1. AquaBlok® Installation:
EARTHEN POND/BASIN
CONSTRUCTION
NOTE: Use the arrows below to
scroll through this photo series; click
on the four arrow icon on the lower
right of this slideshow to view the
series in an enlarged, full-screen
format.
Nature’s Duct Tape. TM
Simple. Unique. Versatile. Effective.
2. Overview of ~1-acre basin prior to inundation with one-third of the basin bottom lined with AquaBlok® at 7-lbs/SF (~1” dry
material thickness). Permeability of native soils were marginal, so only the basin bottom was lined. Note the contrast between
the dark AquaBlok (back of photo) and the light dusting of snow covering the foreground and side slopes of the basin.
3. AquaBlok® liner application from a remote-controlled, belt-driven conveyor (often referred to as a “stone slinger”). Note one
person controlling radial belt and the second person floating the newly applied (dry) product to insure the most consistent
material thickness. Also note bulk bags of AquaBlok in background, staged for transloading into the slinger truck.
4. AquaBlok® liner application from a remote-controlled, belt-driven conveyor (“stone slinger”). Note one person controlling
radial belt and the second person floating the newly applied (dry) product to insure the most consistent material thickness.
Slinger trucks typically have a 15-18 cubic yard capacity and can broadcast AquaBlok up to 90’ from the back bumper.
5. Overview of an AquaBlok® liner application from atop the remote-controlled “stone slinger.” Note one person controlling the
radial belt and the second person available to float the newly applied (dry) product to insure the most consistent material
thickness. A 20-ton capacity truck can offload to achieve a 1” dry material thickness in less than 30 minutes.
6. Overview of ~35,000SF (0.8 acre) of basin bottom just lined with AquaBlok® at 7-lbs/SF (~1” dry material thickness) and prior
to inundation. Note pooling water caused by hydration of bentonite/AquaBlok (darkened product at center). Approximately
125 tons of AquaBlok were placed with a three person crew (including one loading the truck) in approximately four (4) hours.
7. Overview of ~1-acre basin three years after being lined with AquaBlok®. The bentonite-stone composite was applied during
construction and prior to inundation. Precipitation and surface water runoff from surrounding development filled the pond
initially and it has maintained at full pool since.