed façade and ducted air solution is required, via temperature controlled ventilation fancoil units. The modules are pre-fabricated with pre-formed service riser positions to allow the installation of ductwork both horizontally and vertically. Plant and equipment outside the modules will be installed on site, with the pre-fabrication concentrated within the heat & ventilation option 1: modules and local risers. external trickle ventilation The level of pre-fabrication local heater unit in the room will vary between the different types of building and there will be connections of ductwork and services to be made between the units horizontally and vertically dependant on the design strategy for the ventilation system of the modules.
  • 27. VERBUS TECHNOLOGY Sustainability 40 year life cycle Material Transport Dismantling Extraction Second to Construction Operation & rebuild/ and operation site Rebuild processing The Verbus building system brings the following benefits in terms of Stage 1 Stage 2 sustainability: 1. Minimised transport and CO2 Stage One & Stage Two: Impact of Reuse Summary of Verbus Building emissions. (over 40 year Design Life) Materials are sourced close to the factory. The steel used contains re-cycled material. The amount of fossil fuels used for shipping and transportation is less than the fuels used for deliveries by traditional on-site construction techniques. 2. Re-use of the units. The units can be unbolted and refurbished for re-use. They are also flexible and adaptable for modification. 3. Minimised use of Materials and Waste. The prefabrication process maximises the use of material in manufacture, and minimises waste created on site. 4. Good Air-tightness and thermal performance. The continuous outer steel box prevents air leakage allowing venting to be carefully controlled through trickle vents. The Alternative technologies can be incorporated into the Verbus box is insulated inside and out providing good thermal and system to reduce external power and water consumption, such as: acoustic performance. 5. Shading devices and other façade Solar thermal collectors, Photo-voltaics, Ground source Heat pumps, Biomass boiler, Greywater elements: These can be modularised and fixed to the Recycling. outside of the Verbus boxes without additional strengthening. The other measures that can be taken to reduce the environmental impact of the building include good building orientation and use of daylight, natural ventilation and cooling, efficient land use, respect to ecology, efficient water usage, good operation management, and low energy services such as lighting.
  • 28. VERBUS TECHNOLOGY Standard Details wall construction (plan) roof construction (section) floor construction (section)
  • 29. 5 Verbus FAQ’s > Structure > Manufacture & Delivery > External Treatment: Roofing Facade/ Cladding > Glazing > Acoustic Design > Conservation of Fuel & Power - Thermal > Fire Safety > Drainage > Mechanical & Electrical > Internal FF&E > Resistance to Contaminants & Moisture > Toxic Substances > Stairs Lifts & Protection from Falling > Certification & Design Life
  • 30. Verbus FAQ STRUCTURE 1. What is the wall make-up between units for wall acting as party wall? Standard Verbus detail would be two layers 12.5mm fireline, 1 layer of 10mm plywood, 40mm metal stud with rockwool insulation 1.6mm Corten steel folded to give a 20.5mm corrugation. There would be an air gap of approximately 28m before adjacent unit provides an identical wall build up. Typical overall thickness 220mm. 2. What is the wall make-up for an external wall? As detailed above, but Corten steel wall would then have additional insulation, a cavity then the external facade (brick, rendered panel , timber, aluminium cladding etc.) 3. There appear to be a number of posts in the front elevation: is this standard or is this due to opening that is created? There are some posts required in the end walls to give the unit robustness during shipping and stacking on a vessel. Some of these posts can be removed once the unit is in its permanent state (i.e. erected as a building). Some Posts are to form window/ door apertures as required. 4. Is it possible to completely remove the front of a unit? Dependant on width of unit and adjacent structure. The top, bottom & end joists will always be required as will the columns on the corners of the unit. The remainder of the end wall could be removed in the right situation. 5. Will our openings require similar framing? Yes. All openings will need to be framed. There is an opportunity to use the essential elements of structure for this framing (as mentioned above) or an additional frame would be required.
  • 31. Verbus FAQ STRUCTURE 6. Do Verbus design and warrant the overall building stability including core? Verbus will warrant the design of the structure of the Verbus elements of a building. Where a building contains elements of steel / concrete frame (i.e. cores or large open span areas) these elements may designed by the Verbus project engineer. It is the project engineer who takes overall responsibility for the building as a whole. 7. Do Verbus provide wind loading design? Verbus units will be designed for wind loading pressures provided by the structural engineer. 8. Do Verbus provide load bearing design including cladding loads? Dead and live loads would be agreed with the structural engineer. Verbus can provide loadings for interface with supporting structures (e.g. Transfer decks and cores.) 9. Do Verbus provide disproportionate collapse safeguard design? The units are designed and detailed to transmit tie forces to BS 5950 in the event of loss of support. 10. Do Verbus provide loadings for ground slab design? Loads due to Verbus units in contact with the ground slab would be provided by Verbus to the structural engineer designing the ground floor slab. 11. Do Verbus provide loadings for design of foundations? Verbus provides unit loads for incorporation into foundation designs. Note that weight of cladding, roof top plant and other loadings to be provided by the structural engineer.
  • 32. Verbus FAQ MANUFACTURE & DELIVERY 1. What would be the period required for Verbus to prepare drawings, issue for comment, amend and re-issue for construction? Very much dependent on the size of project and variation of unit types. Typically 6-8 weeks from order being placed to Verbus Design Freeze being achieved assuming the Clients Design is “frozen”. 2. What period would be required for manufacture and despatch from factory from the date of construction issued drawings? Typically twelve weeks. 3. What period would be required from factory despatch date for shipping and delivery to site, including time to negotiate exit and entry ports? Typically four weeks. 4. What holding/ storage or other arrangement is provided by Verbus to facilitate a phased delivery to meet the site programme of erection? As required we use a national road haulier with storage facilities throughout the UK 5. Given a clear run, what average site erection rate would Verbus expect to achieve per week – (modules delivered, placed and structurally connected.) Verbus could achieve a rate of ten units per day 6. Will Verbus inspect / accept foundations and erect modules, and attach structurally to the cores and foundations. This is subject to contract conditions. Verbus can carry out these procedures if required
  • 33. Verbus FAQ MANUFACTURE & DELIVERY 7. What protection do units have in transit? The outer skin of the units is 1.6mm Corten Steel. This requires no additional protection. 8. What happens if the boat sinks or a unit falls off the side of the vessel? Verbus provide insurance to cover any such transit related issues. This insurance is valid from the manufacturing facility through to delivery to site.
  • 34. Verbus FAQ EXTERNAL TREATMENT: ROOFING FACADE/ CLADDING 1. Have you ever used a bespoke metal cladding solution externally? There are currently two live projects which utilise metal cladding in part of the external façade system. However the outer face of the unit must be insulated. 2. What rules have to be followed for the fixings / spacing of cleats etc. which cladding rails, trims and flashings can be fixed to? The Verbus units provide fixing points for cladding rails at the top and bottom of the side and end walls. Should brick ties or similar be required then plates are welded to the external skin as required. 3. Cladding connection provision The Verbus units have a steel structure allowing different cladding systems to be fixed to the outside of the units. Flat plates, “Ancon” brackets and other fixing points are provided on the unit for cladding attachments to be added. 4. What types of cladding can be applied to the module and what provision do Verbus make in each case for fixing. Any cladding system can be fixed to a Verbus unit. The standard provision is either brick tie plates welded to the external skin of the unit plus “Ancon” brackets along top and bottom rails to take vertical cladding rails. We would have early discussions with the cladding contractor to ensure that the interfaces are known. 5. Do Verbus normally provide external doorsets and/ or windows factory fitted and glazed? No, not normally. If the employer requires such items they can be supplied loose inside modules. However windows & doors could be pre-installed in the right situation. 6. Can a parapet detail be added to the Verbus units by means of a standard Verbus connection detail? Previous projects have had parapets formed in situ from a timber construction fixed through into the top rail of the units. However in the right situation yes this could be achieved.
  • 35. Verbus FAQ GLAZING 1. How do you deal with window penetrations in a UK brick clad scheme? With particular interest in what the sequence / detail is once the opening has been 'knocked out'. Is the reveal of the Verbus unit simply dry lined from within on site? The window reveal has straps or brackets fixed to it to support the window (which is primarily in the wall cavity). Once the window is fitted the reveal is lined with 1 layer 12.5mm vapour check plasterboard and 1 layer 12.5mm soundbloc plasterboard as standard 2. If the reveal is dry lined on site, how is fixing achieved into the steel surround? Are grounds required first? Grounds are not required first. The plasterboard can be fixed directly to the steel frame of the window aperture. Alternatively a plywood lined reveal could be provided. 3. Is the window normally fixed into the Verbus unit rather than the outer cladding system? This would replace the need for a lined reveal with a simple finish like an architrave. Both are possible. The client usually prefers to have an internal cill detail as a more traditional construction would provide, therefore the window is fitted in the cavity between Verbus wall and external façade. However if there is no requirement for an internal cill or reveal the window can be pre-installed in the unit providing it does not protrude beyond the face of the outer sheet.
  • 36. Verbus FAQ ACOUSTIC DESIGN 1. What sound insulation value does the unit have without additional insulation? Results of theoretical predictions and model constructions For single external wall: Assumptions: Plasterboard 2 layers of 12.5mm board with mass 17.3kg/m2 Plywood 1 layer of 10mm plywood with mass 5.6kg/m2 Void 50mm with 40mm of mineral wool Steel 1.6mm flat steel 12.5kg/m2 Sound reduction index Rw - 51 2. Vibration: To meet design code and Employer's requirements. <= 55Lntw dB 3. Acoustic Design: To meet both Employer's requirements and Building Regulations – impact and airborne sound walls and floors. The design of a standard Verbus unit is such that previous test data confirms it easily attains those targets set by Building Regulations. Acoustic performance measured as a combination of Verbus build-up and external walls. Room to room acoustic performance measured on previous Verbus buildings. Room to room noise reduction: >= 50Dntw +Ctr dB Floor to ceiling noise reduction: >= 54Dntw +Ctr dB
  • 37. Verbus FAQ CONSERVATION OF FUEL & POWER - THERMAL 1. What U value does the unit provide without additional insulation? The unit has the following thermal resistance, which when combined with external cladding and insulation provides a U- value: - wall: R=1.09 m2K/W - roof: R=1.31 m2K/W - floor: R=1.05 m2K/W 2. Does the external insulation need to be positioned tight against the outer face of the unit? Can an air gap be provided with a composite, Kingspan type, insulation or does this cause problems with interstitial condensation? No requirement to place insulation against outer face of unit. 3. Air Tightness Design: To meet both Employer's requirements and Building Regulations including interstitial condensation calculation check. Part L calculations normally carried out by project building services engineer or architect. Construction details of the Verbus units provided by Verbus. 4. Thermal Design: To meet both Employer's requirements and Building Regulations including interstitial condensation calculation check. The thermal properties of the Verbus units are such that additional insulation is required outside of the units in the cavity behind the external cladding / façade. Part L calculations normally carried out by project building services engineer.
  • 38. Verbus FAQ FIRE SAFETY 1. What is the Fire rating for a Verbus Unit and what level of protection is given to its structural elements? 90 minutes standard. Verbus units are fire rated as specified by the architect. Up to 2 hours protection possible.
  • 39. Verbus FAQ DRAINAGE 1. Services Design: Provision of service risers as shown, to meet needs of M&E and Building Regulations Apertures in floor and roof of Verbus units are provided to give vertical access through the building for services. Sizes of these apertures vary dependant on services required and height of building. Risers are generally sized by M&E consultant.
  • 40. Verbus FAQ MECHANICAL & ELECTRICAL 1. Are power and data services run within the wall cavity? Yes. Where certain specialist cabling cannot be supplied (i.e. data or fire) then containment is provided within wall construction with draw wires. 2. What electrics would be included and how would they interface with distribution mains – plug and play or traditional connections? Units will have first fix electrics with regard cabling and containment. Where cabling cannot be supplied (i.e. fire) conduit will be provided with draw wires. 3. How is electrical / mechanical certification achieved? M&E services are tested and certification provided at the point of manufacture, under the supervision of an independent representative.
  • 41. Verbus FAQ INTERNAL FF&E 1. For surface mounted items, such as shelves, are additional studs added to the wall construction or is the plywood sufficient? Typically the standard 10mm plywood behind the plasterboard provides sufficient grounds to fix into. Should a more substantial substrate be required this plywood can be increased. 2. Will Verbus fit out internally to a specification to meet the Employer's Requirements or a pre-determined specification used previously that may not align with Employer's specification? Each project is treated on its own merit, however Verbus. units will be fitted out to the employer's requirements as detailed in the terms of contract unless otherwise agreed. 3. Which components would be sourced from UK? Those which cannot be sourced in China. Typically these are reasonably few but can include specific data cabling or fire detection systems. 4. Which components would be sourced from Europe? Only those which cannot be sourced in China or UK. 5. Which components would be sourced from China? The majority of the components will be sourced in China as quite often the specified components are made in China. These can include sanitary ware, doors and door furniture, beds, light fittings etc. 6. Would bathrooms be 'podded'? Would connections be to UK standard? Verbus have provided both bathroom pods and built-in bathrooms. It has proved more productive to construct the bathrooms in the units in the factory rather than use pods. All connections will be to UK standard.
  • 42. Verbus FAQ INTERNAL FF&E 7. What happens any of the goods supplied are defective? Verbus ensures that replacement products are available in the country of the site and will arrange for replacement to be made where appropriate
  • 43. Verbus FAQ RESISTANCE TO CONTAMINANTS & MOISTURE 1. How are DPCs dealt with where they are required at opening positions? As with traditional construction a Thermabate or similar would be incorporated into the external wall construction around the openings.
  • 44. Verbus FAQ TOXIC SUBSTANCES 1. Does the standard Verbus wall insulation contain Urea-formaldehyde foam of any other substance which could be hazardous to health? If so, how is this managed? No. The insulation in the Verbus wall is an approved Rockwool product.
  • 45. Verbus FAQ STAIRS LIFTS & PROTECTION FROM FALLING 1. Do Verbus have a solution for a staircase within a Unit? A staircase solution, although not offered yet, is in design stage. 2. Design of interface connection of modules with stair/lift shaft cores etc. Verbus provides loads and recommended connection details between the units and stair/lift cores
  • 46. Verbus FAQ CERTIFICATION & DESIGN LIFE 1. Longevity 60 year design life. 2. Do the Verbus units carry any recognised certification? (Eg BBA; BRE; Warrington Fire; ETA; BS or ISO compliance.) Designed to meet UK standards, BS codes etc.