Standards Workshop
Calgary, Alberta
June 6, 2013
GLOBAL CCS INSTITUTE
Agenda
 Opening Remarks: Victor Der - Global CCS Institute
 Session 1: CSA Z741 Geological Storage of CO2
Jeff Walker - CSA Group
 Session 2: Impact of Z741 on Public Engagement and Safety
Jacqueline Sharp - Navius Research
 Session 3: Impact of Z741 0n Project Costs
Allan Greeves - Cenovus
 Session 4: Impact of Z741 on Mitigating Projects Risks
Rob Bioletti - Alberta Energy
 Session 5: Facilitated Discussion
Bob Page – University of Calgary, J-P Jepp – Shell Oil
Company, Rob Craig – ICO2N and participants
 Closing Remarks: Victor Der - Global CCS Institute
Process
 Speakers will give a 20 minute presentation. The balance of
the time is for Q&A and discussion
 There will be an extended open discussion at the end of the
day
 Vic Der will be the principal facilitator
 Ian Hayhow will be the rapporteur
 Chatham House rules apply
 We likely can be a bit flexible with the timelines
Workshop Objectives
The expected outcome for today is:
Identify the advantages and challenges to using standards for
CO2 storage projects
Storage Issues:
• How rigorous is the pre-screening process?
• Should there be a mechanism to recover pre-screening
costs?
• Who can/will do expert reviews?
Next Steps
• Draft summary report to be prepared by the Global CCS
Institute
• Circulate to participants for comment
• Publish on the Institute website
• Comments of the workshop please
• Thoughts for other workshop sessions
CSA Z741 Geological Storage of
Carbon Dioxide
Jeff Walker
GCCSI - The Role of Storage Standards in the
Deployment of CCS Workshop
June 6, 2013
Agenda
• About CSA Group
• About consensus standards
• Role of standards in CCS
• CSA Z741 Geological Storage of CO2
• Update on ISO standards
7
CSA Group
• Independent not-for profit Standards
Development, Product Certification and
Consumer Product Evaluation Organization
• Largest and most diversified Standards
Development Organization in Canada
• Neutral 3rd party
• One billion products worldwide bear a CSA
product safety mark
8
Standards Development
9
3,000
Standards and Codes
8,500
expert Committee Members
54
Program areas
40%
of standards are referenced in
government regulation
95%
of customers recommend
the use of CSA standards
Standards
What is a consensus standard?
A document designed to be used as a rule, guideline
or definition. It is a consensus-built, repeatable way of
doing something
Standards must fit the need
• Prescriptive based
• Objectives based
• Performance based
• Principles based
• Hybrids
10
Consensus
Consensus
General agreement, characterized by the absence of
sustained opposition to substantial issues by any
important part of the concerned interests and by a
process that involves seeking to take into account the
views of all parties concerned and to address any
conflicting arguments.
Consensus is not necessarily unanimity
CSA uses an accredited standards development
process to develop standards through
consensus
11
CSA’s Consensus Process
CSA does not write standards
Technical Committees write standards
CSA does not influence the technical content
12
• Organized to drive diverse stakeholders to consensus on
tough issues
• Accredited by the Standards Council of Canada
• Technical Committee - Balanced Matrix
– All interest groups have equal access
– Minority interest groups have a voice
13
CSA’s Consensus Process
Chair
Associate
Members
5 Year
Reviews
Public
Review
• Owners / Architects/
Regulators
• Suppliers/ Fabricators/
Contractors
• Consultants
Committee
• Owners
• Researchers
• Regulators
• Suppliers
• Fabricators
• Contractors
• Consultants
Role of Standards
Standards and Public Perception of CCS
• People are worried about geological storage
• Public opposition has caused cancelation of several
CCS projects
• Standards can provide assurances that CCS is safe
14
Role of Standards
Standards and Regulations
• Standards and regulations can work together
• Standards are voluntary
• Typically standards initiated by industry
• Demonstrate regulatory compliance
15
Role of Standards
Standards and Regulations
• Streamline the regulatory process
• Harmonize across jurisdictions
• Standards have a revision process
16
Role of Standards
Other Benefits
• Transfer of knowledge and experience
• Mainstream leading practices
• Financing CCS projects
• Acceptance by different interests
17
CSA Z741
CSA Z741 Geological Storage of CO2
• Bi-national USA – Canada
• IPAC CO2 provided support
• Publication in 2012
• CSA Z741 is not a “cookbook”
Promote environmentally safe and long-term
containment of carbon dioxide
18
CSA Z741
Scope
• Establishes requirements for the storage of CO2
• Recognizes projects are site specific
• Primarily applicable to saline aquifers and depleted
hydrocarbon reservoirs
• Does not preclude its application to EOR storage
19
CSA Z741
Scope
• CO2 storage during EOR is different
• Aspects can be used for EOR projects
• When storage is an incident of routine EOR
20
CSA Committee
21
User Interest Category Min Max Actual
General Interest 8 11 10
Government and/or Regulatory Authority 5 7 6
Owner/Operator/Producer 7 9 7
Supplier/Contractor/Consultant Interest 6 9 6
Balanced Matrix Approach to Consensus
Committee Organizations
22
Government/Regulators
– Energy Resources Conservation
Board of Alberta (ERCB)
– BC Oil and Gas Commission
– Ground Water Protection Council
– Alabama Dept. of Env Mgmt
– Mississippi Dept of Env Quality
– Alberta Energy
Owner/Operator/Producer
– SaskPower
– Southern Company
– Cenovus
– Denbury Resources
– Chevron
– Husky Energy
Supplier/Contractor/Consultant Interest
– DNV
– Schlumberger Carbon Services
– Advanced Resources International Inc
– Halliburton
– Golder Associates
– Baker Hughes
General Interest/Expertise
– University of Alberta
– Alberta Innovates-Technology Futures
– World Resources Institute (WRI)
– Global CCS Institute
– International Energy Agency
– PEW Center on Global Climate Change
– Princeton University
CSA Z741
Table of Contents
1 Scope
2 Reference publications
3 Definitions
4 Management systems
5 Site screening, selection, and characterization
6 Risk management
7 Well infrastructure development
8 Monitoring and verification
9 Closure
23
CSA Z741
Clause 4 Management systems
• Ensure that existing best practices are followed
• Promote improvement
• Clarify project operator roles and responsibilities
• Detail principles; internal, external; HSE
• Lay out communication requirements
24
CSA Z741
Clause 5 Site screening, selection, and characterization
• Site screening advice
• Criteria for site selection
• Requirements and recommendations for
characterizations
• Modeling parameters and outcomes
25
CSA Z741
Clause 6 Risk management
• Consistent with ISO 31000 Risk management
26
CSA Z741
Clause 7 Well infrastructure development
• CO2 specific requirements and references
– Materials
– Design
– Construction
– Corrosion control
– O&M
27
CSA Z741
Clause 8 Monitoring and verification
• Flexible and adapt to changes in conditions and phases
• Not technology based
• M&V objectives
• Designing an M&V program
28
CSA Z741
Clause 9 Closure
• Closure plan
• Qualification process requirements
• Preparing for decommissioning
29
International Standards
CCS crosses international borders
• Expertise is international
• Project operators are transnational
• Harmonization has benefits
National differences must be
acknowledged
30
ISO and CCS
New CCS ISO TC 265
• Chaired by Canada (Sandra Locke)
• Secretary Canada, twinned with China
Standardization of design, construction,
operation, and environmental planning and
management, risk management,
quantification, monitoring and verification,
and related activities in the field of carbon
dioxide capture, transportation, and
geological storage (CCS).
31
TC265 Participation
Participating Countries
Australia Malaysia
Canada Netherlands
China Norway
France South Africa
Germany Spain
Italy Switzerland
Japan United Kingdom
Korea United States
10 other observer nations
32
TC 265 Structure
33
CCS TC
Capture
Group
Transportation
Group Storage
Group
Cross-Cutting
Group
Quant. & Verif.
Group
Summary
34
• There are challenges to implementing CCS
• CSA Z741 can help
• alleviate public concerns about safety
• facilitate compliance with the regulatory process
• streamline approvals
• mainstream leading practices
• CSA Z741 on CO2 storage is available for use
• ISO is embarking upon international standards
35
Email - jeff.walker@csagroup.org
The Impact of Z741 on Public
Engagement and Safety
Jacqueline Sharp
Managing Partner, Navius Research Inc.
Presentation Overview
• Z741 and Public Engagement
• Z741 and Safety
• Impact of Z741 on Public Engagement and Safety
• Group Discussion Questions
Z741 and Public Engagement
Who is the “Public”?
• Stakeholders: individuals, groups, companies or
organisations that believe their interests could be
affected by a project and wish to participate in or
have their interests represented in project
decisions.
• ‘Public’ stakeholders: general public, local
community, NGOs
•Other key stakeholders: government/ regulators,
experts, employees, shareholders, suppliers,
customers. Some crossover to ‘public’.
Public stakeholders grant or withhold social license to operate.
What is ‘engagement’?
Engagement goes beyond informing and consulting.
PlanningNSW, 2003
Why does public engagement matter?
• Business case: reduce risk of project delays or
cancellations due to opposition
• Approvals: satisfy or exceed regulatory
requirements
• Project improvements: benefit from different
viewpoints, challenged to address critical issues
• Reputational benefits
Effective public engagement is a key risk mitigation tool.
Z741 and public engagement
Principles:
• “Operate in an open and transparent fashion...
to build public understanding, trust, and
credibility”
• Develop and implement a local stakeholder
advisory strategy
• Report on major milestones or unplanned
events
“Identify project stakeholders early in the storage project life
cycle and engage them during all phases of the project”
Z741 and public engagement cont.
Public Communications:
• Include a trained designated media liaison and a
designated individual to answer public questions
• Involve the community in development of the
outreach and engagement strategy
• Communicate about the project early and often
• Use public meetings, notices, and updates, site
visits, potentially a local newsletter, social media
• Communications should clearly share scientific,
technical, and economic information, and focus on
project issues and local benefits/concerns
Z741 and public engagement cont.
Communications continued:
“The operator should engage the public in
decision-making around aspects of the project
where possible so that it addresses their
concerns and meets local needs”
Z741 and public engagement cont.
• The ‘human culture’ context should be considered
• Stakeholder interests should be considered, and
their needs met to the extent practicable
• Stakeholder views should be appropriately
considered when defining the elements of concern,
identifying criteria, and evaluating risk
• Risk communication program should address
rationale for site selection, risk management plans,
response to unexpected events, stakeholder
concerns/questions
The Risk Management process should include stakeholder
consultation and communication.
Z741 and Safety
Safety Risks Associated with CCS
• Safety risk is a function of likelihood of
occurrence and severity of consequences
• The greatest consequences are associated with
exposure of the public or workers to high
concentrations of CO2. due to leakage or an
accident
• The likelihood of these events occurring is very
low
The actual safety risks associated with CCS are low.
Z741 and Safety
• “Ensure the integrity of all facilities which
includes preventing leakage”
• “Develop and put in place an emergency
response plan and team”
• “Provide the appropriate resources to
continually improve health, safety, and
environmental protection”
“Ensure that health, safety, and environmental protection
for workers and local communities are the project’s
highest priorities”
Z741 and Safety cont.
Very detailed standards for:
• Site characterization and assessment
• Risk assessment and mitigation
• Well materials and construction
• Operation & Maintenance and Monitoring &
Verification plans designed to protect health,
safety, and the environment
Virtually every section of Z741 includes requirements and
recommendations to prevent leakage and ensure safety
Impact of Z741 on Stakeholder
Engagement and Safety
Impact of Z741: Key Points
• Safety sections are quite detailed and
prescriptive; public engagement sections are
general and focus on principles
• Key is how Z741 affects perceived safety risks
• Public engagement sections may not provide
sufficient guidance
Impact of Z741 on Safety
Safety:
• Z741 should ensure implementation of best
practices and further minimize safety risks
• Perceived safety risk is the real issue
• Public tends to focus only on severity of
consequences, on which they can have
misperceptions
Impact of Z741 on Perceived Safety
• The extent to which Z741 impacts perceived
safety will depend on trust in CSA process and
standard versus government regulations.
• Successfully explaining probability of occurrence
and addressing misperceptions about
consequences requires risk communication
• Z741 identifies objectives for risk
communication but not how to conduct effective
risk communication
Risk Communication Best Practices
• Use language appropriate for the audience ()
• Be open and honest ()
• Put risks in context public understands
• Where possible, partner with trusted
messengers
• Acknowledge knowledge gaps and identify
plans to address them
• Make extensive project information available
Impact of Z741 on Public Engagement
• Engage early and often ()
• Use a variety of communication/engagement mechanisms ()
• Meaningfully involve stakeholders in project decisions ()
Specifics
• Conduct social site characterization at the project outset to
identify stakeholders, concerns, misperceptions
• Start engagement even before site characterization
• Develop and implement processes to obtain and incorporate
stakeholder feedback
Public engagement principles generally reflect best
practices but do not provide detail on implementation.
Standards, Public Engagement, and Safety
• Are the standards achievable?
• Are the standards sufficient?
• Are the standards detailed enough? Should
they be more prescriptive about public
engagement and risk communication?
• Are the standards applicable worldwide?
Group discussion questions:
www.NaviusResearch.com
Questions?
Navius Research Inc. Vancouver | Toronto
CSA Z741-12 – Geological Storage
of CO2:
Impact on Project Costs
Allan Greeves
Manager, Weyburn
Cenovus Energy Inc.
Global CCS Institute Workshop | Calgary, AB | June 6, 2013
Disclaimer
This document contains forward-looking information prepared and provided for the
sole purpose of facilitating public consultation in respect of regulatory applications
and is not intended to be, and should not be, relied upon for the purpose of making
investment decisions, including without limitation, to purchase, hold or sell any
securities of Cenovus Energy Inc. Additional information regarding Cenovus Energy Inc.
is available at www.cenovus.com.
Impact of standards on project costs
• How can we set guidelines to
ensure effective standards that
are not overly prescriptive,
causing unnecessary costs (Capex,
Opex, MMV)?
• Can standards in fact lower the
life-cycle costs of a project?
• To what extent have projects been
used as guideposts or adoption
from other projects such as in the
oil and gas industry?
Impacts of standards on project costs
• Impetus for standard development
– 1.1 (a) “This Standard establishes requirements and
recommendations for the geological storage of carbon
dioxide. The purpose of these requirements is to
promote environmentally safe and long-term
containment of carbon dioxide in a way that
minimizes risks to the environment and human
health.” 1
– Standards provides operators, regulators and the
public with knowledge sharing, careful considerations
applicable with the storage of CO2, and provides
guidance for project planning
1. CSA 741-12 Geological storage of carbon dioxide, October 2012, Pg 1.
CSA Z741-12 Geological Storage of CO2
Storage project life cycle
Post-injection period
Entity Site
screening
and selection
period
Site
characterization
period
Design and
development
period
Operational
period
Closure
period
Post closure
period (not
included in
the Standard)
(Private)
operator
Regulatory
authority
Designated
authority
Limits of the Standard
Iterative
process
Injection
starts
Cessation of
injection
Source: CSA Z741-12 Geological storage of carbon dioxide, October 2012, Pg 2
Application of standards
• CSA Z741-12 was created by a diverse team of experts
– Oil & gas E&P companies
– Oil & gas service companies
– Environmental NGO’s
– University researchers
– Research organizations
– Regulators
– Environmental service companies
– The technical committee worked hard to find the balance between
prescriptiveness and flexibility to incorporate site specific conditions
Applying standards
• A proponent is considering its options for reducing
its carbon footprint
– Is geological storage an option?
– Where to begin?
• Standards provide guidance as to the expectations
and considerations necessary for a successful
project:
– Reduce cycle time to understanding the potential scope
of the project
– Provide guidance on the expertize necessary to evaluate
the project
Continuous improvement
Continuous improvement is a key
component of CSA Z741-12
• Recognition of ever improving
technology
• Recognition of ever changing
expectations
• Opportunity to reduce costs
with increased industry
knowledge
• Opportunity to reduce costs
with increased site specific
knowledge
Plan Execute
ReviewImprove
Project life cycle – stage gate cost profileSiteScreening
SiteSelection
Site
Characterization
Time
CumulativeCost
Monitoring & verification
Site screening, selection &
characterization
Site screening Cost considerations
• Storage capacity
• Potential injection capability
• Seal (above & below) the storage unit
• Seismic or tectonic stability
• Faulting / fracturing
• Over-pressured systems
• Hydrodynamic system
• Number of wells already penetrating
the seals / storage unit
• Primarily an ‘office’ assessment
• Utilizes readily available data &
information
• May not require the acquisition of new
data
• May require additional consulting
expertise to conduct the review
• Iterative process – may need to
evaluate several potential storage units
Site screening, selection &
characterization
Site selection Cost considerations
• Builds upon site screening information and
analysis
• Further refines understanding of capacity,
injectivity, storage security (seal integrity
due to faulting, existing wells, etc)
• Explores other requirements like pore space
ownership, other subsurface activities,
surface considerations (lakes, rivers,
population centres, land use, etc)
• Continue to use existing data & information
• Review of core from existing wells,
petrophysical well log analysis, simple
models to assess injectivity, pressure /
hydrodynamic studies
• Review of mineral land tenure records
• Review of surface culture and future land
use including restrictions due to
environmental or heritage concerns
Site screening, selection &
characterization
Site characterization & assessment Cost considerations
Detailed assessment of:
• Geology & hydrogeology of the storage unit
• Characterization of confining strata
• Primary seal
• Secondary barriers to CO2 leakage
• Baseline geochemistry
• Baseline geomechanics
• Well characterization
At this stage new data may be required
including:
• Seismic data (2D & possibly 3D)
• May include the drilling of an exploration or
pilot well for:
• Core & core analysis of storage unit
and seal(s)
• petrophysical & cased hole logging
• DST & well test data (pressure,
injectivity, existing pore fluid analysis)
• Lab studies of fluid compatibility (CO2 with
rock, pore fluids)
• Lab assessment of rock strength properties,
thermal properties, rock deposition &
mineralization characteristics
Site screening, selection &
characterization
Modeling for site characterization Cost considerations
Integration of the acquired data will allow the
construction of:
• Geological static model - areal extent,
stratigraphy, lithology / facies, structure, porosity /
permeability distribution, pore saturations, pressure
/ geothermal regime, initial stress regime
• Flow modeling – assess storage capacity, injectivity,
pressure and plume distribution & movement, fate of
displaced water
• Geochemical modeling – chemical reactions
between injected CO2 and storage unit rock & fluids,
mineral trapping
• Geomechanical modeling – strength of the
primary seal, fault reactivation, potential for induced
seismicity, impact on well integrity
• Integration of existing and captured data into
these various models will require skilled
expertise in various geology, geophysics and
engineering
• Modeling requires calibration to known
behavior (history matching)
• Modeling will allow for scenario analysis of
areas of uncertainty
• Modeling will have an impact on the time
allocated to assess the potential site
• Modeling will help inform the proponent as
well as the regulator and public of the
subsurface impact of the storage project
• Modeling will be an iterative effort,
incorporating new data as it becomes available
(piloting, development)
Well infrastructure development
• Well construction includes the design &
execution for the creation of:
– Wellbore
– Internal well completion,
– Surface wellhead
– Abandonment of infrastructure at the end of the
project
Wellbore design – what makes a well CO2 compliant?
• Number of casing strings required
– Groundwater protection
– Protection of porous zones above storage unit
– Potential lost circulation zones
• Designing to expected service conditions:
– Is the CO2 stream dehydrated?
– Does the stream contain excessive impurities (NOx,
SOx, H2S, O2)?
– Pressure
– Temperature
• Anticipated injection rates
– Hole/casing diameter appropriate for the injection
string and packer assembly required
• Core, DST, logging requirements
• Monitoring
Wellbore design – drilling to make a well CO2 compliant
Drill & Case
• Typical oil and gas well design includes
3 casing strings: conductor, surface
casing & production (long-string)
• Only the long-string is in contact with
the CO2 storage unit
• CSA Z741 requires the casing across the
storage unit be made of corrosion
material like chrome or stainless steel
• CSA Z741 refers to various API
specifications for cementing but also
expects cement design to offer
additional chemical resistance to CO2
degradation to apply latest technologies
Wellbore design – what makes a well CO2 compliant?
Drill & Case (other considerations)
• High standard of care / QA/QC
– Drilling mud system
– Attention to casing centralization
particularly over storage unit, primary
seal and secondary seal
– Cement blend preparation and
placement (compatible water, additive
concentrations, over displacement, etc)
• What kind of monitoring is required?
– Monitoring well vs injection well
– Piloting well vs development well
– Accessibility required for time lapsed
evaluation
– Integrity concerns balanced against
accessibility, monitoring equipment
Drilling a CO2 compliant wellbore
Vertical Well Drilling Costs
Consulting & Supervision Logging, Coring, Mud Gas
Surface Casing & Cement Production Casing & Cement
Drilling Rig & Support Mud Systems & Disposal
Other Services
• Approximately 1/3 of the cost
of drilling a well is for casing
and cement left in the hole
• Remainder of the costs are for
drilling and evaluation of the
well
Wellbore design – what makes a well CO2 compliant?
Well completion
• Designing to expected service
conditions:
• Is the CO2 stream dehydrated?
• Does the stream contain excessive
impurities (NOx, SOx, H2S, O2)?
• Pressure
• Temperature
• Anticipated injection rates
• Annulus inhibited fluid type
• Cement & casing integrity logging
requirements
• Monitoring requirements
Materials selection
• Upgraded materials like this
packer element may be
required to avoid adverse
effects due to CO2
Impact of service conditions
• This coiled tubing was recovered
from an injection well converted
from straight CO2 injection to a
water-alternating-gas (WAG)
injection configuration
• Drehydrated CO2
• Non-coated tubulars
• Coiled tubing string was in place
for ~12 years with little corrosion
with exception of this point
midway down the well
Wellbore design – what makes a wellhead CO2 compliant?
Wellhead design
• Designing to expected service
conditions:
• Is the CO2 stream dehydrated?
• Does the stream contain excessive
impurities (NOx, SOx, H2S, O2)?
• Pressure
• Temperature
• Anticipated injection rates
• Monitoring requirements
• Accessibility requirements to the
wellbore
• Flow / ESD control
Designing surface piping
CO2 compatible seals in
surface piping:
• CO2 does behave differently
than oil & gas industry fluids
• Sometimes it takes a ‘low
tech’ way of
troubleshooting for
performance improvement
Monitoring & verification
Monitoring & verification Cost considerations
“Measurement and surveillance activities necessary to
provide and assurance of the integrity of CO2 storage”2:
• Used at all stages of development – begins with baseline
data right through to the closure of the project
• Provide evidence that CO2 placement is secure
• Allows for comparisons between predicted and
actual conditions
• various data points and perspectives from seismic, to
injection wells and observation wells
• models updated with actual performance data allow
for performance improvement and confidence in
ultimate fate of CO2
• Support quantification efforts
• Is not just one method of monitoring
• Is a suite of site specific approaches to compare to
baseline
• Will require additional project expenditures for:
• Seismic
• Observation wells
• Specialty hardware in injection wells
• Pressure, temperature, flow, composition
monitoring equipment / tools
• Data capture instrumentation and analysis (ie:
SCADA)
• Repeated capture over time
• Updated over time as necessary
• Expanded over time as necessary
2. CSA 741-12 Geological storage of carbon dioxide, October 2012, Pg 55.
Closure
Closure Cost considerations
“purpose… is to provide guidance to and establish
predictability for project operators and regulatory
authorities of..
a) Sufficient understanding of storage site’s
characteristics
b) Low residual risk
c) Adequate well integrity” 3
• Includes incorporation of learning’s throughout the
project life
• Development infrastructure in place and its
condition
• Monitoring & verification results
• Integration of project performance data into
dynamic models
• Updated risk management plan
• Includes the abandonment of storage infrastructure
wells and facilities
• Will likely be done in a staged approach to monitor
for well integrity and containment effectiveness
• Will take some time (year’s) to provide confidence for
risk management plan
• Need to continue monitoring efforts
• Need to retain experts who will update
dynamic models
• End result will ‘qualify’ project for potential hand off
to designated authority
3. CSA 741-12 Geological storage of carbon dioxide, October 2012, Pg 60
Summary
• By providing guidance and expectations
standards can lower the life-cycle costs
of a project
– Improve project understanding with
baseline work and monitoring
– Application of best practices for
development design and quality
– Integrate risk assessment with
monitoring & verification to identify
specific areas of concern
• Learning’s from the oil & gas industry
are directly applicable
– Complementary skills
– Complementary resources and
equipment
• End result is a project with maximum
benefit with effectively managed risks
• Special thanks to:
– Canadian Standards Association
– Cenovus Energy Inc.
Questions?
Session 4
Will Z741 Mitigate Project Risks?
The Role of Storage Standards in the
Deployment of CCS
Rob Bioletti, P.Eng.
Director, CCS Policy
Government of Alberta
June 6, 2013
Reasons for
Standardization
86
Climate Change Mitigation
• No one technology can stabilize greenhouse
gas emissions alone.
• A combination of several climate mitigation
technologies is needed for robust climate
change.
• Standards will aid in the widespread
deployment of CCS.
87
Knowledge Sharing and
Innovation
• Standards will aid in the transfer of
knowledge between jurisdictions.
• Standards need not be prescriptive.
• Organizational structure can aid in separating
well defined versus emerging activities.
88
Public Perception of CCS
• Public opposition has caused cancelation of
several CCS projects throughout the world.
• Standards can help provide assurances that
CCS is safe.
89
CSA Z741
How this Standard Can
Mitigate CCS Project Risks
90
Site Screening, Selection, and
Characterization - Section 5
Site screening and selection will identify
prospective CO2 storage sites that have met the
following criteria:
• Sufficient Capacity;
• Sufficient Injectivity; and
• Effective Retention.
91
Risk Management – Section 6
Effective risk management should:
• Demonstrate achievement of objectives;
• Improve performance relative to elements of
concern;
• Support strategic planning;
• Develop robust project and change management
processes;
• Help decision makers make informed and
prioritized choices;
• Account for uncertainty; and
• Recognize stakeholder intentions.
92
Well Infrastructure Development
- Section 7
Outline criteria needing to be met in order to
best mitigate risk (CO2 leaks, infrastructure
problems, etc.) such criteria include:
• Materials;
• Design;
• Construction;
• Corrosion Control; and
• Operation and Maintenance.
93
Monitoring and Verification
– Section 8
The monitoring and verification standard will be
flexible and adaptable to changes in storage and
injection conditions, the criteria the standards
will address the following concerns:
• Health,
• Safety,
• Environmental Risks; and
• Storage Performance
94
Risks for CCS Projects
95
Risk Profile for a CO2 Storage Site
Source: Benson 2007
Examples of Other Risk Elements
• Environmental
– Natural environment
– Health and safety
– Legal and regulatory environment
• Economic
– Project financing
– Competition with other resources
• Social
– Public support
– Politics
97
Risk Management Process
98
Source: CSA-Z741-12
99
Group Activity!
Question:
Which risk element is the most important
to address for CCS projects?
Tool: Simplified Decision Matrix
Assessing the relative importance of alternatives
Steps
1. Brainstorm up to 5 risk elements
- Environmental (e.g. operational, safety, regulatory)
- Economic (e.g. financing, resource competition)
- Social (e.g. public support, reputation, politics)
2. Assign weights to each element
- Stakeholder views:
Petroleum engineer, policy analyst, farmer, professor, activist, etc
- Scale of 1 to 3 (1 = low importance, 3 = high importance)
- Group must agree on the weight!
3. Score each risk by stakeholder perspective
- Scale of 1 to 5 (1 = low importance, 5 = high importance)
4. Multiply stakeholder scores by weight
5. Total all scores to find “winner”
6. If there is disagreement, re-visit weights or scores
100
Example Decision Matrix
101
Stakeholder Score (1-5)
Industry Government Public Academic
3 (x1) = 3 1 (x1) = 1 2 (x1) = 2
Total
5+3+1+2
= 11
5 (x1) = 5
4 (x2) = 8
4 (x3) = 12
2 (x1) = 2
Weight
(1-3)
1
2
3
1
Risk
Element
Financing
Public
Support
Safety
Etc.
Etc.
Brainstorm Agree Assess
Discussion
1. What were the results? Did one clear
winner emerge?
2. How did stakeholder views help or
hinder the decisions?
3. Should certain risk elements have
more focus?
4. How can CSA Z741 help mitigate
these risks? Are there areas for
improvement?
102
Thank You
Rob Bioletti, P.Eng.
+1 780 644 3204
Rob.Bioletti@gov.ab.ca
www.energy.alberta.ca
Canadian-US standards workshop, Calgary, 6 June 2013

Contenu connexe

Similaire à Canadian-US standards workshop, Calgary, 6 June 2013

Accelerating to Net Zero with Hydrogen Blending Standards Development in the ...
Accelerating to Net Zero with Hydrogen Blending Standards Development in the ...Accelerating to Net Zero with Hydrogen Blending Standards Development in the ...
Accelerating to Net Zero with Hydrogen Blending Standards Development in the ...KTN
 
Boundaries | Gary Davis
Boundaries | Gary DavisBoundaries | Gary Davis
Boundaries | Gary Davisicarb
 
Webinar: Global Status of CCS: 2014 - Powering ahead in The Americas
Webinar: Global Status of CCS: 2014 - Powering ahead in The AmericasWebinar: Global Status of CCS: 2014 - Powering ahead in The Americas
Webinar: Global Status of CCS: 2014 - Powering ahead in The AmericasGlobal CCS Institute
 
ISO 14064_2018.pdf
ISO 14064_2018.pdfISO 14064_2018.pdf
ISO 14064_2018.pdfMau Tau
 
CMS’s Impact – Driven Collaboration Model Addressing Industrial GHGs, Richard...
CMS’s Impact – Driven Collaboration Model Addressing Industrial GHGs, Richard...CMS’s Impact – Driven Collaboration Model Addressing Industrial GHGs, Richard...
CMS’s Impact – Driven Collaboration Model Addressing Industrial GHGs, Richard...UK Carbon Capture and Storage Research Centre
 
Barry Jones - Global Status of CCS – Presentation at the Global CCS Institute...
Barry Jones - Global Status of CCS – Presentation at the Global CCS Institute...Barry Jones - Global Status of CCS – Presentation at the Global CCS Institute...
Barry Jones - Global Status of CCS – Presentation at the Global CCS Institute...Global CCS Institute
 
CCS within the UNFCCC - Luke Warren, CCSA
CCS within the UNFCCC - Luke Warren, CCSACCS within the UNFCCC - Luke Warren, CCSA
CCS within the UNFCCC - Luke Warren, CCSAGlobal CCS Institute
 
Misa Going Green V3
Misa Going Green V3Misa Going Green V3
Misa Going Green V3kmayfield
 
2014 Sustainability Report Conference Call
2014 Sustainability Report Conference Call2014 Sustainability Report Conference Call
2014 Sustainability Report Conference CallTeckResourcesLtd
 
Gowlings - Environmental Law for Business Seminar: Chemical & Substances Mana...
Gowlings - Environmental Law for Business Seminar: Chemical & Substances Mana...Gowlings - Environmental Law for Business Seminar: Chemical & Substances Mana...
Gowlings - Environmental Law for Business Seminar: Chemical & Substances Mana...This account is closed
 
REDD Offset Working Group - Overview of Recommendations
REDD Offset Working Group -  Overview of RecommendationsREDD Offset Working Group -  Overview of Recommendations
REDD Offset Working Group - Overview of RecommendationsJohn Davis
 
Effective enforcement of underground storage of carbon dioxide – A presentati...
Effective enforcement of underground storage of carbon dioxide – A presentati...Effective enforcement of underground storage of carbon dioxide – A presentati...
Effective enforcement of underground storage of carbon dioxide – A presentati...Global CCS Institute
 
Gary Davis | Setting the Boundaries
Gary Davis | Setting the BoundariesGary Davis | Setting the Boundaries
Gary Davis | Setting the Boundariesicarb
 
IHA 2013 World Congress: IHA: Introduction to the Hydropower Sustainability A...
IHA 2013 World Congress: IHA: Introduction to the Hydropower Sustainability A...IHA 2013 World Congress: IHA: Introduction to the Hydropower Sustainability A...
IHA 2013 World Congress: IHA: Introduction to the Hydropower Sustainability A...International Hydropower Association
 
Windpower Monthly Offshore Consenting Conference Brochure
Windpower Monthly Offshore Consenting Conference BrochureWindpower Monthly Offshore Consenting Conference Brochure
Windpower Monthly Offshore Consenting Conference Brochuregm330
 
Four Elements to Strengthen Your Hazardous Waste Management Program
Four Elements to Strengthen Your Hazardous Waste Management ProgramFour Elements to Strengthen Your Hazardous Waste Management Program
Four Elements to Strengthen Your Hazardous Waste Management ProgramTriumvirate Environmental
 
ESG Compliance & Project Financing
ESG Compliance & Project FinancingESG Compliance & Project Financing
ESG Compliance & Project FinancingLR Consultants
 

Similaire à Canadian-US standards workshop, Calgary, 6 June 2013 (20)

UK submarine dismantling: A case study in programme management
UK submarine dismantling: A case study in programme managementUK submarine dismantling: A case study in programme management
UK submarine dismantling: A case study in programme management
 
Accelerating to Net Zero with Hydrogen Blending Standards Development in the ...
Accelerating to Net Zero with Hydrogen Blending Standards Development in the ...Accelerating to Net Zero with Hydrogen Blending Standards Development in the ...
Accelerating to Net Zero with Hydrogen Blending Standards Development in the ...
 
Boundaries | Gary Davis
Boundaries | Gary DavisBoundaries | Gary Davis
Boundaries | Gary Davis
 
Webinar: Global Status of CCS: 2014 - Powering ahead in The Americas
Webinar: Global Status of CCS: 2014 - Powering ahead in The AmericasWebinar: Global Status of CCS: 2014 - Powering ahead in The Americas
Webinar: Global Status of CCS: 2014 - Powering ahead in The Americas
 
ISO 14064_2018.pdf
ISO 14064_2018.pdfISO 14064_2018.pdf
ISO 14064_2018.pdf
 
CMS’s Impact – Driven Collaboration Model Addressing Industrial GHGs, Richard...
CMS’s Impact – Driven Collaboration Model Addressing Industrial GHGs, Richard...CMS’s Impact – Driven Collaboration Model Addressing Industrial GHGs, Richard...
CMS’s Impact – Driven Collaboration Model Addressing Industrial GHGs, Richard...
 
Barry Jones - Global Status of CCS – Presentation at the Global CCS Institute...
Barry Jones - Global Status of CCS – Presentation at the Global CCS Institute...Barry Jones - Global Status of CCS – Presentation at the Global CCS Institute...
Barry Jones - Global Status of CCS – Presentation at the Global CCS Institute...
 
CCS within the UNFCCC - Luke Warren, CCSA
CCS within the UNFCCC - Luke Warren, CCSACCS within the UNFCCC - Luke Warren, CCSA
CCS within the UNFCCC - Luke Warren, CCSA
 
Ching vcs methods ws oct 2011
Ching vcs methods ws oct 2011Ching vcs methods ws oct 2011
Ching vcs methods ws oct 2011
 
Misa Going Green V3
Misa Going Green V3Misa Going Green V3
Misa Going Green V3
 
2014 Sustainability Report Conference Call
2014 Sustainability Report Conference Call2014 Sustainability Report Conference Call
2014 Sustainability Report Conference Call
 
Gowlings - Environmental Law for Business Seminar: Chemical & Substances Mana...
Gowlings - Environmental Law for Business Seminar: Chemical & Substances Mana...Gowlings - Environmental Law for Business Seminar: Chemical & Substances Mana...
Gowlings - Environmental Law for Business Seminar: Chemical & Substances Mana...
 
REDD Offset Working Group - Overview of Recommendations
REDD Offset Working Group -  Overview of RecommendationsREDD Offset Working Group -  Overview of Recommendations
REDD Offset Working Group - Overview of Recommendations
 
Effective enforcement of underground storage of carbon dioxide – A presentati...
Effective enforcement of underground storage of carbon dioxide – A presentati...Effective enforcement of underground storage of carbon dioxide – A presentati...
Effective enforcement of underground storage of carbon dioxide – A presentati...
 
Gary Davis | Setting the Boundaries
Gary Davis | Setting the BoundariesGary Davis | Setting the Boundaries
Gary Davis | Setting the Boundaries
 
IHA 2013 World Congress: IHA: Introduction to the Hydropower Sustainability A...
IHA 2013 World Congress: IHA: Introduction to the Hydropower Sustainability A...IHA 2013 World Congress: IHA: Introduction to the Hydropower Sustainability A...
IHA 2013 World Congress: IHA: Introduction to the Hydropower Sustainability A...
 
Windpower Monthly Offshore Consenting Conference Brochure
Windpower Monthly Offshore Consenting Conference BrochureWindpower Monthly Offshore Consenting Conference Brochure
Windpower Monthly Offshore Consenting Conference Brochure
 
Four Elements to Strengthen Your Hazardous Waste Management Program
Four Elements to Strengthen Your Hazardous Waste Management ProgramFour Elements to Strengthen Your Hazardous Waste Management Program
Four Elements to Strengthen Your Hazardous Waste Management Program
 
Andy Leonard - Digital Innovation in the Oil & Gas Industry
Andy Leonard - Digital Innovation in the Oil & Gas IndustryAndy Leonard - Digital Innovation in the Oil & Gas Industry
Andy Leonard - Digital Innovation in the Oil & Gas Industry
 
ESG Compliance & Project Financing
ESG Compliance & Project FinancingESG Compliance & Project Financing
ESG Compliance & Project Financing
 

Plus de Global CCS Institute

Northern Lights: A European CO2 transport and storage project
Northern Lights: A European CO2 transport and storage project Northern Lights: A European CO2 transport and storage project
Northern Lights: A European CO2 transport and storage project Global CCS Institute
 
Webinar: Policy priorities to incentivise large scale deployment of CCS
Webinar: Policy priorities to incentivise large scale deployment of CCSWebinar: Policy priorities to incentivise large scale deployment of CCS
Webinar: Policy priorities to incentivise large scale deployment of CCSGlobal CCS Institute
 
Telling the Norwegian CCS Story | PART II: CCS: the path to a sustainable and...
Telling the Norwegian CCS Story | PART II: CCS: the path to a sustainable and...Telling the Norwegian CCS Story | PART II: CCS: the path to a sustainable and...
Telling the Norwegian CCS Story | PART II: CCS: the path to a sustainable and...Global CCS Institute
 
Telling the Norwegian CCS Story | PART I: CCS: the path to sustainable and em...
Telling the Norwegian CCS Story | PART I: CCS: the path to sustainable and em...Telling the Norwegian CCS Story | PART I: CCS: the path to sustainable and em...
Telling the Norwegian CCS Story | PART I: CCS: the path to sustainable and em...Global CCS Institute
 
Decarbonizing Industry Using Carbon Capture: Norway Full Chain CCS
Decarbonizing Industry Using Carbon Capture: Norway Full Chain CCSDecarbonizing Industry Using Carbon Capture: Norway Full Chain CCS
Decarbonizing Industry Using Carbon Capture: Norway Full Chain CCSGlobal CCS Institute
 
Cutting Cost of CO2 Capture in Process Industry (CO2stCap) Project overview &...
Cutting Cost of CO2 Capture in Process Industry (CO2stCap) Project overview &...Cutting Cost of CO2 Capture in Process Industry (CO2stCap) Project overview &...
Cutting Cost of CO2 Capture in Process Industry (CO2stCap) Project overview &...Global CCS Institute
 
Membrane Technology & Research (MTR) Presentation
Membrane Technology & Research (MTR) PresentationMembrane Technology & Research (MTR) Presentation
Membrane Technology & Research (MTR) PresentationGlobal CCS Institute
 
Mission Innovation: Carbon Capture Innovation Challenge
Mission Innovation: Carbon Capture Innovation ChallengeMission Innovation: Carbon Capture Innovation Challenge
Mission Innovation: Carbon Capture Innovation ChallengeGlobal CCS Institute
 
Can the United States Achieve a Low Carbon Economy by 2050?
Can the United States Achieve a Low Carbon Economy by 2050?Can the United States Achieve a Low Carbon Economy by 2050?
Can the United States Achieve a Low Carbon Economy by 2050?Global CCS Institute
 
Webinar Series: Carbon Sequestration Leadership Forum Part 1. CCUS in the Uni...
Webinar Series: Carbon Sequestration Leadership Forum Part 1. CCUS in the Uni...Webinar Series: Carbon Sequestration Leadership Forum Part 1. CCUS in the Uni...
Webinar Series: Carbon Sequestration Leadership Forum Part 1. CCUS in the Uni...Global CCS Institute
 
Energy Security and Prosperity in Australia: A roadmap for carbon capture and...
Energy Security and Prosperity in Australia: A roadmap for carbon capture and...Energy Security and Prosperity in Australia: A roadmap for carbon capture and...
Energy Security and Prosperity in Australia: A roadmap for carbon capture and...Global CCS Institute
 
Webinar Series: Public engagement, education and outreach for CCS. Part 5: So...
Webinar Series: Public engagement, education and outreach for CCS. Part 5: So...Webinar Series: Public engagement, education and outreach for CCS. Part 5: So...
Webinar Series: Public engagement, education and outreach for CCS. Part 5: So...Global CCS Institute
 
Managing carbon geological storage and natural resources in sedimentary basins
Managing carbon geological storage and natural resources in sedimentary basinsManaging carbon geological storage and natural resources in sedimentary basins
Managing carbon geological storage and natural resources in sedimentary basinsGlobal CCS Institute
 
Mercury and other trace metals in the gas from an oxy-combustion demonstratio...
Mercury and other trace metals in the gas from an oxy-combustion demonstratio...Mercury and other trace metals in the gas from an oxy-combustion demonstratio...
Mercury and other trace metals in the gas from an oxy-combustion demonstratio...Global CCS Institute
 
Webinar Series: Public engagement, education and outreach for CCS. Part 4: Is...
Webinar Series: Public engagement, education and outreach for CCS. Part 4: Is...Webinar Series: Public engagement, education and outreach for CCS. Part 4: Is...
Webinar Series: Public engagement, education and outreach for CCS. Part 4: Is...Global CCS Institute
 
Laboratory-scale geochemical and geomechanical testing of near wellbore CO2 i...
Laboratory-scale geochemical and geomechanical testing of near wellbore CO2 i...Laboratory-scale geochemical and geomechanical testing of near wellbore CO2 i...
Laboratory-scale geochemical and geomechanical testing of near wellbore CO2 i...Global CCS Institute
 
Webinar Series: Public engagement, education and outreach for CCS. Part 3: Ca...
Webinar Series: Public engagement, education and outreach for CCS. Part 3: Ca...Webinar Series: Public engagement, education and outreach for CCS. Part 3: Ca...
Webinar Series: Public engagement, education and outreach for CCS. Part 3: Ca...Global CCS Institute
 
Water use of thermal power plants equipped with CO2 capture systems
Water use of thermal power plants equipped with CO2 capture systemsWater use of thermal power plants equipped with CO2 capture systems
Water use of thermal power plants equipped with CO2 capture systemsGlobal CCS Institute
 

Plus de Global CCS Institute (20)

Northern Lights: A European CO2 transport and storage project
Northern Lights: A European CO2 transport and storage project Northern Lights: A European CO2 transport and storage project
Northern Lights: A European CO2 transport and storage project
 
Webinar: Policy priorities to incentivise large scale deployment of CCS
Webinar: Policy priorities to incentivise large scale deployment of CCSWebinar: Policy priorities to incentivise large scale deployment of CCS
Webinar: Policy priorities to incentivise large scale deployment of CCS
 
Telling the Norwegian CCS Story | PART II: CCS: the path to a sustainable and...
Telling the Norwegian CCS Story | PART II: CCS: the path to a sustainable and...Telling the Norwegian CCS Story | PART II: CCS: the path to a sustainable and...
Telling the Norwegian CCS Story | PART II: CCS: the path to a sustainable and...
 
Telling the Norwegian CCS Story | PART I: CCS: the path to sustainable and em...
Telling the Norwegian CCS Story | PART I: CCS: the path to sustainable and em...Telling the Norwegian CCS Story | PART I: CCS: the path to sustainable and em...
Telling the Norwegian CCS Story | PART I: CCS: the path to sustainable and em...
 
Decarbonizing Industry Using Carbon Capture: Norway Full Chain CCS
Decarbonizing Industry Using Carbon Capture: Norway Full Chain CCSDecarbonizing Industry Using Carbon Capture: Norway Full Chain CCS
Decarbonizing Industry Using Carbon Capture: Norway Full Chain CCS
 
Cutting Cost of CO2 Capture in Process Industry (CO2stCap) Project overview &...
Cutting Cost of CO2 Capture in Process Industry (CO2stCap) Project overview &...Cutting Cost of CO2 Capture in Process Industry (CO2stCap) Project overview &...
Cutting Cost of CO2 Capture in Process Industry (CO2stCap) Project overview &...
 
Global CCS Institute Presentation
Global CCS Institute PresentationGlobal CCS Institute Presentation
Global CCS Institute Presentation
 
ION Engineering Presentation
ION Engineering PresentationION Engineering Presentation
ION Engineering Presentation
 
Membrane Technology & Research (MTR) Presentation
Membrane Technology & Research (MTR) PresentationMembrane Technology & Research (MTR) Presentation
Membrane Technology & Research (MTR) Presentation
 
Mission Innovation: Carbon Capture Innovation Challenge
Mission Innovation: Carbon Capture Innovation ChallengeMission Innovation: Carbon Capture Innovation Challenge
Mission Innovation: Carbon Capture Innovation Challenge
 
Can the United States Achieve a Low Carbon Economy by 2050?
Can the United States Achieve a Low Carbon Economy by 2050?Can the United States Achieve a Low Carbon Economy by 2050?
Can the United States Achieve a Low Carbon Economy by 2050?
 
Webinar Series: Carbon Sequestration Leadership Forum Part 1. CCUS in the Uni...
Webinar Series: Carbon Sequestration Leadership Forum Part 1. CCUS in the Uni...Webinar Series: Carbon Sequestration Leadership Forum Part 1. CCUS in the Uni...
Webinar Series: Carbon Sequestration Leadership Forum Part 1. CCUS in the Uni...
 
Energy Security and Prosperity in Australia: A roadmap for carbon capture and...
Energy Security and Prosperity in Australia: A roadmap for carbon capture and...Energy Security and Prosperity in Australia: A roadmap for carbon capture and...
Energy Security and Prosperity in Australia: A roadmap for carbon capture and...
 
Webinar Series: Public engagement, education and outreach for CCS. Part 5: So...
Webinar Series: Public engagement, education and outreach for CCS. Part 5: So...Webinar Series: Public engagement, education and outreach for CCS. Part 5: So...
Webinar Series: Public engagement, education and outreach for CCS. Part 5: So...
 
Managing carbon geological storage and natural resources in sedimentary basins
Managing carbon geological storage and natural resources in sedimentary basinsManaging carbon geological storage and natural resources in sedimentary basins
Managing carbon geological storage and natural resources in sedimentary basins
 
Mercury and other trace metals in the gas from an oxy-combustion demonstratio...
Mercury and other trace metals in the gas from an oxy-combustion demonstratio...Mercury and other trace metals in the gas from an oxy-combustion demonstratio...
Mercury and other trace metals in the gas from an oxy-combustion demonstratio...
 
Webinar Series: Public engagement, education and outreach for CCS. Part 4: Is...
Webinar Series: Public engagement, education and outreach for CCS. Part 4: Is...Webinar Series: Public engagement, education and outreach for CCS. Part 4: Is...
Webinar Series: Public engagement, education and outreach for CCS. Part 4: Is...
 
Laboratory-scale geochemical and geomechanical testing of near wellbore CO2 i...
Laboratory-scale geochemical and geomechanical testing of near wellbore CO2 i...Laboratory-scale geochemical and geomechanical testing of near wellbore CO2 i...
Laboratory-scale geochemical and geomechanical testing of near wellbore CO2 i...
 
Webinar Series: Public engagement, education and outreach for CCS. Part 3: Ca...
Webinar Series: Public engagement, education and outreach for CCS. Part 3: Ca...Webinar Series: Public engagement, education and outreach for CCS. Part 3: Ca...
Webinar Series: Public engagement, education and outreach for CCS. Part 3: Ca...
 
Water use of thermal power plants equipped with CO2 capture systems
Water use of thermal power plants equipped with CO2 capture systemsWater use of thermal power plants equipped with CO2 capture systems
Water use of thermal power plants equipped with CO2 capture systems
 

Dernier

Developer Data Modeling Mistakes: From Postgres to NoSQL
Developer Data Modeling Mistakes: From Postgres to NoSQLDeveloper Data Modeling Mistakes: From Postgres to NoSQL
Developer Data Modeling Mistakes: From Postgres to NoSQLScyllaDB
 
Are Multi-Cloud and Serverless Good or Bad?
Are Multi-Cloud and Serverless Good or Bad?Are Multi-Cloud and Serverless Good or Bad?
Are Multi-Cloud and Serverless Good or Bad?Mattias Andersson
 
SIP trunking in Janus @ Kamailio World 2024
SIP trunking in Janus @ Kamailio World 2024SIP trunking in Janus @ Kamailio World 2024
SIP trunking in Janus @ Kamailio World 2024Lorenzo Miniero
 
"Subclassing and Composition – A Pythonic Tour of Trade-Offs", Hynek Schlawack
"Subclassing and Composition – A Pythonic Tour of Trade-Offs", Hynek Schlawack"Subclassing and Composition – A Pythonic Tour of Trade-Offs", Hynek Schlawack
"Subclassing and Composition – A Pythonic Tour of Trade-Offs", Hynek SchlawackFwdays
 
Commit 2024 - Secret Management made easy
Commit 2024 - Secret Management made easyCommit 2024 - Secret Management made easy
Commit 2024 - Secret Management made easyAlfredo García Lavilla
 
Leverage Zilliz Serverless - Up to 50X Saving for Your Vector Storage Cost
Leverage Zilliz Serverless - Up to 50X Saving for Your Vector Storage CostLeverage Zilliz Serverless - Up to 50X Saving for Your Vector Storage Cost
Leverage Zilliz Serverless - Up to 50X Saving for Your Vector Storage CostZilliz
 
Beyond Boundaries: Leveraging No-Code Solutions for Industry Innovation
Beyond Boundaries: Leveraging No-Code Solutions for Industry InnovationBeyond Boundaries: Leveraging No-Code Solutions for Industry Innovation
Beyond Boundaries: Leveraging No-Code Solutions for Industry InnovationSafe Software
 
Vector Databases 101 - An introduction to the world of Vector Databases
Vector Databases 101 - An introduction to the world of Vector DatabasesVector Databases 101 - An introduction to the world of Vector Databases
Vector Databases 101 - An introduction to the world of Vector DatabasesZilliz
 
Tampa BSides - Chef's Tour of Microsoft Security Adoption Framework (SAF)
Tampa BSides - Chef's Tour of Microsoft Security Adoption Framework (SAF)Tampa BSides - Chef's Tour of Microsoft Security Adoption Framework (SAF)
Tampa BSides - Chef's Tour of Microsoft Security Adoption Framework (SAF)Mark Simos
 
Search Engine Optimization SEO PDF for 2024.pdf
Search Engine Optimization SEO PDF for 2024.pdfSearch Engine Optimization SEO PDF for 2024.pdf
Search Engine Optimization SEO PDF for 2024.pdfRankYa
 
Ensuring Technical Readiness For Copilot in Microsoft 365
Ensuring Technical Readiness For Copilot in Microsoft 365Ensuring Technical Readiness For Copilot in Microsoft 365
Ensuring Technical Readiness For Copilot in Microsoft 3652toLead Limited
 
Training state-of-the-art general text embedding
Training state-of-the-art general text embeddingTraining state-of-the-art general text embedding
Training state-of-the-art general text embeddingZilliz
 
Bun (KitWorks Team Study 노별마루 발표 2024.4.22)
Bun (KitWorks Team Study 노별마루 발표 2024.4.22)Bun (KitWorks Team Study 노별마루 발표 2024.4.22)
Bun (KitWorks Team Study 노별마루 발표 2024.4.22)Wonjun Hwang
 
CloudStudio User manual (basic edition):
CloudStudio User manual (basic edition):CloudStudio User manual (basic edition):
CloudStudio User manual (basic edition):comworks
 
My Hashitalk Indonesia April 2024 Presentation
My Hashitalk Indonesia April 2024 PresentationMy Hashitalk Indonesia April 2024 Presentation
My Hashitalk Indonesia April 2024 PresentationRidwan Fadjar
 
Install Stable Diffusion in windows machine
Install Stable Diffusion in windows machineInstall Stable Diffusion in windows machine
Install Stable Diffusion in windows machinePadma Pradeep
 
Kotlin Multiplatform & Compose Multiplatform - Starter kit for pragmatics
Kotlin Multiplatform & Compose Multiplatform - Starter kit for pragmaticsKotlin Multiplatform & Compose Multiplatform - Starter kit for pragmatics
Kotlin Multiplatform & Compose Multiplatform - Starter kit for pragmaticscarlostorres15106
 
Scanning the Internet for External Cloud Exposures via SSL Certs
Scanning the Internet for External Cloud Exposures via SSL CertsScanning the Internet for External Cloud Exposures via SSL Certs
Scanning the Internet for External Cloud Exposures via SSL CertsRizwan Syed
 
Connect Wave/ connectwave Pitch Deck Presentation
Connect Wave/ connectwave Pitch Deck PresentationConnect Wave/ connectwave Pitch Deck Presentation
Connect Wave/ connectwave Pitch Deck PresentationSlibray Presentation
 
Dev Dives: Streamline document processing with UiPath Studio Web
Dev Dives: Streamline document processing with UiPath Studio WebDev Dives: Streamline document processing with UiPath Studio Web
Dev Dives: Streamline document processing with UiPath Studio WebUiPathCommunity
 

Dernier (20)

Developer Data Modeling Mistakes: From Postgres to NoSQL
Developer Data Modeling Mistakes: From Postgres to NoSQLDeveloper Data Modeling Mistakes: From Postgres to NoSQL
Developer Data Modeling Mistakes: From Postgres to NoSQL
 
Are Multi-Cloud and Serverless Good or Bad?
Are Multi-Cloud and Serverless Good or Bad?Are Multi-Cloud and Serverless Good or Bad?
Are Multi-Cloud and Serverless Good or Bad?
 
SIP trunking in Janus @ Kamailio World 2024
SIP trunking in Janus @ Kamailio World 2024SIP trunking in Janus @ Kamailio World 2024
SIP trunking in Janus @ Kamailio World 2024
 
"Subclassing and Composition – A Pythonic Tour of Trade-Offs", Hynek Schlawack
"Subclassing and Composition – A Pythonic Tour of Trade-Offs", Hynek Schlawack"Subclassing and Composition – A Pythonic Tour of Trade-Offs", Hynek Schlawack
"Subclassing and Composition – A Pythonic Tour of Trade-Offs", Hynek Schlawack
 
Commit 2024 - Secret Management made easy
Commit 2024 - Secret Management made easyCommit 2024 - Secret Management made easy
Commit 2024 - Secret Management made easy
 
Leverage Zilliz Serverless - Up to 50X Saving for Your Vector Storage Cost
Leverage Zilliz Serverless - Up to 50X Saving for Your Vector Storage CostLeverage Zilliz Serverless - Up to 50X Saving for Your Vector Storage Cost
Leverage Zilliz Serverless - Up to 50X Saving for Your Vector Storage Cost
 
Beyond Boundaries: Leveraging No-Code Solutions for Industry Innovation
Beyond Boundaries: Leveraging No-Code Solutions for Industry InnovationBeyond Boundaries: Leveraging No-Code Solutions for Industry Innovation
Beyond Boundaries: Leveraging No-Code Solutions for Industry Innovation
 
Vector Databases 101 - An introduction to the world of Vector Databases
Vector Databases 101 - An introduction to the world of Vector DatabasesVector Databases 101 - An introduction to the world of Vector Databases
Vector Databases 101 - An introduction to the world of Vector Databases
 
Tampa BSides - Chef's Tour of Microsoft Security Adoption Framework (SAF)
Tampa BSides - Chef's Tour of Microsoft Security Adoption Framework (SAF)Tampa BSides - Chef's Tour of Microsoft Security Adoption Framework (SAF)
Tampa BSides - Chef's Tour of Microsoft Security Adoption Framework (SAF)
 
Search Engine Optimization SEO PDF for 2024.pdf
Search Engine Optimization SEO PDF for 2024.pdfSearch Engine Optimization SEO PDF for 2024.pdf
Search Engine Optimization SEO PDF for 2024.pdf
 
Ensuring Technical Readiness For Copilot in Microsoft 365
Ensuring Technical Readiness For Copilot in Microsoft 365Ensuring Technical Readiness For Copilot in Microsoft 365
Ensuring Technical Readiness For Copilot in Microsoft 365
 
Training state-of-the-art general text embedding
Training state-of-the-art general text embeddingTraining state-of-the-art general text embedding
Training state-of-the-art general text embedding
 
Bun (KitWorks Team Study 노별마루 발표 2024.4.22)
Bun (KitWorks Team Study 노별마루 발표 2024.4.22)Bun (KitWorks Team Study 노별마루 발표 2024.4.22)
Bun (KitWorks Team Study 노별마루 발표 2024.4.22)
 
CloudStudio User manual (basic edition):
CloudStudio User manual (basic edition):CloudStudio User manual (basic edition):
CloudStudio User manual (basic edition):
 
My Hashitalk Indonesia April 2024 Presentation
My Hashitalk Indonesia April 2024 PresentationMy Hashitalk Indonesia April 2024 Presentation
My Hashitalk Indonesia April 2024 Presentation
 
Install Stable Diffusion in windows machine
Install Stable Diffusion in windows machineInstall Stable Diffusion in windows machine
Install Stable Diffusion in windows machine
 
Kotlin Multiplatform & Compose Multiplatform - Starter kit for pragmatics
Kotlin Multiplatform & Compose Multiplatform - Starter kit for pragmaticsKotlin Multiplatform & Compose Multiplatform - Starter kit for pragmatics
Kotlin Multiplatform & Compose Multiplatform - Starter kit for pragmatics
 
Scanning the Internet for External Cloud Exposures via SSL Certs
Scanning the Internet for External Cloud Exposures via SSL CertsScanning the Internet for External Cloud Exposures via SSL Certs
Scanning the Internet for External Cloud Exposures via SSL Certs
 
Connect Wave/ connectwave Pitch Deck Presentation
Connect Wave/ connectwave Pitch Deck PresentationConnect Wave/ connectwave Pitch Deck Presentation
Connect Wave/ connectwave Pitch Deck Presentation
 
Dev Dives: Streamline document processing with UiPath Studio Web
Dev Dives: Streamline document processing with UiPath Studio WebDev Dives: Streamline document processing with UiPath Studio Web
Dev Dives: Streamline document processing with UiPath Studio Web
 

Canadian-US standards workshop, Calgary, 6 June 2013

  • 1. Standards Workshop Calgary, Alberta June 6, 2013 GLOBAL CCS INSTITUTE
  • 2. Agenda  Opening Remarks: Victor Der - Global CCS Institute  Session 1: CSA Z741 Geological Storage of CO2 Jeff Walker - CSA Group  Session 2: Impact of Z741 on Public Engagement and Safety Jacqueline Sharp - Navius Research  Session 3: Impact of Z741 0n Project Costs Allan Greeves - Cenovus  Session 4: Impact of Z741 on Mitigating Projects Risks Rob Bioletti - Alberta Energy  Session 5: Facilitated Discussion Bob Page – University of Calgary, J-P Jepp – Shell Oil Company, Rob Craig – ICO2N and participants  Closing Remarks: Victor Der - Global CCS Institute
  • 3. Process  Speakers will give a 20 minute presentation. The balance of the time is for Q&A and discussion  There will be an extended open discussion at the end of the day  Vic Der will be the principal facilitator  Ian Hayhow will be the rapporteur  Chatham House rules apply  We likely can be a bit flexible with the timelines
  • 4. Workshop Objectives The expected outcome for today is: Identify the advantages and challenges to using standards for CO2 storage projects Storage Issues: • How rigorous is the pre-screening process? • Should there be a mechanism to recover pre-screening costs? • Who can/will do expert reviews?
  • 5. Next Steps • Draft summary report to be prepared by the Global CCS Institute • Circulate to participants for comment • Publish on the Institute website • Comments of the workshop please • Thoughts for other workshop sessions
  • 6. CSA Z741 Geological Storage of Carbon Dioxide Jeff Walker GCCSI - The Role of Storage Standards in the Deployment of CCS Workshop June 6, 2013
  • 7. Agenda • About CSA Group • About consensus standards • Role of standards in CCS • CSA Z741 Geological Storage of CO2 • Update on ISO standards 7
  • 8. CSA Group • Independent not-for profit Standards Development, Product Certification and Consumer Product Evaluation Organization • Largest and most diversified Standards Development Organization in Canada • Neutral 3rd party • One billion products worldwide bear a CSA product safety mark 8
  • 9. Standards Development 9 3,000 Standards and Codes 8,500 expert Committee Members 54 Program areas 40% of standards are referenced in government regulation 95% of customers recommend the use of CSA standards
  • 10. Standards What is a consensus standard? A document designed to be used as a rule, guideline or definition. It is a consensus-built, repeatable way of doing something Standards must fit the need • Prescriptive based • Objectives based • Performance based • Principles based • Hybrids 10
  • 11. Consensus Consensus General agreement, characterized by the absence of sustained opposition to substantial issues by any important part of the concerned interests and by a process that involves seeking to take into account the views of all parties concerned and to address any conflicting arguments. Consensus is not necessarily unanimity CSA uses an accredited standards development process to develop standards through consensus 11
  • 12. CSA’s Consensus Process CSA does not write standards Technical Committees write standards CSA does not influence the technical content 12
  • 13. • Organized to drive diverse stakeholders to consensus on tough issues • Accredited by the Standards Council of Canada • Technical Committee - Balanced Matrix – All interest groups have equal access – Minority interest groups have a voice 13 CSA’s Consensus Process Chair Associate Members 5 Year Reviews Public Review • Owners / Architects/ Regulators • Suppliers/ Fabricators/ Contractors • Consultants Committee • Owners • Researchers • Regulators • Suppliers • Fabricators • Contractors • Consultants
  • 14. Role of Standards Standards and Public Perception of CCS • People are worried about geological storage • Public opposition has caused cancelation of several CCS projects • Standards can provide assurances that CCS is safe 14
  • 15. Role of Standards Standards and Regulations • Standards and regulations can work together • Standards are voluntary • Typically standards initiated by industry • Demonstrate regulatory compliance 15
  • 16. Role of Standards Standards and Regulations • Streamline the regulatory process • Harmonize across jurisdictions • Standards have a revision process 16
  • 17. Role of Standards Other Benefits • Transfer of knowledge and experience • Mainstream leading practices • Financing CCS projects • Acceptance by different interests 17
  • 18. CSA Z741 CSA Z741 Geological Storage of CO2 • Bi-national USA – Canada • IPAC CO2 provided support • Publication in 2012 • CSA Z741 is not a “cookbook” Promote environmentally safe and long-term containment of carbon dioxide 18
  • 19. CSA Z741 Scope • Establishes requirements for the storage of CO2 • Recognizes projects are site specific • Primarily applicable to saline aquifers and depleted hydrocarbon reservoirs • Does not preclude its application to EOR storage 19
  • 20. CSA Z741 Scope • CO2 storage during EOR is different • Aspects can be used for EOR projects • When storage is an incident of routine EOR 20
  • 21. CSA Committee 21 User Interest Category Min Max Actual General Interest 8 11 10 Government and/or Regulatory Authority 5 7 6 Owner/Operator/Producer 7 9 7 Supplier/Contractor/Consultant Interest 6 9 6 Balanced Matrix Approach to Consensus
  • 22. Committee Organizations 22 Government/Regulators – Energy Resources Conservation Board of Alberta (ERCB) – BC Oil and Gas Commission – Ground Water Protection Council – Alabama Dept. of Env Mgmt – Mississippi Dept of Env Quality – Alberta Energy Owner/Operator/Producer – SaskPower – Southern Company – Cenovus – Denbury Resources – Chevron – Husky Energy Supplier/Contractor/Consultant Interest – DNV – Schlumberger Carbon Services – Advanced Resources International Inc – Halliburton – Golder Associates – Baker Hughes General Interest/Expertise – University of Alberta – Alberta Innovates-Technology Futures – World Resources Institute (WRI) – Global CCS Institute – International Energy Agency – PEW Center on Global Climate Change – Princeton University
  • 23. CSA Z741 Table of Contents 1 Scope 2 Reference publications 3 Definitions 4 Management systems 5 Site screening, selection, and characterization 6 Risk management 7 Well infrastructure development 8 Monitoring and verification 9 Closure 23
  • 24. CSA Z741 Clause 4 Management systems • Ensure that existing best practices are followed • Promote improvement • Clarify project operator roles and responsibilities • Detail principles; internal, external; HSE • Lay out communication requirements 24
  • 25. CSA Z741 Clause 5 Site screening, selection, and characterization • Site screening advice • Criteria for site selection • Requirements and recommendations for characterizations • Modeling parameters and outcomes 25
  • 26. CSA Z741 Clause 6 Risk management • Consistent with ISO 31000 Risk management 26
  • 27. CSA Z741 Clause 7 Well infrastructure development • CO2 specific requirements and references – Materials – Design – Construction – Corrosion control – O&M 27
  • 28. CSA Z741 Clause 8 Monitoring and verification • Flexible and adapt to changes in conditions and phases • Not technology based • M&V objectives • Designing an M&V program 28
  • 29. CSA Z741 Clause 9 Closure • Closure plan • Qualification process requirements • Preparing for decommissioning 29
  • 30. International Standards CCS crosses international borders • Expertise is international • Project operators are transnational • Harmonization has benefits National differences must be acknowledged 30
  • 31. ISO and CCS New CCS ISO TC 265 • Chaired by Canada (Sandra Locke) • Secretary Canada, twinned with China Standardization of design, construction, operation, and environmental planning and management, risk management, quantification, monitoring and verification, and related activities in the field of carbon dioxide capture, transportation, and geological storage (CCS). 31
  • 32. TC265 Participation Participating Countries Australia Malaysia Canada Netherlands China Norway France South Africa Germany Spain Italy Switzerland Japan United Kingdom Korea United States 10 other observer nations 32
  • 33. TC 265 Structure 33 CCS TC Capture Group Transportation Group Storage Group Cross-Cutting Group Quant. & Verif. Group
  • 34. Summary 34 • There are challenges to implementing CCS • CSA Z741 can help • alleviate public concerns about safety • facilitate compliance with the regulatory process • streamline approvals • mainstream leading practices • CSA Z741 on CO2 storage is available for use • ISO is embarking upon international standards
  • 36. The Impact of Z741 on Public Engagement and Safety Jacqueline Sharp Managing Partner, Navius Research Inc.
  • 37. Presentation Overview • Z741 and Public Engagement • Z741 and Safety • Impact of Z741 on Public Engagement and Safety • Group Discussion Questions
  • 38. Z741 and Public Engagement
  • 39. Who is the “Public”? • Stakeholders: individuals, groups, companies or organisations that believe their interests could be affected by a project and wish to participate in or have their interests represented in project decisions. • ‘Public’ stakeholders: general public, local community, NGOs •Other key stakeholders: government/ regulators, experts, employees, shareholders, suppliers, customers. Some crossover to ‘public’. Public stakeholders grant or withhold social license to operate.
  • 40. What is ‘engagement’? Engagement goes beyond informing and consulting. PlanningNSW, 2003
  • 41. Why does public engagement matter? • Business case: reduce risk of project delays or cancellations due to opposition • Approvals: satisfy or exceed regulatory requirements • Project improvements: benefit from different viewpoints, challenged to address critical issues • Reputational benefits Effective public engagement is a key risk mitigation tool.
  • 42. Z741 and public engagement Principles: • “Operate in an open and transparent fashion... to build public understanding, trust, and credibility” • Develop and implement a local stakeholder advisory strategy • Report on major milestones or unplanned events “Identify project stakeholders early in the storage project life cycle and engage them during all phases of the project”
  • 43. Z741 and public engagement cont. Public Communications: • Include a trained designated media liaison and a designated individual to answer public questions • Involve the community in development of the outreach and engagement strategy • Communicate about the project early and often • Use public meetings, notices, and updates, site visits, potentially a local newsletter, social media • Communications should clearly share scientific, technical, and economic information, and focus on project issues and local benefits/concerns
  • 44. Z741 and public engagement cont. Communications continued: “The operator should engage the public in decision-making around aspects of the project where possible so that it addresses their concerns and meets local needs”
  • 45. Z741 and public engagement cont. • The ‘human culture’ context should be considered • Stakeholder interests should be considered, and their needs met to the extent practicable • Stakeholder views should be appropriately considered when defining the elements of concern, identifying criteria, and evaluating risk • Risk communication program should address rationale for site selection, risk management plans, response to unexpected events, stakeholder concerns/questions The Risk Management process should include stakeholder consultation and communication.
  • 47. Safety Risks Associated with CCS • Safety risk is a function of likelihood of occurrence and severity of consequences • The greatest consequences are associated with exposure of the public or workers to high concentrations of CO2. due to leakage or an accident • The likelihood of these events occurring is very low The actual safety risks associated with CCS are low.
  • 48. Z741 and Safety • “Ensure the integrity of all facilities which includes preventing leakage” • “Develop and put in place an emergency response plan and team” • “Provide the appropriate resources to continually improve health, safety, and environmental protection” “Ensure that health, safety, and environmental protection for workers and local communities are the project’s highest priorities”
  • 49. Z741 and Safety cont. Very detailed standards for: • Site characterization and assessment • Risk assessment and mitigation • Well materials and construction • Operation & Maintenance and Monitoring & Verification plans designed to protect health, safety, and the environment Virtually every section of Z741 includes requirements and recommendations to prevent leakage and ensure safety
  • 50. Impact of Z741 on Stakeholder Engagement and Safety
  • 51. Impact of Z741: Key Points • Safety sections are quite detailed and prescriptive; public engagement sections are general and focus on principles • Key is how Z741 affects perceived safety risks • Public engagement sections may not provide sufficient guidance
  • 52. Impact of Z741 on Safety Safety: • Z741 should ensure implementation of best practices and further minimize safety risks • Perceived safety risk is the real issue • Public tends to focus only on severity of consequences, on which they can have misperceptions
  • 53. Impact of Z741 on Perceived Safety • The extent to which Z741 impacts perceived safety will depend on trust in CSA process and standard versus government regulations. • Successfully explaining probability of occurrence and addressing misperceptions about consequences requires risk communication • Z741 identifies objectives for risk communication but not how to conduct effective risk communication
  • 54. Risk Communication Best Practices • Use language appropriate for the audience () • Be open and honest () • Put risks in context public understands • Where possible, partner with trusted messengers • Acknowledge knowledge gaps and identify plans to address them • Make extensive project information available
  • 55. Impact of Z741 on Public Engagement • Engage early and often () • Use a variety of communication/engagement mechanisms () • Meaningfully involve stakeholders in project decisions () Specifics • Conduct social site characterization at the project outset to identify stakeholders, concerns, misperceptions • Start engagement even before site characterization • Develop and implement processes to obtain and incorporate stakeholder feedback Public engagement principles generally reflect best practices but do not provide detail on implementation.
  • 56. Standards, Public Engagement, and Safety • Are the standards achievable? • Are the standards sufficient? • Are the standards detailed enough? Should they be more prescriptive about public engagement and risk communication? • Are the standards applicable worldwide? Group discussion questions:
  • 58. CSA Z741-12 – Geological Storage of CO2: Impact on Project Costs Allan Greeves Manager, Weyburn Cenovus Energy Inc. Global CCS Institute Workshop | Calgary, AB | June 6, 2013
  • 59. Disclaimer This document contains forward-looking information prepared and provided for the sole purpose of facilitating public consultation in respect of regulatory applications and is not intended to be, and should not be, relied upon for the purpose of making investment decisions, including without limitation, to purchase, hold or sell any securities of Cenovus Energy Inc. Additional information regarding Cenovus Energy Inc. is available at www.cenovus.com.
  • 60. Impact of standards on project costs • How can we set guidelines to ensure effective standards that are not overly prescriptive, causing unnecessary costs (Capex, Opex, MMV)? • Can standards in fact lower the life-cycle costs of a project? • To what extent have projects been used as guideposts or adoption from other projects such as in the oil and gas industry?
  • 61. Impacts of standards on project costs • Impetus for standard development – 1.1 (a) “This Standard establishes requirements and recommendations for the geological storage of carbon dioxide. The purpose of these requirements is to promote environmentally safe and long-term containment of carbon dioxide in a way that minimizes risks to the environment and human health.” 1 – Standards provides operators, regulators and the public with knowledge sharing, careful considerations applicable with the storage of CO2, and provides guidance for project planning 1. CSA 741-12 Geological storage of carbon dioxide, October 2012, Pg 1.
  • 62. CSA Z741-12 Geological Storage of CO2 Storage project life cycle Post-injection period Entity Site screening and selection period Site characterization period Design and development period Operational period Closure period Post closure period (not included in the Standard) (Private) operator Regulatory authority Designated authority Limits of the Standard Iterative process Injection starts Cessation of injection Source: CSA Z741-12 Geological storage of carbon dioxide, October 2012, Pg 2
  • 63. Application of standards • CSA Z741-12 was created by a diverse team of experts – Oil & gas E&P companies – Oil & gas service companies – Environmental NGO’s – University researchers – Research organizations – Regulators – Environmental service companies – The technical committee worked hard to find the balance between prescriptiveness and flexibility to incorporate site specific conditions
  • 64. Applying standards • A proponent is considering its options for reducing its carbon footprint – Is geological storage an option? – Where to begin? • Standards provide guidance as to the expectations and considerations necessary for a successful project: – Reduce cycle time to understanding the potential scope of the project – Provide guidance on the expertize necessary to evaluate the project
  • 65. Continuous improvement Continuous improvement is a key component of CSA Z741-12 • Recognition of ever improving technology • Recognition of ever changing expectations • Opportunity to reduce costs with increased industry knowledge • Opportunity to reduce costs with increased site specific knowledge Plan Execute ReviewImprove
  • 66. Project life cycle – stage gate cost profileSiteScreening SiteSelection Site Characterization Time CumulativeCost Monitoring & verification
  • 67. Site screening, selection & characterization Site screening Cost considerations • Storage capacity • Potential injection capability • Seal (above & below) the storage unit • Seismic or tectonic stability • Faulting / fracturing • Over-pressured systems • Hydrodynamic system • Number of wells already penetrating the seals / storage unit • Primarily an ‘office’ assessment • Utilizes readily available data & information • May not require the acquisition of new data • May require additional consulting expertise to conduct the review • Iterative process – may need to evaluate several potential storage units
  • 68. Site screening, selection & characterization Site selection Cost considerations • Builds upon site screening information and analysis • Further refines understanding of capacity, injectivity, storage security (seal integrity due to faulting, existing wells, etc) • Explores other requirements like pore space ownership, other subsurface activities, surface considerations (lakes, rivers, population centres, land use, etc) • Continue to use existing data & information • Review of core from existing wells, petrophysical well log analysis, simple models to assess injectivity, pressure / hydrodynamic studies • Review of mineral land tenure records • Review of surface culture and future land use including restrictions due to environmental or heritage concerns
  • 69. Site screening, selection & characterization Site characterization & assessment Cost considerations Detailed assessment of: • Geology & hydrogeology of the storage unit • Characterization of confining strata • Primary seal • Secondary barriers to CO2 leakage • Baseline geochemistry • Baseline geomechanics • Well characterization At this stage new data may be required including: • Seismic data (2D & possibly 3D) • May include the drilling of an exploration or pilot well for: • Core & core analysis of storage unit and seal(s) • petrophysical & cased hole logging • DST & well test data (pressure, injectivity, existing pore fluid analysis) • Lab studies of fluid compatibility (CO2 with rock, pore fluids) • Lab assessment of rock strength properties, thermal properties, rock deposition & mineralization characteristics
  • 70. Site screening, selection & characterization Modeling for site characterization Cost considerations Integration of the acquired data will allow the construction of: • Geological static model - areal extent, stratigraphy, lithology / facies, structure, porosity / permeability distribution, pore saturations, pressure / geothermal regime, initial stress regime • Flow modeling – assess storage capacity, injectivity, pressure and plume distribution & movement, fate of displaced water • Geochemical modeling – chemical reactions between injected CO2 and storage unit rock & fluids, mineral trapping • Geomechanical modeling – strength of the primary seal, fault reactivation, potential for induced seismicity, impact on well integrity • Integration of existing and captured data into these various models will require skilled expertise in various geology, geophysics and engineering • Modeling requires calibration to known behavior (history matching) • Modeling will allow for scenario analysis of areas of uncertainty • Modeling will have an impact on the time allocated to assess the potential site • Modeling will help inform the proponent as well as the regulator and public of the subsurface impact of the storage project • Modeling will be an iterative effort, incorporating new data as it becomes available (piloting, development)
  • 71. Well infrastructure development • Well construction includes the design & execution for the creation of: – Wellbore – Internal well completion, – Surface wellhead – Abandonment of infrastructure at the end of the project
  • 72. Wellbore design – what makes a well CO2 compliant? • Number of casing strings required – Groundwater protection – Protection of porous zones above storage unit – Potential lost circulation zones • Designing to expected service conditions: – Is the CO2 stream dehydrated? – Does the stream contain excessive impurities (NOx, SOx, H2S, O2)? – Pressure – Temperature • Anticipated injection rates – Hole/casing diameter appropriate for the injection string and packer assembly required • Core, DST, logging requirements • Monitoring
  • 73. Wellbore design – drilling to make a well CO2 compliant Drill & Case • Typical oil and gas well design includes 3 casing strings: conductor, surface casing & production (long-string) • Only the long-string is in contact with the CO2 storage unit • CSA Z741 requires the casing across the storage unit be made of corrosion material like chrome or stainless steel • CSA Z741 refers to various API specifications for cementing but also expects cement design to offer additional chemical resistance to CO2 degradation to apply latest technologies
  • 74. Wellbore design – what makes a well CO2 compliant? Drill & Case (other considerations) • High standard of care / QA/QC – Drilling mud system – Attention to casing centralization particularly over storage unit, primary seal and secondary seal – Cement blend preparation and placement (compatible water, additive concentrations, over displacement, etc) • What kind of monitoring is required? – Monitoring well vs injection well – Piloting well vs development well – Accessibility required for time lapsed evaluation – Integrity concerns balanced against accessibility, monitoring equipment
  • 75. Drilling a CO2 compliant wellbore Vertical Well Drilling Costs Consulting & Supervision Logging, Coring, Mud Gas Surface Casing & Cement Production Casing & Cement Drilling Rig & Support Mud Systems & Disposal Other Services • Approximately 1/3 of the cost of drilling a well is for casing and cement left in the hole • Remainder of the costs are for drilling and evaluation of the well
  • 76. Wellbore design – what makes a well CO2 compliant? Well completion • Designing to expected service conditions: • Is the CO2 stream dehydrated? • Does the stream contain excessive impurities (NOx, SOx, H2S, O2)? • Pressure • Temperature • Anticipated injection rates • Annulus inhibited fluid type • Cement & casing integrity logging requirements • Monitoring requirements
  • 77. Materials selection • Upgraded materials like this packer element may be required to avoid adverse effects due to CO2
  • 78. Impact of service conditions • This coiled tubing was recovered from an injection well converted from straight CO2 injection to a water-alternating-gas (WAG) injection configuration • Drehydrated CO2 • Non-coated tubulars • Coiled tubing string was in place for ~12 years with little corrosion with exception of this point midway down the well
  • 79. Wellbore design – what makes a wellhead CO2 compliant? Wellhead design • Designing to expected service conditions: • Is the CO2 stream dehydrated? • Does the stream contain excessive impurities (NOx, SOx, H2S, O2)? • Pressure • Temperature • Anticipated injection rates • Monitoring requirements • Accessibility requirements to the wellbore • Flow / ESD control
  • 80. Designing surface piping CO2 compatible seals in surface piping: • CO2 does behave differently than oil & gas industry fluids • Sometimes it takes a ‘low tech’ way of troubleshooting for performance improvement
  • 81. Monitoring & verification Monitoring & verification Cost considerations “Measurement and surveillance activities necessary to provide and assurance of the integrity of CO2 storage”2: • Used at all stages of development – begins with baseline data right through to the closure of the project • Provide evidence that CO2 placement is secure • Allows for comparisons between predicted and actual conditions • various data points and perspectives from seismic, to injection wells and observation wells • models updated with actual performance data allow for performance improvement and confidence in ultimate fate of CO2 • Support quantification efforts • Is not just one method of monitoring • Is a suite of site specific approaches to compare to baseline • Will require additional project expenditures for: • Seismic • Observation wells • Specialty hardware in injection wells • Pressure, temperature, flow, composition monitoring equipment / tools • Data capture instrumentation and analysis (ie: SCADA) • Repeated capture over time • Updated over time as necessary • Expanded over time as necessary 2. CSA 741-12 Geological storage of carbon dioxide, October 2012, Pg 55.
  • 82. Closure Closure Cost considerations “purpose… is to provide guidance to and establish predictability for project operators and regulatory authorities of.. a) Sufficient understanding of storage site’s characteristics b) Low residual risk c) Adequate well integrity” 3 • Includes incorporation of learning’s throughout the project life • Development infrastructure in place and its condition • Monitoring & verification results • Integration of project performance data into dynamic models • Updated risk management plan • Includes the abandonment of storage infrastructure wells and facilities • Will likely be done in a staged approach to monitor for well integrity and containment effectiveness • Will take some time (year’s) to provide confidence for risk management plan • Need to continue monitoring efforts • Need to retain experts who will update dynamic models • End result will ‘qualify’ project for potential hand off to designated authority 3. CSA 741-12 Geological storage of carbon dioxide, October 2012, Pg 60
  • 83. Summary • By providing guidance and expectations standards can lower the life-cycle costs of a project – Improve project understanding with baseline work and monitoring – Application of best practices for development design and quality – Integrate risk assessment with monitoring & verification to identify specific areas of concern • Learning’s from the oil & gas industry are directly applicable – Complementary skills – Complementary resources and equipment • End result is a project with maximum benefit with effectively managed risks
  • 84. • Special thanks to: – Canadian Standards Association – Cenovus Energy Inc. Questions?
  • 85. Session 4 Will Z741 Mitigate Project Risks? The Role of Storage Standards in the Deployment of CCS Rob Bioletti, P.Eng. Director, CCS Policy Government of Alberta June 6, 2013
  • 87. Climate Change Mitigation • No one technology can stabilize greenhouse gas emissions alone. • A combination of several climate mitigation technologies is needed for robust climate change. • Standards will aid in the widespread deployment of CCS. 87
  • 88. Knowledge Sharing and Innovation • Standards will aid in the transfer of knowledge between jurisdictions. • Standards need not be prescriptive. • Organizational structure can aid in separating well defined versus emerging activities. 88
  • 89. Public Perception of CCS • Public opposition has caused cancelation of several CCS projects throughout the world. • Standards can help provide assurances that CCS is safe. 89
  • 90. CSA Z741 How this Standard Can Mitigate CCS Project Risks 90
  • 91. Site Screening, Selection, and Characterization - Section 5 Site screening and selection will identify prospective CO2 storage sites that have met the following criteria: • Sufficient Capacity; • Sufficient Injectivity; and • Effective Retention. 91
  • 92. Risk Management – Section 6 Effective risk management should: • Demonstrate achievement of objectives; • Improve performance relative to elements of concern; • Support strategic planning; • Develop robust project and change management processes; • Help decision makers make informed and prioritized choices; • Account for uncertainty; and • Recognize stakeholder intentions. 92
  • 93. Well Infrastructure Development - Section 7 Outline criteria needing to be met in order to best mitigate risk (CO2 leaks, infrastructure problems, etc.) such criteria include: • Materials; • Design; • Construction; • Corrosion Control; and • Operation and Maintenance. 93
  • 94. Monitoring and Verification – Section 8 The monitoring and verification standard will be flexible and adaptable to changes in storage and injection conditions, the criteria the standards will address the following concerns: • Health, • Safety, • Environmental Risks; and • Storage Performance 94
  • 95. Risks for CCS Projects 95
  • 96. Risk Profile for a CO2 Storage Site Source: Benson 2007
  • 97. Examples of Other Risk Elements • Environmental – Natural environment – Health and safety – Legal and regulatory environment • Economic – Project financing – Competition with other resources • Social – Public support – Politics 97
  • 99. 99 Group Activity! Question: Which risk element is the most important to address for CCS projects? Tool: Simplified Decision Matrix Assessing the relative importance of alternatives
  • 100. Steps 1. Brainstorm up to 5 risk elements - Environmental (e.g. operational, safety, regulatory) - Economic (e.g. financing, resource competition) - Social (e.g. public support, reputation, politics) 2. Assign weights to each element - Stakeholder views: Petroleum engineer, policy analyst, farmer, professor, activist, etc - Scale of 1 to 3 (1 = low importance, 3 = high importance) - Group must agree on the weight! 3. Score each risk by stakeholder perspective - Scale of 1 to 5 (1 = low importance, 5 = high importance) 4. Multiply stakeholder scores by weight 5. Total all scores to find “winner” 6. If there is disagreement, re-visit weights or scores 100
  • 101. Example Decision Matrix 101 Stakeholder Score (1-5) Industry Government Public Academic 3 (x1) = 3 1 (x1) = 1 2 (x1) = 2 Total 5+3+1+2 = 11 5 (x1) = 5 4 (x2) = 8 4 (x3) = 12 2 (x1) = 2 Weight (1-3) 1 2 3 1 Risk Element Financing Public Support Safety Etc. Etc. Brainstorm Agree Assess
  • 102. Discussion 1. What were the results? Did one clear winner emerge? 2. How did stakeholder views help or hinder the decisions? 3. Should certain risk elements have more focus? 4. How can CSA Z741 help mitigate these risks? Are there areas for improvement? 102
  • 103. Thank You Rob Bioletti, P.Eng. +1 780 644 3204 Rob.Bioletti@gov.ab.ca www.energy.alberta.ca