Created by ejlp12@gmail.com, June 2010 5 - Project Integration Management Project Management Training
Project Integration Management Monitoring & Controlling Processes Planning Processes Enter phase/ Start project Exit phase/ End project Initiating Processes Closing Processes Executing Processes
Project Integration Management Process and activities needed to identify, define, combine, unify, and coordinate the various processes and project management activities within the Project Management Process Groups.
4.1 Develop Project Charter The process of developing a document that formally authorizes a project or a phase and documenting initial requirements that satisfy the stakeholder’s needs and expectations
Develop Project Charter (Input) Project are authorized by someone external to the project such as sponsor, PMO, portfolio steering committee. Project charter can be created by them or delegated to Project Manager. Statement of Work (SOW) A narrative description of products or services to be delivered by the project. The SOW references: Business need Product scope description  Strategic plan Business case ,[object Object],[object Object]
Project Selection – Economic Models You just need to understand the following concepts FP = future value r = interest rate n = number of time period Present value (PV): The value today of future cash flows Net present value (NPV): Project with positive & greater NPV value is better Internal rate of return (IRR): Project with greater IRR value is better Payback period: The number of  time periods it takes to recover your investment in the project before you start accumulating  profit. Benefit-cost ratio: compares  the benefits to the costs of different options relates to costing projects and to determining what work should be done Project with greater benefit-cost ratio value is better
Project Selection – Important Terms Economic Value Added (EVA): concerned with whether the project returns to the company more value  than it costs. Opportunity Cost: the opportunity given up by selecting one project over another Sunk Costs:  Are expended costs Should not be considered when deciding whether to continue with a troubled project. Lay of Diminishing Returns: after a certain point, adding more input/resource will not produce a proportional increase  in productivity
Project Selection – Important Terms Working Capital current assets minus current  liabilities  for an organization or amount of money the company has available to invest Depreciation Straight line depreciation The same amount of depreciation  is taken each year. Accelerated depreciation Depreciates faster  than straight line Two forms: (1) Double Declining Balance,  (2) Sum  of the Years Digits
Develop Project Charter (Tools & Techniques, Output) Expert Judgment, includes: Project Charter, includes: Project purpose or justification,  Measurable project objectives and related success criteria,  High-level requirements,  High-level project description,  High-level risks,  Summary milestone schedule,  Summary budget,  Project approval requirements Assigned project manager, responsibility, and authority level Name and authority of the sponsor or other person(s) authorizing the project charter.  ,[object Object]
Consultants
Stakeholders including customer or sponsor
Subject matter experts
PMO
Industry groups
Professional & technical association,[object Object]
Project Management Plan (Output) The strategy for managing the project and the processes in each knowledge area Covers how you will define, plan, manage, and control  the project. Also includes: Change management plan Configuration management plan Requirements management plan Process  improvement plan How to handle a problem on a project? ,[object Object],[object Object]
Change Management Plan Describes how changes will be managed and controlled. Covers for the project as whole May includes: Change control procedures (how and who)  The approval levels for authorizing changes  The creation of a change control board to approve changes A plan outlining how changes will be managed and controlled Who should attend meetings regarding changes  Tools to use to track and control changes  Each knowledge area are described in the individual management plans
Configuration Management Plan Defines how you will manage changes to the deliverables and the resulting documentation, including which organizational tools you will use
4.3 Direct & Manage Project Execution The process of performing the work defined in the project management plan to achieve the project’s objectives.
4.4 Monitor & Control Project Work The process of tracking, reviewing, and regulating the progress to meet the performance objectives defined in the project management plan.

More Related Content

What's hot

Chap 4.7 Project or Phase Close
Chap 4.7 Project or Phase CloseChap 4.7 Project or Phase Close
Chap 4.7 Project or Phase CloseAnand Bobade
 
Project management
Project managementProject management
Project managementJay Raval
 
Project integration management
Project integration managementProject integration management
Project integration managementPrabudh Dhingra
 
Brief introduction to project management and project management tools
Brief introduction to project management and project management toolsBrief introduction to project management and project management tools
Brief introduction to project management and project management toolsNathan Petralia
 
Project Management Fundamentals
Project Management FundamentalsProject Management Fundamentals
Project Management FundamentalsOxfordCambridge
 
PMP Chap 5 - Project Scope Management - Part1
PMP Chap 5 - Project Scope Management - Part1PMP Chap 5 - Project Scope Management - Part1
PMP Chap 5 - Project Scope Management - Part1Anand Bobade
 
Project Management Processes
Project Management ProcessesProject Management Processes
Project Management ProcessesJoshua Render
 
Project management life cycle
Project management life cycleProject management life cycle
Project management life cycleAmjad Idries
 
PMP NOTES Based on PMBOK Guide 5th Edition and updated PMP syllabus after 11 ...
PMP NOTES Based on PMBOK Guide 5th Edition and updated PMP syllabus after 11 ...PMP NOTES Based on PMBOK Guide 5th Edition and updated PMP syllabus after 11 ...
PMP NOTES Based on PMBOK Guide 5th Edition and updated PMP syllabus after 11 ...JustAcademy
 
PMP Chap 4 - Project Integration Management - Part1
PMP Chap 4 - Project Integration Management - Part1PMP Chap 4 - Project Integration Management - Part1
PMP Chap 4 - Project Integration Management - Part1Anand Bobade
 
PMP chap 1 - PMP Introduction (PMBOK 6)
PMP chap 1 - PMP  Introduction (PMBOK 6)PMP chap 1 - PMP  Introduction (PMBOK 6)
PMP chap 1 - PMP Introduction (PMBOK 6)Anand Bobade
 
Project Schedule Management - PMBOK6
Project Schedule Management - PMBOK6Project Schedule Management - PMBOK6
Project Schedule Management - PMBOK6Agus Suhanto
 
1 b. project monitoring and control
1 b. project monitoring and control1 b. project monitoring and control
1 b. project monitoring and controlDr.R. SELVAM
 

What's hot (20)

Chap 4.7 Project or Phase Close
Chap 4.7 Project or Phase CloseChap 4.7 Project or Phase Close
Chap 4.7 Project or Phase Close
 
Project management
Project managementProject management
Project management
 
Project integration management
Project integration managementProject integration management
Project integration management
 
Brief introduction to project management and project management tools
Brief introduction to project management and project management toolsBrief introduction to project management and project management tools
Brief introduction to project management and project management tools
 
Project Closure Checklist
Project Closure ChecklistProject Closure Checklist
Project Closure Checklist
 
Overview of Program Management
Overview of Program ManagementOverview of Program Management
Overview of Program Management
 
project management concepts
project management conceptsproject management concepts
project management concepts
 
Final Project Closing
Final Project ClosingFinal Project Closing
Final Project Closing
 
Project Management Fundamentals
Project Management FundamentalsProject Management Fundamentals
Project Management Fundamentals
 
PMP Chap 5 - Project Scope Management - Part1
PMP Chap 5 - Project Scope Management - Part1PMP Chap 5 - Project Scope Management - Part1
PMP Chap 5 - Project Scope Management - Part1
 
PMP PMBOK 6th
PMP PMBOK 6thPMP PMBOK 6th
PMP PMBOK 6th
 
Project Management Processes
Project Management ProcessesProject Management Processes
Project Management Processes
 
Pmp study-notes
Pmp study-notesPmp study-notes
Pmp study-notes
 
Project management life cycle
Project management life cycleProject management life cycle
Project management life cycle
 
Project Time Management
Project Time ManagementProject Time Management
Project Time Management
 
PMP NOTES Based on PMBOK Guide 5th Edition and updated PMP syllabus after 11 ...
PMP NOTES Based on PMBOK Guide 5th Edition and updated PMP syllabus after 11 ...PMP NOTES Based on PMBOK Guide 5th Edition and updated PMP syllabus after 11 ...
PMP NOTES Based on PMBOK Guide 5th Edition and updated PMP syllabus after 11 ...
 
PMP Chap 4 - Project Integration Management - Part1
PMP Chap 4 - Project Integration Management - Part1PMP Chap 4 - Project Integration Management - Part1
PMP Chap 4 - Project Integration Management - Part1
 
PMP chap 1 - PMP Introduction (PMBOK 6)
PMP chap 1 - PMP  Introduction (PMBOK 6)PMP chap 1 - PMP  Introduction (PMBOK 6)
PMP chap 1 - PMP Introduction (PMBOK 6)
 
Project Schedule Management - PMBOK6
Project Schedule Management - PMBOK6Project Schedule Management - PMBOK6
Project Schedule Management - PMBOK6
 
1 b. project monitoring and control
1 b. project monitoring and control1 b. project monitoring and control
1 b. project monitoring and control
 

Viewers also liked

PMP Training - 06 project time management2
PMP Training - 06 project time management2PMP Training - 06 project time management2
PMP Training - 06 project time management2ejlp12
 
PMP Training - 01 introduction to framework
PMP Training - 01 introduction to frameworkPMP Training - 01 introduction to framework
PMP Training - 01 introduction to frameworkejlp12
 
PMP Training - 08 project quality management
PMP Training - 08 project quality managementPMP Training - 08 project quality management
PMP Training - 08 project quality managementejlp12
 
PMP Training - 05 project scope management
PMP Training - 05 project scope managementPMP Training - 05 project scope management
PMP Training - 05 project scope managementejlp12
 
PMP Training - 11 project risk management
PMP Training - 11 project risk managementPMP Training - 11 project risk management
PMP Training - 11 project risk managementejlp12
 
PMP Training - 09 project human resource management
PMP Training - 09 project human resource managementPMP Training - 09 project human resource management
PMP Training - 09 project human resource managementejlp12
 
PMP Training - 07 project cost management
PMP Training - 07 project cost managementPMP Training - 07 project cost management
PMP Training - 07 project cost managementejlp12
 
PMP Training - 10 project communication management
PMP Training - 10 project communication managementPMP Training - 10 project communication management
PMP Training - 10 project communication managementejlp12
 
PMP Training - 12 project procurement management
PMP Training - 12 project procurement managementPMP Training - 12 project procurement management
PMP Training - 12 project procurement managementejlp12
 
RESTful web service with JBoss Fuse
RESTful web service with JBoss FuseRESTful web service with JBoss Fuse
RESTful web service with JBoss Fuseejlp12
 
Agile & SCRUM
Agile & SCRUMAgile & SCRUM
Agile & SCRUMejlp12
 
Pmp – pmbok 5th edition chapter4 project integration management final
Pmp – pmbok 5th edition chapter4 project integration management finalPmp – pmbok 5th edition chapter4 project integration management final
Pmp – pmbok 5th edition chapter4 project integration management finalYudha Pratama, PMP
 
Project Management Framework - PMBOK 5
Project Management Framework - PMBOK 5Project Management Framework - PMBOK 5
Project Management Framework - PMBOK 5pankajsh10
 
Project Integration Management
Project Integration ManagementProject Integration Management
Project Integration Managementpankajsh10
 
Pmp presentation chapter 1 to 7
Pmp presentation chapter 1 to 7Pmp presentation chapter 1 to 7
Pmp presentation chapter 1 to 7Saad Merie
 
Pmp – pmbok 5th edition develop project charter
Pmp – pmbok 5th edition develop project charterPmp – pmbok 5th edition develop project charter
Pmp – pmbok 5th edition develop project charterYudha Pratama, PMP
 
PMPProcessGroupTasks
PMPProcessGroupTasksPMPProcessGroupTasks
PMPProcessGroupTasksAnand Bobade
 
PMBOK 5th Edition - Chapter 6 PROJECT TIME MANAGEMENT Summary
PMBOK 5th Edition - Chapter 6 PROJECT TIME MANAGEMENT SummaryPMBOK 5th Edition - Chapter 6 PROJECT TIME MANAGEMENT Summary
PMBOK 5th Edition - Chapter 6 PROJECT TIME MANAGEMENT SummaryYudha Pratama, PMP
 
Project Stakeholder Management - PMBOK 5
Project Stakeholder Management - PMBOK 5Project Stakeholder Management - PMBOK 5
Project Stakeholder Management - PMBOK 5pankajsh10
 

Viewers also liked (20)

PMP Training - 06 project time management2
PMP Training - 06 project time management2PMP Training - 06 project time management2
PMP Training - 06 project time management2
 
PMP Training - 01 introduction to framework
PMP Training - 01 introduction to frameworkPMP Training - 01 introduction to framework
PMP Training - 01 introduction to framework
 
PMP Training - 08 project quality management
PMP Training - 08 project quality managementPMP Training - 08 project quality management
PMP Training - 08 project quality management
 
PMP Training - 05 project scope management
PMP Training - 05 project scope managementPMP Training - 05 project scope management
PMP Training - 05 project scope management
 
PMP Training - 11 project risk management
PMP Training - 11 project risk managementPMP Training - 11 project risk management
PMP Training - 11 project risk management
 
PMP Training - 09 project human resource management
PMP Training - 09 project human resource managementPMP Training - 09 project human resource management
PMP Training - 09 project human resource management
 
PMP Training - 07 project cost management
PMP Training - 07 project cost managementPMP Training - 07 project cost management
PMP Training - 07 project cost management
 
PMP Training - 10 project communication management
PMP Training - 10 project communication managementPMP Training - 10 project communication management
PMP Training - 10 project communication management
 
PMP Training - 12 project procurement management
PMP Training - 12 project procurement managementPMP Training - 12 project procurement management
PMP Training - 12 project procurement management
 
RESTful web service with JBoss Fuse
RESTful web service with JBoss FuseRESTful web service with JBoss Fuse
RESTful web service with JBoss Fuse
 
Agile & SCRUM
Agile & SCRUMAgile & SCRUM
Agile & SCRUM
 
Pmp – pmbok 5th edition chapter4 project integration management final
Pmp – pmbok 5th edition chapter4 project integration management finalPmp – pmbok 5th edition chapter4 project integration management final
Pmp – pmbok 5th edition chapter4 project integration management final
 
Project Management Framework - PMBOK 5
Project Management Framework - PMBOK 5Project Management Framework - PMBOK 5
Project Management Framework - PMBOK 5
 
Project Cost Management
Project Cost ManagementProject Cost Management
Project Cost Management
 
Project Integration Management
Project Integration ManagementProject Integration Management
Project Integration Management
 
Pmp presentation chapter 1 to 7
Pmp presentation chapter 1 to 7Pmp presentation chapter 1 to 7
Pmp presentation chapter 1 to 7
 
Pmp – pmbok 5th edition develop project charter
Pmp – pmbok 5th edition develop project charterPmp – pmbok 5th edition develop project charter
Pmp – pmbok 5th edition develop project charter
 
PMPProcessGroupTasks
PMPProcessGroupTasksPMPProcessGroupTasks
PMPProcessGroupTasks
 
PMBOK 5th Edition - Chapter 6 PROJECT TIME MANAGEMENT Summary
PMBOK 5th Edition - Chapter 6 PROJECT TIME MANAGEMENT SummaryPMBOK 5th Edition - Chapter 6 PROJECT TIME MANAGEMENT Summary
PMBOK 5th Edition - Chapter 6 PROJECT TIME MANAGEMENT Summary
 
Project Stakeholder Management - PMBOK 5
Project Stakeholder Management - PMBOK 5Project Stakeholder Management - PMBOK 5
Project Stakeholder Management - PMBOK 5
 

Similar to PMP Training - 04 project integration management

L03 integration management
L03 integration managementL03 integration management
L03 integration managementAsa Chan
 
2.04 integration management
2.04 integration management2.04 integration management
2.04 integration managementreddvise
 
2.1 integration management
2.1 integration management2.1 integration management
2.1 integration managementIrefuser1
 
Online PMP Training Material for PMP Exam - Integration Management Knowledge ...
Online PMP Training Material for PMP Exam - Integration Management Knowledge ...Online PMP Training Material for PMP Exam - Integration Management Knowledge ...
Online PMP Training Material for PMP Exam - Integration Management Knowledge ...GlobalSkillup
 
Undestand PMBok 5th, Section 3
Undestand PMBok 5th, Section 3Undestand PMBok 5th, Section 3
Undestand PMBok 5th, Section 3Amr Miqdadi
 
Project Management Process and Its Phases
Project Management Process and Its PhasesProject Management Process and Its Phases
Project Management Process and Its PhasesGaurav Sukhija
 
04 projectintegrationmanagement
04 projectintegrationmanagement04 projectintegrationmanagement
04 projectintegrationmanagementDhamo daran
 
Project management processes Groups
Project management processes GroupsProject management processes Groups
Project management processes GroupsSourabh Kumar
 
Project Integration
Project IntegrationProject Integration
Project IntegrationTechNoleGirl
 
Effective Project Integration Management
Effective Project Integration ManagementEffective Project Integration Management
Effective Project Integration Managementssuser9d62d6
 
Projects Management
Projects ManagementProjects Management
Projects ManagementNirmal Shah
 
Mmi entrepreneurship 6
Mmi entrepreneurship 6Mmi entrepreneurship 6
Mmi entrepreneurship 6gatecomro
 
Project Management Framework.pptx
Project Management Framework.pptxProject Management Framework.pptx
Project Management Framework.pptxvamsnrsfdevuqsrtmy
 
PM Session 4
PM Session 4PM Session 4
PM Session 4dmdk12
 
PMBOK_5th_Initiating Process Group -
PMBOK_5th_Initiating Process Group -PMBOK_5th_Initiating Process Group -
PMBOK_5th_Initiating Process Group -Hossam Maghrabi
 

Similar to PMP Training - 04 project integration management (20)

L03 integration management
L03 integration managementL03 integration management
L03 integration management
 
2.04 integration management
2.04 integration management2.04 integration management
2.04 integration management
 
Ch04
Ch04Ch04
Ch04
 
2.1 integration management
2.1 integration management2.1 integration management
2.1 integration management
 
Online PMP Training Material for PMP Exam - Integration Management Knowledge ...
Online PMP Training Material for PMP Exam - Integration Management Knowledge ...Online PMP Training Material for PMP Exam - Integration Management Knowledge ...
Online PMP Training Material for PMP Exam - Integration Management Knowledge ...
 
Undestand PMBok 5th, Section 3
Undestand PMBok 5th, Section 3Undestand PMBok 5th, Section 3
Undestand PMBok 5th, Section 3
 
Project Management Process and Its Phases
Project Management Process and Its PhasesProject Management Process and Its Phases
Project Management Process and Its Phases
 
04 projectintegrationmanagement
04 projectintegrationmanagement04 projectintegrationmanagement
04 projectintegrationmanagement
 
Project management processes Groups
Project management processes GroupsProject management processes Groups
Project management processes Groups
 
4 integration
4 integration4 integration
4 integration
 
Project Integration
Project IntegrationProject Integration
Project Integration
 
Effective Project Integration Management
Effective Project Integration ManagementEffective Project Integration Management
Effective Project Integration Management
 
PMP integration review
PMP integration reviewPMP integration review
PMP integration review
 
Projects Management
Projects ManagementProjects Management
Projects Management
 
Mmi entrepreneurship 6
Mmi entrepreneurship 6Mmi entrepreneurship 6
Mmi entrepreneurship 6
 
Project Management Framework.pptx
Project Management Framework.pptxProject Management Framework.pptx
Project Management Framework.pptx
 
Project management
Project managementProject management
Project management
 
1. project integration management
1. project integration management1. project integration management
1. project integration management
 
PM Session 4
PM Session 4PM Session 4
PM Session 4
 
PMBOK_5th_Initiating Process Group -
PMBOK_5th_Initiating Process Group -PMBOK_5th_Initiating Process Group -
PMBOK_5th_Initiating Process Group -
 

More from ejlp12

Introduction to Docker storage, volume and image
Introduction to Docker storage, volume and imageIntroduction to Docker storage, volume and image
Introduction to Docker storage, volume and imageejlp12
 
Java troubleshooting thread dump
Java troubleshooting thread dumpJava troubleshooting thread dump
Java troubleshooting thread dumpejlp12
 
WebSphere Application Server Information Resources
WebSphere Application Server Information ResourcesWebSphere Application Server Information Resources
WebSphere Application Server Information Resourcesejlp12
 
WebSphere Application Server Family (Editions Comparison)
WebSphere Application Server Family (Editions Comparison)WebSphere Application Server Family (Editions Comparison)
WebSphere Application Server Family (Editions Comparison)ejlp12
 
Linux container & docker
Linux container & dockerLinux container & docker
Linux container & dockerejlp12
 
BPEL, BPEL vs ESB (Integration)
BPEL, BPEL vs ESB (Integration)BPEL, BPEL vs ESB (Integration)
BPEL, BPEL vs ESB (Integration)ejlp12
 
BPMN Introduction
BPMN IntroductionBPMN Introduction
BPMN Introductionejlp12
 
JBoss Data Virtualization (JDV) Sample Physical Deployment Architecture
JBoss Data Virtualization (JDV) Sample Physical Deployment ArchitectureJBoss Data Virtualization (JDV) Sample Physical Deployment Architecture
JBoss Data Virtualization (JDV) Sample Physical Deployment Architectureejlp12
 
WebSphere Application Server Topology Options
WebSphere Application Server Topology OptionsWebSphere Application Server Topology Options
WebSphere Application Server Topology Optionsejlp12
 
IBM WebSphere Application Server version to version comparison
IBM WebSphere Application Server version to version comparisonIBM WebSphere Application Server version to version comparison
IBM WebSphere Application Server version to version comparisonejlp12
 
IBM WebSphere Application Server (Clustering) Concept
IBM WebSphere Application Server (Clustering) ConceptIBM WebSphere Application Server (Clustering) Concept
IBM WebSphere Application Server (Clustering) Conceptejlp12
 
IBM WebSphere MQ Introduction
IBM WebSphere MQ Introduction IBM WebSphere MQ Introduction
IBM WebSphere MQ Introduction ejlp12
 
Java EE Introduction
Java EE IntroductionJava EE Introduction
Java EE Introductionejlp12
 
Introduction to Apache Cordova (Phonegap)
Introduction to Apache Cordova (Phonegap)Introduction to Apache Cordova (Phonegap)
Introduction to Apache Cordova (Phonegap)ejlp12
 
Introduction to jQuery Mobile
Introduction to jQuery MobileIntroduction to jQuery Mobile
Introduction to jQuery Mobileejlp12
 
Introduction to JPA (JPA version 2.0)
Introduction to JPA (JPA version 2.0)Introduction to JPA (JPA version 2.0)
Introduction to JPA (JPA version 2.0)ejlp12
 
Introduction to JavaBeans Activation Framework v1.1
Introduction to JavaBeans Activation Framework v1.1Introduction to JavaBeans Activation Framework v1.1
Introduction to JavaBeans Activation Framework v1.1ejlp12
 
Arah pengembangan core network architecture (Indonesia)
Arah pengembangan core network architecture (Indonesia)Arah pengembangan core network architecture (Indonesia)
Arah pengembangan core network architecture (Indonesia)ejlp12
 
GSM/UMTS network architecture tutorial (Indonesia)
GSM/UMTS network architecture tutorial (Indonesia)GSM/UMTS network architecture tutorial (Indonesia)
GSM/UMTS network architecture tutorial (Indonesia)ejlp12
 

More from ejlp12 (19)

Introduction to Docker storage, volume and image
Introduction to Docker storage, volume and imageIntroduction to Docker storage, volume and image
Introduction to Docker storage, volume and image
 
Java troubleshooting thread dump
Java troubleshooting thread dumpJava troubleshooting thread dump
Java troubleshooting thread dump
 
WebSphere Application Server Information Resources
WebSphere Application Server Information ResourcesWebSphere Application Server Information Resources
WebSphere Application Server Information Resources
 
WebSphere Application Server Family (Editions Comparison)
WebSphere Application Server Family (Editions Comparison)WebSphere Application Server Family (Editions Comparison)
WebSphere Application Server Family (Editions Comparison)
 
Linux container & docker
Linux container & dockerLinux container & docker
Linux container & docker
 
BPEL, BPEL vs ESB (Integration)
BPEL, BPEL vs ESB (Integration)BPEL, BPEL vs ESB (Integration)
BPEL, BPEL vs ESB (Integration)
 
BPMN Introduction
BPMN IntroductionBPMN Introduction
BPMN Introduction
 
JBoss Data Virtualization (JDV) Sample Physical Deployment Architecture
JBoss Data Virtualization (JDV) Sample Physical Deployment ArchitectureJBoss Data Virtualization (JDV) Sample Physical Deployment Architecture
JBoss Data Virtualization (JDV) Sample Physical Deployment Architecture
 
WebSphere Application Server Topology Options
WebSphere Application Server Topology OptionsWebSphere Application Server Topology Options
WebSphere Application Server Topology Options
 
IBM WebSphere Application Server version to version comparison
IBM WebSphere Application Server version to version comparisonIBM WebSphere Application Server version to version comparison
IBM WebSphere Application Server version to version comparison
 
IBM WebSphere Application Server (Clustering) Concept
IBM WebSphere Application Server (Clustering) ConceptIBM WebSphere Application Server (Clustering) Concept
IBM WebSphere Application Server (Clustering) Concept
 
IBM WebSphere MQ Introduction
IBM WebSphere MQ Introduction IBM WebSphere MQ Introduction
IBM WebSphere MQ Introduction
 
Java EE Introduction
Java EE IntroductionJava EE Introduction
Java EE Introduction
 
Introduction to Apache Cordova (Phonegap)
Introduction to Apache Cordova (Phonegap)Introduction to Apache Cordova (Phonegap)
Introduction to Apache Cordova (Phonegap)
 
Introduction to jQuery Mobile
Introduction to jQuery MobileIntroduction to jQuery Mobile
Introduction to jQuery Mobile
 
Introduction to JPA (JPA version 2.0)
Introduction to JPA (JPA version 2.0)Introduction to JPA (JPA version 2.0)
Introduction to JPA (JPA version 2.0)
 
Introduction to JavaBeans Activation Framework v1.1
Introduction to JavaBeans Activation Framework v1.1Introduction to JavaBeans Activation Framework v1.1
Introduction to JavaBeans Activation Framework v1.1
 
Arah pengembangan core network architecture (Indonesia)
Arah pengembangan core network architecture (Indonesia)Arah pengembangan core network architecture (Indonesia)
Arah pengembangan core network architecture (Indonesia)
 
GSM/UMTS network architecture tutorial (Indonesia)
GSM/UMTS network architecture tutorial (Indonesia)GSM/UMTS network architecture tutorial (Indonesia)
GSM/UMTS network architecture tutorial (Indonesia)
 

Recently uploaded

7.pdf This presentation captures many uses and the significance of the number...
7.pdf This presentation captures many uses and the significance of the number...7.pdf This presentation captures many uses and the significance of the number...
7.pdf This presentation captures many uses and the significance of the number...Paul Menig
 
VIP Call Girls In Saharaganj ( Lucknow ) 🔝 8923113531 🔝 Cash Payment (COD) 👒
VIP Call Girls In Saharaganj ( Lucknow  ) 🔝 8923113531 🔝  Cash Payment (COD) 👒VIP Call Girls In Saharaganj ( Lucknow  ) 🔝 8923113531 🔝  Cash Payment (COD) 👒
VIP Call Girls In Saharaganj ( Lucknow ) 🔝 8923113531 🔝 Cash Payment (COD) 👒anilsa9823
 
Call Girls in Delhi, Escort Service Available 24x7 in Delhi 959961-/-3876
Call Girls in Delhi, Escort Service Available 24x7 in Delhi 959961-/-3876Call Girls in Delhi, Escort Service Available 24x7 in Delhi 959961-/-3876
Call Girls in Delhi, Escort Service Available 24x7 in Delhi 959961-/-3876dlhescort
 
Mondelez State of Snacking and Future Trends 2023
Mondelez State of Snacking and Future Trends 2023Mondelez State of Snacking and Future Trends 2023
Mondelez State of Snacking and Future Trends 2023Neil Kimberley
 
Best Basmati Rice Manufacturers in India
Best Basmati Rice Manufacturers in IndiaBest Basmati Rice Manufacturers in India
Best Basmati Rice Manufacturers in IndiaShree Krishna Exports
 
Event mailer assignment progress report .pdf
Event mailer assignment progress report .pdfEvent mailer assignment progress report .pdf
Event mailer assignment progress report .pdftbatkhuu1
 
Value Proposition canvas- Customer needs and pains
Value Proposition canvas- Customer needs and painsValue Proposition canvas- Customer needs and pains
Value Proposition canvas- Customer needs and painsP&CO
 
Monte Carlo simulation : Simulation using MCSM
Monte Carlo simulation : Simulation using MCSMMonte Carlo simulation : Simulation using MCSM
Monte Carlo simulation : Simulation using MCSMRavindra Nath Shukla
 
Cracking the Cultural Competence Code.pptx
Cracking the Cultural Competence Code.pptxCracking the Cultural Competence Code.pptx
Cracking the Cultural Competence Code.pptxWorkforce Group
 
The Coffee Bean & Tea Leaf(CBTL), Business strategy case study
The Coffee Bean & Tea Leaf(CBTL), Business strategy case studyThe Coffee Bean & Tea Leaf(CBTL), Business strategy case study
The Coffee Bean & Tea Leaf(CBTL), Business strategy case studyEthan lee
 
Grateful 7 speech thanking everyone that has helped.pdf
Grateful 7 speech thanking everyone that has helped.pdfGrateful 7 speech thanking everyone that has helped.pdf
Grateful 7 speech thanking everyone that has helped.pdfPaul Menig
 
Insurers' journeys to build a mastery in the IoT usage
Insurers' journeys to build a mastery in the IoT usageInsurers' journeys to build a mastery in the IoT usage
Insurers' journeys to build a mastery in the IoT usageMatteo Carbone
 
9599632723 Top Call Girls in Delhi at your Door Step Available 24x7 Delhi
9599632723 Top Call Girls in Delhi at your Door Step Available 24x7 Delhi9599632723 Top Call Girls in Delhi at your Door Step Available 24x7 Delhi
9599632723 Top Call Girls in Delhi at your Door Step Available 24x7 DelhiCall Girls in Delhi
 
Call Girls in Gomti Nagar - 7388211116 - With room Service
Call Girls in Gomti Nagar - 7388211116  - With room ServiceCall Girls in Gomti Nagar - 7388211116  - With room Service
Call Girls in Gomti Nagar - 7388211116 - With room Servicediscovermytutordmt
 
Ensure the security of your HCL environment by applying the Zero Trust princi...
Ensure the security of your HCL environment by applying the Zero Trust princi...Ensure the security of your HCL environment by applying the Zero Trust princi...
Ensure the security of your HCL environment by applying the Zero Trust princi...Roland Driesen
 
MONA 98765-12871 CALL GIRLS IN LUDHIANA LUDHIANA CALL GIRL
MONA 98765-12871 CALL GIRLS IN LUDHIANA LUDHIANA CALL GIRLMONA 98765-12871 CALL GIRLS IN LUDHIANA LUDHIANA CALL GIRL
MONA 98765-12871 CALL GIRLS IN LUDHIANA LUDHIANA CALL GIRLSeo
 
Call Girls Pune Just Call 9907093804 Top Class Call Girl Service Available
Call Girls Pune Just Call 9907093804 Top Class Call Girl Service AvailableCall Girls Pune Just Call 9907093804 Top Class Call Girl Service Available
Call Girls Pune Just Call 9907093804 Top Class Call Girl Service AvailableDipal Arora
 

Recently uploaded (20)

7.pdf This presentation captures many uses and the significance of the number...
7.pdf This presentation captures many uses and the significance of the number...7.pdf This presentation captures many uses and the significance of the number...
7.pdf This presentation captures many uses and the significance of the number...
 
VIP Call Girls In Saharaganj ( Lucknow ) 🔝 8923113531 🔝 Cash Payment (COD) 👒
VIP Call Girls In Saharaganj ( Lucknow  ) 🔝 8923113531 🔝  Cash Payment (COD) 👒VIP Call Girls In Saharaganj ( Lucknow  ) 🔝 8923113531 🔝  Cash Payment (COD) 👒
VIP Call Girls In Saharaganj ( Lucknow ) 🔝 8923113531 🔝 Cash Payment (COD) 👒
 
Forklift Operations: Safety through Cartoons
Forklift Operations: Safety through CartoonsForklift Operations: Safety through Cartoons
Forklift Operations: Safety through Cartoons
 
Call Girls in Delhi, Escort Service Available 24x7 in Delhi 959961-/-3876
Call Girls in Delhi, Escort Service Available 24x7 in Delhi 959961-/-3876Call Girls in Delhi, Escort Service Available 24x7 in Delhi 959961-/-3876
Call Girls in Delhi, Escort Service Available 24x7 in Delhi 959961-/-3876
 
Mondelez State of Snacking and Future Trends 2023
Mondelez State of Snacking and Future Trends 2023Mondelez State of Snacking and Future Trends 2023
Mondelez State of Snacking and Future Trends 2023
 
Best Basmati Rice Manufacturers in India
Best Basmati Rice Manufacturers in IndiaBest Basmati Rice Manufacturers in India
Best Basmati Rice Manufacturers in India
 
Event mailer assignment progress report .pdf
Event mailer assignment progress report .pdfEvent mailer assignment progress report .pdf
Event mailer assignment progress report .pdf
 
Value Proposition canvas- Customer needs and pains
Value Proposition canvas- Customer needs and painsValue Proposition canvas- Customer needs and pains
Value Proposition canvas- Customer needs and pains
 
Monte Carlo simulation : Simulation using MCSM
Monte Carlo simulation : Simulation using MCSMMonte Carlo simulation : Simulation using MCSM
Monte Carlo simulation : Simulation using MCSM
 
unwanted pregnancy Kit [+918133066128] Abortion Pills IN Dubai UAE Abudhabi
unwanted pregnancy Kit [+918133066128] Abortion Pills IN Dubai UAE Abudhabiunwanted pregnancy Kit [+918133066128] Abortion Pills IN Dubai UAE Abudhabi
unwanted pregnancy Kit [+918133066128] Abortion Pills IN Dubai UAE Abudhabi
 
Cracking the Cultural Competence Code.pptx
Cracking the Cultural Competence Code.pptxCracking the Cultural Competence Code.pptx
Cracking the Cultural Competence Code.pptx
 
The Coffee Bean & Tea Leaf(CBTL), Business strategy case study
The Coffee Bean & Tea Leaf(CBTL), Business strategy case studyThe Coffee Bean & Tea Leaf(CBTL), Business strategy case study
The Coffee Bean & Tea Leaf(CBTL), Business strategy case study
 
Grateful 7 speech thanking everyone that has helped.pdf
Grateful 7 speech thanking everyone that has helped.pdfGrateful 7 speech thanking everyone that has helped.pdf
Grateful 7 speech thanking everyone that has helped.pdf
 
Insurers' journeys to build a mastery in the IoT usage
Insurers' journeys to build a mastery in the IoT usageInsurers' journeys to build a mastery in the IoT usage
Insurers' journeys to build a mastery in the IoT usage
 
9599632723 Top Call Girls in Delhi at your Door Step Available 24x7 Delhi
9599632723 Top Call Girls in Delhi at your Door Step Available 24x7 Delhi9599632723 Top Call Girls in Delhi at your Door Step Available 24x7 Delhi
9599632723 Top Call Girls in Delhi at your Door Step Available 24x7 Delhi
 
Call Girls in Gomti Nagar - 7388211116 - With room Service
Call Girls in Gomti Nagar - 7388211116  - With room ServiceCall Girls in Gomti Nagar - 7388211116  - With room Service
Call Girls in Gomti Nagar - 7388211116 - With room Service
 
Ensure the security of your HCL environment by applying the Zero Trust princi...
Ensure the security of your HCL environment by applying the Zero Trust princi...Ensure the security of your HCL environment by applying the Zero Trust princi...
Ensure the security of your HCL environment by applying the Zero Trust princi...
 
MONA 98765-12871 CALL GIRLS IN LUDHIANA LUDHIANA CALL GIRL
MONA 98765-12871 CALL GIRLS IN LUDHIANA LUDHIANA CALL GIRLMONA 98765-12871 CALL GIRLS IN LUDHIANA LUDHIANA CALL GIRL
MONA 98765-12871 CALL GIRLS IN LUDHIANA LUDHIANA CALL GIRL
 
VVVIP Call Girls In Greater Kailash ➡️ Delhi ➡️ 9999965857 🚀 No Advance 24HRS...
VVVIP Call Girls In Greater Kailash ➡️ Delhi ➡️ 9999965857 🚀 No Advance 24HRS...VVVIP Call Girls In Greater Kailash ➡️ Delhi ➡️ 9999965857 🚀 No Advance 24HRS...
VVVIP Call Girls In Greater Kailash ➡️ Delhi ➡️ 9999965857 🚀 No Advance 24HRS...
 
Call Girls Pune Just Call 9907093804 Top Class Call Girl Service Available
Call Girls Pune Just Call 9907093804 Top Class Call Girl Service AvailableCall Girls Pune Just Call 9907093804 Top Class Call Girl Service Available
Call Girls Pune Just Call 9907093804 Top Class Call Girl Service Available
 

PMP Training - 04 project integration management

  • 1. Created by ejlp12@gmail.com, June 2010 5 - Project Integration Management Project Management Training
  • 2. Project Integration Management Monitoring & Controlling Processes Planning Processes Enter phase/ Start project Exit phase/ End project Initiating Processes Closing Processes Executing Processes
  • 3. Project Integration Management Process and activities needed to identify, define, combine, unify, and coordinate the various processes and project management activities within the Project Management Process Groups.
  • 4. 4.1 Develop Project Charter The process of developing a document that formally authorizes a project or a phase and documenting initial requirements that satisfy the stakeholder’s needs and expectations
  • 5.
  • 6. Project Selection – Economic Models You just need to understand the following concepts FP = future value r = interest rate n = number of time period Present value (PV): The value today of future cash flows Net present value (NPV): Project with positive & greater NPV value is better Internal rate of return (IRR): Project with greater IRR value is better Payback period: The number of time periods it takes to recover your investment in the project before you start accumulating profit. Benefit-cost ratio: compares the benefits to the costs of different options relates to costing projects and to determining what work should be done Project with greater benefit-cost ratio value is better
  • 7. Project Selection – Important Terms Economic Value Added (EVA): concerned with whether the project returns to the company more value than it costs. Opportunity Cost: the opportunity given up by selecting one project over another Sunk Costs: Are expended costs Should not be considered when deciding whether to continue with a troubled project. Lay of Diminishing Returns: after a certain point, adding more input/resource will not produce a proportional increase in productivity
  • 8. Project Selection – Important Terms Working Capital current assets minus current liabilities for an organization or amount of money the company has available to invest Depreciation Straight line depreciation The same amount of depreciation is taken each year. Accelerated depreciation Depreciates faster than straight line Two forms: (1) Double Declining Balance, (2) Sum of the Years Digits
  • 9.
  • 13. PMO
  • 15.
  • 16.
  • 17. Change Management Plan Describes how changes will be managed and controlled. Covers for the project as whole May includes: Change control procedures (how and who) The approval levels for authorizing changes The creation of a change control board to approve changes A plan outlining how changes will be managed and controlled Who should attend meetings regarding changes Tools to use to track and control changes Each knowledge area are described in the individual management plans
  • 18. Configuration Management Plan Defines how you will manage changes to the deliverables and the resulting documentation, including which organizational tools you will use
  • 19. 4.3 Direct & Manage Project Execution The process of performing the work defined in the project management plan to achieve the project’s objectives.
  • 20. 4.4 Monitor & Control Project Work The process of tracking, reviewing, and regulating the progress to meet the performance objectives defined in the project management plan.
  • 21. 4.5 Perform Integrated Change Control The process of reviewing all change requests, approving changes and managing changes to deliverables, organizational process assets, project documents and the project management plan.
  • 22. 4.6 Closing Project or Phase The process of of finalizing all activities across all of the Project Management Process Groups to formally complete the project or phase.
  • 23. Next topic: Project Scope Management Thank You