SlideShare une entreprise Scribd logo
1  sur  20
Télécharger pour lire hors ligne
Earned Value
         in
       Five
    Easy Pieces
Not that Earned Value can be
 made that easy, but this is
the start of getting our mind
  around the concepts of
    project performance
       measurement

                            1
1.   Using a credible schedule, define the planned value of the work
2.   Measure the Physical % Complete for each period of performance
3.   Calculate Earned Value = Planned Value x Physical % Complete
4.   Using the Earned Value variables ,calculate the performance indices
5.   With the performance indices take corrective actions
                                                                           2
1




 Using a credible
schedule, define
   the planned
value of the work



                   3
1




      Create Work
    Packages for the
     activities that
    produce physical
       outcomes


I                      4
1




    Define the planned
     value (PV)(BCWS)
     spreads for each
       Work Package



I                        5
Measure Physical Percent Complete of Work
               Package Outcomes




2
                                                6
Define 0/100 or
     50/50 activities
    within each Work
        Package.
      You’re either
    done or not done.
       There is no
    “partial” done for
    a Work Package.


2
                         7
2



      Define Apportioned
        Milestones that
         describe the
          incremental
     progress of the Work
       Package in units
       meaningful to the
           customer



II                         8
2


     Use evidentiary materials
      for each measurement.
       These are the only
      measures of progress.
     Not the passage of time
      or the consumption of
            resources.
          “Show Me the
           Outcomes”


II                               9
Calculate the Earned Value   3




                                 10
EV = PV  Physical Percent Complete


    The Value that is Earned - the Earned Value
    - is the percent of the Planned Value that
    was delivered at the end of the period of
    performance.
    The percentage assessment is always
    measured by some physical assessment,
    some evidence that this percentage was
    actually achieved
3
                                                  11
Using the Earned Value variables (BCWS, BCWP,
    ACWP), calculate Performance Indices




4
                                                12
The To Complete Performance Index (TCPI)




                   BAC  BCWP 
    TCPIEAC     
                   EAC  ACWP 


4
                                               13
The Independent Estimate At Completion (IEAC)


                    Probably as Good
EAC1  BAC CPI       as it Gets

EAC2  ACWPcum   BAC  BCWPcum  SPI
EAC3  ACWPcum   BAC  BCWPcum  SPI  CPI      Probably as Bad
                                                    as it Gets

EAC4  ACWPcum   BAC  BCWPcum  wt1  SPI  wt 2  CPI 
EAC5  ACWPcum   BAC  BCWPcum  CPI( period )




 4
                                                                       14
5



        With the
      performance
      indices‘, take
    corrective action
     for remaining
          work


V                      15
Earned Value must measure work
     performance within a pre-defined
     period of time – the period of
     performance

     At the end of a project, the Earned Value
     always equals the Planned Value – since all
     the work has been done.
     What is different is how long it took and how
     much money is cost.
     Earned Value bounds the time period to the
     Planned period



IV                                                   16
Failing to us discipline and
                                                     rigor can put you on the
                                                     beach. So remember…
                                                     A ship on the beach is a
                                                     lighthouse to the sea
                                                     – Dutch Proverb

   Inattention to budgetary responsibilities    Progress not monitored in a regular and
   Work authorization not always followed        consistent manner
   Budget and data reconciliation issues        Lack of vertical and horizontal traceability
   Lack of integrated management systems         (critical path)
   Baseline fluctuations and frequent           Not capturing and using cost and schedule
    replanting                                    data for corrective action
   Current period and retroactive changes       Lack of predictive variance analysis
   Improper use of management reserve           Lack of internal surveillance and controls
   Earned Value techniques not reflecting       Managerial actions not demonstrated
    actual accomplishments                        using Earned Value
   Untimely and unrealistic Latest Revised
    Estimates (LRE)
                                                                                             17
Are You Doing
                              Earned Value?
                           Do we know the value of
                            the planned work?
                           Have we bounded the
                            period of performance for
                            each work element?
                           Do we know how to
                            measure Physical Percent
                            Complete?



www.jack-nicholson.info
                                                    18
Earned Value is
                          fundamentally a
                          planning tool.
                          It will not “fix”
                          problems with
                          projects.
                          But it will make the
                          performance
                          problems visible in
                          analytical ways.



www.jack-nicholson.info
                                                 19
Glen B. Alleman
                                         Niwot Ridge Consulting
                                        4347 Pebble Beach Drive
                                          Niwot, Colorado 80503
                                               303.241.9633
                                      glen.alleman@niwotridge.com
                                    Performance Based Management(sm)
                                              Integrated Master Plan
                                           Integrated Master Schedule
                                       Earned Value Management Systems
                                                 Risk Management
                                            Proposal Support Services




Glen B. Alleman, Copyright © 2012                                        20/58

Contenu connexe

Tendances

Earned Value Reporting
Earned Value ReportingEarned Value Reporting
Earned Value Reportingcfreema7
 
Earned Value Analysis
Earned Value AnalysisEarned Value Analysis
Earned Value AnalysisSaqib Raza
 
Earning Value from Earned Value Management
Earning Value from Earned Value ManagementEarning Value from Earned Value Management
Earning Value from Earned Value ManagementGlen Alleman
 
Earned value
Earned valueEarned value
Earned valueOliver
 
Earned value analysis training
Earned value analysis trainingEarned value analysis training
Earned value analysis trainingPaul King
 
Earned value analysis for a construction project
Earned value analysis for a construction projectEarned value analysis for a construction project
Earned value analysis for a construction projectIAEME Publication
 
Earned value for pmp and pmi acp exam
Earned value for pmp and pmi acp examEarned value for pmp and pmi acp exam
Earned value for pmp and pmi acp examManish Purwar
 
Earned value Project Management (evpm)
Earned value Project Management (evpm)Earned value Project Management (evpm)
Earned value Project Management (evpm)Ejaz Bhatti
 
Earned value management for Beginners
Earned value management for Beginners Earned value management for Beginners
Earned value management for Beginners Shenin Hassan
 
Earned Value Management
Earned Value ManagementEarned Value Management
Earned Value ManagementMansoor Shoaib
 
EVM in MS Project
EVM in MS ProjectEVM in MS Project
EVM in MS Projectorsmoot
 
EVM of Project Management...
EVM of Project Management...EVM of Project Management...
EVM of Project Management...Fahad Ali
 
Project Management Earned Value
Project Management Earned ValueProject Management Earned Value
Project Management Earned Valueconstructioninside
 
Earned Value Management Essentials
Earned Value Management EssentialsEarned Value Management Essentials
Earned Value Management EssentialsGlen Alleman
 

Tendances (20)

Earned Value Reporting
Earned Value ReportingEarned Value Reporting
Earned Value Reporting
 
Earned Value Management
Earned Value ManagementEarned Value Management
Earned Value Management
 
Earned Value Analysis
Earned Value AnalysisEarned Value Analysis
Earned Value Analysis
 
Earning Value from Earned Value Management
Earning Value from Earned Value ManagementEarning Value from Earned Value Management
Earning Value from Earned Value Management
 
Projects Performance Analysis & Forecasting
Projects Performance Analysis & Forecasting Projects Performance Analysis & Forecasting
Projects Performance Analysis & Forecasting
 
Earned value
Earned valueEarned value
Earned value
 
Earned value analysis training
Earned value analysis trainingEarned value analysis training
Earned value analysis training
 
Earned value analysis for a construction project
Earned value analysis for a construction projectEarned value analysis for a construction project
Earned value analysis for a construction project
 
Earned value for pmp and pmi acp exam
Earned value for pmp and pmi acp examEarned value for pmp and pmi acp exam
Earned value for pmp and pmi acp exam
 
Earned value Project Management (evpm)
Earned value Project Management (evpm)Earned value Project Management (evpm)
Earned value Project Management (evpm)
 
Earned value management for Beginners
Earned value management for Beginners Earned value management for Beginners
Earned value management for Beginners
 
Project Control Process
Project Control ProcessProject Control Process
Project Control Process
 
Earned Value Management
Earned Value ManagementEarned Value Management
Earned Value Management
 
EVM in MS Project
EVM in MS ProjectEVM in MS Project
EVM in MS Project
 
EVM of Project Management...
EVM of Project Management...EVM of Project Management...
EVM of Project Management...
 
Project Management Earned Value
Project Management Earned ValueProject Management Earned Value
Project Management Earned Value
 
The Benefits of using Earned Value Management
The Benefits of using Earned Value ManagementThe Benefits of using Earned Value Management
The Benefits of using Earned Value Management
 
Earned Value Management Essentials
Earned Value Management EssentialsEarned Value Management Essentials
Earned Value Management Essentials
 
Learning pmp formulas the easy way
Learning pmp formulas the easy wayLearning pmp formulas the easy way
Learning pmp formulas the easy way
 
Earned Value Analysis
Earned Value AnalysisEarned Value Analysis
Earned Value Analysis
 

En vedette

A simple example of Earned Value Management (EVM) in action
A simple example of Earned Value Management (EVM) in actionA simple example of Earned Value Management (EVM) in action
A simple example of Earned Value Management (EVM) in actionPlanisware
 
Integrating Risk With Earned Value
Integrating Risk With Earned ValueIntegrating Risk With Earned Value
Integrating Risk With Earned ValueGlen Alleman
 
Forecasting cost and schedule performance
Forecasting cost and schedule performanceForecasting cost and schedule performance
Forecasting cost and schedule performanceGlen Alleman
 
Earned schedule v. Earned Value
Earned schedule v. Earned ValueEarned schedule v. Earned Value
Earned schedule v. Earned ValueGlen Alleman
 
Chapter 0 of Performance Based Project Management (sm)
Chapter 0 of Performance Based Project Management (sm)Chapter 0 of Performance Based Project Management (sm)
Chapter 0 of Performance Based Project Management (sm)Glen Alleman
 
Top habits of successful project managers brown bag (v3.2)
Top habits of successful project managers brown bag (v3.2)Top habits of successful project managers brown bag (v3.2)
Top habits of successful project managers brown bag (v3.2)Glen Alleman
 
Project Controls Expo 13th Nov 2013 - "From Cost Plan To Bid Evaluation To Co...
Project Controls Expo 13th Nov 2013 - "From Cost Plan To Bid Evaluation To Co...Project Controls Expo 13th Nov 2013 - "From Cost Plan To Bid Evaluation To Co...
Project Controls Expo 13th Nov 2013 - "From Cost Plan To Bid Evaluation To Co...Project Controls Expo
 

En vedette (12)

Comment mesurer l'avancement physique ?
Comment mesurer l'avancement physique ?Comment mesurer l'avancement physique ?
Comment mesurer l'avancement physique ?
 
Comment calculer la valeur acquise ?
Comment calculer la valeur acquise ?Comment calculer la valeur acquise ?
Comment calculer la valeur acquise ?
 
A simple example of Earned Value Management (EVM) in action
A simple example of Earned Value Management (EVM) in actionA simple example of Earned Value Management (EVM) in action
A simple example of Earned Value Management (EVM) in action
 
Integrating Risk With Earned Value
Integrating Risk With Earned ValueIntegrating Risk With Earned Value
Integrating Risk With Earned Value
 
Earned Value
Earned ValueEarned Value
Earned Value
 
Earned Value fundamentals
Earned Value fundamentalsEarned Value fundamentals
Earned Value fundamentals
 
Forecasting cost and schedule performance
Forecasting cost and schedule performanceForecasting cost and schedule performance
Forecasting cost and schedule performance
 
Earned schedule v. Earned Value
Earned schedule v. Earned ValueEarned schedule v. Earned Value
Earned schedule v. Earned Value
 
Chapter 0 of Performance Based Project Management (sm)
Chapter 0 of Performance Based Project Management (sm)Chapter 0 of Performance Based Project Management (sm)
Chapter 0 of Performance Based Project Management (sm)
 
Top habits of successful project managers brown bag (v3.2)
Top habits of successful project managers brown bag (v3.2)Top habits of successful project managers brown bag (v3.2)
Top habits of successful project managers brown bag (v3.2)
 
Project Controls Expo 13th Nov 2013 - "From Cost Plan To Bid Evaluation To Co...
Project Controls Expo 13th Nov 2013 - "From Cost Plan To Bid Evaluation To Co...Project Controls Expo 13th Nov 2013 - "From Cost Plan To Bid Evaluation To Co...
Project Controls Expo 13th Nov 2013 - "From Cost Plan To Bid Evaluation To Co...
 
Back to basics - Earned Value Management for beginners webinar
Back to basics - Earned Value Management for beginners webinarBack to basics - Earned Value Management for beginners webinar
Back to basics - Earned Value Management for beginners webinar
 

Similaire à Earned value in five easy pieces

Improving project performance presentation
Improving project performance presentationImproving project performance presentation
Improving project performance presentationGlen Alleman
 
A gentle introduction to earned value management systems (neutral)
A gentle introduction to earned value management systems (neutral)A gentle introduction to earned value management systems (neutral)
A gentle introduction to earned value management systems (neutral)Glen Alleman
 
The simple problem of schedule performance indices
The simple problem of schedule performance indicesThe simple problem of schedule performance indices
The simple problem of schedule performance indicesGlen Alleman
 
Earned Value Management and Agile
Earned Value Management and AgileEarned Value Management and Agile
Earned Value Management and AgileGlen Alleman
 
Integrating Agile and Earned Value Management
Integrating Agile and Earned Value ManagementIntegrating Agile and Earned Value Management
Integrating Agile and Earned Value ManagementGlen Alleman
 
Establishing the performance measurement baseline (pmi northern utah)(v1)
Establishing the performance measurement baseline (pmi northern utah)(v1)Establishing the performance measurement baseline (pmi northern utah)(v1)
Establishing the performance measurement baseline (pmi northern utah)(v1)Glen Alleman
 
Successfully Integrating Agile and Earned Value
Successfully Integrating Agile and Earned ValueSuccessfully Integrating Agile and Earned Value
Successfully Integrating Agile and Earned ValueGlen Alleman
 
at ADAPT: AgileEVM Delivering Value within Constrained Systems
at ADAPT: AgileEVM Delivering Value within Constrained Systemsat ADAPT: AgileEVM Delivering Value within Constrained Systems
at ADAPT: AgileEVM Delivering Value within Constrained SystemsBrent Barton
 
2011 pmo symposium Bridging the Agile-to-PMO Communication Gap
2011 pmo symposium Bridging the Agile-to-PMO Communication Gap2011 pmo symposium Bridging the Agile-to-PMO Communication Gap
2011 pmo symposium Bridging the Agile-to-PMO Communication GapBrent Barton
 
The Intersection of Earned Value Management and Agile Software Development
The Intersection of Earned Value Management and Agile Software DevelopmentThe Intersection of Earned Value Management and Agile Software Development
The Intersection of Earned Value Management and Agile Software DevelopmentGlen Alleman
 
Project Monitoring and Control
Project Monitoring and ControlProject Monitoring and Control
Project Monitoring and Controlguy_davis
 
Law.richard
Law.richardLaw.richard
Law.richardNASAPMC
 
Earned Value Management and Agile Tips for Success
Earned Value Management and Agile Tips for Success Earned Value Management and Agile Tips for Success
Earned Value Management and Agile Tips for Success Brent Barton
 
Agile in an ANSI-748-C environment
Agile in an ANSI-748-C environmentAgile in an ANSI-748-C environment
Agile in an ANSI-748-C environmentGlen Alleman
 
Integrated Agile Software Development with Earned Value Management
Integrated Agile Software Development with Earned Value ManagementIntegrated Agile Software Development with Earned Value Management
Integrated Agile Software Development with Earned Value ManagementGlen Alleman
 
Building A Credible Measurement Baseline
Building A Credible Measurement BaselineBuilding A Credible Measurement Baseline
Building A Credible Measurement BaselineGlen Alleman
 
Vanessa.jeff
Vanessa.jeffVanessa.jeff
Vanessa.jeffNASAPMC
 

Similaire à Earned value in five easy pieces (20)

Improving project performance presentation
Improving project performance presentationImproving project performance presentation
Improving project performance presentation
 
A gentle introduction to earned value management systems (neutral)
A gentle introduction to earned value management systems (neutral)A gentle introduction to earned value management systems (neutral)
A gentle introduction to earned value management systems (neutral)
 
The simple problem of schedule performance indices
The simple problem of schedule performance indicesThe simple problem of schedule performance indices
The simple problem of schedule performance indices
 
Earned Value Management and Agile
Earned Value Management and AgileEarned Value Management and Agile
Earned Value Management and Agile
 
Integrating Agile and Earned Value Management
Integrating Agile and Earned Value ManagementIntegrating Agile and Earned Value Management
Integrating Agile and Earned Value Management
 
Establishing the performance measurement baseline (pmi northern utah)(v1)
Establishing the performance measurement baseline (pmi northern utah)(v1)Establishing the performance measurement baseline (pmi northern utah)(v1)
Establishing the performance measurement baseline (pmi northern utah)(v1)
 
EVMS Made Simple
EVMS Made SimpleEVMS Made Simple
EVMS Made Simple
 
Successfully Integrating Agile and Earned Value
Successfully Integrating Agile and Earned ValueSuccessfully Integrating Agile and Earned Value
Successfully Integrating Agile and Earned Value
 
at ADAPT: AgileEVM Delivering Value within Constrained Systems
at ADAPT: AgileEVM Delivering Value within Constrained Systemsat ADAPT: AgileEVM Delivering Value within Constrained Systems
at ADAPT: AgileEVM Delivering Value within Constrained Systems
 
2011 pmo symposium Bridging the Agile-to-PMO Communication Gap
2011 pmo symposium Bridging the Agile-to-PMO Communication Gap2011 pmo symposium Bridging the Agile-to-PMO Communication Gap
2011 pmo symposium Bridging the Agile-to-PMO Communication Gap
 
Earned value
Earned valueEarned value
Earned value
 
The Intersection of Earned Value Management and Agile Software Development
The Intersection of Earned Value Management and Agile Software DevelopmentThe Intersection of Earned Value Management and Agile Software Development
The Intersection of Earned Value Management and Agile Software Development
 
Project Monitoring and Control
Project Monitoring and ControlProject Monitoring and Control
Project Monitoring and Control
 
Law.richard
Law.richardLaw.richard
Law.richard
 
Earned Value Management and Agile Tips for Success
Earned Value Management and Agile Tips for Success Earned Value Management and Agile Tips for Success
Earned Value Management and Agile Tips for Success
 
PROJECT HEALTH MONITORING BY EARNED VALUE ANALYSIS
PROJECT HEALTH MONITORING BY EARNED VALUE ANALYSISPROJECT HEALTH MONITORING BY EARNED VALUE ANALYSIS
PROJECT HEALTH MONITORING BY EARNED VALUE ANALYSIS
 
Agile in an ANSI-748-C environment
Agile in an ANSI-748-C environmentAgile in an ANSI-748-C environment
Agile in an ANSI-748-C environment
 
Integrated Agile Software Development with Earned Value Management
Integrated Agile Software Development with Earned Value ManagementIntegrated Agile Software Development with Earned Value Management
Integrated Agile Software Development with Earned Value Management
 
Building A Credible Measurement Baseline
Building A Credible Measurement BaselineBuilding A Credible Measurement Baseline
Building A Credible Measurement Baseline
 
Vanessa.jeff
Vanessa.jeffVanessa.jeff
Vanessa.jeff
 

Plus de Glen Alleman

Managing risk with deliverables planning
Managing risk with deliverables planningManaging risk with deliverables planning
Managing risk with deliverables planningGlen Alleman
 
A Gentle Introduction to the IMP/IMS
A Gentle Introduction to the IMP/IMSA Gentle Introduction to the IMP/IMS
A Gentle Introduction to the IMP/IMSGlen Alleman
 
Increasing the Probability of Project Success
Increasing the Probability of Project SuccessIncreasing the Probability of Project Success
Increasing the Probability of Project SuccessGlen Alleman
 
Process Flow and Narrative for Agile+PPM
Process Flow and Narrative for Agile+PPMProcess Flow and Narrative for Agile+PPM
Process Flow and Narrative for Agile+PPMGlen Alleman
 
Practices of risk management
Practices of risk managementPractices of risk management
Practices of risk managementGlen Alleman
 
Principles of Risk Management
Principles of Risk ManagementPrinciples of Risk Management
Principles of Risk ManagementGlen Alleman
 
Deliverables Based Planning, PMBOK® and 5 Immutable Principles of Project Suc...
Deliverables Based Planning, PMBOK® and 5 Immutable Principles of Project Suc...Deliverables Based Planning, PMBOK® and 5 Immutable Principles of Project Suc...
Deliverables Based Planning, PMBOK® and 5 Immutable Principles of Project Suc...Glen Alleman
 
From Principles to Strategies for Systems Engineering
From Principles to Strategies for Systems EngineeringFrom Principles to Strategies for Systems Engineering
From Principles to Strategies for Systems EngineeringGlen Alleman
 
NAVAIR Integrated Master Schedule Guide guide
NAVAIR Integrated Master Schedule Guide guideNAVAIR Integrated Master Schedule Guide guide
NAVAIR Integrated Master Schedule Guide guideGlen Alleman
 
Building a Credible Performance Measurement Baseline
Building a Credible Performance Measurement BaselineBuilding a Credible Performance Measurement Baseline
Building a Credible Performance Measurement BaselineGlen Alleman
 
Integrated master plan methodology (v2)
Integrated master plan methodology (v2)Integrated master plan methodology (v2)
Integrated master plan methodology (v2)Glen Alleman
 
IMP / IMS Step by Step
IMP / IMS Step by StepIMP / IMS Step by Step
IMP / IMS Step by StepGlen Alleman
 
DHS - Using functions points to estimate agile development programs (v2)
DHS - Using functions points to estimate agile development programs (v2)DHS - Using functions points to estimate agile development programs (v2)
DHS - Using functions points to estimate agile development programs (v2)Glen Alleman
 
Making the impossible possible
Making the impossible possibleMaking the impossible possible
Making the impossible possibleGlen Alleman
 
Heliotropic Abundance
Heliotropic AbundanceHeliotropic Abundance
Heliotropic AbundanceGlen Alleman
 
Capabilities based planning
Capabilities based planningCapabilities based planning
Capabilities based planningGlen Alleman
 
Process Flow and Narrative for Agile
Process Flow and Narrative for AgileProcess Flow and Narrative for Agile
Process Flow and Narrative for AgileGlen Alleman
 
Building the Performance Measurement Baseline
Building the Performance Measurement BaselineBuilding the Performance Measurement Baseline
Building the Performance Measurement BaselineGlen Alleman
 
Program Management Office Lean Software Development and Six Sigma
Program Management Office Lean Software Development and Six SigmaProgram Management Office Lean Software Development and Six Sigma
Program Management Office Lean Software Development and Six SigmaGlen Alleman
 
Policy and Procedure Rollout
Policy and Procedure RolloutPolicy and Procedure Rollout
Policy and Procedure RolloutGlen Alleman
 

Plus de Glen Alleman (20)

Managing risk with deliverables planning
Managing risk with deliverables planningManaging risk with deliverables planning
Managing risk with deliverables planning
 
A Gentle Introduction to the IMP/IMS
A Gentle Introduction to the IMP/IMSA Gentle Introduction to the IMP/IMS
A Gentle Introduction to the IMP/IMS
 
Increasing the Probability of Project Success
Increasing the Probability of Project SuccessIncreasing the Probability of Project Success
Increasing the Probability of Project Success
 
Process Flow and Narrative for Agile+PPM
Process Flow and Narrative for Agile+PPMProcess Flow and Narrative for Agile+PPM
Process Flow and Narrative for Agile+PPM
 
Practices of risk management
Practices of risk managementPractices of risk management
Practices of risk management
 
Principles of Risk Management
Principles of Risk ManagementPrinciples of Risk Management
Principles of Risk Management
 
Deliverables Based Planning, PMBOK® and 5 Immutable Principles of Project Suc...
Deliverables Based Planning, PMBOK® and 5 Immutable Principles of Project Suc...Deliverables Based Planning, PMBOK® and 5 Immutable Principles of Project Suc...
Deliverables Based Planning, PMBOK® and 5 Immutable Principles of Project Suc...
 
From Principles to Strategies for Systems Engineering
From Principles to Strategies for Systems EngineeringFrom Principles to Strategies for Systems Engineering
From Principles to Strategies for Systems Engineering
 
NAVAIR Integrated Master Schedule Guide guide
NAVAIR Integrated Master Schedule Guide guideNAVAIR Integrated Master Schedule Guide guide
NAVAIR Integrated Master Schedule Guide guide
 
Building a Credible Performance Measurement Baseline
Building a Credible Performance Measurement BaselineBuilding a Credible Performance Measurement Baseline
Building a Credible Performance Measurement Baseline
 
Integrated master plan methodology (v2)
Integrated master plan methodology (v2)Integrated master plan methodology (v2)
Integrated master plan methodology (v2)
 
IMP / IMS Step by Step
IMP / IMS Step by StepIMP / IMS Step by Step
IMP / IMS Step by Step
 
DHS - Using functions points to estimate agile development programs (v2)
DHS - Using functions points to estimate agile development programs (v2)DHS - Using functions points to estimate agile development programs (v2)
DHS - Using functions points to estimate agile development programs (v2)
 
Making the impossible possible
Making the impossible possibleMaking the impossible possible
Making the impossible possible
 
Heliotropic Abundance
Heliotropic AbundanceHeliotropic Abundance
Heliotropic Abundance
 
Capabilities based planning
Capabilities based planningCapabilities based planning
Capabilities based planning
 
Process Flow and Narrative for Agile
Process Flow and Narrative for AgileProcess Flow and Narrative for Agile
Process Flow and Narrative for Agile
 
Building the Performance Measurement Baseline
Building the Performance Measurement BaselineBuilding the Performance Measurement Baseline
Building the Performance Measurement Baseline
 
Program Management Office Lean Software Development and Six Sigma
Program Management Office Lean Software Development and Six SigmaProgram Management Office Lean Software Development and Six Sigma
Program Management Office Lean Software Development and Six Sigma
 
Policy and Procedure Rollout
Policy and Procedure RolloutPolicy and Procedure Rollout
Policy and Procedure Rollout
 

Dernier

🐬 The future of MySQL is Postgres 🐘
🐬  The future of MySQL is Postgres   🐘🐬  The future of MySQL is Postgres   🐘
🐬 The future of MySQL is Postgres 🐘RTylerCroy
 
Apidays New York 2024 - Scaling API-first by Ian Reasor and Radu Cotescu, Adobe
Apidays New York 2024 - Scaling API-first by Ian Reasor and Radu Cotescu, AdobeApidays New York 2024 - Scaling API-first by Ian Reasor and Radu Cotescu, Adobe
Apidays New York 2024 - Scaling API-first by Ian Reasor and Radu Cotescu, Adobeapidays
 
Boost PC performance: How more available memory can improve productivity
Boost PC performance: How more available memory can improve productivityBoost PC performance: How more available memory can improve productivity
Boost PC performance: How more available memory can improve productivityPrincipled Technologies
 
Strategies for Unlocking Knowledge Management in Microsoft 365 in the Copilot...
Strategies for Unlocking Knowledge Management in Microsoft 365 in the Copilot...Strategies for Unlocking Knowledge Management in Microsoft 365 in the Copilot...
Strategies for Unlocking Knowledge Management in Microsoft 365 in the Copilot...Drew Madelung
 
MINDCTI Revenue Release Quarter One 2024
MINDCTI Revenue Release Quarter One 2024MINDCTI Revenue Release Quarter One 2024
MINDCTI Revenue Release Quarter One 2024MIND CTI
 
Cloud Frontiers: A Deep Dive into Serverless Spatial Data and FME
Cloud Frontiers:  A Deep Dive into Serverless Spatial Data and FMECloud Frontiers:  A Deep Dive into Serverless Spatial Data and FME
Cloud Frontiers: A Deep Dive into Serverless Spatial Data and FMESafe Software
 
Scaling API-first – The story of a global engineering organization
Scaling API-first – The story of a global engineering organizationScaling API-first – The story of a global engineering organization
Scaling API-first – The story of a global engineering organizationRadu Cotescu
 
Strategies for Landing an Oracle DBA Job as a Fresher
Strategies for Landing an Oracle DBA Job as a FresherStrategies for Landing an Oracle DBA Job as a Fresher
Strategies for Landing an Oracle DBA Job as a FresherRemote DBA Services
 
Apidays New York 2024 - The value of a flexible API Management solution for O...
Apidays New York 2024 - The value of a flexible API Management solution for O...Apidays New York 2024 - The value of a flexible API Management solution for O...
Apidays New York 2024 - The value of a flexible API Management solution for O...apidays
 
Artificial Intelligence: Facts and Myths
Artificial Intelligence: Facts and MythsArtificial Intelligence: Facts and Myths
Artificial Intelligence: Facts and MythsJoaquim Jorge
 
The 7 Things I Know About Cyber Security After 25 Years | April 2024
The 7 Things I Know About Cyber Security After 25 Years | April 2024The 7 Things I Know About Cyber Security After 25 Years | April 2024
The 7 Things I Know About Cyber Security After 25 Years | April 2024Rafal Los
 
Deploy with confidence: VMware Cloud Foundation 5.1 on next gen Dell PowerEdg...
Deploy with confidence: VMware Cloud Foundation 5.1 on next gen Dell PowerEdg...Deploy with confidence: VMware Cloud Foundation 5.1 on next gen Dell PowerEdg...
Deploy with confidence: VMware Cloud Foundation 5.1 on next gen Dell PowerEdg...Principled Technologies
 
Tata AIG General Insurance Company - Insurer Innovation Award 2024
Tata AIG General Insurance Company - Insurer Innovation Award 2024Tata AIG General Insurance Company - Insurer Innovation Award 2024
Tata AIG General Insurance Company - Insurer Innovation Award 2024The Digital Insurer
 
Real Time Object Detection Using Open CV
Real Time Object Detection Using Open CVReal Time Object Detection Using Open CV
Real Time Object Detection Using Open CVKhem
 
Axa Assurance Maroc - Insurer Innovation Award 2024
Axa Assurance Maroc - Insurer Innovation Award 2024Axa Assurance Maroc - Insurer Innovation Award 2024
Axa Assurance Maroc - Insurer Innovation Award 2024The Digital Insurer
 
A Year of the Servo Reboot: Where Are We Now?
A Year of the Servo Reboot: Where Are We Now?A Year of the Servo Reboot: Where Are We Now?
A Year of the Servo Reboot: Where Are We Now?Igalia
 
AWS Community Day CPH - Three problems of Terraform
AWS Community Day CPH - Three problems of TerraformAWS Community Day CPH - Three problems of Terraform
AWS Community Day CPH - Three problems of TerraformAndrey Devyatkin
 
2024: Domino Containers - The Next Step. News from the Domino Container commu...
2024: Domino Containers - The Next Step. News from the Domino Container commu...2024: Domino Containers - The Next Step. News from the Domino Container commu...
2024: Domino Containers - The Next Step. News from the Domino Container commu...Martijn de Jong
 
Polkadot JAM Slides - Token2049 - By Dr. Gavin Wood
Polkadot JAM Slides - Token2049 - By Dr. Gavin WoodPolkadot JAM Slides - Token2049 - By Dr. Gavin Wood
Polkadot JAM Slides - Token2049 - By Dr. Gavin WoodJuan lago vázquez
 

Dernier (20)

🐬 The future of MySQL is Postgres 🐘
🐬  The future of MySQL is Postgres   🐘🐬  The future of MySQL is Postgres   🐘
🐬 The future of MySQL is Postgres 🐘
 
Apidays New York 2024 - Scaling API-first by Ian Reasor and Radu Cotescu, Adobe
Apidays New York 2024 - Scaling API-first by Ian Reasor and Radu Cotescu, AdobeApidays New York 2024 - Scaling API-first by Ian Reasor and Radu Cotescu, Adobe
Apidays New York 2024 - Scaling API-first by Ian Reasor and Radu Cotescu, Adobe
 
Boost PC performance: How more available memory can improve productivity
Boost PC performance: How more available memory can improve productivityBoost PC performance: How more available memory can improve productivity
Boost PC performance: How more available memory can improve productivity
 
Strategies for Unlocking Knowledge Management in Microsoft 365 in the Copilot...
Strategies for Unlocking Knowledge Management in Microsoft 365 in the Copilot...Strategies for Unlocking Knowledge Management in Microsoft 365 in the Copilot...
Strategies for Unlocking Knowledge Management in Microsoft 365 in the Copilot...
 
MINDCTI Revenue Release Quarter One 2024
MINDCTI Revenue Release Quarter One 2024MINDCTI Revenue Release Quarter One 2024
MINDCTI Revenue Release Quarter One 2024
 
Cloud Frontiers: A Deep Dive into Serverless Spatial Data and FME
Cloud Frontiers:  A Deep Dive into Serverless Spatial Data and FMECloud Frontiers:  A Deep Dive into Serverless Spatial Data and FME
Cloud Frontiers: A Deep Dive into Serverless Spatial Data and FME
 
Scaling API-first – The story of a global engineering organization
Scaling API-first – The story of a global engineering organizationScaling API-first – The story of a global engineering organization
Scaling API-first – The story of a global engineering organization
 
Strategies for Landing an Oracle DBA Job as a Fresher
Strategies for Landing an Oracle DBA Job as a FresherStrategies for Landing an Oracle DBA Job as a Fresher
Strategies for Landing an Oracle DBA Job as a Fresher
 
Apidays New York 2024 - The value of a flexible API Management solution for O...
Apidays New York 2024 - The value of a flexible API Management solution for O...Apidays New York 2024 - The value of a flexible API Management solution for O...
Apidays New York 2024 - The value of a flexible API Management solution for O...
 
Artificial Intelligence: Facts and Myths
Artificial Intelligence: Facts and MythsArtificial Intelligence: Facts and Myths
Artificial Intelligence: Facts and Myths
 
+971581248768>> SAFE AND ORIGINAL ABORTION PILLS FOR SALE IN DUBAI AND ABUDHA...
+971581248768>> SAFE AND ORIGINAL ABORTION PILLS FOR SALE IN DUBAI AND ABUDHA...+971581248768>> SAFE AND ORIGINAL ABORTION PILLS FOR SALE IN DUBAI AND ABUDHA...
+971581248768>> SAFE AND ORIGINAL ABORTION PILLS FOR SALE IN DUBAI AND ABUDHA...
 
The 7 Things I Know About Cyber Security After 25 Years | April 2024
The 7 Things I Know About Cyber Security After 25 Years | April 2024The 7 Things I Know About Cyber Security After 25 Years | April 2024
The 7 Things I Know About Cyber Security After 25 Years | April 2024
 
Deploy with confidence: VMware Cloud Foundation 5.1 on next gen Dell PowerEdg...
Deploy with confidence: VMware Cloud Foundation 5.1 on next gen Dell PowerEdg...Deploy with confidence: VMware Cloud Foundation 5.1 on next gen Dell PowerEdg...
Deploy with confidence: VMware Cloud Foundation 5.1 on next gen Dell PowerEdg...
 
Tata AIG General Insurance Company - Insurer Innovation Award 2024
Tata AIG General Insurance Company - Insurer Innovation Award 2024Tata AIG General Insurance Company - Insurer Innovation Award 2024
Tata AIG General Insurance Company - Insurer Innovation Award 2024
 
Real Time Object Detection Using Open CV
Real Time Object Detection Using Open CVReal Time Object Detection Using Open CV
Real Time Object Detection Using Open CV
 
Axa Assurance Maroc - Insurer Innovation Award 2024
Axa Assurance Maroc - Insurer Innovation Award 2024Axa Assurance Maroc - Insurer Innovation Award 2024
Axa Assurance Maroc - Insurer Innovation Award 2024
 
A Year of the Servo Reboot: Where Are We Now?
A Year of the Servo Reboot: Where Are We Now?A Year of the Servo Reboot: Where Are We Now?
A Year of the Servo Reboot: Where Are We Now?
 
AWS Community Day CPH - Three problems of Terraform
AWS Community Day CPH - Three problems of TerraformAWS Community Day CPH - Three problems of Terraform
AWS Community Day CPH - Three problems of Terraform
 
2024: Domino Containers - The Next Step. News from the Domino Container commu...
2024: Domino Containers - The Next Step. News from the Domino Container commu...2024: Domino Containers - The Next Step. News from the Domino Container commu...
2024: Domino Containers - The Next Step. News from the Domino Container commu...
 
Polkadot JAM Slides - Token2049 - By Dr. Gavin Wood
Polkadot JAM Slides - Token2049 - By Dr. Gavin WoodPolkadot JAM Slides - Token2049 - By Dr. Gavin Wood
Polkadot JAM Slides - Token2049 - By Dr. Gavin Wood
 

Earned value in five easy pieces

  • 1. Earned Value in Five Easy Pieces Not that Earned Value can be made that easy, but this is the start of getting our mind around the concepts of project performance measurement 1
  • 2. 1. Using a credible schedule, define the planned value of the work 2. Measure the Physical % Complete for each period of performance 3. Calculate Earned Value = Planned Value x Physical % Complete 4. Using the Earned Value variables ,calculate the performance indices 5. With the performance indices take corrective actions 2
  • 3. 1 Using a credible schedule, define the planned value of the work 3
  • 4. 1 Create Work Packages for the activities that produce physical outcomes I 4
  • 5. 1 Define the planned value (PV)(BCWS) spreads for each Work Package I 5
  • 6. Measure Physical Percent Complete of Work Package Outcomes 2 6
  • 7. Define 0/100 or 50/50 activities within each Work Package. You’re either done or not done. There is no “partial” done for a Work Package. 2 7
  • 8. 2 Define Apportioned Milestones that describe the incremental progress of the Work Package in units meaningful to the customer II 8
  • 9. 2 Use evidentiary materials for each measurement. These are the only measures of progress. Not the passage of time or the consumption of resources. “Show Me the Outcomes” II 9
  • 10. Calculate the Earned Value 3 10
  • 11. EV = PV  Physical Percent Complete The Value that is Earned - the Earned Value - is the percent of the Planned Value that was delivered at the end of the period of performance. The percentage assessment is always measured by some physical assessment, some evidence that this percentage was actually achieved 3 11
  • 12. Using the Earned Value variables (BCWS, BCWP, ACWP), calculate Performance Indices 4 12
  • 13. The To Complete Performance Index (TCPI)  BAC  BCWP  TCPIEAC   EAC  ACWP  4 13
  • 14. The Independent Estimate At Completion (IEAC)  Probably as Good EAC1  BAC CPI as it Gets EAC2  ACWPcum   BAC  BCWPcum  SPI EAC3  ACWPcum   BAC  BCWPcum  SPI  CPI   Probably as Bad as it Gets EAC4  ACWPcum   BAC  BCWPcum  wt1  SPI  wt 2  CPI  EAC5  ACWPcum   BAC  BCWPcum  CPI( period ) 4 14
  • 15. 5 With the performance indices‘, take corrective action for remaining work V 15
  • 16. Earned Value must measure work performance within a pre-defined period of time – the period of performance At the end of a project, the Earned Value always equals the Planned Value – since all the work has been done. What is different is how long it took and how much money is cost. Earned Value bounds the time period to the Planned period IV 16
  • 17. Failing to us discipline and rigor can put you on the beach. So remember… A ship on the beach is a lighthouse to the sea – Dutch Proverb  Inattention to budgetary responsibilities  Progress not monitored in a regular and  Work authorization not always followed consistent manner  Budget and data reconciliation issues  Lack of vertical and horizontal traceability  Lack of integrated management systems (critical path)  Baseline fluctuations and frequent  Not capturing and using cost and schedule replanting data for corrective action  Current period and retroactive changes  Lack of predictive variance analysis  Improper use of management reserve  Lack of internal surveillance and controls  Earned Value techniques not reflecting  Managerial actions not demonstrated actual accomplishments using Earned Value  Untimely and unrealistic Latest Revised Estimates (LRE) 17
  • 18. Are You Doing Earned Value?  Do we know the value of the planned work?  Have we bounded the period of performance for each work element?  Do we know how to measure Physical Percent Complete? www.jack-nicholson.info 18
  • 19. Earned Value is fundamentally a planning tool. It will not “fix” problems with projects. But it will make the performance problems visible in analytical ways. www.jack-nicholson.info 19
  • 20. Glen B. Alleman Niwot Ridge Consulting 4347 Pebble Beach Drive Niwot, Colorado 80503 303.241.9633 glen.alleman@niwotridge.com Performance Based Management(sm) Integrated Master Plan Integrated Master Schedule Earned Value Management Systems Risk Management Proposal Support Services Glen B. Alleman, Copyright © 2012 20/58