Project Management Basic concepts
with
Microsoft
®
Project 2010
By:
Abdul Ghaffar PMP
ghaffarsarwar@gmail.com
+923434017209
Objective
• Projects Management Basics
– What is a Project
– Project Constraints
– Project Planning, Monitoring & control
– WBS
• Getting started with MS Project
(General Schedule Settings and Currency)
• Creating Project in MS Project
– Project Calendar
– Task List
– Task Notes
– Duration
– Linking Tasks
6/10/2014 By : Abdul Ghaffar, PMP 3
Objective …
– Lead & Lag
– MileStone
– Network Diagram
– Critical Path
– Adding Resource and its cost
– Creating Baseline
– Custom Fields
• Tracking Project
• Other Views and Reports
6/10/2014 By : Abdul Ghaffar, PMP 4
What is a Project?
A project is a temporary endeavor that helps to
accomplish some specific objective by utilizing definite
interconnected tasks and the effective utilization of
resources.
• To achieve an objective
• One Time (Start and finish dates)
• Constraints of time, cost and resources
• Performed by People – Single or Group
• Coordinated and controlled activities
• Specific Deliverables
• Progressive Elaboration
6/10/2014 By : Abdul Ghaffar, PMP 5
Major Constraint on Project
6/10/2014 By : Abdul Ghaffar, PMP 6
Project Process Groups
6/10/2014 By : Abdul Ghaffar, PMP 7
PMBOK 5
6/10/2014 By : Abdul Ghaffar, PMP 8
WBS for MS Project Training
1. Soft ware
Development Plan
1.1
Scope
1.2
Analysis/Soft
ware
Requirements
1.3
Design
1.4
Developme
nt
1.5
Testing
1.5.1
Unit Testing
1.5.2
Integration Testing
1.6
Training
1.7
Documenta
tion
1.8
Pilot
1.9
Deploymen
t
1.10
Post
Implement
ation
Review
6/10/2014 By : Abdul Ghaffar, PMP 9
Starting With MS Project 2010
File
->options
-> Display
6/10/2014 By : Abdul Ghaffar, PMP 10
Starting With MS Project 2010
File
->options
-> Schedule
6/10/2014 By : Abdul Ghaffar, PMP 11
MS Project 2010
6/10/2014 By : Abdul Ghaffar, PMP 12
Task List
6/10/2014 By : Abdul Ghaffar, PMP 13
Task Duration
6/10/2014 By : Abdul Ghaffar, PMP 14
WBS Code
6/10/2014 By : Abdul Ghaffar, PMP 15
Sub Task
6/10/2014 By : Abdul Ghaffar, PMP 16
Link Task..
Finish to Start (FS),
where the first must be finished before
the next begins.
Start to Start (SS),
where 2 tasks must start at the same
time.
Finish to Finish (FF),
where 2 tasks must end at the same time.
Start to Finish (SF) ,
where the start of the first is linked to
the completion of the second (with a lag
time specified as well.
6/10/2014 By : Abdul Ghaffar, PMP 17
Link Task
6/10/2014 By : Abdul Ghaffar, PMP 18
Predecessors
6/10/2014 By : Abdul Ghaffar, PMP 19
Lead & Lag Time
• Lead time causes a successor task to overlap
a predecessor even though they are linked
finish to start (FS).
• Lag time allows you to add a delay between
the start of the successor and the end of the
predecessor.
– Simply specify lead or lag time in the
Predecessor column.
• Lead time is represented with a minus sign (-)
• Lag time is represented with a plus sign (+).
6/10/2014 By : Abdul Ghaffar, PMP 20
Lead and Lag
6/10/2014 By : Abdul Ghaffar, PMP 21
Calendar
6/10/2014 By : Abdul Ghaffar, PMP 22
MileStone
Milestones let you gauge your progress through the project.
It’s good practice to include a Start and Finish Milestone for each division/part of your WBS.6/10/2014 By : Abdul Ghaffar, PMP 23
Resource
6/10/2014 By : Abdul Ghaffar, PMP 24
Assign Resources to Tasks
6/10/2014 By : Abdul Ghaffar, PMP 25
The Critical Path
The Critical path is the flow of tasks, of which,
a delay in any one of these tasks will cause a
delay to the project.
It is the longest path through the project
network diagram and the shortest possible
time to complete the project
6/10/2014 By : Abdul Ghaffar, PMP 26
Critical Path
6/10/2014 By : Abdul Ghaffar, PMP 27
Critical Path..
6/10/2014 By : Abdul Ghaffar, PMP 28
Slack
6/10/2014 By : Abdul Ghaffar, PMP 29
Slack is the amount of time that a task can slip before it affects another task
or the project's finish date.
Custom Field
6/10/2014 By : Abdul Ghaffar, PMP 30
Tracking Project
To control the variations from actual plan (baseline)
we need to track project and continuously check
the health of the project.
• EVM is a financial measurement tool that
combines the conflicting aspects of scope,
schedule and cost into a unified set of metrics.
• These metrics can be used for measuring,
monitoring, reporting and forecasting project
performance. It can be used through all the
phases of a project, from initiation to closure.
6/10/2014 By : Abdul Ghaffar, PMP 31
Earned Value …
6/10/2014 By : Abdul Ghaffar, PMP 32
Example
You have a project to build a new fence. the fence is
four sided as shown.
Each side is to take one day to build and is budgeted
for $1000 per side.
The sides are planed to be completed one after the
other.
Today is the end of day three.
• Calculate AC, BAC, CV, CPI,SV, SPI, EAC etc.
6/10/2014 By : Abdul Ghaffar, PMP 33
Plan Tasks
6/10/2014 By : Abdul Ghaffar, PMP 34
Set Baseline
6/10/2014 By : Abdul Ghaffar, PMP 35
Actual Status
6/10/2014 By : Abdul Ghaffar, PMP 36
Check Status
6/10/2014 By : Abdul Ghaffar, PMP 37
Status Summary
6/10/2014 By : Abdul Ghaffar, PMP 38
Calendar View
6/10/2014 By : Abdul Ghaffar, PMP 39
Network Diagram
6/10/2014 By : Abdul Ghaffar, PMP 40
Other Reports
6/10/2014 By : Abdul Ghaffar, PMP 41
THANKS
6/10/2014 By : Abdul Ghaffar, PMP 42

More Related Content

What's hot

44259126 ms-project-presentation
44259126 ms-project-presentation44259126 ms-project-presentation
44259126 ms-project-presentationFarrukh Raja
 
MICROSOFT PROJECT TUTORIAL
MICROSOFT PROJECT TUTORIALMICROSOFT PROJECT TUTORIAL
MICROSOFT PROJECT TUTORIALVismay Shah
 
Scheduling by using microsoft project 2013
Scheduling by using microsoft project 2013Scheduling by using microsoft project 2013
Scheduling by using microsoft project 2013Chetanraj M
 
Microsoft Projects; a step by-step guide for beginner's
Microsoft Projects; a step by-step guide for beginner'sMicrosoft Projects; a step by-step guide for beginner's
Microsoft Projects; a step by-step guide for beginner'sAbhik Tushar Das
 
Primavera presentation
Primavera presentationPrimavera presentation
Primavera presentationNithin Dev
 
Primavara
PrimavaraPrimavara
Primavaradanabl
 
Introduction to Primavera Reflections
Introduction to Primavera ReflectionsIntroduction to Primavera Reflections
Introduction to Primavera Reflectionsp6academy
 
Ms project training ppt
Ms project training pptMs project training ppt
Ms project training pptglobalp7
 
Introduction To Primavera (P6)
Introduction To Primavera (P6)Introduction To Primavera (P6)
Introduction To Primavera (P6)Sandip Kumar Verma
 
Practical Use of Microsoft Project for Project Managers
Practical Use of Microsoft Project for Project ManagersPractical Use of Microsoft Project for Project Managers
Practical Use of Microsoft Project for Project ManagersSteve Gladstone
 
Lec 03 project life cycle
Lec 03 project life cycleLec 03 project life cycle
Lec 03 project life cycleSAJID ALI RUK
 
PMP Knowledge Areas - PMBOK 6 (PMI) INFOGRAPHIC
PMP Knowledge Areas  - PMBOK 6  (PMI)   INFOGRAPHICPMP Knowledge Areas  - PMBOK 6  (PMI)   INFOGRAPHIC
PMP Knowledge Areas - PMBOK 6 (PMI) INFOGRAPHICJonathan Donado
 

What's hot (20)

44259126 ms-project-presentation
44259126 ms-project-presentation44259126 ms-project-presentation
44259126 ms-project-presentation
 
MICROSOFT PROJECT TUTORIAL
MICROSOFT PROJECT TUTORIALMICROSOFT PROJECT TUTORIAL
MICROSOFT PROJECT TUTORIAL
 
Scheduling by using microsoft project 2013
Scheduling by using microsoft project 2013Scheduling by using microsoft project 2013
Scheduling by using microsoft project 2013
 
Microsoft Projects; a step by-step guide for beginner's
Microsoft Projects; a step by-step guide for beginner'sMicrosoft Projects; a step by-step guide for beginner's
Microsoft Projects; a step by-step guide for beginner's
 
Project Scheduling
Project SchedulingProject Scheduling
Project Scheduling
 
Microsoft Project 2013
Microsoft Project 2013Microsoft Project 2013
Microsoft Project 2013
 
MS Project
MS ProjectMS Project
MS Project
 
Ms Project 2010
Ms Project 2010Ms Project 2010
Ms Project 2010
 
Primavera Training P6
Primavera Training P6Primavera Training P6
Primavera Training P6
 
Ms project training ver 01
Ms project training ver 01Ms project training ver 01
Ms project training ver 01
 
Primavera presentation
Primavera presentationPrimavera presentation
Primavera presentation
 
tcc primavera
tcc primaveratcc primavera
tcc primavera
 
Primavara
PrimavaraPrimavara
Primavara
 
Introduction to Primavera Reflections
Introduction to Primavera ReflectionsIntroduction to Primavera Reflections
Introduction to Primavera Reflections
 
Ms project training ppt
Ms project training pptMs project training ppt
Ms project training ppt
 
Introduction To Primavera (P6)
Introduction To Primavera (P6)Introduction To Primavera (P6)
Introduction To Primavera (P6)
 
Practical Use of Microsoft Project for Project Managers
Practical Use of Microsoft Project for Project ManagersPractical Use of Microsoft Project for Project Managers
Practical Use of Microsoft Project for Project Managers
 
Lec 03 project life cycle
Lec 03 project life cycleLec 03 project life cycle
Lec 03 project life cycle
 
PMP Knowledge Areas - PMBOK 6 (PMI) INFOGRAPHIC
PMP Knowledge Areas  - PMBOK 6  (PMI)   INFOGRAPHICPMP Knowledge Areas  - PMBOK 6  (PMI)   INFOGRAPHIC
PMP Knowledge Areas - PMBOK 6 (PMI) INFOGRAPHIC
 
Project Charter Guide
Project Charter GuideProject Charter Guide
Project Charter Guide
 

Viewers also liked

MS Project 2010 Getting Started
MS Project 2010 Getting StartedMS Project 2010 Getting Started
MS Project 2010 Getting Startedmsprojectpros
 
EVM in MS Project
EVM in MS ProjectEVM in MS Project
EVM in MS Projectorsmoot
 
Ms Project 2007(advanced)
Ms Project 2007(advanced)Ms Project 2007(advanced)
Ms Project 2007(advanced)Dinesh Singh
 
نموذج للامتحان
نموذج للامتحاننموذج للامتحان
نموذج للامتحانu083125
 
Duration - The Holy Grail of MS Project?
Duration - The Holy Grail of MS Project?Duration - The Holy Grail of MS Project?
Duration - The Holy Grail of MS Project?dmdk12
 
2010 ms project 2010 (2)
2010 ms project 2010 (2)2010 ms project 2010 (2)
2010 ms project 2010 (2)douggillis
 
Ms Project - Tracking Indicator
Ms Project - Tracking IndicatorMs Project - Tracking Indicator
Ms Project - Tracking IndicatorMic Xen, MSc, PMP
 
How to schedule_a_project_in_ms_project_2003
How to schedule_a_project_in_ms_project_2003How to schedule_a_project_in_ms_project_2003
How to schedule_a_project_in_ms_project_2003bebocole
 
Green transportation
Green  transportationGreen  transportation
Green transportationMs Wilson
 
Microsoft office project 2007
Microsoft office project 2007Microsoft office project 2007
Microsoft office project 2007Sapperg
 
Ms project trainee
Ms project traineeMs project trainee
Ms project traineeziadfdaher
 
Critical path and pert
Critical path and pertCritical path and pert
Critical path and pertdjoufack
 
Ms project working example
Ms project working exampleMs project working example
Ms project working exampleKushal Patel
 
Manajemen Proyek (CPM, PIM, EVM)
Manajemen Proyek (CPM, PIM, EVM)Manajemen Proyek (CPM, PIM, EVM)
Manajemen Proyek (CPM, PIM, EVM)Kukuh Setiawan
 

Viewers also liked (20)

MS Project 2010 Getting Started
MS Project 2010 Getting StartedMS Project 2010 Getting Started
MS Project 2010 Getting Started
 
EVM in MS Project
EVM in MS ProjectEVM in MS Project
EVM in MS Project
 
Ms Project 2007(advanced)
Ms Project 2007(advanced)Ms Project 2007(advanced)
Ms Project 2007(advanced)
 
نموذج للامتحان
نموذج للامتحاننموذج للامتحان
نموذج للامتحان
 
Duration - The Holy Grail of MS Project?
Duration - The Holy Grail of MS Project?Duration - The Holy Grail of MS Project?
Duration - The Holy Grail of MS Project?
 
Ms project
Ms projectMs project
Ms project
 
2010 ms project 2010 (2)
2010 ms project 2010 (2)2010 ms project 2010 (2)
2010 ms project 2010 (2)
 
Ms Project - Tracking Indicator
Ms Project - Tracking IndicatorMs Project - Tracking Indicator
Ms Project - Tracking Indicator
 
How to schedule_a_project_in_ms_project_2003
How to schedule_a_project_in_ms_project_2003How to schedule_a_project_in_ms_project_2003
How to schedule_a_project_in_ms_project_2003
 
Green transportation
Green  transportationGreen  transportation
Green transportation
 
Microsoft office project 2007
Microsoft office project 2007Microsoft office project 2007
Microsoft office project 2007
 
مشروع4
مشروع4مشروع4
مشروع4
 
Ms project trainee
Ms project traineeMs project trainee
Ms project trainee
 
MS Project 2007 Tips and Tricks
MS Project 2007 Tips and TricksMS Project 2007 Tips and Tricks
MS Project 2007 Tips and Tricks
 
Ms project
Ms  projectMs  project
Ms project
 
Strategic Value of Project Management - Arabic
Strategic Value of Project Management - ArabicStrategic Value of Project Management - Arabic
Strategic Value of Project Management - Arabic
 
Critical path and pert
Critical path and pertCritical path and pert
Critical path and pert
 
Ms project working example
Ms project working exampleMs project working example
Ms project working example
 
Ms project
Ms projectMs project
Ms project
 
Manajemen Proyek (CPM, PIM, EVM)
Manajemen Proyek (CPM, PIM, EVM)Manajemen Proyek (CPM, PIM, EVM)
Manajemen Proyek (CPM, PIM, EVM)
 

Similar to Project Management using MS Project 2010

MS Project Terminology -Top 20 terms everyone must know
MS Project Terminology -Top 20 terms everyone must knowMS Project Terminology -Top 20 terms everyone must know
MS Project Terminology -Top 20 terms everyone must knowSHAZEBALIKHAN1
 
Avoiding unrealistic schedules
Avoiding unrealistic schedulesAvoiding unrealistic schedules
Avoiding unrealistic schedulesHatem Hegazi
 
Summer Internship Report by waqar ahmed javed
Summer Internship Report by waqar ahmed javedSummer Internship Report by waqar ahmed javed
Summer Internship Report by waqar ahmed javedWaqar Ahmed
 
Smsvn pmp training_slides_chapter_6
Smsvn pmp training_slides_chapter_6Smsvn pmp training_slides_chapter_6
Smsvn pmp training_slides_chapter_6Nam Trung
 
Smsvn pmp training_slides_chapter_7
Smsvn pmp training_slides_chapter_7Smsvn pmp training_slides_chapter_7
Smsvn pmp training_slides_chapter_7Nam Trung
 
Ms Project 2010 Application For PMP
Ms Project 2010 Application For PMPMs Project 2010 Application For PMP
Ms Project 2010 Application For PMPAndy Pham, PMP
 
Fundamentals of project planning and scheduling
Fundamentals of project planning and schedulingFundamentals of project planning and scheduling
Fundamentals of project planning and schedulingAtul Gaur PMP
 
Reducing Project Duration_Jagat Prasad Upadhyay.pptx
Reducing Project Duration_Jagat Prasad Upadhyay.pptxReducing Project Duration_Jagat Prasad Upadhyay.pptx
Reducing Project Duration_Jagat Prasad Upadhyay.pptxJagat Upadhyay
 
#Project Scheduling - Network Diagrams : PERT & CPM# By SN Panigrahi
#Project Scheduling - Network Diagrams : PERT & CPM# By SN Panigrahi#Project Scheduling - Network Diagrams : PERT & CPM# By SN Panigrahi
#Project Scheduling - Network Diagrams : PERT & CPM# By SN PanigrahiSN Panigrahi, PMP
 
76 s201905
76 s20190576 s201905
76 s201905IJRAT
 
Lesson 1 PMT Project Life Cycle (Microsoft Project Management)
Lesson 1 PMT Project Life Cycle (Microsoft Project Management)Lesson 1 PMT Project Life Cycle (Microsoft Project Management)
Lesson 1 PMT Project Life Cycle (Microsoft Project Management)amirasghar6
 
- CV Planning Engr - Clinton Chidi -Jan 2023.docx
- CV Planning Engr - Clinton Chidi -Jan 2023.docx- CV Planning Engr - Clinton Chidi -Jan 2023.docx
- CV Planning Engr - Clinton Chidi -Jan 2023.docxMbachu Clinton
 
Chap 4.7 Project or Phase Close
Chap 4.7 Project or Phase CloseChap 4.7 Project or Phase Close
Chap 4.7 Project or Phase CloseAnand Bobade
 
Advanced Scheduling for Large, Complex Industrial Projects
Advanced Scheduling for Large, Complex Industrial ProjectsAdvanced Scheduling for Large, Complex Industrial Projects
Advanced Scheduling for Large, Complex Industrial ProjectsJeremie Averous
 

Similar to Project Management using MS Project 2010 (20)

MS Project Terminology -Top 20 terms everyone must know
MS Project Terminology -Top 20 terms everyone must knowMS Project Terminology -Top 20 terms everyone must know
MS Project Terminology -Top 20 terms everyone must know
 
Project Scheduling
Project SchedulingProject Scheduling
Project Scheduling
 
50 Planning Fundamentals V5.0 - procedures only
50 Planning Fundamentals V5.0 - procedures only50 Planning Fundamentals V5.0 - procedures only
50 Planning Fundamentals V5.0 - procedures only
 
Avoiding unrealistic schedules
Avoiding unrealistic schedulesAvoiding unrealistic schedules
Avoiding unrealistic schedules
 
Summer Internship Report by waqar ahmed javed
Summer Internship Report by waqar ahmed javedSummer Internship Report by waqar ahmed javed
Summer Internship Report by waqar ahmed javed
 
Smsvn pmp training_slides_chapter_6
Smsvn pmp training_slides_chapter_6Smsvn pmp training_slides_chapter_6
Smsvn pmp training_slides_chapter_6
 
Smsvn pmp training_slides_chapter_7
Smsvn pmp training_slides_chapter_7Smsvn pmp training_slides_chapter_7
Smsvn pmp training_slides_chapter_7
 
Project scheduling
Project schedulingProject scheduling
Project scheduling
 
Ms Project 2010 Application For PMP
Ms Project 2010 Application For PMPMs Project 2010 Application For PMP
Ms Project 2010 Application For PMP
 
Fundamentals of project planning and scheduling
Fundamentals of project planning and schedulingFundamentals of project planning and scheduling
Fundamentals of project planning and scheduling
 
Reducing Project Duration_Jagat Prasad Upadhyay.pptx
Reducing Project Duration_Jagat Prasad Upadhyay.pptxReducing Project Duration_Jagat Prasad Upadhyay.pptx
Reducing Project Duration_Jagat Prasad Upadhyay.pptx
 
1 - Basic Concepts.pdf
1 - Basic Concepts.pdf1 - Basic Concepts.pdf
1 - Basic Concepts.pdf
 
S curves
S curvesS curves
S curves
 
#Project Scheduling - Network Diagrams : PERT & CPM# By SN Panigrahi
#Project Scheduling - Network Diagrams : PERT & CPM# By SN Panigrahi#Project Scheduling - Network Diagrams : PERT & CPM# By SN Panigrahi
#Project Scheduling - Network Diagrams : PERT & CPM# By SN Panigrahi
 
Project Sheduling.pptx
Project Sheduling.pptxProject Sheduling.pptx
Project Sheduling.pptx
 
76 s201905
76 s20190576 s201905
76 s201905
 
Lesson 1 PMT Project Life Cycle (Microsoft Project Management)
Lesson 1 PMT Project Life Cycle (Microsoft Project Management)Lesson 1 PMT Project Life Cycle (Microsoft Project Management)
Lesson 1 PMT Project Life Cycle (Microsoft Project Management)
 
- CV Planning Engr - Clinton Chidi -Jan 2023.docx
- CV Planning Engr - Clinton Chidi -Jan 2023.docx- CV Planning Engr - Clinton Chidi -Jan 2023.docx
- CV Planning Engr - Clinton Chidi -Jan 2023.docx
 
Chap 4.7 Project or Phase Close
Chap 4.7 Project or Phase CloseChap 4.7 Project or Phase Close
Chap 4.7 Project or Phase Close
 
Advanced Scheduling for Large, Complex Industrial Projects
Advanced Scheduling for Large, Complex Industrial ProjectsAdvanced Scheduling for Large, Complex Industrial Projects
Advanced Scheduling for Large, Complex Industrial Projects
 

Recently uploaded

International Ocean Transportation p.pdf
International Ocean Transportation p.pdfInternational Ocean Transportation p.pdf
International Ocean Transportation p.pdfAlejandromexEspino
 
Day 0- Bootcamp Roadmap for PLC Bootcamp
Day 0- Bootcamp Roadmap for PLC BootcampDay 0- Bootcamp Roadmap for PLC Bootcamp
Day 0- Bootcamp Roadmap for PLC BootcampPLCLeadershipDevelop
 
Beyond the Codes_Repositioning towards sustainable development
Beyond the Codes_Repositioning towards sustainable developmentBeyond the Codes_Repositioning towards sustainable development
Beyond the Codes_Repositioning towards sustainable developmentNimot Muili
 
Agile Coaching Change Management Framework.pptx
Agile Coaching Change Management Framework.pptxAgile Coaching Change Management Framework.pptx
Agile Coaching Change Management Framework.pptxalinstan901
 
Strategic Management, Vision Mission, Internal Analsysis
Strategic Management, Vision Mission, Internal AnalsysisStrategic Management, Vision Mission, Internal Analsysis
Strategic Management, Vision Mission, Internal Analsysistanmayarora45
 
Safety T fire missions army field Artillery
Safety T fire missions army field ArtillerySafety T fire missions army field Artillery
Safety T fire missions army field ArtilleryKennethSwanberg
 
Call now : 9892124323 Nalasopara Beautiful Call Girls Vasai virar Best Call G...
Call now : 9892124323 Nalasopara Beautiful Call Girls Vasai virar Best Call G...Call now : 9892124323 Nalasopara Beautiful Call Girls Vasai virar Best Call G...
Call now : 9892124323 Nalasopara Beautiful Call Girls Vasai virar Best Call G...Pooja Nehwal
 
Call Now Pooja Mehta : 7738631006 Door Step Call Girls Rate 100% Satisfactio...
Call Now Pooja Mehta :  7738631006 Door Step Call Girls Rate 100% Satisfactio...Call Now Pooja Mehta :  7738631006 Door Step Call Girls Rate 100% Satisfactio...
Call Now Pooja Mehta : 7738631006 Door Step Call Girls Rate 100% Satisfactio...Pooja Nehwal
 
internal analysis on strategic management
internal analysis on strategic managementinternal analysis on strategic management
internal analysis on strategic managementharfimakarim
 
BDSM⚡Call Girls in Sector 99 Noida Escorts >༒8448380779 Escort Service
BDSM⚡Call Girls in Sector 99 Noida Escorts >༒8448380779 Escort ServiceBDSM⚡Call Girls in Sector 99 Noida Escorts >༒8448380779 Escort Service
BDSM⚡Call Girls in Sector 99 Noida Escorts >༒8448380779 Escort ServiceDelhi Call girls
 
Dealing with Poor Performance - get the full picture from 3C Performance Mana...
Dealing with Poor Performance - get the full picture from 3C Performance Mana...Dealing with Poor Performance - get the full picture from 3C Performance Mana...
Dealing with Poor Performance - get the full picture from 3C Performance Mana...Hedda Bird
 
GENUINE Babe,Call Girls IN Baderpur Delhi | +91-8377087607
GENUINE Babe,Call Girls IN Baderpur  Delhi | +91-8377087607GENUINE Babe,Call Girls IN Baderpur  Delhi | +91-8377087607
GENUINE Babe,Call Girls IN Baderpur Delhi | +91-8377087607dollysharma2066
 
Reviewing and summarization of university ranking system to.pptx
Reviewing and summarization of university ranking system  to.pptxReviewing and summarization of university ranking system  to.pptx
Reviewing and summarization of university ranking system to.pptxAss.Prof. Dr. Mogeeb Mosleh
 

Recently uploaded (15)

Abortion pills in Jeddah |• +966572737505 ] GET CYTOTEC
Abortion pills in Jeddah |• +966572737505 ] GET CYTOTECAbortion pills in Jeddah |• +966572737505 ] GET CYTOTEC
Abortion pills in Jeddah |• +966572737505 ] GET CYTOTEC
 
International Ocean Transportation p.pdf
International Ocean Transportation p.pdfInternational Ocean Transportation p.pdf
International Ocean Transportation p.pdf
 
Intro_University_Ranking_Introduction.pptx
Intro_University_Ranking_Introduction.pptxIntro_University_Ranking_Introduction.pptx
Intro_University_Ranking_Introduction.pptx
 
Day 0- Bootcamp Roadmap for PLC Bootcamp
Day 0- Bootcamp Roadmap for PLC BootcampDay 0- Bootcamp Roadmap for PLC Bootcamp
Day 0- Bootcamp Roadmap for PLC Bootcamp
 
Beyond the Codes_Repositioning towards sustainable development
Beyond the Codes_Repositioning towards sustainable developmentBeyond the Codes_Repositioning towards sustainable development
Beyond the Codes_Repositioning towards sustainable development
 
Agile Coaching Change Management Framework.pptx
Agile Coaching Change Management Framework.pptxAgile Coaching Change Management Framework.pptx
Agile Coaching Change Management Framework.pptx
 
Strategic Management, Vision Mission, Internal Analsysis
Strategic Management, Vision Mission, Internal AnalsysisStrategic Management, Vision Mission, Internal Analsysis
Strategic Management, Vision Mission, Internal Analsysis
 
Safety T fire missions army field Artillery
Safety T fire missions army field ArtillerySafety T fire missions army field Artillery
Safety T fire missions army field Artillery
 
Call now : 9892124323 Nalasopara Beautiful Call Girls Vasai virar Best Call G...
Call now : 9892124323 Nalasopara Beautiful Call Girls Vasai virar Best Call G...Call now : 9892124323 Nalasopara Beautiful Call Girls Vasai virar Best Call G...
Call now : 9892124323 Nalasopara Beautiful Call Girls Vasai virar Best Call G...
 
Call Now Pooja Mehta : 7738631006 Door Step Call Girls Rate 100% Satisfactio...
Call Now Pooja Mehta :  7738631006 Door Step Call Girls Rate 100% Satisfactio...Call Now Pooja Mehta :  7738631006 Door Step Call Girls Rate 100% Satisfactio...
Call Now Pooja Mehta : 7738631006 Door Step Call Girls Rate 100% Satisfactio...
 
internal analysis on strategic management
internal analysis on strategic managementinternal analysis on strategic management
internal analysis on strategic management
 
BDSM⚡Call Girls in Sector 99 Noida Escorts >༒8448380779 Escort Service
BDSM⚡Call Girls in Sector 99 Noida Escorts >༒8448380779 Escort ServiceBDSM⚡Call Girls in Sector 99 Noida Escorts >༒8448380779 Escort Service
BDSM⚡Call Girls in Sector 99 Noida Escorts >༒8448380779 Escort Service
 
Dealing with Poor Performance - get the full picture from 3C Performance Mana...
Dealing with Poor Performance - get the full picture from 3C Performance Mana...Dealing with Poor Performance - get the full picture from 3C Performance Mana...
Dealing with Poor Performance - get the full picture from 3C Performance Mana...
 
GENUINE Babe,Call Girls IN Baderpur Delhi | +91-8377087607
GENUINE Babe,Call Girls IN Baderpur  Delhi | +91-8377087607GENUINE Babe,Call Girls IN Baderpur  Delhi | +91-8377087607
GENUINE Babe,Call Girls IN Baderpur Delhi | +91-8377087607
 
Reviewing and summarization of university ranking system to.pptx
Reviewing and summarization of university ranking system  to.pptxReviewing and summarization of university ranking system  to.pptx
Reviewing and summarization of university ranking system to.pptx
 

Project Management using MS Project 2010

  • 1.
  • 2. Project Management Basic concepts with Microsoft ® Project 2010 By: Abdul Ghaffar PMP ghaffarsarwar@gmail.com +923434017209
  • 3. Objective • Projects Management Basics – What is a Project – Project Constraints – Project Planning, Monitoring & control – WBS • Getting started with MS Project (General Schedule Settings and Currency) • Creating Project in MS Project – Project Calendar – Task List – Task Notes – Duration – Linking Tasks 6/10/2014 By : Abdul Ghaffar, PMP 3
  • 4. Objective … – Lead & Lag – MileStone – Network Diagram – Critical Path – Adding Resource and its cost – Creating Baseline – Custom Fields • Tracking Project • Other Views and Reports 6/10/2014 By : Abdul Ghaffar, PMP 4
  • 5. What is a Project? A project is a temporary endeavor that helps to accomplish some specific objective by utilizing definite interconnected tasks and the effective utilization of resources. • To achieve an objective • One Time (Start and finish dates) • Constraints of time, cost and resources • Performed by People – Single or Group • Coordinated and controlled activities • Specific Deliverables • Progressive Elaboration 6/10/2014 By : Abdul Ghaffar, PMP 5
  • 6. Major Constraint on Project 6/10/2014 By : Abdul Ghaffar, PMP 6
  • 7. Project Process Groups 6/10/2014 By : Abdul Ghaffar, PMP 7
  • 8. PMBOK 5 6/10/2014 By : Abdul Ghaffar, PMP 8
  • 9. WBS for MS Project Training 1. Soft ware Development Plan 1.1 Scope 1.2 Analysis/Soft ware Requirements 1.3 Design 1.4 Developme nt 1.5 Testing 1.5.1 Unit Testing 1.5.2 Integration Testing 1.6 Training 1.7 Documenta tion 1.8 Pilot 1.9 Deploymen t 1.10 Post Implement ation Review 6/10/2014 By : Abdul Ghaffar, PMP 9
  • 10. Starting With MS Project 2010 File ->options -> Display 6/10/2014 By : Abdul Ghaffar, PMP 10
  • 11. Starting With MS Project 2010 File ->options -> Schedule 6/10/2014 By : Abdul Ghaffar, PMP 11
  • 12. MS Project 2010 6/10/2014 By : Abdul Ghaffar, PMP 12
  • 13. Task List 6/10/2014 By : Abdul Ghaffar, PMP 13
  • 14. Task Duration 6/10/2014 By : Abdul Ghaffar, PMP 14
  • 15. WBS Code 6/10/2014 By : Abdul Ghaffar, PMP 15
  • 16. Sub Task 6/10/2014 By : Abdul Ghaffar, PMP 16
  • 17. Link Task.. Finish to Start (FS), where the first must be finished before the next begins. Start to Start (SS), where 2 tasks must start at the same time. Finish to Finish (FF), where 2 tasks must end at the same time. Start to Finish (SF) , where the start of the first is linked to the completion of the second (with a lag time specified as well. 6/10/2014 By : Abdul Ghaffar, PMP 17
  • 18. Link Task 6/10/2014 By : Abdul Ghaffar, PMP 18
  • 19. Predecessors 6/10/2014 By : Abdul Ghaffar, PMP 19
  • 20. Lead & Lag Time • Lead time causes a successor task to overlap a predecessor even though they are linked finish to start (FS). • Lag time allows you to add a delay between the start of the successor and the end of the predecessor. – Simply specify lead or lag time in the Predecessor column. • Lead time is represented with a minus sign (-) • Lag time is represented with a plus sign (+). 6/10/2014 By : Abdul Ghaffar, PMP 20
  • 21. Lead and Lag 6/10/2014 By : Abdul Ghaffar, PMP 21
  • 22. Calendar 6/10/2014 By : Abdul Ghaffar, PMP 22
  • 23. MileStone Milestones let you gauge your progress through the project. It’s good practice to include a Start and Finish Milestone for each division/part of your WBS.6/10/2014 By : Abdul Ghaffar, PMP 23
  • 24. Resource 6/10/2014 By : Abdul Ghaffar, PMP 24
  • 25. Assign Resources to Tasks 6/10/2014 By : Abdul Ghaffar, PMP 25
  • 26. The Critical Path The Critical path is the flow of tasks, of which, a delay in any one of these tasks will cause a delay to the project. It is the longest path through the project network diagram and the shortest possible time to complete the project 6/10/2014 By : Abdul Ghaffar, PMP 26
  • 27. Critical Path 6/10/2014 By : Abdul Ghaffar, PMP 27
  • 28. Critical Path.. 6/10/2014 By : Abdul Ghaffar, PMP 28
  • 29. Slack 6/10/2014 By : Abdul Ghaffar, PMP 29 Slack is the amount of time that a task can slip before it affects another task or the project's finish date.
  • 30. Custom Field 6/10/2014 By : Abdul Ghaffar, PMP 30
  • 31. Tracking Project To control the variations from actual plan (baseline) we need to track project and continuously check the health of the project. • EVM is a financial measurement tool that combines the conflicting aspects of scope, schedule and cost into a unified set of metrics. • These metrics can be used for measuring, monitoring, reporting and forecasting project performance. It can be used through all the phases of a project, from initiation to closure. 6/10/2014 By : Abdul Ghaffar, PMP 31
  • 32. Earned Value … 6/10/2014 By : Abdul Ghaffar, PMP 32
  • 33. Example You have a project to build a new fence. the fence is four sided as shown. Each side is to take one day to build and is budgeted for $1000 per side. The sides are planed to be completed one after the other. Today is the end of day three. • Calculate AC, BAC, CV, CPI,SV, SPI, EAC etc. 6/10/2014 By : Abdul Ghaffar, PMP 33
  • 34. Plan Tasks 6/10/2014 By : Abdul Ghaffar, PMP 34
  • 35. Set Baseline 6/10/2014 By : Abdul Ghaffar, PMP 35
  • 36. Actual Status 6/10/2014 By : Abdul Ghaffar, PMP 36
  • 37. Check Status 6/10/2014 By : Abdul Ghaffar, PMP 37
  • 38. Status Summary 6/10/2014 By : Abdul Ghaffar, PMP 38
  • 39. Calendar View 6/10/2014 By : Abdul Ghaffar, PMP 39
  • 40. Network Diagram 6/10/2014 By : Abdul Ghaffar, PMP 40
  • 41. Other Reports 6/10/2014 By : Abdul Ghaffar, PMP 41
  • 42. THANKS 6/10/2014 By : Abdul Ghaffar, PMP 42