SlideShare a Scribd company logo
1 of 7
Download to read offline
B. V. R. Uday Kiran et al Int. Journal of Engineering Research and Applications www.ijera.com
ISSN: 2248-9622, Vol. 4, Issue 6(Version 4), June 2014, pp.41-47
www.ijera.com 41 | P a g e
Under Ground Cable Sizing Using MAT LAB
B. V. R. Uday Kiran1
, A. V. Raghava Ram2
, K. Jitendra3
Abstract
The main theme of this paper is to explain the procedure to calculate the cross sectional area of a conductor of
an underground cable for a specified power & voltage ratings. This paper will also explain one of the simplest
ways to calculate the cross section. In this paper we analyzed various factors that effect in deciding the ampacity
of the conductor. We developed a Mat lab code to find the cross sectional area by including some of the
parameters and also the voltage drop , maximum permissible voltage drop for that size of the conductor and also
the number of runs of the cable that are to be laid.
Key words: Conduction cross section, derating factor, XLPE cable, MATLAB
I. INTRODUCTION
CABLE (or conductor) sizing is the process of
selecting appropriate sizes for electrical power cable
conductors. Cable sizes are typically described in
terms of cross-sectional area, American Wire Gauge
(AWG) or kcmil, depending on geographic region. In
this we have taken CCI (Cable Corporation of India)
standards into consideration for calculating cable size.
The purpose of Conductor and Cable Sizing is to
determine the best to transport a given current,
determined by voltage, through an insulated
conductive material. Conductor size must be
calculated by taking factors like distance, raceways
and environmental conditions into account which
includes minimizing heat generated from resistance or
impedance of the cable itself.
Proper sizing of an electrical (load bearing) cable
ensures that the cable can:
1. Operate continuously under full load without
being damaged
2. Withstand the worst short circuit currents flowing
through the cable
3. Provide suitable voltage to the load (and avoid
excessive voltage drops)
4. Ensures operation of protective devices during an
earth fault
II. PROBLEM STATEMENT
Consider a 3-phase, 11 kV substation, from which
a 1 MVA power is to be transferred to a load which is
situated at certain distance from the substation,
through a 3 core cable. This article gives the sizing of
a cable in a generalized way i.e., from a substation at
any voltage level transferring a certain power to the
load.
III. GENERAL METHODOLOGY
All cable sizing methods more or less follow the
same basic four step process:
1. Gathering data about the cable, its installation
conditions, and the load that it has to carry.
2. Determine the minimum cable size based on
continuous current carrying capacity.
3. Determine the minimum cable size based on
voltage drop considerations
4. Select the cable size based on the highest of the
sizes calculated in step 2 and 3.
Step 1:
The first step is to collate the relevant
information that is required to perform the sizing
calculation
Load Details
 The type of load to which cable is connected i.e.,
feeder or motor (This article generally deals with
feeder type of cables).
 Three phase, single phase or DC (here 3-phase) .
 System / source voltage at which cables is
operating.
 Full load current (A) - or calculate this if the load
is defined in terms of power (kW) .
 Desired full load power factor (p.u) at which
system should operate.
 Distance / length of cable run from source to load
.
This length should be as close as possible to the
actual route of the cable and include enough
contingency for vertical drops / rises and
termination of the cable tails.
Cable Construction:
The basic characteristics of the cable's physical
construction, which includes:
 Material of conductor (normally copper or
aluminum).
 Shape of conductor (like circular or shaped).
 Type of conductor (like stranded or solid).
 Conductor surface coating (like plain (no
coating), tinned, silver or nickel ).
 Insulation type (mostly preferred PVC,
XLPE, EPR )
RESEARCH ARTICLE OPEN ACCESS
B. V. R. Uday Kiran et al Int. Journal of Engineering Research and Applications www.ijera.com
ISSN: 2248-9622, Vol. 4, Issue 6(Version 4), June 2014, pp.41-47
www.ijera.com 42 | P a g e
 Number of cores - single core or multicore
(2-core ,3-core, etc..,).
Installation Conditions:
How the cable will be installed:
 Installation / arrangement - e.g. for
underground cables, is it directly buried or buried
in conduit? for above ground cables, is it installed
on cable tray / ladder, against a wall, in air, etc.
 Ambient or soil temperature of the installation
site
 Cable grouping, i.e. the number of cables that are
grouped together.
 Cable spacing, i.e. whether cables are installed
touching or spaced from each other.
 Soil thermal resistivity.
 Depth of laying.
 For single core three-phase cables, are the cables
installed in trefoil or laid flat?
Note:350
C ground temperature for cables directly
buried in ground, the depth of laying being 900 mm
and soil thermal resistivity being 1500
C cm/W is
assumed.
STEP 2:
The substation rating from which cable is to be
sized is to be given (V in 3-phase) and the power (in
MW or MVA) that is to be transferred through this
cable (say P) is to be given. The current (I) passing
through the cable is calculated as [5]
(1)
(2)
Current at 110% loading (Ifl) is given as
Let, Ifl = I (1.1) (3)
This is here considered in order to ensure that
cable can withstand over loading up to some extent
which prevents damage of the cable and the electrical
equipment (load) connected to the delivering end of
the cable. This value can be taken higher for more
safety but it increases the losses and also the amount
of material used which is waste of economy.
Current flowing through a cable generates heat
through the resistive losses in the conductors,
dielectric losses through the insulation and resistive
losses from current flowing through any cable screens
/ shields and armouring.
The component parts that make up the cable (e.g.
conductors, insulation, bedding, sheath, armour, etc.)
must be capable of withstanding the temperature rise
and heat emanating from the cable. The current
carrying capacity of a cable is the maximum current
that can flow continuously through a cable without
damaging the cable's insulation and other components
(e.g. bedding, sheath, etc.). It is sometimes also
referred to as the continuous current rating or
ampacity of a cable.
Cables with larger conductor cross-sectional areas
have lower resistive losses and are able to dissipate
the heat better than smaller cables. Therefore we can
say that 16 mm2
cables will have a higher current
carrying capacity than a 4 mm2
cables.
Base Current Ratings
International standards and manufacturers of
cables will quote base current ratings of different
types of cables in tables such as the one shown
below. The tables given below are given by Cable
Corporation of India (CCI).
TABLE I: ALUMINIUM COND. 3 CORE
CABLES FROM 3.3 kV TO 33 kV (E) [1]
Conductor
Cross-
Section
3.3 kV to
11(UE)
Direct in
ground
22 kV to
33 (E)
Direct in
ground
Sq.mm Amps Amps
25 95
35 110 110
50 130 130
70 160 160
95 190 190
120 215 210
150 245 240
185 275 270
240 320 310
300 360 350
400 410 400
TABLE II: COPPER COND. 3 CORE CABLES
FROM 3.3kV TO 33kV (E) [1]
Conductor
Cross-
Section
3.3kV to
11(UE)
Direct in
ground
22kV to 33(E)
Direct in
Ground
Sq.mm Amps Amps
25 120
35 145 145
50 170 165
70 205 205
95 245 240
120 280 275
150 310 305
B. V. R. Uday Kiran et al Int. Journal of Engineering Research and Applications www.ijera.com
ISSN: 2248-9622, Vol. 4, Issue 6(Version 4), June 2014, pp.41-47
www.ijera.com 43 | P a g e
185 350 345
240 405 395
300 455 445
400 510 505
Installed Current Ratings
When the proposed installation conditions differ
from the base conditions, derating (or correction)
factors can be applied to the base current ratings to
obtain the actual installed current ratings.
International standards and cable manufacturers
will provide derating factors for a range of installation
conditions, for example ambient / soil temperature,
grouping or bunching of cables, soil thermal
resistivity, etc. The installed current rating is
calculated by multiplying the base current rating with
each of the derating factors, i.e.
[3]
Id=It * DF (4)
Where Id the installed current rating (A)
It is the current rating (A)
DF are the product of all the derating
factors
The various factors that cause derating of current
carrying capacity of a cable are ground thermal
resistivity, grouping of cables, ground temperature and
air temperature. The values of derating factors for the
above mentioned parameters for some standard values
are:
TABLE III: GROUND THERMAL RESISTIVITY
[2]
Thermal Resistivity
(K.m/W)
Direct in ground
1,0
1,2
1,5
2,0
2,5
1,08
1,00
0,93
0,83
0,78
TABLE IV: GROUPING OF CABLES [2]
No of
cables
in
Group
Direct in Ground
Axial Spacing (mm)
Touching 150 300 450 600
2
3
4
5
6
0.81
0.70
0.63
0.59
0.55
0.87
0.78
0.74
0.70
0.67
0.91
0.84
0.81
0.78
0.76
0.93
0.87
0.86
0.83
0.82
0.94
0.90
0.89
0.87
0.86
TABLE V: GROUND TEMPERATURE [2]
Maximum
Conductor
Temp (ºC)
Ground temperatures (ºC)
25 30 35 40 45 50
70(PVC) 1.00 0.95 0.90 0.85 0.80 0.70
90(XLPE) 1.00 0.96 0.92 0.88 0.82 0.76
TABLE VI: AIR TEMPERATURE [2]
Maximum
conductor
temp(ºC)
Air temperature (ºC)
30 35 40 45
70(PVC) 1.00 0.94 0.87 0.79
90(XLPE) 1.00 0.95 0.89 0.84
For example, suppose a cable had an ambient
temperature derating factor 0.94 and a group derating
factor of 0.9 then the overall derating factor will be
(0.94*0.9) which is approximately equal to 0.855.
This derating value is taken in the code just as
reference but this can vary depending on the operating
and environmental conditions (which can also be
changed in the Mat lab code).
a) Cable Selection
When sizing cables for feeders, the cross-section
of cables is also typically selected to protect the cable
against damage from thermal overload. The cross-
section of cable must therefore be selected to exceed
the full load current, but not exceed the cable's
installed current rating, i.e. this inequality must be
met:
Id ≥ Ifl (5)
Here if this inequality is not satisfied with any of
the values given in the Table 1 or Table 2(according to
the material chosen) then the base current rating of the
cable is multiplied by an integral factor „r‟ (where
r=1,2,3,…) i.e., the current carrying capacity of the
cable is increased by laying it in „r‟ runs.
r(Id)≥Ifl (6)
STEP 3:
A cable's conductor can be seen as an impedance
and therefore whenever current flows through a cable,
there will be a voltage drop across it, which can be
derived from Ohm‟s Law (i.e. V = IZ). The voltage
drop will depend on two things:
 Current flow through the cable – the higher
the current flow, the higher the voltage drop
 Impedance of the conductor – the larger the
impedance, the higher the voltage drop
The impedance of the cable is a function of the
cable size (cross-sectional area) and the length of the
cable. Most cable manufacturers will quote a cable‟s
resistance and reactance in Ω/km. The following
typical cable impedances given by CCI (Cable
B. V. R. Uday Kiran et al Int. Journal of Engineering Research and Applications www.ijera.com
ISSN: 2248-9622, Vol. 4, Issue 6(Version 4), June 2014, pp.41-47
www.ijera.com 44 | P a g e
Corporation of India) can be used in the absence of
any other data.
TABLE VII RESISTANCE VALUES OF
3CORE CABLES [2]
Condu
ctor
Cross
Section
Max
D.C
Resistan
ce At
20˚C
Approx
A.C
Resistan
-
ce
At 90˚C
Max
D.C
Resist
an-
ce
At
20˚C
Approx
A.C
Resistan
-ce
At 90˚C
Aluminum Copper
Sq.mm Ohm/k
m
Ohm/k
m
Ohm/
km
Ohm/k
m
25 1.200 1.5500 0.727
0
0.9260
35 0.8680 1.1200 0.524
0
0.6680
50 0.6410 0.8280 0.387
0
0.4930
70 0.4430 0.2720 0.268
0
0.3410
95 0.3200 0.4140 0.193
0
0.2460
120 0.2530 0.3270 0.153
0
0.1950
150 0.2060 0.2660 0.124
0
0.1580
185 0.1640 0.2120 0.099
1
0.1260
240 0.1250 0.1620 0.075
4
0.0961
300 0.1000 0.1290 0.060
1
0.0766
400 0.0778 0.1010 0.047
0
0.0600
TABLE VIII REACTANCE OF 3CORE CABLE
[2]
Conduct
or
Cross
Section
Reactance of 3core Cables conforming to
IS:7098(pt-2)-1985
Approx Reactance at 50Hz
3.8/6.6
Kv
6.6/6.6
&
6.35/1
1
Kv
11/11
Kv
12.7/2
2
Kv
19/33
Kv
25 0.126 0.133 0.145 --- ---
35 0.12 0.126 0.138 0.141 ---
50 0.144 0.118 0.129 0.132 0.146
70 0.107 0.116 0.124 0.125 0.138
95 0.102 0.107 0.116 0.119 0.13
120 0.0977 0.102 0.112 0.114 0.125
150 0.0953 0.0994 0.108 0.111 0.122
185 0.0926 0.0969 0.105 0.107 0.118
240 0.0902 0.0936 0.102 0.104 0.113
300 0.09 0.0926 0.0999 0.102 0.111
400 0.0872 0.0886 0.0954 0.0969 0.106
Calculating Voltage Drop
For AC systems, the method of calculating voltage
drops based on load power factor is commonly used.
Full load currents are normally used, but if the load
has high startup currents (e.g. motors), then voltage
drops based on starting current (and power factor if
applicable) should also be calculated.
For a three phase system: [3]
(7)
Where
V3ø is the three phase voltage drop (V)
I=Ifl nominal full load current as applicable (A)
Rc is the ac resistance of the cable (Ω/km)
Xc is the ac reactance of the cable (Ω/km)
cos ø is the load power factor (pu)
L is the length of the cable (m)
For a single phase system: [3]
(8)
Where V1ø is the single phase voltage drop (V)
I is the nominal full load current as applicable
(A)
Rc is the ac resistance of the cable (Ω/km)
Xc is the ac reactance of the cable (Ω/km)
cos ø is the load power factor (pu)
L is the length of the cable (m)
B. V. R. Uday Kiran et al Int. Journal of Engineering Research and Applications www.ijera.com
ISSN: 2248-9622, Vol. 4, Issue 6(Version 4), June 2014, pp.41-47
www.ijera.com 45 | P a g e
For a DC system:[3]
(9)
Where
Vdc is the dc voltage drop (V)
I is the nominal full load current as applicable
(A)
Rc is the dc resistance of the cable (Ω/km)
L is the length of the cable (m)
It is customary for standards (or clients) to specify
maximum permissible voltage drops, which is the
highest voltage drop that is allowed across a cable. If
your cable exceeds this voltage drop, then a larger
cable size should be selected.
In general, most electrical equipment will operate
normally at a voltage as low as 80% nominal voltage.
For example, if the nominal voltage is 230VAC, then
most appliances will run at >184VAC. Cables are
typically sized
for a more conservative maximum voltage drop, in the
range of 5 – 10% at full load.
The following table give the maximum
permissible voltage drop that can allowed while
current is flowing in the cable. These standards are
given by CCI.
TABLE IX ESTIMATED VOLTAGE DROP [2]
Conduct
or
Cross-
section
Estimated Voltage Drop for XLPE
Aluminum conductor armored
3-Core Cables
Voltage Drop V/km/A
3.8/6.
6KV
6.6/6.6
&
6.35/11
KV
11/1
1
KV
12.7/2
2 KV
19/3
3K
V
25 2.67 2.67 2.67 --- ---
35 1.94 1.94 1.94 1.94 ---
50 1.44 1.44 1.44 1.44 1.44
70 1.00 1.00 1.01 1.01 1.44
95 0.70 0.74 0.74 0.74 0.74
120 0.56 0.59 0.60 0.60 0.60
150 0.48 0.49 0.49 0.49 0.50
185 0.40 0.40 0.41 0.41 0.44
240 0.30 0.32 0.33 0.33 0.32
300 0.26 0.27 0.28 0.28 0.29
400 0.21 0.23 0.24 0.24 0.25
For a cable to be selected it should not only satisfy the
inequality Id ≥ Ifl, but also should not exceed its
permissible voltage drop i.e.,
VD ≤ VDt (10)
Where
VD is the calculated voltage drop
VDt is the voltage drop taken according to
Table 5 with respect to the corresponding
cable size selected that satisfies the current
inequality (used in Mat lab code)
Note: Here voltage drop calculation is done in
V/Km/A i.e., the equation for voltage drop calculation
for 3 phase system is rewritten as
(11)
Where „r‟ is the no: of runs
STEP 4:
The size of the cable which satisfies full load current
inequality and voltage drop inequality is selected for
laying.
Alternatively, the size of the cable can be
calculated using Mat lab. The flow chart below
explains how the Mat lab code [4] code calculates the
size of the cable for desired voltage and power rating
at a desired power factor.
B. V. R. Uday Kiran et al Int. Journal of Engineering Research and Applications www.ijera.com
ISSN: 2248-9622, Vol. 4, Issue 6(Version 4), June 2014, pp.41-47
www.ijera.com 46 | P a g e
Fig.1 Flowchart for calculating cable sizing
IV. RESULT
These are the two results we have obtained by
executing the mat lab code.
1. ENTER BASIC CABLE SPECIFICATIONS
Enter 1 for copper or 2 for aluminium: 1
Enter nominal load voltage (3.3kV or 6.6kV or
11kV or 22kV 0r 33kV) only: 33
Enter full load power factor: 0.8
Enter power in MW: 22
 OUTPUT
Current in the cable = 481.1252
Full load current = 529.237
Derating factor = 0.8550
Voltage drop in the cable = 0.1729
Maximum permissible voltage drop taken from
standards = 0.4900
REQUIRED PARAMETERS
Required cross section of the cable = 150
Number of runs: r = 2
Note:
[Current: amps; voltage drop: volts; crossection: mm]
2. ENTER BASIC CABLE SPECIFICATIONS
Enter 1 for copper or 2 for aluminum: 2
Enter nominal load voltage (3.3kV or 6.6kV or 11kV
or 22kV 0r 33kV) only: 11
Enter full load power factor: 0.85
Enter power in MW: 8.5
 OUTPUT
Current in the cable = 524.8639
Full load current = 577.3503
Derating factor = 0.8550
Voltage drop in the cable = 0.1405
Maximum permissible voltage drop taken from
standards =
0.2800
REQUIRED PARAMETERS
Required cross section of the cable = 300
Number of runs: r = 2
Note:
[Current: amps; voltage drop: volts; crossection: mm]
V. SCREEN SHOTS
1. Matlab output screen shots ( copper cable)
B. V. R. Uday Kiran et al Int. Journal of Engineering Research and Applications www.ijera.com
ISSN: 2248-9622, Vol. 4, Issue 6(Version 4), June 2014, pp.41-47
www.ijera.com 47 | P a g e
2. Matlab output screen shots (Aluminum cable)
VI. CONCLUSION
We have discussed a novel method by which we can
estimate the approximate size of the cable considering
various effects that effect the ampacity of the cable.
We have discussed a simplified approach for
calculating the size using mat lab coding there by
reducing human effort greatly. In future we would like
to extend this program in order to include other
parameters which effect the ampacity and also to
apply this approach for other different cables.
REFERENCES
[1] Tropothen-X cables: Cable Corporation of
India Ltd.
[2] R. (Dick) Hardie, Aberdare Cables (Pty) Ltd:
“Electric Power Cables-Whatever Happened to
the Factor of Safety?”
[3] Stephen W. Fardo, Dale R. Patrick:”Electrical
Power Systems Technology: 3rd
Edition”.
[4] Stephen. J.Chapman: “MATLAB Programming
for engineers, 4th Edition“
[5] J.B.Gupta: “Electrical Power Systems”, 3rd
edition.
[6] Ossama E. Gouda, Adel Z. El Dein, Ghada
M. Amer: “Improving the Under-Ground
Cables Ampacity”, Proceedings of the 14th
International Middle East Power Systems
Conference (MEPCON‟10), Cairo University,
Egypt, Paper ID 110.

More Related Content

What's hot

Extra High Voltage Underground Power Cable
Extra High Voltage Underground Power CableExtra High Voltage Underground Power Cable
Extra High Voltage Underground Power CableLeonardo ENERGY
 
Power system slide notes
Power system slide notesPower system slide notes
Power system slide notesmichaeljmack
 
Analysis of Stranded Multi-Conductor Cable in Multilayered Dielectric Media
Analysis of Stranded Multi-Conductor Cable in Multilayered Dielectric MediaAnalysis of Stranded Multi-Conductor Cable in Multilayered Dielectric Media
Analysis of Stranded Multi-Conductor Cable in Multilayered Dielectric MediaJimmi James
 
DISTRIBUTION OF ELECTRIC FIELD ANALYSIS IN 36 KV ROOF TOP BUSHING BY USING FE...
DISTRIBUTION OF ELECTRIC FIELD ANALYSIS IN 36 KV ROOF TOP BUSHING BY USING FE...DISTRIBUTION OF ELECTRIC FIELD ANALYSIS IN 36 KV ROOF TOP BUSHING BY USING FE...
DISTRIBUTION OF ELECTRIC FIELD ANALYSIS IN 36 KV ROOF TOP BUSHING BY USING FE...Journal For Research
 
Analysis and Design of Transmission Tower
Analysis and Design of Transmission Tower Analysis and Design of Transmission Tower
Analysis and Design of Transmission Tower IJMER
 
Capacitance of the cables
Capacitance of the cablesCapacitance of the cables
Capacitance of the cablesRahim92
 
Design of 230 kV Twin Bundle Double Circuit Overhead Transmission Line
Design of 230 kV Twin Bundle Double Circuit Overhead Transmission LineDesign of 230 kV Twin Bundle Double Circuit Overhead Transmission Line
Design of 230 kV Twin Bundle Double Circuit Overhead Transmission Lineijtsrd
 
An analytical model for the current voltage characteristics of GaN-capped AlG...
An analytical model for the current voltage characteristics of GaN-capped AlG...An analytical model for the current voltage characteristics of GaN-capped AlG...
An analytical model for the current voltage characteristics of GaN-capped AlG...IJECEIAES
 
ANALYSIS OF SMALL-SIGNAL PARAMETERS OF 2-D MODFET WITH POLARIZATION EFFECTS F...
ANALYSIS OF SMALL-SIGNAL PARAMETERS OF 2-D MODFET WITH POLARIZATION EFFECTS F...ANALYSIS OF SMALL-SIGNAL PARAMETERS OF 2-D MODFET WITH POLARIZATION EFFECTS F...
ANALYSIS OF SMALL-SIGNAL PARAMETERS OF 2-D MODFET WITH POLARIZATION EFFECTS F...VLSICS Design
 
CTC Global - Economic & Environmental Impact of Power Line Loss Reductions
CTC Global - Economic & Environmental Impact of Power Line Loss ReductionsCTC Global - Economic & Environmental Impact of Power Line Loss Reductions
CTC Global - Economic & Environmental Impact of Power Line Loss ReductionsDave Bryant
 
Electrical properties of insulating materials under VLF voltage
Electrical properties of insulating materials under VLF voltageElectrical properties of insulating materials under VLF voltage
Electrical properties of insulating materials under VLF voltagePower System Operation
 
Analysis-And-Design-Of-220kv-Transmission-Line-Tower-In-Different-Zones-I-&-V...
Analysis-And-Design-Of-220kv-Transmission-Line-Tower-In-Different-Zones-I-&-V...Analysis-And-Design-Of-220kv-Transmission-Line-Tower-In-Different-Zones-I-&-V...
Analysis-And-Design-Of-220kv-Transmission-Line-Tower-In-Different-Zones-I-&-V...Deepak Saxena
 

What's hot (18)

Ijetr011742
Ijetr011742Ijetr011742
Ijetr011742
 
Extra High Voltage Underground Power Cable
Extra High Voltage Underground Power CableExtra High Voltage Underground Power Cable
Extra High Voltage Underground Power Cable
 
High voltage underground cables
High voltage underground cablesHigh voltage underground cables
High voltage underground cables
 
Power system slide notes
Power system slide notesPower system slide notes
Power system slide notes
 
Analysis of Stranded Multi-Conductor Cable in Multilayered Dielectric Media
Analysis of Stranded Multi-Conductor Cable in Multilayered Dielectric MediaAnalysis of Stranded Multi-Conductor Cable in Multilayered Dielectric Media
Analysis of Stranded Multi-Conductor Cable in Multilayered Dielectric Media
 
DISTRIBUTION OF ELECTRIC FIELD ANALYSIS IN 36 KV ROOF TOP BUSHING BY USING FE...
DISTRIBUTION OF ELECTRIC FIELD ANALYSIS IN 36 KV ROOF TOP BUSHING BY USING FE...DISTRIBUTION OF ELECTRIC FIELD ANALYSIS IN 36 KV ROOF TOP BUSHING BY USING FE...
DISTRIBUTION OF ELECTRIC FIELD ANALYSIS IN 36 KV ROOF TOP BUSHING BY USING FE...
 
Cable and laying
Cable and layingCable and laying
Cable and laying
 
Analysis and Design of Transmission Tower
Analysis and Design of Transmission Tower Analysis and Design of Transmission Tower
Analysis and Design of Transmission Tower
 
DB Cable
DB CableDB Cable
DB Cable
 
design of tower
design of towerdesign of tower
design of tower
 
Capacitance of the cables
Capacitance of the cablesCapacitance of the cables
Capacitance of the cables
 
Design of 230 kV Twin Bundle Double Circuit Overhead Transmission Line
Design of 230 kV Twin Bundle Double Circuit Overhead Transmission LineDesign of 230 kV Twin Bundle Double Circuit Overhead Transmission Line
Design of 230 kV Twin Bundle Double Circuit Overhead Transmission Line
 
Patel Wire Industries, Nashik , Aluminum Wires
Patel Wire Industries, Nashik , Aluminum WiresPatel Wire Industries, Nashik , Aluminum Wires
Patel Wire Industries, Nashik , Aluminum Wires
 
An analytical model for the current voltage characteristics of GaN-capped AlG...
An analytical model for the current voltage characteristics of GaN-capped AlG...An analytical model for the current voltage characteristics of GaN-capped AlG...
An analytical model for the current voltage characteristics of GaN-capped AlG...
 
ANALYSIS OF SMALL-SIGNAL PARAMETERS OF 2-D MODFET WITH POLARIZATION EFFECTS F...
ANALYSIS OF SMALL-SIGNAL PARAMETERS OF 2-D MODFET WITH POLARIZATION EFFECTS F...ANALYSIS OF SMALL-SIGNAL PARAMETERS OF 2-D MODFET WITH POLARIZATION EFFECTS F...
ANALYSIS OF SMALL-SIGNAL PARAMETERS OF 2-D MODFET WITH POLARIZATION EFFECTS F...
 
CTC Global - Economic & Environmental Impact of Power Line Loss Reductions
CTC Global - Economic & Environmental Impact of Power Line Loss ReductionsCTC Global - Economic & Environmental Impact of Power Line Loss Reductions
CTC Global - Economic & Environmental Impact of Power Line Loss Reductions
 
Electrical properties of insulating materials under VLF voltage
Electrical properties of insulating materials under VLF voltageElectrical properties of insulating materials under VLF voltage
Electrical properties of insulating materials under VLF voltage
 
Analysis-And-Design-Of-220kv-Transmission-Line-Tower-In-Different-Zones-I-&-V...
Analysis-And-Design-Of-220kv-Transmission-Line-Tower-In-Different-Zones-I-&-V...Analysis-And-Design-Of-220kv-Transmission-Line-Tower-In-Different-Zones-I-&-V...
Analysis-And-Design-Of-220kv-Transmission-Line-Tower-In-Different-Zones-I-&-V...
 

Viewers also liked

eTICtar - versão completa
eTICtar - versão completaeTICtar - versão completa
eTICtar - versão completaBetina Astride
 
Fundação - Isaac Asimov
Fundação - Isaac AsimovFundação - Isaac Asimov
Fundação - Isaac AsimovNanda Soares
 
Ericsson 2016 - Effective Communication for leaders
Ericsson 2016 - Effective Communication for leadersEricsson 2016 - Effective Communication for leaders
Ericsson 2016 - Effective Communication for leadersonellialessandro
 
Miguel Escalona. Coloquio Regiones, 2010
Miguel Escalona. Coloquio Regiones, 2010Miguel Escalona. Coloquio Regiones, 2010
Miguel Escalona. Coloquio Regiones, 2010Pro Regiones
 
Brincando e construindo com papel fantoches
Brincando e construindo com papel fantochesBrincando e construindo com papel fantoches
Brincando e construindo com papel fantochesSimoneHelenDrumond
 

Viewers also liked (10)

eTICtar - versão completa
eTICtar - versão completaeTICtar - versão completa
eTICtar - versão completa
 
Fundação - Isaac Asimov
Fundação - Isaac AsimovFundação - Isaac Asimov
Fundação - Isaac Asimov
 
Tigana 2 trecho
Tigana 2 trechoTigana 2 trecho
Tigana 2 trecho
 
Tigana trecho
Tigana trechoTigana trecho
Tigana trecho
 
Ericsson 2016 - Effective Communication for leaders
Ericsson 2016 - Effective Communication for leadersEricsson 2016 - Effective Communication for leaders
Ericsson 2016 - Effective Communication for leaders
 
Diabetes
DiabetesDiabetes
Diabetes
 
Miguel Escalona. Coloquio Regiones, 2010
Miguel Escalona. Coloquio Regiones, 2010Miguel Escalona. Coloquio Regiones, 2010
Miguel Escalona. Coloquio Regiones, 2010
 
Empleate y ocupate
Empleate y ocupateEmpleate y ocupate
Empleate y ocupate
 
Brincando e construindo com papel fantoches
Brincando e construindo com papel fantochesBrincando e construindo com papel fantoches
Brincando e construindo com papel fantoches
 
Comemorações de junho
Comemorações de junhoComemorações de junho
Comemorações de junho
 

Similar to H046044147

Cableshjtuy uifchgnhmj,kuytdfghjytfgkuhj
Cableshjtuy uifchgnhmj,kuytdfghjytfgkuhjCableshjtuy uifchgnhmj,kuytdfghjytfgkuhj
Cableshjtuy uifchgnhmj,kuytdfghjytfgkuhjKamalMohamed47
 
Principles of Cable Sizing
Principles of Cable SizingPrinciples of Cable Sizing
Principles of Cable SizingLeonardo ENERGY
 
System design-engineering-j jicable11-0279_final-evolution-in-method-performa...
System design-engineering-j jicable11-0279_final-evolution-in-method-performa...System design-engineering-j jicable11-0279_final-evolution-in-method-performa...
System design-engineering-j jicable11-0279_final-evolution-in-method-performa...nak maneth
 
Capacitance and Cable Testing
Capacitance and Cable TestingCapacitance and Cable Testing
Capacitance and Cable TestingHussein Kassem
 
Cable ampacity calculations iec
Cable ampacity calculations  iecCable ampacity calculations  iec
Cable ampacity calculations iecJoe Khan
 
Darkawi_et_al_CEIDP_2012_VF_IEEE
Darkawi_et_al_CEIDP_2012_VF_IEEEDarkawi_et_al_CEIDP_2012_VF_IEEE
Darkawi_et_al_CEIDP_2012_VF_IEEEAbdallah Darkawi
 
Power capacity of transmission lines
Power capacity of transmission linesPower capacity of transmission lines
Power capacity of transmission linesAlexander Decker
 
T&D GP.ppt
T&D GP.pptT&D GP.ppt
T&D GP.ppt52VikasV
 
cable sizing.ppt
cable sizing.pptcable sizing.ppt
cable sizing.pptChadWood16
 
Simulation and detection of transients on a 150kV HV Cable-paper
Simulation and detection of transients on a 150kV HV Cable-paperSimulation and detection of transients on a 150kV HV Cable-paper
Simulation and detection of transients on a 150kV HV Cable-paperThomas Mathew
 
Domestic wiring
Domestic wiringDomestic wiring
Domestic wiringVima Mali
 

Similar to H046044147 (20)

Cable sizing.pptx
Cable sizing.pptxCable sizing.pptx
Cable sizing.pptx
 
Cableshjtuy uifchgnhmj,kuytdfghjytfgkuhj
Cableshjtuy uifchgnhmj,kuytdfghjytfgkuhjCableshjtuy uifchgnhmj,kuytdfghjytfgkuhj
Cableshjtuy uifchgnhmj,kuytdfghjytfgkuhj
 
Principles of Cable Sizing
Principles of Cable SizingPrinciples of Cable Sizing
Principles of Cable Sizing
 
Sheath bonding method for underground cables
Sheath bonding method for underground cablesSheath bonding method for underground cables
Sheath bonding method for underground cables
 
System design-engineering-j jicable11-0279_final-evolution-in-method-performa...
System design-engineering-j jicable11-0279_final-evolution-in-method-performa...System design-engineering-j jicable11-0279_final-evolution-in-method-performa...
System design-engineering-j jicable11-0279_final-evolution-in-method-performa...
 
Cable Course.pptx
Cable Course.pptxCable Course.pptx
Cable Course.pptx
 
Capacitance and Cable Testing
Capacitance and Cable TestingCapacitance and Cable Testing
Capacitance and Cable Testing
 
B011120723
B011120723B011120723
B011120723
 
Eat 105 Chapter 3
Eat 105  Chapter 3Eat 105  Chapter 3
Eat 105 Chapter 3
 
Cable ampacity calculations iec
Cable ampacity calculations  iecCable ampacity calculations  iec
Cable ampacity calculations iec
 
Darkawi_et_al_CEIDP_2012_VF_IEEE
Darkawi_et_al_CEIDP_2012_VF_IEEEDarkawi_et_al_CEIDP_2012_VF_IEEE
Darkawi_et_al_CEIDP_2012_VF_IEEE
 
Power capacity of transmission lines
Power capacity of transmission linesPower capacity of transmission lines
Power capacity of transmission lines
 
T&D GP.ppt
T&D GP.pptT&D GP.ppt
T&D GP.ppt
 
Cable Sizing Calculations
Cable Sizing CalculationsCable Sizing Calculations
Cable Sizing Calculations
 
Ech
EchEch
Ech
 
cable sizing.ppt
cable sizing.pptcable sizing.ppt
cable sizing.ppt
 
Simulation and detection of transients on a 150kV HV Cable-paper
Simulation and detection of transients on a 150kV HV Cable-paperSimulation and detection of transients on a 150kV HV Cable-paper
Simulation and detection of transients on a 150kV HV Cable-paper
 
Akt tl design01
Akt tl design01Akt tl design01
Akt tl design01
 
Unit I.pdf
Unit I.pdfUnit I.pdf
Unit I.pdf
 
Domestic wiring
Domestic wiringDomestic wiring
Domestic wiring
 

Recently uploaded

WordPress Websites for Engineers: Elevate Your Brand
WordPress Websites for Engineers: Elevate Your BrandWordPress Websites for Engineers: Elevate Your Brand
WordPress Websites for Engineers: Elevate Your Brandgvaughan
 
How to write a Business Continuity Plan
How to write a Business Continuity PlanHow to write a Business Continuity Plan
How to write a Business Continuity PlanDatabarracks
 
Nell’iperspazio con Rocket: il Framework Web di Rust!
Nell’iperspazio con Rocket: il Framework Web di Rust!Nell’iperspazio con Rocket: il Framework Web di Rust!
Nell’iperspazio con Rocket: il Framework Web di Rust!Commit University
 
SIP trunking in Janus @ Kamailio World 2024
SIP trunking in Janus @ Kamailio World 2024SIP trunking in Janus @ Kamailio World 2024
SIP trunking in Janus @ Kamailio World 2024Lorenzo Miniero
 
Take control of your SAP testing with UiPath Test Suite
Take control of your SAP testing with UiPath Test SuiteTake control of your SAP testing with UiPath Test Suite
Take control of your SAP testing with UiPath Test SuiteDianaGray10
 
Merck Moving Beyond Passwords: FIDO Paris Seminar.pptx
Merck Moving Beyond Passwords: FIDO Paris Seminar.pptxMerck Moving Beyond Passwords: FIDO Paris Seminar.pptx
Merck Moving Beyond Passwords: FIDO Paris Seminar.pptxLoriGlavin3
 
Transcript: New from BookNet Canada for 2024: BNC CataList - Tech Forum 2024
Transcript: New from BookNet Canada for 2024: BNC CataList - Tech Forum 2024Transcript: New from BookNet Canada for 2024: BNC CataList - Tech Forum 2024
Transcript: New from BookNet Canada for 2024: BNC CataList - Tech Forum 2024BookNet Canada
 
DevEX - reference for building teams, processes, and platforms
DevEX - reference for building teams, processes, and platformsDevEX - reference for building teams, processes, and platforms
DevEX - reference for building teams, processes, and platformsSergiu Bodiu
 
How AI, OpenAI, and ChatGPT impact business and software.
How AI, OpenAI, and ChatGPT impact business and software.How AI, OpenAI, and ChatGPT impact business and software.
How AI, OpenAI, and ChatGPT impact business and software.Curtis Poe
 
SAP Build Work Zone - Overview L2-L3.pptx
SAP Build Work Zone - Overview L2-L3.pptxSAP Build Work Zone - Overview L2-L3.pptx
SAP Build Work Zone - Overview L2-L3.pptxNavinnSomaal
 
"LLMs for Python Engineers: Advanced Data Analysis and Semantic Kernel",Oleks...
"LLMs for Python Engineers: Advanced Data Analysis and Semantic Kernel",Oleks..."LLMs for Python Engineers: Advanced Data Analysis and Semantic Kernel",Oleks...
"LLMs for Python Engineers: Advanced Data Analysis and Semantic Kernel",Oleks...Fwdays
 
Are Multi-Cloud and Serverless Good or Bad?
Are Multi-Cloud and Serverless Good or Bad?Are Multi-Cloud and Serverless Good or Bad?
Are Multi-Cloud and Serverless Good or Bad?Mattias Andersson
 
DSPy a system for AI to Write Prompts and Do Fine Tuning
DSPy a system for AI to Write Prompts and Do Fine TuningDSPy a system for AI to Write Prompts and Do Fine Tuning
DSPy a system for AI to Write Prompts and Do Fine TuningLars Bell
 
What's New in Teams Calling, Meetings and Devices March 2024
What's New in Teams Calling, Meetings and Devices March 2024What's New in Teams Calling, Meetings and Devices March 2024
What's New in Teams Calling, Meetings and Devices March 2024Stephanie Beckett
 
Tampa BSides - Chef's Tour of Microsoft Security Adoption Framework (SAF)
Tampa BSides - Chef's Tour of Microsoft Security Adoption Framework (SAF)Tampa BSides - Chef's Tour of Microsoft Security Adoption Framework (SAF)
Tampa BSides - Chef's Tour of Microsoft Security Adoption Framework (SAF)Mark Simos
 
Advanced Computer Architecture – An Introduction
Advanced Computer Architecture – An IntroductionAdvanced Computer Architecture – An Introduction
Advanced Computer Architecture – An IntroductionDilum Bandara
 
Artificial intelligence in cctv survelliance.pptx
Artificial intelligence in cctv survelliance.pptxArtificial intelligence in cctv survelliance.pptx
Artificial intelligence in cctv survelliance.pptxhariprasad279825
 
"Subclassing and Composition – A Pythonic Tour of Trade-Offs", Hynek Schlawack
"Subclassing and Composition – A Pythonic Tour of Trade-Offs", Hynek Schlawack"Subclassing and Composition – A Pythonic Tour of Trade-Offs", Hynek Schlawack
"Subclassing and Composition – A Pythonic Tour of Trade-Offs", Hynek SchlawackFwdays
 
Gen AI in Business - Global Trends Report 2024.pdf
Gen AI in Business - Global Trends Report 2024.pdfGen AI in Business - Global Trends Report 2024.pdf
Gen AI in Business - Global Trends Report 2024.pdfAddepto
 

Recently uploaded (20)

WordPress Websites for Engineers: Elevate Your Brand
WordPress Websites for Engineers: Elevate Your BrandWordPress Websites for Engineers: Elevate Your Brand
WordPress Websites for Engineers: Elevate Your Brand
 
How to write a Business Continuity Plan
How to write a Business Continuity PlanHow to write a Business Continuity Plan
How to write a Business Continuity Plan
 
Nell’iperspazio con Rocket: il Framework Web di Rust!
Nell’iperspazio con Rocket: il Framework Web di Rust!Nell’iperspazio con Rocket: il Framework Web di Rust!
Nell’iperspazio con Rocket: il Framework Web di Rust!
 
SIP trunking in Janus @ Kamailio World 2024
SIP trunking in Janus @ Kamailio World 2024SIP trunking in Janus @ Kamailio World 2024
SIP trunking in Janus @ Kamailio World 2024
 
Take control of your SAP testing with UiPath Test Suite
Take control of your SAP testing with UiPath Test SuiteTake control of your SAP testing with UiPath Test Suite
Take control of your SAP testing with UiPath Test Suite
 
Merck Moving Beyond Passwords: FIDO Paris Seminar.pptx
Merck Moving Beyond Passwords: FIDO Paris Seminar.pptxMerck Moving Beyond Passwords: FIDO Paris Seminar.pptx
Merck Moving Beyond Passwords: FIDO Paris Seminar.pptx
 
Transcript: New from BookNet Canada for 2024: BNC CataList - Tech Forum 2024
Transcript: New from BookNet Canada for 2024: BNC CataList - Tech Forum 2024Transcript: New from BookNet Canada for 2024: BNC CataList - Tech Forum 2024
Transcript: New from BookNet Canada for 2024: BNC CataList - Tech Forum 2024
 
DevEX - reference for building teams, processes, and platforms
DevEX - reference for building teams, processes, and platformsDevEX - reference for building teams, processes, and platforms
DevEX - reference for building teams, processes, and platforms
 
How AI, OpenAI, and ChatGPT impact business and software.
How AI, OpenAI, and ChatGPT impact business and software.How AI, OpenAI, and ChatGPT impact business and software.
How AI, OpenAI, and ChatGPT impact business and software.
 
SAP Build Work Zone - Overview L2-L3.pptx
SAP Build Work Zone - Overview L2-L3.pptxSAP Build Work Zone - Overview L2-L3.pptx
SAP Build Work Zone - Overview L2-L3.pptx
 
"LLMs for Python Engineers: Advanced Data Analysis and Semantic Kernel",Oleks...
"LLMs for Python Engineers: Advanced Data Analysis and Semantic Kernel",Oleks..."LLMs for Python Engineers: Advanced Data Analysis and Semantic Kernel",Oleks...
"LLMs for Python Engineers: Advanced Data Analysis and Semantic Kernel",Oleks...
 
Are Multi-Cloud and Serverless Good or Bad?
Are Multi-Cloud and Serverless Good or Bad?Are Multi-Cloud and Serverless Good or Bad?
Are Multi-Cloud and Serverless Good or Bad?
 
DSPy a system for AI to Write Prompts and Do Fine Tuning
DSPy a system for AI to Write Prompts and Do Fine TuningDSPy a system for AI to Write Prompts and Do Fine Tuning
DSPy a system for AI to Write Prompts and Do Fine Tuning
 
What's New in Teams Calling, Meetings and Devices March 2024
What's New in Teams Calling, Meetings and Devices March 2024What's New in Teams Calling, Meetings and Devices March 2024
What's New in Teams Calling, Meetings and Devices March 2024
 
Tampa BSides - Chef's Tour of Microsoft Security Adoption Framework (SAF)
Tampa BSides - Chef's Tour of Microsoft Security Adoption Framework (SAF)Tampa BSides - Chef's Tour of Microsoft Security Adoption Framework (SAF)
Tampa BSides - Chef's Tour of Microsoft Security Adoption Framework (SAF)
 
Advanced Computer Architecture – An Introduction
Advanced Computer Architecture – An IntroductionAdvanced Computer Architecture – An Introduction
Advanced Computer Architecture – An Introduction
 
E-Vehicle_Hacking_by_Parul Sharma_null_owasp.pptx
E-Vehicle_Hacking_by_Parul Sharma_null_owasp.pptxE-Vehicle_Hacking_by_Parul Sharma_null_owasp.pptx
E-Vehicle_Hacking_by_Parul Sharma_null_owasp.pptx
 
Artificial intelligence in cctv survelliance.pptx
Artificial intelligence in cctv survelliance.pptxArtificial intelligence in cctv survelliance.pptx
Artificial intelligence in cctv survelliance.pptx
 
"Subclassing and Composition – A Pythonic Tour of Trade-Offs", Hynek Schlawack
"Subclassing and Composition – A Pythonic Tour of Trade-Offs", Hynek Schlawack"Subclassing and Composition – A Pythonic Tour of Trade-Offs", Hynek Schlawack
"Subclassing and Composition – A Pythonic Tour of Trade-Offs", Hynek Schlawack
 
Gen AI in Business - Global Trends Report 2024.pdf
Gen AI in Business - Global Trends Report 2024.pdfGen AI in Business - Global Trends Report 2024.pdf
Gen AI in Business - Global Trends Report 2024.pdf
 

H046044147

  • 1. B. V. R. Uday Kiran et al Int. Journal of Engineering Research and Applications www.ijera.com ISSN: 2248-9622, Vol. 4, Issue 6(Version 4), June 2014, pp.41-47 www.ijera.com 41 | P a g e Under Ground Cable Sizing Using MAT LAB B. V. R. Uday Kiran1 , A. V. Raghava Ram2 , K. Jitendra3 Abstract The main theme of this paper is to explain the procedure to calculate the cross sectional area of a conductor of an underground cable for a specified power & voltage ratings. This paper will also explain one of the simplest ways to calculate the cross section. In this paper we analyzed various factors that effect in deciding the ampacity of the conductor. We developed a Mat lab code to find the cross sectional area by including some of the parameters and also the voltage drop , maximum permissible voltage drop for that size of the conductor and also the number of runs of the cable that are to be laid. Key words: Conduction cross section, derating factor, XLPE cable, MATLAB I. INTRODUCTION CABLE (or conductor) sizing is the process of selecting appropriate sizes for electrical power cable conductors. Cable sizes are typically described in terms of cross-sectional area, American Wire Gauge (AWG) or kcmil, depending on geographic region. In this we have taken CCI (Cable Corporation of India) standards into consideration for calculating cable size. The purpose of Conductor and Cable Sizing is to determine the best to transport a given current, determined by voltage, through an insulated conductive material. Conductor size must be calculated by taking factors like distance, raceways and environmental conditions into account which includes minimizing heat generated from resistance or impedance of the cable itself. Proper sizing of an electrical (load bearing) cable ensures that the cable can: 1. Operate continuously under full load without being damaged 2. Withstand the worst short circuit currents flowing through the cable 3. Provide suitable voltage to the load (and avoid excessive voltage drops) 4. Ensures operation of protective devices during an earth fault II. PROBLEM STATEMENT Consider a 3-phase, 11 kV substation, from which a 1 MVA power is to be transferred to a load which is situated at certain distance from the substation, through a 3 core cable. This article gives the sizing of a cable in a generalized way i.e., from a substation at any voltage level transferring a certain power to the load. III. GENERAL METHODOLOGY All cable sizing methods more or less follow the same basic four step process: 1. Gathering data about the cable, its installation conditions, and the load that it has to carry. 2. Determine the minimum cable size based on continuous current carrying capacity. 3. Determine the minimum cable size based on voltage drop considerations 4. Select the cable size based on the highest of the sizes calculated in step 2 and 3. Step 1: The first step is to collate the relevant information that is required to perform the sizing calculation Load Details  The type of load to which cable is connected i.e., feeder or motor (This article generally deals with feeder type of cables).  Three phase, single phase or DC (here 3-phase) .  System / source voltage at which cables is operating.  Full load current (A) - or calculate this if the load is defined in terms of power (kW) .  Desired full load power factor (p.u) at which system should operate.  Distance / length of cable run from source to load . This length should be as close as possible to the actual route of the cable and include enough contingency for vertical drops / rises and termination of the cable tails. Cable Construction: The basic characteristics of the cable's physical construction, which includes:  Material of conductor (normally copper or aluminum).  Shape of conductor (like circular or shaped).  Type of conductor (like stranded or solid).  Conductor surface coating (like plain (no coating), tinned, silver or nickel ).  Insulation type (mostly preferred PVC, XLPE, EPR ) RESEARCH ARTICLE OPEN ACCESS
  • 2. B. V. R. Uday Kiran et al Int. Journal of Engineering Research and Applications www.ijera.com ISSN: 2248-9622, Vol. 4, Issue 6(Version 4), June 2014, pp.41-47 www.ijera.com 42 | P a g e  Number of cores - single core or multicore (2-core ,3-core, etc..,). Installation Conditions: How the cable will be installed:  Installation / arrangement - e.g. for underground cables, is it directly buried or buried in conduit? for above ground cables, is it installed on cable tray / ladder, against a wall, in air, etc.  Ambient or soil temperature of the installation site  Cable grouping, i.e. the number of cables that are grouped together.  Cable spacing, i.e. whether cables are installed touching or spaced from each other.  Soil thermal resistivity.  Depth of laying.  For single core three-phase cables, are the cables installed in trefoil or laid flat? Note:350 C ground temperature for cables directly buried in ground, the depth of laying being 900 mm and soil thermal resistivity being 1500 C cm/W is assumed. STEP 2: The substation rating from which cable is to be sized is to be given (V in 3-phase) and the power (in MW or MVA) that is to be transferred through this cable (say P) is to be given. The current (I) passing through the cable is calculated as [5] (1) (2) Current at 110% loading (Ifl) is given as Let, Ifl = I (1.1) (3) This is here considered in order to ensure that cable can withstand over loading up to some extent which prevents damage of the cable and the electrical equipment (load) connected to the delivering end of the cable. This value can be taken higher for more safety but it increases the losses and also the amount of material used which is waste of economy. Current flowing through a cable generates heat through the resistive losses in the conductors, dielectric losses through the insulation and resistive losses from current flowing through any cable screens / shields and armouring. The component parts that make up the cable (e.g. conductors, insulation, bedding, sheath, armour, etc.) must be capable of withstanding the temperature rise and heat emanating from the cable. The current carrying capacity of a cable is the maximum current that can flow continuously through a cable without damaging the cable's insulation and other components (e.g. bedding, sheath, etc.). It is sometimes also referred to as the continuous current rating or ampacity of a cable. Cables with larger conductor cross-sectional areas have lower resistive losses and are able to dissipate the heat better than smaller cables. Therefore we can say that 16 mm2 cables will have a higher current carrying capacity than a 4 mm2 cables. Base Current Ratings International standards and manufacturers of cables will quote base current ratings of different types of cables in tables such as the one shown below. The tables given below are given by Cable Corporation of India (CCI). TABLE I: ALUMINIUM COND. 3 CORE CABLES FROM 3.3 kV TO 33 kV (E) [1] Conductor Cross- Section 3.3 kV to 11(UE) Direct in ground 22 kV to 33 (E) Direct in ground Sq.mm Amps Amps 25 95 35 110 110 50 130 130 70 160 160 95 190 190 120 215 210 150 245 240 185 275 270 240 320 310 300 360 350 400 410 400 TABLE II: COPPER COND. 3 CORE CABLES FROM 3.3kV TO 33kV (E) [1] Conductor Cross- Section 3.3kV to 11(UE) Direct in ground 22kV to 33(E) Direct in Ground Sq.mm Amps Amps 25 120 35 145 145 50 170 165 70 205 205 95 245 240 120 280 275 150 310 305
  • 3. B. V. R. Uday Kiran et al Int. Journal of Engineering Research and Applications www.ijera.com ISSN: 2248-9622, Vol. 4, Issue 6(Version 4), June 2014, pp.41-47 www.ijera.com 43 | P a g e 185 350 345 240 405 395 300 455 445 400 510 505 Installed Current Ratings When the proposed installation conditions differ from the base conditions, derating (or correction) factors can be applied to the base current ratings to obtain the actual installed current ratings. International standards and cable manufacturers will provide derating factors for a range of installation conditions, for example ambient / soil temperature, grouping or bunching of cables, soil thermal resistivity, etc. The installed current rating is calculated by multiplying the base current rating with each of the derating factors, i.e. [3] Id=It * DF (4) Where Id the installed current rating (A) It is the current rating (A) DF are the product of all the derating factors The various factors that cause derating of current carrying capacity of a cable are ground thermal resistivity, grouping of cables, ground temperature and air temperature. The values of derating factors for the above mentioned parameters for some standard values are: TABLE III: GROUND THERMAL RESISTIVITY [2] Thermal Resistivity (K.m/W) Direct in ground 1,0 1,2 1,5 2,0 2,5 1,08 1,00 0,93 0,83 0,78 TABLE IV: GROUPING OF CABLES [2] No of cables in Group Direct in Ground Axial Spacing (mm) Touching 150 300 450 600 2 3 4 5 6 0.81 0.70 0.63 0.59 0.55 0.87 0.78 0.74 0.70 0.67 0.91 0.84 0.81 0.78 0.76 0.93 0.87 0.86 0.83 0.82 0.94 0.90 0.89 0.87 0.86 TABLE V: GROUND TEMPERATURE [2] Maximum Conductor Temp (ºC) Ground temperatures (ºC) 25 30 35 40 45 50 70(PVC) 1.00 0.95 0.90 0.85 0.80 0.70 90(XLPE) 1.00 0.96 0.92 0.88 0.82 0.76 TABLE VI: AIR TEMPERATURE [2] Maximum conductor temp(ºC) Air temperature (ºC) 30 35 40 45 70(PVC) 1.00 0.94 0.87 0.79 90(XLPE) 1.00 0.95 0.89 0.84 For example, suppose a cable had an ambient temperature derating factor 0.94 and a group derating factor of 0.9 then the overall derating factor will be (0.94*0.9) which is approximately equal to 0.855. This derating value is taken in the code just as reference but this can vary depending on the operating and environmental conditions (which can also be changed in the Mat lab code). a) Cable Selection When sizing cables for feeders, the cross-section of cables is also typically selected to protect the cable against damage from thermal overload. The cross- section of cable must therefore be selected to exceed the full load current, but not exceed the cable's installed current rating, i.e. this inequality must be met: Id ≥ Ifl (5) Here if this inequality is not satisfied with any of the values given in the Table 1 or Table 2(according to the material chosen) then the base current rating of the cable is multiplied by an integral factor „r‟ (where r=1,2,3,…) i.e., the current carrying capacity of the cable is increased by laying it in „r‟ runs. r(Id)≥Ifl (6) STEP 3: A cable's conductor can be seen as an impedance and therefore whenever current flows through a cable, there will be a voltage drop across it, which can be derived from Ohm‟s Law (i.e. V = IZ). The voltage drop will depend on two things:  Current flow through the cable – the higher the current flow, the higher the voltage drop  Impedance of the conductor – the larger the impedance, the higher the voltage drop The impedance of the cable is a function of the cable size (cross-sectional area) and the length of the cable. Most cable manufacturers will quote a cable‟s resistance and reactance in Ω/km. The following typical cable impedances given by CCI (Cable
  • 4. B. V. R. Uday Kiran et al Int. Journal of Engineering Research and Applications www.ijera.com ISSN: 2248-9622, Vol. 4, Issue 6(Version 4), June 2014, pp.41-47 www.ijera.com 44 | P a g e Corporation of India) can be used in the absence of any other data. TABLE VII RESISTANCE VALUES OF 3CORE CABLES [2] Condu ctor Cross Section Max D.C Resistan ce At 20˚C Approx A.C Resistan - ce At 90˚C Max D.C Resist an- ce At 20˚C Approx A.C Resistan -ce At 90˚C Aluminum Copper Sq.mm Ohm/k m Ohm/k m Ohm/ km Ohm/k m 25 1.200 1.5500 0.727 0 0.9260 35 0.8680 1.1200 0.524 0 0.6680 50 0.6410 0.8280 0.387 0 0.4930 70 0.4430 0.2720 0.268 0 0.3410 95 0.3200 0.4140 0.193 0 0.2460 120 0.2530 0.3270 0.153 0 0.1950 150 0.2060 0.2660 0.124 0 0.1580 185 0.1640 0.2120 0.099 1 0.1260 240 0.1250 0.1620 0.075 4 0.0961 300 0.1000 0.1290 0.060 1 0.0766 400 0.0778 0.1010 0.047 0 0.0600 TABLE VIII REACTANCE OF 3CORE CABLE [2] Conduct or Cross Section Reactance of 3core Cables conforming to IS:7098(pt-2)-1985 Approx Reactance at 50Hz 3.8/6.6 Kv 6.6/6.6 & 6.35/1 1 Kv 11/11 Kv 12.7/2 2 Kv 19/33 Kv 25 0.126 0.133 0.145 --- --- 35 0.12 0.126 0.138 0.141 --- 50 0.144 0.118 0.129 0.132 0.146 70 0.107 0.116 0.124 0.125 0.138 95 0.102 0.107 0.116 0.119 0.13 120 0.0977 0.102 0.112 0.114 0.125 150 0.0953 0.0994 0.108 0.111 0.122 185 0.0926 0.0969 0.105 0.107 0.118 240 0.0902 0.0936 0.102 0.104 0.113 300 0.09 0.0926 0.0999 0.102 0.111 400 0.0872 0.0886 0.0954 0.0969 0.106 Calculating Voltage Drop For AC systems, the method of calculating voltage drops based on load power factor is commonly used. Full load currents are normally used, but if the load has high startup currents (e.g. motors), then voltage drops based on starting current (and power factor if applicable) should also be calculated. For a three phase system: [3] (7) Where V3ø is the three phase voltage drop (V) I=Ifl nominal full load current as applicable (A) Rc is the ac resistance of the cable (Ω/km) Xc is the ac reactance of the cable (Ω/km) cos ø is the load power factor (pu) L is the length of the cable (m) For a single phase system: [3] (8) Where V1ø is the single phase voltage drop (V) I is the nominal full load current as applicable (A) Rc is the ac resistance of the cable (Ω/km) Xc is the ac reactance of the cable (Ω/km) cos ø is the load power factor (pu) L is the length of the cable (m)
  • 5. B. V. R. Uday Kiran et al Int. Journal of Engineering Research and Applications www.ijera.com ISSN: 2248-9622, Vol. 4, Issue 6(Version 4), June 2014, pp.41-47 www.ijera.com 45 | P a g e For a DC system:[3] (9) Where Vdc is the dc voltage drop (V) I is the nominal full load current as applicable (A) Rc is the dc resistance of the cable (Ω/km) L is the length of the cable (m) It is customary for standards (or clients) to specify maximum permissible voltage drops, which is the highest voltage drop that is allowed across a cable. If your cable exceeds this voltage drop, then a larger cable size should be selected. In general, most electrical equipment will operate normally at a voltage as low as 80% nominal voltage. For example, if the nominal voltage is 230VAC, then most appliances will run at >184VAC. Cables are typically sized for a more conservative maximum voltage drop, in the range of 5 – 10% at full load. The following table give the maximum permissible voltage drop that can allowed while current is flowing in the cable. These standards are given by CCI. TABLE IX ESTIMATED VOLTAGE DROP [2] Conduct or Cross- section Estimated Voltage Drop for XLPE Aluminum conductor armored 3-Core Cables Voltage Drop V/km/A 3.8/6. 6KV 6.6/6.6 & 6.35/11 KV 11/1 1 KV 12.7/2 2 KV 19/3 3K V 25 2.67 2.67 2.67 --- --- 35 1.94 1.94 1.94 1.94 --- 50 1.44 1.44 1.44 1.44 1.44 70 1.00 1.00 1.01 1.01 1.44 95 0.70 0.74 0.74 0.74 0.74 120 0.56 0.59 0.60 0.60 0.60 150 0.48 0.49 0.49 0.49 0.50 185 0.40 0.40 0.41 0.41 0.44 240 0.30 0.32 0.33 0.33 0.32 300 0.26 0.27 0.28 0.28 0.29 400 0.21 0.23 0.24 0.24 0.25 For a cable to be selected it should not only satisfy the inequality Id ≥ Ifl, but also should not exceed its permissible voltage drop i.e., VD ≤ VDt (10) Where VD is the calculated voltage drop VDt is the voltage drop taken according to Table 5 with respect to the corresponding cable size selected that satisfies the current inequality (used in Mat lab code) Note: Here voltage drop calculation is done in V/Km/A i.e., the equation for voltage drop calculation for 3 phase system is rewritten as (11) Where „r‟ is the no: of runs STEP 4: The size of the cable which satisfies full load current inequality and voltage drop inequality is selected for laying. Alternatively, the size of the cable can be calculated using Mat lab. The flow chart below explains how the Mat lab code [4] code calculates the size of the cable for desired voltage and power rating at a desired power factor.
  • 6. B. V. R. Uday Kiran et al Int. Journal of Engineering Research and Applications www.ijera.com ISSN: 2248-9622, Vol. 4, Issue 6(Version 4), June 2014, pp.41-47 www.ijera.com 46 | P a g e Fig.1 Flowchart for calculating cable sizing IV. RESULT These are the two results we have obtained by executing the mat lab code. 1. ENTER BASIC CABLE SPECIFICATIONS Enter 1 for copper or 2 for aluminium: 1 Enter nominal load voltage (3.3kV or 6.6kV or 11kV or 22kV 0r 33kV) only: 33 Enter full load power factor: 0.8 Enter power in MW: 22  OUTPUT Current in the cable = 481.1252 Full load current = 529.237 Derating factor = 0.8550 Voltage drop in the cable = 0.1729 Maximum permissible voltage drop taken from standards = 0.4900 REQUIRED PARAMETERS Required cross section of the cable = 150 Number of runs: r = 2 Note: [Current: amps; voltage drop: volts; crossection: mm] 2. ENTER BASIC CABLE SPECIFICATIONS Enter 1 for copper or 2 for aluminum: 2 Enter nominal load voltage (3.3kV or 6.6kV or 11kV or 22kV 0r 33kV) only: 11 Enter full load power factor: 0.85 Enter power in MW: 8.5  OUTPUT Current in the cable = 524.8639 Full load current = 577.3503 Derating factor = 0.8550 Voltage drop in the cable = 0.1405 Maximum permissible voltage drop taken from standards = 0.2800 REQUIRED PARAMETERS Required cross section of the cable = 300 Number of runs: r = 2 Note: [Current: amps; voltage drop: volts; crossection: mm] V. SCREEN SHOTS 1. Matlab output screen shots ( copper cable)
  • 7. B. V. R. Uday Kiran et al Int. Journal of Engineering Research and Applications www.ijera.com ISSN: 2248-9622, Vol. 4, Issue 6(Version 4), June 2014, pp.41-47 www.ijera.com 47 | P a g e 2. Matlab output screen shots (Aluminum cable) VI. CONCLUSION We have discussed a novel method by which we can estimate the approximate size of the cable considering various effects that effect the ampacity of the cable. We have discussed a simplified approach for calculating the size using mat lab coding there by reducing human effort greatly. In future we would like to extend this program in order to include other parameters which effect the ampacity and also to apply this approach for other different cables. REFERENCES [1] Tropothen-X cables: Cable Corporation of India Ltd. [2] R. (Dick) Hardie, Aberdare Cables (Pty) Ltd: “Electric Power Cables-Whatever Happened to the Factor of Safety?” [3] Stephen W. Fardo, Dale R. Patrick:”Electrical Power Systems Technology: 3rd Edition”. [4] Stephen. J.Chapman: “MATLAB Programming for engineers, 4th Edition“ [5] J.B.Gupta: “Electrical Power Systems”, 3rd edition. [6] Ossama E. Gouda, Adel Z. El Dein, Ghada M. Amer: “Improving the Under-Ground Cables Ampacity”, Proceedings of the 14th International Middle East Power Systems Conference (MEPCON‟10), Cairo University, Egypt, Paper ID 110.