This document analyzes different ship design options for carrying the equipment and personnel of a future Maritime Prepositioned Force (MPF(F)). It studies eight designs and evaluates each one's ability to load and transport the required equipment, vehicles, supplies and personnel of a 2015 Marine Expeditionary Brigade (MEB) reinforced with supporting Navy forces. The analysis finds that only two of the designs, Option 1 (Distributed Capabilities) and Options 2 & 5 (Family of Ships), can fully load and offload the MPF(F) forces within the desired 8-10 hour timeline. However, none of the designs can fully accommodate all of the required equipment and personnel while maintaining the desired capabilities.