SlideShare une entreprise Scribd logo
1  sur  33
Télécharger pour lire hors ligne
Metro Emissions Reduction Project
     A.S. King Rehabilitation



            Ron Elsner
          Project Director
            June 20, 2006
Presentation Outline
  MN MERP Overview
  Allen S. King Project Schedule Overview
  Status Update ( including progress photos)
  Key Remaining Activities
  Influences – Internal & External
MN MERP Overview
 Emissions Reduction Rider signed into law: Summer 2001
 Project development: September 2001 – May 2002
 Initial proposal filed with MPUC: May 2002
 MERP Project Proposal filed with MPUC: July 2002
 Regulatory review and public hearings: Sept 2002 –
 November 2003
 Settlement Agreement executed: November 2003
 — King Rehabilitation           $382 M      May 2007
 — High Bridge Combined Cycle $395 M         May 2008
 — Riverside Repower             $212 M      May 2009
 MPUC Approval: December 18, 2003
King Plant Rehabilitation
Install new state-of-the-art pollution control equipment,
rebuild the existing boiler, replace the existing steam turbine,
install new digital plant control system, and upgrade balance
of plant equipment as necessary.

   In-Service Date:    May 2007

   Capital Cost:       Settlement Estimate: $382 million

   Emissions Reductions:       NOx     ~17,000 TPY (89%)

                               SO2     ~24,000 TPY (91%)

                               PM      ~90 TPY (20%)

                               HG      ~ 15 #/yr (20%)
High Bridge Conversion
Install two new natural gas fired combustion turbines operating in
‘combined cycle’ mode to power a new steam turbine. Retire and
demolish the existing facility after the new system is installed.

   In-Service Date:   May 2008

   Capital Cost:      Settlement Estimate: $395 million

   Emissions Reductions:      NOx     ~ 4,400 TPY (98%)

                              SO2    ~ 3,100 TPY (100%)

                              PM     ~ 100 TPY (100%)

                              HG     ~ 66 #/yr (100%)
High Bridge – Future View
Riverside Repowering
Install two new, natural gas fired combustion turbines operating in
‘combined cycle’ mode to power the existing Unit 7 Steam turbine.
Retire and demolish Unit 8 after completion of the new installation.

   In-Service Date:    May 2009

   Capital Cost:       Settlement Estimate: $212 million

   Emissions Reductions:      NOx     ~ 13,000 TPY (99%)

                              SO2     ~ 12,000 TPY (100%)

                              PM      ~ 540 TPY (100%)

                              HG      ~ 98 #/yr (100%)
Riverside – Future View
Combined Emissions Reductions

   NOx            ~ 34,000 TPY                   91%

   SO2            ~ 39,000 TPY                   93%

   PM             ~     730 TPY                  55%

   HG             ~     179 #/YR                 77%

   (Projected annual average for combined emissions
   from three plants over period 2010 – 2020)
King Rehabilitation
Lime Prep Building looking NE
Functional Organization
          Engineering Manager
                                                        Co nstruction Man ag er
                Russ Girtz                                                                         Project Management Consult an t
                                                            Byron Nordell
  Over sight of Design Basis
                                                                                                             Wayn e Osat iuk
                                                Safety
  Support Data Requests from other
                                                                                               Master Project Schedule
                                                Constr uction Planning
  Xcel Ener gy Depts. and/or Business                                                          Master Project Cost
                                                Contractor Over sight
  Units
                                                                                               Project Scope
                                                Site Support Labor
  Inter face with the B&V Project T eam
                                                                                               Project Resour ce Management
                                                Site Services Supervision
  Pr ovide oversight of and dir ection to                                                      Project Procurement
                                                Inspection and T esting
  other technical and engineering
                                                Project Administr ation                        Project Risk Management
  resources on the Project, Including:
                                                                                               Project Collaboration Tool ( Expedition)
                                                Labor Relations with Minnesota Building
      Environmental Consultants                                                                Project Reporting
                                                T rades Council
      King System Engineer s
      ES Pr oduction Resources
      UEC Engineer ing
      Supply Matter Experts
                                                                                                          Commercial Manag er
  Technical Data Review
                                                       Pro ject Director
  Construction Suppor t                                                                                       Brian Westerh au s
 Subject Matter Experts (SMEs)                                                                          Supplier Selection Process
                                                             Ron Elsn er
                                                                                                        Bid Package Creation
                                                     Develop and implement
                                                                                                        Bid Analysis Process
                                                     Pr oject Plan
                                                                                                        Contract Administration
                                                     External Interface
                                                     Technical
          A&E Project Management
                                                     Financial
                 Cat hy Weber
                                                     Planning and Scheduling
  Manage and supervise ES contract.
                                                     Implementation and
  Ensure engineering activities are carr ied                                                               Plant Liaison
                                                     constr uction
  out to support the pr oject schedule,
                                                                                                                Mike Miser
                                                     Star t- up
  budget, and needs of all pr oject
                                                                                           Distr ibution of:
  par ticipants.
                                                                                                 General pr oject infor mation
  Supervise the engineer ing staff at B&V to
                                                                                                 Issue specific and/or task specific information
  ensure that budget and schedule are met.
                                                                                                 to the plant staff
  Pr ovide timely reviews of project
                                                                                           Communicating schedule infor mation to plant
  engineer ing status.
                                                                                           personnel
  Ensure that all Quality Assur ance and
                                                                                           Participating in and representing plant inter ests in
  Quality Control requir ements for
                                                                                           the development and review of the project
  engineer ing are met.
                                                          Start-Up Manager                 schedule
  Establish and maintain procedur es and
                                                                                           Responsible for determining which groups and/or
  process.                                                    Rich Goshorn
                                                                                           individual member s of the plant staff should
                                                    Develop Star t up & Commissioning
  Meet with Xcel Energy Core Management
                                                                                           pr ovide subject matter expertise on given topics
  Team to update the project status, note           plan and schedule
                                                                                           Accountable for assuring that necessary and
  and r esolve ar eas of concern, and provide       Oversee development of Start-Up
                                                                                           appropriate groups and/or individuals at the plant
                                                    Pr oceedur es
  support as requested.
                                                                                           ar e involved in (or, are given the oppor tunity to
  Pr oject Reporting                                Oversee Star t-Up & Commissioning of
                                                                                           pr ovide input to) the project.
  Ensure that the ES pr ovided support for          all new equipment
                                                                                           Accountable for meeting deadlines for review,
  the r equirements in the King Plant
                                                                                           consolidation, and return of data/infor mation/
  Rehabilitation Project Settlement
                                                                                           comments from the plant to the project.
  Agr eement.
Project Approach/ Plan
Collection of distinct sub-projects

Familiarity and experience with sub-projects

Traditional Owner-Managed approach
—   Owner’s Engineer: B&V
—   Equipment Procurement and Installation: Self Contract
—   Construction Management: Utility Engineering
—   Commissioning & Start-up: Self Perform
Allen S. King Project Schedule Overview

Start of engineering: October 31, 2003
Contracted for major equipment: July, 2004
Groundbreaking: April 22, 2005
Foundations and substructures complete: December 28, 2005
Start of new equipment commissioning: March 2006
Unit comes out-of-service: September 5, 2006
Boiler rebuild & steam turbine replacement: Sept 2006 – Jan 2007
‘First Fire’ on coal:   March 2007
Return to service:      May 2007 – Project remains on schedule
Activities Completed to Date
  All environmental permitting complete – State
  and Federal
  Detailed design and integration: 95% complete
  Major procurement: 100% Complete
  — Competitive bidding process
  — Firm price contracts
  Overall construction : ~45% complete
  Commissioning & startup:
  — Planning: Complete
  — Implementation: In progress
  Operating procedures development: In progress
  Operator training: In progress
Procurement of Major Components
AQCS:
 – Alstom ECS; Knoxville
 – Delivery ~95%; Construction ~60%
SCR:
 – Mitsubishi Power Systems; Newport Beach
 – Delivery ~95%; Construction ~50%
Boiler:
 – B&W; Barberton
 – Design ~100%; Manufacturing: 90+%
Steam Turbine:
 – Alstom Power; Richmond, Rugby, Elblag
 – Design ~100%; Manufacturing 90+%
Major Construction Contracts
Substructures: Lunda Construction; Little Chute, WI
SCR Mechanical: Graycor; Homewood, IL
AQCS Mechanical: Graycor
AQCS Electrical: Frauenshuh PD; Minneapolis
DCS/BOP Electrical: Capital; Kansas City
Steam Turbine Area Mechanical: O.J.Boldt; Appleton, WI
Boiler Area Mechanical: B&WCC (pending)
General Construction
     Progress
1st Pier
Being
Drilled
Circulating Water Pipe
SCR
Structural
AQCS Structural
SDA Vessels
Fabric Filter Structural
Lime Prep Building
ID Fans
AQCS Switchgear
New Cooling Tower
Steam Turbine
Boiler
Cyclone
Distributed Control System
   (on factory test floor)
Key Remaining Activities
 Cooling Towers In-Service: June 1, 2006
 AQCS/SCR Mechanically Complete: September 1, 2006
 Unit Out-of-Service: September 5, 2006
 Demolition Substantially Complete: October 15, 2006
 Boiler Pressure Parts Complete: January 31, 2007
 First Fire on Gas: February 2007
 First Fire on Coal: March 2007
 First synch to the grid: April 2007
 Unit Return-to-Service: May 2007
Influences – Internal & External
 Construction labor availability and productivity
 in Fall 2006
  – Extended periods of multi-shift overtime activities
  – May be competing with ourselves for resources (Sherco)
 Tight marketplace and commodity price increases
 Operator training & initial plant operation
  – Rehabilitated plant will have some fundamental
    differences from existing configuration.

Contenu connexe

Tendances

Mulenburg jerry
Mulenburg jerryMulenburg jerry
Mulenburg jerryNASAPMC
 
Tynan Group Qualifications
Tynan Group QualificationsTynan Group Qualifications
Tynan Group Qualificationsmegnbarnes
 
Cloudpreneurs - McKinsey Reveals Fast Growth of Cloud Adoption
Cloudpreneurs - McKinsey Reveals Fast Growth of Cloud AdoptionCloudpreneurs - McKinsey Reveals Fast Growth of Cloud Adoption
Cloudpreneurs - McKinsey Reveals Fast Growth of Cloud AdoptionNewvewm
 
Onshore Windfarm Part 2
Onshore Windfarm Part 2Onshore Windfarm Part 2
Onshore Windfarm Part 2Grant Elder
 
Les.sorge
Les.sorgeLes.sorge
Les.sorgeNASAPMC
 
D brown gbezos_shirshorn
D brown gbezos_shirshornD brown gbezos_shirshorn
D brown gbezos_shirshornNASAPMC
 
Ed.mango
Ed.mangoEd.mango
Ed.mangoNASAPMC
 
Alfred mecum
Alfred mecumAlfred mecum
Alfred mecumNASAPMC
 
David.oberhettinger
David.oberhettingerDavid.oberhettinger
David.oberhettingerNASAPMC
 
Carsile.azarbain
Carsile.azarbainCarsile.azarbain
Carsile.azarbainNASAPMC
 
Bladwin.kristen
Bladwin.kristenBladwin.kristen
Bladwin.kristenNASAPMC
 
Carol.scott
Carol.scottCarol.scott
Carol.scottNASAPMC
 
Kathleen English Gulf Coast Green 2010
Kathleen English Gulf Coast Green 2010Kathleen English Gulf Coast Green 2010
Kathleen English Gulf Coast Green 2010Hayley Pallister
 
Bilardo2 15-2012
Bilardo2 15-2012Bilardo2 15-2012
Bilardo2 15-2012NASAPMC
 

Tendances (17)

Mulenburg jerry
Mulenburg jerryMulenburg jerry
Mulenburg jerry
 
Tynan Group Qualifications
Tynan Group QualificationsTynan Group Qualifications
Tynan Group Qualifications
 
Cloudpreneurs - McKinsey Reveals Fast Growth of Cloud Adoption
Cloudpreneurs - McKinsey Reveals Fast Growth of Cloud AdoptionCloudpreneurs - McKinsey Reveals Fast Growth of Cloud Adoption
Cloudpreneurs - McKinsey Reveals Fast Growth of Cloud Adoption
 
Onshore Windfarm Part 2
Onshore Windfarm Part 2Onshore Windfarm Part 2
Onshore Windfarm Part 2
 
Les.sorge
Les.sorgeLes.sorge
Les.sorge
 
D brown gbezos_shirshorn
D brown gbezos_shirshornD brown gbezos_shirshorn
D brown gbezos_shirshorn
 
Ohl project risk register
Ohl project risk registerOhl project risk register
Ohl project risk register
 
Ed.mango
Ed.mangoEd.mango
Ed.mango
 
Alfred mecum
Alfred mecumAlfred mecum
Alfred mecum
 
David.oberhettinger
David.oberhettingerDavid.oberhettinger
David.oberhettinger
 
Carsile.azarbain
Carsile.azarbainCarsile.azarbain
Carsile.azarbain
 
Bladwin.kristen
Bladwin.kristenBladwin.kristen
Bladwin.kristen
 
Ohl project risk register
Ohl project risk registerOhl project risk register
Ohl project risk register
 
Krishen
KrishenKrishen
Krishen
 
Carol.scott
Carol.scottCarol.scott
Carol.scott
 
Kathleen English Gulf Coast Green 2010
Kathleen English Gulf Coast Green 2010Kathleen English Gulf Coast Green 2010
Kathleen English Gulf Coast Green 2010
 
Bilardo2 15-2012
Bilardo2 15-2012Bilardo2 15-2012
Bilardo2 15-2012
 

En vedette

xcel energy
xcel energy   xcel energy
xcel energy finance26
 
xcel energy NSP-MN_Q206_10Qb
xcel energy NSP-MN_Q206_10Qbxcel energy NSP-MN_Q206_10Qb
xcel energy NSP-MN_Q206_10Qbfinance26
 
xel_061405_print
xel_061405_printxel_061405_print
xel_061405_printfinance26
 
xcel energy 7_17XCEL10QQ32006
xcel energy 7_17XCEL10QQ32006xcel energy 7_17XCEL10QQ32006
xcel energy 7_17XCEL10QQ32006finance26
 

En vedette (6)

xcel energy
xcel energy   xcel energy
xcel energy
 
xcel energy NSP-MN_Q206_10Qb
xcel energy NSP-MN_Q206_10Qbxcel energy NSP-MN_Q206_10Qb
xcel energy NSP-MN_Q206_10Qb
 
XEL_051106
XEL_051106XEL_051106
XEL_051106
 
xel_061405_print
xel_061405_printxel_061405_print
xel_061405_print
 
XEL_031406
XEL_031406XEL_031406
XEL_031406
 
xcel energy 7_17XCEL10QQ32006
xcel energy 7_17XCEL10QQ32006xcel energy 7_17XCEL10QQ32006
xcel energy 7_17XCEL10QQ32006
 

Similaire à xel_062006_kingplant

Are you geared for Outsourcing Governance?
Are you geared for Outsourcing Governance?Are you geared for Outsourcing Governance?
Are you geared for Outsourcing Governance?Digite Inc
 
Advanced Projects(tm) Brochure Oct09
Advanced Projects(tm)   Brochure   Oct09Advanced Projects(tm)   Brochure   Oct09
Advanced Projects(tm) Brochure Oct09dbevort
 
Contract construction-management142
Contract construction-management142Contract construction-management142
Contract construction-management142rkress61
 
Exploration Production Portals
Exploration Production Portals Exploration Production Portals
Exploration Production Portals Infosys
 
Tendering in Construction
Tendering in ConstructionTendering in Construction
Tendering in Constructionshillier38
 
Keo Projects
Keo ProjectsKeo Projects
Keo Projectsron75
 
Putting technology to_work_reviving_new_yorks_200_year_old_city_hall
Putting technology to_work_reviving_new_yorks_200_year_old_city_hallPutting technology to_work_reviving_new_yorks_200_year_old_city_hall
Putting technology to_work_reviving_new_yorks_200_year_old_city_hallQuestexConf
 
Program Management
Program ManagementProgram Management
Program Managementbtharp
 
Plans andspecificationsmep design
Plans andspecificationsmep designPlans andspecificationsmep design
Plans andspecificationsmep designjmd2011
 
Engineering
EngineeringEngineering
EngineeringHaDeGo
 
Offshore Engineering Brochure August2012
Offshore Engineering Brochure August2012Offshore Engineering Brochure August2012
Offshore Engineering Brochure August2012ggurudev
 
Au 09 Bi Mmeans Business.1.05.10
Au 09 Bi Mmeans Business.1.05.10Au 09 Bi Mmeans Business.1.05.10
Au 09 Bi Mmeans Business.1.05.10friscozephyr
 
T&T Draft Brochure Rev Dark
T&T Draft Brochure Rev DarkT&T Draft Brochure Rev Dark
T&T Draft Brochure Rev Darkbmehmet
 

Similaire à xel_062006_kingplant (20)

Grieman
GriemanGrieman
Grieman
 
Grieman
GriemanGrieman
Grieman
 
Are you geared for Outsourcing Governance?
Are you geared for Outsourcing Governance?Are you geared for Outsourcing Governance?
Are you geared for Outsourcing Governance?
 
Advanced Projects(tm) Brochure Oct09
Advanced Projects(tm)   Brochure   Oct09Advanced Projects(tm)   Brochure   Oct09
Advanced Projects(tm) Brochure Oct09
 
Contract construction-management142
Contract construction-management142Contract construction-management142
Contract construction-management142
 
Exploration Production Portals
Exploration Production Portals Exploration Production Portals
Exploration Production Portals
 
Tendering in Construction
Tendering in ConstructionTendering in Construction
Tendering in Construction
 
Keo Projects
Keo ProjectsKeo Projects
Keo Projects
 
Putting technology to_work_reviving_new_yorks_200_year_old_city_hall
Putting technology to_work_reviving_new_yorks_200_year_old_city_hallPutting technology to_work_reviving_new_yorks_200_year_old_city_hall
Putting technology to_work_reviving_new_yorks_200_year_old_city_hall
 
Program Management
Program ManagementProgram Management
Program Management
 
Integrated Solutions
Integrated SolutionsIntegrated Solutions
Integrated Solutions
 
Ska3
Ska3Ska3
Ska3
 
Itto
IttoItto
Itto
 
4epcm
4epcm4epcm
4epcm
 
Plans andspecificationsmep design
Plans andspecificationsmep designPlans andspecificationsmep design
Plans andspecificationsmep design
 
Engineering
EngineeringEngineering
Engineering
 
Offshore Engineering Brochure August2012
Offshore Engineering Brochure August2012Offshore Engineering Brochure August2012
Offshore Engineering Brochure August2012
 
Shivamtech brochure
Shivamtech brochureShivamtech brochure
Shivamtech brochure
 
Au 09 Bi Mmeans Business.1.05.10
Au 09 Bi Mmeans Business.1.05.10Au 09 Bi Mmeans Business.1.05.10
Au 09 Bi Mmeans Business.1.05.10
 
T&T Draft Brochure Rev Dark
T&T Draft Brochure Rev DarkT&T Draft Brochure Rev Dark
T&T Draft Brochure Rev Dark
 

Plus de finance26

xcel energy merrill_09/16//03
xcel energy  merrill_09/16//03xcel energy  merrill_09/16//03
xcel energy merrill_09/16//03finance26
 
xcel energy merrill_09/16/03
xcel energy  merrill_09/16/03xcel energy  merrill_09/16/03
xcel energy merrill_09/16/03finance26
 
xcel energy merrill_09/16/03
xcel energy  merrill_09/16/03xcel energy  merrill_09/16/03
xcel energy merrill_09/16/03finance26
 
xcel energy BofA_09/16/03
xcel energy  BofA_09/16/03xcel energy  BofA_09/16/03
xcel energy BofA_09/16/03finance26
 
xcel energy BofA_09/16/03
xcel energy  BofA_09/16/03xcel energy  BofA_09/16/03
xcel energy BofA_09/16/03finance26
 
xcel energy BofA_09/16/03
xcel energy  BofA_09/16/03xcel energy  BofA_09/16/03
xcel energy BofA_09/16/03finance26
 

Plus de finance26 (20)

xcel energy merrill_09/16//03
xcel energy  merrill_09/16//03xcel energy  merrill_09/16//03
xcel energy merrill_09/16//03
 
xcel energy merrill_09/16/03
xcel energy  merrill_09/16/03xcel energy  merrill_09/16/03
xcel energy merrill_09/16/03
 
xcel energy merrill_09/16/03
xcel energy  merrill_09/16/03xcel energy  merrill_09/16/03
xcel energy merrill_09/16/03
 
xcel energy BofA_09/16/03
xcel energy  BofA_09/16/03xcel energy  BofA_09/16/03
xcel energy BofA_09/16/03
 
xcel energy BofA_09/16/03
xcel energy  BofA_09/16/03xcel energy  BofA_09/16/03
xcel energy BofA_09/16/03
 
xcel energy BofA_09/16/03
xcel energy  BofA_09/16/03xcel energy  BofA_09/16/03
xcel energy BofA_09/16/03
 
xel_102303b
xel_102303bxel_102303b
xel_102303b
 
xel_102303b
xel_102303bxel_102303b
xel_102303b
 
xel_102303b
xel_102303bxel_102303b
xel_102303b
 
xel_111403
xel_111403xel_111403
xel_111403
 
xel_111403
xel_111403xel_111403
xel_111403
 
xel_111403
xel_111403xel_111403
xel_111403
 
xel_021104
xel_021104xel_021104
xel_021104
 
xel_021104
xel_021104xel_021104
xel_021104
 
xel_021104
xel_021104xel_021104
xel_021104
 
xel_072804
xel_072804xel_072804
xel_072804
 
xel_090804
xel_090804xel_090804
xel_090804
 
xel_092404
xel_092404xel_092404
xel_092404
 
xel_092404
xel_092404xel_092404
xel_092404
 
xel_092404
xel_092404xel_092404
xel_092404
 

Dernier

原版1:1复刻堪萨斯大学毕业证KU毕业证留信学历认证
原版1:1复刻堪萨斯大学毕业证KU毕业证留信学历认证原版1:1复刻堪萨斯大学毕业证KU毕业证留信学历认证
原版1:1复刻堪萨斯大学毕业证KU毕业证留信学历认证jdkhjh
 
The AES Investment Code - the go-to counsel for the most well-informed, wise...
The AES Investment Code -  the go-to counsel for the most well-informed, wise...The AES Investment Code -  the go-to counsel for the most well-informed, wise...
The AES Investment Code - the go-to counsel for the most well-informed, wise...AES International
 
原版1:1复刻温哥华岛大学毕业证Vancouver毕业证留信学历认证
原版1:1复刻温哥华岛大学毕业证Vancouver毕业证留信学历认证原版1:1复刻温哥华岛大学毕业证Vancouver毕业证留信学历认证
原版1:1复刻温哥华岛大学毕业证Vancouver毕业证留信学历认证rjrjkk
 
NO1 Certified Black Magic Specialist Expert In Bahawalpur, Sargodha, Sialkot,...
NO1 Certified Black Magic Specialist Expert In Bahawalpur, Sargodha, Sialkot,...NO1 Certified Black Magic Specialist Expert In Bahawalpur, Sargodha, Sialkot,...
NO1 Certified Black Magic Specialist Expert In Bahawalpur, Sargodha, Sialkot,...Amil baba
 
Managing Finances in a Small Business (yes).pdf
Managing Finances  in a Small Business (yes).pdfManaging Finances  in a Small Business (yes).pdf
Managing Finances in a Small Business (yes).pdfmar yame
 
PMFBY , Pradhan Mantri Fasal bima yojna
PMFBY , Pradhan Mantri  Fasal bima yojnaPMFBY , Pradhan Mantri  Fasal bima yojna
PMFBY , Pradhan Mantri Fasal bima yojnaDharmendra Kumar
 
The Inspirational Story of Julio Herrera Velutini - Global Finance Leader
The Inspirational Story of Julio Herrera Velutini - Global Finance LeaderThe Inspirational Story of Julio Herrera Velutini - Global Finance Leader
The Inspirational Story of Julio Herrera Velutini - Global Finance LeaderArianna Varetto
 
(中央兰开夏大学毕业证学位证成绩单-案例)
(中央兰开夏大学毕业证学位证成绩单-案例)(中央兰开夏大学毕业证学位证成绩单-案例)
(中央兰开夏大学毕业证学位证成绩单-案例)twfkn8xj
 
Uae-NO1 Black Magic Specialist In Lahore Black magic In Pakistan Kala Ilam Ex...
Uae-NO1 Black Magic Specialist In Lahore Black magic In Pakistan Kala Ilam Ex...Uae-NO1 Black Magic Specialist In Lahore Black magic In Pakistan Kala Ilam Ex...
Uae-NO1 Black Magic Specialist In Lahore Black magic In Pakistan Kala Ilam Ex...Amil baba
 
Economics, Commerce and Trade Management: An International Journal (ECTIJ)
Economics, Commerce and Trade Management: An International Journal (ECTIJ)Economics, Commerce and Trade Management: An International Journal (ECTIJ)
Economics, Commerce and Trade Management: An International Journal (ECTIJ)ECTIJ
 
Financial analysis on Risk and Return.ppt
Financial analysis on Risk and Return.pptFinancial analysis on Risk and Return.ppt
Financial analysis on Risk and Return.ppttadegebreyesus
 
House of Commons ; CDC schemes overview document
House of Commons ; CDC schemes overview documentHouse of Commons ; CDC schemes overview document
House of Commons ; CDC schemes overview documentHenry Tapper
 
Role of Information and technology in banking and finance .pptx
Role of Information and technology in banking and finance .pptxRole of Information and technology in banking and finance .pptx
Role of Information and technology in banking and finance .pptxNarayaniTripathi2
 
NO1 WorldWide Love marriage specialist baba ji Amil Baba Kala ilam powerful v...
NO1 WorldWide Love marriage specialist baba ji Amil Baba Kala ilam powerful v...NO1 WorldWide Love marriage specialist baba ji Amil Baba Kala ilam powerful v...
NO1 WorldWide Love marriage specialist baba ji Amil Baba Kala ilam powerful v...Amil baba
 
NO1 Certified kala jadu karne wale ka contact number kala jadu karne wale bab...
NO1 Certified kala jadu karne wale ka contact number kala jadu karne wale bab...NO1 Certified kala jadu karne wale ka contact number kala jadu karne wale bab...
NO1 Certified kala jadu karne wale ka contact number kala jadu karne wale bab...Amil baba
 
Overview of Inkel Unlisted Shares Price.
Overview of Inkel Unlisted Shares Price.Overview of Inkel Unlisted Shares Price.
Overview of Inkel Unlisted Shares Price.Precize Formely Leadoff
 
BPPG response - Options for Defined Benefit schemes - 19Apr24.pdf
BPPG response - Options for Defined Benefit schemes - 19Apr24.pdfBPPG response - Options for Defined Benefit schemes - 19Apr24.pdf
BPPG response - Options for Defined Benefit schemes - 19Apr24.pdfHenry Tapper
 
Call Girls Near Delhi Pride Hotel, New Delhi|9873777170
Call Girls Near Delhi Pride Hotel, New Delhi|9873777170Call Girls Near Delhi Pride Hotel, New Delhi|9873777170
Call Girls Near Delhi Pride Hotel, New Delhi|9873777170Sonam Pathan
 
Economic Risk Factor Update: April 2024 [SlideShare]
Economic Risk Factor Update: April 2024 [SlideShare]Economic Risk Factor Update: April 2024 [SlideShare]
Economic Risk Factor Update: April 2024 [SlideShare]Commonwealth
 
cost of capital questions financial management
cost of capital questions financial managementcost of capital questions financial management
cost of capital questions financial managementtanmayarora23
 

Dernier (20)

原版1:1复刻堪萨斯大学毕业证KU毕业证留信学历认证
原版1:1复刻堪萨斯大学毕业证KU毕业证留信学历认证原版1:1复刻堪萨斯大学毕业证KU毕业证留信学历认证
原版1:1复刻堪萨斯大学毕业证KU毕业证留信学历认证
 
The AES Investment Code - the go-to counsel for the most well-informed, wise...
The AES Investment Code -  the go-to counsel for the most well-informed, wise...The AES Investment Code -  the go-to counsel for the most well-informed, wise...
The AES Investment Code - the go-to counsel for the most well-informed, wise...
 
原版1:1复刻温哥华岛大学毕业证Vancouver毕业证留信学历认证
原版1:1复刻温哥华岛大学毕业证Vancouver毕业证留信学历认证原版1:1复刻温哥华岛大学毕业证Vancouver毕业证留信学历认证
原版1:1复刻温哥华岛大学毕业证Vancouver毕业证留信学历认证
 
NO1 Certified Black Magic Specialist Expert In Bahawalpur, Sargodha, Sialkot,...
NO1 Certified Black Magic Specialist Expert In Bahawalpur, Sargodha, Sialkot,...NO1 Certified Black Magic Specialist Expert In Bahawalpur, Sargodha, Sialkot,...
NO1 Certified Black Magic Specialist Expert In Bahawalpur, Sargodha, Sialkot,...
 
Managing Finances in a Small Business (yes).pdf
Managing Finances  in a Small Business (yes).pdfManaging Finances  in a Small Business (yes).pdf
Managing Finances in a Small Business (yes).pdf
 
PMFBY , Pradhan Mantri Fasal bima yojna
PMFBY , Pradhan Mantri  Fasal bima yojnaPMFBY , Pradhan Mantri  Fasal bima yojna
PMFBY , Pradhan Mantri Fasal bima yojna
 
The Inspirational Story of Julio Herrera Velutini - Global Finance Leader
The Inspirational Story of Julio Herrera Velutini - Global Finance LeaderThe Inspirational Story of Julio Herrera Velutini - Global Finance Leader
The Inspirational Story of Julio Herrera Velutini - Global Finance Leader
 
(中央兰开夏大学毕业证学位证成绩单-案例)
(中央兰开夏大学毕业证学位证成绩单-案例)(中央兰开夏大学毕业证学位证成绩单-案例)
(中央兰开夏大学毕业证学位证成绩单-案例)
 
Uae-NO1 Black Magic Specialist In Lahore Black magic In Pakistan Kala Ilam Ex...
Uae-NO1 Black Magic Specialist In Lahore Black magic In Pakistan Kala Ilam Ex...Uae-NO1 Black Magic Specialist In Lahore Black magic In Pakistan Kala Ilam Ex...
Uae-NO1 Black Magic Specialist In Lahore Black magic In Pakistan Kala Ilam Ex...
 
Economics, Commerce and Trade Management: An International Journal (ECTIJ)
Economics, Commerce and Trade Management: An International Journal (ECTIJ)Economics, Commerce and Trade Management: An International Journal (ECTIJ)
Economics, Commerce and Trade Management: An International Journal (ECTIJ)
 
Financial analysis on Risk and Return.ppt
Financial analysis on Risk and Return.pptFinancial analysis on Risk and Return.ppt
Financial analysis on Risk and Return.ppt
 
House of Commons ; CDC schemes overview document
House of Commons ; CDC schemes overview documentHouse of Commons ; CDC schemes overview document
House of Commons ; CDC schemes overview document
 
Role of Information and technology in banking and finance .pptx
Role of Information and technology in banking and finance .pptxRole of Information and technology in banking and finance .pptx
Role of Information and technology in banking and finance .pptx
 
NO1 WorldWide Love marriage specialist baba ji Amil Baba Kala ilam powerful v...
NO1 WorldWide Love marriage specialist baba ji Amil Baba Kala ilam powerful v...NO1 WorldWide Love marriage specialist baba ji Amil Baba Kala ilam powerful v...
NO1 WorldWide Love marriage specialist baba ji Amil Baba Kala ilam powerful v...
 
NO1 Certified kala jadu karne wale ka contact number kala jadu karne wale bab...
NO1 Certified kala jadu karne wale ka contact number kala jadu karne wale bab...NO1 Certified kala jadu karne wale ka contact number kala jadu karne wale bab...
NO1 Certified kala jadu karne wale ka contact number kala jadu karne wale bab...
 
Overview of Inkel Unlisted Shares Price.
Overview of Inkel Unlisted Shares Price.Overview of Inkel Unlisted Shares Price.
Overview of Inkel Unlisted Shares Price.
 
BPPG response - Options for Defined Benefit schemes - 19Apr24.pdf
BPPG response - Options for Defined Benefit schemes - 19Apr24.pdfBPPG response - Options for Defined Benefit schemes - 19Apr24.pdf
BPPG response - Options for Defined Benefit schemes - 19Apr24.pdf
 
Call Girls Near Delhi Pride Hotel, New Delhi|9873777170
Call Girls Near Delhi Pride Hotel, New Delhi|9873777170Call Girls Near Delhi Pride Hotel, New Delhi|9873777170
Call Girls Near Delhi Pride Hotel, New Delhi|9873777170
 
Economic Risk Factor Update: April 2024 [SlideShare]
Economic Risk Factor Update: April 2024 [SlideShare]Economic Risk Factor Update: April 2024 [SlideShare]
Economic Risk Factor Update: April 2024 [SlideShare]
 
cost of capital questions financial management
cost of capital questions financial managementcost of capital questions financial management
cost of capital questions financial management
 

xel_062006_kingplant

  • 1. Metro Emissions Reduction Project A.S. King Rehabilitation Ron Elsner Project Director June 20, 2006
  • 2. Presentation Outline MN MERP Overview Allen S. King Project Schedule Overview Status Update ( including progress photos) Key Remaining Activities Influences – Internal & External
  • 3. MN MERP Overview Emissions Reduction Rider signed into law: Summer 2001 Project development: September 2001 – May 2002 Initial proposal filed with MPUC: May 2002 MERP Project Proposal filed with MPUC: July 2002 Regulatory review and public hearings: Sept 2002 – November 2003 Settlement Agreement executed: November 2003 — King Rehabilitation $382 M May 2007 — High Bridge Combined Cycle $395 M May 2008 — Riverside Repower $212 M May 2009 MPUC Approval: December 18, 2003
  • 4. King Plant Rehabilitation Install new state-of-the-art pollution control equipment, rebuild the existing boiler, replace the existing steam turbine, install new digital plant control system, and upgrade balance of plant equipment as necessary. In-Service Date: May 2007 Capital Cost: Settlement Estimate: $382 million Emissions Reductions: NOx ~17,000 TPY (89%) SO2 ~24,000 TPY (91%) PM ~90 TPY (20%) HG ~ 15 #/yr (20%)
  • 5. High Bridge Conversion Install two new natural gas fired combustion turbines operating in ‘combined cycle’ mode to power a new steam turbine. Retire and demolish the existing facility after the new system is installed. In-Service Date: May 2008 Capital Cost: Settlement Estimate: $395 million Emissions Reductions: NOx ~ 4,400 TPY (98%) SO2 ~ 3,100 TPY (100%) PM ~ 100 TPY (100%) HG ~ 66 #/yr (100%)
  • 6. High Bridge – Future View
  • 7. Riverside Repowering Install two new, natural gas fired combustion turbines operating in ‘combined cycle’ mode to power the existing Unit 7 Steam turbine. Retire and demolish Unit 8 after completion of the new installation. In-Service Date: May 2009 Capital Cost: Settlement Estimate: $212 million Emissions Reductions: NOx ~ 13,000 TPY (99%) SO2 ~ 12,000 TPY (100%) PM ~ 540 TPY (100%) HG ~ 98 #/yr (100%)
  • 9. Combined Emissions Reductions NOx ~ 34,000 TPY 91% SO2 ~ 39,000 TPY 93% PM ~ 730 TPY 55% HG ~ 179 #/YR 77% (Projected annual average for combined emissions from three plants over period 2010 – 2020)
  • 11. Lime Prep Building looking NE
  • 12. Functional Organization Engineering Manager Co nstruction Man ag er Russ Girtz Project Management Consult an t Byron Nordell Over sight of Design Basis Wayn e Osat iuk Safety Support Data Requests from other Master Project Schedule Constr uction Planning Xcel Ener gy Depts. and/or Business Master Project Cost Contractor Over sight Units Project Scope Site Support Labor Inter face with the B&V Project T eam Project Resour ce Management Site Services Supervision Pr ovide oversight of and dir ection to Project Procurement Inspection and T esting other technical and engineering Project Administr ation Project Risk Management resources on the Project, Including: Project Collaboration Tool ( Expedition) Labor Relations with Minnesota Building Environmental Consultants Project Reporting T rades Council King System Engineer s ES Pr oduction Resources UEC Engineer ing Supply Matter Experts Commercial Manag er Technical Data Review Pro ject Director Construction Suppor t Brian Westerh au s Subject Matter Experts (SMEs) Supplier Selection Process Ron Elsn er Bid Package Creation Develop and implement Bid Analysis Process Pr oject Plan Contract Administration External Interface Technical A&E Project Management Financial Cat hy Weber Planning and Scheduling Manage and supervise ES contract. Implementation and Ensure engineering activities are carr ied Plant Liaison constr uction out to support the pr oject schedule, Mike Miser Star t- up budget, and needs of all pr oject Distr ibution of: par ticipants. General pr oject infor mation Supervise the engineer ing staff at B&V to Issue specific and/or task specific information ensure that budget and schedule are met. to the plant staff Pr ovide timely reviews of project Communicating schedule infor mation to plant engineer ing status. personnel Ensure that all Quality Assur ance and Participating in and representing plant inter ests in Quality Control requir ements for the development and review of the project engineer ing are met. Start-Up Manager schedule Establish and maintain procedur es and Responsible for determining which groups and/or process. Rich Goshorn individual member s of the plant staff should Develop Star t up & Commissioning Meet with Xcel Energy Core Management pr ovide subject matter expertise on given topics Team to update the project status, note plan and schedule Accountable for assuring that necessary and and r esolve ar eas of concern, and provide Oversee development of Start-Up appropriate groups and/or individuals at the plant Pr oceedur es support as requested. ar e involved in (or, are given the oppor tunity to Pr oject Reporting Oversee Star t-Up & Commissioning of pr ovide input to) the project. Ensure that the ES pr ovided support for all new equipment Accountable for meeting deadlines for review, the r equirements in the King Plant consolidation, and return of data/infor mation/ Rehabilitation Project Settlement comments from the plant to the project. Agr eement.
  • 13. Project Approach/ Plan Collection of distinct sub-projects Familiarity and experience with sub-projects Traditional Owner-Managed approach — Owner’s Engineer: B&V — Equipment Procurement and Installation: Self Contract — Construction Management: Utility Engineering — Commissioning & Start-up: Self Perform
  • 14. Allen S. King Project Schedule Overview Start of engineering: October 31, 2003 Contracted for major equipment: July, 2004 Groundbreaking: April 22, 2005 Foundations and substructures complete: December 28, 2005 Start of new equipment commissioning: March 2006 Unit comes out-of-service: September 5, 2006 Boiler rebuild & steam turbine replacement: Sept 2006 – Jan 2007 ‘First Fire’ on coal: March 2007 Return to service: May 2007 – Project remains on schedule
  • 15. Activities Completed to Date All environmental permitting complete – State and Federal Detailed design and integration: 95% complete Major procurement: 100% Complete — Competitive bidding process — Firm price contracts Overall construction : ~45% complete Commissioning & startup: — Planning: Complete — Implementation: In progress Operating procedures development: In progress Operator training: In progress
  • 16. Procurement of Major Components AQCS: – Alstom ECS; Knoxville – Delivery ~95%; Construction ~60% SCR: – Mitsubishi Power Systems; Newport Beach – Delivery ~95%; Construction ~50% Boiler: – B&W; Barberton – Design ~100%; Manufacturing: 90+% Steam Turbine: – Alstom Power; Richmond, Rugby, Elblag – Design ~100%; Manufacturing 90+%
  • 17. Major Construction Contracts Substructures: Lunda Construction; Little Chute, WI SCR Mechanical: Graycor; Homewood, IL AQCS Mechanical: Graycor AQCS Electrical: Frauenshuh PD; Minneapolis DCS/BOP Electrical: Capital; Kansas City Steam Turbine Area Mechanical: O.J.Boldt; Appleton, WI Boiler Area Mechanical: B&WCC (pending)
  • 31. Distributed Control System (on factory test floor)
  • 32. Key Remaining Activities Cooling Towers In-Service: June 1, 2006 AQCS/SCR Mechanically Complete: September 1, 2006 Unit Out-of-Service: September 5, 2006 Demolition Substantially Complete: October 15, 2006 Boiler Pressure Parts Complete: January 31, 2007 First Fire on Gas: February 2007 First Fire on Coal: March 2007 First synch to the grid: April 2007 Unit Return-to-Service: May 2007
  • 33. Influences – Internal & External Construction labor availability and productivity in Fall 2006 – Extended periods of multi-shift overtime activities – May be competing with ourselves for resources (Sherco) Tight marketplace and commodity price increases Operator training & initial plant operation – Rehabilitated plant will have some fundamental differences from existing configuration.