Island School Redevelopment
at 20 Borrett Road, Mid-Levels, Hong Kong
Students Workshop
22 January 2015
ESF / Island School / TCA / shl / RLB / AECOM / AURECON / URBIS / MVA / Fotton/ isBIM
01	Introduction
ESF / Island School / TCA / shl / RLB / AECOM / AURECON / URBIS / MVA / Fotton / isBIM
Island School Redevelopment / Hong Kong
Students’ Workshop
22 January 2015
INTRODUCTION OVERALL DESIGN
APPROACH
TECHNICAL ISSUES RECOMMENDATION
& PROGRAMME
01 02 03 04
S
R
Q
P
N
M
L
K
H
G
F
E
D
C
B
A
J
Island School
BORRETT ROAD
N
ESF / Island School / TCA / shl / RLB / AECOM / AURECON / URBIS / MVA / Fotton / isBIM
Island School Redevelopment / Hong Kong
Students’ Workshop
22 January 2015
INTRODUCTION OVERALL DESIGN
APPROACH
TECHNICAL ISSUES RECOMMENDATION
& PROGRAMME
01 02 03 04
VISION/
ESF & Island School’s vision for the new Island School provides a qualitative design framework:
•	 To ensure that the educational, personal and social needs of the students,
staff and community be met in a safe, secure, welcoming and
inclusive environment;
•	 To create an environment which is flexible and can embrace the use of
new technologies and different learning styles;
•	 To create a campus that is an exemplar of sustainable design,
which can be used as a tool for teaching the principles of environmental
conservation to students;
•	 To ensure our new campus reflects all that works so well about our current
one, that it supports ESF and Island School ethos and yet it
benefits from all that is best about emerging ideas for school design from
around the world.
BLOCK 5 PLAYGROUNDCOMMUNAL SPACESHOUSES
02	Overall Design Approach
INTRODUCTION OVERALL DESIGN
APPROACH
TECHNICAL ISSUES RECOMMENDATION
& PROGRAMME
01 02 03 04
ESF / Island School / TCA / shl / RLB / AECOM / AURECON / URBIS / MVA / Fotton / isBIM
Island School Redevelopment / Hong Kong
Students’ Workshop
22 January 2015
classroom classroom
classroom
classroom
classroom
classroom
classroom classroom
classroom
classroom
classroom
classroom
classroom
classroom
sroom
sroom
classroom
classroom
lassroomclassroomclassroomclassroom
corridor
classroom
classroom
classroom
classroom
classroom
classroom
classroomclassroom
classroomclassroom
classroom
classroom
classroomclassroom
classroom
classroom
classroom
classroom
classroom
classroomclassroom classroom classroom classroom classroom
corridor
classroom
classroom
classroom
classroom
classroom classroom
classroom
classroom
classroom
classroom
classroom classroom
classroom
classroom
classroom
classroom
classroom
classroom
classroom
classroom
classroomclassroom
classroom
classroom
classroom
classroom
classroom
classroom classroomclassroomclassroomclassroomclassroom
corridor
classroom
classroom
classroom
classroom
classroomclassroom
classroom
classroom
classroom
classroom
classroomclassroom
classroom
classroom
classroom
classroom
classroom
classroom
classroom
classroom
classroomclassroom
classroom
classroom
classroom
classroom
classroom
classroom
classroom classroom classroom classroom classroom
corridor
classroom
classroom
classroom
classroom
classroom classroom
classroom
classroom
classroom
classroom
classroom classroom
classroom
classroom
classroom
classroom
classroom
classroom
classroom
classroom
classroomclassroom
classroom
classroom
classroom
classroom
classroom
classroom
classroom classroom classroom classroom classroom
corridor
classroom
classroom
classroom
classroom
classroom classroom
classroom
classroom
classroom
classroom
classroom classroom
classroom
classroom
classroom
classroom
classroom
classroom
classroom
classroom
classroomclassroom
classroom
classroom
classroom
classroom
classroom
classroom
lassroomclassroomclassroomclassroom
corridor
classroom
classroom
classroom
classroom
classroom
classroom
classroomclassroom
classroomclassroom
classroom
classroom
classroom classroom
classroom
classroom
classroom
classroom
classroom
classroom
classroom classroom classroom classroom classroom
corridor
classroom
classroom
classroom
classroom
classroom classroom
classroom
classroom
classroom
classroom
classroom classroom
classroom
classroom
classroom
classroom
classroom
classroom
classroom
classroom
classroomclassroom
classroom
classroom
classroom
classroom
classroom
classroom
classroom classroom classroom classroom classroom
corridor
classroom
classroom
classroom
classroom
classroom classroom
classroom
classroom
classroom
classroom
classroom classroom
classroom
classroom
classroom
classroom
classroom
classroom
classroom
classroom
classroomclassroom
classroom
classroom
classroom
classroom
classroom
classroom
classroom classroom classroom classroom classroom
corridor
classroom
classroom
classroom
classroom
classroom classroom
classroom
classroom
classroom
classroom
classroom classroom
classroom
classroom
classroom
classroom
classroom
classroom
classroom
classroom
classroomclassroom
classroom
classroom
classroom
classroom
classroom
classroom
Social/
•	 Hybrid of village & campus approach
to create an extended social spaces
between buildings
•	 This social approach focus on the spatial
organisation to encourage social activities
Landscape/
•	 The building form adapt to the site
topography, another landscape is re-
created
•	 Greening area is maximised and more
flexible spaces are created
Village/
•	 Conventional
•	 Cluster with small footprints
•	 Series of open spaces formed
•	 Resemble existing IS arrangement
Loop/
•	 Hybrid of linear and folded approach to
form a loop to maximise the use of site
area
•	 Large internal social space is formed,
Kellett School is an example of this type
Campus/
•	 Larger footprint with internal social
spaces
•	 Encourage more social activities
•	 More flexible learning spaces could be
enabled with larger footprints
classroom classroom classroom classroom classroom
corridor
classroom
classroom
classroom
classroom
classroom classroom
classroom
classroom
classroom
classroom
classroom classroom
classroom
classroom
classroom
classroom
classroom
classroom
classroom
classroom
classroomclassroom
classroom
classroom
classroom
classroom
classroom
classroom
classroom classroom classroom classroom classroom
corridor
classroom
classroom
classroom
classroom
classroom classroom
classroom
classroom
classroom
classroom
classroom classroom
classroom
classroom
classroom
classroom
classroom
classroom
classroom
classroom
classroomclassroom
classroom
classroom
classroom
classroom
classroom
classroom
+ + FILLING
MASSING OPTIONS OVERVIEW/
INTRODUCTION OVERALL DESIGN
APPROACH
TECHNICAL ISSUES RECOMMENDATION
& PROGRAMME
01 02 03 04
ESF / Island School / TCA / shl / RLB / AECOM / AURECON / URBIS / MVA / Fotton / isBIM
Island School Redevelopment / Hong Kong
Students’ Workshop
22 January 2015 Thomas Chow Architects + schmidt hammer lassen architects 42/Island School Redevelopment / Hong Kong
Co-Creation (Stage C) Design Review - Massing Design Options
14/10/2014
Massing Typology Options Overview/
Social Option/ Option C/ LandscapeOption A/ Village Option D/ LoopOption B/ Campus
Island Spirit (Communal Space)/
Island Spirit (Sightline)/
Flexibility/
Natural Light/
Ventilation/
Greening/
Island Spirit (Communal Space)/
Island Spirit (Sightline)/
Flexibility/
Natural Light/
Ventilation/
Greening/
Island Spirit (Communal Space)/
Island Spirit (Sightline)/
Flexibility/
Natural Light/
Ventilation/
Greening/
Island Spirit (Communal Space)/
Island Spirit (Sightline)/
Flexibility/
Natural Light/
Ventilation/
Greening/
Island Spirit (Communal Space)/
Island Spirit (Sightline)/
Flexibility/
Natural Light/
Ventilation/
Greening/
MASSING OPTIONS OVERVIEW/
INTRODUCTION OVERALL DESIGN
APPROACH
TECHNICAL ISSUES RECOMMENDATION
& PROGRAMME
01 02 03 04
ESF / Island School / TCA / shl / RLB / AECOM / AURECON / URBIS / MVA / Fotton / isBIM
Island School Redevelopment / Hong Kong
Students’ Workshop
22 January 2015
Social Option Landscape Option
INTRODUCTION OVERALL DESIGN
APPROACH
TECHNICAL ISSUES RECOMMENDATION
& PROGRAMME
01 02 03 04
ESF / Island School / TCA / shl / RLB / AECOM / AURECON / URBIS / MVA / Fotton / isBIM
Island School Redevelopment / Hong Kong
Students’ Workshop
22 January 2015
Science
Technology
Creative Arts
Sharing/ Flexible Teaching
+167.4 4/F
Science
Technology
Creative Arts
Sharing/ Flexible Teaching
Adminstration
+163.8 3/F
English
Humanities
IN/ EAL
Administration
+160.2 2/F
Language
IN/ EAL
Sharing/ Flexible Teaching
Administration
+156.6 1/F
Mathematics
Physical Education
Sharing/ Flexible Teaching
Administration
Amenities
+152.1 G/F
Creative Arts
Physical Education
Administration
Amenities
+148.1 LG1M
Creative Arts
Physical Education
Sharing/ Flexible Teaching
Amenities
+143.4 LG1
Car Park
+136.0 LG2
Social Option/
NOFA	 14,751m2
		 17,251m2
		 (incl. covered carpark & drop-off)
CFA		 29,590m2
Efficiency (NOFA/CFA)	 0.58
INTRODUCTION OVERALL DESIGN
APPROACH
TECHNICAL ISSUES RECOMMENDATION
& PROGRAMME
01 02 03 04
ESF / Island School / TCA / shl / RLB / AECOM / AURECON / URBIS / MVA / Fotton / isBIM
Island School Redevelopment / Hong Kong
Students’ Workshop
22 January 2015
English
Language
IN/ EAL
Administration
Humanities
Mathematics
Technology
Administration
Administration
Technology
Creative Arts
Science
Technology
Creative Arts
Science
Creative Arts
Physical Education
Creative Arts
Physical Education
Sharing/ Flexible Teaching
Administration
Amenities
Physical Education
+152.0 G/F
+148.2 LG1M
+143.0 LG1
+136.0 LG2
+158.4 2/F
+162.3 3/F
+166.2 4/F
+154.5 1/F
Landscape Option/
NOFA	 14,751m2
		 17,251m2
		 (incl. covered carpark & drop-off)
CFA		 32,480m2
Efficiency (NOFA/CFA)	 0.53
INTRODUCTION OVERALL DESIGN
APPROACH
TECHNICAL ISSUES RECOMMENDATION
& PROGRAMME
01 02 03 04
ESF / Island School / TCA / shl / RLB / AECOM / AURECON / URBIS / MVA / Fotton / isBIM
Island School Redevelopment / Hong Kong
Students’ Workshop
22 January 2015
02a	 The PATH
INTRODUCTION OVERALL DESIGN
APPROACH
TECHNICAL ISSUES RECOMMENDATION
& PROGRAMME
01 02 03 04
ESF / Island School / TCA / shl / RLB / AECOM / AURECON / URBIS / MVA / Fotton / isBIM
Island School Redevelopment / Hong Kong
Students’ Workshop
22 January 2015
The Heart of the Island School - The Path/
to link the mountain/nature with the harbour/city with a lot of different activities extended from it
•	 THE PATH
INTRODUCTION OVERALL DESIGN
APPROACH
TECHNICAL ISSUES RECOMMENDATION
& PROGRAMME
01 02 03 04
ESF / Island School / TCA / shl / RLB / AECOM / AURECON / URBIS / MVA / Fotton / isBIM
Island School Redevelopment / Hong Kong
Students’ Workshop
22 January 2015
PLAZA 2PLAZA 1
SCIENCE
RESEARCH LAB
INTEGRATED
HUMANITIES STUDIO
CREATIVE HUB
LANGUAGE
SHARED
LRC/ SLC
& SHARED
TEACHING
SPACES
LRC
(QUIET)
ADMISSION
OFFICE etc
+RECEPTION
SLT & ADMIN
HARBOUR
BORRETTROAD
CAFE
MINI LECTURE
THEATRE
BORRETTROAD
MINI LECTURE
THEATRE
ART
D&T
ATRIUM
SOCCER
PITCH
•	 Open
•	 Vibrant
•	 Well-articulated & More Vibrant
•	 House Commons along the Path
•	 Internal
•	 More Enclosed
•	 Spaces Connected by More Enclosed Corridors
•	 Follow the stepping of the Building Mass
PLAYGROUND
•	 THE PATH
Social Option Landscape Option
INTRODUCTION OVERALL DESIGN
APPROACH
TECHNICAL ISSUES RECOMMENDATION
& PROGRAMME
01 02 03 04
ESF / Island School / TCA / shl / RLB / AECOM / AURECON / URBIS / MVA / Fotton / isBIM
Island School Redevelopment / Hong Kong
Students’ Workshop
22 January 2015
•	 THE PATH/ Houses
INTRODUCTION OVERALL DESIGN
APPROACH
TECHNICAL ISSUES RECOMMENDATION
& PROGRAMME
01 02 03 04
ESF / Island School / TCA / shl / RLB / AECOM / AURECON / URBIS / MVA / Fotton / isBIM
Island School Redevelopment / Hong Kong
Students’ Workshop
22 January 2015
LG/ 2* GF/ 1 L1/ 3 L2/ 2*
Proposed
HOUSE COMMONS
Proposed HOUSE COMMONS
on the other side of the PATH
L2/ 2*
L1/ 3
GF/ 1
LG/ 2*
•	 THE PATH/ Houses
Social Option
INTRODUCTION OVERALL DESIGN
APPROACH
TECHNICAL ISSUES RECOMMENDATION
& PROGRAMME
01 02 03 04
ESF / Island School / TCA / shl / RLB / AECOM / AURECON / URBIS / MVA / Fotton / isBIM
Island School Redevelopment / Hong Kong
Students’ Workshop
22 January 2015
GF/ 2 L1/ 2 L2/ 2
L2/ 2
The Path
L1/ 2
GF/ 2
•	 THE PATH/ Houses
Landscape Option
INTRODUCTION OVERALL DESIGN
APPROACH
TECHNICAL ISSUES RECOMMENDATION
& PROGRAMME
01 02 03 04
ESF / Island School / TCA / shl / RLB / AECOM / AURECON / URBIS / MVA / Fotton / isBIM
Island School Redevelopment / Hong Kong
Students’ Workshop
22 January 2015
02b	Terraces
INTRODUCTION OVERALL DESIGN
APPROACH
TECHNICAL ISSUES RECOMMENDATION
& PROGRAMME
01 02 03 04
ESF / Island School / TCA / shl / RLB / AECOM / AURECON / URBIS / MVA / Fotton / isBIM
Island School Redevelopment / Hong Kong
Students’ Workshop
22 January 2015
•	 Visual Connection from Above to the Open Playground
•	 Enable Students’ Participation from Above as Existing School
•	 Visual Connection with the Hill behind
•	 Terraces with Varieties in Size
•	 No Visual Connection with the Ballcourts
•	 Stepping Effect Easily Visualised from the Outside - Image of the
Island School
•	 TERRACES
Social Option Landscape Option
INTRODUCTION OVERALL DESIGN
APPROACH
TECHNICAL ISSUES RECOMMENDATION
& PROGRAMME
01 02 03 04
ESF / Island School / TCA / shl / RLB / AECOM / AURECON / URBIS / MVA / Fotton / isBIM
Island School Redevelopment / Hong Kong
Students’ Workshop
22 January 2015
•	 TERRACES
•	Visual Connection from Above to the
Open Playground
•	Enable Students’ Participation from
Above as Existing School
•	Visual Connection with the Hill behind
INTRODUCTION OVERALL DESIGN
APPROACH
TECHNICAL ISSUES RECOMMENDATION
& PROGRAMME
01 02 03 04
ESF / Island School / TCA / shl / RLB / AECOM / AURECON / URBIS / MVA / Fotton / isBIM
Island School Redevelopment / Hong Kong
Students’ Workshop
22 January 2015
02c	 Open Playgrounds
INTRODUCTION OVERALL DESIGN
APPROACH
TECHNICAL ISSUES RECOMMENDATION
& PROGRAMME
01 02 03 04
ESF / Island School / TCA / shl / RLB / AECOM / AURECON / URBIS / MVA / Fotton / isBIM
Island School Redevelopment / Hong Kong
Students’ Workshop
22 January 2015
1
2
450 m2
/ GF
About 80% of existing block 5
playground
255 m2
/ L1
1650 m2
/ GF
More than twice of block 5
playground
660 m2
/ GF
About the size of existing block 5
playground
850 m2
/ L3
500 m2
/ GF
Open Deck
•	 2 no. of outdoor spaces with total area of more than 3 times of existing block 5 playground •	 Open playground at GF to fulfil lease conditions requirement
•	 OPEN PLAYGROUNDS
Social Option Landscape Option
•	 More Open Playgrounds •	 Less Open Playgrounds
INTRODUCTION OVERALL DESIGN
APPROACH
TECHNICAL ISSUES RECOMMENDATION
& PROGRAMME
01 02 03 04
ESF / Island School / TCA / shl / RLB / AECOM / AURECON / URBIS / MVA / Fotton / isBIM
Island School Redevelopment / Hong Kong
Students’ Workshop
22 January 2015
02d	 Flexible Teaching Spaces
INTRODUCTION OVERALL DESIGN
APPROACH
TECHNICAL ISSUES RECOMMENDATION
& PROGRAMME
01 02 03 04
ESF / Island School / TCA / shl / RLB / AECOM / AURECON / URBIS / MVA / Fotton / isBIM
Island School Redevelopment / Hong Kong
Students’ Workshop
22 January 2015
•	 house area/
•	 learning area/
•	 informal learning/
•	 social interaction/
informal learning/
self-study/
group work/
Architectural furniture
(lockers) can be
installed in the house
areas in zone C for
space definition and
to integrate social
space with learning
space
•	 FLEXIBLE TEACHING SPACES
INTRODUCTION OVERALL DESIGN
APPROACH
TECHNICAL ISSUES RECOMMENDATION
& PROGRAMME
01 02 03 04
ESF / Island School / TCA / shl / RLB / AECOM / AURECON / URBIS / MVA / Fotton / isBIM
Island School Redevelopment / Hong Kong
Students’ Workshop
22 January 2015
•	 engagement activities and briefings
•	 involve more teacher led activities and whole class
work
•	 support lecture style learning
•	 considerable degree of flexibility through judicious
choice of furniture
Engagement Space (Zone A)/
•	 researching, analysing, questioning, creating and
collaborating activities
•	 support both individual and group work
•	 high level of porosity
•	 division by architecural furniture and non-load bearing
“walls”
Processing Space (Zone B)/
•	 combined learning/ house areas
•	 support more informal learning and social interaction
•	 larger level of movement and link with main circulation
routes directly
•	 combine with terraces look over and across large
communal spaces
Community Space (Zone C)/
B CA
OPAQUE
FIXED
IMPERMEABLE
FORMAL
TRANSPARENT
FLEXIBLE
PERMEABLE
SOCIAL
Transition of Learning Spaces/
•	 Opacity
•	 Flexibility
•	 Permeability
•	 Formality
•	 FLEXIBLE TEACHING SPACES
INTRODUCTION OVERALL DESIGN
APPROACH
TECHNICAL ISSUES RECOMMENDATION
& PROGRAMME
01 02 03 04
ESF / Island School / TCA / shl / RLB / AECOM / AURECON / URBIS / MVA / Fotton / isBIM
Island School Redevelopment / Hong Kong
Students’ Workshop
22 January 2015
A
A A
AA
A
A
A
C
C C
C
C
B
B B
B
B
A
A
A
A
A
A
A
A A
A
C
C
C
B
B B
B
B
A
A
A A
A
A
A
C
C
A
A
A
A A
Typology for Flexible Arrangement/
•	 SOA (teaching) = A+B
•	 which could be converted to 10 no. of enclosed teaching spaces if required
•	 more space provided
•	 more flexible layout to adapt to different uses
AREA A < AREA A+B EFFICIENCY
OR
Typology for Traditional Arrangement/
•	 SOA (teaching) = A
•	 10 enclosed teaching spaces
•	 less space provided
•	 more difficult to use break-out spaces
•	 FLEXIBLE TEACHING SPACES
INTRODUCTION OVERALL DESIGN
APPROACH
TECHNICAL ISSUES RECOMMENDATION
& PROGRAMME
01 02 03 04
ESF / Island School / TCA / shl / RLB / AECOM / AURECON / URBIS / MVA / Fotton / isBIM
Island School Redevelopment / Hong Kong
Students’ Workshop
22 January 2015
Transition of Learning Spaces/
Transition radially from the Heart of the School towards the skin, from sharing spaces to more specific spaces
SPECIFIC
SHARED
OPAQUE
FIXED
IMPERMEABLE
FORMAL
TRANSPARENT
FLEXIBLE
PERMEABLE
SOCIAL
SPECIFIC OPAQUE
FIXED
IMPERMEABLE
FORMAL
SPECIFIC
SHARED
OPAQUE
FIXED
IMPERMEABLE
FORMAL
TRANSPARENT
FLEXIBLE
PERMEABLE
SOCIAL
SP
OPA
FIXE
IMP
FOR
•	 CAMPUS ORGANISATION
INTRODUCTION OVERALL DESIGN
APPROACH
TECHNICAL ISSUES RECOMMENDATION
& PROGRAMME
01 02 03 04
ESF / Island School / TCA / shl / RLB / AECOM / AURECON / URBIS / MVA / Fotton / isBIM
Island School Redevelopment / Hong Kong
Students’ Workshop
22 January 2015
•	 FLEXIBLE TEACHING SPACES (SPACE PLANNING, NATURAL LIGHTING & VENTILATION
and ENERGY CONSUMPTION)
Social Option
•	 Balanced Flexible Teaching Spaces
•	 Adequate Natural Light and Ventilation Provision
•	 Less Energy Consumption
INTRODUCTION OVERALL DESIGN
APPROACH
TECHNICAL ISSUES RECOMMENDATION
& PROGRAMME
01 02 03 04
ESF / Island School / TCA / shl / RLB / AECOM / AURECON / URBIS / MVA / Fotton / isBIM
Island School Redevelopment / Hong Kong
Students’ Workshop
22 January 2015
Landscape Option
•	 More Flexible Teaching Spaces
•	 Deeper Floor Plate leading to Inadequate Natural Light and
Ventilation
•	 Light wells Introduced which limits the Flexibility of the spaces
•	 More Energy Consumption
•	 FLEXIBLE TEACHING SPACES (SPACE PLANNING, NATURAL LIGHTING & VENTILATION
and ENERGY CONSUMPTION)
INTRODUCTION OVERALL DESIGN
APPROACH
TECHNICAL ISSUES RECOMMENDATION
& PROGRAMME
01 02 03 04
ESF / Island School / TCA / shl / RLB / AECOM / AURECON / URBIS / MVA / Fotton / isBIM
Island School Redevelopment / Hong Kong
Students’ Workshop
22 January 2015
•	 FLEXIBLE TEACHING SPACES (SPACE PLANNING, NATURAL LIGHTING & VENTILATION
and ENERGY CONSUMPTION)
Social Option
Landscape Option
INTRODUCTION OVERALL DESIGN
APPROACH
TECHNICAL ISSUES RECOMMENDATION
& PROGRAMME
01 02 03 04
ESF / Island School / TCA / shl / RLB / AECOM / AURECON / URBIS / MVA / Fotton / isBIM
Island School Redevelopment / Hong Kong
Students’ Workshop
22 January 2015
Landscape Option
•	 FLEXIBLE TEACHING SPACES/ LRC
INTRODUCTION OVERALL DESIGN
APPROACH
TECHNICAL ISSUES RECOMMENDATION
& PROGRAMME
01 02 03 04
ESF / Island School / TCA / shl / RLB / AECOM / AURECON / URBIS / MVA / Fotton / isBIM
Island School Redevelopment / Hong Kong
Students’ Workshop
22 January 2015
Social Option
•	 FLEXIBLE TEACHING SPACES/ LRC
INTRODUCTION OVERALL DESIGN
APPROACH
TECHNICAL ISSUES RECOMMENDATION
& PROGRAMME
01 02 03 04
ESF / Island School / TCA / shl / RLB / AECOM / AURECON / URBIS / MVA / Fotton / isBIM
Island School Redevelopment / Hong Kong
Students’ Workshop
22 January 2015
02f	 Sports Complex
INTRODUCTION OVERALL DESIGN
APPROACH
TECHNICAL ISSUES RECOMMENDATION
& PROGRAMME
01 02 03 04
ESF / Island School / TCA / shl / RLB / AECOM / AURECON / URBIS / MVA / Fotton / isBIM
Island School Redevelopment / Hong Kong
Students’ Workshop
22 January 2015
GF
Transfer & Open Playground
LG
Large Volumes
SPORTS
HALLBLACK
BOX
SWIMMING
POOL
PLAY-
GROUND
GF
Transfer & Open Playground
LG
Large Volumes
BLACK
BOX
SPORTS
HALL
SWIMMING
POOL
PLAY-
GROUND
Swimming Pool/Swimming Pool/
•	 SPORTS COMPLEX
Social Option Landscape Option
INTRODUCTION OVERALL DESIGN
APPROACH
TECHNICAL ISSUES RECOMMENDATION
& PROGRAMME
01 02 03 04
ESF / Island School / TCA / shl / RLB / AECOM / AURECON / URBIS / MVA / Fotton / isBIM
Island School Redevelopment / Hong Kong
Students’ Workshop
22 January 2015
02h	Summary
INTRODUCTION OVERALL DESIGN
APPROACH
TECHNICAL ISSUES RECOMMENDATION
& PROGRAMME
01 02 03 04
ESF / Island School / TCA / shl / RLB / AECOM / AURECON / URBIS / MVA / Fotton / isBIM
Island School Redevelopment / Hong Kong
Students’ Workshop
22 January 2015
Social Option Landscape Option
DESIGN & PLANNING SUMMARY/
03 Technical Issues
a)		 Site Formation, Foundation
b)		 Superstructure
c)		 Building Services
d)		 Greening Design
e)		 Sustainability
f)		 Cost Issues
INTRODUCTION OVERALL DESIGN
APPROACH
TECHNICAL ISSUES RECOMMENDATION
& PROGRAMME
01 02 03 04
ESF / Island School / TCA / shl / RLB / AECOM / AURECON / URBIS / MVA / Fotton / isBIM
Island School Redevelopment / Hong Kong
Students’ Workshop
22 January 2015
Site Formation & Foundation Design Strategy/
•	 Re-use Existing Retaining Structures
•	 Avoid Extensive Excavation by Localising the Extent of Areas Lower than Existing Levels
•	 Back-fill
BLOCK
7
BLOCK
2
HALL
Swim
m
ing
Pool
Block5
Playground
BLOCK
1
BLOCK
5
BLOCK
4
BLOCK
3
B O R R E T T R O A D
Keep
Keep & Abandoned
Demolished
INTRODUCTION OVERALL DESIGN
APPROACH
TECHNICAL ISSUES RECOMMENDATION
& PROGRAMME
01 02 03 04
ESF / Island School / TCA / shl / RLB / AECOM / AURECON / URBIS / MVA / Fotton / isBIM
Island School Redevelopment / Hong Kong
Students’ Workshop
22 January 2015
Hybrid of Foundation Systems/
•	 Footing, where Rock Head Level is High
•	 Piling, where Rock Head Level is Low
INTRODUCTION OVERALL DESIGN
APPROACH
TECHNICAL ISSUES RECOMMENDATION
& PROGRAMME
01 02 03 04
ESF / Island School / TCA / shl / RLB / AECOM / AURECON / URBIS / MVA / Fotton / isBIM
Island School Redevelopment / Hong Kong
Students’ Workshop
22 January 2015
SPORTS HALL
BORRETTROAD
Deep Transfer
Structure (3m)
Cantilever
Structure
towards the Hill
Swimming Pool
•	 Sports Hall - no Transfer Above
•	 Black Box - no Transfer Above
•	 Swimming Pool - Partial Transfer Above
•	 Reinforced Concrete Ratio:		 0.49m3
/m2
floor area
•	 Steel Reinforcement:			148kg/m2
floor area
•	 Sports Hall - Transfer of 5 floors Above
•	 Black Box - Transfer of 5 floors Above
•	 Swimming Pool - Transfer of 5 floors Above
•	 Reinforced Concrete Ratio:		 0.61m3
/m2
floor area
•	 Steel Reinforcement:			183kg/m2
floor area
Transfer Structure
-> Larger Structural Member Size and More Reinforcement
-> Less Headroom and More Costly
Superstructure/
INTRODUCTION OVERALL DESIGN
APPROACH
TECHNICAL ISSUES RECOMMENDATION
& PROGRAMME
01 02 03 04
ESF / Island School / TCA / shl / RLB / AECOM / AURECON / URBIS / MVA / Fotton / isBIM
Island School Redevelopment / Hong Kong
Students’ Workshop
22 January 2015
Building Services/
Electrical Services
Electrical Supply System
Metering
Earthing and Lightning System
Lighting System
Elevator System
Emergency Lighting System
Security System
Broadcast Reception Installation
Telephone Installation
BMS
Mechanical Services
MVAC System
Fire Services System
Water Supply System
Drainage System
Gas Supply System
Swimming Pool Water Filtration System
Other Specialist Systems
Wireless Broadband System
Public Address System
IT Network and Backbone Infrastructure
Library Security System
Library Lending and Borrowing System
Smart Card System
Audio/ Visual System (AV)
AV and Stage Lighting System
Master School Bell System
INTRODUCTION OVERALL DESIGN
APPROACH
TECHNICAL ISSUES RECOMMENDATION
& PROGRAMME
01 02 03 04
ESF / Island School / TCA / shl / RLB / AECOM / AURECON / URBIS / MVA / Fotton / isBIM
Island School Redevelopment / Hong Kong
Students’ Workshop
22 January 2015
Greening Design/
Vertical greening next to Half Court
Figure 8
Terraced landscape at hillside
Figure 4
Entrance of the PATH
Figure 6
•	The PATH
•	PATH Entrance
•	Hillside Terraces •	Green Wall screen off
Ball Courts
INTRODUCTION OVERALL DESIGN
APPROACH
TECHNICAL ISSUES RECOMMENDATION
& PROGRAMME
01 02 03 04
ESF / Island School / TCA / shl / RLB / AECOM / AURECON / URBIS / MVA / Fotton / isBIM
Island School Redevelopment / Hong Kong
Students’ Workshop
22 January 2015
Sustainable Design/
•	 Food Waste Decomposition
•	 Dead Plants Decomposition
•	 Grey Water Recycling System
•	 Rainwater Recycling for Irrigation
•	 Energy Generating Floor
•	 Weather-based Irrigation
Control System
•	 Wind Turbine
at Science Garden
•	 Photovoltaic (PV) Panel
•	 Rainwater Heat Island
Control System
(self-sustained w/ BIPV
panels and Rain Water
Recycling)
•	 Solar LED Bollards
•	 Solar Hot Water System
for pre-heating of hot water
for changing rooms
•	 Exposed System as Demonstration & Education Purpose
•	 Cost Effectiveness
•	 Maintainability
•	 Constructability
INTRODUCTION OVERALL DESIGN
APPROACH
TECHNICAL ISSUES RECOMMENDATION
& PROGRAMME
01 02 03 04
ESF / Island School / TCA / shl / RLB / AECOM / AURECON / URBIS / MVA / Fotton / isBIM
Island School Redevelopment / Hong Kong
Students’ Workshop
22 January 2015
04 RECOMMENDATION &
PROGRAMME
INTRODUCTION OVERALL DESIGN
APPROACH
TECHNICAL ISSUES RECOMMENDATION
& PROGRAMME
01 02 03 04
ESF / Island School / TCA / shl / RLB / AECOM / AURECON / URBIS / MVA / Fotton / isBIM
Island School Redevelopment / Hong Kong
Students’ Workshop
22 January 2015
SOCIAL
OPTION
LANDSCAPE
OPTION
CFA/
Efficiency (NOA/CFA)
THE PATH
(SPATIAL QUALITY)
TERRACES FLEXIBLE USE OF
SPACE
SUSTAINABILITY/
NATURAL LIGHT &
VENTILATION
SUSTAINABILITY/
ENERGY
CONSUMPTION
STRUCTURAL
EFFICIENCY
29,590 m2
/ 0.58
•	 Open
•	 Vibrant
•	 Well-articulated
•	 House Commons along
the Path
•	 Internal
•	 More enclosed
32,480 m2
/ 0.53
HigherLess
LowerMore
good
not as good as the other scheme
not good enough
COMPARISON SUMMARY & RECOMMENDATION/
PLAZA 2PLAZA 1
SCIENCE
RESEARCH LAB
INTEGRATED
HUMANITIES STUDIO
CREATIVE HUB
LANGUAGE
SHARED
LRC/ SLC
& SHARED
TEACHING
SPACES
LRC
(QUIET)
ADMISSION
OFFICE etc
+RECEPTION
SLT & ADMIN
HARBOUR
BORRETTROAD
CAFE
MINI LECTURE
THEATRE
BORRETTROAD
MINI LECTURE
THEATRE
ART
D&T
ATRIUM
SOCCER
PITCH
PLAYGROUND
THANK YOU

Contenu connexe

Similaire à 20150122 isr students workshop

20140122 design workshop compressed
20140122 design workshop compressed20140122 design workshop compressed
20140122 design workshop compressedGareth Stevens
 
Strategies and practices for integrating EnglishCentral activities, 2015.02.15
Strategies and practices for integrating EnglishCentral activities, 2015.02.15Strategies and practices for integrating EnglishCentral activities, 2015.02.15
Strategies and practices for integrating EnglishCentral activities, 2015.02.15Paul Beaufait
 
CEFPI Mayfield project- Curriculum Group-Multi-purpose spaces-Dr Neda Abbasi-...
CEFPI Mayfield project- Curriculum Group-Multi-purpose spaces-Dr Neda Abbasi-...CEFPI Mayfield project- Curriculum Group-Multi-purpose spaces-Dr Neda Abbasi-...
CEFPI Mayfield project- Curriculum Group-Multi-purpose spaces-Dr Neda Abbasi-...Neda Abbasi
 
Multidisciplinary Flipped Learning with ICT
Multidisciplinary Flipped Learning with ICTMultidisciplinary Flipped Learning with ICT
Multidisciplinary Flipped Learning with ICTAyla Savaşçı
 
Teaching English as a Second Language – Edu Kite
Teaching English as a Second Language – Edu KiteTeaching English as a Second Language – Edu Kite
Teaching English as a Second Language – Edu KiteEduKite
 
Teachers guide
Teachers guideTeachers guide
Teachers guideNana Gagua
 
Teaching english as foreign language (tefl) course gate
Teaching english as foreign language (tefl)   course gateTeaching english as foreign language (tefl)   course gate
Teaching english as foreign language (tefl) course gateCourse Gate
 
Side description1
Side description1Side description1
Side description1jfam21
 
TOETOE International : Stories from the open frontier of English language res...
TOETOE International: Stories from the open frontier of English language res...TOETOE International: Stories from the open frontier of English language res...
TOETOE International : Stories from the open frontier of English language res...Alannah Fitzgerald
 
Conference Input Mmu The Diploma Experience 0809
Conference Input Mmu The Diploma Experience 0809Conference Input Mmu The Diploma Experience 0809
Conference Input Mmu The Diploma Experience 0809Mike Blamires
 
AaaaaaaaaaaaRPMS_PORTFOLIO-TEMPLATE.pptx
AaaaaaaaaaaaRPMS_PORTFOLIO-TEMPLATE.pptxAaaaaaaaaaaaRPMS_PORTFOLIO-TEMPLATE.pptx
AaaaaaaaaaaaRPMS_PORTFOLIO-TEMPLATE.pptxJustinJayVargas
 
Guidelines For Implementing Tell Me More To Align With College English Curric...
Guidelines For Implementing Tell Me More To Align With College English Curric...Guidelines For Implementing Tell Me More To Align With College English Curric...
Guidelines For Implementing Tell Me More To Align With College English Curric...Armstrong WANG
 
EVOLUTION-STEAME-PRESENTATION-PPT-13.3.2021-V1.pdf
EVOLUTION-STEAME-PRESENTATION-PPT-13.3.2021-V1.pdfEVOLUTION-STEAME-PRESENTATION-PPT-13.3.2021-V1.pdf
EVOLUTION-STEAME-PRESENTATION-PPT-13.3.2021-V1.pdfMuhammadZiaUlHaq63
 

Similaire à 20150122 isr students workshop (20)

20140122 design workshop compressed
20140122 design workshop compressed20140122 design workshop compressed
20140122 design workshop compressed
 
Strategies and practices for integrating EnglishCentral activities, 2015.02.15
Strategies and practices for integrating EnglishCentral activities, 2015.02.15Strategies and practices for integrating EnglishCentral activities, 2015.02.15
Strategies and practices for integrating EnglishCentral activities, 2015.02.15
 
Web as a way of teaching english language
Web as a way of teaching english languageWeb as a way of teaching english language
Web as a way of teaching english language
 
CEFPI Mayfield project- Curriculum Group-Multi-purpose spaces-Dr Neda Abbasi-...
CEFPI Mayfield project- Curriculum Group-Multi-purpose spaces-Dr Neda Abbasi-...CEFPI Mayfield project- Curriculum Group-Multi-purpose spaces-Dr Neda Abbasi-...
CEFPI Mayfield project- Curriculum Group-Multi-purpose spaces-Dr Neda Abbasi-...
 
Ssat2012 handout
Ssat2012 handoutSsat2012 handout
Ssat2012 handout
 
Multidisciplinary Flipped Learning with ICT
Multidisciplinary Flipped Learning with ICTMultidisciplinary Flipped Learning with ICT
Multidisciplinary Flipped Learning with ICT
 
Teaching English as a Second Language – Edu Kite
Teaching English as a Second Language – Edu KiteTeaching English as a Second Language – Edu Kite
Teaching English as a Second Language – Edu Kite
 
Teachers guide
Teachers guideTeachers guide
Teachers guide
 
F1 leveraging startalk resources and impact - hart ingold
F1   leveraging startalk resources and impact - hart ingoldF1   leveraging startalk resources and impact - hart ingold
F1 leveraging startalk resources and impact - hart ingold
 
Teaching english as foreign language (tefl) course gate
Teaching english as foreign language (tefl)   course gateTeaching english as foreign language (tefl)   course gate
Teaching english as foreign language (tefl) course gate
 
Side description1
Side description1Side description1
Side description1
 
Component 2 intro english
Component 2 intro englishComponent 2 intro english
Component 2 intro english
 
TOETOE International : Stories from the open frontier of English language res...
TOETOE International: Stories from the open frontier of English language res...TOETOE International: Stories from the open frontier of English language res...
TOETOE International : Stories from the open frontier of English language res...
 
Conference Input Mmu The Diploma Experience 0809
Conference Input Mmu The Diploma Experience 0809Conference Input Mmu The Diploma Experience 0809
Conference Input Mmu The Diploma Experience 0809
 
Component 2 intro lao version
Component 2 intro lao versionComponent 2 intro lao version
Component 2 intro lao version
 
naac sample.pptx
naac sample.pptxnaac sample.pptx
naac sample.pptx
 
2010 Educational facilities manual
2010 Educational facilities manual2010 Educational facilities manual
2010 Educational facilities manual
 
AaaaaaaaaaaaRPMS_PORTFOLIO-TEMPLATE.pptx
AaaaaaaaaaaaRPMS_PORTFOLIO-TEMPLATE.pptxAaaaaaaaaaaaRPMS_PORTFOLIO-TEMPLATE.pptx
AaaaaaaaaaaaRPMS_PORTFOLIO-TEMPLATE.pptx
 
Guidelines For Implementing Tell Me More To Align With College English Curric...
Guidelines For Implementing Tell Me More To Align With College English Curric...Guidelines For Implementing Tell Me More To Align With College English Curric...
Guidelines For Implementing Tell Me More To Align With College English Curric...
 
EVOLUTION-STEAME-PRESENTATION-PPT-13.3.2021-V1.pdf
EVOLUTION-STEAME-PRESENTATION-PPT-13.3.2021-V1.pdfEVOLUTION-STEAME-PRESENTATION-PPT-13.3.2021-V1.pdf
EVOLUTION-STEAME-PRESENTATION-PPT-13.3.2021-V1.pdf
 

Plus de gwsis

Esf island school decant report 100614
Esf island school decant report 100614Esf island school decant report 100614
Esf island school decant report 100614gwsis
 
Intuition tok 2
Intuition tok 2Intuition tok 2
Intuition tok 2gwsis
 
Decant workshop 3.9.13
Decant workshop 3.9.13Decant workshop 3.9.13
Decant workshop 3.9.13gwsis
 
Cas week ppt
Cas week pptCas week ppt
Cas week pptgwsis
 
Pshe cas
Pshe casPshe cas
Pshe casgwsis
 
Pshe project ark eden powerpoint
Pshe project ark eden powerpointPshe project ark eden powerpoint
Pshe project ark eden powerpointgwsis
 
Pshe cas saving the pink dolphins
Pshe cas saving the pink dolphins Pshe cas saving the pink dolphins
Pshe cas saving the pink dolphins gwsis
 
Saving the dogs
Saving the dogsSaving the dogs
Saving the dogsgwsis
 
Pshe
PshePshe
Pshegwsis
 
Tekfishprezi
TekfishpreziTekfishprezi
Tekfishprezigwsis
 
Mothers choice
Mothers choiceMothers choice
Mothers choicegwsis
 
Cas exhibition
Cas exhibitionCas exhibition
Cas exhibitiongwsis
 
Tok prezis 2013
Tok prezis 2013Tok prezis 2013
Tok prezis 2013gwsis
 
Students 8 ways thinking q #1
Students 8 ways thinking q #1Students 8 ways thinking q #1
Students 8 ways thinking q #1gwsis
 
Students 8 ways thinking q #2
Students 8 ways thinking q #2Students 8 ways thinking q #2
Students 8 ways thinking q #2gwsis
 
Thinking questions final
Thinking questions finalThinking questions final
Thinking questions finalgwsis
 
Thinking questions
Thinking questionsThinking questions
Thinking questionsgwsis
 
Mock trial car accident (1) copy
Mock trial car accident (1) copyMock trial car accident (1) copy
Mock trial car accident (1) copygwsis
 
Tok ethics 10.4.13
Tok ethics 10.4.13Tok ethics 10.4.13
Tok ethics 10.4.13gwsis
 
Tok prezi wed 6th march 2013
Tok prezi wed 6th march 2013Tok prezi wed 6th march 2013
Tok prezi wed 6th march 2013gwsis
 

Plus de gwsis (20)

Esf island school decant report 100614
Esf island school decant report 100614Esf island school decant report 100614
Esf island school decant report 100614
 
Intuition tok 2
Intuition tok 2Intuition tok 2
Intuition tok 2
 
Decant workshop 3.9.13
Decant workshop 3.9.13Decant workshop 3.9.13
Decant workshop 3.9.13
 
Cas week ppt
Cas week pptCas week ppt
Cas week ppt
 
Pshe cas
Pshe casPshe cas
Pshe cas
 
Pshe project ark eden powerpoint
Pshe project ark eden powerpointPshe project ark eden powerpoint
Pshe project ark eden powerpoint
 
Pshe cas saving the pink dolphins
Pshe cas saving the pink dolphins Pshe cas saving the pink dolphins
Pshe cas saving the pink dolphins
 
Saving the dogs
Saving the dogsSaving the dogs
Saving the dogs
 
Pshe
PshePshe
Pshe
 
Tekfishprezi
TekfishpreziTekfishprezi
Tekfishprezi
 
Mothers choice
Mothers choiceMothers choice
Mothers choice
 
Cas exhibition
Cas exhibitionCas exhibition
Cas exhibition
 
Tok prezis 2013
Tok prezis 2013Tok prezis 2013
Tok prezis 2013
 
Students 8 ways thinking q #1
Students 8 ways thinking q #1Students 8 ways thinking q #1
Students 8 ways thinking q #1
 
Students 8 ways thinking q #2
Students 8 ways thinking q #2Students 8 ways thinking q #2
Students 8 ways thinking q #2
 
Thinking questions final
Thinking questions finalThinking questions final
Thinking questions final
 
Thinking questions
Thinking questionsThinking questions
Thinking questions
 
Mock trial car accident (1) copy
Mock trial car accident (1) copyMock trial car accident (1) copy
Mock trial car accident (1) copy
 
Tok ethics 10.4.13
Tok ethics 10.4.13Tok ethics 10.4.13
Tok ethics 10.4.13
 
Tok prezi wed 6th march 2013
Tok prezi wed 6th march 2013Tok prezi wed 6th march 2013
Tok prezi wed 6th march 2013
 

20150122 isr students workshop

  • 1. Island School Redevelopment at 20 Borrett Road, Mid-Levels, Hong Kong Students Workshop 22 January 2015 ESF / Island School / TCA / shl / RLB / AECOM / AURECON / URBIS / MVA / Fotton/ isBIM
  • 3. ESF / Island School / TCA / shl / RLB / AECOM / AURECON / URBIS / MVA / Fotton / isBIM Island School Redevelopment / Hong Kong Students’ Workshop 22 January 2015 INTRODUCTION OVERALL DESIGN APPROACH TECHNICAL ISSUES RECOMMENDATION & PROGRAMME 01 02 03 04 S R Q P N M L K H G F E D C B A J Island School BORRETT ROAD N
  • 4. ESF / Island School / TCA / shl / RLB / AECOM / AURECON / URBIS / MVA / Fotton / isBIM Island School Redevelopment / Hong Kong Students’ Workshop 22 January 2015 INTRODUCTION OVERALL DESIGN APPROACH TECHNICAL ISSUES RECOMMENDATION & PROGRAMME 01 02 03 04 VISION/ ESF & Island School’s vision for the new Island School provides a qualitative design framework: • To ensure that the educational, personal and social needs of the students, staff and community be met in a safe, secure, welcoming and inclusive environment; • To create an environment which is flexible and can embrace the use of new technologies and different learning styles; • To create a campus that is an exemplar of sustainable design, which can be used as a tool for teaching the principles of environmental conservation to students; • To ensure our new campus reflects all that works so well about our current one, that it supports ESF and Island School ethos and yet it benefits from all that is best about emerging ideas for school design from around the world. BLOCK 5 PLAYGROUNDCOMMUNAL SPACESHOUSES
  • 6. INTRODUCTION OVERALL DESIGN APPROACH TECHNICAL ISSUES RECOMMENDATION & PROGRAMME 01 02 03 04 ESF / Island School / TCA / shl / RLB / AECOM / AURECON / URBIS / MVA / Fotton / isBIM Island School Redevelopment / Hong Kong Students’ Workshop 22 January 2015 classroom classroom classroom classroom classroom classroom classroom classroom classroom classroom classroom classroom classroom classroom sroom sroom classroom classroom lassroomclassroomclassroomclassroom corridor classroom classroom classroom classroom classroom classroom classroomclassroom classroomclassroom classroom classroom classroomclassroom classroom classroom classroom classroom classroom classroomclassroom classroom classroom classroom classroom corridor classroom classroom classroom classroom classroom classroom classroom classroom classroom classroom classroom classroom classroom classroom classroom classroom classroom classroom classroom classroom classroomclassroom classroom classroom classroom classroom classroom classroom classroomclassroomclassroomclassroomclassroom corridor classroom classroom classroom classroom classroomclassroom classroom classroom classroom classroom classroomclassroom classroom classroom classroom classroom classroom classroom classroom classroom classroomclassroom classroom classroom classroom classroom classroom classroom classroom classroom classroom classroom classroom corridor classroom classroom classroom classroom classroom classroom classroom classroom classroom classroom classroom classroom classroom classroom classroom classroom classroom classroom classroom classroom classroomclassroom classroom classroom classroom classroom classroom classroom classroom classroom classroom classroom classroom corridor classroom classroom classroom classroom classroom classroom classroom classroom classroom classroom classroom classroom classroom classroom classroom classroom classroom classroom classroom classroom classroomclassroom classroom classroom classroom classroom classroom classroom lassroomclassroomclassroomclassroom corridor classroom classroom classroom classroom classroom classroom classroomclassroom classroomclassroom classroom classroom classroom classroom classroom classroom classroom classroom classroom classroom classroom classroom classroom classroom classroom corridor classroom classroom classroom classroom classroom classroom classroom classroom classroom classroom classroom classroom classroom classroom classroom classroom classroom classroom classroom classroom classroomclassroom classroom classroom classroom classroom classroom classroom classroom classroom classroom classroom classroom corridor classroom classroom classroom classroom classroom classroom classroom classroom classroom classroom classroom classroom classroom classroom classroom classroom classroom classroom classroom classroom classroomclassroom classroom classroom classroom classroom classroom classroom classroom classroom classroom classroom classroom corridor classroom classroom classroom classroom classroom classroom classroom classroom classroom classroom classroom classroom classroom classroom classroom classroom classroom classroom classroom classroom classroomclassroom classroom classroom classroom classroom classroom classroom Social/ • Hybrid of village & campus approach to create an extended social spaces between buildings • This social approach focus on the spatial organisation to encourage social activities Landscape/ • The building form adapt to the site topography, another landscape is re- created • Greening area is maximised and more flexible spaces are created Village/ • Conventional • Cluster with small footprints • Series of open spaces formed • Resemble existing IS arrangement Loop/ • Hybrid of linear and folded approach to form a loop to maximise the use of site area • Large internal social space is formed, Kellett School is an example of this type Campus/ • Larger footprint with internal social spaces • Encourage more social activities • More flexible learning spaces could be enabled with larger footprints classroom classroom classroom classroom classroom corridor classroom classroom classroom classroom classroom classroom classroom classroom classroom classroom classroom classroom classroom classroom classroom classroom classroom classroom classroom classroom classroomclassroom classroom classroom classroom classroom classroom classroom classroom classroom classroom classroom classroom corridor classroom classroom classroom classroom classroom classroom classroom classroom classroom classroom classroom classroom classroom classroom classroom classroom classroom classroom classroom classroom classroomclassroom classroom classroom classroom classroom classroom classroom + + FILLING MASSING OPTIONS OVERVIEW/
  • 7. INTRODUCTION OVERALL DESIGN APPROACH TECHNICAL ISSUES RECOMMENDATION & PROGRAMME 01 02 03 04 ESF / Island School / TCA / shl / RLB / AECOM / AURECON / URBIS / MVA / Fotton / isBIM Island School Redevelopment / Hong Kong Students’ Workshop 22 January 2015 Thomas Chow Architects + schmidt hammer lassen architects 42/Island School Redevelopment / Hong Kong Co-Creation (Stage C) Design Review - Massing Design Options 14/10/2014 Massing Typology Options Overview/ Social Option/ Option C/ LandscapeOption A/ Village Option D/ LoopOption B/ Campus Island Spirit (Communal Space)/ Island Spirit (Sightline)/ Flexibility/ Natural Light/ Ventilation/ Greening/ Island Spirit (Communal Space)/ Island Spirit (Sightline)/ Flexibility/ Natural Light/ Ventilation/ Greening/ Island Spirit (Communal Space)/ Island Spirit (Sightline)/ Flexibility/ Natural Light/ Ventilation/ Greening/ Island Spirit (Communal Space)/ Island Spirit (Sightline)/ Flexibility/ Natural Light/ Ventilation/ Greening/ Island Spirit (Communal Space)/ Island Spirit (Sightline)/ Flexibility/ Natural Light/ Ventilation/ Greening/ MASSING OPTIONS OVERVIEW/
  • 8. INTRODUCTION OVERALL DESIGN APPROACH TECHNICAL ISSUES RECOMMENDATION & PROGRAMME 01 02 03 04 ESF / Island School / TCA / shl / RLB / AECOM / AURECON / URBIS / MVA / Fotton / isBIM Island School Redevelopment / Hong Kong Students’ Workshop 22 January 2015 Social Option Landscape Option
  • 9. INTRODUCTION OVERALL DESIGN APPROACH TECHNICAL ISSUES RECOMMENDATION & PROGRAMME 01 02 03 04 ESF / Island School / TCA / shl / RLB / AECOM / AURECON / URBIS / MVA / Fotton / isBIM Island School Redevelopment / Hong Kong Students’ Workshop 22 January 2015 Science Technology Creative Arts Sharing/ Flexible Teaching +167.4 4/F Science Technology Creative Arts Sharing/ Flexible Teaching Adminstration +163.8 3/F English Humanities IN/ EAL Administration +160.2 2/F Language IN/ EAL Sharing/ Flexible Teaching Administration +156.6 1/F Mathematics Physical Education Sharing/ Flexible Teaching Administration Amenities +152.1 G/F Creative Arts Physical Education Administration Amenities +148.1 LG1M Creative Arts Physical Education Sharing/ Flexible Teaching Amenities +143.4 LG1 Car Park +136.0 LG2 Social Option/ NOFA 14,751m2 17,251m2 (incl. covered carpark & drop-off) CFA 29,590m2 Efficiency (NOFA/CFA) 0.58
  • 10. INTRODUCTION OVERALL DESIGN APPROACH TECHNICAL ISSUES RECOMMENDATION & PROGRAMME 01 02 03 04 ESF / Island School / TCA / shl / RLB / AECOM / AURECON / URBIS / MVA / Fotton / isBIM Island School Redevelopment / Hong Kong Students’ Workshop 22 January 2015 English Language IN/ EAL Administration Humanities Mathematics Technology Administration Administration Technology Creative Arts Science Technology Creative Arts Science Creative Arts Physical Education Creative Arts Physical Education Sharing/ Flexible Teaching Administration Amenities Physical Education +152.0 G/F +148.2 LG1M +143.0 LG1 +136.0 LG2 +158.4 2/F +162.3 3/F +166.2 4/F +154.5 1/F Landscape Option/ NOFA 14,751m2 17,251m2 (incl. covered carpark & drop-off) CFA 32,480m2 Efficiency (NOFA/CFA) 0.53
  • 11. INTRODUCTION OVERALL DESIGN APPROACH TECHNICAL ISSUES RECOMMENDATION & PROGRAMME 01 02 03 04 ESF / Island School / TCA / shl / RLB / AECOM / AURECON / URBIS / MVA / Fotton / isBIM Island School Redevelopment / Hong Kong Students’ Workshop 22 January 2015 02a The PATH
  • 12. INTRODUCTION OVERALL DESIGN APPROACH TECHNICAL ISSUES RECOMMENDATION & PROGRAMME 01 02 03 04 ESF / Island School / TCA / shl / RLB / AECOM / AURECON / URBIS / MVA / Fotton / isBIM Island School Redevelopment / Hong Kong Students’ Workshop 22 January 2015 The Heart of the Island School - The Path/ to link the mountain/nature with the harbour/city with a lot of different activities extended from it • THE PATH
  • 13. INTRODUCTION OVERALL DESIGN APPROACH TECHNICAL ISSUES RECOMMENDATION & PROGRAMME 01 02 03 04 ESF / Island School / TCA / shl / RLB / AECOM / AURECON / URBIS / MVA / Fotton / isBIM Island School Redevelopment / Hong Kong Students’ Workshop 22 January 2015 PLAZA 2PLAZA 1 SCIENCE RESEARCH LAB INTEGRATED HUMANITIES STUDIO CREATIVE HUB LANGUAGE SHARED LRC/ SLC & SHARED TEACHING SPACES LRC (QUIET) ADMISSION OFFICE etc +RECEPTION SLT & ADMIN HARBOUR BORRETTROAD CAFE MINI LECTURE THEATRE BORRETTROAD MINI LECTURE THEATRE ART D&T ATRIUM SOCCER PITCH • Open • Vibrant • Well-articulated & More Vibrant • House Commons along the Path • Internal • More Enclosed • Spaces Connected by More Enclosed Corridors • Follow the stepping of the Building Mass PLAYGROUND • THE PATH Social Option Landscape Option
  • 14. INTRODUCTION OVERALL DESIGN APPROACH TECHNICAL ISSUES RECOMMENDATION & PROGRAMME 01 02 03 04 ESF / Island School / TCA / shl / RLB / AECOM / AURECON / URBIS / MVA / Fotton / isBIM Island School Redevelopment / Hong Kong Students’ Workshop 22 January 2015 • THE PATH/ Houses
  • 15. INTRODUCTION OVERALL DESIGN APPROACH TECHNICAL ISSUES RECOMMENDATION & PROGRAMME 01 02 03 04 ESF / Island School / TCA / shl / RLB / AECOM / AURECON / URBIS / MVA / Fotton / isBIM Island School Redevelopment / Hong Kong Students’ Workshop 22 January 2015 LG/ 2* GF/ 1 L1/ 3 L2/ 2* Proposed HOUSE COMMONS Proposed HOUSE COMMONS on the other side of the PATH L2/ 2* L1/ 3 GF/ 1 LG/ 2* • THE PATH/ Houses Social Option
  • 16. INTRODUCTION OVERALL DESIGN APPROACH TECHNICAL ISSUES RECOMMENDATION & PROGRAMME 01 02 03 04 ESF / Island School / TCA / shl / RLB / AECOM / AURECON / URBIS / MVA / Fotton / isBIM Island School Redevelopment / Hong Kong Students’ Workshop 22 January 2015 GF/ 2 L1/ 2 L2/ 2 L2/ 2 The Path L1/ 2 GF/ 2 • THE PATH/ Houses Landscape Option
  • 17. INTRODUCTION OVERALL DESIGN APPROACH TECHNICAL ISSUES RECOMMENDATION & PROGRAMME 01 02 03 04 ESF / Island School / TCA / shl / RLB / AECOM / AURECON / URBIS / MVA / Fotton / isBIM Island School Redevelopment / Hong Kong Students’ Workshop 22 January 2015 02b Terraces
  • 18. INTRODUCTION OVERALL DESIGN APPROACH TECHNICAL ISSUES RECOMMENDATION & PROGRAMME 01 02 03 04 ESF / Island School / TCA / shl / RLB / AECOM / AURECON / URBIS / MVA / Fotton / isBIM Island School Redevelopment / Hong Kong Students’ Workshop 22 January 2015 • Visual Connection from Above to the Open Playground • Enable Students’ Participation from Above as Existing School • Visual Connection with the Hill behind • Terraces with Varieties in Size • No Visual Connection with the Ballcourts • Stepping Effect Easily Visualised from the Outside - Image of the Island School • TERRACES Social Option Landscape Option
  • 19. INTRODUCTION OVERALL DESIGN APPROACH TECHNICAL ISSUES RECOMMENDATION & PROGRAMME 01 02 03 04 ESF / Island School / TCA / shl / RLB / AECOM / AURECON / URBIS / MVA / Fotton / isBIM Island School Redevelopment / Hong Kong Students’ Workshop 22 January 2015 • TERRACES • Visual Connection from Above to the Open Playground • Enable Students’ Participation from Above as Existing School • Visual Connection with the Hill behind
  • 20. INTRODUCTION OVERALL DESIGN APPROACH TECHNICAL ISSUES RECOMMENDATION & PROGRAMME 01 02 03 04 ESF / Island School / TCA / shl / RLB / AECOM / AURECON / URBIS / MVA / Fotton / isBIM Island School Redevelopment / Hong Kong Students’ Workshop 22 January 2015 02c Open Playgrounds
  • 21. INTRODUCTION OVERALL DESIGN APPROACH TECHNICAL ISSUES RECOMMENDATION & PROGRAMME 01 02 03 04 ESF / Island School / TCA / shl / RLB / AECOM / AURECON / URBIS / MVA / Fotton / isBIM Island School Redevelopment / Hong Kong Students’ Workshop 22 January 2015 1 2 450 m2 / GF About 80% of existing block 5 playground 255 m2 / L1 1650 m2 / GF More than twice of block 5 playground 660 m2 / GF About the size of existing block 5 playground 850 m2 / L3 500 m2 / GF Open Deck • 2 no. of outdoor spaces with total area of more than 3 times of existing block 5 playground • Open playground at GF to fulfil lease conditions requirement • OPEN PLAYGROUNDS Social Option Landscape Option • More Open Playgrounds • Less Open Playgrounds
  • 22. INTRODUCTION OVERALL DESIGN APPROACH TECHNICAL ISSUES RECOMMENDATION & PROGRAMME 01 02 03 04 ESF / Island School / TCA / shl / RLB / AECOM / AURECON / URBIS / MVA / Fotton / isBIM Island School Redevelopment / Hong Kong Students’ Workshop 22 January 2015 02d Flexible Teaching Spaces
  • 23. INTRODUCTION OVERALL DESIGN APPROACH TECHNICAL ISSUES RECOMMENDATION & PROGRAMME 01 02 03 04 ESF / Island School / TCA / shl / RLB / AECOM / AURECON / URBIS / MVA / Fotton / isBIM Island School Redevelopment / Hong Kong Students’ Workshop 22 January 2015 • house area/ • learning area/ • informal learning/ • social interaction/ informal learning/ self-study/ group work/ Architectural furniture (lockers) can be installed in the house areas in zone C for space definition and to integrate social space with learning space • FLEXIBLE TEACHING SPACES
  • 24. INTRODUCTION OVERALL DESIGN APPROACH TECHNICAL ISSUES RECOMMENDATION & PROGRAMME 01 02 03 04 ESF / Island School / TCA / shl / RLB / AECOM / AURECON / URBIS / MVA / Fotton / isBIM Island School Redevelopment / Hong Kong Students’ Workshop 22 January 2015 • engagement activities and briefings • involve more teacher led activities and whole class work • support lecture style learning • considerable degree of flexibility through judicious choice of furniture Engagement Space (Zone A)/ • researching, analysing, questioning, creating and collaborating activities • support both individual and group work • high level of porosity • division by architecural furniture and non-load bearing “walls” Processing Space (Zone B)/ • combined learning/ house areas • support more informal learning and social interaction • larger level of movement and link with main circulation routes directly • combine with terraces look over and across large communal spaces Community Space (Zone C)/ B CA OPAQUE FIXED IMPERMEABLE FORMAL TRANSPARENT FLEXIBLE PERMEABLE SOCIAL Transition of Learning Spaces/ • Opacity • Flexibility • Permeability • Formality • FLEXIBLE TEACHING SPACES
  • 25. INTRODUCTION OVERALL DESIGN APPROACH TECHNICAL ISSUES RECOMMENDATION & PROGRAMME 01 02 03 04 ESF / Island School / TCA / shl / RLB / AECOM / AURECON / URBIS / MVA / Fotton / isBIM Island School Redevelopment / Hong Kong Students’ Workshop 22 January 2015 A A A AA A A A C C C C C B B B B B A A A A A A A A A A C C C B B B B B A A A A A A A C C A A A A A Typology for Flexible Arrangement/ • SOA (teaching) = A+B • which could be converted to 10 no. of enclosed teaching spaces if required • more space provided • more flexible layout to adapt to different uses AREA A < AREA A+B EFFICIENCY OR Typology for Traditional Arrangement/ • SOA (teaching) = A • 10 enclosed teaching spaces • less space provided • more difficult to use break-out spaces • FLEXIBLE TEACHING SPACES
  • 26. INTRODUCTION OVERALL DESIGN APPROACH TECHNICAL ISSUES RECOMMENDATION & PROGRAMME 01 02 03 04 ESF / Island School / TCA / shl / RLB / AECOM / AURECON / URBIS / MVA / Fotton / isBIM Island School Redevelopment / Hong Kong Students’ Workshop 22 January 2015 Transition of Learning Spaces/ Transition radially from the Heart of the School towards the skin, from sharing spaces to more specific spaces SPECIFIC SHARED OPAQUE FIXED IMPERMEABLE FORMAL TRANSPARENT FLEXIBLE PERMEABLE SOCIAL SPECIFIC OPAQUE FIXED IMPERMEABLE FORMAL SPECIFIC SHARED OPAQUE FIXED IMPERMEABLE FORMAL TRANSPARENT FLEXIBLE PERMEABLE SOCIAL SP OPA FIXE IMP FOR • CAMPUS ORGANISATION
  • 27. INTRODUCTION OVERALL DESIGN APPROACH TECHNICAL ISSUES RECOMMENDATION & PROGRAMME 01 02 03 04 ESF / Island School / TCA / shl / RLB / AECOM / AURECON / URBIS / MVA / Fotton / isBIM Island School Redevelopment / Hong Kong Students’ Workshop 22 January 2015 • FLEXIBLE TEACHING SPACES (SPACE PLANNING, NATURAL LIGHTING & VENTILATION and ENERGY CONSUMPTION) Social Option • Balanced Flexible Teaching Spaces • Adequate Natural Light and Ventilation Provision • Less Energy Consumption
  • 28. INTRODUCTION OVERALL DESIGN APPROACH TECHNICAL ISSUES RECOMMENDATION & PROGRAMME 01 02 03 04 ESF / Island School / TCA / shl / RLB / AECOM / AURECON / URBIS / MVA / Fotton / isBIM Island School Redevelopment / Hong Kong Students’ Workshop 22 January 2015 Landscape Option • More Flexible Teaching Spaces • Deeper Floor Plate leading to Inadequate Natural Light and Ventilation • Light wells Introduced which limits the Flexibility of the spaces • More Energy Consumption • FLEXIBLE TEACHING SPACES (SPACE PLANNING, NATURAL LIGHTING & VENTILATION and ENERGY CONSUMPTION)
  • 29. INTRODUCTION OVERALL DESIGN APPROACH TECHNICAL ISSUES RECOMMENDATION & PROGRAMME 01 02 03 04 ESF / Island School / TCA / shl / RLB / AECOM / AURECON / URBIS / MVA / Fotton / isBIM Island School Redevelopment / Hong Kong Students’ Workshop 22 January 2015 • FLEXIBLE TEACHING SPACES (SPACE PLANNING, NATURAL LIGHTING & VENTILATION and ENERGY CONSUMPTION) Social Option Landscape Option
  • 30. INTRODUCTION OVERALL DESIGN APPROACH TECHNICAL ISSUES RECOMMENDATION & PROGRAMME 01 02 03 04 ESF / Island School / TCA / shl / RLB / AECOM / AURECON / URBIS / MVA / Fotton / isBIM Island School Redevelopment / Hong Kong Students’ Workshop 22 January 2015 Landscape Option • FLEXIBLE TEACHING SPACES/ LRC
  • 31. INTRODUCTION OVERALL DESIGN APPROACH TECHNICAL ISSUES RECOMMENDATION & PROGRAMME 01 02 03 04 ESF / Island School / TCA / shl / RLB / AECOM / AURECON / URBIS / MVA / Fotton / isBIM Island School Redevelopment / Hong Kong Students’ Workshop 22 January 2015 Social Option • FLEXIBLE TEACHING SPACES/ LRC
  • 32. INTRODUCTION OVERALL DESIGN APPROACH TECHNICAL ISSUES RECOMMENDATION & PROGRAMME 01 02 03 04 ESF / Island School / TCA / shl / RLB / AECOM / AURECON / URBIS / MVA / Fotton / isBIM Island School Redevelopment / Hong Kong Students’ Workshop 22 January 2015 02f Sports Complex
  • 33. INTRODUCTION OVERALL DESIGN APPROACH TECHNICAL ISSUES RECOMMENDATION & PROGRAMME 01 02 03 04 ESF / Island School / TCA / shl / RLB / AECOM / AURECON / URBIS / MVA / Fotton / isBIM Island School Redevelopment / Hong Kong Students’ Workshop 22 January 2015 GF Transfer & Open Playground LG Large Volumes SPORTS HALLBLACK BOX SWIMMING POOL PLAY- GROUND GF Transfer & Open Playground LG Large Volumes BLACK BOX SPORTS HALL SWIMMING POOL PLAY- GROUND Swimming Pool/Swimming Pool/ • SPORTS COMPLEX Social Option Landscape Option
  • 34. INTRODUCTION OVERALL DESIGN APPROACH TECHNICAL ISSUES RECOMMENDATION & PROGRAMME 01 02 03 04 ESF / Island School / TCA / shl / RLB / AECOM / AURECON / URBIS / MVA / Fotton / isBIM Island School Redevelopment / Hong Kong Students’ Workshop 22 January 2015 02h Summary
  • 35. INTRODUCTION OVERALL DESIGN APPROACH TECHNICAL ISSUES RECOMMENDATION & PROGRAMME 01 02 03 04 ESF / Island School / TCA / shl / RLB / AECOM / AURECON / URBIS / MVA / Fotton / isBIM Island School Redevelopment / Hong Kong Students’ Workshop 22 January 2015 Social Option Landscape Option DESIGN & PLANNING SUMMARY/
  • 36. 03 Technical Issues a) Site Formation, Foundation b) Superstructure c) Building Services d) Greening Design e) Sustainability f) Cost Issues
  • 37. INTRODUCTION OVERALL DESIGN APPROACH TECHNICAL ISSUES RECOMMENDATION & PROGRAMME 01 02 03 04 ESF / Island School / TCA / shl / RLB / AECOM / AURECON / URBIS / MVA / Fotton / isBIM Island School Redevelopment / Hong Kong Students’ Workshop 22 January 2015 Site Formation & Foundation Design Strategy/ • Re-use Existing Retaining Structures • Avoid Extensive Excavation by Localising the Extent of Areas Lower than Existing Levels • Back-fill BLOCK 7 BLOCK 2 HALL Swim m ing Pool Block5 Playground BLOCK 1 BLOCK 5 BLOCK 4 BLOCK 3 B O R R E T T R O A D Keep Keep & Abandoned Demolished
  • 38. INTRODUCTION OVERALL DESIGN APPROACH TECHNICAL ISSUES RECOMMENDATION & PROGRAMME 01 02 03 04 ESF / Island School / TCA / shl / RLB / AECOM / AURECON / URBIS / MVA / Fotton / isBIM Island School Redevelopment / Hong Kong Students’ Workshop 22 January 2015 Hybrid of Foundation Systems/ • Footing, where Rock Head Level is High • Piling, where Rock Head Level is Low
  • 39. INTRODUCTION OVERALL DESIGN APPROACH TECHNICAL ISSUES RECOMMENDATION & PROGRAMME 01 02 03 04 ESF / Island School / TCA / shl / RLB / AECOM / AURECON / URBIS / MVA / Fotton / isBIM Island School Redevelopment / Hong Kong Students’ Workshop 22 January 2015 SPORTS HALL BORRETTROAD Deep Transfer Structure (3m) Cantilever Structure towards the Hill Swimming Pool • Sports Hall - no Transfer Above • Black Box - no Transfer Above • Swimming Pool - Partial Transfer Above • Reinforced Concrete Ratio: 0.49m3 /m2 floor area • Steel Reinforcement: 148kg/m2 floor area • Sports Hall - Transfer of 5 floors Above • Black Box - Transfer of 5 floors Above • Swimming Pool - Transfer of 5 floors Above • Reinforced Concrete Ratio: 0.61m3 /m2 floor area • Steel Reinforcement: 183kg/m2 floor area Transfer Structure -> Larger Structural Member Size and More Reinforcement -> Less Headroom and More Costly Superstructure/
  • 40. INTRODUCTION OVERALL DESIGN APPROACH TECHNICAL ISSUES RECOMMENDATION & PROGRAMME 01 02 03 04 ESF / Island School / TCA / shl / RLB / AECOM / AURECON / URBIS / MVA / Fotton / isBIM Island School Redevelopment / Hong Kong Students’ Workshop 22 January 2015 Building Services/ Electrical Services Electrical Supply System Metering Earthing and Lightning System Lighting System Elevator System Emergency Lighting System Security System Broadcast Reception Installation Telephone Installation BMS Mechanical Services MVAC System Fire Services System Water Supply System Drainage System Gas Supply System Swimming Pool Water Filtration System Other Specialist Systems Wireless Broadband System Public Address System IT Network and Backbone Infrastructure Library Security System Library Lending and Borrowing System Smart Card System Audio/ Visual System (AV) AV and Stage Lighting System Master School Bell System
  • 41. INTRODUCTION OVERALL DESIGN APPROACH TECHNICAL ISSUES RECOMMENDATION & PROGRAMME 01 02 03 04 ESF / Island School / TCA / shl / RLB / AECOM / AURECON / URBIS / MVA / Fotton / isBIM Island School Redevelopment / Hong Kong Students’ Workshop 22 January 2015 Greening Design/ Vertical greening next to Half Court Figure 8 Terraced landscape at hillside Figure 4 Entrance of the PATH Figure 6 • The PATH • PATH Entrance • Hillside Terraces • Green Wall screen off Ball Courts
  • 42. INTRODUCTION OVERALL DESIGN APPROACH TECHNICAL ISSUES RECOMMENDATION & PROGRAMME 01 02 03 04 ESF / Island School / TCA / shl / RLB / AECOM / AURECON / URBIS / MVA / Fotton / isBIM Island School Redevelopment / Hong Kong Students’ Workshop 22 January 2015 Sustainable Design/ • Food Waste Decomposition • Dead Plants Decomposition • Grey Water Recycling System • Rainwater Recycling for Irrigation • Energy Generating Floor • Weather-based Irrigation Control System • Wind Turbine at Science Garden • Photovoltaic (PV) Panel • Rainwater Heat Island Control System (self-sustained w/ BIPV panels and Rain Water Recycling) • Solar LED Bollards • Solar Hot Water System for pre-heating of hot water for changing rooms • Exposed System as Demonstration & Education Purpose • Cost Effectiveness • Maintainability • Constructability
  • 43. INTRODUCTION OVERALL DESIGN APPROACH TECHNICAL ISSUES RECOMMENDATION & PROGRAMME 01 02 03 04 ESF / Island School / TCA / shl / RLB / AECOM / AURECON / URBIS / MVA / Fotton / isBIM Island School Redevelopment / Hong Kong Students’ Workshop 22 January 2015 04 RECOMMENDATION & PROGRAMME
  • 44. INTRODUCTION OVERALL DESIGN APPROACH TECHNICAL ISSUES RECOMMENDATION & PROGRAMME 01 02 03 04 ESF / Island School / TCA / shl / RLB / AECOM / AURECON / URBIS / MVA / Fotton / isBIM Island School Redevelopment / Hong Kong Students’ Workshop 22 January 2015 SOCIAL OPTION LANDSCAPE OPTION CFA/ Efficiency (NOA/CFA) THE PATH (SPATIAL QUALITY) TERRACES FLEXIBLE USE OF SPACE SUSTAINABILITY/ NATURAL LIGHT & VENTILATION SUSTAINABILITY/ ENERGY CONSUMPTION STRUCTURAL EFFICIENCY 29,590 m2 / 0.58 • Open • Vibrant • Well-articulated • House Commons along the Path • Internal • More enclosed 32,480 m2 / 0.53 HigherLess LowerMore good not as good as the other scheme not good enough COMPARISON SUMMARY & RECOMMENDATION/ PLAZA 2PLAZA 1 SCIENCE RESEARCH LAB INTEGRATED HUMANITIES STUDIO CREATIVE HUB LANGUAGE SHARED LRC/ SLC & SHARED TEACHING SPACES LRC (QUIET) ADMISSION OFFICE etc +RECEPTION SLT & ADMIN HARBOUR BORRETTROAD CAFE MINI LECTURE THEATRE BORRETTROAD MINI LECTURE THEATRE ART D&T ATRIUM SOCCER PITCH PLAYGROUND