SlideShare a Scribd company logo
1 of 23
Download to read offline
An Introduction to the Complex
Projects Contract 2013
23 April 2013
Introduction
Adam Constable Q.C., Keating Chambers
CIOB Research, background to CPC2013 and
availability
Keith Pickavance, Executive Consultant, Hill International, Past President
CIOB
Project suitability and procurement
strategy
Francis Ho
Senior Associate, Olswang LLP
Where should CPC2013 be used?
Suitable for: Less suitable for:
Works of high value or complexity ✓ Simpler works or those of short duration ✗
Major real estate projects ✓ Construction management/EPCM without amendment ✗
Engineering and infrastructure projects ✓ Inexperienced clients/contractors ✗
www.olswang.com5
International Usage
Contract England and Wales International
CPC2013 ✓ ✓
JCT ✓ ✗
NEC3 ✓ ✓
FIDIC ✗ ✓
www.olswang.com6
Procurement Routes
✓ Turnkey/EPC ✓ Works-only
Bankable Control over quality
Time and cost certainty Time and cost certainty
Single-point responsibility Longer programme
More expensive More client involvement
Contractor design input Less contractor design input
www.olswang.com7
Time and Risk Management Provisions, and
Contrast with other Standard Forms
Keith Pickavance, Executive Consultant, Hill International, Past President
CIOB
Cost and Risk Management Provisions, and
Contrast with other Standard Forms
Roy Pickavance, Director, DAQS Ltd.
To Review
• The Role of the Valuer
• Contractor’s Pricing Document
• The Method of Measurement
• Pricing of Time Contingencies
• Event Pricing and Valuation of Variations
• Compensation for Delay and/or Disruption
• BIM
23/04/2013 10
THE ROLE of the VALUER
• Listed Person – Appendix B
• Appendix definition - The person identified as such in the Contract Agreement or,
on ceasing to be the Valuer such other person as the Employer shall appoint and
confirm to the Contractor and Contract Administrator, or, if none is appointed, the
Contract Administrator
• Clause 5.2 - …exercise its discretion independently and fairly
• User Guide – Roles and Responsibilities - The Valuer is appointed by the Employer
to advise the Employer, Contract Administrator and Listed Persons on
– the CONTENT of the CONTRACTOR’S PRICING DOCUMENT and the
VALUATION OF ACTIVITIES in the WORKING SCHEDULE (Clause 28),
– the MEASUREMENT AND VALUATION OF VARIATIONS (Clause 24),
– the PREDICTED OUT-TURN COST OF THE WORKS (Clause 53) and
– for PAYMENT PURPOSES THE CURRENT VALUE OF THE WORKS, from time to
time (Clause 54).
• Flow charts are provided- e.g.FC2 – Working Scheduled; FC7 – Extension of Time
and Compensation; FC10 - Payment
23/04/2013 11
CONTRACTOR’S
PRICING DOCUMENT
• Clause 28 - The document setting out the work which the
Contractor identifies as being necessary to satisfy the Conditions of
Contract, any applicable Model, Bill of Quantities, and/or
Specification and Drawings together with any conditions, resources,
materials or goods which the Contractor requires to be made
available to it, and the detailed method of pricing the financial
reward which the Contractor requires for carrying out the Works
• The importance of the Valuer’s Role – Active rather than passive
– Integration into the Working Schedule- Activity Based (Clause 28 and
Appendix D)
– Utilisation of updated Working Schedule ( Clause 33) to determine
the value of work completed (Current Value - Clause 54) and the
Predicted Cost ( Clause 53)
23/04/2013 12
THE METHOD OF
MEASUREMENT
• Where quantities are provided to determine the scope
of part of or the whole of the Works, or where a
schedule of descriptions is provided for pricing to be
used in the valuations of variations, it is essential to
specify the rules by which the quantities will be or have
been measured.
– Definition - Appendix A;
– Defined - Appendix B -Default NRM2; User Guide – see
MOM and BOQ
– BIM generated quantities
• Whatever form the measurement takes, if priced, it
needs to be aligned to the working Schedule
23/04/2013 13
PRICING OF
TIME CONTINGENCIES
• Clause 27; Appendix Definitions; Included in Appendix D Working Schedule
• Where Contractor’s Time Contingency periods are on the Critical Path to a
Relevant Completion Date, and hence included in the Contract duration, the effect
of those time contingencies in the priced Working Schedule is to require the
Contractor to pre-price (by virtue of its tender or bid) the prolongation costs it is
likely to suffer as a result of those contingency periods later being absorbed by
Contractor’s risks.
• Where Employer’s Time Contingency periods are on the Critical Path to a
Relevant Completion Date, and hence included in the Contract duration, the effect
of those time contingencies in the priced Working Schedule is to require the
Contractor to pre-price (through its tender or bid) the prolongation costs it is likely
to suffer as a result of those contingency periods later being absorbed by Events. If
the Employer does not use its critical contingencies then, all other things being
equal, there will be a reduction in the duration of the Works, an earlier Substantial
Completion date and hence a reduction in the Contract price, to the Employer’s
benefit.
23/04/2013 14
EVENT PRICING and
VALUATION of VARIATIONS
• Event - An occurrence which is an Employer’s
Cost Risk Event or an Employer’s Time Risk Event
– Defined in Appendix F – brought into the
Working Schedule
– Calculation of the effect of Event on Time
• Dealt with by KAP
– Calculation of the effect of Event on Cost – Clause 39
• Direct Cost - Activity costed - Clause 24 Variations
• Indirect Cost – Level of Effort costed using the updated
Working Schedule (Clause 38)
• Loss and/or Expense – Clause 28
23/04/2013 15
COMPENSATION FOR
DELAY AND/OR DISRUPTION
23/04/2013 16
Compensation for
Prolongation
• Clause 28.5 - If no rate for Preliminaries and/or Overheads and
Profit is indicated in the Contractor’s Pricing Document, it shall be
deemed to be agreed that the Contractor is not entitled to recover
such Preliminaries and/or Overheads and Profit as a part of the loss
and/or expense incurred as a result of any Employer’s Cost Risk
Event.
• The Contractor is required to identify its Preliminaries (Clause
28.4.1 ) and Overheads and Profit (Clause 28.4.2) by Level of Effort
durations logically linked to the Activities to which they relate.
• Provided that the information required has been incorporated in
the Working Schedule (Clause 28.5), prolongation costs can be
estimated during the course of the Works based upon the extent by
which any Level of Effort durations are adjusted from time to time
by the impact of Employer’s Cost Risk Events on the Working
Schedule (Clauses 39.1 and 53.2.3).
23/04/2013 17
Compensation for
Disruption
• PROGRESS RECORDS - Although the Working Schedule cannot be accurately
updated without Progress Records(Clause 33.1) and they are thus the essential
informational resource for managing time and for determining the extent to which
an Event has caused delay or disruption, the Contract is unique amongst standard
form contracts in requiring the Contractor to maintain any Progress Records other
than those in support of a claim.(Appendix B)
• Loss and/or Expense is Quantified under Clause 39.2.4 arising from an Employer’s
Cost Risk Event, and
• The Predicted Cost is to include for any change in a Level of Effort and any other
loss and/or expense (Clause 53.2.3)
• If the Contractor fails to provide the information required to enable the Valuer to
calculate the amount of the Contractor’s entitlement to compensation for
disruption and/or prolongation, the amount shall be calculated after Substantial
Completion using
– 39.3.1 the progress records and schedules produced under Clause 25.2, or (if none)
– such records and schedules as, in its absolute discretion, the Valuer adopts for the purpose of
this Clause 39.3.
23/04/2013 18
BIM
• Under CPC will the QS’s roll differ in Complex
Contracts?
a) In a current procurement environment (e.g.
Traditional, Design and Build etc. )
b) In a BIM environment
23/04/2013 19
Nick Lane
Partner and Head of Construction, Olswang LLP
Dispute resolution provisions and
procedures
Questions…?
Adam Constable Q.C., Keating Chambers
Contact us…
Francis Ho
Senior Associate
Olswang LLP
T +44 20 7067 3505
E francis.ho@olswang.com
Nick Lane
Partner
Olswang LLP
T +44 20 7067 3548
E nick.lane@olswang.com
Adam Constable QC
Keating Chambers
T +44 20 7544 2600
E aconstable@keatingchambers.com
Contact us…
Roy Pickavance
Director, DAQS Ltd BSc, FRICS, FCIOB,
FCIArb
T +44 (0) 1949 829287
E arp@daqs.co.uk
Keith Pickavance
Executive Consultant Hill International
T +44 (0) 207 618 1200
E keithpickavance@hillintl.com

More Related Content

What's hot

Construction Futures Wales - NEC Workshop - Importance of Program Control & M...
Construction Futures Wales - NEC Workshop - Importance of Program Control & M...Construction Futures Wales - NEC Workshop - Importance of Program Control & M...
Construction Futures Wales - NEC Workshop - Importance of Program Control & M...Rae Davies
 
project initiation
project initiationproject initiation
project initiationNaji Maalouf
 
project initiation
project initiationproject initiation
project initiationNaji Maalouf
 
FINAL ACCOUNT CONCLUSION OF BUILDING PROJECTS
FINAL ACCOUNT CONCLUSION OF BUILDING PROJECTSFINAL ACCOUNT CONCLUSION OF BUILDING PROJECTS
FINAL ACCOUNT CONCLUSION OF BUILDING PROJECTSLenson Mhango
 
Pp2 coursework 2 BRIEF 201708
Pp2 coursework 2  BRIEF  201708Pp2 coursework 2  BRIEF  201708
Pp2 coursework 2 BRIEF 201708Pang Khai Shuen
 
Construction Futures Wales - NEC Contracts Overview Workshop
Construction Futures Wales  - NEC Contracts Overview WorkshopConstruction Futures Wales  - NEC Contracts Overview Workshop
Construction Futures Wales - NEC Contracts Overview WorkshopRae Davies
 
Time value-of-money-formulas-sheet
Time value-of-money-formulas-sheetTime value-of-money-formulas-sheet
Time value-of-money-formulas-sheetMohana Krishna
 
Cfr ias 11 construction contract presentation by MOHSIN MUMTAZ
Cfr  ias 11 construction contract presentation by MOHSIN MUMTAZCfr  ias 11 construction contract presentation by MOHSIN MUMTAZ
Cfr ias 11 construction contract presentation by MOHSIN MUMTAZmianmohsinmumtazshb
 
Professional practice 2
Professional practice 2Professional practice 2
Professional practice 2Shze Hwa Lee
 
Assignment - Final Account
Assignment - Final AccountAssignment - Final Account
Assignment - Final AccountKai Yun Pang
 
Assignment - Report
Assignment - ReportAssignment - Report
Assignment - ReportKai Yun Pang
 
Variations in works contracts
Variations in works contractsVariations in works contracts
Variations in works contractsDr K M SONI
 
Real estate guidance note 2012 (drti)
Real estate guidance note 2012 (drti)Real estate guidance note 2012 (drti)
Real estate guidance note 2012 (drti)Dhruv Seth
 

What's hot (20)

Construction Futures Wales - NEC Workshop - Importance of Program Control & M...
Construction Futures Wales - NEC Workshop - Importance of Program Control & M...Construction Futures Wales - NEC Workshop - Importance of Program Control & M...
Construction Futures Wales - NEC Workshop - Importance of Program Control & M...
 
project initiation
project initiationproject initiation
project initiation
 
project initiation
project initiationproject initiation
project initiation
 
Accounting standard 7
Accounting standard 7Accounting standard 7
Accounting standard 7
 
FINAL ACCOUNT CONCLUSION OF BUILDING PROJECTS
FINAL ACCOUNT CONCLUSION OF BUILDING PROJECTSFINAL ACCOUNT CONCLUSION OF BUILDING PROJECTS
FINAL ACCOUNT CONCLUSION OF BUILDING PROJECTS
 
Pp2 coursework 2 BRIEF 201708
Pp2 coursework 2  BRIEF  201708Pp2 coursework 2  BRIEF  201708
Pp2 coursework 2 BRIEF 201708
 
Chapter 2- Contract Management
Chapter 2- Contract ManagementChapter 2- Contract Management
Chapter 2- Contract Management
 
Construction Futures Wales - NEC Contracts Overview Workshop
Construction Futures Wales  - NEC Contracts Overview WorkshopConstruction Futures Wales  - NEC Contracts Overview Workshop
Construction Futures Wales - NEC Contracts Overview Workshop
 
WORKS MANAGEMENT IN CPWD PART-I
WORKS MANAGEMENT IN CPWD PART-IWORKS MANAGEMENT IN CPWD PART-I
WORKS MANAGEMENT IN CPWD PART-I
 
Time value-of-money-formulas-sheet
Time value-of-money-formulas-sheetTime value-of-money-formulas-sheet
Time value-of-money-formulas-sheet
 
Cfr ias 11 construction contract presentation by MOHSIN MUMTAZ
Cfr  ias 11 construction contract presentation by MOHSIN MUMTAZCfr  ias 11 construction contract presentation by MOHSIN MUMTAZ
Cfr ias 11 construction contract presentation by MOHSIN MUMTAZ
 
Professional practice 2
Professional practice 2Professional practice 2
Professional practice 2
 
contract procedure
contract procedurecontract procedure
contract procedure
 
Assignment - Final Account
Assignment - Final AccountAssignment - Final Account
Assignment - Final Account
 
Assignment - Report
Assignment - ReportAssignment - Report
Assignment - Report
 
Variations in works contracts
Variations in works contractsVariations in works contracts
Variations in works contracts
 
Ias11
Ias11Ias11
Ias11
 
Real estate guidance note 2012 (drti)
Real estate guidance note 2012 (drti)Real estate guidance note 2012 (drti)
Real estate guidance note 2012 (drti)
 
Pp2 final report
Pp2 final reportPp2 final report
Pp2 final report
 
Pp2 p5
Pp2   p5Pp2   p5
Pp2 p5
 

Viewers also liked

敏捷实践和安装开发
敏捷实践和安装开发 敏捷实践和安装开发
敏捷实践和安装开发 Flexera
 
Recent Case Law Developments - 2014 Olswang Construction Law Conference
Recent Case Law Developments - 2014 Olswang Construction Law ConferenceRecent Case Law Developments - 2014 Olswang Construction Law Conference
Recent Case Law Developments - 2014 Olswang Construction Law ConferenceFrancis Ho
 
Walking To Wellness Holistic View Dr Shriniwas Kashalikatr
Walking To Wellness Holistic View Dr Shriniwas KashalikatrWalking To Wellness Holistic View Dr Shriniwas Kashalikatr
Walking To Wellness Holistic View Dr Shriniwas Kashalikatrshriniwaskashalikar
 
R E F E L C T I O N S A N D C R E A T I O N S Dr
R E F E L C T I O N S A N D  C R E A T I O N S  DrR E F E L C T I O N S A N D  C R E A T I O N S  Dr
R E F E L C T I O N S A N D C R E A T I O N S Drshriniwaskashalikar
 
1 kapitulli ii pasqyrat financiare
1 kapitulli ii  pasqyrat financiare1 kapitulli ii  pasqyrat financiare
1 kapitulli ii pasqyrat financiareMenaxherat
 
Banner maker展现端flash性能优化
Banner maker展现端flash性能优化 Banner maker展现端flash性能优化
Banner maker展现端flash性能优化 taobao.com
 
Bunding Or Binding Dr. Shriniwas Kashalikar
Bunding Or Binding  Dr. Shriniwas KashalikarBunding Or Binding  Dr. Shriniwas Kashalikar
Bunding Or Binding Dr. Shriniwas Kashalikarshriniwaskashalikar
 
教學訪問教師及受訪學校合作計畫書
教學訪問教師及受訪學校合作計畫書教學訪問教師及受訪學校合作計畫書
教學訪問教師及受訪學校合作計畫書Josephine C
 
Presentatie Jaap Haas
Presentatie Jaap HaasPresentatie Jaap Haas
Presentatie Jaap HaasMijnZorgnet
 
Vũ trụ & các học thuyết
Vũ trụ & các học thuyếtVũ trụ & các học thuyết
Vũ trụ & các học thuyếtMai Trong
 
Tash Magazine Cover
Tash Magazine CoverTash Magazine Cover
Tash Magazine Coverguest969fd6
 
N E W S T U D Y O F G I T A N O V 8 D R
N E W  S T U D Y  O F  G I T A  N O V 8  D RN E W  S T U D Y  O F  G I T A  N O V 8  D R
N E W S T U D Y O F G I T A N O V 8 D Rshriniwaskashalikar
 
B H O V A R A ( M A R A T H I B E S T S E L L E R A U T O F I C T I O N) Dr
B H O V A R A ( M A R A T H I  B E S T S E L L E R  A U T O F I C T I O N)  DrB H O V A R A ( M A R A T H I  B E S T S E L L E R  A U T O F I C T I O N)  Dr
B H O V A R A ( M A R A T H I B E S T S E L L E R A U T O F I C T I O N) Drshriniwaskashalikar
 
アダプター設定および開発サービス
アダプター設定および開発サービスアダプター設定および開発サービス
アダプター設定および開発サービスFlexera
 
Globus Eventi Presentation
Globus Eventi PresentationGlobus Eventi Presentation
Globus Eventi PresentationGlobus Eventi
 
Y O G A A N D S U P E R J O Y D R
Y O G A  A N D  S U P E R J O Y  D RY O G A  A N D  S U P E R J O Y  D R
Y O G A A N D S U P E R J O Y D Rshriniwaskashalikar
 

Viewers also liked (20)

敏捷实践和安装开发
敏捷实践和安装开发 敏捷实践和安装开发
敏捷实践和安装开发
 
Recent Case Law Developments - 2014 Olswang Construction Law Conference
Recent Case Law Developments - 2014 Olswang Construction Law ConferenceRecent Case Law Developments - 2014 Olswang Construction Law Conference
Recent Case Law Developments - 2014 Olswang Construction Law Conference
 
Walking To Wellness Holistic View Dr Shriniwas Kashalikatr
Walking To Wellness Holistic View Dr Shriniwas KashalikatrWalking To Wellness Holistic View Dr Shriniwas Kashalikatr
Walking To Wellness Holistic View Dr Shriniwas Kashalikatr
 
Belkan danaci
Belkan danaciBelkan danaci
Belkan danaci
 
Report Splinternetmarketing.Com Internet Marketing Services 5 9 2012
Report Splinternetmarketing.Com Internet Marketing Services   5 9 2012Report Splinternetmarketing.Com Internet Marketing Services   5 9 2012
Report Splinternetmarketing.Com Internet Marketing Services 5 9 2012
 
medical tourism
medical tourismmedical tourism
medical tourism
 
R E F E L C T I O N S A N D C R E A T I O N S Dr
R E F E L C T I O N S A N D  C R E A T I O N S  DrR E F E L C T I O N S A N D  C R E A T I O N S  Dr
R E F E L C T I O N S A N D C R E A T I O N S Dr
 
1 kapitulli ii pasqyrat financiare
1 kapitulli ii  pasqyrat financiare1 kapitulli ii  pasqyrat financiare
1 kapitulli ii pasqyrat financiare
 
Banner maker展现端flash性能优化
Banner maker展现端flash性能优化 Banner maker展现端flash性能优化
Banner maker展现端flash性能优化
 
Bunding Or Binding Dr. Shriniwas Kashalikar
Bunding Or Binding  Dr. Shriniwas KashalikarBunding Or Binding  Dr. Shriniwas Kashalikar
Bunding Or Binding Dr. Shriniwas Kashalikar
 
教學訪問教師及受訪學校合作計畫書
教學訪問教師及受訪學校合作計畫書教學訪問教師及受訪學校合作計畫書
教學訪問教師及受訪學校合作計畫書
 
Presentatie Jaap Haas
Presentatie Jaap HaasPresentatie Jaap Haas
Presentatie Jaap Haas
 
Vũ trụ & các học thuyết
Vũ trụ & các học thuyếtVũ trụ & các học thuyết
Vũ trụ & các học thuyết
 
Tash Magazine Cover
Tash Magazine CoverTash Magazine Cover
Tash Magazine Cover
 
N E W S T U D Y O F G I T A N O V 8 D R
N E W  S T U D Y  O F  G I T A  N O V 8  D RN E W  S T U D Y  O F  G I T A  N O V 8  D R
N E W S T U D Y O F G I T A N O V 8 D R
 
B H O V A R A ( M A R A T H I B E S T S E L L E R A U T O F I C T I O N) Dr
B H O V A R A ( M A R A T H I  B E S T S E L L E R  A U T O F I C T I O N)  DrB H O V A R A ( M A R A T H I  B E S T S E L L E R  A U T O F I C T I O N)  Dr
B H O V A R A ( M A R A T H I B E S T S E L L E R A U T O F I C T I O N) Dr
 
アダプター設定および開発サービス
アダプター設定および開発サービスアダプター設定および開発サービス
アダプター設定および開発サービス
 
Globus Eventi Presentation
Globus Eventi PresentationGlobus Eventi Presentation
Globus Eventi Presentation
 
Internet marketing-services-search-engine-rankings-11-29-2011
Internet marketing-services-search-engine-rankings-11-29-2011Internet marketing-services-search-engine-rankings-11-29-2011
Internet marketing-services-search-engine-rankings-11-29-2011
 
Y O G A A N D S U P E R J O Y D R
Y O G A  A N D  S U P E R J O Y  D RY O G A  A N D  S U P E R J O Y  D R
Y O G A A N D S U P E R J O Y D R
 

Similar to Chartered Institute of Building - Launch of Complex Projects Contract 2013 - Ascot - 23 April 2013

Assignment - Management Contracting (Presentation Slide)
Assignment - Management Contracting (Presentation Slide)Assignment - Management Contracting (Presentation Slide)
Assignment - Management Contracting (Presentation Slide)Kai Yun Pang
 
Planning and Project Controls under NEC4 – the choice isn’t yours! by "Glenn ...
Planning and Project Controls under NEC4 – the choice isn’t yours! by "Glenn ...Planning and Project Controls under NEC4 – the choice isn’t yours! by "Glenn ...
Planning and Project Controls under NEC4 – the choice isn’t yours! by "Glenn ...Project Controls Expo
 
Professional Practice II - Presentation - Construction Delays & EOT
Professional Practice II - Presentation - Construction Delays & EOTProfessional Practice II - Presentation - Construction Delays & EOT
Professional Practice II - Presentation - Construction Delays & EOTYee Len Wan
 
C. Site managment chapter 5.pptx
C. Site managment chapter 5.pptxC. Site managment chapter 5.pptx
C. Site managment chapter 5.pptxEdenBekele5
 
M4 - Making Target Cost Contracts Work, under NEC3
M4 - Making Target Cost Contracts Work, under NEC3M4 - Making Target Cost Contracts Work, under NEC3
M4 - Making Target Cost Contracts Work, under NEC3Project Controls Expo
 
PP Seminar Tutorial 7
PP Seminar Tutorial 7PP Seminar Tutorial 7
PP Seminar Tutorial 7Farah Sham
 
المحاضرة 160 بعنوان البرنامج الزمنى فى عقود التشيد
المحاضرة 160 بعنوان البرنامج الزمنى فى عقود التشيدالمحاضرة 160 بعنوان البرنامج الزمنى فى عقود التشيد
المحاضرة 160 بعنوان البرنامج الزمنى فى عقود التشيدEgyptian Engineers Association
 
CONTRACT ADMINISTRATION- Presentation dated 22.11.16
CONTRACT ADMINISTRATION- Presentation dated 22.11.16CONTRACT ADMINISTRATION- Presentation dated 22.11.16
CONTRACT ADMINISTRATION- Presentation dated 22.11.16Arvind Solanki
 
Construction contract_Existing and Proposed Accounting Standards
Construction contract_Existing and Proposed Accounting StandardsConstruction contract_Existing and Proposed Accounting Standards
Construction contract_Existing and Proposed Accounting StandardsAdi Iskandar Iliyas
 
The importance of 3 Core NEC Time Clauses when submitting a programme.docx
The importance of 3 Core NEC Time Clauses when submitting a programme.docxThe importance of 3 Core NEC Time Clauses when submitting a programme.docx
The importance of 3 Core NEC Time Clauses when submitting a programme.docxMy own
 
Professional Practice 2: Group Assignment
Professional Practice 2: Group AssignmentProfessional Practice 2: Group Assignment
Professional Practice 2: Group Assignment마 이환
 
Contract payment and variation
Contract payment and variationContract payment and variation
Contract payment and variationVj NiroSh
 
AS-7 Construction Contracts and AS-18 Related Party Transactions
AS-7 Construction Contracts and AS-18 Related Party TransactionsAS-7 Construction Contracts and AS-18 Related Party Transactions
AS-7 Construction Contracts and AS-18 Related Party TransactionsPrakhar Jain
 

Similar to Chartered Institute of Building - Launch of Complex Projects Contract 2013 - Ascot - 23 April 2013 (20)

Assignment - Management Contracting (Presentation Slide)
Assignment - Management Contracting (Presentation Slide)Assignment - Management Contracting (Presentation Slide)
Assignment - Management Contracting (Presentation Slide)
 
Planning and Project Controls under NEC4 – the choice isn’t yours! by "Glenn ...
Planning and Project Controls under NEC4 – the choice isn’t yours! by "Glenn ...Planning and Project Controls under NEC4 – the choice isn’t yours! by "Glenn ...
Planning and Project Controls under NEC4 – the choice isn’t yours! by "Glenn ...
 
Professional Practice II - Presentation - Construction Delays & EOT
Professional Practice II - Presentation - Construction Delays & EOTProfessional Practice II - Presentation - Construction Delays & EOT
Professional Practice II - Presentation - Construction Delays & EOT
 
Claims and insolvencies (1)
Claims and insolvencies (1)Claims and insolvencies (1)
Claims and insolvencies (1)
 
Essentials of EOT Claims
Essentials of EOT ClaimsEssentials of EOT Claims
Essentials of EOT Claims
 
C. Site managment chapter 5.pptx
C. Site managment chapter 5.pptxC. Site managment chapter 5.pptx
C. Site managment chapter 5.pptx
 
M4 - Making Target Cost Contracts Work, under NEC3
M4 - Making Target Cost Contracts Work, under NEC3M4 - Making Target Cost Contracts Work, under NEC3
M4 - Making Target Cost Contracts Work, under NEC3
 
PP Seminar Tutorial 7
PP Seminar Tutorial 7PP Seminar Tutorial 7
PP Seminar Tutorial 7
 
المحاضرة 160 بعنوان البرنامج الزمنى فى عقود التشيد
المحاضرة 160 بعنوان البرنامج الزمنى فى عقود التشيدالمحاضرة 160 بعنوان البرنامج الزمنى فى عقود التشيد
المحاضرة 160 بعنوان البرنامج الزمنى فى عقود التشيد
 
NEC3 programme
NEC3 programmeNEC3 programme
NEC3 programme
 
Cl presentation
Cl presentationCl presentation
Cl presentation
 
Construction contract
Construction contractConstruction contract
Construction contract
 
Construction contract
Construction contractConstruction contract
Construction contract
 
CONTRACT ADMINISTRATION- Presentation dated 22.11.16
CONTRACT ADMINISTRATION- Presentation dated 22.11.16CONTRACT ADMINISTRATION- Presentation dated 22.11.16
CONTRACT ADMINISTRATION- Presentation dated 22.11.16
 
Pp2 asignment-1
Pp2 asignment-1Pp2 asignment-1
Pp2 asignment-1
 
Construction contract_Existing and Proposed Accounting Standards
Construction contract_Existing and Proposed Accounting StandardsConstruction contract_Existing and Proposed Accounting Standards
Construction contract_Existing and Proposed Accounting Standards
 
The importance of 3 Core NEC Time Clauses when submitting a programme.docx
The importance of 3 Core NEC Time Clauses when submitting a programme.docxThe importance of 3 Core NEC Time Clauses when submitting a programme.docx
The importance of 3 Core NEC Time Clauses when submitting a programme.docx
 
Professional Practice 2: Group Assignment
Professional Practice 2: Group AssignmentProfessional Practice 2: Group Assignment
Professional Practice 2: Group Assignment
 
Contract payment and variation
Contract payment and variationContract payment and variation
Contract payment and variation
 
AS-7 Construction Contracts and AS-18 Related Party Transactions
AS-7 Construction Contracts and AS-18 Related Party TransactionsAS-7 Construction Contracts and AS-18 Related Party Transactions
AS-7 Construction Contracts and AS-18 Related Party Transactions
 

More from Francis Ho

COP26: Eating for the Planet
COP26: Eating for the PlanetCOP26: Eating for the Planet
COP26: Eating for the PlanetFrancis Ho
 
City of London Law Society - Submittal to BEIS on Statutory Retention Deposit...
City of London Law Society - Submittal to BEIS on Statutory Retention Deposit...City of London Law Society - Submittal to BEIS on Statutory Retention Deposit...
City of London Law Society - Submittal to BEIS on Statutory Retention Deposit...Francis Ho
 
City of London Law Society - Construction Law Committee - Response to Retenti...
City of London Law Society - Construction Law Committee - Response to Retenti...City of London Law Society - Construction Law Committee - Response to Retenti...
City of London Law Society - Construction Law Committee - Response to Retenti...Francis Ho
 
How will Brexit impact on Construction?
How will Brexit impact on Construction?How will Brexit impact on Construction?
How will Brexit impact on Construction?Francis Ho
 
Variations and their Consequences - Olswang Construction Law Masterclass - 5 ...
Variations and their Consequences - Olswang Construction Law Masterclass - 5 ...Variations and their Consequences - Olswang Construction Law Masterclass - 5 ...
Variations and their Consequences - Olswang Construction Law Masterclass - 5 ...Francis Ho
 
Construction Insolvency
Construction InsolvencyConstruction Insolvency
Construction InsolvencyFrancis Ho
 
The Management of Complex Contracts
The Management of Complex ContractsThe Management of Complex Contracts
The Management of Complex ContractsFrancis Ho
 
Key Developments in Emerging Markets
Key Developments in Emerging MarketsKey Developments in Emerging Markets
Key Developments in Emerging MarketsFrancis Ho
 
Using Two-Stage Tendering Effectively
Using Two-Stage Tendering EffectivelyUsing Two-Stage Tendering Effectively
Using Two-Stage Tendering EffectivelyFrancis Ho
 
Managing the Risks of Delay in Construction Projects
Managing the Risks of Delay in Construction ProjectsManaging the Risks of Delay in Construction Projects
Managing the Risks of Delay in Construction ProjectsFrancis Ho
 
It Pays to Be Right: Payment in Construction Contracts
It Pays to Be Right: Payment in Construction ContractsIt Pays to Be Right: Payment in Construction Contracts
It Pays to Be Right: Payment in Construction ContractsFrancis Ho
 
Adjudication: Tips, Traps and Tactics
Adjudication: Tips, Traps and TacticsAdjudication: Tips, Traps and Tactics
Adjudication: Tips, Traps and TacticsFrancis Ho
 
Contractual Options for Procuring Major Projects in the UK
Contractual Options for Procuring Major Projects in the UKContractual Options for Procuring Major Projects in the UK
Contractual Options for Procuring Major Projects in the UKFrancis Ho
 
Introductory Note on International Construction Contracts
Introductory Note on International Construction ContractsIntroductory Note on International Construction Contracts
Introductory Note on International Construction ContractsFrancis Ho
 
Works Insurance and Latent Defects Insurance
Works Insurance and Latent Defects InsuranceWorks Insurance and Latent Defects Insurance
Works Insurance and Latent Defects InsuranceFrancis Ho
 
Third Party Rights and Why They Matter
Third Party Rights and Why They MatterThird Party Rights and Why They Matter
Third Party Rights and Why They MatterFrancis Ho
 
A Practical Guide to the Construction (Design and Management) Regulations 2015
A Practical Guide to the Construction (Design and Management) Regulations 2015A Practical Guide to the Construction (Design and Management) Regulations 2015
A Practical Guide to the Construction (Design and Management) Regulations 2015Francis Ho
 
Construction Dispute Resolution and Avoidance in a Boom Market
Construction Dispute Resolution and Avoidance in a Boom MarketConstruction Dispute Resolution and Avoidance in a Boom Market
Construction Dispute Resolution and Avoidance in a Boom MarketFrancis Ho
 
Letters of Intent
Letters of IntentLetters of Intent
Letters of IntentFrancis Ho
 
Collateral Warranties and Third Party Rights
Collateral Warranties and Third Party RightsCollateral Warranties and Third Party Rights
Collateral Warranties and Third Party RightsFrancis Ho
 

More from Francis Ho (20)

COP26: Eating for the Planet
COP26: Eating for the PlanetCOP26: Eating for the Planet
COP26: Eating for the Planet
 
City of London Law Society - Submittal to BEIS on Statutory Retention Deposit...
City of London Law Society - Submittal to BEIS on Statutory Retention Deposit...City of London Law Society - Submittal to BEIS on Statutory Retention Deposit...
City of London Law Society - Submittal to BEIS on Statutory Retention Deposit...
 
City of London Law Society - Construction Law Committee - Response to Retenti...
City of London Law Society - Construction Law Committee - Response to Retenti...City of London Law Society - Construction Law Committee - Response to Retenti...
City of London Law Society - Construction Law Committee - Response to Retenti...
 
How will Brexit impact on Construction?
How will Brexit impact on Construction?How will Brexit impact on Construction?
How will Brexit impact on Construction?
 
Variations and their Consequences - Olswang Construction Law Masterclass - 5 ...
Variations and their Consequences - Olswang Construction Law Masterclass - 5 ...Variations and their Consequences - Olswang Construction Law Masterclass - 5 ...
Variations and their Consequences - Olswang Construction Law Masterclass - 5 ...
 
Construction Insolvency
Construction InsolvencyConstruction Insolvency
Construction Insolvency
 
The Management of Complex Contracts
The Management of Complex ContractsThe Management of Complex Contracts
The Management of Complex Contracts
 
Key Developments in Emerging Markets
Key Developments in Emerging MarketsKey Developments in Emerging Markets
Key Developments in Emerging Markets
 
Using Two-Stage Tendering Effectively
Using Two-Stage Tendering EffectivelyUsing Two-Stage Tendering Effectively
Using Two-Stage Tendering Effectively
 
Managing the Risks of Delay in Construction Projects
Managing the Risks of Delay in Construction ProjectsManaging the Risks of Delay in Construction Projects
Managing the Risks of Delay in Construction Projects
 
It Pays to Be Right: Payment in Construction Contracts
It Pays to Be Right: Payment in Construction ContractsIt Pays to Be Right: Payment in Construction Contracts
It Pays to Be Right: Payment in Construction Contracts
 
Adjudication: Tips, Traps and Tactics
Adjudication: Tips, Traps and TacticsAdjudication: Tips, Traps and Tactics
Adjudication: Tips, Traps and Tactics
 
Contractual Options for Procuring Major Projects in the UK
Contractual Options for Procuring Major Projects in the UKContractual Options for Procuring Major Projects in the UK
Contractual Options for Procuring Major Projects in the UK
 
Introductory Note on International Construction Contracts
Introductory Note on International Construction ContractsIntroductory Note on International Construction Contracts
Introductory Note on International Construction Contracts
 
Works Insurance and Latent Defects Insurance
Works Insurance and Latent Defects InsuranceWorks Insurance and Latent Defects Insurance
Works Insurance and Latent Defects Insurance
 
Third Party Rights and Why They Matter
Third Party Rights and Why They MatterThird Party Rights and Why They Matter
Third Party Rights and Why They Matter
 
A Practical Guide to the Construction (Design and Management) Regulations 2015
A Practical Guide to the Construction (Design and Management) Regulations 2015A Practical Guide to the Construction (Design and Management) Regulations 2015
A Practical Guide to the Construction (Design and Management) Regulations 2015
 
Construction Dispute Resolution and Avoidance in a Boom Market
Construction Dispute Resolution and Avoidance in a Boom MarketConstruction Dispute Resolution and Avoidance in a Boom Market
Construction Dispute Resolution and Avoidance in a Boom Market
 
Letters of Intent
Letters of IntentLetters of Intent
Letters of Intent
 
Collateral Warranties and Third Party Rights
Collateral Warranties and Third Party RightsCollateral Warranties and Third Party Rights
Collateral Warranties and Third Party Rights
 

Recently uploaded

Kolte Patil Mirabilis at Horamavu Road, Bangalore E brochure.pdf
Kolte Patil Mirabilis at Horamavu Road, Bangalore E brochure.pdfKolte Patil Mirabilis at Horamavu Road, Bangalore E brochure.pdf
Kolte Patil Mirabilis at Horamavu Road, Bangalore E brochure.pdfAhanundefined
 
Dynamic Netsoft A leader In Property management Software
Dynamic Netsoft A leader In Property management SoftwareDynamic Netsoft A leader In Property management Software
Dynamic Netsoft A leader In Property management SoftwareDynamic Netsoft
 
Kolte Patil Universe Hinjewadi Pune Brochure.pdf
Kolte Patil Universe Hinjewadi Pune Brochure.pdfKolte Patil Universe Hinjewadi Pune Brochure.pdf
Kolte Patil Universe Hinjewadi Pune Brochure.pdfPrachiRudram
 
DLF Plots Sriperumbudur in Chennai E Brochure Pdf
DLF Plots Sriperumbudur in Chennai E Brochure PdfDLF Plots Sriperumbudur in Chennai E Brochure Pdf
DLF Plots Sriperumbudur in Chennai E Brochure Pdfashiyadav24
 
Everything you ever Wanted to Know about Florida Property Tax Exemptions.pdf
Everything you ever Wanted to Know about Florida Property Tax Exemptions.pdfEverything you ever Wanted to Know about Florida Property Tax Exemptions.pdf
Everything you ever Wanted to Know about Florida Property Tax Exemptions.pdfTim Wilmath
 
Prestige Rainbow Waters Raidurgam, Gachibowli Hyderabad E- Brochure.pdf
Prestige Rainbow Waters Raidurgam, Gachibowli Hyderabad E- Brochure.pdfPrestige Rainbow Waters Raidurgam, Gachibowli Hyderabad E- Brochure.pdf
Prestige Rainbow Waters Raidurgam, Gachibowli Hyderabad E- Brochure.pdffaheemali990101
 
Ryan Mahoney - How Property Technology Is Altering the Real Estate Market
Ryan Mahoney - How Property Technology Is Altering the Real Estate MarketRyan Mahoney - How Property Technology Is Altering the Real Estate Market
Ryan Mahoney - How Property Technology Is Altering the Real Estate MarketRyan Mahoney
 
Kumar Fireworks Hadapsar Link Road Pune Brochure.pdf
Kumar Fireworks Hadapsar Link Road Pune Brochure.pdfKumar Fireworks Hadapsar Link Road Pune Brochure.pdf
Kumar Fireworks Hadapsar Link Road Pune Brochure.pdfBabyrudram
 
Managed Farmland Brochures to get more in
Managed Farmland Brochures to get more inManaged Farmland Brochures to get more in
Managed Farmland Brochures to get more inknoxdigital1
 
Provident Solitaire Park Square Kanakapura Road, Bangalore E- Brochure.pdf
Provident Solitaire Park Square Kanakapura Road, Bangalore E- Brochure.pdfProvident Solitaire Park Square Kanakapura Road, Bangalore E- Brochure.pdf
Provident Solitaire Park Square Kanakapura Road, Bangalore E- Brochure.pdffaheemali990101
 
Prestige Sector 94 at Noida E Brochure.pdf
Prestige Sector 94 at Noida E Brochure.pdfPrestige Sector 94 at Noida E Brochure.pdf
Prestige Sector 94 at Noida E Brochure.pdfsarak0han45400
 
Brigade Neopolis Kokapet, Hyderabad E- Brochure
Brigade Neopolis Kokapet, Hyderabad E- BrochureBrigade Neopolis Kokapet, Hyderabad E- Brochure
Brigade Neopolis Kokapet, Hyderabad E- Brochurefaheemali990101
 
Clemson Engineering Consultant Dubai For Innovative and Sustainable Engineeri...
Clemson Engineering Consultant Dubai For Innovative and Sustainable Engineeri...Clemson Engineering Consultant Dubai For Innovative and Sustainable Engineeri...
Clemson Engineering Consultant Dubai For Innovative and Sustainable Engineeri...Clemson Engineering Consultant
 
Ebullient Investments Limited specializes in Building contractor
Ebullient Investments Limited specializes in Building contractorEbullient Investments Limited specializes in Building contractor
Ebullient Investments Limited specializes in Building contractorEbullient Investments Limited
 
Prestige Somerville Whitefield Bangalore E- Brochure.pdf
Prestige Somerville Whitefield Bangalore E- Brochure.pdfPrestige Somerville Whitefield Bangalore E- Brochure.pdf
Prestige Somerville Whitefield Bangalore E- Brochure.pdffaheemali990101
 
Mahindra Vista Kandivali East Mumbai Brochure.pdf
Mahindra Vista Kandivali East Mumbai Brochure.pdfMahindra Vista Kandivali East Mumbai Brochure.pdf
Mahindra Vista Kandivali East Mumbai Brochure.pdfPrachiRudram
 
Experion Elements Sector 45 Noida_Brochure.pdf.pdf
Experion Elements Sector 45 Noida_Brochure.pdf.pdfExperion Elements Sector 45 Noida_Brochure.pdf.pdf
Experion Elements Sector 45 Noida_Brochure.pdf.pdfkratirudram
 
A Brief History of Intangibles in Ad Valorem Taxation.pdf
A Brief History of Intangibles in Ad Valorem Taxation.pdfA Brief History of Intangibles in Ad Valorem Taxation.pdf
A Brief History of Intangibles in Ad Valorem Taxation.pdfTim Wilmath
 
Maha Mauka Squarefeet Brochure |Maha Mauka Squarefeet PDF Brochure|
Maha Mauka Squarefeet Brochure |Maha Mauka Squarefeet PDF Brochure|Maha Mauka Squarefeet Brochure |Maha Mauka Squarefeet PDF Brochure|
Maha Mauka Squarefeet Brochure |Maha Mauka Squarefeet PDF Brochure|AkshayJoshi575980
 
Anandtara Iris Residences Mundhwa Pune Brochure.pdf
Anandtara Iris Residences Mundhwa Pune Brochure.pdfAnandtara Iris Residences Mundhwa Pune Brochure.pdf
Anandtara Iris Residences Mundhwa Pune Brochure.pdfabbu831446
 

Recently uploaded (20)

Kolte Patil Mirabilis at Horamavu Road, Bangalore E brochure.pdf
Kolte Patil Mirabilis at Horamavu Road, Bangalore E brochure.pdfKolte Patil Mirabilis at Horamavu Road, Bangalore E brochure.pdf
Kolte Patil Mirabilis at Horamavu Road, Bangalore E brochure.pdf
 
Dynamic Netsoft A leader In Property management Software
Dynamic Netsoft A leader In Property management SoftwareDynamic Netsoft A leader In Property management Software
Dynamic Netsoft A leader In Property management Software
 
Kolte Patil Universe Hinjewadi Pune Brochure.pdf
Kolte Patil Universe Hinjewadi Pune Brochure.pdfKolte Patil Universe Hinjewadi Pune Brochure.pdf
Kolte Patil Universe Hinjewadi Pune Brochure.pdf
 
DLF Plots Sriperumbudur in Chennai E Brochure Pdf
DLF Plots Sriperumbudur in Chennai E Brochure PdfDLF Plots Sriperumbudur in Chennai E Brochure Pdf
DLF Plots Sriperumbudur in Chennai E Brochure Pdf
 
Everything you ever Wanted to Know about Florida Property Tax Exemptions.pdf
Everything you ever Wanted to Know about Florida Property Tax Exemptions.pdfEverything you ever Wanted to Know about Florida Property Tax Exemptions.pdf
Everything you ever Wanted to Know about Florida Property Tax Exemptions.pdf
 
Prestige Rainbow Waters Raidurgam, Gachibowli Hyderabad E- Brochure.pdf
Prestige Rainbow Waters Raidurgam, Gachibowli Hyderabad E- Brochure.pdfPrestige Rainbow Waters Raidurgam, Gachibowli Hyderabad E- Brochure.pdf
Prestige Rainbow Waters Raidurgam, Gachibowli Hyderabad E- Brochure.pdf
 
Ryan Mahoney - How Property Technology Is Altering the Real Estate Market
Ryan Mahoney - How Property Technology Is Altering the Real Estate MarketRyan Mahoney - How Property Technology Is Altering the Real Estate Market
Ryan Mahoney - How Property Technology Is Altering the Real Estate Market
 
Kumar Fireworks Hadapsar Link Road Pune Brochure.pdf
Kumar Fireworks Hadapsar Link Road Pune Brochure.pdfKumar Fireworks Hadapsar Link Road Pune Brochure.pdf
Kumar Fireworks Hadapsar Link Road Pune Brochure.pdf
 
Managed Farmland Brochures to get more in
Managed Farmland Brochures to get more inManaged Farmland Brochures to get more in
Managed Farmland Brochures to get more in
 
Provident Solitaire Park Square Kanakapura Road, Bangalore E- Brochure.pdf
Provident Solitaire Park Square Kanakapura Road, Bangalore E- Brochure.pdfProvident Solitaire Park Square Kanakapura Road, Bangalore E- Brochure.pdf
Provident Solitaire Park Square Kanakapura Road, Bangalore E- Brochure.pdf
 
Prestige Sector 94 at Noida E Brochure.pdf
Prestige Sector 94 at Noida E Brochure.pdfPrestige Sector 94 at Noida E Brochure.pdf
Prestige Sector 94 at Noida E Brochure.pdf
 
Brigade Neopolis Kokapet, Hyderabad E- Brochure
Brigade Neopolis Kokapet, Hyderabad E- BrochureBrigade Neopolis Kokapet, Hyderabad E- Brochure
Brigade Neopolis Kokapet, Hyderabad E- Brochure
 
Clemson Engineering Consultant Dubai For Innovative and Sustainable Engineeri...
Clemson Engineering Consultant Dubai For Innovative and Sustainable Engineeri...Clemson Engineering Consultant Dubai For Innovative and Sustainable Engineeri...
Clemson Engineering Consultant Dubai For Innovative and Sustainable Engineeri...
 
Ebullient Investments Limited specializes in Building contractor
Ebullient Investments Limited specializes in Building contractorEbullient Investments Limited specializes in Building contractor
Ebullient Investments Limited specializes in Building contractor
 
Prestige Somerville Whitefield Bangalore E- Brochure.pdf
Prestige Somerville Whitefield Bangalore E- Brochure.pdfPrestige Somerville Whitefield Bangalore E- Brochure.pdf
Prestige Somerville Whitefield Bangalore E- Brochure.pdf
 
Mahindra Vista Kandivali East Mumbai Brochure.pdf
Mahindra Vista Kandivali East Mumbai Brochure.pdfMahindra Vista Kandivali East Mumbai Brochure.pdf
Mahindra Vista Kandivali East Mumbai Brochure.pdf
 
Experion Elements Sector 45 Noida_Brochure.pdf.pdf
Experion Elements Sector 45 Noida_Brochure.pdf.pdfExperion Elements Sector 45 Noida_Brochure.pdf.pdf
Experion Elements Sector 45 Noida_Brochure.pdf.pdf
 
A Brief History of Intangibles in Ad Valorem Taxation.pdf
A Brief History of Intangibles in Ad Valorem Taxation.pdfA Brief History of Intangibles in Ad Valorem Taxation.pdf
A Brief History of Intangibles in Ad Valorem Taxation.pdf
 
Maha Mauka Squarefeet Brochure |Maha Mauka Squarefeet PDF Brochure|
Maha Mauka Squarefeet Brochure |Maha Mauka Squarefeet PDF Brochure|Maha Mauka Squarefeet Brochure |Maha Mauka Squarefeet PDF Brochure|
Maha Mauka Squarefeet Brochure |Maha Mauka Squarefeet PDF Brochure|
 
Anandtara Iris Residences Mundhwa Pune Brochure.pdf
Anandtara Iris Residences Mundhwa Pune Brochure.pdfAnandtara Iris Residences Mundhwa Pune Brochure.pdf
Anandtara Iris Residences Mundhwa Pune Brochure.pdf
 

Chartered Institute of Building - Launch of Complex Projects Contract 2013 - Ascot - 23 April 2013

  • 1. An Introduction to the Complex Projects Contract 2013 23 April 2013
  • 3. CIOB Research, background to CPC2013 and availability Keith Pickavance, Executive Consultant, Hill International, Past President CIOB
  • 4. Project suitability and procurement strategy Francis Ho Senior Associate, Olswang LLP
  • 5. Where should CPC2013 be used? Suitable for: Less suitable for: Works of high value or complexity ✓ Simpler works or those of short duration ✗ Major real estate projects ✓ Construction management/EPCM without amendment ✗ Engineering and infrastructure projects ✓ Inexperienced clients/contractors ✗ www.olswang.com5
  • 6. International Usage Contract England and Wales International CPC2013 ✓ ✓ JCT ✓ ✗ NEC3 ✓ ✓ FIDIC ✗ ✓ www.olswang.com6
  • 7. Procurement Routes ✓ Turnkey/EPC ✓ Works-only Bankable Control over quality Time and cost certainty Time and cost certainty Single-point responsibility Longer programme More expensive More client involvement Contractor design input Less contractor design input www.olswang.com7
  • 8. Time and Risk Management Provisions, and Contrast with other Standard Forms Keith Pickavance, Executive Consultant, Hill International, Past President CIOB
  • 9. Cost and Risk Management Provisions, and Contrast with other Standard Forms Roy Pickavance, Director, DAQS Ltd.
  • 10. To Review • The Role of the Valuer • Contractor’s Pricing Document • The Method of Measurement • Pricing of Time Contingencies • Event Pricing and Valuation of Variations • Compensation for Delay and/or Disruption • BIM 23/04/2013 10
  • 11. THE ROLE of the VALUER • Listed Person – Appendix B • Appendix definition - The person identified as such in the Contract Agreement or, on ceasing to be the Valuer such other person as the Employer shall appoint and confirm to the Contractor and Contract Administrator, or, if none is appointed, the Contract Administrator • Clause 5.2 - …exercise its discretion independently and fairly • User Guide – Roles and Responsibilities - The Valuer is appointed by the Employer to advise the Employer, Contract Administrator and Listed Persons on – the CONTENT of the CONTRACTOR’S PRICING DOCUMENT and the VALUATION OF ACTIVITIES in the WORKING SCHEDULE (Clause 28), – the MEASUREMENT AND VALUATION OF VARIATIONS (Clause 24), – the PREDICTED OUT-TURN COST OF THE WORKS (Clause 53) and – for PAYMENT PURPOSES THE CURRENT VALUE OF THE WORKS, from time to time (Clause 54). • Flow charts are provided- e.g.FC2 – Working Scheduled; FC7 – Extension of Time and Compensation; FC10 - Payment 23/04/2013 11
  • 12. CONTRACTOR’S PRICING DOCUMENT • Clause 28 - The document setting out the work which the Contractor identifies as being necessary to satisfy the Conditions of Contract, any applicable Model, Bill of Quantities, and/or Specification and Drawings together with any conditions, resources, materials or goods which the Contractor requires to be made available to it, and the detailed method of pricing the financial reward which the Contractor requires for carrying out the Works • The importance of the Valuer’s Role – Active rather than passive – Integration into the Working Schedule- Activity Based (Clause 28 and Appendix D) – Utilisation of updated Working Schedule ( Clause 33) to determine the value of work completed (Current Value - Clause 54) and the Predicted Cost ( Clause 53) 23/04/2013 12
  • 13. THE METHOD OF MEASUREMENT • Where quantities are provided to determine the scope of part of or the whole of the Works, or where a schedule of descriptions is provided for pricing to be used in the valuations of variations, it is essential to specify the rules by which the quantities will be or have been measured. – Definition - Appendix A; – Defined - Appendix B -Default NRM2; User Guide – see MOM and BOQ – BIM generated quantities • Whatever form the measurement takes, if priced, it needs to be aligned to the working Schedule 23/04/2013 13
  • 14. PRICING OF TIME CONTINGENCIES • Clause 27; Appendix Definitions; Included in Appendix D Working Schedule • Where Contractor’s Time Contingency periods are on the Critical Path to a Relevant Completion Date, and hence included in the Contract duration, the effect of those time contingencies in the priced Working Schedule is to require the Contractor to pre-price (by virtue of its tender or bid) the prolongation costs it is likely to suffer as a result of those contingency periods later being absorbed by Contractor’s risks. • Where Employer’s Time Contingency periods are on the Critical Path to a Relevant Completion Date, and hence included in the Contract duration, the effect of those time contingencies in the priced Working Schedule is to require the Contractor to pre-price (through its tender or bid) the prolongation costs it is likely to suffer as a result of those contingency periods later being absorbed by Events. If the Employer does not use its critical contingencies then, all other things being equal, there will be a reduction in the duration of the Works, an earlier Substantial Completion date and hence a reduction in the Contract price, to the Employer’s benefit. 23/04/2013 14
  • 15. EVENT PRICING and VALUATION of VARIATIONS • Event - An occurrence which is an Employer’s Cost Risk Event or an Employer’s Time Risk Event – Defined in Appendix F – brought into the Working Schedule – Calculation of the effect of Event on Time • Dealt with by KAP – Calculation of the effect of Event on Cost – Clause 39 • Direct Cost - Activity costed - Clause 24 Variations • Indirect Cost – Level of Effort costed using the updated Working Schedule (Clause 38) • Loss and/or Expense – Clause 28 23/04/2013 15
  • 16. COMPENSATION FOR DELAY AND/OR DISRUPTION 23/04/2013 16
  • 17. Compensation for Prolongation • Clause 28.5 - If no rate for Preliminaries and/or Overheads and Profit is indicated in the Contractor’s Pricing Document, it shall be deemed to be agreed that the Contractor is not entitled to recover such Preliminaries and/or Overheads and Profit as a part of the loss and/or expense incurred as a result of any Employer’s Cost Risk Event. • The Contractor is required to identify its Preliminaries (Clause 28.4.1 ) and Overheads and Profit (Clause 28.4.2) by Level of Effort durations logically linked to the Activities to which they relate. • Provided that the information required has been incorporated in the Working Schedule (Clause 28.5), prolongation costs can be estimated during the course of the Works based upon the extent by which any Level of Effort durations are adjusted from time to time by the impact of Employer’s Cost Risk Events on the Working Schedule (Clauses 39.1 and 53.2.3). 23/04/2013 17
  • 18. Compensation for Disruption • PROGRESS RECORDS - Although the Working Schedule cannot be accurately updated without Progress Records(Clause 33.1) and they are thus the essential informational resource for managing time and for determining the extent to which an Event has caused delay or disruption, the Contract is unique amongst standard form contracts in requiring the Contractor to maintain any Progress Records other than those in support of a claim.(Appendix B) • Loss and/or Expense is Quantified under Clause 39.2.4 arising from an Employer’s Cost Risk Event, and • The Predicted Cost is to include for any change in a Level of Effort and any other loss and/or expense (Clause 53.2.3) • If the Contractor fails to provide the information required to enable the Valuer to calculate the amount of the Contractor’s entitlement to compensation for disruption and/or prolongation, the amount shall be calculated after Substantial Completion using – 39.3.1 the progress records and schedules produced under Clause 25.2, or (if none) – such records and schedules as, in its absolute discretion, the Valuer adopts for the purpose of this Clause 39.3. 23/04/2013 18
  • 19. BIM • Under CPC will the QS’s roll differ in Complex Contracts? a) In a current procurement environment (e.g. Traditional, Design and Build etc. ) b) In a BIM environment 23/04/2013 19
  • 20. Nick Lane Partner and Head of Construction, Olswang LLP Dispute resolution provisions and procedures
  • 22. Contact us… Francis Ho Senior Associate Olswang LLP T +44 20 7067 3505 E francis.ho@olswang.com Nick Lane Partner Olswang LLP T +44 20 7067 3548 E nick.lane@olswang.com Adam Constable QC Keating Chambers T +44 20 7544 2600 E aconstable@keatingchambers.com
  • 23. Contact us… Roy Pickavance Director, DAQS Ltd BSc, FRICS, FCIOB, FCIArb T +44 (0) 1949 829287 E arp@daqs.co.uk Keith Pickavance Executive Consultant Hill International T +44 (0) 207 618 1200 E keithpickavance@hillintl.com