SlideShare a Scribd company logo
1 of 7
Download to read offline
International Journal of Management (IJM), ISSN 0976 – 6502(Print), ISSN 0976 - 6510(Online), 
Volume 5, Issue 7, July (2014), pp. 44-50 © IAEME 
INTERNATIONAL JOURNAL OF MANAGEMENT (IJM) 
ISSN 0976-6502 (Print) 
ISSN 0976-6510 (Online) 
Volume 5, Issue 7, July (2014), pp. 44-50 
© IAEME: http://www.iaeme.com/IJM.asp 
Journal Impact Factor (2014): 7.2230 (Calculated by GISI) 
www.jifactor.com 
44 
 
IJM 
© I A E M E 
A PERSPECTIVE OF RISK ASSESSMENT FOR PRODUCT 
DEVELOPMENTS IN BIOTECHNOLOGY AND PHARMACEUTICAL 
PRODUCTS 
Samaraj S. Thiyagarajan, PMP 
Austin, Texas, USA- 78749 
ABSTRACT 
This paper provides an insight on risk assessment, which is a component of risk management. 
Risk assessment is an essential process during the product developments phase of biotechnological 
and pharmaceutical products. Risk management is an iterative process. It starts from project scoping 
and completesupon projectfinish. Basically, risk are categorized as known risks and unknown risks. 
Risk assessment is the first stage of the risk management followed by risk evaluation, and developing 
a risk management strategy to monitor and mitigate risks. Ideally in any project scenario, risks will 
be high during the project initiation phase and reduce as project enters into later stages. This paper 
discusses the process of risk assessment for each phase of the developmental stage of new products. 
In summary, for successful execution of projects, product development needs adequate risk 
assessment strategy. 
Keywords: New Product Development, Risk Assessment, Biotechnology, Pharmaceutical. 
INTRODUCTION 
New product introductions are the life line of any business. A successful business model will 
spread its roots only when new products are commercialized and sustained without any failures. The 
long term competitiveness of a business relies on the company’s new product development 
capabilities (SC Wheelwright, KB Clark, 1992). Any new product commercialization process 
involves numerous risks. It is imperative to understand the project risks and its management, past 
research indicates there is only six out ten products were successful after commercialization (Garry, 
1997). Each new product introduction has its own unique sets of risks. New product launches are 
resource intensive and has prolonged timelines, especially, in the pharmaceutical and biotech 
industry. This consequently translates into high development costs, which involves facility, 
instruments, machinery, and miscellaneous (Kahn, 2002).
International Journal of Management (IJM), ISSN 0976 – 6502(Print), ISSN 0976 - 6510(Online), 
Volume 5, Issue 7, July (2014), pp. 44-50 © IAEME 
45 
 
Developing a risk management involves planning, and developing quality standards, and 
quality mission of the organization. Systems and practices that guides the project team to make a 
clear and consistent decisions and communications for the management (FDA, 2004). An important 
aspect in any product life cycle is product design. Developing a design based on QbD approach will 
significantly reduce the risk. Risk management entails a comprehensive understanding of product 
design to manufacturing, reaching the customer and use by the customer. Many factors that can 
influence the safety, and efficacy of a product. An efficient project team will need to characterize the 
aspects of the product in every angle. It is critical to have a risk management plan that is tailored to 
the particular project. 
In a product development and transfer, with so many tasks and deliverables need to occur 
coherently, the project team need to have significant emphasis on identifying, assessing, and 
evaluating the risks at every stage. A solid risk management plan will help the team to anticipate 
issues, and proactively address them. It helps the team to have a smooth execution to reach the 
designated goal of efficient and successful product development. The objective of this paper is to 
provide a detail risk management process for commercializing new biotechnology and 
pharmaceutical products. Based on the risk assessment, the project team will then need to draft a 
detail mitigation strategy, which itself is a separate process. The team needs to establish several high 
level categories for risk identification. Each identified risk will then need to be categorized as project 
risk, or a particular event associated in a given phase of the project. 
PROJECT SCOPE 
A crucial phase of any project is the project scoping. Successful scoping includes 
understanding the risks. Critical risks include but not limited to the following aspects: Project team at 
certain times may not clearly define the goals of the proposed project, which may be from inadequate 
scope development that results in conflicting agendas (Atkinson et.al, 2006). Failure to translate the 
customer/user requirements and product requirements to the scope of the project often lead to 
product failures. Often project teams falls short of drafting a complete and fully vetted business plan, 
also called as aggregated project plan (SC Wheelwright, KB Clark, 1992). In several instances, 
oversight of management in terms project scope and project execution lead to issues in the project. 
Failure of the team to clearly identify in scope/out of scope of the project to achieve its indented 
purpose.A project team can group these risks as project risks. 
STAKEHOLDER 
Stakeholder identification and understanding their needs is required for successful project 
execution and completion. The concept of stakeholder management is intended to devise methods to 
manage a group of decision makers or parties that may positively or negatively impact the project or 
impacted by the project. Their relationships are crucial to success of product launch (R. Edward 
Freeman and John McVea). Significant issues arise when stakeholders and their needs were not 
correctly identified. Team need to identify risks associated with the following aspects. If the project 
team failed to identify all the stakeholders during the project scoping, it will result in project facing 
significant delays or scope creep. 
Once stakeholders are identified project team needs to identify the stakeholder’s interest and 
their influence on the new product development project. Failure to identify interest and influence can 
be as damaging as other risks. Risks could also be failure to identify the hidden needs of both 
internal and external stakeholders. This had resulted in offsetting the project timeline due unplanned 
works that needs to be performed. Disconnect between the stakeholders and project team poses 
significant risk. Regulatory agencies like FDA, USDA and other international organizations will
International Journal of Management (IJM), ISSN 0976 – 6502(Print), ISSN 0976 - 6510(Online), 
Volume 5, Issue 7, July (2014), pp. 44-50 © IAEME 
have a significant influence, failure to understand their requirementswill be costly and challenging 
for the projects. Stakeholder concepts were evolved and their influence had recently been embedded 
in the management thinking (Ronald K, 1997). 
46 
 
The team needs to identify and assess these risks as project risk, and they are characterized in 
the decision to commercialize phase. It is essential to look for any gaps in the risk assessment section 
and reassess the risks to make surethe team is covering this critical risk. 
PRODUCT REQUIREMENTS 
In order to achieve successful commercialization, the team needs to undergo an extensive risk 
assessment and management regardingproduct requirements. The requirements for considering the 
needs of product specification based on the information that has been understood from the customers 
and key stakeholders (Alison McKay, et, al, 2001) Sometime combing the risk assessment for voice 
of the customer and the product requirements together is crucial. In many instance products had 
failed at the hands of the customers. The fundamental reason for this is incomplete understanding the 
of product requirements based on the customer requirements. Risk of incomplete coordination of 
customer requirements to product requirements will be one of the failure mode. Also, trying to 
address many facets of customer requirement, some of the NPI had issues in executing transfer to 
manufacturing for this type of products. Failure to address safety and handling requirements. 
Another crucial document that is invariably used is Product requirement document, and failure to 
capture all the requirements in the PRD. Most pharmaceutical products require connecting product 
requirements to traceability matrix. A great way to effectively eliminate any issues that were 
discussed above and managing an efficient product development is QFD – Quality Functional 
Deployment (Kurt Matzlera, et.al, 1998). These risks are both categorized as project and product 
risks. Close attention to these risks is warranted because they may have a significant effect on the 
manufacturing. 
PILOT STUDIES 
In any product development, irrespective of industry, risks were basically identified by 
developing prototypes. Another critical phase in the commercialization process involves conducting 
pilot studies. Since pilot studies are used to develop, and characterize the product, and to establish 
adequate design controls.These are essentially grouped under product risks. The pilot study helps to 
identify the risks on the following: 
Specification Development: In any new product development, specification development is a 
significant task (FDA, guidance). It is important to assess risks extensively on this process. 
Several projects failed to achieve its long term goal due to inadequate and inappropriate 
specifications. Project team uses several approachto assess if there is any risks associated with 
specification developed pilot studies are setup Risks were identified from the pilot studies, DOE, 
guard branding, and design space studies.Design of Experiments – a great tool for understanding 
and mitigating any specifications based risks. This is done by analyzing the interaction between 
critical factors such as chemicals, mixing, pH, solubility, and their impact on the specification. 
Certain risks also need to be analyzed for tolerance of certain impurities from raw materials on 
the specification.The proposed specification may not address customer requirements. This is a 
significant risk that leads to numerous customer complaints.Some new product development 
process lacks the analytical method/quality control method development. Even the developed 
method may not be optimized for addressing calling good vs. bad lots.
International Journal of Management (IJM), ISSN 0976 – 6502(Print), ISSN 0976 - 6510(Online), 
Volume 5, Issue 7, July (2014), pp. 44-50 © IAEME 
47 
 
Raw Material requirements: Raw material characterizations are crucial for developing 
specifications and consistent product performance. This is a critical process, any issues arises in 
this may results in product recalls and compliance issues. Risks were identified on the quality of 
the raw materials. (One common supplier’s claim is that the raw materials are 99% pure. The risk 
of combination effect of 1% impurities from five or six raw materials used to make a product. 
More prevalent risk is failure to detect substandard materials during incoming inspection (Trivedi 
et al, 2011). More frequent product failures comes from risk involving contamination including 
microbial, chemical and other materials. Recently several nations have imposed ban on certain 
materials and team need to assess the risks if those materials will be part of the product and how 
it may impact the marketing in those countries. Assessment need to be made for stability of the 
raw materials, and handling and storage of raw materials. 
Process Development: Based on pilot studies, risks assessment for process development is done. 
The project team assesses the risks through process characterization, design verification and 
validation. Identified risks includetranslating the product requirements to process requirements. 
The risk assessment should include whether the developed process will consistently produce the 
products with all requirements and specifications. Assessing the risks of not understanding the 
flow requirements in operations/ manufacturing. Risks need to be assessed onconverting from 
pilot build to full scale build using the developed process. A critical failure of products during 
manufacturing is developed process not able to withstand minor variations in raw material, 
operator, equipment, etc. The project team has to assess the risks involving long term and short 
term process capabilities (CPK). 
Analytical/Quality control Method development: Once a manufacturing process was designed, 
team identifies appropriate quality sampling and testing method. More emphasis for developing 
testing at adequate steps along the process, and establishing the final release criteria are 
mandatory. Project team requires assessing the risk involving failure of the developed test 
method to take into consideration of any variation in equipment, and operator to operator.Risks 
from either excessive testing, or too few testing. Product performance risk from method not 
characterized adequately, resulting in frequent failures in the manufacturing.Risk of failure of the 
testing process that cannot identify good vs. bad lots. This type of risk is always ranked high 
because this may lead to a flawed product passing the test and being shipped to the customer, 
failing at the customer’s hand. Alternatively, test may incorrectly classify a good lot as a bad, and 
disposition to scrap, resulting in revenue loss. 
Design Verification and Validation: Once the pilot lots are completed and process identified, a 
plan is created to verify and validate the design and the design controls established. Risk 
assessments performed during the 3P process as well. Design FMEA will be conducted. Some 
common risks that team may identify are: Failure of the validation to provide any conclusive 
results.Risk of failure of the validation studies. 
Design Controls: With FDA giving more emphasis on having adequate design controls in new 
product development ((FDA, guidance).Based on the pilot lots, and validation, assessing risks 
related to design control are more critical. The whole process of risk assessment and chances for 
improvement are done through conducting the 3P process. Risks need to be identified from 
inadequate or not so robust design controls in the process. Risks may arise from product liability 
from inadequate design controls.
International Journal of Management (IJM), ISSN 0976 – 6502(Print), ISSN 0976 - 6510(Online), 
Volume 5, Issue 7, July (2014), pp. 44-50 © IAEME 
48 
 
Design FMEA: The final stage of the risk assessment is to combine all previously identified 
risks and entered them in the risk register (Susan. P. et.al, 2003), project team need to conduct an 
extensive design FMEA to understand the failure mode of each identified risks and its impact on 
the products performance, safety and efficacy. Ranking need to be based on the severity, 
occurrence and detection of risks. RPN calculated and risks need to be prioritized based on the 
several factors including RPN number, threat to success of the project and for the upstream 
manufacturing. (Figure 1).
International Journal of Management (IJM), ISSN 0976 – 6502(Print), ISSN 0976 - 6510(Online), 
Volume 5, Issue 7, July (2014), pp. 44-50 © IAEME 
49 
CONCLUSIONS 
 
Risk assessment is an integral part of any project; especially, more crucial during the product 
development stage in a new product commercialization process. Several product development 
projects that do not have adequate risk assessment process had undergone numerous distress in the 
aspects of overrunning project cost, delayed project schedule, and increased quality issues down the 
road in the manufacturing process. In a biotech/pharmaceutical environment, planning suitable 
process for risk assessment is important, considering the longer period of development phase. 
Performing risk assessment during the upfront phase will significantly reduce the project cost. For 
any project manager, knowing the known risks and planning contingency response for unknown risks 
put him as well as the project at better position for success. 
REFERENCE 
1. Griffin, A. (1997). PDMA Research on New Product Development, Practices: Updating 
Trends and Benchmarking Best Practices. Journal of Product Innovation Management 
14(6):429–458. 
2. Gary E. Blau, Joseph F. Pekny, Vishal A. Varma and Paul R. BunchManaging a Portfolio of 
Interdependent New Product Candidates in the Pharmaceutical Industry, Journal of Product 
Innovation Management, Volume 21, Issue 4, pages 227–245, July 2004. 
3. Kahn, K.B. (2002). An Exploratory Investigation of New Product Forecasting Practices. 
Journal of Product Innovation Management, 19(2):133–143. 
4. Food and Drug Administration. Final Report on Pharmaceutical cGMPs for the 21st Century – 
ARisk Based Approach, http://www.fda.gov/ cder/ gmp/ gmp 2004/ GMP_ final report 
2004.htm. 
5. Atkinson, Roger, Crawford, Lynn and Ward, Stephen (2006) Fundamental uncertainties in 
projects and the scope of project management. International Journal of Project Management, 
24, (8), 687-698. 
6. SC Wheelwright, KB Clark – 1992, Creating project plans to focus product development, 
mis.postech.ac.kr. 
7. R. Edward Freeman and John McVea, A Stakeholder Approach to Strategic management, 
Handbook of Strategic Management, Oxford: Blackwell Publishing. 
8. Ronald K. Mitchell, Bradley R. Agle and Donna J. Wood, Toward a Theory of Stakeholder 
Identification and Salience: Defining the Principle of Who and What Really Counts, The 
Academy of Management Review, 1997, Page 853 of 853-886. 
9. Alison McKay, Alan de Pennington, Jim Baxter, Requirements management: a representation 
scheme for product specifications, Computer-Aided Design 33 (2001) 511±520. 
10. Kurt Matzlera, Hans H. Hinterhuber, How to make product development projects more 
successful by integrating Kano's model of customer satisfaction into quality function 
deployment, Technovation, Volume 18, Issue 1, January 1998, Pages 25–38. 
11. Bhagyesh Trivedi, Quality By Design (Qbd) In Pharmaceuticals, International Journal of 
Pharmacy And Pharmaceutical Sciences, Vol 4, Issue 1, 2012. 
12. Susan P. Felter, Cindy A. Ryan,a David A. Basketter, Nicola J. Gilmour, and G. Frank 
Gerbericka, Application of the risk assessment paradigm to the induction of allergic contact 
dermatitis, Regulatory Toxicology and Pharmacology 37 (2003) 1–10. 
13. Guidance for Industry Q8 (R2) - Food and Drug Administration. 
14. W. L. Pearn  K. S. Chen , A Practical Implementation Of The Process Capability Index Cpk, 
Quality Engineering , Volume 9, Issue 4, 1997.
International Journal of Management (IJM), ISSN 0976 – 6502(Print), ISSN 0976 - 6510(Online), 
Volume 5, Issue 7, July (2014), pp. 44-50 © IAEME 
50 
 
15. Neeti Jain, Jimmy Kansal, AshwagoshaGanju, Anil Khurana, PramodSatyawali, 2013. The 
Effect of Implementation of ISO 9001:2008 QMS on the Organizational Performance in an 
RD Establishment International Journal of Management (IJM), Volume: 4, Issue: 1, 
Pages: 47 - 55, ISSN 0976-6510 (Online). 
16. Neha Kalra and Anoop Pant, 2013. TQM-A Management Philosophy in Indian Automobile 
Industry (NCR). International Journal of Management (IJM).Volume:4, Issue: 6, Pages: 12-20. 
17. Anil Khurana, Prof. Jamal A Farooquie, Dr. Manjit Singh and Jimmy Kansal, 2013. Effect of 
Iso 9001 Quality Management Systems Certification on the Performance in Indian Defence 
RD Organisation. International Journal of Management (IJM). Volume: 4, Issue: 6, 
Pages: 61-76, ISSN 0976-6510 (Online). 
18. Er. Amit Bijon Dutta and Dr. M. J. Kolhatkar, 2014. Study of Risk Management in 
Construction Projects. International Journal of Management (IJM). Volume: 5, Issue: 6, 
Pages: 32-39, ISSN 0976-6510 (Online).

More Related Content

What's hot

Anju drolia
Anju droliaAnju drolia
Anju droliaPMI2011
 
Medical Device Project Management MBA Powell
Medical Device Project Management MBA PowellMedical Device Project Management MBA Powell
Medical Device Project Management MBA PowellDave Powell, ATP
 
First Step in QbD - How to Get it Right
First Step in QbD - How to Get it RightFirst Step in QbD - How to Get it Right
First Step in QbD - How to Get it RightSun Kim
 
Regulatory Challenges: Lecture @ University of Michigan 21 Feb 2013
Regulatory Challenges: Lecture @ University of Michigan 21 Feb 2013Regulatory Challenges: Lecture @ University of Michigan 21 Feb 2013
Regulatory Challenges: Lecture @ University of Michigan 21 Feb 2013Ajaz Hussain
 
Risk Analysis and Management
Risk Analysis and ManagementRisk Analysis and Management
Risk Analysis and ManagementGenie
 
Chemometrics Pharmacometrics Econometrics of QbD Swiss Pharma-6 2012
Chemometrics Pharmacometrics Econometrics of QbD Swiss Pharma-6 2012Chemometrics Pharmacometrics Econometrics of QbD Swiss Pharma-6 2012
Chemometrics Pharmacometrics Econometrics of QbD Swiss Pharma-6 2012Ajaz Hussain
 
Risk assesment template
Risk assesment templateRisk assesment template
Risk assesment templateGlen Alleman
 
Risk Driven Approach to Test Device Software
Risk Driven Approach to Test Device SoftwareRisk Driven Approach to Test Device Software
Risk Driven Approach to Test Device Softwareijtsrd
 
Quality Risk Management-ICH Q9-2014
Quality Risk Management-ICH Q9-2014Quality Risk Management-ICH Q9-2014
Quality Risk Management-ICH Q9-2014Cepal & Co.
 
Continuous Risk Management
Continuous Risk ManagementContinuous Risk Management
Continuous Risk ManagementGlen Alleman
 
New Product Planning in the Pharmaceutical Industry
New Product Planning in the Pharmaceutical IndustryNew Product Planning in the Pharmaceutical Industry
New Product Planning in the Pharmaceutical IndustryAnthony Russell
 
transftec
transftectransftec
transftecselks
 
Six Sigma Case Cart Project Final Report Jan. 2011
Six Sigma Case Cart Project Final Report Jan. 2011Six Sigma Case Cart Project Final Report Jan. 2011
Six Sigma Case Cart Project Final Report Jan. 2011dpjphx
 

What's hot (18)

Anju drolia
Anju droliaAnju drolia
Anju drolia
 
Medical Device Project Management MBA Powell
Medical Device Project Management MBA PowellMedical Device Project Management MBA Powell
Medical Device Project Management MBA Powell
 
First Step in QbD - How to Get it Right
First Step in QbD - How to Get it RightFirst Step in QbD - How to Get it Right
First Step in QbD - How to Get it Right
 
Regulatory Challenges: Lecture @ University of Michigan 21 Feb 2013
Regulatory Challenges: Lecture @ University of Michigan 21 Feb 2013Regulatory Challenges: Lecture @ University of Michigan 21 Feb 2013
Regulatory Challenges: Lecture @ University of Michigan 21 Feb 2013
 
Risk Analysis and Management
Risk Analysis and ManagementRisk Analysis and Management
Risk Analysis and Management
 
ETPM1
ETPM1ETPM1
ETPM1
 
RM Maturity Level Development 2002
RM Maturity Level Development 2002RM Maturity Level Development 2002
RM Maturity Level Development 2002
 
Chemometrics Pharmacometrics Econometrics of QbD Swiss Pharma-6 2012
Chemometrics Pharmacometrics Econometrics of QbD Swiss Pharma-6 2012Chemometrics Pharmacometrics Econometrics of QbD Swiss Pharma-6 2012
Chemometrics Pharmacometrics Econometrics of QbD Swiss Pharma-6 2012
 
What is risk?
What is risk?What is risk?
What is risk?
 
Risk assesment template
Risk assesment templateRisk assesment template
Risk assesment template
 
Risk Driven Approach to Test Device Software
Risk Driven Approach to Test Device SoftwareRisk Driven Approach to Test Device Software
Risk Driven Approach to Test Device Software
 
Quality by design
Quality by designQuality by design
Quality by design
 
Quality Risk Management-ICH Q9-2014
Quality Risk Management-ICH Q9-2014Quality Risk Management-ICH Q9-2014
Quality Risk Management-ICH Q9-2014
 
Pm session10
Pm session10Pm session10
Pm session10
 
Continuous Risk Management
Continuous Risk ManagementContinuous Risk Management
Continuous Risk Management
 
New Product Planning in the Pharmaceutical Industry
New Product Planning in the Pharmaceutical IndustryNew Product Planning in the Pharmaceutical Industry
New Product Planning in the Pharmaceutical Industry
 
transftec
transftectransftec
transftec
 
Six Sigma Case Cart Project Final Report Jan. 2011
Six Sigma Case Cart Project Final Report Jan. 2011Six Sigma Case Cart Project Final Report Jan. 2011
Six Sigma Case Cart Project Final Report Jan. 2011
 

Viewers also liked

Behavior of concrete damaged by high temperature exposureand confined with cf...
Behavior of concrete damaged by high temperature exposureand confined with cf...Behavior of concrete damaged by high temperature exposureand confined with cf...
Behavior of concrete damaged by high temperature exposureand confined with cf...IAEME Publication
 
Rcc beam with spiral reinforcement
Rcc beam with spiral reinforcementRcc beam with spiral reinforcement
Rcc beam with spiral reinforcementIAEME Publication
 
Percentage replacement of bitumen with sugarcane waste molasses
Percentage replacement of bitumen with sugarcane waste molassesPercentage replacement of bitumen with sugarcane waste molasses
Percentage replacement of bitumen with sugarcane waste molassesIAEME Publication
 

Viewers also liked (9)

20320140503041
2032014050304120320140503041
20320140503041
 
Behavior of concrete damaged by high temperature exposureand confined with cf...
Behavior of concrete damaged by high temperature exposureand confined with cf...Behavior of concrete damaged by high temperature exposureand confined with cf...
Behavior of concrete damaged by high temperature exposureand confined with cf...
 
Rcc beam with spiral reinforcement
Rcc beam with spiral reinforcementRcc beam with spiral reinforcement
Rcc beam with spiral reinforcement
 
40120140507006
4012014050700640120140507006
40120140507006
 
30420140503003
3042014050300330420140503003
30420140503003
 
50120140507004
5012014050700450120140507004
50120140507004
 
30120140507011
3012014050701130120140507011
30120140507011
 
Percentage replacement of bitumen with sugarcane waste molasses
Percentage replacement of bitumen with sugarcane waste molassesPercentage replacement of bitumen with sugarcane waste molasses
Percentage replacement of bitumen with sugarcane waste molasses
 
30120140507005
3012014050700530120140507005
30120140507005
 

Similar to 10120140507004

""Tech transfer making it as a risk free approach in pharmaceutical and biote...
""Tech transfer making it as a risk free approach in pharmaceutical and biote...""Tech transfer making it as a risk free approach in pharmaceutical and biote...
""Tech transfer making it as a risk free approach in pharmaceutical and biote...IAEME Publication
 
Project risk management_in_new_product_development
Project risk management_in_new_product_developmentProject risk management_in_new_product_development
Project risk management_in_new_product_developmentOmid Aminzadeh Gohari
 
Project risk management in new product development
Project risk management in new product developmentProject risk management in new product development
Project risk management in new product developmentOmid Aminzadeh Gohari
 
Application of voc translationtools a case study
Application of voc translationtools a case studyApplication of voc translationtools a case study
Application of voc translationtools a case studyiaemedu
 
Application of voc translationtools a case study
Application of voc translationtools a case studyApplication of voc translationtools a case study
Application of voc translationtools a case studyiaemedu
 
IRJET- Risk Management in Residential Project by Primavera Software
IRJET- Risk Management in Residential Project by Primavera SoftwareIRJET- Risk Management in Residential Project by Primavera Software
IRJET- Risk Management in Residential Project by Primavera SoftwareIRJET Journal
 
IRJET- Risk Management in Construction: A Literature Review
IRJET- Risk Management in Construction: A Literature ReviewIRJET- Risk Management in Construction: A Literature Review
IRJET- Risk Management in Construction: A Literature ReviewIRJET Journal
 
RISK ASSESSMENT OF CONSTRUCTION BUILDING PROJECTS
RISK ASSESSMENT OF CONSTRUCTION BUILDING PROJECTSRISK ASSESSMENT OF CONSTRUCTION BUILDING PROJECTS
RISK ASSESSMENT OF CONSTRUCTION BUILDING PROJECTSIRJET Journal
 
RISK ASSESSMENT OF CONSTRUCTION BUILDING PROJECTS
RISK ASSESSMENT OF CONSTRUCTION BUILDING PROJECTSRISK ASSESSMENT OF CONSTRUCTION BUILDING PROJECTS
RISK ASSESSMENT OF CONSTRUCTION BUILDING PROJECTSIRJET Journal
 
Aligning data life cycle with qb d risk management principle across the produ...
Aligning data life cycle with qb d risk management principle across the produ...Aligning data life cycle with qb d risk management principle across the produ...
Aligning data life cycle with qb d risk management principle across the produ...SANDEEP DIWAKER
 
Value Engineering. Measuring and managing risks in the wind energy industry
Value Engineering. Measuring and managing risks in the wind energy industryValue Engineering. Measuring and managing risks in the wind energy industry
Value Engineering. Measuring and managing risks in the wind energy industryStavros Thomas
 
Table of ContentsIntroduction3P.docx
Table of ContentsIntroduction3P.docxTable of ContentsIntroduction3P.docx
Table of ContentsIntroduction3P.docxmattinsonjanel
 
Risk management Phase 1-5 Individual Project.docx
Risk management Phase 1-5 Individual Project.docxRisk management Phase 1-5 Individual Project.docx
Risk management Phase 1-5 Individual Project.docxjoellemurphey
 
MBA 6941, Managing Project Teams 1 Course Learning Ou.docx
 MBA 6941, Managing Project Teams 1 Course Learning Ou.docx MBA 6941, Managing Project Teams 1 Course Learning Ou.docx
MBA 6941, Managing Project Teams 1 Course Learning Ou.docxaryan532920
 
IRJET- Review on Developing a Model of Risk Allocation and Risk Handling for ...
IRJET- Review on Developing a Model of Risk Allocation and Risk Handling for ...IRJET- Review on Developing a Model of Risk Allocation and Risk Handling for ...
IRJET- Review on Developing a Model of Risk Allocation and Risk Handling for ...IRJET Journal
 
PAPERS72 September 2009 ■ Project Management.docx
PAPERS72 September 2009 ■ Project Management.docxPAPERS72 September 2009 ■ Project Management.docx
PAPERS72 September 2009 ■ Project Management.docxherbertwilson5999
 
Software Project Risk Management Practice in Oman
Software Project Risk Management Practice in OmanSoftware Project Risk Management Practice in Oman
Software Project Risk Management Practice in OmanEECJOURNAL
 

Similar to 10120140507004 (20)

18 .docx
18                                  .docx18                                  .docx
18 .docx
 
9 .docx
9                                   .docx9                                   .docx
9 .docx
 
""Tech transfer making it as a risk free approach in pharmaceutical and biote...
""Tech transfer making it as a risk free approach in pharmaceutical and biote...""Tech transfer making it as a risk free approach in pharmaceutical and biote...
""Tech transfer making it as a risk free approach in pharmaceutical and biote...
 
Project risk management_in_new_product_development
Project risk management_in_new_product_developmentProject risk management_in_new_product_development
Project risk management_in_new_product_development
 
Project risk management in new product development
Project risk management in new product developmentProject risk management in new product development
Project risk management in new product development
 
Application of voc translationtools a case study
Application of voc translationtools a case studyApplication of voc translationtools a case study
Application of voc translationtools a case study
 
Application of voc translationtools a case study
Application of voc translationtools a case studyApplication of voc translationtools a case study
Application of voc translationtools a case study
 
IRJET- Risk Management in Residential Project by Primavera Software
IRJET- Risk Management in Residential Project by Primavera SoftwareIRJET- Risk Management in Residential Project by Primavera Software
IRJET- Risk Management in Residential Project by Primavera Software
 
IRJET- Risk Management in Construction: A Literature Review
IRJET- Risk Management in Construction: A Literature ReviewIRJET- Risk Management in Construction: A Literature Review
IRJET- Risk Management in Construction: A Literature Review
 
RISK ASSESSMENT OF CONSTRUCTION BUILDING PROJECTS
RISK ASSESSMENT OF CONSTRUCTION BUILDING PROJECTSRISK ASSESSMENT OF CONSTRUCTION BUILDING PROJECTS
RISK ASSESSMENT OF CONSTRUCTION BUILDING PROJECTS
 
RISK ASSESSMENT OF CONSTRUCTION BUILDING PROJECTS
RISK ASSESSMENT OF CONSTRUCTION BUILDING PROJECTSRISK ASSESSMENT OF CONSTRUCTION BUILDING PROJECTS
RISK ASSESSMENT OF CONSTRUCTION BUILDING PROJECTS
 
Aligning data life cycle with qb d risk management principle across the produ...
Aligning data life cycle with qb d risk management principle across the produ...Aligning data life cycle with qb d risk management principle across the produ...
Aligning data life cycle with qb d risk management principle across the produ...
 
Value Engineering. Measuring and managing risks in the wind energy industry
Value Engineering. Measuring and managing risks in the wind energy industryValue Engineering. Measuring and managing risks in the wind energy industry
Value Engineering. Measuring and managing risks in the wind energy industry
 
Ijetcas14 370
Ijetcas14 370Ijetcas14 370
Ijetcas14 370
 
Table of ContentsIntroduction3P.docx
Table of ContentsIntroduction3P.docxTable of ContentsIntroduction3P.docx
Table of ContentsIntroduction3P.docx
 
Risk management Phase 1-5 Individual Project.docx
Risk management Phase 1-5 Individual Project.docxRisk management Phase 1-5 Individual Project.docx
Risk management Phase 1-5 Individual Project.docx
 
MBA 6941, Managing Project Teams 1 Course Learning Ou.docx
 MBA 6941, Managing Project Teams 1 Course Learning Ou.docx MBA 6941, Managing Project Teams 1 Course Learning Ou.docx
MBA 6941, Managing Project Teams 1 Course Learning Ou.docx
 
IRJET- Review on Developing a Model of Risk Allocation and Risk Handling for ...
IRJET- Review on Developing a Model of Risk Allocation and Risk Handling for ...IRJET- Review on Developing a Model of Risk Allocation and Risk Handling for ...
IRJET- Review on Developing a Model of Risk Allocation and Risk Handling for ...
 
PAPERS72 September 2009 ■ Project Management.docx
PAPERS72 September 2009 ■ Project Management.docxPAPERS72 September 2009 ■ Project Management.docx
PAPERS72 September 2009 ■ Project Management.docx
 
Software Project Risk Management Practice in Oman
Software Project Risk Management Practice in OmanSoftware Project Risk Management Practice in Oman
Software Project Risk Management Practice in Oman
 

More from IAEME Publication

IAEME_Publication_Call_for_Paper_September_2022.pdf
IAEME_Publication_Call_for_Paper_September_2022.pdfIAEME_Publication_Call_for_Paper_September_2022.pdf
IAEME_Publication_Call_for_Paper_September_2022.pdfIAEME Publication
 
MODELING AND ANALYSIS OF SURFACE ROUGHNESS AND WHITE LATER THICKNESS IN WIRE-...
MODELING AND ANALYSIS OF SURFACE ROUGHNESS AND WHITE LATER THICKNESS IN WIRE-...MODELING AND ANALYSIS OF SURFACE ROUGHNESS AND WHITE LATER THICKNESS IN WIRE-...
MODELING AND ANALYSIS OF SURFACE ROUGHNESS AND WHITE LATER THICKNESS IN WIRE-...IAEME Publication
 
A STUDY ON THE REASONS FOR TRANSGENDER TO BECOME ENTREPRENEURS
A STUDY ON THE REASONS FOR TRANSGENDER TO BECOME ENTREPRENEURSA STUDY ON THE REASONS FOR TRANSGENDER TO BECOME ENTREPRENEURS
A STUDY ON THE REASONS FOR TRANSGENDER TO BECOME ENTREPRENEURSIAEME Publication
 
BROAD UNEXPOSED SKILLS OF TRANSGENDER ENTREPRENEURS
BROAD UNEXPOSED SKILLS OF TRANSGENDER ENTREPRENEURSBROAD UNEXPOSED SKILLS OF TRANSGENDER ENTREPRENEURS
BROAD UNEXPOSED SKILLS OF TRANSGENDER ENTREPRENEURSIAEME Publication
 
DETERMINANTS AFFECTING THE USER'S INTENTION TO USE MOBILE BANKING APPLICATIONS
DETERMINANTS AFFECTING THE USER'S INTENTION TO USE MOBILE BANKING APPLICATIONSDETERMINANTS AFFECTING THE USER'S INTENTION TO USE MOBILE BANKING APPLICATIONS
DETERMINANTS AFFECTING THE USER'S INTENTION TO USE MOBILE BANKING APPLICATIONSIAEME Publication
 
ANALYSE THE USER PREDILECTION ON GPAY AND PHONEPE FOR DIGITAL TRANSACTIONS
ANALYSE THE USER PREDILECTION ON GPAY AND PHONEPE FOR DIGITAL TRANSACTIONSANALYSE THE USER PREDILECTION ON GPAY AND PHONEPE FOR DIGITAL TRANSACTIONS
ANALYSE THE USER PREDILECTION ON GPAY AND PHONEPE FOR DIGITAL TRANSACTIONSIAEME Publication
 
VOICE BASED ATM FOR VISUALLY IMPAIRED USING ARDUINO
VOICE BASED ATM FOR VISUALLY IMPAIRED USING ARDUINOVOICE BASED ATM FOR VISUALLY IMPAIRED USING ARDUINO
VOICE BASED ATM FOR VISUALLY IMPAIRED USING ARDUINOIAEME Publication
 
IMPACT OF EMOTIONAL INTELLIGENCE ON HUMAN RESOURCE MANAGEMENT PRACTICES AMONG...
IMPACT OF EMOTIONAL INTELLIGENCE ON HUMAN RESOURCE MANAGEMENT PRACTICES AMONG...IMPACT OF EMOTIONAL INTELLIGENCE ON HUMAN RESOURCE MANAGEMENT PRACTICES AMONG...
IMPACT OF EMOTIONAL INTELLIGENCE ON HUMAN RESOURCE MANAGEMENT PRACTICES AMONG...IAEME Publication
 
VISUALISING AGING PARENTS & THEIR CLOSE CARERS LIFE JOURNEY IN AGING ECONOMY
VISUALISING AGING PARENTS & THEIR CLOSE CARERS LIFE JOURNEY IN AGING ECONOMYVISUALISING AGING PARENTS & THEIR CLOSE CARERS LIFE JOURNEY IN AGING ECONOMY
VISUALISING AGING PARENTS & THEIR CLOSE CARERS LIFE JOURNEY IN AGING ECONOMYIAEME Publication
 
A STUDY ON THE IMPACT OF ORGANIZATIONAL CULTURE ON THE EFFECTIVENESS OF PERFO...
A STUDY ON THE IMPACT OF ORGANIZATIONAL CULTURE ON THE EFFECTIVENESS OF PERFO...A STUDY ON THE IMPACT OF ORGANIZATIONAL CULTURE ON THE EFFECTIVENESS OF PERFO...
A STUDY ON THE IMPACT OF ORGANIZATIONAL CULTURE ON THE EFFECTIVENESS OF PERFO...IAEME Publication
 
GANDHI ON NON-VIOLENT POLICE
GANDHI ON NON-VIOLENT POLICEGANDHI ON NON-VIOLENT POLICE
GANDHI ON NON-VIOLENT POLICEIAEME Publication
 
A STUDY ON TALENT MANAGEMENT AND ITS IMPACT ON EMPLOYEE RETENTION IN SELECTED...
A STUDY ON TALENT MANAGEMENT AND ITS IMPACT ON EMPLOYEE RETENTION IN SELECTED...A STUDY ON TALENT MANAGEMENT AND ITS IMPACT ON EMPLOYEE RETENTION IN SELECTED...
A STUDY ON TALENT MANAGEMENT AND ITS IMPACT ON EMPLOYEE RETENTION IN SELECTED...IAEME Publication
 
ATTRITION IN THE IT INDUSTRY DURING COVID-19 PANDEMIC: LINKING EMOTIONAL INTE...
ATTRITION IN THE IT INDUSTRY DURING COVID-19 PANDEMIC: LINKING EMOTIONAL INTE...ATTRITION IN THE IT INDUSTRY DURING COVID-19 PANDEMIC: LINKING EMOTIONAL INTE...
ATTRITION IN THE IT INDUSTRY DURING COVID-19 PANDEMIC: LINKING EMOTIONAL INTE...IAEME Publication
 
INFLUENCE OF TALENT MANAGEMENT PRACTICES ON ORGANIZATIONAL PERFORMANCE A STUD...
INFLUENCE OF TALENT MANAGEMENT PRACTICES ON ORGANIZATIONAL PERFORMANCE A STUD...INFLUENCE OF TALENT MANAGEMENT PRACTICES ON ORGANIZATIONAL PERFORMANCE A STUD...
INFLUENCE OF TALENT MANAGEMENT PRACTICES ON ORGANIZATIONAL PERFORMANCE A STUD...IAEME Publication
 
A STUDY OF VARIOUS TYPES OF LOANS OF SELECTED PUBLIC AND PRIVATE SECTOR BANKS...
A STUDY OF VARIOUS TYPES OF LOANS OF SELECTED PUBLIC AND PRIVATE SECTOR BANKS...A STUDY OF VARIOUS TYPES OF LOANS OF SELECTED PUBLIC AND PRIVATE SECTOR BANKS...
A STUDY OF VARIOUS TYPES OF LOANS OF SELECTED PUBLIC AND PRIVATE SECTOR BANKS...IAEME Publication
 
EXPERIMENTAL STUDY OF MECHANICAL AND TRIBOLOGICAL RELATION OF NYLON/BaSO4 POL...
EXPERIMENTAL STUDY OF MECHANICAL AND TRIBOLOGICAL RELATION OF NYLON/BaSO4 POL...EXPERIMENTAL STUDY OF MECHANICAL AND TRIBOLOGICAL RELATION OF NYLON/BaSO4 POL...
EXPERIMENTAL STUDY OF MECHANICAL AND TRIBOLOGICAL RELATION OF NYLON/BaSO4 POL...IAEME Publication
 
ROLE OF SOCIAL ENTREPRENEURSHIP IN RURAL DEVELOPMENT OF INDIA - PROBLEMS AND ...
ROLE OF SOCIAL ENTREPRENEURSHIP IN RURAL DEVELOPMENT OF INDIA - PROBLEMS AND ...ROLE OF SOCIAL ENTREPRENEURSHIP IN RURAL DEVELOPMENT OF INDIA - PROBLEMS AND ...
ROLE OF SOCIAL ENTREPRENEURSHIP IN RURAL DEVELOPMENT OF INDIA - PROBLEMS AND ...IAEME Publication
 
OPTIMAL RECONFIGURATION OF POWER DISTRIBUTION RADIAL NETWORK USING HYBRID MET...
OPTIMAL RECONFIGURATION OF POWER DISTRIBUTION RADIAL NETWORK USING HYBRID MET...OPTIMAL RECONFIGURATION OF POWER DISTRIBUTION RADIAL NETWORK USING HYBRID MET...
OPTIMAL RECONFIGURATION OF POWER DISTRIBUTION RADIAL NETWORK USING HYBRID MET...IAEME Publication
 
APPLICATION OF FRUGAL APPROACH FOR PRODUCTIVITY IMPROVEMENT - A CASE STUDY OF...
APPLICATION OF FRUGAL APPROACH FOR PRODUCTIVITY IMPROVEMENT - A CASE STUDY OF...APPLICATION OF FRUGAL APPROACH FOR PRODUCTIVITY IMPROVEMENT - A CASE STUDY OF...
APPLICATION OF FRUGAL APPROACH FOR PRODUCTIVITY IMPROVEMENT - A CASE STUDY OF...IAEME Publication
 
A MULTIPLE – CHANNEL QUEUING MODELS ON FUZZY ENVIRONMENT
A MULTIPLE – CHANNEL QUEUING MODELS ON FUZZY ENVIRONMENTA MULTIPLE – CHANNEL QUEUING MODELS ON FUZZY ENVIRONMENT
A MULTIPLE – CHANNEL QUEUING MODELS ON FUZZY ENVIRONMENTIAEME Publication
 

More from IAEME Publication (20)

IAEME_Publication_Call_for_Paper_September_2022.pdf
IAEME_Publication_Call_for_Paper_September_2022.pdfIAEME_Publication_Call_for_Paper_September_2022.pdf
IAEME_Publication_Call_for_Paper_September_2022.pdf
 
MODELING AND ANALYSIS OF SURFACE ROUGHNESS AND WHITE LATER THICKNESS IN WIRE-...
MODELING AND ANALYSIS OF SURFACE ROUGHNESS AND WHITE LATER THICKNESS IN WIRE-...MODELING AND ANALYSIS OF SURFACE ROUGHNESS AND WHITE LATER THICKNESS IN WIRE-...
MODELING AND ANALYSIS OF SURFACE ROUGHNESS AND WHITE LATER THICKNESS IN WIRE-...
 
A STUDY ON THE REASONS FOR TRANSGENDER TO BECOME ENTREPRENEURS
A STUDY ON THE REASONS FOR TRANSGENDER TO BECOME ENTREPRENEURSA STUDY ON THE REASONS FOR TRANSGENDER TO BECOME ENTREPRENEURS
A STUDY ON THE REASONS FOR TRANSGENDER TO BECOME ENTREPRENEURS
 
BROAD UNEXPOSED SKILLS OF TRANSGENDER ENTREPRENEURS
BROAD UNEXPOSED SKILLS OF TRANSGENDER ENTREPRENEURSBROAD UNEXPOSED SKILLS OF TRANSGENDER ENTREPRENEURS
BROAD UNEXPOSED SKILLS OF TRANSGENDER ENTREPRENEURS
 
DETERMINANTS AFFECTING THE USER'S INTENTION TO USE MOBILE BANKING APPLICATIONS
DETERMINANTS AFFECTING THE USER'S INTENTION TO USE MOBILE BANKING APPLICATIONSDETERMINANTS AFFECTING THE USER'S INTENTION TO USE MOBILE BANKING APPLICATIONS
DETERMINANTS AFFECTING THE USER'S INTENTION TO USE MOBILE BANKING APPLICATIONS
 
ANALYSE THE USER PREDILECTION ON GPAY AND PHONEPE FOR DIGITAL TRANSACTIONS
ANALYSE THE USER PREDILECTION ON GPAY AND PHONEPE FOR DIGITAL TRANSACTIONSANALYSE THE USER PREDILECTION ON GPAY AND PHONEPE FOR DIGITAL TRANSACTIONS
ANALYSE THE USER PREDILECTION ON GPAY AND PHONEPE FOR DIGITAL TRANSACTIONS
 
VOICE BASED ATM FOR VISUALLY IMPAIRED USING ARDUINO
VOICE BASED ATM FOR VISUALLY IMPAIRED USING ARDUINOVOICE BASED ATM FOR VISUALLY IMPAIRED USING ARDUINO
VOICE BASED ATM FOR VISUALLY IMPAIRED USING ARDUINO
 
IMPACT OF EMOTIONAL INTELLIGENCE ON HUMAN RESOURCE MANAGEMENT PRACTICES AMONG...
IMPACT OF EMOTIONAL INTELLIGENCE ON HUMAN RESOURCE MANAGEMENT PRACTICES AMONG...IMPACT OF EMOTIONAL INTELLIGENCE ON HUMAN RESOURCE MANAGEMENT PRACTICES AMONG...
IMPACT OF EMOTIONAL INTELLIGENCE ON HUMAN RESOURCE MANAGEMENT PRACTICES AMONG...
 
VISUALISING AGING PARENTS & THEIR CLOSE CARERS LIFE JOURNEY IN AGING ECONOMY
VISUALISING AGING PARENTS & THEIR CLOSE CARERS LIFE JOURNEY IN AGING ECONOMYVISUALISING AGING PARENTS & THEIR CLOSE CARERS LIFE JOURNEY IN AGING ECONOMY
VISUALISING AGING PARENTS & THEIR CLOSE CARERS LIFE JOURNEY IN AGING ECONOMY
 
A STUDY ON THE IMPACT OF ORGANIZATIONAL CULTURE ON THE EFFECTIVENESS OF PERFO...
A STUDY ON THE IMPACT OF ORGANIZATIONAL CULTURE ON THE EFFECTIVENESS OF PERFO...A STUDY ON THE IMPACT OF ORGANIZATIONAL CULTURE ON THE EFFECTIVENESS OF PERFO...
A STUDY ON THE IMPACT OF ORGANIZATIONAL CULTURE ON THE EFFECTIVENESS OF PERFO...
 
GANDHI ON NON-VIOLENT POLICE
GANDHI ON NON-VIOLENT POLICEGANDHI ON NON-VIOLENT POLICE
GANDHI ON NON-VIOLENT POLICE
 
A STUDY ON TALENT MANAGEMENT AND ITS IMPACT ON EMPLOYEE RETENTION IN SELECTED...
A STUDY ON TALENT MANAGEMENT AND ITS IMPACT ON EMPLOYEE RETENTION IN SELECTED...A STUDY ON TALENT MANAGEMENT AND ITS IMPACT ON EMPLOYEE RETENTION IN SELECTED...
A STUDY ON TALENT MANAGEMENT AND ITS IMPACT ON EMPLOYEE RETENTION IN SELECTED...
 
ATTRITION IN THE IT INDUSTRY DURING COVID-19 PANDEMIC: LINKING EMOTIONAL INTE...
ATTRITION IN THE IT INDUSTRY DURING COVID-19 PANDEMIC: LINKING EMOTIONAL INTE...ATTRITION IN THE IT INDUSTRY DURING COVID-19 PANDEMIC: LINKING EMOTIONAL INTE...
ATTRITION IN THE IT INDUSTRY DURING COVID-19 PANDEMIC: LINKING EMOTIONAL INTE...
 
INFLUENCE OF TALENT MANAGEMENT PRACTICES ON ORGANIZATIONAL PERFORMANCE A STUD...
INFLUENCE OF TALENT MANAGEMENT PRACTICES ON ORGANIZATIONAL PERFORMANCE A STUD...INFLUENCE OF TALENT MANAGEMENT PRACTICES ON ORGANIZATIONAL PERFORMANCE A STUD...
INFLUENCE OF TALENT MANAGEMENT PRACTICES ON ORGANIZATIONAL PERFORMANCE A STUD...
 
A STUDY OF VARIOUS TYPES OF LOANS OF SELECTED PUBLIC AND PRIVATE SECTOR BANKS...
A STUDY OF VARIOUS TYPES OF LOANS OF SELECTED PUBLIC AND PRIVATE SECTOR BANKS...A STUDY OF VARIOUS TYPES OF LOANS OF SELECTED PUBLIC AND PRIVATE SECTOR BANKS...
A STUDY OF VARIOUS TYPES OF LOANS OF SELECTED PUBLIC AND PRIVATE SECTOR BANKS...
 
EXPERIMENTAL STUDY OF MECHANICAL AND TRIBOLOGICAL RELATION OF NYLON/BaSO4 POL...
EXPERIMENTAL STUDY OF MECHANICAL AND TRIBOLOGICAL RELATION OF NYLON/BaSO4 POL...EXPERIMENTAL STUDY OF MECHANICAL AND TRIBOLOGICAL RELATION OF NYLON/BaSO4 POL...
EXPERIMENTAL STUDY OF MECHANICAL AND TRIBOLOGICAL RELATION OF NYLON/BaSO4 POL...
 
ROLE OF SOCIAL ENTREPRENEURSHIP IN RURAL DEVELOPMENT OF INDIA - PROBLEMS AND ...
ROLE OF SOCIAL ENTREPRENEURSHIP IN RURAL DEVELOPMENT OF INDIA - PROBLEMS AND ...ROLE OF SOCIAL ENTREPRENEURSHIP IN RURAL DEVELOPMENT OF INDIA - PROBLEMS AND ...
ROLE OF SOCIAL ENTREPRENEURSHIP IN RURAL DEVELOPMENT OF INDIA - PROBLEMS AND ...
 
OPTIMAL RECONFIGURATION OF POWER DISTRIBUTION RADIAL NETWORK USING HYBRID MET...
OPTIMAL RECONFIGURATION OF POWER DISTRIBUTION RADIAL NETWORK USING HYBRID MET...OPTIMAL RECONFIGURATION OF POWER DISTRIBUTION RADIAL NETWORK USING HYBRID MET...
OPTIMAL RECONFIGURATION OF POWER DISTRIBUTION RADIAL NETWORK USING HYBRID MET...
 
APPLICATION OF FRUGAL APPROACH FOR PRODUCTIVITY IMPROVEMENT - A CASE STUDY OF...
APPLICATION OF FRUGAL APPROACH FOR PRODUCTIVITY IMPROVEMENT - A CASE STUDY OF...APPLICATION OF FRUGAL APPROACH FOR PRODUCTIVITY IMPROVEMENT - A CASE STUDY OF...
APPLICATION OF FRUGAL APPROACH FOR PRODUCTIVITY IMPROVEMENT - A CASE STUDY OF...
 
A MULTIPLE – CHANNEL QUEUING MODELS ON FUZZY ENVIRONMENT
A MULTIPLE – CHANNEL QUEUING MODELS ON FUZZY ENVIRONMENTA MULTIPLE – CHANNEL QUEUING MODELS ON FUZZY ENVIRONMENT
A MULTIPLE – CHANNEL QUEUING MODELS ON FUZZY ENVIRONMENT
 

Recently uploaded

SAP Build Work Zone - Overview L2-L3.pptx
SAP Build Work Zone - Overview L2-L3.pptxSAP Build Work Zone - Overview L2-L3.pptx
SAP Build Work Zone - Overview L2-L3.pptxNavinnSomaal
 
Hyperautomation and AI/ML: A Strategy for Digital Transformation Success.pdf
Hyperautomation and AI/ML: A Strategy for Digital Transformation Success.pdfHyperautomation and AI/ML: A Strategy for Digital Transformation Success.pdf
Hyperautomation and AI/ML: A Strategy for Digital Transformation Success.pdfPrecisely
 
Scanning the Internet for External Cloud Exposures via SSL Certs
Scanning the Internet for External Cloud Exposures via SSL CertsScanning the Internet for External Cloud Exposures via SSL Certs
Scanning the Internet for External Cloud Exposures via SSL CertsRizwan Syed
 
New from BookNet Canada for 2024: BNC CataList - Tech Forum 2024
New from BookNet Canada for 2024: BNC CataList - Tech Forum 2024New from BookNet Canada for 2024: BNC CataList - Tech Forum 2024
New from BookNet Canada for 2024: BNC CataList - Tech Forum 2024BookNet Canada
 
WordPress Websites for Engineers: Elevate Your Brand
WordPress Websites for Engineers: Elevate Your BrandWordPress Websites for Engineers: Elevate Your Brand
WordPress Websites for Engineers: Elevate Your Brandgvaughan
 
Digital Identity is Under Attack: FIDO Paris Seminar.pptx
Digital Identity is Under Attack: FIDO Paris Seminar.pptxDigital Identity is Under Attack: FIDO Paris Seminar.pptx
Digital Identity is Under Attack: FIDO Paris Seminar.pptxLoriGlavin3
 
A Deep Dive on Passkeys: FIDO Paris Seminar.pptx
A Deep Dive on Passkeys: FIDO Paris Seminar.pptxA Deep Dive on Passkeys: FIDO Paris Seminar.pptx
A Deep Dive on Passkeys: FIDO Paris Seminar.pptxLoriGlavin3
 
"Debugging python applications inside k8s environment", Andrii Soldatenko
"Debugging python applications inside k8s environment", Andrii Soldatenko"Debugging python applications inside k8s environment", Andrii Soldatenko
"Debugging python applications inside k8s environment", Andrii SoldatenkoFwdays
 
"Subclassing and Composition – A Pythonic Tour of Trade-Offs", Hynek Schlawack
"Subclassing and Composition – A Pythonic Tour of Trade-Offs", Hynek Schlawack"Subclassing and Composition – A Pythonic Tour of Trade-Offs", Hynek Schlawack
"Subclassing and Composition – A Pythonic Tour of Trade-Offs", Hynek SchlawackFwdays
 
Take control of your SAP testing with UiPath Test Suite
Take control of your SAP testing with UiPath Test SuiteTake control of your SAP testing with UiPath Test Suite
Take control of your SAP testing with UiPath Test SuiteDianaGray10
 
Gen AI in Business - Global Trends Report 2024.pdf
Gen AI in Business - Global Trends Report 2024.pdfGen AI in Business - Global Trends Report 2024.pdf
Gen AI in Business - Global Trends Report 2024.pdfAddepto
 
"ML in Production",Oleksandr Bagan
"ML in Production",Oleksandr Bagan"ML in Production",Oleksandr Bagan
"ML in Production",Oleksandr BaganFwdays
 
Transcript: New from BookNet Canada for 2024: Loan Stars - Tech Forum 2024
Transcript: New from BookNet Canada for 2024: Loan Stars - Tech Forum 2024Transcript: New from BookNet Canada for 2024: Loan Stars - Tech Forum 2024
Transcript: New from BookNet Canada for 2024: Loan Stars - Tech Forum 2024BookNet Canada
 
Dev Dives: Streamline document processing with UiPath Studio Web
Dev Dives: Streamline document processing with UiPath Studio WebDev Dives: Streamline document processing with UiPath Studio Web
Dev Dives: Streamline document processing with UiPath Studio WebUiPathCommunity
 
Generative AI for Technical Writer or Information Developers
Generative AI for Technical Writer or Information DevelopersGenerative AI for Technical Writer or Information Developers
Generative AI for Technical Writer or Information DevelopersRaghuram Pandurangan
 
Merck Moving Beyond Passwords: FIDO Paris Seminar.pptx
Merck Moving Beyond Passwords: FIDO Paris Seminar.pptxMerck Moving Beyond Passwords: FIDO Paris Seminar.pptx
Merck Moving Beyond Passwords: FIDO Paris Seminar.pptxLoriGlavin3
 
Nell’iperspazio con Rocket: il Framework Web di Rust!
Nell’iperspazio con Rocket: il Framework Web di Rust!Nell’iperspazio con Rocket: il Framework Web di Rust!
Nell’iperspazio con Rocket: il Framework Web di Rust!Commit University
 
The Role of FIDO in a Cyber Secure Netherlands: FIDO Paris Seminar.pptx
The Role of FIDO in a Cyber Secure Netherlands: FIDO Paris Seminar.pptxThe Role of FIDO in a Cyber Secure Netherlands: FIDO Paris Seminar.pptx
The Role of FIDO in a Cyber Secure Netherlands: FIDO Paris Seminar.pptxLoriGlavin3
 
TeamStation AI System Report LATAM IT Salaries 2024
TeamStation AI System Report LATAM IT Salaries 2024TeamStation AI System Report LATAM IT Salaries 2024
TeamStation AI System Report LATAM IT Salaries 2024Lonnie McRorey
 
How to write a Business Continuity Plan
How to write a Business Continuity PlanHow to write a Business Continuity Plan
How to write a Business Continuity PlanDatabarracks
 

Recently uploaded (20)

SAP Build Work Zone - Overview L2-L3.pptx
SAP Build Work Zone - Overview L2-L3.pptxSAP Build Work Zone - Overview L2-L3.pptx
SAP Build Work Zone - Overview L2-L3.pptx
 
Hyperautomation and AI/ML: A Strategy for Digital Transformation Success.pdf
Hyperautomation and AI/ML: A Strategy for Digital Transformation Success.pdfHyperautomation and AI/ML: A Strategy for Digital Transformation Success.pdf
Hyperautomation and AI/ML: A Strategy for Digital Transformation Success.pdf
 
Scanning the Internet for External Cloud Exposures via SSL Certs
Scanning the Internet for External Cloud Exposures via SSL CertsScanning the Internet for External Cloud Exposures via SSL Certs
Scanning the Internet for External Cloud Exposures via SSL Certs
 
New from BookNet Canada for 2024: BNC CataList - Tech Forum 2024
New from BookNet Canada for 2024: BNC CataList - Tech Forum 2024New from BookNet Canada for 2024: BNC CataList - Tech Forum 2024
New from BookNet Canada for 2024: BNC CataList - Tech Forum 2024
 
WordPress Websites for Engineers: Elevate Your Brand
WordPress Websites for Engineers: Elevate Your BrandWordPress Websites for Engineers: Elevate Your Brand
WordPress Websites for Engineers: Elevate Your Brand
 
Digital Identity is Under Attack: FIDO Paris Seminar.pptx
Digital Identity is Under Attack: FIDO Paris Seminar.pptxDigital Identity is Under Attack: FIDO Paris Seminar.pptx
Digital Identity is Under Attack: FIDO Paris Seminar.pptx
 
A Deep Dive on Passkeys: FIDO Paris Seminar.pptx
A Deep Dive on Passkeys: FIDO Paris Seminar.pptxA Deep Dive on Passkeys: FIDO Paris Seminar.pptx
A Deep Dive on Passkeys: FIDO Paris Seminar.pptx
 
"Debugging python applications inside k8s environment", Andrii Soldatenko
"Debugging python applications inside k8s environment", Andrii Soldatenko"Debugging python applications inside k8s environment", Andrii Soldatenko
"Debugging python applications inside k8s environment", Andrii Soldatenko
 
"Subclassing and Composition – A Pythonic Tour of Trade-Offs", Hynek Schlawack
"Subclassing and Composition – A Pythonic Tour of Trade-Offs", Hynek Schlawack"Subclassing and Composition – A Pythonic Tour of Trade-Offs", Hynek Schlawack
"Subclassing and Composition – A Pythonic Tour of Trade-Offs", Hynek Schlawack
 
Take control of your SAP testing with UiPath Test Suite
Take control of your SAP testing with UiPath Test SuiteTake control of your SAP testing with UiPath Test Suite
Take control of your SAP testing with UiPath Test Suite
 
Gen AI in Business - Global Trends Report 2024.pdf
Gen AI in Business - Global Trends Report 2024.pdfGen AI in Business - Global Trends Report 2024.pdf
Gen AI in Business - Global Trends Report 2024.pdf
 
"ML in Production",Oleksandr Bagan
"ML in Production",Oleksandr Bagan"ML in Production",Oleksandr Bagan
"ML in Production",Oleksandr Bagan
 
Transcript: New from BookNet Canada for 2024: Loan Stars - Tech Forum 2024
Transcript: New from BookNet Canada for 2024: Loan Stars - Tech Forum 2024Transcript: New from BookNet Canada for 2024: Loan Stars - Tech Forum 2024
Transcript: New from BookNet Canada for 2024: Loan Stars - Tech Forum 2024
 
Dev Dives: Streamline document processing with UiPath Studio Web
Dev Dives: Streamline document processing with UiPath Studio WebDev Dives: Streamline document processing with UiPath Studio Web
Dev Dives: Streamline document processing with UiPath Studio Web
 
Generative AI for Technical Writer or Information Developers
Generative AI for Technical Writer or Information DevelopersGenerative AI for Technical Writer or Information Developers
Generative AI for Technical Writer or Information Developers
 
Merck Moving Beyond Passwords: FIDO Paris Seminar.pptx
Merck Moving Beyond Passwords: FIDO Paris Seminar.pptxMerck Moving Beyond Passwords: FIDO Paris Seminar.pptx
Merck Moving Beyond Passwords: FIDO Paris Seminar.pptx
 
Nell’iperspazio con Rocket: il Framework Web di Rust!
Nell’iperspazio con Rocket: il Framework Web di Rust!Nell’iperspazio con Rocket: il Framework Web di Rust!
Nell’iperspazio con Rocket: il Framework Web di Rust!
 
The Role of FIDO in a Cyber Secure Netherlands: FIDO Paris Seminar.pptx
The Role of FIDO in a Cyber Secure Netherlands: FIDO Paris Seminar.pptxThe Role of FIDO in a Cyber Secure Netherlands: FIDO Paris Seminar.pptx
The Role of FIDO in a Cyber Secure Netherlands: FIDO Paris Seminar.pptx
 
TeamStation AI System Report LATAM IT Salaries 2024
TeamStation AI System Report LATAM IT Salaries 2024TeamStation AI System Report LATAM IT Salaries 2024
TeamStation AI System Report LATAM IT Salaries 2024
 
How to write a Business Continuity Plan
How to write a Business Continuity PlanHow to write a Business Continuity Plan
How to write a Business Continuity Plan
 

10120140507004

  • 1. International Journal of Management (IJM), ISSN 0976 – 6502(Print), ISSN 0976 - 6510(Online), Volume 5, Issue 7, July (2014), pp. 44-50 © IAEME INTERNATIONAL JOURNAL OF MANAGEMENT (IJM) ISSN 0976-6502 (Print) ISSN 0976-6510 (Online) Volume 5, Issue 7, July (2014), pp. 44-50 © IAEME: http://www.iaeme.com/IJM.asp Journal Impact Factor (2014): 7.2230 (Calculated by GISI) www.jifactor.com 44 IJM © I A E M E A PERSPECTIVE OF RISK ASSESSMENT FOR PRODUCT DEVELOPMENTS IN BIOTECHNOLOGY AND PHARMACEUTICAL PRODUCTS Samaraj S. Thiyagarajan, PMP Austin, Texas, USA- 78749 ABSTRACT This paper provides an insight on risk assessment, which is a component of risk management. Risk assessment is an essential process during the product developments phase of biotechnological and pharmaceutical products. Risk management is an iterative process. It starts from project scoping and completesupon projectfinish. Basically, risk are categorized as known risks and unknown risks. Risk assessment is the first stage of the risk management followed by risk evaluation, and developing a risk management strategy to monitor and mitigate risks. Ideally in any project scenario, risks will be high during the project initiation phase and reduce as project enters into later stages. This paper discusses the process of risk assessment for each phase of the developmental stage of new products. In summary, for successful execution of projects, product development needs adequate risk assessment strategy. Keywords: New Product Development, Risk Assessment, Biotechnology, Pharmaceutical. INTRODUCTION New product introductions are the life line of any business. A successful business model will spread its roots only when new products are commercialized and sustained without any failures. The long term competitiveness of a business relies on the company’s new product development capabilities (SC Wheelwright, KB Clark, 1992). Any new product commercialization process involves numerous risks. It is imperative to understand the project risks and its management, past research indicates there is only six out ten products were successful after commercialization (Garry, 1997). Each new product introduction has its own unique sets of risks. New product launches are resource intensive and has prolonged timelines, especially, in the pharmaceutical and biotech industry. This consequently translates into high development costs, which involves facility, instruments, machinery, and miscellaneous (Kahn, 2002).
  • 2. International Journal of Management (IJM), ISSN 0976 – 6502(Print), ISSN 0976 - 6510(Online), Volume 5, Issue 7, July (2014), pp. 44-50 © IAEME 45 Developing a risk management involves planning, and developing quality standards, and quality mission of the organization. Systems and practices that guides the project team to make a clear and consistent decisions and communications for the management (FDA, 2004). An important aspect in any product life cycle is product design. Developing a design based on QbD approach will significantly reduce the risk. Risk management entails a comprehensive understanding of product design to manufacturing, reaching the customer and use by the customer. Many factors that can influence the safety, and efficacy of a product. An efficient project team will need to characterize the aspects of the product in every angle. It is critical to have a risk management plan that is tailored to the particular project. In a product development and transfer, with so many tasks and deliverables need to occur coherently, the project team need to have significant emphasis on identifying, assessing, and evaluating the risks at every stage. A solid risk management plan will help the team to anticipate issues, and proactively address them. It helps the team to have a smooth execution to reach the designated goal of efficient and successful product development. The objective of this paper is to provide a detail risk management process for commercializing new biotechnology and pharmaceutical products. Based on the risk assessment, the project team will then need to draft a detail mitigation strategy, which itself is a separate process. The team needs to establish several high level categories for risk identification. Each identified risk will then need to be categorized as project risk, or a particular event associated in a given phase of the project. PROJECT SCOPE A crucial phase of any project is the project scoping. Successful scoping includes understanding the risks. Critical risks include but not limited to the following aspects: Project team at certain times may not clearly define the goals of the proposed project, which may be from inadequate scope development that results in conflicting agendas (Atkinson et.al, 2006). Failure to translate the customer/user requirements and product requirements to the scope of the project often lead to product failures. Often project teams falls short of drafting a complete and fully vetted business plan, also called as aggregated project plan (SC Wheelwright, KB Clark, 1992). In several instances, oversight of management in terms project scope and project execution lead to issues in the project. Failure of the team to clearly identify in scope/out of scope of the project to achieve its indented purpose.A project team can group these risks as project risks. STAKEHOLDER Stakeholder identification and understanding their needs is required for successful project execution and completion. The concept of stakeholder management is intended to devise methods to manage a group of decision makers or parties that may positively or negatively impact the project or impacted by the project. Their relationships are crucial to success of product launch (R. Edward Freeman and John McVea). Significant issues arise when stakeholders and their needs were not correctly identified. Team need to identify risks associated with the following aspects. If the project team failed to identify all the stakeholders during the project scoping, it will result in project facing significant delays or scope creep. Once stakeholders are identified project team needs to identify the stakeholder’s interest and their influence on the new product development project. Failure to identify interest and influence can be as damaging as other risks. Risks could also be failure to identify the hidden needs of both internal and external stakeholders. This had resulted in offsetting the project timeline due unplanned works that needs to be performed. Disconnect between the stakeholders and project team poses significant risk. Regulatory agencies like FDA, USDA and other international organizations will
  • 3. International Journal of Management (IJM), ISSN 0976 – 6502(Print), ISSN 0976 - 6510(Online), Volume 5, Issue 7, July (2014), pp. 44-50 © IAEME have a significant influence, failure to understand their requirementswill be costly and challenging for the projects. Stakeholder concepts were evolved and their influence had recently been embedded in the management thinking (Ronald K, 1997). 46 The team needs to identify and assess these risks as project risk, and they are characterized in the decision to commercialize phase. It is essential to look for any gaps in the risk assessment section and reassess the risks to make surethe team is covering this critical risk. PRODUCT REQUIREMENTS In order to achieve successful commercialization, the team needs to undergo an extensive risk assessment and management regardingproduct requirements. The requirements for considering the needs of product specification based on the information that has been understood from the customers and key stakeholders (Alison McKay, et, al, 2001) Sometime combing the risk assessment for voice of the customer and the product requirements together is crucial. In many instance products had failed at the hands of the customers. The fundamental reason for this is incomplete understanding the of product requirements based on the customer requirements. Risk of incomplete coordination of customer requirements to product requirements will be one of the failure mode. Also, trying to address many facets of customer requirement, some of the NPI had issues in executing transfer to manufacturing for this type of products. Failure to address safety and handling requirements. Another crucial document that is invariably used is Product requirement document, and failure to capture all the requirements in the PRD. Most pharmaceutical products require connecting product requirements to traceability matrix. A great way to effectively eliminate any issues that were discussed above and managing an efficient product development is QFD – Quality Functional Deployment (Kurt Matzlera, et.al, 1998). These risks are both categorized as project and product risks. Close attention to these risks is warranted because they may have a significant effect on the manufacturing. PILOT STUDIES In any product development, irrespective of industry, risks were basically identified by developing prototypes. Another critical phase in the commercialization process involves conducting pilot studies. Since pilot studies are used to develop, and characterize the product, and to establish adequate design controls.These are essentially grouped under product risks. The pilot study helps to identify the risks on the following: Specification Development: In any new product development, specification development is a significant task (FDA, guidance). It is important to assess risks extensively on this process. Several projects failed to achieve its long term goal due to inadequate and inappropriate specifications. Project team uses several approachto assess if there is any risks associated with specification developed pilot studies are setup Risks were identified from the pilot studies, DOE, guard branding, and design space studies.Design of Experiments – a great tool for understanding and mitigating any specifications based risks. This is done by analyzing the interaction between critical factors such as chemicals, mixing, pH, solubility, and their impact on the specification. Certain risks also need to be analyzed for tolerance of certain impurities from raw materials on the specification.The proposed specification may not address customer requirements. This is a significant risk that leads to numerous customer complaints.Some new product development process lacks the analytical method/quality control method development. Even the developed method may not be optimized for addressing calling good vs. bad lots.
  • 4. International Journal of Management (IJM), ISSN 0976 – 6502(Print), ISSN 0976 - 6510(Online), Volume 5, Issue 7, July (2014), pp. 44-50 © IAEME 47 Raw Material requirements: Raw material characterizations are crucial for developing specifications and consistent product performance. This is a critical process, any issues arises in this may results in product recalls and compliance issues. Risks were identified on the quality of the raw materials. (One common supplier’s claim is that the raw materials are 99% pure. The risk of combination effect of 1% impurities from five or six raw materials used to make a product. More prevalent risk is failure to detect substandard materials during incoming inspection (Trivedi et al, 2011). More frequent product failures comes from risk involving contamination including microbial, chemical and other materials. Recently several nations have imposed ban on certain materials and team need to assess the risks if those materials will be part of the product and how it may impact the marketing in those countries. Assessment need to be made for stability of the raw materials, and handling and storage of raw materials. Process Development: Based on pilot studies, risks assessment for process development is done. The project team assesses the risks through process characterization, design verification and validation. Identified risks includetranslating the product requirements to process requirements. The risk assessment should include whether the developed process will consistently produce the products with all requirements and specifications. Assessing the risks of not understanding the flow requirements in operations/ manufacturing. Risks need to be assessed onconverting from pilot build to full scale build using the developed process. A critical failure of products during manufacturing is developed process not able to withstand minor variations in raw material, operator, equipment, etc. The project team has to assess the risks involving long term and short term process capabilities (CPK). Analytical/Quality control Method development: Once a manufacturing process was designed, team identifies appropriate quality sampling and testing method. More emphasis for developing testing at adequate steps along the process, and establishing the final release criteria are mandatory. Project team requires assessing the risk involving failure of the developed test method to take into consideration of any variation in equipment, and operator to operator.Risks from either excessive testing, or too few testing. Product performance risk from method not characterized adequately, resulting in frequent failures in the manufacturing.Risk of failure of the testing process that cannot identify good vs. bad lots. This type of risk is always ranked high because this may lead to a flawed product passing the test and being shipped to the customer, failing at the customer’s hand. Alternatively, test may incorrectly classify a good lot as a bad, and disposition to scrap, resulting in revenue loss. Design Verification and Validation: Once the pilot lots are completed and process identified, a plan is created to verify and validate the design and the design controls established. Risk assessments performed during the 3P process as well. Design FMEA will be conducted. Some common risks that team may identify are: Failure of the validation to provide any conclusive results.Risk of failure of the validation studies. Design Controls: With FDA giving more emphasis on having adequate design controls in new product development ((FDA, guidance).Based on the pilot lots, and validation, assessing risks related to design control are more critical. The whole process of risk assessment and chances for improvement are done through conducting the 3P process. Risks need to be identified from inadequate or not so robust design controls in the process. Risks may arise from product liability from inadequate design controls.
  • 5. International Journal of Management (IJM), ISSN 0976 – 6502(Print), ISSN 0976 - 6510(Online), Volume 5, Issue 7, July (2014), pp. 44-50 © IAEME 48 Design FMEA: The final stage of the risk assessment is to combine all previously identified risks and entered them in the risk register (Susan. P. et.al, 2003), project team need to conduct an extensive design FMEA to understand the failure mode of each identified risks and its impact on the products performance, safety and efficacy. Ranking need to be based on the severity, occurrence and detection of risks. RPN calculated and risks need to be prioritized based on the several factors including RPN number, threat to success of the project and for the upstream manufacturing. (Figure 1).
  • 6. International Journal of Management (IJM), ISSN 0976 – 6502(Print), ISSN 0976 - 6510(Online), Volume 5, Issue 7, July (2014), pp. 44-50 © IAEME 49 CONCLUSIONS Risk assessment is an integral part of any project; especially, more crucial during the product development stage in a new product commercialization process. Several product development projects that do not have adequate risk assessment process had undergone numerous distress in the aspects of overrunning project cost, delayed project schedule, and increased quality issues down the road in the manufacturing process. In a biotech/pharmaceutical environment, planning suitable process for risk assessment is important, considering the longer period of development phase. Performing risk assessment during the upfront phase will significantly reduce the project cost. For any project manager, knowing the known risks and planning contingency response for unknown risks put him as well as the project at better position for success. REFERENCE 1. Griffin, A. (1997). PDMA Research on New Product Development, Practices: Updating Trends and Benchmarking Best Practices. Journal of Product Innovation Management 14(6):429–458. 2. Gary E. Blau, Joseph F. Pekny, Vishal A. Varma and Paul R. BunchManaging a Portfolio of Interdependent New Product Candidates in the Pharmaceutical Industry, Journal of Product Innovation Management, Volume 21, Issue 4, pages 227–245, July 2004. 3. Kahn, K.B. (2002). An Exploratory Investigation of New Product Forecasting Practices. Journal of Product Innovation Management, 19(2):133–143. 4. Food and Drug Administration. Final Report on Pharmaceutical cGMPs for the 21st Century – ARisk Based Approach, http://www.fda.gov/ cder/ gmp/ gmp 2004/ GMP_ final report 2004.htm. 5. Atkinson, Roger, Crawford, Lynn and Ward, Stephen (2006) Fundamental uncertainties in projects and the scope of project management. International Journal of Project Management, 24, (8), 687-698. 6. SC Wheelwright, KB Clark – 1992, Creating project plans to focus product development, mis.postech.ac.kr. 7. R. Edward Freeman and John McVea, A Stakeholder Approach to Strategic management, Handbook of Strategic Management, Oxford: Blackwell Publishing. 8. Ronald K. Mitchell, Bradley R. Agle and Donna J. Wood, Toward a Theory of Stakeholder Identification and Salience: Defining the Principle of Who and What Really Counts, The Academy of Management Review, 1997, Page 853 of 853-886. 9. Alison McKay, Alan de Pennington, Jim Baxter, Requirements management: a representation scheme for product specifications, Computer-Aided Design 33 (2001) 511±520. 10. Kurt Matzlera, Hans H. Hinterhuber, How to make product development projects more successful by integrating Kano's model of customer satisfaction into quality function deployment, Technovation, Volume 18, Issue 1, January 1998, Pages 25–38. 11. Bhagyesh Trivedi, Quality By Design (Qbd) In Pharmaceuticals, International Journal of Pharmacy And Pharmaceutical Sciences, Vol 4, Issue 1, 2012. 12. Susan P. Felter, Cindy A. Ryan,a David A. Basketter, Nicola J. Gilmour, and G. Frank Gerbericka, Application of the risk assessment paradigm to the induction of allergic contact dermatitis, Regulatory Toxicology and Pharmacology 37 (2003) 1–10. 13. Guidance for Industry Q8 (R2) - Food and Drug Administration. 14. W. L. Pearn K. S. Chen , A Practical Implementation Of The Process Capability Index Cpk, Quality Engineering , Volume 9, Issue 4, 1997.
  • 7. International Journal of Management (IJM), ISSN 0976 – 6502(Print), ISSN 0976 - 6510(Online), Volume 5, Issue 7, July (2014), pp. 44-50 © IAEME 50 15. Neeti Jain, Jimmy Kansal, AshwagoshaGanju, Anil Khurana, PramodSatyawali, 2013. The Effect of Implementation of ISO 9001:2008 QMS on the Organizational Performance in an RD Establishment International Journal of Management (IJM), Volume: 4, Issue: 1, Pages: 47 - 55, ISSN 0976-6510 (Online). 16. Neha Kalra and Anoop Pant, 2013. TQM-A Management Philosophy in Indian Automobile Industry (NCR). International Journal of Management (IJM).Volume:4, Issue: 6, Pages: 12-20. 17. Anil Khurana, Prof. Jamal A Farooquie, Dr. Manjit Singh and Jimmy Kansal, 2013. Effect of Iso 9001 Quality Management Systems Certification on the Performance in Indian Defence RD Organisation. International Journal of Management (IJM). Volume: 4, Issue: 6, Pages: 61-76, ISSN 0976-6510 (Online). 18. Er. Amit Bijon Dutta and Dr. M. J. Kolhatkar, 2014. Study of Risk Management in Construction Projects. International Journal of Management (IJM). Volume: 5, Issue: 6, Pages: 32-39, ISSN 0976-6510 (Online).