SlideShare une entreprise Scribd logo
1  sur  3
Télécharger pour lire hors ligne
The use of time bar clauses in standard form EPC contracts is common. How effective
a tool are such clauses for managing contractors’ claims for extensions of time and
additional payment, and what challenges will there be in enforcing a time bar clause?
Raising the Bar
Time Bars and their enforceability in
English law EPC contracts
What is a time bar clause?
Almost all EPC contracts will contain a contractual
mechanism for giving the contractor an extension of time
to complete the works, by extending the contractual
completion date upon the occurrence of specified events.
EPC contracts will usually also provide for such events to
trigger the contractor’s right to claim additional payment.
Additionally, the contract may specify a date by which
the contractor must notify the employer or contract
administrator of any claim it has (for time and/or money). A
time bar clause provides that if the contractor fails to serve
the requisite notice within the specified period it will, in
theory, become time barred from claiming any extension of
time or additional payment.
Time bar provisions of the type described above can be
found in most standard form EPC contracts. The FIDIC major
works contracts1
include a time bar provision at Clause 20.1,
which is set out as follows:
“If the Contractor considers himself to be entitled to
any extension of the Time for Completion and/or any
additional payment, under any Clause of these Conditions
or otherwise in connection with the Contract, the
Contractor shall give notice to the Employer, describing the
event or circumstance giving rise to the claim. The notice
shall be given as soon as practicable, and not later than 28
days after the contractor became aware, or should have
become aware, of the event or circumstance.
If the Contractor fails to give notice of a claim within such
period of 28 days, the Time for Completion shall not be
extended, the Contractor shall not be entitled to additional
payment, and the Employer shall be discharged from all
liability in connection with the claim…”
1	 The FIDIC 1999 suite of contracts – Conditions of Contract for Construction
(Red Book), Conditions of Contract for EPC/Turnkey Projects (Silver Book)
and Conditions of Contract for Plant and Design-Build (Yellow Book).
For a project executed under FIDIC conditions, there will
be a clear requirement for the contractor to provide the
employer with notice of its claim no later than 28 days after it
becomes aware of the relevant event. The second paragraph
of Clause 20.1 makes the contractor’s compliance with the
28-day requirement a condition precedent to any entitlement
it may have to additional time or money under the contract.
Most bespoke EPC contracts will include similar provisions.
Why are time bar clauses used?
The principle purpose of using strict time bar clauses,
such as that provided for by Clause 20.1, is to improve the
administration of the contract. By ensuring a hard deadline for
the contractor to notify it of any events which may give rise
to a claim, the employer is alerted to the contractor’s claim at
an early stage. This allows the employer to evaluate the claim,
and also take any steps to work with the contractor to mitigate
the delay. It should also help to avoid a build up of contractor’s
claims during a project, which historically has often led to a
final account dispute between the employer and contractor.
This process imposes a more proactive contemporaneous
approach to dealing with unexpected events when they
arrive, and providing cost and programme certainty and
transparency. An effective time bar clause can be used as a
tool for achieving a more collaborative approach between the
contractor and employer in relation to claims for additional
time and money.
Will my time bar clause be effective?
Condition Precedent
The starting point to determine whether a time bar clause
will be enforceable by the employer against the contractor
is to understand whether compliance with the clause is
a condition precedent to the contractor’s claim. When
considering this question, the English courts have typically
taken the view that the notice requirements in construction
contracts are directory, not mandatory, and that a contractor
may not lose its entitlement to a claim, unless the contract
expressly states that a non-compliant contractor will lose its
rights to additional time and/or money.
However, within standard form EPC contracts time bar
clauses will usually be drafted such that they have the
necessary elements of a condition precedent. Clause 20.1
of the FIDIC Silver Book is a good example of a provision
intended to be a condition precedent as:
(i)	 the clause specifies the time period within which notice
must be served by the contractor; and
(ii)	the clause expressly states the consequences of the
contractor’s failure to serve notice of its claim within the
relevant time (i.e. that the contractor will lose its rights
against the employer).2
2	 See Bremer Handelgesellschaft mbH v Vanden Avenne Izegem PVBA
[1978] 2 Lloyd’s Rep. 113 as to the rules on condition precedents.
In a recent decision, Obrascon Huarte Lain SA v Attorney
General for Gibraltar3
, it was accepted by counsel for
the contractor that Clause 20.14
did impose a condition
precedent on the contractor. It is very likely that should
Clause 20.1 be challenged before a court or arbitral tribunal
it will be interpreted as in Obrascon Huarte. Therefore for
projects carried out on FIDIC conditions, the parties should
treat strict compliance with the provisions of Clause 20.1 as
a condition precedent to the contractor’s claim. Clauses with
similar features as Clause 20.1 are likely to be interpreted in
the same way.
In the case of Adyard Abu Dhabi v SD Marine Services5
,
which concerned a shipbuilding contract, the English High
court found that clauses requiring the shipbuilder to give
notice of delays were to be treated as condition precedents,
and as the shipbuilder failed to give such notices it lost its
entitlement to make a claim in respect of such delay.
The Contractor’s Notice
The next issue to consider is what information the contractor
will be required to give to the employer in its notice of a
claim for additional time and/or money. Whilst it is open for
parties to specify in the contract exactly what details must
be included in the contractor’s notice, not all EPC contracts
do so. We have advised on EPC contracts where critical path
analysis (amongst other demands) is required within 28 days
of an event giving rise to an extension of time arising. Often,
EPC contractors will find such demands challenging.
In the absence of requirements set out in the contract, the
English courts have generally considered that the contractor
is only required to give the best information it is reasonably
able to do so, and only information which is available to the
contractor at that time.6
In Obrascon Huarte, the TCC considered that for Clause 20.1:
“… one should construe it as permitting any claim
provided that it is made by notice in writing to
the Engineer, that the notice describes the event or
circumstance relied on and that the notice is intended to
notify a claim for extension (or for additional payment
or both) under the Contract or in connection with it. It
must be recognizable as a “claim”.”7
Obrascon also looked at when time will start running for the
purposes of the contractor serving its notice under the time
bar clause. The TCC concluded that there must have been
awareness of the circumstance, or the means of awareness
of the relevant circumstance, before the condition precedent
will bite. Furthermore, the time bar clause should not be
construed strictly against the contractor in this respect. The
burden of proof would instead be on the employer seeking
to argue that a notice had not been given in time.
3	 [2014] EWHC 1028 (TCC)
4	 This case considered a project executed under the FIDIC Yellow Book con-
ditions
5	 [2011] EWHC 848 (Comm)
6	 Multiplex Constructions (UK) Ltd v Honeywell Control Systems (No 2)
7	 Obrascon Huarte Lain SA v Attorney General for Gibraltar [2014] EWHC
1028 (TCC) at para. 313
‘Prevention Principle’ Arguments
It is often suggested that a contractor may seek to avoid
the strict application of a time bar clause by arguing that,
irrespective of its own non-compliance with the provision,
the prevention principle may still defeat an employer’s
claim for liquidated damages where the delay is caused by
an occurrence which is the employer’s responsibility under
the contract.
This line of argument has support from a series of Australian
decisions which considered that the prevention principle
could result in time bar provisions being defeated.8
However,
this approach is not one that would necessarily be followed
by an English court or by an arbitral tribunal. In City Inn
Ltd v Shepherd Construction Ltd9
, a Scottish case, the court
took a robust view of the contractor’s obligation to time
bar provisions, and whilst the court did not, on the facts,
decide whether the prevention principle would operate, it
considered the contractor to have an obligation to comply
with the provisions of the time bar clause, unless waived by
the employer (or as on the facts, the employer’s architect).
In the Adyard Abu Dhabi case, referred to above, the court
accepted the argument that the contract contained provisions
entitling the shipyard to an extension of time, therefore the
prevention principle was displaced. Hamblen J stated that:
“However, as Jackson J stated in the Multiplex v
Honeywell case, the prevention principle does not apply
if the contract provides for an extension of time in
respect of the relevant events.”10
8	 Gaymark Investments Pty Ltd v Walter Construction Group Ltd (2000) 16
BCL 449 and Peninsula Balmain Pty Ltd v Abigroup Contractors Corp Pty
Ltd [2002] NSWCA 211
9	 [2003] BLR 468
10	 [2011] EWHC 848 (Comm) at paragraph 243
Conclusion
The time bar clause will continue to be a feature of most EPC
contracts for major projects, and provides a useful tool for
the employer in the administration of the contract, ensuring
certainty and transparency of time and cost.
From the contractor’s perspective, it should not be an overly
onerous obligation provided that the contractor is alert to
the requirements of the clause. There can also be upsides for
EPC contractors in efficiently managing and prospectively
agreeing the time/money effect of change as and when it
occurs. Time bar clauses should work to the advantage of
all parties to the project by ensuring the early notification of
circumstances giving rise to potential claims, conducive to a
cooperative approach between the parties.
A strict approach to time bar clauses is likely to be preferred
by courts and arbitral tribunals, as were it to be found that
the prevention principle did override time bar provisions,
this would create a possibility of abuse by the contractor. It
has been identified that if the prevention principle were to
be applied in such cases, it would enable the contractor to
disregard the time bar provision, and set time at large under
the contract, without recourse by the employer.11
Such an
outcome is clearly not satisfactory in light of a time bar clause
negotiated between commercial parties.
11	 Multiplex Constructions (UK) Ltd v Honeywell Control Systems (No 2),
para. 103
www.eversheds.com
©EVERSHEDS LLP 2014. Eversheds LLP is a limited liability partnership. DT03641_07/14
Paul Giles
Partner, Eversheds LLP
+ 44 20 7497 9797
paulgiles@eversheds.com
Steve Gibson
Associate, Eversheds LLP
+65 6572 5587
stevengibson@eversheds.com

Contenu connexe

Tendances

Agreements withholding consideration
Agreements withholding considerationAgreements withholding consideration
Agreements withholding considerationEzat Dandashi
 
media report analysis (final)
media report analysis (final)media report analysis (final)
media report analysis (final)John McMahon
 
Cases in Delays - Indian Contract Act, 1872
Cases in Delays - Indian Contract Act, 1872Cases in Delays - Indian Contract Act, 1872
Cases in Delays - Indian Contract Act, 1872Karthik Madhavan
 
Security for Performance
Security for PerformanceSecurity for Performance
Security for PerformanceLaina Chan
 
Action to Recover Solicitor's Fees - Locus Standi and Privity Hurdle: The cas...
Action to Recover Solicitor's Fees - Locus Standi and Privity Hurdle: The cas...Action to Recover Solicitor's Fees - Locus Standi and Privity Hurdle: The cas...
Action to Recover Solicitor's Fees - Locus Standi and Privity Hurdle: The cas...Acas Media
 
The Law of Penalties - ANZ v Andrews and beyond
The Law of Penalties - ANZ v Andrews and beyond The Law of Penalties - ANZ v Andrews and beyond
The Law of Penalties - ANZ v Andrews and beyond Laina Chan
 
FIDIC 2016 Day02-1010 Variations Under FIDIC Forms, Adrias Tan
FIDIC 2016 Day02-1010 Variations Under FIDIC Forms, Adrias TanFIDIC 2016 Day02-1010 Variations Under FIDIC Forms, Adrias Tan
FIDIC 2016 Day02-1010 Variations Under FIDIC Forms, Adrias TanAdrias TAN
 
Powerpoint for Legalwise Annual Property Seminar March 2016
Powerpoint for Legalwise Annual Property Seminar March 2016Powerpoint for Legalwise Annual Property Seminar March 2016
Powerpoint for Legalwise Annual Property Seminar March 2016Laina Chan
 
Construction Law - Remedies for Breach of Contract
Construction Law - Remedies for Breach of ContractConstruction Law - Remedies for Breach of Contract
Construction Law - Remedies for Breach of ContractPang Khai Shuen
 
25 No 1 J Bankr L And Prac NL Art 2
25 No 1 J Bankr L And Prac NL Art 225 No 1 J Bankr L And Prac NL Art 2
25 No 1 J Bankr L And Prac NL Art 2Janine Lee
 
Lawweb.in whether dispute involving enforcement of intellectual property righ...
Lawweb.in whether dispute involving enforcement of intellectual property righ...Lawweb.in whether dispute involving enforcement of intellectual property righ...
Lawweb.in whether dispute involving enforcement of intellectual property righ...Law Web
 
UNL1622 – CONTRACT LAW II (REMOTENESS)
UNL1622 – CONTRACT LAW II (REMOTENESS)UNL1622 – CONTRACT LAW II (REMOTENESS)
UNL1622 – CONTRACT LAW II (REMOTENESS)Wei Lie Lim
 
parol evidence rule and collateral contract
parol evidence rule and collateral contractparol evidence rule and collateral contract
parol evidence rule and collateral contractNur Farhana Ana
 
Insuring Risk in Construction Projects
Insuring Risk in Construction ProjectsInsuring Risk in Construction Projects
Insuring Risk in Construction ProjectsLaina Chan
 
Business Money talks to City barrister Professor Mark Watson-Gandy about sett...
Business Money talks to City barrister Professor Mark Watson-Gandy about sett...Business Money talks to City barrister Professor Mark Watson-Gandy about sett...
Business Money talks to City barrister Professor Mark Watson-Gandy about sett...Sofiane Bounoua
 
Mardia chemicals case by shreya a322509022
Mardia chemicals case by shreya a322509022Mardia chemicals case by shreya a322509022
Mardia chemicals case by shreya a322509022Shreya Ganguly
 

Tendances (19)

Agreements withholding consideration
Agreements withholding considerationAgreements withholding consideration
Agreements withholding consideration
 
media report analysis (final)
media report analysis (final)media report analysis (final)
media report analysis (final)
 
Cases in Delays - Indian Contract Act, 1872
Cases in Delays - Indian Contract Act, 1872Cases in Delays - Indian Contract Act, 1872
Cases in Delays - Indian Contract Act, 1872
 
Security for Performance
Security for PerformanceSecurity for Performance
Security for Performance
 
Action to Recover Solicitor's Fees - Locus Standi and Privity Hurdle: The cas...
Action to Recover Solicitor's Fees - Locus Standi and Privity Hurdle: The cas...Action to Recover Solicitor's Fees - Locus Standi and Privity Hurdle: The cas...
Action to Recover Solicitor's Fees - Locus Standi and Privity Hurdle: The cas...
 
The Law of Penalties - ANZ v Andrews and beyond
The Law of Penalties - ANZ v Andrews and beyond The Law of Penalties - ANZ v Andrews and beyond
The Law of Penalties - ANZ v Andrews and beyond
 
FIDIC 2016 Day02-1010 Variations Under FIDIC Forms, Adrias Tan
FIDIC 2016 Day02-1010 Variations Under FIDIC Forms, Adrias TanFIDIC 2016 Day02-1010 Variations Under FIDIC Forms, Adrias Tan
FIDIC 2016 Day02-1010 Variations Under FIDIC Forms, Adrias Tan
 
Powerpoint for Legalwise Annual Property Seminar March 2016
Powerpoint for Legalwise Annual Property Seminar March 2016Powerpoint for Legalwise Annual Property Seminar March 2016
Powerpoint for Legalwise Annual Property Seminar March 2016
 
Construction Law - Remedies for Breach of Contract
Construction Law - Remedies for Breach of ContractConstruction Law - Remedies for Breach of Contract
Construction Law - Remedies for Breach of Contract
 
25 No 1 J Bankr L And Prac NL Art 2
25 No 1 J Bankr L And Prac NL Art 225 No 1 J Bankr L And Prac NL Art 2
25 No 1 J Bankr L And Prac NL Art 2
 
Dealing with 'fit for purpose' obligation
Dealing with 'fit for purpose' obligationDealing with 'fit for purpose' obligation
Dealing with 'fit for purpose' obligation
 
Lawweb.in whether dispute involving enforcement of intellectual property righ...
Lawweb.in whether dispute involving enforcement of intellectual property righ...Lawweb.in whether dispute involving enforcement of intellectual property righ...
Lawweb.in whether dispute involving enforcement of intellectual property righ...
 
Business laws
Business lawsBusiness laws
Business laws
 
UNL1622 – CONTRACT LAW II (REMOTENESS)
UNL1622 – CONTRACT LAW II (REMOTENESS)UNL1622 – CONTRACT LAW II (REMOTENESS)
UNL1622 – CONTRACT LAW II (REMOTENESS)
 
Standard Form Contract
Standard Form ContractStandard Form Contract
Standard Form Contract
 
parol evidence rule and collateral contract
parol evidence rule and collateral contractparol evidence rule and collateral contract
parol evidence rule and collateral contract
 
Insuring Risk in Construction Projects
Insuring Risk in Construction ProjectsInsuring Risk in Construction Projects
Insuring Risk in Construction Projects
 
Business Money talks to City barrister Professor Mark Watson-Gandy about sett...
Business Money talks to City barrister Professor Mark Watson-Gandy about sett...Business Money talks to City barrister Professor Mark Watson-Gandy about sett...
Business Money talks to City barrister Professor Mark Watson-Gandy about sett...
 
Mardia chemicals case by shreya a322509022
Mardia chemicals case by shreya a322509022Mardia chemicals case by shreya a322509022
Mardia chemicals case by shreya a322509022
 

Similaire à Time Bars and their enforceability in English law EPC contracts

time bar clauses
time bar clausestime bar clauses
time bar clausesAMILA GAYAN
 
Techno Engineering & Associates
Techno Engineering & AssociatesTechno Engineering & Associates
Techno Engineering & AssociatesCerasela Angelescu
 
Dispute Resolution-Mechanism.pptx
Dispute Resolution-Mechanism.pptxDispute Resolution-Mechanism.pptx
Dispute Resolution-Mechanism.pptxPujanNeupane6
 
A Case Study based on FIDIC and PAM Form 2006
A Case Study based on FIDIC and PAM Form 2006A Case Study based on FIDIC and PAM Form 2006
A Case Study based on FIDIC and PAM Form 2006Melvin Lim
 
PP2 - Seminar Presentation
PP2 - Seminar Presentation PP2 - Seminar Presentation
PP2 - Seminar Presentation Lin Hui
 
Construction law update august 2015 quarter 2 a
Construction law update august 2015 quarter 2 aConstruction law update august 2015 quarter 2 a
Construction law update august 2015 quarter 2 aColin Tomlinson
 
Commercial and Construction Law Update Q2 2015
Commercial and Construction Law Update Q2 2015Commercial and Construction Law Update Q2 2015
Commercial and Construction Law Update Q2 2015Colin Tomlinson
 
Commericial Management and Construction law update 2015 Q2
Commericial Management and Construction law update 2015 Q2Commericial Management and Construction law update 2015 Q2
Commericial Management and Construction law update 2015 Q2Colin Tomlinson
 
PRC Contract Law Principles and Risk Management in Contract Drafting
PRC Contract Law Principles and Risk Management in Contract DraftingPRC Contract Law Principles and Risk Management in Contract Drafting
PRC Contract Law Principles and Risk Management in Contract DraftingRHKLegal
 
المحاضرة 160 بعنوان البرنامج الزمنى فى عقود التشيد
المحاضرة 160 بعنوان البرنامج الزمنى فى عقود التشيدالمحاضرة 160 بعنوان البرنامج الزمنى فى عقود التشيد
المحاضرة 160 بعنوان البرنامج الزمنى فى عقود التشيدEgyptian Engineers Association
 
Substitute and vicarious_performance
Substitute and vicarious_performanceSubstitute and vicarious_performance
Substitute and vicarious_performanceHafizul Mukhlis
 
Clause 16 suspension
Clause 16 suspensionClause 16 suspension
Clause 16 suspensionbreyerhanna
 
Article 41 payment and pay less notices february 2017 rm03
Article 41 payment and pay less notices february 2017 rm03Article 41 payment and pay less notices february 2017 rm03
Article 41 payment and pay less notices february 2017 rm03Nick Cheetham
 
Professional Practice II - Presentation - Construction Delays & EOT
Professional Practice II - Presentation - Construction Delays & EOTProfessional Practice II - Presentation - Construction Delays & EOT
Professional Practice II - Presentation - Construction Delays & EOTYee Len Wan
 
Nachfrist for late performance
Nachfrist for late performanceNachfrist for late performance
Nachfrist for late performanceSaman Sara
 

Similaire à Time Bars and their enforceability in English law EPC contracts (20)

time bar clauses
time bar clausestime bar clauses
time bar clauses
 
Techno Engineering & Associates
Techno Engineering & AssociatesTechno Engineering & Associates
Techno Engineering & Associates
 
Dispute Resolution-Mechanism.pptx
Dispute Resolution-Mechanism.pptxDispute Resolution-Mechanism.pptx
Dispute Resolution-Mechanism.pptx
 
A Case Study based on FIDIC and PAM Form 2006
A Case Study based on FIDIC and PAM Form 2006A Case Study based on FIDIC and PAM Form 2006
A Case Study based on FIDIC and PAM Form 2006
 
PP2 - Seminar Presentation
PP2 - Seminar Presentation PP2 - Seminar Presentation
PP2 - Seminar Presentation
 
UK Adjudicators November 2020 Newsletter
UK Adjudicators November 2020 NewsletterUK Adjudicators November 2020 Newsletter
UK Adjudicators November 2020 Newsletter
 
Construction law update august 2015 quarter 2 a
Construction law update august 2015 quarter 2 aConstruction law update august 2015 quarter 2 a
Construction law update august 2015 quarter 2 a
 
Commercial and Construction Law Update Q2 2015
Commercial and Construction Law Update Q2 2015Commercial and Construction Law Update Q2 2015
Commercial and Construction Law Update Q2 2015
 
Commericial Management and Construction law update 2015 Q2
Commericial Management and Construction law update 2015 Q2Commericial Management and Construction law update 2015 Q2
Commericial Management and Construction law update 2015 Q2
 
PRC Contract Law Principles and Risk Management in Contract Drafting
PRC Contract Law Principles and Risk Management in Contract DraftingPRC Contract Law Principles and Risk Management in Contract Drafting
PRC Contract Law Principles and Risk Management in Contract Drafting
 
Cl compilation
Cl compilationCl compilation
Cl compilation
 
المحاضرة 160 بعنوان البرنامج الزمنى فى عقود التشيد
المحاضرة 160 بعنوان البرنامج الزمنى فى عقود التشيدالمحاضرة 160 بعنوان البرنامج الزمنى فى عقود التشيد
المحاضرة 160 بعنوان البرنامج الزمنى فى عقود التشيد
 
Substitute and vicarious_performance
Substitute and vicarious_performanceSubstitute and vicarious_performance
Substitute and vicarious_performance
 
Clause 16 suspension
Clause 16 suspensionClause 16 suspension
Clause 16 suspension
 
Good Title
Good TitleGood Title
Good Title
 
Quantum Meruit
Quantum MeruitQuantum Meruit
Quantum Meruit
 
Article 41 payment and pay less notices february 2017 rm03
Article 41 payment and pay less notices february 2017 rm03Article 41 payment and pay less notices february 2017 rm03
Article 41 payment and pay less notices february 2017 rm03
 
Professional Practice II - Presentation - Construction Delays & EOT
Professional Practice II - Presentation - Construction Delays & EOTProfessional Practice II - Presentation - Construction Delays & EOT
Professional Practice II - Presentation - Construction Delays & EOT
 
Nachfrist for late performance
Nachfrist for late performanceNachfrist for late performance
Nachfrist for late performance
 
Claims and insolvencies (1)
Claims and insolvencies (1)Claims and insolvencies (1)
Claims and insolvencies (1)
 

Plus de Eversheds Sutherland

Conduct Risk – What Corporates Can Learn From The Financial Sector
Conduct Risk – What Corporates Can Learn From The Financial SectorConduct Risk – What Corporates Can Learn From The Financial Sector
Conduct Risk – What Corporates Can Learn From The Financial SectorEversheds Sutherland
 
How technology and innovative processes can make your legal team more efficient
How technology and innovative processes can make your legal team more efficientHow technology and innovative processes can make your legal team more efficient
How technology and innovative processes can make your legal team more efficientEversheds Sutherland
 
Preparing for Brexit - Future proofing your contracts
Preparing for Brexit - Future proofing your contractsPreparing for Brexit - Future proofing your contracts
Preparing for Brexit - Future proofing your contractsEversheds Sutherland
 
State Aid and Tax – Understanding the risks
State Aid and Tax – Understanding the risksState Aid and Tax – Understanding the risks
State Aid and Tax – Understanding the risksEversheds Sutherland
 
Opportunities and challenges of managing a globally mobile workforce
Opportunities and challenges of managing a globally mobile workforceOpportunities and challenges of managing a globally mobile workforce
Opportunities and challenges of managing a globally mobile workforceEversheds Sutherland
 
Getting over ‘Regrexit’ - Post Brexit Real Estate Opportunities
Getting over ‘Regrexit’ - Post Brexit Real Estate OpportunitiesGetting over ‘Regrexit’ - Post Brexit Real Estate Opportunities
Getting over ‘Regrexit’ - Post Brexit Real Estate OpportunitiesEversheds Sutherland
 
State Aid and Tax challenges - 13 May 2016
State Aid and Tax challenges - 13 May 2016State Aid and Tax challenges - 13 May 2016
State Aid and Tax challenges - 13 May 2016Eversheds Sutherland
 
Is your intellectual property at risk?
Is your intellectual property at risk?Is your intellectual property at risk?
Is your intellectual property at risk?Eversheds Sutherland
 
The Key Role of In-House Legal in Business and Human Rights
The Key Role of In-House Legal in Business and Human RightsThe Key Role of In-House Legal in Business and Human Rights
The Key Role of In-House Legal in Business and Human RightsEversheds Sutherland
 
Front office controls – what are the FCA’s expectations?
Front office controls – what are the FCA’s expectations?Front office controls – what are the FCA’s expectations?
Front office controls – what are the FCA’s expectations?Eversheds Sutherland
 
Eversheds CREATE Workshop #1: Real estate holding structures
Eversheds CREATE Workshop #1: Real estate holding structuresEversheds CREATE Workshop #1: Real estate holding structures
Eversheds CREATE Workshop #1: Real estate holding structuresEversheds Sutherland
 
Data Security Breach – knowing the risks and protecting your business
Data Security Breach – knowing the risks and protecting your businessData Security Breach – knowing the risks and protecting your business
Data Security Breach – knowing the risks and protecting your businessEversheds Sutherland
 
LawWithoutWalls - 2016 projects of worth
LawWithoutWalls - 2016 projects of worthLawWithoutWalls - 2016 projects of worth
LawWithoutWalls - 2016 projects of worthEversheds Sutherland
 
Eversheds 'Spotlight on the Cloud' - headline results presentation and key sp...
Eversheds 'Spotlight on the Cloud' - headline results presentation and key sp...Eversheds 'Spotlight on the Cloud' - headline results presentation and key sp...
Eversheds 'Spotlight on the Cloud' - headline results presentation and key sp...Eversheds Sutherland
 
Talent Management – Harnessing the power of your team
Talent Management – Harnessing the power of your teamTalent Management – Harnessing the power of your team
Talent Management – Harnessing the power of your teamEversheds Sutherland
 

Plus de Eversheds Sutherland (20)

The fourth industrial revolution
The fourth industrial revolutionThe fourth industrial revolution
The fourth industrial revolution
 
Conduct Risk – What Corporates Can Learn From The Financial Sector
Conduct Risk – What Corporates Can Learn From The Financial SectorConduct Risk – What Corporates Can Learn From The Financial Sector
Conduct Risk – What Corporates Can Learn From The Financial Sector
 
Navigating the Insurance Act
Navigating the Insurance ActNavigating the Insurance Act
Navigating the Insurance Act
 
How technology and innovative processes can make your legal team more efficient
How technology and innovative processes can make your legal team more efficientHow technology and innovative processes can make your legal team more efficient
How technology and innovative processes can make your legal team more efficient
 
Preparing for Brexit - Future proofing your contracts
Preparing for Brexit - Future proofing your contractsPreparing for Brexit - Future proofing your contracts
Preparing for Brexit - Future proofing your contracts
 
State Aid and Tax – Understanding the risks
State Aid and Tax – Understanding the risksState Aid and Tax – Understanding the risks
State Aid and Tax – Understanding the risks
 
Opportunities and challenges of managing a globally mobile workforce
Opportunities and challenges of managing a globally mobile workforceOpportunities and challenges of managing a globally mobile workforce
Opportunities and challenges of managing a globally mobile workforce
 
Post Brexit Update
Post Brexit UpdatePost Brexit Update
Post Brexit Update
 
Getting over ‘Regrexit’ - Post Brexit Real Estate Opportunities
Getting over ‘Regrexit’ - Post Brexit Real Estate OpportunitiesGetting over ‘Regrexit’ - Post Brexit Real Estate Opportunities
Getting over ‘Regrexit’ - Post Brexit Real Estate Opportunities
 
Metrics for In-House Teams
Metrics for In-House TeamsMetrics for In-House Teams
Metrics for In-House Teams
 
State Aid and Tax challenges - 13 May 2016
State Aid and Tax challenges - 13 May 2016State Aid and Tax challenges - 13 May 2016
State Aid and Tax challenges - 13 May 2016
 
Is your intellectual property at risk?
Is your intellectual property at risk?Is your intellectual property at risk?
Is your intellectual property at risk?
 
The Key Role of In-House Legal in Business and Human Rights
The Key Role of In-House Legal in Business and Human RightsThe Key Role of In-House Legal in Business and Human Rights
The Key Role of In-House Legal in Business and Human Rights
 
Front office controls – what are the FCA’s expectations?
Front office controls – what are the FCA’s expectations?Front office controls – what are the FCA’s expectations?
Front office controls – what are the FCA’s expectations?
 
Eversheds CREATE Workshop #1: Real estate holding structures
Eversheds CREATE Workshop #1: Real estate holding structuresEversheds CREATE Workshop #1: Real estate holding structures
Eversheds CREATE Workshop #1: Real estate holding structures
 
Data Security Breach – knowing the risks and protecting your business
Data Security Breach – knowing the risks and protecting your businessData Security Breach – knowing the risks and protecting your business
Data Security Breach – knowing the risks and protecting your business
 
LawWithoutWalls - 2016 projects of worth
LawWithoutWalls - 2016 projects of worthLawWithoutWalls - 2016 projects of worth
LawWithoutWalls - 2016 projects of worth
 
Eversheds 'Spotlight on the Cloud' - headline results presentation and key sp...
Eversheds 'Spotlight on the Cloud' - headline results presentation and key sp...Eversheds 'Spotlight on the Cloud' - headline results presentation and key sp...
Eversheds 'Spotlight on the Cloud' - headline results presentation and key sp...
 
Bribery and Corruption Campaign
Bribery and Corruption CampaignBribery and Corruption Campaign
Bribery and Corruption Campaign
 
Talent Management – Harnessing the power of your team
Talent Management – Harnessing the power of your teamTalent Management – Harnessing the power of your team
Talent Management – Harnessing the power of your team
 

Dernier

Russian Call Girls In Gurgaon ❤️8448577510 ⊹Best Escorts Service In 24/7 Delh...
Russian Call Girls In Gurgaon ❤️8448577510 ⊹Best Escorts Service In 24/7 Delh...Russian Call Girls In Gurgaon ❤️8448577510 ⊹Best Escorts Service In 24/7 Delh...
Russian Call Girls In Gurgaon ❤️8448577510 ⊹Best Escorts Service In 24/7 Delh...lizamodels9
 
Organizational Transformation Lead with Culture
Organizational Transformation Lead with CultureOrganizational Transformation Lead with Culture
Organizational Transformation Lead with CultureSeta Wicaksana
 
RSA Conference Exhibitor List 2024 - Exhibitors Data
RSA Conference Exhibitor List 2024 - Exhibitors DataRSA Conference Exhibitor List 2024 - Exhibitors Data
RSA Conference Exhibitor List 2024 - Exhibitors DataExhibitors Data
 
Call Girls Kengeri Satellite Town Just Call 👗 7737669865 👗 Top Class Call Gir...
Call Girls Kengeri Satellite Town Just Call 👗 7737669865 👗 Top Class Call Gir...Call Girls Kengeri Satellite Town Just Call 👗 7737669865 👗 Top Class Call Gir...
Call Girls Kengeri Satellite Town Just Call 👗 7737669865 👗 Top Class Call Gir...amitlee9823
 
Eluru Call Girls Service ☎ ️93326-06886 ❤️‍🔥 Enjoy 24/7 Escort Service
Eluru Call Girls Service ☎ ️93326-06886 ❤️‍🔥 Enjoy 24/7 Escort ServiceEluru Call Girls Service ☎ ️93326-06886 ❤️‍🔥 Enjoy 24/7 Escort Service
Eluru Call Girls Service ☎ ️93326-06886 ❤️‍🔥 Enjoy 24/7 Escort ServiceDamini Dixit
 
Katrina Personal Brand Project and portfolio 1
Katrina Personal Brand Project and portfolio 1Katrina Personal Brand Project and portfolio 1
Katrina Personal Brand Project and portfolio 1kcpayne
 
Nelamangala Call Girls: 🍓 7737669865 🍓 High Profile Model Escorts | Bangalore...
Nelamangala Call Girls: 🍓 7737669865 🍓 High Profile Model Escorts | Bangalore...Nelamangala Call Girls: 🍓 7737669865 🍓 High Profile Model Escorts | Bangalore...
Nelamangala Call Girls: 🍓 7737669865 🍓 High Profile Model Escorts | Bangalore...amitlee9823
 
Call Girls In Noida 959961⊹3876 Independent Escort Service Noida
Call Girls In Noida 959961⊹3876 Independent Escort Service NoidaCall Girls In Noida 959961⊹3876 Independent Escort Service Noida
Call Girls In Noida 959961⊹3876 Independent Escort Service Noidadlhescort
 
Falcon Invoice Discounting: Empowering Your Business Growth
Falcon Invoice Discounting: Empowering Your Business GrowthFalcon Invoice Discounting: Empowering Your Business Growth
Falcon Invoice Discounting: Empowering Your Business GrowthFalcon investment
 
Cracking the Cultural Competence Code.pptx
Cracking the Cultural Competence Code.pptxCracking the Cultural Competence Code.pptx
Cracking the Cultural Competence Code.pptxWorkforce Group
 
Dr. Admir Softic_ presentation_Green Club_ENG.pdf
Dr. Admir Softic_ presentation_Green Club_ENG.pdfDr. Admir Softic_ presentation_Green Club_ENG.pdf
Dr. Admir Softic_ presentation_Green Club_ENG.pdfAdmir Softic
 
BAGALUR CALL GIRL IN 98274*61493 ❤CALL GIRLS IN ESCORT SERVICE❤CALL GIRL
BAGALUR CALL GIRL IN 98274*61493 ❤CALL GIRLS IN ESCORT SERVICE❤CALL GIRLBAGALUR CALL GIRL IN 98274*61493 ❤CALL GIRLS IN ESCORT SERVICE❤CALL GIRL
BAGALUR CALL GIRL IN 98274*61493 ❤CALL GIRLS IN ESCORT SERVICE❤CALL GIRLkapoorjyoti4444
 
Call Girls in Delhi, Escort Service Available 24x7 in Delhi 959961-/-3876
Call Girls in Delhi, Escort Service Available 24x7 in Delhi 959961-/-3876Call Girls in Delhi, Escort Service Available 24x7 in Delhi 959961-/-3876
Call Girls in Delhi, Escort Service Available 24x7 in Delhi 959961-/-3876dlhescort
 
The Path to Product Excellence: Avoiding Common Pitfalls and Enhancing Commun...
The Path to Product Excellence: Avoiding Common Pitfalls and Enhancing Commun...The Path to Product Excellence: Avoiding Common Pitfalls and Enhancing Commun...
The Path to Product Excellence: Avoiding Common Pitfalls and Enhancing Commun...Aggregage
 
Call Girls Electronic City Just Call 👗 7737669865 👗 Top Class Call Girl Servi...
Call Girls Electronic City Just Call 👗 7737669865 👗 Top Class Call Girl Servi...Call Girls Electronic City Just Call 👗 7737669865 👗 Top Class Call Girl Servi...
Call Girls Electronic City Just Call 👗 7737669865 👗 Top Class Call Girl Servi...amitlee9823
 
Falcon's Invoice Discounting: Your Path to Prosperity
Falcon's Invoice Discounting: Your Path to ProsperityFalcon's Invoice Discounting: Your Path to Prosperity
Falcon's Invoice Discounting: Your Path to Prosperityhemanthkumar470700
 
Cheap Rate Call Girls In Noida Sector 62 Metro 959961乂3876
Cheap Rate Call Girls In Noida Sector 62 Metro 959961乂3876Cheap Rate Call Girls In Noida Sector 62 Metro 959961乂3876
Cheap Rate Call Girls In Noida Sector 62 Metro 959961乂3876dlhescort
 
Mysore Call Girls 8617370543 WhatsApp Number 24x7 Best Services
Mysore Call Girls 8617370543 WhatsApp Number 24x7 Best ServicesMysore Call Girls 8617370543 WhatsApp Number 24x7 Best Services
Mysore Call Girls 8617370543 WhatsApp Number 24x7 Best ServicesDipal Arora
 
How to Get Started in Social Media for Art League City
How to Get Started in Social Media for Art League CityHow to Get Started in Social Media for Art League City
How to Get Started in Social Media for Art League CityEric T. Tung
 

Dernier (20)

Russian Call Girls In Gurgaon ❤️8448577510 ⊹Best Escorts Service In 24/7 Delh...
Russian Call Girls In Gurgaon ❤️8448577510 ⊹Best Escorts Service In 24/7 Delh...Russian Call Girls In Gurgaon ❤️8448577510 ⊹Best Escorts Service In 24/7 Delh...
Russian Call Girls In Gurgaon ❤️8448577510 ⊹Best Escorts Service In 24/7 Delh...
 
Organizational Transformation Lead with Culture
Organizational Transformation Lead with CultureOrganizational Transformation Lead with Culture
Organizational Transformation Lead with Culture
 
RSA Conference Exhibitor List 2024 - Exhibitors Data
RSA Conference Exhibitor List 2024 - Exhibitors DataRSA Conference Exhibitor List 2024 - Exhibitors Data
RSA Conference Exhibitor List 2024 - Exhibitors Data
 
Call Girls Kengeri Satellite Town Just Call 👗 7737669865 👗 Top Class Call Gir...
Call Girls Kengeri Satellite Town Just Call 👗 7737669865 👗 Top Class Call Gir...Call Girls Kengeri Satellite Town Just Call 👗 7737669865 👗 Top Class Call Gir...
Call Girls Kengeri Satellite Town Just Call 👗 7737669865 👗 Top Class Call Gir...
 
Eluru Call Girls Service ☎ ️93326-06886 ❤️‍🔥 Enjoy 24/7 Escort Service
Eluru Call Girls Service ☎ ️93326-06886 ❤️‍🔥 Enjoy 24/7 Escort ServiceEluru Call Girls Service ☎ ️93326-06886 ❤️‍🔥 Enjoy 24/7 Escort Service
Eluru Call Girls Service ☎ ️93326-06886 ❤️‍🔥 Enjoy 24/7 Escort Service
 
Katrina Personal Brand Project and portfolio 1
Katrina Personal Brand Project and portfolio 1Katrina Personal Brand Project and portfolio 1
Katrina Personal Brand Project and portfolio 1
 
(Anamika) VIP Call Girls Napur Call Now 8617697112 Napur Escorts 24x7
(Anamika) VIP Call Girls Napur Call Now 8617697112 Napur Escorts 24x7(Anamika) VIP Call Girls Napur Call Now 8617697112 Napur Escorts 24x7
(Anamika) VIP Call Girls Napur Call Now 8617697112 Napur Escorts 24x7
 
Nelamangala Call Girls: 🍓 7737669865 🍓 High Profile Model Escorts | Bangalore...
Nelamangala Call Girls: 🍓 7737669865 🍓 High Profile Model Escorts | Bangalore...Nelamangala Call Girls: 🍓 7737669865 🍓 High Profile Model Escorts | Bangalore...
Nelamangala Call Girls: 🍓 7737669865 🍓 High Profile Model Escorts | Bangalore...
 
Call Girls In Noida 959961⊹3876 Independent Escort Service Noida
Call Girls In Noida 959961⊹3876 Independent Escort Service NoidaCall Girls In Noida 959961⊹3876 Independent Escort Service Noida
Call Girls In Noida 959961⊹3876 Independent Escort Service Noida
 
Falcon Invoice Discounting: Empowering Your Business Growth
Falcon Invoice Discounting: Empowering Your Business GrowthFalcon Invoice Discounting: Empowering Your Business Growth
Falcon Invoice Discounting: Empowering Your Business Growth
 
Cracking the Cultural Competence Code.pptx
Cracking the Cultural Competence Code.pptxCracking the Cultural Competence Code.pptx
Cracking the Cultural Competence Code.pptx
 
Dr. Admir Softic_ presentation_Green Club_ENG.pdf
Dr. Admir Softic_ presentation_Green Club_ENG.pdfDr. Admir Softic_ presentation_Green Club_ENG.pdf
Dr. Admir Softic_ presentation_Green Club_ENG.pdf
 
BAGALUR CALL GIRL IN 98274*61493 ❤CALL GIRLS IN ESCORT SERVICE❤CALL GIRL
BAGALUR CALL GIRL IN 98274*61493 ❤CALL GIRLS IN ESCORT SERVICE❤CALL GIRLBAGALUR CALL GIRL IN 98274*61493 ❤CALL GIRLS IN ESCORT SERVICE❤CALL GIRL
BAGALUR CALL GIRL IN 98274*61493 ❤CALL GIRLS IN ESCORT SERVICE❤CALL GIRL
 
Call Girls in Delhi, Escort Service Available 24x7 in Delhi 959961-/-3876
Call Girls in Delhi, Escort Service Available 24x7 in Delhi 959961-/-3876Call Girls in Delhi, Escort Service Available 24x7 in Delhi 959961-/-3876
Call Girls in Delhi, Escort Service Available 24x7 in Delhi 959961-/-3876
 
The Path to Product Excellence: Avoiding Common Pitfalls and Enhancing Commun...
The Path to Product Excellence: Avoiding Common Pitfalls and Enhancing Commun...The Path to Product Excellence: Avoiding Common Pitfalls and Enhancing Commun...
The Path to Product Excellence: Avoiding Common Pitfalls and Enhancing Commun...
 
Call Girls Electronic City Just Call 👗 7737669865 👗 Top Class Call Girl Servi...
Call Girls Electronic City Just Call 👗 7737669865 👗 Top Class Call Girl Servi...Call Girls Electronic City Just Call 👗 7737669865 👗 Top Class Call Girl Servi...
Call Girls Electronic City Just Call 👗 7737669865 👗 Top Class Call Girl Servi...
 
Falcon's Invoice Discounting: Your Path to Prosperity
Falcon's Invoice Discounting: Your Path to ProsperityFalcon's Invoice Discounting: Your Path to Prosperity
Falcon's Invoice Discounting: Your Path to Prosperity
 
Cheap Rate Call Girls In Noida Sector 62 Metro 959961乂3876
Cheap Rate Call Girls In Noida Sector 62 Metro 959961乂3876Cheap Rate Call Girls In Noida Sector 62 Metro 959961乂3876
Cheap Rate Call Girls In Noida Sector 62 Metro 959961乂3876
 
Mysore Call Girls 8617370543 WhatsApp Number 24x7 Best Services
Mysore Call Girls 8617370543 WhatsApp Number 24x7 Best ServicesMysore Call Girls 8617370543 WhatsApp Number 24x7 Best Services
Mysore Call Girls 8617370543 WhatsApp Number 24x7 Best Services
 
How to Get Started in Social Media for Art League City
How to Get Started in Social Media for Art League CityHow to Get Started in Social Media for Art League City
How to Get Started in Social Media for Art League City
 

Time Bars and their enforceability in English law EPC contracts

  • 1. The use of time bar clauses in standard form EPC contracts is common. How effective a tool are such clauses for managing contractors’ claims for extensions of time and additional payment, and what challenges will there be in enforcing a time bar clause? Raising the Bar Time Bars and their enforceability in English law EPC contracts What is a time bar clause? Almost all EPC contracts will contain a contractual mechanism for giving the contractor an extension of time to complete the works, by extending the contractual completion date upon the occurrence of specified events. EPC contracts will usually also provide for such events to trigger the contractor’s right to claim additional payment. Additionally, the contract may specify a date by which the contractor must notify the employer or contract administrator of any claim it has (for time and/or money). A time bar clause provides that if the contractor fails to serve the requisite notice within the specified period it will, in theory, become time barred from claiming any extension of time or additional payment. Time bar provisions of the type described above can be found in most standard form EPC contracts. The FIDIC major works contracts1 include a time bar provision at Clause 20.1, which is set out as follows: “If the Contractor considers himself to be entitled to any extension of the Time for Completion and/or any additional payment, under any Clause of these Conditions or otherwise in connection with the Contract, the Contractor shall give notice to the Employer, describing the event or circumstance giving rise to the claim. The notice shall be given as soon as practicable, and not later than 28 days after the contractor became aware, or should have become aware, of the event or circumstance. If the Contractor fails to give notice of a claim within such period of 28 days, the Time for Completion shall not be extended, the Contractor shall not be entitled to additional payment, and the Employer shall be discharged from all liability in connection with the claim…” 1 The FIDIC 1999 suite of contracts – Conditions of Contract for Construction (Red Book), Conditions of Contract for EPC/Turnkey Projects (Silver Book) and Conditions of Contract for Plant and Design-Build (Yellow Book).
  • 2. For a project executed under FIDIC conditions, there will be a clear requirement for the contractor to provide the employer with notice of its claim no later than 28 days after it becomes aware of the relevant event. The second paragraph of Clause 20.1 makes the contractor’s compliance with the 28-day requirement a condition precedent to any entitlement it may have to additional time or money under the contract. Most bespoke EPC contracts will include similar provisions. Why are time bar clauses used? The principle purpose of using strict time bar clauses, such as that provided for by Clause 20.1, is to improve the administration of the contract. By ensuring a hard deadline for the contractor to notify it of any events which may give rise to a claim, the employer is alerted to the contractor’s claim at an early stage. This allows the employer to evaluate the claim, and also take any steps to work with the contractor to mitigate the delay. It should also help to avoid a build up of contractor’s claims during a project, which historically has often led to a final account dispute between the employer and contractor. This process imposes a more proactive contemporaneous approach to dealing with unexpected events when they arrive, and providing cost and programme certainty and transparency. An effective time bar clause can be used as a tool for achieving a more collaborative approach between the contractor and employer in relation to claims for additional time and money. Will my time bar clause be effective? Condition Precedent The starting point to determine whether a time bar clause will be enforceable by the employer against the contractor is to understand whether compliance with the clause is a condition precedent to the contractor’s claim. When considering this question, the English courts have typically taken the view that the notice requirements in construction contracts are directory, not mandatory, and that a contractor may not lose its entitlement to a claim, unless the contract expressly states that a non-compliant contractor will lose its rights to additional time and/or money. However, within standard form EPC contracts time bar clauses will usually be drafted such that they have the necessary elements of a condition precedent. Clause 20.1 of the FIDIC Silver Book is a good example of a provision intended to be a condition precedent as: (i) the clause specifies the time period within which notice must be served by the contractor; and (ii) the clause expressly states the consequences of the contractor’s failure to serve notice of its claim within the relevant time (i.e. that the contractor will lose its rights against the employer).2 2 See Bremer Handelgesellschaft mbH v Vanden Avenne Izegem PVBA [1978] 2 Lloyd’s Rep. 113 as to the rules on condition precedents. In a recent decision, Obrascon Huarte Lain SA v Attorney General for Gibraltar3 , it was accepted by counsel for the contractor that Clause 20.14 did impose a condition precedent on the contractor. It is very likely that should Clause 20.1 be challenged before a court or arbitral tribunal it will be interpreted as in Obrascon Huarte. Therefore for projects carried out on FIDIC conditions, the parties should treat strict compliance with the provisions of Clause 20.1 as a condition precedent to the contractor’s claim. Clauses with similar features as Clause 20.1 are likely to be interpreted in the same way. In the case of Adyard Abu Dhabi v SD Marine Services5 , which concerned a shipbuilding contract, the English High court found that clauses requiring the shipbuilder to give notice of delays were to be treated as condition precedents, and as the shipbuilder failed to give such notices it lost its entitlement to make a claim in respect of such delay. The Contractor’s Notice The next issue to consider is what information the contractor will be required to give to the employer in its notice of a claim for additional time and/or money. Whilst it is open for parties to specify in the contract exactly what details must be included in the contractor’s notice, not all EPC contracts do so. We have advised on EPC contracts where critical path analysis (amongst other demands) is required within 28 days of an event giving rise to an extension of time arising. Often, EPC contractors will find such demands challenging. In the absence of requirements set out in the contract, the English courts have generally considered that the contractor is only required to give the best information it is reasonably able to do so, and only information which is available to the contractor at that time.6 In Obrascon Huarte, the TCC considered that for Clause 20.1: “… one should construe it as permitting any claim provided that it is made by notice in writing to the Engineer, that the notice describes the event or circumstance relied on and that the notice is intended to notify a claim for extension (or for additional payment or both) under the Contract or in connection with it. It must be recognizable as a “claim”.”7 Obrascon also looked at when time will start running for the purposes of the contractor serving its notice under the time bar clause. The TCC concluded that there must have been awareness of the circumstance, or the means of awareness of the relevant circumstance, before the condition precedent will bite. Furthermore, the time bar clause should not be construed strictly against the contractor in this respect. The burden of proof would instead be on the employer seeking to argue that a notice had not been given in time. 3 [2014] EWHC 1028 (TCC) 4 This case considered a project executed under the FIDIC Yellow Book con- ditions 5 [2011] EWHC 848 (Comm) 6 Multiplex Constructions (UK) Ltd v Honeywell Control Systems (No 2) 7 Obrascon Huarte Lain SA v Attorney General for Gibraltar [2014] EWHC 1028 (TCC) at para. 313
  • 3. ‘Prevention Principle’ Arguments It is often suggested that a contractor may seek to avoid the strict application of a time bar clause by arguing that, irrespective of its own non-compliance with the provision, the prevention principle may still defeat an employer’s claim for liquidated damages where the delay is caused by an occurrence which is the employer’s responsibility under the contract. This line of argument has support from a series of Australian decisions which considered that the prevention principle could result in time bar provisions being defeated.8 However, this approach is not one that would necessarily be followed by an English court or by an arbitral tribunal. In City Inn Ltd v Shepherd Construction Ltd9 , a Scottish case, the court took a robust view of the contractor’s obligation to time bar provisions, and whilst the court did not, on the facts, decide whether the prevention principle would operate, it considered the contractor to have an obligation to comply with the provisions of the time bar clause, unless waived by the employer (or as on the facts, the employer’s architect). In the Adyard Abu Dhabi case, referred to above, the court accepted the argument that the contract contained provisions entitling the shipyard to an extension of time, therefore the prevention principle was displaced. Hamblen J stated that: “However, as Jackson J stated in the Multiplex v Honeywell case, the prevention principle does not apply if the contract provides for an extension of time in respect of the relevant events.”10 8 Gaymark Investments Pty Ltd v Walter Construction Group Ltd (2000) 16 BCL 449 and Peninsula Balmain Pty Ltd v Abigroup Contractors Corp Pty Ltd [2002] NSWCA 211 9 [2003] BLR 468 10 [2011] EWHC 848 (Comm) at paragraph 243 Conclusion The time bar clause will continue to be a feature of most EPC contracts for major projects, and provides a useful tool for the employer in the administration of the contract, ensuring certainty and transparency of time and cost. From the contractor’s perspective, it should not be an overly onerous obligation provided that the contractor is alert to the requirements of the clause. There can also be upsides for EPC contractors in efficiently managing and prospectively agreeing the time/money effect of change as and when it occurs. Time bar clauses should work to the advantage of all parties to the project by ensuring the early notification of circumstances giving rise to potential claims, conducive to a cooperative approach between the parties. A strict approach to time bar clauses is likely to be preferred by courts and arbitral tribunals, as were it to be found that the prevention principle did override time bar provisions, this would create a possibility of abuse by the contractor. It has been identified that if the prevention principle were to be applied in such cases, it would enable the contractor to disregard the time bar provision, and set time at large under the contract, without recourse by the employer.11 Such an outcome is clearly not satisfactory in light of a time bar clause negotiated between commercial parties. 11 Multiplex Constructions (UK) Ltd v Honeywell Control Systems (No 2), para. 103 www.eversheds.com ©EVERSHEDS LLP 2014. Eversheds LLP is a limited liability partnership. DT03641_07/14 Paul Giles Partner, Eversheds LLP + 44 20 7497 9797 paulgiles@eversheds.com Steve Gibson Associate, Eversheds LLP +65 6572 5587 stevengibson@eversheds.com