SlideShare a Scribd company logo
1 of 19
CCS Activities in Developing Asia–
Insights and Next Steps

Ashok Bhargava
Director, Energy Division
East Asia Department
Seoul, 10 October 2013
ADB CCS Fund
 In June 2009, ADB established a CCS Fund with an initial

contribution of AUD 21.5 million from the Global CCS
Institute, Australia. In 2012, Government of the United
Kingdom also pledged £35 million in the fund.
 Specific Eligibility Criteria
 Accelerate demonstration of CCS technologies
 Identify, lower and / or eliminate general or country specific

barriers for CCS demonstration
 Identify, eliminate or mitigate risks in capture, transport and

storage technology demonstration
… in the People’s Republic of China
PRC – Overview of ADB Activities
Capacity Development and Policy Advisory Assistance
 Key Partner

Department of Climate Change, NDRC

 Target three major

China Huaneng : pre-combustion capture –
IGCC

capture technologies

China Datang : post-combustion capture natural gas plant
Dongfang Boiler – Oxy-fuel combustion
capture - coal-based power plant

Support upstream analytical work, analyze issues, identify costs and risks
on real projects
PRC – Overview of ADB Activities
Develop CCS Roadmap
 Aims to develop a

 Includes following major outputs
1.

Time bound action plan for demonstration
(up to 2020) and deployment (up to 2025)

2.

A policy and regulatory framework with an
accompanying set of incentives

3.

Shortlist and ranking of early-stage CCS
demonstration projects

4.

key planning tool for
the Government to
demonstrate and
deploy CCS

Suitable business models for implementing
early-stage projects

Establish enabling environment for CCS demonstration and possible
deployment.
Next Steps in the PRC ………..
Pilot Project
Next Steps ……….
Pilot CCS Project at Tianjin IGCC Power Plant
 Capture up to 100,000 tons CO2 / year to

partially used for EOR and partially for
storage
 Due diligence is underway; power and oil

company collaboration proving difficult
 ADB may provide up to $10 million grant

for CapEx and a compensatory
mechanism to offset energy penalty
 Pilot project likely to be in operation by

2015
Next Steps ……….
FEED Studies for a large-scale CCS project
 Need to scale-up

CCS efforts urgently

 Discussions underway to select one of

the early-stage projects identified
through the ongoing CCS road map work
What have we learned so far in the PRC
 Technical readiness

 In-country technical capacity exists; large

 Weak policy support

number of point sources in close
proximity to potential storage sites
 CCS is not a strategic choice; no national
target, incentives or support mechanism
in place.

 Fragmented

institutional setup
across CCS chain
 Need for public

financing

 Negligible cooperation between power

and oil companies not conducive for
CCS
 Early projects will need risk sharing or
preferably
risk
bearing
by
the
Government
Moving on to Southeast Asia ………..
Potential for CCS in Southeast Asia
• A regional study with focus on Thailand,

Vietnam, Indonesia, Philippines completed
recently
 Study aimed to:

i.

Establish inventory of CO2 emission
sources

ii.

Estimate storage potential
Determine source-sink matches for CCS
Identify potential pilot projects
Propose Road Map for CCS development
Develop “CCS Working Groups” which
could provide leadership on CCS

iii.
iv.
v.
vi.
Potential for CCS in Southeast Asia - Main Results
 Sufficient capture

streams are available

 Natural gas

processing and new
power plants are best
sources for capture

Annual inventory of 200 million tons of CO2
emissions from sources (coal and gas power
plants, natural gas processing facilities, future
power plants, and smaller sources such as
fertilizer plants)

Natural gas processing facilities are preferred
because of lower incremental cost of capture,
storage site proximity, and existing transport
infrastructure
Potential for CCS in Southeast Asia - Main Results….contd
 Large storage

capacity

 Large number of oil

and gas fields
provide adequate
storage for early
stage projects

Estimated storage capacity of 56 giga tons of
which about 90% is in saline aquifiers. But due
to uncertainties of aquifiers, study concentrated
on oil and gas fields
143 oil and gas fields offer more than 3 giga
tons of capacity. Since the geology is well
understood of these fields, they were ranked for
early stage projects.
Potential for CCS in Southeast Asia - Main Results….contd
Next step in Southeast Asia Region –
Pilot Project in Indonesia
 Collaborative

approach

Collaboration with JICA, Pertamina, and Institut
Teknologi di Bandung
Follows on a JICA scoping study ($5 million, 5year) at Gundih gas field in Central Java

 Due diligence

support

• Pilot project

financing
support

ADB to provide due diligence support to
PERTAMINA to review preliminary design of
surface facilities for test injection, identify legal
and regulatory issues and develop regulations
and apply for permits as appropriate.
ADB may follow with a $10 million grant for
capture and test injection from its CCS Fund
What did we learn so far in developing Asia
for CCS ………..
Key Issues and Barriers
ADB (2011):
“… key barriers to
CCS are amplified in
developing countries
….”

CCS is a last
resort policy
approach
Limited public
awareness

Absence of
targeted
incentives /
concessional
financing
mechanism

Lack of delivery
mechanism /
business model

Energy
intensive
mitigation
approach
Lack of incountry
experience in
planning,
construction
and operation
Way Forward
Demonstration projects in
identification stage
ADB (2011):
CCS is a last
“… key barriers to
resort policy
CCS are amplified in
approach
developing countries
Government Commitment, incl.
….”
Limited
policy targets, regulatory, fiscal, public
awareness
and financial support measures
Right business models for early
Absence of
stage demonstration projects
targeted
incentives /
concessional
Mechanisms to offset higher costs, and
financing
energy penalty
mechanism
Lack of delivery
Awareness and support from civil /
mechanism
business model
society

Energy
intensive
mitigation
approach
Lack of incountry
experience in
planning,
construction
and operation

Realized demonstration projects
From:
ADB Team

For further info :
Indonesia – ptharakan@adb.org
PRC – aseiler@adb.org

More Related Content

Similar to Panel 2. CCS in the Asian Century - Ashok Bhargava, ADB

Status of CCS in developing countries
Status of CCS in developing countriesStatus of CCS in developing countries
Status of CCS in developing countriesGlobal CCS Institute
 
Key issues and barriers in developing countries
Key issues and barriers in developing countriesKey issues and barriers in developing countries
Key issues and barriers in developing countriesGlobal CCS Institute
 
Gccsi japan members'_meeting_200613_barry-jones_gccsi
Gccsi japan members'_meeting_200613_barry-jones_gccsiGccsi japan members'_meeting_200613_barry-jones_gccsi
Gccsi japan members'_meeting_200613_barry-jones_gccsiGlobal CCS Institute
 
Brad Page - The Global Status of CCS: 2014
Brad Page - The Global Status of CCS: 2014Brad Page - The Global Status of CCS: 2014
Brad Page - The Global Status of CCS: 2014Global CCS Institute
 
Roadmap for CCS Demonstration and Deployment for the People's Republic of China
Roadmap for CCS Demonstration and Deployment for the People's Republic of ChinaRoadmap for CCS Demonstration and Deployment for the People's Republic of China
Roadmap for CCS Demonstration and Deployment for the People's Republic of ChinaGlobal CCS Institute
 
Webinar: The Global Status of CCS: 2014 - Overcoming challenges in Europe
Webinar: The Global Status of CCS: 2014 - Overcoming challenges in EuropeWebinar: The Global Status of CCS: 2014 - Overcoming challenges in Europe
Webinar: The Global Status of CCS: 2014 - Overcoming challenges in EuropeGlobal CCS Institute
 
Global Status of CCS: 2014, Hiroshi Nambo
Global Status of CCS: 2014, Hiroshi NamboGlobal Status of CCS: 2014, Hiroshi Nambo
Global Status of CCS: 2014, Hiroshi NamboGlobal CCS Institute
 
Webinar: Revitalizing CCS: bringing scale and speed to CCS deployment
Webinar: Revitalizing CCS: bringing scale and speed to CCS deploymentWebinar: Revitalizing CCS: bringing scale and speed to CCS deployment
Webinar: Revitalizing CCS: bringing scale and speed to CCS deploymentGlobal CCS Institute
 
Gccsi japan members'_meeting_200613_tom-connor_aust_gov
Gccsi japan members'_meeting_200613_tom-connor_aust_govGccsi japan members'_meeting_200613_tom-connor_aust_gov
Gccsi japan members'_meeting_200613_tom-connor_aust_govGlobal CCS Institute
 
Introduction to Carbon Capture and Storage
Introduction to Carbon Capture and Storage Introduction to Carbon Capture and Storage
Introduction to Carbon Capture and Storage The Climate Institute
 
Webinar: Global Status of CCS: 2014 - Driving development in the Asia Pacific
Webinar: Global Status of CCS: 2014 - Driving development in the Asia Pacific Webinar: Global Status of CCS: 2014 - Driving development in the Asia Pacific
Webinar: Global Status of CCS: 2014 - Driving development in the Asia Pacific Global CCS Institute
 
Juho Lipponen - CCS & the global climate agenda
Juho Lipponen - CCS & the global climate agendaJuho Lipponen - CCS & the global climate agenda
Juho Lipponen - CCS & the global climate agendaGlobal CCS Institute
 
Debrief on Global CCS Institute Annual Meeting 2013
Debrief on Global CCS Institute Annual Meeting 2013Debrief on Global CCS Institute Annual Meeting 2013
Debrief on Global CCS Institute Annual Meeting 2013Global CCS Institute
 
Institute’s Americas office launches The Global Status of CCS: 2016 at the Cl...
Institute’s Americas office launches The Global Status of CCS: 2016 at the Cl...Institute’s Americas office launches The Global Status of CCS: 2016 at the Cl...
Institute’s Americas office launches The Global Status of CCS: 2016 at the Cl...Global CCS Institute
 
Webinar: Global Status of CCS: 2014 - Powering ahead in The Americas
Webinar: Global Status of CCS: 2014 - Powering ahead in The AmericasWebinar: Global Status of CCS: 2014 - Powering ahead in The Americas
Webinar: Global Status of CCS: 2014 - Powering ahead in The AmericasGlobal CCS Institute
 
نرم افزار کامفار: تهیه گزارشات تخصصی طرح توجیهی با کامفار ویژه سال 1398 (COMFAR)
نرم افزار کامفار: تهیه گزارشات تخصصی طرح توجیهی با کامفار ویژه سال 1398 (COMFAR)نرم افزار کامفار: تهیه گزارشات تخصصی طرح توجیهی با کامفار ویژه سال 1398 (COMFAR)
نرم افزار کامفار: تهیه گزارشات تخصصی طرح توجیهی با کامفار ویژه سال 1398 (COMFAR)AMPA
 
Mexico CCUS roadmap, Moises Davila, SENER
Mexico CCUS roadmap, Moises Davila, SENERMexico CCUS roadmap, Moises Davila, SENER
Mexico CCUS roadmap, Moises Davila, SENERGlobal CCS Institute
 

Similar to Panel 2. CCS in the Asian Century - Ashok Bhargava, ADB (20)

Status of CCS in developing countries
Status of CCS in developing countriesStatus of CCS in developing countries
Status of CCS in developing countries
 
Key issues and barriers in developing countries
Key issues and barriers in developing countriesKey issues and barriers in developing countries
Key issues and barriers in developing countries
 
Gccsi japan members'_meeting_200613_barry-jones_gccsi
Gccsi japan members'_meeting_200613_barry-jones_gccsiGccsi japan members'_meeting_200613_barry-jones_gccsi
Gccsi japan members'_meeting_200613_barry-jones_gccsi
 
Brad Page - The Global Status of CCS: 2014
Brad Page - The Global Status of CCS: 2014Brad Page - The Global Status of CCS: 2014
Brad Page - The Global Status of CCS: 2014
 
What is CCS Ready - Alice Gibson
What is CCS Ready - Alice GibsonWhat is CCS Ready - Alice Gibson
What is CCS Ready - Alice Gibson
 
Roadmap for CCS Demonstration and Deployment for the People's Republic of China
Roadmap for CCS Demonstration and Deployment for the People's Republic of ChinaRoadmap for CCS Demonstration and Deployment for the People's Republic of China
Roadmap for CCS Demonstration and Deployment for the People's Republic of China
 
Webinar: The Global Status of CCS: 2014 - Overcoming challenges in Europe
Webinar: The Global Status of CCS: 2014 - Overcoming challenges in EuropeWebinar: The Global Status of CCS: 2014 - Overcoming challenges in Europe
Webinar: The Global Status of CCS: 2014 - Overcoming challenges in Europe
 
Global Status of CCS: 2014, Hiroshi Nambo
Global Status of CCS: 2014, Hiroshi NamboGlobal Status of CCS: 2014, Hiroshi Nambo
Global Status of CCS: 2014, Hiroshi Nambo
 
Webinar: Revitalizing CCS: bringing scale and speed to CCS deployment
Webinar: Revitalizing CCS: bringing scale and speed to CCS deploymentWebinar: Revitalizing CCS: bringing scale and speed to CCS deployment
Webinar: Revitalizing CCS: bringing scale and speed to CCS deployment
 
Gccsi japan members'_meeting_200613_tom-connor_aust_gov
Gccsi japan members'_meeting_200613_tom-connor_aust_govGccsi japan members'_meeting_200613_tom-connor_aust_gov
Gccsi japan members'_meeting_200613_tom-connor_aust_gov
 
Introduction to Carbon Capture and Storage
Introduction to Carbon Capture and Storage Introduction to Carbon Capture and Storage
Introduction to Carbon Capture and Storage
 
Webinar: Global Status of CCS: 2014 - Driving development in the Asia Pacific
Webinar: Global Status of CCS: 2014 - Driving development in the Asia Pacific Webinar: Global Status of CCS: 2014 - Driving development in the Asia Pacific
Webinar: Global Status of CCS: 2014 - Driving development in the Asia Pacific
 
Juho Lipponen - CCS & the global climate agenda
Juho Lipponen - CCS & the global climate agendaJuho Lipponen - CCS & the global climate agenda
Juho Lipponen - CCS & the global climate agenda
 
Williams2012 - April 2012 Biannual Meeting, UCL
Williams2012 - April 2012 Biannual Meeting, UCLWilliams2012 - April 2012 Biannual Meeting, UCL
Williams2012 - April 2012 Biannual Meeting, UCL
 
Introduction to UK-China (Guangdong) CCUS Centre Activities - presentation by...
Introduction to UK-China (Guangdong) CCUS Centre Activities - presentation by...Introduction to UK-China (Guangdong) CCUS Centre Activities - presentation by...
Introduction to UK-China (Guangdong) CCUS Centre Activities - presentation by...
 
Debrief on Global CCS Institute Annual Meeting 2013
Debrief on Global CCS Institute Annual Meeting 2013Debrief on Global CCS Institute Annual Meeting 2013
Debrief on Global CCS Institute Annual Meeting 2013
 
Institute’s Americas office launches The Global Status of CCS: 2016 at the Cl...
Institute’s Americas office launches The Global Status of CCS: 2016 at the Cl...Institute’s Americas office launches The Global Status of CCS: 2016 at the Cl...
Institute’s Americas office launches The Global Status of CCS: 2016 at the Cl...
 
Webinar: Global Status of CCS: 2014 - Powering ahead in The Americas
Webinar: Global Status of CCS: 2014 - Powering ahead in The AmericasWebinar: Global Status of CCS: 2014 - Powering ahead in The Americas
Webinar: Global Status of CCS: 2014 - Powering ahead in The Americas
 
نرم افزار کامفار: تهیه گزارشات تخصصی طرح توجیهی با کامفار ویژه سال 1398 (COMFAR)
نرم افزار کامفار: تهیه گزارشات تخصصی طرح توجیهی با کامفار ویژه سال 1398 (COMFAR)نرم افزار کامفار: تهیه گزارشات تخصصی طرح توجیهی با کامفار ویژه سال 1398 (COMFAR)
نرم افزار کامفار: تهیه گزارشات تخصصی طرح توجیهی با کامفار ویژه سال 1398 (COMFAR)
 
Mexico CCUS roadmap, Moises Davila, SENER
Mexico CCUS roadmap, Moises Davila, SENERMexico CCUS roadmap, Moises Davila, SENER
Mexico CCUS roadmap, Moises Davila, SENER
 

More from Global CCS Institute

Northern Lights: A European CO2 transport and storage project
Northern Lights: A European CO2 transport and storage project Northern Lights: A European CO2 transport and storage project
Northern Lights: A European CO2 transport and storage project Global CCS Institute
 
Webinar: Policy priorities to incentivise large scale deployment of CCS
Webinar: Policy priorities to incentivise large scale deployment of CCSWebinar: Policy priorities to incentivise large scale deployment of CCS
Webinar: Policy priorities to incentivise large scale deployment of CCSGlobal CCS Institute
 
Telling the Norwegian CCS Story | PART II: CCS: the path to a sustainable and...
Telling the Norwegian CCS Story | PART II: CCS: the path to a sustainable and...Telling the Norwegian CCS Story | PART II: CCS: the path to a sustainable and...
Telling the Norwegian CCS Story | PART II: CCS: the path to a sustainable and...Global CCS Institute
 
Telling the Norwegian CCS Story | PART I: CCS: the path to sustainable and em...
Telling the Norwegian CCS Story | PART I: CCS: the path to sustainable and em...Telling the Norwegian CCS Story | PART I: CCS: the path to sustainable and em...
Telling the Norwegian CCS Story | PART I: CCS: the path to sustainable and em...Global CCS Institute
 
Decarbonizing Industry Using Carbon Capture: Norway Full Chain CCS
Decarbonizing Industry Using Carbon Capture: Norway Full Chain CCSDecarbonizing Industry Using Carbon Capture: Norway Full Chain CCS
Decarbonizing Industry Using Carbon Capture: Norway Full Chain CCSGlobal CCS Institute
 
Cutting Cost of CO2 Capture in Process Industry (CO2stCap) Project overview &...
Cutting Cost of CO2 Capture in Process Industry (CO2stCap) Project overview &...Cutting Cost of CO2 Capture in Process Industry (CO2stCap) Project overview &...
Cutting Cost of CO2 Capture in Process Industry (CO2stCap) Project overview &...Global CCS Institute
 
Membrane Technology & Research (MTR) Presentation
Membrane Technology & Research (MTR) PresentationMembrane Technology & Research (MTR) Presentation
Membrane Technology & Research (MTR) PresentationGlobal CCS Institute
 
Mission Innovation: Carbon Capture Innovation Challenge
Mission Innovation: Carbon Capture Innovation ChallengeMission Innovation: Carbon Capture Innovation Challenge
Mission Innovation: Carbon Capture Innovation ChallengeGlobal CCS Institute
 
Can the United States Achieve a Low Carbon Economy by 2050?
Can the United States Achieve a Low Carbon Economy by 2050?Can the United States Achieve a Low Carbon Economy by 2050?
Can the United States Achieve a Low Carbon Economy by 2050?Global CCS Institute
 
Webinar Series: Carbon Sequestration Leadership Forum Part 1. CCUS in the Uni...
Webinar Series: Carbon Sequestration Leadership Forum Part 1. CCUS in the Uni...Webinar Series: Carbon Sequestration Leadership Forum Part 1. CCUS in the Uni...
Webinar Series: Carbon Sequestration Leadership Forum Part 1. CCUS in the Uni...Global CCS Institute
 
Energy Security and Prosperity in Australia: A roadmap for carbon capture and...
Energy Security and Prosperity in Australia: A roadmap for carbon capture and...Energy Security and Prosperity in Australia: A roadmap for carbon capture and...
Energy Security and Prosperity in Australia: A roadmap for carbon capture and...Global CCS Institute
 
Webinar Series: Public engagement, education and outreach for CCS. Part 5: So...
Webinar Series: Public engagement, education and outreach for CCS. Part 5: So...Webinar Series: Public engagement, education and outreach for CCS. Part 5: So...
Webinar Series: Public engagement, education and outreach for CCS. Part 5: So...Global CCS Institute
 
Managing carbon geological storage and natural resources in sedimentary basins
Managing carbon geological storage and natural resources in sedimentary basinsManaging carbon geological storage and natural resources in sedimentary basins
Managing carbon geological storage and natural resources in sedimentary basinsGlobal CCS Institute
 
Mercury and other trace metals in the gas from an oxy-combustion demonstratio...
Mercury and other trace metals in the gas from an oxy-combustion demonstratio...Mercury and other trace metals in the gas from an oxy-combustion demonstratio...
Mercury and other trace metals in the gas from an oxy-combustion demonstratio...Global CCS Institute
 
Webinar Series: Public engagement, education and outreach for CCS. Part 4: Is...
Webinar Series: Public engagement, education and outreach for CCS. Part 4: Is...Webinar Series: Public engagement, education and outreach for CCS. Part 4: Is...
Webinar Series: Public engagement, education and outreach for CCS. Part 4: Is...Global CCS Institute
 
Laboratory-scale geochemical and geomechanical testing of near wellbore CO2 i...
Laboratory-scale geochemical and geomechanical testing of near wellbore CO2 i...Laboratory-scale geochemical and geomechanical testing of near wellbore CO2 i...
Laboratory-scale geochemical and geomechanical testing of near wellbore CO2 i...Global CCS Institute
 
Webinar Series: Public engagement, education and outreach for CCS. Part 3: Ca...
Webinar Series: Public engagement, education and outreach for CCS. Part 3: Ca...Webinar Series: Public engagement, education and outreach for CCS. Part 3: Ca...
Webinar Series: Public engagement, education and outreach for CCS. Part 3: Ca...Global CCS Institute
 
Water use of thermal power plants equipped with CO2 capture systems
Water use of thermal power plants equipped with CO2 capture systemsWater use of thermal power plants equipped with CO2 capture systems
Water use of thermal power plants equipped with CO2 capture systemsGlobal CCS Institute
 

More from Global CCS Institute (20)

Northern Lights: A European CO2 transport and storage project
Northern Lights: A European CO2 transport and storage project Northern Lights: A European CO2 transport and storage project
Northern Lights: A European CO2 transport and storage project
 
Webinar: Policy priorities to incentivise large scale deployment of CCS
Webinar: Policy priorities to incentivise large scale deployment of CCSWebinar: Policy priorities to incentivise large scale deployment of CCS
Webinar: Policy priorities to incentivise large scale deployment of CCS
 
Telling the Norwegian CCS Story | PART II: CCS: the path to a sustainable and...
Telling the Norwegian CCS Story | PART II: CCS: the path to a sustainable and...Telling the Norwegian CCS Story | PART II: CCS: the path to a sustainable and...
Telling the Norwegian CCS Story | PART II: CCS: the path to a sustainable and...
 
Telling the Norwegian CCS Story | PART I: CCS: the path to sustainable and em...
Telling the Norwegian CCS Story | PART I: CCS: the path to sustainable and em...Telling the Norwegian CCS Story | PART I: CCS: the path to sustainable and em...
Telling the Norwegian CCS Story | PART I: CCS: the path to sustainable and em...
 
Decarbonizing Industry Using Carbon Capture: Norway Full Chain CCS
Decarbonizing Industry Using Carbon Capture: Norway Full Chain CCSDecarbonizing Industry Using Carbon Capture: Norway Full Chain CCS
Decarbonizing Industry Using Carbon Capture: Norway Full Chain CCS
 
Cutting Cost of CO2 Capture in Process Industry (CO2stCap) Project overview &...
Cutting Cost of CO2 Capture in Process Industry (CO2stCap) Project overview &...Cutting Cost of CO2 Capture in Process Industry (CO2stCap) Project overview &...
Cutting Cost of CO2 Capture in Process Industry (CO2stCap) Project overview &...
 
Global CCS Institute Presentation
Global CCS Institute PresentationGlobal CCS Institute Presentation
Global CCS Institute Presentation
 
ION Engineering Presentation
ION Engineering PresentationION Engineering Presentation
ION Engineering Presentation
 
Membrane Technology & Research (MTR) Presentation
Membrane Technology & Research (MTR) PresentationMembrane Technology & Research (MTR) Presentation
Membrane Technology & Research (MTR) Presentation
 
Mission Innovation: Carbon Capture Innovation Challenge
Mission Innovation: Carbon Capture Innovation ChallengeMission Innovation: Carbon Capture Innovation Challenge
Mission Innovation: Carbon Capture Innovation Challenge
 
Can the United States Achieve a Low Carbon Economy by 2050?
Can the United States Achieve a Low Carbon Economy by 2050?Can the United States Achieve a Low Carbon Economy by 2050?
Can the United States Achieve a Low Carbon Economy by 2050?
 
Webinar Series: Carbon Sequestration Leadership Forum Part 1. CCUS in the Uni...
Webinar Series: Carbon Sequestration Leadership Forum Part 1. CCUS in the Uni...Webinar Series: Carbon Sequestration Leadership Forum Part 1. CCUS in the Uni...
Webinar Series: Carbon Sequestration Leadership Forum Part 1. CCUS in the Uni...
 
Energy Security and Prosperity in Australia: A roadmap for carbon capture and...
Energy Security and Prosperity in Australia: A roadmap for carbon capture and...Energy Security and Prosperity in Australia: A roadmap for carbon capture and...
Energy Security and Prosperity in Australia: A roadmap for carbon capture and...
 
Webinar Series: Public engagement, education and outreach for CCS. Part 5: So...
Webinar Series: Public engagement, education and outreach for CCS. Part 5: So...Webinar Series: Public engagement, education and outreach for CCS. Part 5: So...
Webinar Series: Public engagement, education and outreach for CCS. Part 5: So...
 
Managing carbon geological storage and natural resources in sedimentary basins
Managing carbon geological storage and natural resources in sedimentary basinsManaging carbon geological storage and natural resources in sedimentary basins
Managing carbon geological storage and natural resources in sedimentary basins
 
Mercury and other trace metals in the gas from an oxy-combustion demonstratio...
Mercury and other trace metals in the gas from an oxy-combustion demonstratio...Mercury and other trace metals in the gas from an oxy-combustion demonstratio...
Mercury and other trace metals in the gas from an oxy-combustion demonstratio...
 
Webinar Series: Public engagement, education and outreach for CCS. Part 4: Is...
Webinar Series: Public engagement, education and outreach for CCS. Part 4: Is...Webinar Series: Public engagement, education and outreach for CCS. Part 4: Is...
Webinar Series: Public engagement, education and outreach for CCS. Part 4: Is...
 
Laboratory-scale geochemical and geomechanical testing of near wellbore CO2 i...
Laboratory-scale geochemical and geomechanical testing of near wellbore CO2 i...Laboratory-scale geochemical and geomechanical testing of near wellbore CO2 i...
Laboratory-scale geochemical and geomechanical testing of near wellbore CO2 i...
 
Webinar Series: Public engagement, education and outreach for CCS. Part 3: Ca...
Webinar Series: Public engagement, education and outreach for CCS. Part 3: Ca...Webinar Series: Public engagement, education and outreach for CCS. Part 3: Ca...
Webinar Series: Public engagement, education and outreach for CCS. Part 3: Ca...
 
Water use of thermal power plants equipped with CO2 capture systems
Water use of thermal power plants equipped with CO2 capture systemsWater use of thermal power plants equipped with CO2 capture systems
Water use of thermal power plants equipped with CO2 capture systems
 

Recently uploaded

Mondelez State of Snacking and Future Trends 2023
Mondelez State of Snacking and Future Trends 2023Mondelez State of Snacking and Future Trends 2023
Mondelez State of Snacking and Future Trends 2023Neil Kimberley
 
Call Girls Navi Mumbai Just Call 9907093804 Top Class Call Girl Service Avail...
Call Girls Navi Mumbai Just Call 9907093804 Top Class Call Girl Service Avail...Call Girls Navi Mumbai Just Call 9907093804 Top Class Call Girl Service Avail...
Call Girls Navi Mumbai Just Call 9907093804 Top Class Call Girl Service Avail...Dipal Arora
 
Call Girls In Panjim North Goa 9971646499 Genuine Service
Call Girls In Panjim North Goa 9971646499 Genuine ServiceCall Girls In Panjim North Goa 9971646499 Genuine Service
Call Girls In Panjim North Goa 9971646499 Genuine Serviceritikaroy0888
 
Monte Carlo simulation : Simulation using MCSM
Monte Carlo simulation : Simulation using MCSMMonte Carlo simulation : Simulation using MCSM
Monte Carlo simulation : Simulation using MCSMRavindra Nath Shukla
 
Ensure the security of your HCL environment by applying the Zero Trust princi...
Ensure the security of your HCL environment by applying the Zero Trust princi...Ensure the security of your HCL environment by applying the Zero Trust princi...
Ensure the security of your HCL environment by applying the Zero Trust princi...Roland Driesen
 
Yaroslav Rozhankivskyy: Три складові і три передумови максимальної продуктивн...
Yaroslav Rozhankivskyy: Три складові і три передумови максимальної продуктивн...Yaroslav Rozhankivskyy: Три складові і три передумови максимальної продуктивн...
Yaroslav Rozhankivskyy: Три складові і три передумови максимальної продуктивн...Lviv Startup Club
 
How to Get Started in Social Media for Art League City
How to Get Started in Social Media for Art League CityHow to Get Started in Social Media for Art League City
How to Get Started in Social Media for Art League CityEric T. Tung
 
Call Girls Jp Nagar Just Call 👗 7737669865 👗 Top Class Call Girl Service Bang...
Call Girls Jp Nagar Just Call 👗 7737669865 👗 Top Class Call Girl Service Bang...Call Girls Jp Nagar Just Call 👗 7737669865 👗 Top Class Call Girl Service Bang...
Call Girls Jp Nagar Just Call 👗 7737669865 👗 Top Class Call Girl Service Bang...amitlee9823
 
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756dollysharma2066
 
Lucknow 💋 Escorts in Lucknow - 450+ Call Girl Cash Payment 8923113531 Neha Th...
Lucknow 💋 Escorts in Lucknow - 450+ Call Girl Cash Payment 8923113531 Neha Th...Lucknow 💋 Escorts in Lucknow - 450+ Call Girl Cash Payment 8923113531 Neha Th...
Lucknow 💋 Escorts in Lucknow - 450+ Call Girl Cash Payment 8923113531 Neha Th...anilsa9823
 
Famous Olympic Siblings from the 21st Century
Famous Olympic Siblings from the 21st CenturyFamous Olympic Siblings from the 21st Century
Famous Olympic Siblings from the 21st Centuryrwgiffor
 
Mysore Call Girls 8617370543 WhatsApp Number 24x7 Best Services
Mysore Call Girls 8617370543 WhatsApp Number 24x7 Best ServicesMysore Call Girls 8617370543 WhatsApp Number 24x7 Best Services
Mysore Call Girls 8617370543 WhatsApp Number 24x7 Best ServicesDipal Arora
 
Call Girls In DLf Gurgaon ➥99902@11544 ( Best price)100% Genuine Escort In 24...
Call Girls In DLf Gurgaon ➥99902@11544 ( Best price)100% Genuine Escort In 24...Call Girls In DLf Gurgaon ➥99902@11544 ( Best price)100% Genuine Escort In 24...
Call Girls In DLf Gurgaon ➥99902@11544 ( Best price)100% Genuine Escort In 24...lizamodels9
 
Best VIP Call Girls Noida Sector 40 Call Me: 8448380779
Best VIP Call Girls Noida Sector 40 Call Me: 8448380779Best VIP Call Girls Noida Sector 40 Call Me: 8448380779
Best VIP Call Girls Noida Sector 40 Call Me: 8448380779Delhi Call girls
 
7.pdf This presentation captures many uses and the significance of the number...
7.pdf This presentation captures many uses and the significance of the number...7.pdf This presentation captures many uses and the significance of the number...
7.pdf This presentation captures many uses and the significance of the number...Paul Menig
 
KYC-Verified Accounts: Helping Companies Handle Challenging Regulatory Enviro...
KYC-Verified Accounts: Helping Companies Handle Challenging Regulatory Enviro...KYC-Verified Accounts: Helping Companies Handle Challenging Regulatory Enviro...
KYC-Verified Accounts: Helping Companies Handle Challenging Regulatory Enviro...Any kyc Account
 
Pharma Works Profile of Karan Communications
Pharma Works Profile of Karan CommunicationsPharma Works Profile of Karan Communications
Pharma Works Profile of Karan Communicationskarancommunications
 

Recently uploaded (20)

Mondelez State of Snacking and Future Trends 2023
Mondelez State of Snacking and Future Trends 2023Mondelez State of Snacking and Future Trends 2023
Mondelez State of Snacking and Future Trends 2023
 
Call Girls Navi Mumbai Just Call 9907093804 Top Class Call Girl Service Avail...
Call Girls Navi Mumbai Just Call 9907093804 Top Class Call Girl Service Avail...Call Girls Navi Mumbai Just Call 9907093804 Top Class Call Girl Service Avail...
Call Girls Navi Mumbai Just Call 9907093804 Top Class Call Girl Service Avail...
 
Call Girls In Panjim North Goa 9971646499 Genuine Service
Call Girls In Panjim North Goa 9971646499 Genuine ServiceCall Girls In Panjim North Goa 9971646499 Genuine Service
Call Girls In Panjim North Goa 9971646499 Genuine Service
 
Monte Carlo simulation : Simulation using MCSM
Monte Carlo simulation : Simulation using MCSMMonte Carlo simulation : Simulation using MCSM
Monte Carlo simulation : Simulation using MCSM
 
Mifty kit IN Salmiya (+918133066128) Abortion pills IN Salmiyah Cytotec pills
Mifty kit IN Salmiya (+918133066128) Abortion pills IN Salmiyah Cytotec pillsMifty kit IN Salmiya (+918133066128) Abortion pills IN Salmiyah Cytotec pills
Mifty kit IN Salmiya (+918133066128) Abortion pills IN Salmiyah Cytotec pills
 
Ensure the security of your HCL environment by applying the Zero Trust princi...
Ensure the security of your HCL environment by applying the Zero Trust princi...Ensure the security of your HCL environment by applying the Zero Trust princi...
Ensure the security of your HCL environment by applying the Zero Trust princi...
 
Yaroslav Rozhankivskyy: Три складові і три передумови максимальної продуктивн...
Yaroslav Rozhankivskyy: Три складові і три передумови максимальної продуктивн...Yaroslav Rozhankivskyy: Три складові і три передумови максимальної продуктивн...
Yaroslav Rozhankivskyy: Три складові і три передумови максимальної продуктивн...
 
How to Get Started in Social Media for Art League City
How to Get Started in Social Media for Art League CityHow to Get Started in Social Media for Art League City
How to Get Started in Social Media for Art League City
 
Call Girls Jp Nagar Just Call 👗 7737669865 👗 Top Class Call Girl Service Bang...
Call Girls Jp Nagar Just Call 👗 7737669865 👗 Top Class Call Girl Service Bang...Call Girls Jp Nagar Just Call 👗 7737669865 👗 Top Class Call Girl Service Bang...
Call Girls Jp Nagar Just Call 👗 7737669865 👗 Top Class Call Girl Service Bang...
 
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
 
Lucknow 💋 Escorts in Lucknow - 450+ Call Girl Cash Payment 8923113531 Neha Th...
Lucknow 💋 Escorts in Lucknow - 450+ Call Girl Cash Payment 8923113531 Neha Th...Lucknow 💋 Escorts in Lucknow - 450+ Call Girl Cash Payment 8923113531 Neha Th...
Lucknow 💋 Escorts in Lucknow - 450+ Call Girl Cash Payment 8923113531 Neha Th...
 
Famous Olympic Siblings from the 21st Century
Famous Olympic Siblings from the 21st CenturyFamous Olympic Siblings from the 21st Century
Famous Olympic Siblings from the 21st Century
 
Mysore Call Girls 8617370543 WhatsApp Number 24x7 Best Services
Mysore Call Girls 8617370543 WhatsApp Number 24x7 Best ServicesMysore Call Girls 8617370543 WhatsApp Number 24x7 Best Services
Mysore Call Girls 8617370543 WhatsApp Number 24x7 Best Services
 
Call Girls In DLf Gurgaon ➥99902@11544 ( Best price)100% Genuine Escort In 24...
Call Girls In DLf Gurgaon ➥99902@11544 ( Best price)100% Genuine Escort In 24...Call Girls In DLf Gurgaon ➥99902@11544 ( Best price)100% Genuine Escort In 24...
Call Girls In DLf Gurgaon ➥99902@11544 ( Best price)100% Genuine Escort In 24...
 
Best VIP Call Girls Noida Sector 40 Call Me: 8448380779
Best VIP Call Girls Noida Sector 40 Call Me: 8448380779Best VIP Call Girls Noida Sector 40 Call Me: 8448380779
Best VIP Call Girls Noida Sector 40 Call Me: 8448380779
 
7.pdf This presentation captures many uses and the significance of the number...
7.pdf This presentation captures many uses and the significance of the number...7.pdf This presentation captures many uses and the significance of the number...
7.pdf This presentation captures many uses and the significance of the number...
 
Forklift Operations: Safety through Cartoons
Forklift Operations: Safety through CartoonsForklift Operations: Safety through Cartoons
Forklift Operations: Safety through Cartoons
 
VVVIP Call Girls In Greater Kailash ➡️ Delhi ➡️ 9999965857 🚀 No Advance 24HRS...
VVVIP Call Girls In Greater Kailash ➡️ Delhi ➡️ 9999965857 🚀 No Advance 24HRS...VVVIP Call Girls In Greater Kailash ➡️ Delhi ➡️ 9999965857 🚀 No Advance 24HRS...
VVVIP Call Girls In Greater Kailash ➡️ Delhi ➡️ 9999965857 🚀 No Advance 24HRS...
 
KYC-Verified Accounts: Helping Companies Handle Challenging Regulatory Enviro...
KYC-Verified Accounts: Helping Companies Handle Challenging Regulatory Enviro...KYC-Verified Accounts: Helping Companies Handle Challenging Regulatory Enviro...
KYC-Verified Accounts: Helping Companies Handle Challenging Regulatory Enviro...
 
Pharma Works Profile of Karan Communications
Pharma Works Profile of Karan CommunicationsPharma Works Profile of Karan Communications
Pharma Works Profile of Karan Communications
 

Panel 2. CCS in the Asian Century - Ashok Bhargava, ADB

  • 1. CCS Activities in Developing Asia– Insights and Next Steps Ashok Bhargava Director, Energy Division East Asia Department Seoul, 10 October 2013
  • 2. ADB CCS Fund  In June 2009, ADB established a CCS Fund with an initial contribution of AUD 21.5 million from the Global CCS Institute, Australia. In 2012, Government of the United Kingdom also pledged £35 million in the fund.  Specific Eligibility Criteria  Accelerate demonstration of CCS technologies  Identify, lower and / or eliminate general or country specific barriers for CCS demonstration  Identify, eliminate or mitigate risks in capture, transport and storage technology demonstration
  • 3. … in the People’s Republic of China
  • 4. PRC – Overview of ADB Activities Capacity Development and Policy Advisory Assistance  Key Partner Department of Climate Change, NDRC  Target three major China Huaneng : pre-combustion capture – IGCC capture technologies China Datang : post-combustion capture natural gas plant Dongfang Boiler – Oxy-fuel combustion capture - coal-based power plant Support upstream analytical work, analyze issues, identify costs and risks on real projects
  • 5. PRC – Overview of ADB Activities Develop CCS Roadmap  Aims to develop a  Includes following major outputs 1. Time bound action plan for demonstration (up to 2020) and deployment (up to 2025) 2. A policy and regulatory framework with an accompanying set of incentives 3. Shortlist and ranking of early-stage CCS demonstration projects 4. key planning tool for the Government to demonstrate and deploy CCS Suitable business models for implementing early-stage projects Establish enabling environment for CCS demonstration and possible deployment.
  • 6. Next Steps in the PRC ……….. Pilot Project
  • 7. Next Steps ………. Pilot CCS Project at Tianjin IGCC Power Plant  Capture up to 100,000 tons CO2 / year to partially used for EOR and partially for storage  Due diligence is underway; power and oil company collaboration proving difficult  ADB may provide up to $10 million grant for CapEx and a compensatory mechanism to offset energy penalty  Pilot project likely to be in operation by 2015
  • 8. Next Steps ………. FEED Studies for a large-scale CCS project  Need to scale-up CCS efforts urgently  Discussions underway to select one of the early-stage projects identified through the ongoing CCS road map work
  • 9. What have we learned so far in the PRC  Technical readiness  In-country technical capacity exists; large  Weak policy support number of point sources in close proximity to potential storage sites  CCS is not a strategic choice; no national target, incentives or support mechanism in place.  Fragmented institutional setup across CCS chain  Need for public financing  Negligible cooperation between power and oil companies not conducive for CCS  Early projects will need risk sharing or preferably risk bearing by the Government
  • 10. Moving on to Southeast Asia ………..
  • 11. Potential for CCS in Southeast Asia • A regional study with focus on Thailand, Vietnam, Indonesia, Philippines completed recently  Study aimed to: i. Establish inventory of CO2 emission sources ii. Estimate storage potential Determine source-sink matches for CCS Identify potential pilot projects Propose Road Map for CCS development Develop “CCS Working Groups” which could provide leadership on CCS iii. iv. v. vi.
  • 12. Potential for CCS in Southeast Asia - Main Results  Sufficient capture streams are available  Natural gas processing and new power plants are best sources for capture Annual inventory of 200 million tons of CO2 emissions from sources (coal and gas power plants, natural gas processing facilities, future power plants, and smaller sources such as fertilizer plants) Natural gas processing facilities are preferred because of lower incremental cost of capture, storage site proximity, and existing transport infrastructure
  • 13. Potential for CCS in Southeast Asia - Main Results….contd  Large storage capacity  Large number of oil and gas fields provide adequate storage for early stage projects Estimated storage capacity of 56 giga tons of which about 90% is in saline aquifiers. But due to uncertainties of aquifiers, study concentrated on oil and gas fields 143 oil and gas fields offer more than 3 giga tons of capacity. Since the geology is well understood of these fields, they were ranked for early stage projects.
  • 14. Potential for CCS in Southeast Asia - Main Results….contd
  • 15. Next step in Southeast Asia Region – Pilot Project in Indonesia  Collaborative approach Collaboration with JICA, Pertamina, and Institut Teknologi di Bandung Follows on a JICA scoping study ($5 million, 5year) at Gundih gas field in Central Java  Due diligence support • Pilot project financing support ADB to provide due diligence support to PERTAMINA to review preliminary design of surface facilities for test injection, identify legal and regulatory issues and develop regulations and apply for permits as appropriate. ADB may follow with a $10 million grant for capture and test injection from its CCS Fund
  • 16. What did we learn so far in developing Asia for CCS ………..
  • 17. Key Issues and Barriers ADB (2011): “… key barriers to CCS are amplified in developing countries ….” CCS is a last resort policy approach Limited public awareness Absence of targeted incentives / concessional financing mechanism Lack of delivery mechanism / business model Energy intensive mitigation approach Lack of incountry experience in planning, construction and operation
  • 18. Way Forward Demonstration projects in identification stage ADB (2011): CCS is a last “… key barriers to resort policy CCS are amplified in approach developing countries Government Commitment, incl. ….” Limited policy targets, regulatory, fiscal, public awareness and financial support measures Right business models for early Absence of stage demonstration projects targeted incentives / concessional Mechanisms to offset higher costs, and financing energy penalty mechanism Lack of delivery Awareness and support from civil / mechanism business model society Energy intensive mitigation approach Lack of incountry experience in planning, construction and operation Realized demonstration projects