SlideShare une entreprise Scribd logo
1  sur  11
Top Down Construction

Presentation by:
Gagan Goswami

1
Why Top Down Construction Required






Top Down Construction are commonly used in
congested areas. These can be installed in close
proximity to existing structure with minimal loss of
support to existing foundations. In addition,
construction dewatering is not required, so there is
no associated subsidence. Top Down Construction
are practically suited in the construction of deep
basements , Metro Railway Projects.
The “Top Down” method of construction is
designated to enable above ground construction
work to be carried out simultaneously with the
excavation of the basement resulting in significant
saving of time on a project.
Using Top Down Construction more Building and
Basement Area can use. Suitable for two or more
basement.
2
METHODOLOGY OF TOP DOWN
CONSTRUCTION







Diaphragm wall Installed in both side up to design
depth with coupler bars/dowel bars for different
level slabs as per alignment. if span is more
between diaphragm wall Barrete Piles can be use as
a intermediate Columns to support the slabs.
The soil is excavated just below roof slab level with
margin for P.C.C. thickness, if roof slab level is
more than 3 meter and span is more than
structural strut to be provided to support
diaphragm wall as per design.
Coupler bars/ Dowel bars to be exposed from
Diaphragm wall both end reinforcement to be
completed as per design.
3








R.C.C. slab to be cast with suitable size openings
for further Construction in suitable interval (around
40 t0 50 mtr) suit to site and for proper air
ventilation.
Coupler bars/Dowels bars provisions to be kept for
centre wall (In Tunnel case) and opening closing
after construction. 100/150 mm pipe (1 meter
C/C)opening to be kept in roof slab thickness for
concreting of center wall.
After Casting of slab, excavation to be continued
through opening provided with the help of Long
arm excavators/Crane and Bucket.
Small excavator to be lowered inside to feed soils
for long arm excavator.(Proper Lighting, Air
Circulation is must).
4










P.C.C. to be break by using small excavator and
excavation to be continued till base slab level.
Coupler bars to be exposed and base slab to be
cast as per design.
Center wall to be cast with dowel bars from Base
slab and finally connect with coupler bars from roof
slab.
Scaffolding and bottom form work to be fixed below
openings , coupler bars to be exposed and
reinforcement for opening to be completed and
concreting to be done.
After concreting of openings , water proofing if
required to be done than backfilling to be done in
layers and finally surface to be leveled and
reinstating the same.
5
Schematic section of Top Down
Construction

6
Schematic section of Top Down
Construction

7
Schematic section of Top Down
Construction

8
PROJECT PHOTOGRAPHS

Anchor Slab

9
PROJECT PHOTOGRAPHS

Anchor Slab

10
Contact Details
Gagan Goswami
 Cell-+919662506595
Address HERITAGE INFRASPACE INDIA PVT. LTD
 F-36,Sukh Shine Complex,
 Opposite to Himalaya Mall
 Sunrise park Road, Drive In ,
 Ahmedabad-380052, Gujarat ,India


E mail- info@diaphragmwallconstruction.com,gagangoswami@yahoo.co.in
Website- www.diaphragmwallconstruction.com

11

Contenu connexe

Tendances

Types of modern construction formwork
Types of modern construction formwork Types of modern construction formwork
Types of modern construction formwork adarshkaushik6
 
Details of RCC Building
Details of RCC BuildingDetails of RCC Building
Details of RCC Buildingppt_master
 
Repair to overcome low member strength
Repair to overcome low member strength Repair to overcome low member strength
Repair to overcome low member strength RAMPRASAD KUMAWAT
 
Formwork failures and remedial measures
Formwork failures and remedial measuresFormwork failures and remedial measures
Formwork failures and remedial measuressabnisajit
 
Techniques for various structural repair
Techniques for various  structural repairTechniques for various  structural repair
Techniques for various structural repairUdayram Patil
 
EXCAVATION FOR FOUNDATION - Methods & Temporary Earth Retaining Structures
EXCAVATION FOR FOUNDATION - Methods & Temporary Earth Retaining StructuresEXCAVATION FOR FOUNDATION - Methods & Temporary Earth Retaining Structures
EXCAVATION FOR FOUNDATION - Methods & Temporary Earth Retaining StructuresShivananda Roy
 
Pile Foundation for advanced construction equipments
Pile Foundation for advanced construction equipmentsPile Foundation for advanced construction equipments
Pile Foundation for advanced construction equipmentsNagma Modi
 
prefabricated Structures
prefabricated Structuresprefabricated Structures
prefabricated StructuresBoopathi Raja
 
formwork centering and scaffolding by khalid
formwork centering and scaffolding by khalid formwork centering and scaffolding by khalid
formwork centering and scaffolding by khalid shaikh khalid
 
Design principles in prefabricated structures unit iii ce6016 pfs
Design principles in prefabricated structures unit iii   ce6016 pfsDesign principles in prefabricated structures unit iii   ce6016 pfs
Design principles in prefabricated structures unit iii ce6016 pfsPrakash Kumar Sekar
 
building defects & remidies
building  defects & remidiesbuilding  defects & remidies
building defects & remidiesKirtika Gupta
 

Tendances (20)

Types of modern construction formwork
Types of modern construction formwork Types of modern construction formwork
Types of modern construction formwork
 
Top down construction
Top down constructionTop down construction
Top down construction
 
Joints in concrete
Joints in concreteJoints in concrete
Joints in concrete
 
Details of RCC Building
Details of RCC BuildingDetails of RCC Building
Details of RCC Building
 
Shuttering (Formwork)
Shuttering (Formwork)Shuttering (Formwork)
Shuttering (Formwork)
 
Formwork
FormworkFormwork
Formwork
 
Mivan shuttering
Mivan shutteringMivan shuttering
Mivan shuttering
 
Repair to overcome low member strength
Repair to overcome low member strength Repair to overcome low member strength
Repair to overcome low member strength
 
Underpinning
UnderpinningUnderpinning
Underpinning
 
Formwork failures and remedial measures
Formwork failures and remedial measuresFormwork failures and remedial measures
Formwork failures and remedial measures
 
Techniques for various structural repair
Techniques for various  structural repairTechniques for various  structural repair
Techniques for various structural repair
 
EXCAVATION FOR FOUNDATION - Methods & Temporary Earth Retaining Structures
EXCAVATION FOR FOUNDATION - Methods & Temporary Earth Retaining StructuresEXCAVATION FOR FOUNDATION - Methods & Temporary Earth Retaining Structures
EXCAVATION FOR FOUNDATION - Methods & Temporary Earth Retaining Structures
 
Pile foundation ppt
Pile foundation pptPile foundation ppt
Pile foundation ppt
 
Pile Foundation for advanced construction equipments
Pile Foundation for advanced construction equipmentsPile Foundation for advanced construction equipments
Pile Foundation for advanced construction equipments
 
prefabricated Structures
prefabricated Structuresprefabricated Structures
prefabricated Structures
 
formwork centering and scaffolding by khalid
formwork centering and scaffolding by khalid formwork centering and scaffolding by khalid
formwork centering and scaffolding by khalid
 
Design principles in prefabricated structures unit iii ce6016 pfs
Design principles in prefabricated structures unit iii   ce6016 pfsDesign principles in prefabricated structures unit iii   ce6016 pfs
Design principles in prefabricated structures unit iii ce6016 pfs
 
Retaining Walls
Retaining WallsRetaining Walls
Retaining Walls
 
Underpinning
UnderpinningUnderpinning
Underpinning
 
building defects & remidies
building  defects & remidiesbuilding  defects & remidies
building defects & remidies
 

En vedette

Top down construction by Sai Towers P Ltd.
Top down construction by Sai Towers P Ltd.Top down construction by Sai Towers P Ltd.
Top down construction by Sai Towers P Ltd.Sai Towers P Ltd.
 
Practices in Planning, Design and Construction of Head Race Tunnel of a Hydro...
Practices in Planning, Design and Construction of Head Race Tunnel of a Hydro...Practices in Planning, Design and Construction of Head Race Tunnel of a Hydro...
Practices in Planning, Design and Construction of Head Race Tunnel of a Hydro...Mohit Shukla
 
NEW AUSTRIAN TUNNELING METHOD
NEW AUSTRIAN TUNNELING METHODNEW AUSTRIAN TUNNELING METHOD
NEW AUSTRIAN TUNNELING METHODADIL BIN AYOUB
 
My publication Tunnels and Tunnelling magazine
My publication Tunnels and Tunnelling magazineMy publication Tunnels and Tunnelling magazine
My publication Tunnels and Tunnelling magazineFilipe Mello
 
Strukturas General Presentation (200ppi)
Strukturas General Presentation (200ppi)Strukturas General Presentation (200ppi)
Strukturas General Presentation (200ppi)Strukturas
 
Innovative Precast Bridge System
Innovative Precast Bridge SystemInnovative Precast Bridge System
Innovative Precast Bridge SystemAltosMarketing
 
Structural design of tunnel lining
Structural design of tunnel liningStructural design of tunnel lining
Structural design of tunnel liningMahesh Raj Bhatt
 
tunnelling scope, construction techniques and necessity
tunnelling scope, construction techniques and necessitytunnelling scope, construction techniques and necessity
tunnelling scope, construction techniques and necessityShashank Gaurav
 
Corrugated Steel Bridge and Tunnel Solutions
Corrugated Steel Bridge and Tunnel SolutionsCorrugated Steel Bridge and Tunnel Solutions
Corrugated Steel Bridge and Tunnel SolutionsCommunications Branding
 
Ecg533 rock-tunnel-engineering
Ecg533 rock-tunnel-engineeringEcg533 rock-tunnel-engineering
Ecg533 rock-tunnel-engineeringJunaida Wally
 
Areas related to circles - Area of sector and segment of a circle (Class 10 m...
Areas related to circles - Area of sector and segment of a circle (Class 10 m...Areas related to circles - Area of sector and segment of a circle (Class 10 m...
Areas related to circles - Area of sector and segment of a circle (Class 10 m...Let's Tute
 
tunnel boring machine
tunnel boring machinetunnel boring machine
tunnel boring machineNaquiakhter
 

En vedette (20)

Top down construction by Sai Towers P Ltd.
Top down construction by Sai Towers P Ltd.Top down construction by Sai Towers P Ltd.
Top down construction by Sai Towers P Ltd.
 
Deep excavation
Deep excavationDeep excavation
Deep excavation
 
Tunnel engg.2
Tunnel engg.2Tunnel engg.2
Tunnel engg.2
 
Diaphragm Wall Presentation By Gagan
Diaphragm Wall Presentation By GaganDiaphragm Wall Presentation By Gagan
Diaphragm Wall Presentation By Gagan
 
Guidelines
GuidelinesGuidelines
Guidelines
 
Bridges precast
Bridges precastBridges precast
Bridges precast
 
Practices in Planning, Design and Construction of Head Race Tunnel of a Hydro...
Practices in Planning, Design and Construction of Head Race Tunnel of a Hydro...Practices in Planning, Design and Construction of Head Race Tunnel of a Hydro...
Practices in Planning, Design and Construction of Head Race Tunnel of a Hydro...
 
Tunneling
Tunneling  Tunneling
Tunneling
 
Bridge
BridgeBridge
Bridge
 
NEW AUSTRIAN TUNNELING METHOD
NEW AUSTRIAN TUNNELING METHODNEW AUSTRIAN TUNNELING METHOD
NEW AUSTRIAN TUNNELING METHOD
 
Precast segmental concrete bridges a
Precast segmental concrete bridges aPrecast segmental concrete bridges a
Precast segmental concrete bridges a
 
My publication Tunnels and Tunnelling magazine
My publication Tunnels and Tunnelling magazineMy publication Tunnels and Tunnelling magazine
My publication Tunnels and Tunnelling magazine
 
Strukturas General Presentation (200ppi)
Strukturas General Presentation (200ppi)Strukturas General Presentation (200ppi)
Strukturas General Presentation (200ppi)
 
Innovative Precast Bridge System
Innovative Precast Bridge SystemInnovative Precast Bridge System
Innovative Precast Bridge System
 
Structural design of tunnel lining
Structural design of tunnel liningStructural design of tunnel lining
Structural design of tunnel lining
 
tunnelling scope, construction techniques and necessity
tunnelling scope, construction techniques and necessitytunnelling scope, construction techniques and necessity
tunnelling scope, construction techniques and necessity
 
Corrugated Steel Bridge and Tunnel Solutions
Corrugated Steel Bridge and Tunnel SolutionsCorrugated Steel Bridge and Tunnel Solutions
Corrugated Steel Bridge and Tunnel Solutions
 
Ecg533 rock-tunnel-engineering
Ecg533 rock-tunnel-engineeringEcg533 rock-tunnel-engineering
Ecg533 rock-tunnel-engineering
 
Areas related to circles - Area of sector and segment of a circle (Class 10 m...
Areas related to circles - Area of sector and segment of a circle (Class 10 m...Areas related to circles - Area of sector and segment of a circle (Class 10 m...
Areas related to circles - Area of sector and segment of a circle (Class 10 m...
 
tunnel boring machine
tunnel boring machinetunnel boring machine
tunnel boring machine
 

Similaire à Top down construction presentation

bulding foundation for costruction (6).ppt
bulding foundation for costruction (6).pptbulding foundation for costruction (6).ppt
bulding foundation for costruction (6).pptAbdulwalimusemohamed
 
Tutor cavity wall construction .ppt 1
Tutor cavity wall construction .ppt 1Tutor cavity wall construction .ppt 1
Tutor cavity wall construction .ppt 1Luke D'Arcy
 
Construction Technology Essay Sample Harvard
Construction Technology Essay Sample HarvardConstruction Technology Essay Sample Harvard
Construction Technology Essay Sample HarvardWriters Per Hour
 
Floors, roofs, shoring and underpinning.pptx
Floors, roofs, shoring and underpinning.pptxFloors, roofs, shoring and underpinning.pptx
Floors, roofs, shoring and underpinning.pptxAraniProbha1
 
Underpinning presentation chakamba
Underpinning presentation  chakambaUnderpinning presentation  chakamba
Underpinning presentation chakambaJohn Chakamba
 
Basement construction report
Basement construction reportBasement construction report
Basement construction reportANKITAARORA85
 
Diaphragm walls
Diaphragm wallsDiaphragm walls
Diaphragm wallsNguyen Bao
 
Btech compile 6 oct 4am
Btech compile 6 oct 4amBtech compile 6 oct 4am
Btech compile 6 oct 4amCeline Tan
 
Cut and cover_sections
Cut and cover_sectionsCut and cover_sections
Cut and cover_sectionsjuwes
 
Construction Sequence.pptx
Construction Sequence.pptxConstruction Sequence.pptx
Construction Sequence.pptxssuser480182
 
Lesson 3 Floor screeds _suspended floors.pptx
Lesson 3 Floor screeds _suspended floors.pptxLesson 3 Floor screeds _suspended floors.pptx
Lesson 3 Floor screeds _suspended floors.pptxsydneyaugust1
 
Soldier Bored and Diaphragm
Soldier Bored and DiaphragmSoldier Bored and Diaphragm
Soldier Bored and DiaphragmYingHongKang
 
Rehabilitation and strengthening of existing structures
Rehabilitation and strengthening of existing structuresRehabilitation and strengthening of existing structures
Rehabilitation and strengthening of existing structuresShahrukh Niaz
 
Visual Dictionary - Soffit
Visual Dictionary - SoffitVisual Dictionary - Soffit
Visual Dictionary - SoffitSoffit
 
Rehabilitation of foundation
Rehabilitation of foundationRehabilitation of foundation
Rehabilitation of foundationABIRAMI G
 

Similaire à Top down construction presentation (20)

bulding foundation for costruction (6).ppt
bulding foundation for costruction (6).pptbulding foundation for costruction (6).ppt
bulding foundation for costruction (6).ppt
 
Eport work copy pdf
Eport work copy pdfEport work copy pdf
Eport work copy pdf
 
Tutor cavity wall construction .ppt 1
Tutor cavity wall construction .ppt 1Tutor cavity wall construction .ppt 1
Tutor cavity wall construction .ppt 1
 
Construction Technology Essay Sample Harvard
Construction Technology Essay Sample HarvardConstruction Technology Essay Sample Harvard
Construction Technology Essay Sample Harvard
 
Floors, roofs, shoring and underpinning.pptx
Floors, roofs, shoring and underpinning.pptxFloors, roofs, shoring and underpinning.pptx
Floors, roofs, shoring and underpinning.pptx
 
Underpinning presentation chakamba
Underpinning presentation  chakambaUnderpinning presentation  chakamba
Underpinning presentation chakamba
 
Floors
FloorsFloors
Floors
 
Basement construction report
Basement construction reportBasement construction report
Basement construction report
 
Diaphragm walls
Diaphragm wallsDiaphragm walls
Diaphragm walls
 
Btech compile 6 oct 4am
Btech compile 6 oct 4amBtech compile 6 oct 4am
Btech compile 6 oct 4am
 
Cut and cover_sections
Cut and cover_sectionsCut and cover_sections
Cut and cover_sections
 
Construction Sequence.pptx
Construction Sequence.pptxConstruction Sequence.pptx
Construction Sequence.pptx
 
pile wall
pile wallpile wall
pile wall
 
Lesson 3 Floor screeds _suspended floors.pptx
Lesson 3 Floor screeds _suspended floors.pptxLesson 3 Floor screeds _suspended floors.pptx
Lesson 3 Floor screeds _suspended floors.pptx
 
Soldier Bored and Diaphragm
Soldier Bored and DiaphragmSoldier Bored and Diaphragm
Soldier Bored and Diaphragm
 
1.2 Diaphragm walls.pptx
1.2 Diaphragm walls.pptx1.2 Diaphragm walls.pptx
1.2 Diaphragm walls.pptx
 
Rehabilitation and strengthening of existing structures
Rehabilitation and strengthening of existing structuresRehabilitation and strengthening of existing structures
Rehabilitation and strengthening of existing structures
 
Deep excavations
Deep excavationsDeep excavations
Deep excavations
 
Visual Dictionary - Soffit
Visual Dictionary - SoffitVisual Dictionary - Soffit
Visual Dictionary - Soffit
 
Rehabilitation of foundation
Rehabilitation of foundationRehabilitation of foundation
Rehabilitation of foundation
 

Dernier

Transcript: New from BookNet Canada for 2024: Loan Stars - Tech Forum 2024
Transcript: New from BookNet Canada for 2024: Loan Stars - Tech Forum 2024Transcript: New from BookNet Canada for 2024: Loan Stars - Tech Forum 2024
Transcript: New from BookNet Canada for 2024: Loan Stars - Tech Forum 2024BookNet Canada
 
Assure Ecommerce and Retail Operations Uptime with ThousandEyes
Assure Ecommerce and Retail Operations Uptime with ThousandEyesAssure Ecommerce and Retail Operations Uptime with ThousandEyes
Assure Ecommerce and Retail Operations Uptime with ThousandEyesThousandEyes
 
What is DBT - The Ultimate Data Build Tool.pdf
What is DBT - The Ultimate Data Build Tool.pdfWhat is DBT - The Ultimate Data Build Tool.pdf
What is DBT - The Ultimate Data Build Tool.pdfMounikaPolabathina
 
Merck Moving Beyond Passwords: FIDO Paris Seminar.pptx
Merck Moving Beyond Passwords: FIDO Paris Seminar.pptxMerck Moving Beyond Passwords: FIDO Paris Seminar.pptx
Merck Moving Beyond Passwords: FIDO Paris Seminar.pptxLoriGlavin3
 
Genislab builds better products and faster go-to-market with Lean project man...
Genislab builds better products and faster go-to-market with Lean project man...Genislab builds better products and faster go-to-market with Lean project man...
Genislab builds better products and faster go-to-market with Lean project man...Farhan Tariq
 
Decarbonising Buildings: Making a net-zero built environment a reality
Decarbonising Buildings: Making a net-zero built environment a realityDecarbonising Buildings: Making a net-zero built environment a reality
Decarbonising Buildings: Making a net-zero built environment a realityIES VE
 
Connecting the Dots for Information Discovery.pdf
Connecting the Dots for Information Discovery.pdfConnecting the Dots for Information Discovery.pdf
Connecting the Dots for Information Discovery.pdfNeo4j
 
Long journey of Ruby standard library at RubyConf AU 2024
Long journey of Ruby standard library at RubyConf AU 2024Long journey of Ruby standard library at RubyConf AU 2024
Long journey of Ruby standard library at RubyConf AU 2024Hiroshi SHIBATA
 
TrustArc Webinar - How to Build Consumer Trust Through Data Privacy
TrustArc Webinar - How to Build Consumer Trust Through Data PrivacyTrustArc Webinar - How to Build Consumer Trust Through Data Privacy
TrustArc Webinar - How to Build Consumer Trust Through Data PrivacyTrustArc
 
The Role of FIDO in a Cyber Secure Netherlands: FIDO Paris Seminar.pptx
The Role of FIDO in a Cyber Secure Netherlands: FIDO Paris Seminar.pptxThe Role of FIDO in a Cyber Secure Netherlands: FIDO Paris Seminar.pptx
The Role of FIDO in a Cyber Secure Netherlands: FIDO Paris Seminar.pptxLoriGlavin3
 
Testing tools and AI - ideas what to try with some tool examples
Testing tools and AI - ideas what to try with some tool examplesTesting tools and AI - ideas what to try with some tool examples
Testing tools and AI - ideas what to try with some tool examplesKari Kakkonen
 
Potential of AI (Generative AI) in Business: Learnings and Insights
Potential of AI (Generative AI) in Business: Learnings and InsightsPotential of AI (Generative AI) in Business: Learnings and Insights
Potential of AI (Generative AI) in Business: Learnings and InsightsRavi Sanghani
 
How to Effectively Monitor SD-WAN and SASE Environments with ThousandEyes
How to Effectively Monitor SD-WAN and SASE Environments with ThousandEyesHow to Effectively Monitor SD-WAN and SASE Environments with ThousandEyes
How to Effectively Monitor SD-WAN and SASE Environments with ThousandEyesThousandEyes
 
Data governance with Unity Catalog Presentation
Data governance with Unity Catalog PresentationData governance with Unity Catalog Presentation
Data governance with Unity Catalog PresentationKnoldus Inc.
 
Passkey Providers and Enabling Portability: FIDO Paris Seminar.pptx
Passkey Providers and Enabling Portability: FIDO Paris Seminar.pptxPasskey Providers and Enabling Portability: FIDO Paris Seminar.pptx
Passkey Providers and Enabling Portability: FIDO Paris Seminar.pptxLoriGlavin3
 
From Family Reminiscence to Scholarly Archive .
From Family Reminiscence to Scholarly Archive .From Family Reminiscence to Scholarly Archive .
From Family Reminiscence to Scholarly Archive .Alan Dix
 
Manual 508 Accessibility Compliance Audit
Manual 508 Accessibility Compliance AuditManual 508 Accessibility Compliance Audit
Manual 508 Accessibility Compliance AuditSkynet Technologies
 
Modern Roaming for Notes and Nomad – Cheaper Faster Better Stronger
Modern Roaming for Notes and Nomad – Cheaper Faster Better StrongerModern Roaming for Notes and Nomad – Cheaper Faster Better Stronger
Modern Roaming for Notes and Nomad – Cheaper Faster Better Strongerpanagenda
 
The Future Roadmap for the Composable Data Stack - Wes McKinney - Data Counci...
The Future Roadmap for the Composable Data Stack - Wes McKinney - Data Counci...The Future Roadmap for the Composable Data Stack - Wes McKinney - Data Counci...
The Future Roadmap for the Composable Data Stack - Wes McKinney - Data Counci...Wes McKinney
 
The State of Passkeys with FIDO Alliance.pptx
The State of Passkeys with FIDO Alliance.pptxThe State of Passkeys with FIDO Alliance.pptx
The State of Passkeys with FIDO Alliance.pptxLoriGlavin3
 

Dernier (20)

Transcript: New from BookNet Canada for 2024: Loan Stars - Tech Forum 2024
Transcript: New from BookNet Canada for 2024: Loan Stars - Tech Forum 2024Transcript: New from BookNet Canada for 2024: Loan Stars - Tech Forum 2024
Transcript: New from BookNet Canada for 2024: Loan Stars - Tech Forum 2024
 
Assure Ecommerce and Retail Operations Uptime with ThousandEyes
Assure Ecommerce and Retail Operations Uptime with ThousandEyesAssure Ecommerce and Retail Operations Uptime with ThousandEyes
Assure Ecommerce and Retail Operations Uptime with ThousandEyes
 
What is DBT - The Ultimate Data Build Tool.pdf
What is DBT - The Ultimate Data Build Tool.pdfWhat is DBT - The Ultimate Data Build Tool.pdf
What is DBT - The Ultimate Data Build Tool.pdf
 
Merck Moving Beyond Passwords: FIDO Paris Seminar.pptx
Merck Moving Beyond Passwords: FIDO Paris Seminar.pptxMerck Moving Beyond Passwords: FIDO Paris Seminar.pptx
Merck Moving Beyond Passwords: FIDO Paris Seminar.pptx
 
Genislab builds better products and faster go-to-market with Lean project man...
Genislab builds better products and faster go-to-market with Lean project man...Genislab builds better products and faster go-to-market with Lean project man...
Genislab builds better products and faster go-to-market with Lean project man...
 
Decarbonising Buildings: Making a net-zero built environment a reality
Decarbonising Buildings: Making a net-zero built environment a realityDecarbonising Buildings: Making a net-zero built environment a reality
Decarbonising Buildings: Making a net-zero built environment a reality
 
Connecting the Dots for Information Discovery.pdf
Connecting the Dots for Information Discovery.pdfConnecting the Dots for Information Discovery.pdf
Connecting the Dots for Information Discovery.pdf
 
Long journey of Ruby standard library at RubyConf AU 2024
Long journey of Ruby standard library at RubyConf AU 2024Long journey of Ruby standard library at RubyConf AU 2024
Long journey of Ruby standard library at RubyConf AU 2024
 
TrustArc Webinar - How to Build Consumer Trust Through Data Privacy
TrustArc Webinar - How to Build Consumer Trust Through Data PrivacyTrustArc Webinar - How to Build Consumer Trust Through Data Privacy
TrustArc Webinar - How to Build Consumer Trust Through Data Privacy
 
The Role of FIDO in a Cyber Secure Netherlands: FIDO Paris Seminar.pptx
The Role of FIDO in a Cyber Secure Netherlands: FIDO Paris Seminar.pptxThe Role of FIDO in a Cyber Secure Netherlands: FIDO Paris Seminar.pptx
The Role of FIDO in a Cyber Secure Netherlands: FIDO Paris Seminar.pptx
 
Testing tools and AI - ideas what to try with some tool examples
Testing tools and AI - ideas what to try with some tool examplesTesting tools and AI - ideas what to try with some tool examples
Testing tools and AI - ideas what to try with some tool examples
 
Potential of AI (Generative AI) in Business: Learnings and Insights
Potential of AI (Generative AI) in Business: Learnings and InsightsPotential of AI (Generative AI) in Business: Learnings and Insights
Potential of AI (Generative AI) in Business: Learnings and Insights
 
How to Effectively Monitor SD-WAN and SASE Environments with ThousandEyes
How to Effectively Monitor SD-WAN and SASE Environments with ThousandEyesHow to Effectively Monitor SD-WAN and SASE Environments with ThousandEyes
How to Effectively Monitor SD-WAN and SASE Environments with ThousandEyes
 
Data governance with Unity Catalog Presentation
Data governance with Unity Catalog PresentationData governance with Unity Catalog Presentation
Data governance with Unity Catalog Presentation
 
Passkey Providers and Enabling Portability: FIDO Paris Seminar.pptx
Passkey Providers and Enabling Portability: FIDO Paris Seminar.pptxPasskey Providers and Enabling Portability: FIDO Paris Seminar.pptx
Passkey Providers and Enabling Portability: FIDO Paris Seminar.pptx
 
From Family Reminiscence to Scholarly Archive .
From Family Reminiscence to Scholarly Archive .From Family Reminiscence to Scholarly Archive .
From Family Reminiscence to Scholarly Archive .
 
Manual 508 Accessibility Compliance Audit
Manual 508 Accessibility Compliance AuditManual 508 Accessibility Compliance Audit
Manual 508 Accessibility Compliance Audit
 
Modern Roaming for Notes and Nomad – Cheaper Faster Better Stronger
Modern Roaming for Notes and Nomad – Cheaper Faster Better StrongerModern Roaming for Notes and Nomad – Cheaper Faster Better Stronger
Modern Roaming for Notes and Nomad – Cheaper Faster Better Stronger
 
The Future Roadmap for the Composable Data Stack - Wes McKinney - Data Counci...
The Future Roadmap for the Composable Data Stack - Wes McKinney - Data Counci...The Future Roadmap for the Composable Data Stack - Wes McKinney - Data Counci...
The Future Roadmap for the Composable Data Stack - Wes McKinney - Data Counci...
 
The State of Passkeys with FIDO Alliance.pptx
The State of Passkeys with FIDO Alliance.pptxThe State of Passkeys with FIDO Alliance.pptx
The State of Passkeys with FIDO Alliance.pptx
 

Top down construction presentation

  • 2. Why Top Down Construction Required    Top Down Construction are commonly used in congested areas. These can be installed in close proximity to existing structure with minimal loss of support to existing foundations. In addition, construction dewatering is not required, so there is no associated subsidence. Top Down Construction are practically suited in the construction of deep basements , Metro Railway Projects. The “Top Down” method of construction is designated to enable above ground construction work to be carried out simultaneously with the excavation of the basement resulting in significant saving of time on a project. Using Top Down Construction more Building and Basement Area can use. Suitable for two or more basement. 2
  • 3. METHODOLOGY OF TOP DOWN CONSTRUCTION    Diaphragm wall Installed in both side up to design depth with coupler bars/dowel bars for different level slabs as per alignment. if span is more between diaphragm wall Barrete Piles can be use as a intermediate Columns to support the slabs. The soil is excavated just below roof slab level with margin for P.C.C. thickness, if roof slab level is more than 3 meter and span is more than structural strut to be provided to support diaphragm wall as per design. Coupler bars/ Dowel bars to be exposed from Diaphragm wall both end reinforcement to be completed as per design. 3
  • 4.     R.C.C. slab to be cast with suitable size openings for further Construction in suitable interval (around 40 t0 50 mtr) suit to site and for proper air ventilation. Coupler bars/Dowels bars provisions to be kept for centre wall (In Tunnel case) and opening closing after construction. 100/150 mm pipe (1 meter C/C)opening to be kept in roof slab thickness for concreting of center wall. After Casting of slab, excavation to be continued through opening provided with the help of Long arm excavators/Crane and Bucket. Small excavator to be lowered inside to feed soils for long arm excavator.(Proper Lighting, Air Circulation is must). 4
  • 5.      P.C.C. to be break by using small excavator and excavation to be continued till base slab level. Coupler bars to be exposed and base slab to be cast as per design. Center wall to be cast with dowel bars from Base slab and finally connect with coupler bars from roof slab. Scaffolding and bottom form work to be fixed below openings , coupler bars to be exposed and reinforcement for opening to be completed and concreting to be done. After concreting of openings , water proofing if required to be done than backfilling to be done in layers and finally surface to be leveled and reinstating the same. 5
  • 6. Schematic section of Top Down Construction 6
  • 7. Schematic section of Top Down Construction 7
  • 8. Schematic section of Top Down Construction 8
  • 11. Contact Details Gagan Goswami  Cell-+919662506595 Address HERITAGE INFRASPACE INDIA PVT. LTD  F-36,Sukh Shine Complex,  Opposite to Himalaya Mall  Sunrise park Road, Drive In ,  Ahmedabad-380052, Gujarat ,India  E mail- info@diaphragmwallconstruction.com,gagangoswami@yahoo.co.in Website- www.diaphragmwallconstruction.com 11