Al Qasr Mall Project



‫مشاريع دار الركان‬


             20th Feb. 2012
Al-Qasr Plan
Al Qasr Shopping Centre
  Lead Architect: Albert Speer & Partners
  Lead Consultant: Saudi Diyar
  Main Contractor: Saudi Constructioneers

  67,500 m² Land Area
  215,000 m² of BUA
  76,489.6 m² of Leasable Area
  368 Shop/Store
  1756 Parking Capacity


  Construction Start:  May 2008
  Expected completion: 31st Jan 2012
Current Status of Packages
Pkg 6A: SAUDICO- Structural Works
             Work In Place                    100%

             Forecast Completion Date         17-Dec-09
Pkg 6B: SAUDICO- Finishes & MEP Works
             Work In Place                    98.8%

             Forecast Completion Date         15-Feb-12
Pkg 6C: Al Ojaimi- Substation & Cable Works
             Work In Place                    100%

             Forecast Completion Date         30-Oct-11

Project Total of completion all packages:     99.6%
Critical Milestones to Achieve
                  Completion Date
All Construction Works Completed on or before- 15 Feb 2012
Energize Transformer Rooms- 30 Oct 2011 ( Done)
Telephone Cables and Cabinet- all material delivered & partially installed.
Way finding mock up approval : 04.01.12, 45days for installation after
     releasing LOI.
Balance of the interior design packages in Process
Electrical Panel Boards Delivery- 100 % delivered.
Execution of the STC Contract Agreement- awaiting Signature
Finalizing Al Shaya requirements
Finalizing the A/C requirements for the Stores
Finalizing The Food Court Requirement (GAS)
Epoxy Paint- Ground Floor painting
PROJECT: AL QASR MALL
LIST OF POTENTIAL ADDITIONAL WORKS

  SN                          Description              Rough Estimated Cost        Duration                            Remarks

   1    Fun Zone (Part A) - Waterproofing                                                          Awaiting SCE Cost



                                                                                                   Awaiting SCE Cost from conceptual drawing
   2    Drop Off area                                                                              provided by SDC

   3    Additional Parking Areas (at North East)                                                   Awaiting SCE Cost


                                                                                                   SR 649,982 - cost from Supplier/contractor
                                                                                                   (AL ROWAFED Est), Excluding Civil works
   4    LPG Central Tank & Services                           649,982.00           2 months        which still awaiting from SCE


   5    Additional HVAC works for Tenant (AL SHAYAH)        6,000,000.00           9 months        As proposed by SCE


   6    Water and Drainage for 17 shops                       590,150.00      10 weeks (2.5 month) As proposed by SCE



                                                                                                   * includes 1month design period of SDC
                                                                                                   * SDC awaiting DAAR's instruction to provide
   7    Additional 4 nos. Panoramic Elevator                                      12 Months        the design.
Tenant Submitted
                                                                         Handed
                                                        Handed Over to                Fit Out Design
                                          Total HO To                    Over to                            Fit-Out
                       In Process of                     DAAR-PM with                    Drawings
               Total                      DAAR-PM (or                  Tenant with                          Works
   Floor               Handing Over                          No                     for DAAR Approval
                (1)                         skipped)                   No Further                           Started
                             (2)                         Tenant Action             but Did Not Start Fit-
                                               (3)                       Action                               (7)
                                                              (4)                       Out Works
                                                                           (5)
                                                                                            (6)



Ground Floor    54           2                52              44             2                1               5

 First Floor    79           2                77              22             8                0               47

Second Floor    91           1                90              66             4                0               20

 Third Floor   140           84               56              38             8                1               9
TOTAL          364           89               275             170           22                2               81



               Area of Fit out on board
                                              Total Leasable Area M2         Percentage achieved
                          M2


                       33793                        76489.6                         44.18%
THE KEY PRE-OPENING TASKS NEEDED TO BE
 COMPLETED PRIOR TO THE MALL OPENING
Al Qasr Mall Project



‫مشاريع دار الركان‬


               Thank You

Contenu connexe

Similaire à Al Qasr Mall Feb2012

Similaire à Al Qasr Mall Feb2012 (12)

Monthly Progress Report - September 2014
Monthly Progress Report - September 2014Monthly Progress Report - September 2014
Monthly Progress Report - September 2014
 
MEED Projects Oil and gas Webinar Presentation 10.12.12
MEED Projects Oil and gas Webinar Presentation 10.12.12MEED Projects Oil and gas Webinar Presentation 10.12.12
MEED Projects Oil and gas Webinar Presentation 10.12.12
 
Meed projects oil and gas webinar (2012.12)
Meed projects oil and gas webinar (2012.12)Meed projects oil and gas webinar (2012.12)
Meed projects oil and gas webinar (2012.12)
 
InduSoft OPC UA Webinar with Genesis RTS
InduSoft OPC UA Webinar with Genesis RTSInduSoft OPC UA Webinar with Genesis RTS
InduSoft OPC UA Webinar with Genesis RTS
 
Project Management Report for Tank Farm
Project Management Report for Tank FarmProject Management Report for Tank Farm
Project Management Report for Tank Farm
 
DAMAC Heights Project
DAMAC Heights ProjectDAMAC Heights Project
DAMAC Heights Project
 
MEED Projects Oil and gas webinar presentation 101212
MEED Projects Oil and gas webinar presentation 101212MEED Projects Oil and gas webinar presentation 101212
MEED Projects Oil and gas webinar presentation 101212
 
AGTL Project Status and Progress_20-01-2021.pptx
AGTL Project Status and Progress_20-01-2021.pptxAGTL Project Status and Progress_20-01-2021.pptx
AGTL Project Status and Progress_20-01-2021.pptx
 
Designing at 2x nanometers Some New Problems Appear & Some Old Ones Remain
Designing at 2x nanometers Some New Problems Appear & Some Old Ones RemainDesigning at 2x nanometers Some New Problems Appear & Some Old Ones Remain
Designing at 2x nanometers Some New Problems Appear & Some Old Ones Remain
 
Osx project update agosto_final_inglês
Osx project update agosto_final_inglêsOsx project update agosto_final_inglês
Osx project update agosto_final_inglês
 
4th Fighter Wing Briefing
4th Fighter Wing Briefing4th Fighter Wing Briefing
4th Fighter Wing Briefing
 
FIT_in PV market
FIT_in PV marketFIT_in PV market
FIT_in PV market
 

Al Qasr Mall Feb2012

  • 1. Al Qasr Mall Project ‫مشاريع دار الركان‬ 20th Feb. 2012
  • 3. Al Qasr Shopping Centre Lead Architect: Albert Speer & Partners Lead Consultant: Saudi Diyar Main Contractor: Saudi Constructioneers 67,500 m² Land Area 215,000 m² of BUA 76,489.6 m² of Leasable Area 368 Shop/Store 1756 Parking Capacity Construction Start: May 2008 Expected completion: 31st Jan 2012
  • 4. Current Status of Packages Pkg 6A: SAUDICO- Structural Works Work In Place 100% Forecast Completion Date 17-Dec-09 Pkg 6B: SAUDICO- Finishes & MEP Works Work In Place 98.8% Forecast Completion Date 15-Feb-12 Pkg 6C: Al Ojaimi- Substation & Cable Works Work In Place 100% Forecast Completion Date 30-Oct-11 Project Total of completion all packages: 99.6%
  • 5. Critical Milestones to Achieve Completion Date All Construction Works Completed on or before- 15 Feb 2012 Energize Transformer Rooms- 30 Oct 2011 ( Done) Telephone Cables and Cabinet- all material delivered & partially installed. Way finding mock up approval : 04.01.12, 45days for installation after releasing LOI. Balance of the interior design packages in Process Electrical Panel Boards Delivery- 100 % delivered. Execution of the STC Contract Agreement- awaiting Signature Finalizing Al Shaya requirements Finalizing the A/C requirements for the Stores Finalizing The Food Court Requirement (GAS) Epoxy Paint- Ground Floor painting
  • 6.
  • 7.
  • 8.
  • 9.
  • 10.
  • 11.
  • 12.
  • 13.
  • 14.
  • 15.
  • 16.
  • 17. PROJECT: AL QASR MALL LIST OF POTENTIAL ADDITIONAL WORKS SN Description Rough Estimated Cost Duration Remarks 1 Fun Zone (Part A) - Waterproofing Awaiting SCE Cost Awaiting SCE Cost from conceptual drawing 2 Drop Off area provided by SDC 3 Additional Parking Areas (at North East) Awaiting SCE Cost SR 649,982 - cost from Supplier/contractor (AL ROWAFED Est), Excluding Civil works 4 LPG Central Tank & Services 649,982.00 2 months which still awaiting from SCE 5 Additional HVAC works for Tenant (AL SHAYAH) 6,000,000.00 9 months As proposed by SCE 6 Water and Drainage for 17 shops 590,150.00 10 weeks (2.5 month) As proposed by SCE * includes 1month design period of SDC * SDC awaiting DAAR's instruction to provide 7 Additional 4 nos. Panoramic Elevator 12 Months the design.
  • 18.
  • 19.
  • 20.
  • 21.
  • 22.
  • 23.
  • 24.
  • 25.
  • 26.
  • 27.
  • 28.
  • 29.
  • 30.
  • 31.
  • 32.
  • 33.
  • 34.
  • 35.
  • 36.
  • 37.
  • 38.
  • 39.
  • 40.
  • 41.
  • 42.
  • 43.
  • 44.
  • 45.
  • 46.
  • 47.
  • 48.
  • 49.
  • 50.
  • 51.
  • 52.
  • 53.
  • 54.
  • 55.
  • 56.
  • 57.
  • 58.
  • 59.
  • 60.
  • 61. Tenant Submitted Handed Handed Over to Fit Out Design Total HO To Over to Fit-Out In Process of DAAR-PM with Drawings Total DAAR-PM (or Tenant with Works Floor Handing Over No for DAAR Approval (1) skipped) No Further Started (2) Tenant Action but Did Not Start Fit- (3) Action (7) (4) Out Works (5) (6) Ground Floor 54 2 52 44 2 1 5 First Floor 79 2 77 22 8 0 47 Second Floor 91 1 90 66 4 0 20 Third Floor 140 84 56 38 8 1 9 TOTAL 364 89 275 170 22 2 81 Area of Fit out on board Total Leasable Area M2 Percentage achieved M2 33793 76489.6 44.18%
  • 62. THE KEY PRE-OPENING TASKS NEEDED TO BE COMPLETED PRIOR TO THE MALL OPENING