“EURORAIL” Project 
Organizational model
EURORAIL Project 
Initiator: Ministry of transport and communications of Ukraine 
Lviv Oblast State Administration 
Lviv City Council 
Cost: 500 mln. EUR 
Terms: 2010-2015 
Prerequisites: 
• Discrepancy of Ukrainian and CIS countries’ railways 
(1520) with the EU railway standard UIC (1435) 
• Increased demand for fast and qualified 
communication between Ukraine (CIS) and Europe
EURORAIL Project
Project main statements 
Project subject: The construction of 84 km long EU standard rail 
track and all required infrastructure between Lviv and Polish- 
Ukrainian border (Prezemysl/Mostyska and Krakivets). 
Goal: to provide high speed railway connection between Lviv and 
Polish-Ukrainian border within III Euro transport corridor. 
Mechanism: Concession for construction and further operation of 
the rail track and its infrastructure. 
Participants: Cabinet of Ministers of Ukraine, Ministry of transport 
and communication of Ukraine, Lviv Oblast State Administration, 
Lviv City Council, private companiesЛьвівська обласна Рада, 
Львівська міська Рада, приватні компанії. Participation of Ministry 
of infrastructure of Poland is also needed.
Implementation algorithm 
1. JSC “Evrokoliya” set up by experienced in this field companies. 
2. The Cabinet of Ministers of Ukraine is to issue the Resolution 
regarding “Eurorail” Project implementation and assign core 
Ministry (Ministry of transport and communication of Ukraine) 
to be responsible for its realization. 
3. The Concession Agreement is to be signed with the Company-contractor 
identified through the Tender. 
4. The Concession Agreement is to be prepared and signed by 
Ministry of transport and communication of Ukraine, Lviv Oblast 
State Administration, Lviv City Council and JSC “Evrokoliya” 
and is to contain Project implementation mechanisms. 
5. JSC “Evrokoliya” attracts all required financial funds and 
contractors for the Project implementation. 
6. After the project is implemented it is to be managed and used 
by Ministry of transport and communication of Ukraine. The last 
is to make payments for the benefit of JSC “Evrokoliya”.
Project scheme 
JSC 
“Eurokoliya 
Ministry of transport 
“Eurokoliya” 
Specifications 
Rail track and 
infrastructure 
operation 
Ownership for 
the rail track 
and the part of 
infrastructure 
JSC 
Plots 
ІInformation 
Ministry of transport 
Lviv Oblast 
Administration 
Investments 
Lviv City Council 
Founders 
Construction process 
Ownership for 
the part of 
infrastructure 
Euro rail track usage payments according to the 
Concession Agreement as the investments 
return source
JSC “Evrokoliya” set up 
 “Evrokoliya” is to be joint-stock company 
 JSC “Evrokoliya” founders (companies) are to be able to provide 
qualified Project implementation. 
Company’s dominant task – is to develop contract and legal 
platform for its further activity (including possible relations 
coordination between core Ministers of Ukraine and Poland and 
between Lviv Oblast Administration and Lviv City Council). 
 JSC “Evrokoliya” is to hold a research on a Project, provide its 
feasibility study and approve the Project with all Participants. 
 The last stage – Project Business Plan, investments attraction 
and Project implementation.
Concession Agreement 
Main regulations: 
 Project participant’s collaboration mechanism. 
 Participant’s obligations (land plots, information, specifications 
provision for the Project by its Participants). 
 Constructed object’s ownership (tracks, terminals, technical 
buildings, warehouses etc.). 
 Relations among Project Participants on the after construction 
stage when the rail track and its infrastructure will be operated. 
 Rail track and its infrastructure usage payments as the 
investments return source
Implementation phases 
 Phase I: 2008 - 2009 
•Pre-feasibility study 
• Memorandum of Understanding with Dutch MOVARES and NEA for pre-feasibility 
study, 133,000 EUR attracted from the Dutch government. 
•Additional investment required for Phase 1 – 250,000 eur 
 Phase II: 2009 – 2010 
•Pre-feasibility study presentation to all the stakeholders for final decision-making 
•The establishment of the International Project Implementation Consortium 
•Finalizing Project Finance Structure and Legal Model (PPP) 
 Phase III: 2010 – 2013 
Project Implementation: 
•Construction the rail track from Polish/Ukrainian border to Lviv (86 km) 
•New rail infrastructure development, including modern passenger and goods 
terminal near and in Lviv
Project impact assessment 
Increase of passenger and cargo flows 
Maximum shortening of the travel time 
Social and economic development of the region 
Ukraine’s integration with 
main European cities
Leonid Bogdanov, CEO bogdanov@unidevelop.com 
Yuryi Stetskiv, CFO stetskiv@unidevelop.com 
Kyiv, Ukraine 01133 
9 Lesi Ukrainki Blvd, 
Tel.: +38 044 585 10 80 
Fax: +38 044 585 10 79 
www.unidevelop.com

Contenu connexe

Tendances

South East Europe Rail conference - Nedim Begovic
South East Europe Rail conference -  Nedim BegovicSouth East Europe Rail conference -  Nedim Begovic
South East Europe Rail conference - Nedim Begovic
Russell Publishing
 
Port Integration - EU Maritime Developments - Jonathan Millins
Port Integration - EU Maritime Developments - Jonathan Millins Port Integration - EU Maritime Developments - Jonathan Millins
Port Integration - EU Maritime Developments - Jonathan Millins
Port of Riga
 
Dryportpresentation roso 135 (1)
Dryportpresentation roso 135 (1)Dryportpresentation roso 135 (1)
Dryportpresentation roso 135 (1)
StudsPlanet.com
 
Transexpress Pres. English
Transexpress Pres. EnglishTransexpress Pres. English
Transexpress Pres. English
Georgi Nedelchev
 
The Railway Infrastructure in Bosnia and Herzegovina
The Railway Infrastructure in Bosnia and HerzegovinaThe Railway Infrastructure in Bosnia and Herzegovina
The Railway Infrastructure in Bosnia and Herzegovina
Amel Kovacevic
 

Tendances (20)

Skonto Buve
Skonto BuveSkonto Buve
Skonto Buve
 
Corridors progrreport version1_2014
Corridors progrreport version1_2014Corridors progrreport version1_2014
Corridors progrreport version1_2014
 
Construction and Operation of New Lviv - Krakovets Highway
Construction and Operation of New Lviv - Krakovets HighwayConstruction and Operation of New Lviv - Krakovets Highway
Construction and Operation of New Lviv - Krakovets Highway
 
Ukrainian infrastructure: open for investors
Ukrainian infrastructure: open for investorsUkrainian infrastructure: open for investors
Ukrainian infrastructure: open for investors
 
Mt2014 wider mos-svc
Mt2014 wider mos-svcMt2014 wider mos-svc
Mt2014 wider mos-svc
 
South East Europe Rail conference - Nedim Begovic
South East Europe Rail conference -  Nedim BegovicSouth East Europe Rail conference -  Nedim Begovic
South East Europe Rail conference - Nedim Begovic
 
Donor meeting. Ministry of Infrastructure of Ukraine 6th of December
Donor meeting. Ministry of Infrastructure of Ukraine 6th of DecemberDonor meeting. Ministry of Infrastructure of Ukraine 6th of December
Donor meeting. Ministry of Infrastructure of Ukraine 6th of December
 
Overview of EBRD and the Transport Sector
Overview of EBRD and the Transport SectorOverview of EBRD and the Transport Sector
Overview of EBRD and the Transport Sector
 
Transport: New EU Infraestructure Policy
Transport: New EU Infraestructure PolicyTransport: New EU Infraestructure Policy
Transport: New EU Infraestructure Policy
 
Port Integration - EU Maritime Developments - Jonathan Millins
Port Integration - EU Maritime Developments - Jonathan Millins Port Integration - EU Maritime Developments - Jonathan Millins
Port Integration - EU Maritime Developments - Jonathan Millins
 
Rail Baltica planning process
Rail Baltica planning processRail Baltica planning process
Rail Baltica planning process
 
Baltic adriatique corridor k. bodewig
Baltic adriatique corridor   k. bodewigBaltic adriatique corridor   k. bodewig
Baltic adriatique corridor k. bodewig
 
WSP Parsons Brinckerhoff
WSP Parsons BrinckerhoffWSP Parsons Brinckerhoff
WSP Parsons Brinckerhoff
 
Dryportpresentation roso 135 (1)
Dryportpresentation roso 135 (1)Dryportpresentation roso 135 (1)
Dryportpresentation roso 135 (1)
 
MBFT 2015
MBFT 2015MBFT 2015
MBFT 2015
 
The Adriatic Group's Marko Polo Bridge Proposal
The Adriatic Group's  Marko Polo Bridge Proposal The Adriatic Group's  Marko Polo Bridge Proposal
The Adriatic Group's Marko Polo Bridge Proposal
 
Keynote Speaker Mr. Christos Pipitsoulis
Keynote Speaker Mr. Christos PipitsoulisKeynote Speaker Mr. Christos Pipitsoulis
Keynote Speaker Mr. Christos Pipitsoulis
 
CEF 2016
CEF 2016CEF 2016
CEF 2016
 
Transexpress Pres. English
Transexpress Pres. EnglishTransexpress Pres. English
Transexpress Pres. English
 
The Railway Infrastructure in Bosnia and Herzegovina
The Railway Infrastructure in Bosnia and HerzegovinaThe Railway Infrastructure in Bosnia and Herzegovina
The Railway Infrastructure in Bosnia and Herzegovina
 

Similaire à Euro rail eng_full

François davenne intergovernmental organisation for international carriage ...
François davenne  intergovernmental organisation for international carriage ...François davenne  intergovernmental organisation for international carriage ...
François davenne intergovernmental organisation for international carriage ...
Ibrahim Al-Hudhaif
 
Current situation and future opportunities for PPP in CEE region
Current situation and future opportunities for PPP in CEE region Current situation and future opportunities for PPP in CEE region
Current situation and future opportunities for PPP in CEE region
bartoszmysiorski
 
Current situation and future opportunities for PPP in CEE region
Current situation and future opportunities for PPP in CEE regionCurrent situation and future opportunities for PPP in CEE region
Current situation and future opportunities for PPP in CEE region
bartoszmysiorski
 
Business park in_lviv_bez_tpf
Business park in_lviv_bez_tpfBusiness park in_lviv_bez_tpf
Business park in_lviv_bez_tpf
investinlviv
 
South East Europe Rail conference - Thomas Wimroither
South East Europe Rail conference -  Thomas WimroitherSouth East Europe Rail conference -  Thomas Wimroither
South East Europe Rail conference - Thomas Wimroither
Russell Publishing
 

Similaire à Euro rail eng_full (20)

Progress in implementation of the eu ua association agreement on transport is...
Progress in implementation of the eu ua association agreement on transport is...Progress in implementation of the eu ua association agreement on transport is...
Progress in implementation of the eu ua association agreement on transport is...
 
ERRAC and how proposals for Horizon 2020 have been developed - Andy Doherty
ERRAC and how proposals for Horizon 2020 have been developed - Andy DohertyERRAC and how proposals for Horizon 2020 have been developed - Andy Doherty
ERRAC and how proposals for Horizon 2020 have been developed - Andy Doherty
 
Legislative Developments in Rail Transport in 2010
Legislative Developments in Rail Transport in 2010Legislative Developments in Rail Transport in 2010
Legislative Developments in Rail Transport in 2010
 
Kari rouhonen
Kari rouhonenKari rouhonen
Kari rouhonen
 
Media seminar s. ouaki
Media seminar   s. ouakiMedia seminar   s. ouaki
Media seminar s. ouaki
 
François davenne intergovernmental organisation for international carriage ...
François davenne  intergovernmental organisation for international carriage ...François davenne  intergovernmental organisation for international carriage ...
François davenne intergovernmental organisation for international carriage ...
 
Current situation and future opportunities for PPP in CEE region
Current situation and future opportunities for PPP in CEE region Current situation and future opportunities for PPP in CEE region
Current situation and future opportunities for PPP in CEE region
 
Current situation and future opportunities for PPP in CEE region
Current situation and future opportunities for PPP in CEE regionCurrent situation and future opportunities for PPP in CEE region
Current situation and future opportunities for PPP in CEE region
 
Business park in_lviv_bez_tpf
Business park in_lviv_bez_tpfBusiness park in_lviv_bez_tpf
Business park in_lviv_bez_tpf
 
Hydrogen, fuel cells and Electro-mobility in European Regions
Hydrogen, fuel cells and  Electro-mobility in European Regions Hydrogen, fuel cells and  Electro-mobility in European Regions
Hydrogen, fuel cells and Electro-mobility in European Regions
 
Aurh weastflows-atlas-english-sept2013
Aurh weastflows-atlas-english-sept2013Aurh weastflows-atlas-english-sept2013
Aurh weastflows-atlas-english-sept2013
 
South East Europe Rail conference - Thomas Wimroither
South East Europe Rail conference -  Thomas WimroitherSouth East Europe Rail conference -  Thomas Wimroither
South East Europe Rail conference - Thomas Wimroither
 
CV Rezart Arkaxhiu_Sep2018
CV Rezart Arkaxhiu_Sep2018CV Rezart Arkaxhiu_Sep2018
CV Rezart Arkaxhiu_Sep2018
 
North sea baltic corridor c. trautmann
North sea baltic corridor   c. trautmannNorth sea baltic corridor   c. trautmann
North sea baltic corridor c. trautmann
 
3 laichanrasti
 3 laichanrasti 3 laichanrasti
3 laichanrasti
 
Opening passenger rail transport to competition in Finland, Minister Anne Ber...
Opening passenger rail transport to competition in Finland, Minister Anne Ber...Opening passenger rail transport to competition in Finland, Minister Anne Ber...
Opening passenger rail transport to competition in Finland, Minister Anne Ber...
 
EU_White Paper_Presentation of the White Paper Andres GALVAN RAMIREZ.ppt
EU_White Paper_Presentation of the White Paper Andres GALVAN RAMIREZ.pptEU_White Paper_Presentation of the White Paper Andres GALVAN RAMIREZ.ppt
EU_White Paper_Presentation of the White Paper Andres GALVAN RAMIREZ.ppt
 
"European Commission Open Source Observatory and Repository Project" by Ismae...
"European Commission Open Source Observatory and Repository Project" by Ismae..."European Commission Open Source Observatory and Repository Project" by Ismae...
"European Commission Open Source Observatory and Repository Project" by Ismae...
 
Projects and activities of the City of Pécs Concerning Sustainable Public Tra...
Projects and activities of the City of Pécs Concerning Sustainable Public Tra...Projects and activities of the City of Pécs Concerning Sustainable Public Tra...
Projects and activities of the City of Pécs Concerning Sustainable Public Tra...
 
Perspectives on the European Railway Standardisation System
Perspectives on the European Railway Standardisation SystemPerspectives on the European Railway Standardisation System
Perspectives on the European Railway Standardisation System
 

Plus de investinlviv

львів з ним варто познайомитися
львів з ним варто познайомитисяльвів з ним варто познайомитися
львів з ним варто познайомитися
investinlviv
 
львів 2012 для міжнародників eng
львів 2012 для міжнародників engльвів 2012 для міжнародників eng
львів 2012 для міжнародників eng
investinlviv
 
Katalog vilnyh vyrobnychyh_ploshch
Katalog vilnyh vyrobnychyh_ploshchKatalog vilnyh vyrobnychyh_ploshch
Katalog vilnyh vyrobnychyh_ploshch
investinlviv
 
Catalogue of existing_industrial_and_warehousing_premises
Catalogue of existing_industrial_and_warehousing_premisesCatalogue of existing_industrial_and_warehousing_premises
Catalogue of existing_industrial_and_warehousing_premises
investinlviv
 
Booklet industrial park_2
Booklet industrial park_2Booklet industrial park_2
Booklet industrial park_2
investinlviv
 
Booklet industrial park_ua
Booklet industrial park_uaBooklet industrial park_ua
Booklet industrial park_ua
investinlviv
 
Industrial park beztpf
Industrial park beztpfIndustrial park beztpf
Industrial park beztpf
investinlviv
 
Залучення інвестицій на місцевому рівні
Залучення інвестицій на місцевому рівніЗалучення інвестицій на місцевому рівні
Залучення інвестицій на місцевому рівні
investinlviv
 
Залучення інвестицій на місцевому рівні eng
Залучення інвестицій на місцевому рівні engЗалучення інвестицій на місцевому рівні eng
Залучення інвестицій на місцевому рівні eng
investinlviv
 

Plus de investinlviv (14)

львів з ним варто познайомитися
львів з ним варто познайомитисяльвів з ним варто познайомитися
львів з ним варто познайомитися
 
львів 2012 для міжнародників eng
львів 2012 для міжнародників engльвів 2012 для міжнародників eng
львів 2012 для міжнародників eng
 
Strategy Lviv
Strategy LvivStrategy Lviv
Strategy Lviv
 
Katalog vilnyh vyrobnychyh_ploshch
Katalog vilnyh vyrobnychyh_ploshchKatalog vilnyh vyrobnychyh_ploshch
Katalog vilnyh vyrobnychyh_ploshch
 
Catalogue of existing_industrial_and_warehousing_premises
Catalogue of existing_industrial_and_warehousing_premisesCatalogue of existing_industrial_and_warehousing_premises
Catalogue of existing_industrial_and_warehousing_premises
 
Annex 3 01
Annex 3 01Annex 3 01
Annex 3 01
 
Booklet industrial park_2
Booklet industrial park_2Booklet industrial park_2
Booklet industrial park_2
 
Annex 3 1_ua_dorogy
Annex 3 1_ua_dorogyAnnex 3 1_ua_dorogy
Annex 3 1_ua_dorogy
 
Booklet industrial park_ua
Booklet industrial park_uaBooklet industrial park_ua
Booklet industrial park_ua
 
Eurorail ukr
Eurorail ukrEurorail ukr
Eurorail ukr
 
Industrial park beztpf
Industrial park beztpfIndustrial park beztpf
Industrial park beztpf
 
World bank macro update october 2014 eng fin
World bank macro update october 2014 eng finWorld bank macro update october 2014 eng fin
World bank macro update october 2014 eng fin
 
Залучення інвестицій на місцевому рівні
Залучення інвестицій на місцевому рівніЗалучення інвестицій на місцевому рівні
Залучення інвестицій на місцевому рівні
 
Залучення інвестицій на місцевому рівні eng
Залучення інвестицій на місцевому рівні engЗалучення інвестицій на місцевому рівні eng
Залучення інвестицій на місцевому рівні eng
 

Dernier

VIP Call Girls Mehsana 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Mehsana 7001035870 Whatsapp Number, 24/07 BookingVIP Call Girls Mehsana 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Mehsana 7001035870 Whatsapp Number, 24/07 Booking
dharasingh5698
 
Editing progress 20th march.docxxxxxxxxx
Editing progress 20th march.docxxxxxxxxxEditing progress 20th march.docxxxxxxxxx
Editing progress 20th march.docxxxxxxxxx
MollyBrown86
 
Terna - 1Q 2024 Consolidated Results Presentation
Terna - 1Q 2024 Consolidated Results PresentationTerna - 1Q 2024 Consolidated Results Presentation
Terna - 1Q 2024 Consolidated Results Presentation
Terna SpA
 
VIP Call Girls Kheda 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Kheda 7001035870 Whatsapp Number, 24/07 BookingVIP Call Girls Kheda 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Kheda 7001035870 Whatsapp Number, 24/07 Booking
dharasingh5698
 
💚😋 jamshedpur Escort Service Call Girls, 9352852248 ₹5000 To 25K With AC💚😋
💚😋 jamshedpur Escort Service Call Girls, 9352852248 ₹5000 To 25K With AC💚😋💚😋 jamshedpur Escort Service Call Girls, 9352852248 ₹5000 To 25K With AC💚😋
💚😋 jamshedpur Escort Service Call Girls, 9352852248 ₹5000 To 25K With AC💚😋
nirzagarg
 
Corporate Presentation Probe Canaccord Conference 2024.pdf
Corporate Presentation Probe Canaccord Conference 2024.pdfCorporate Presentation Probe Canaccord Conference 2024.pdf
Corporate Presentation Probe Canaccord Conference 2024.pdf
Probe Gold
 

Dernier (20)

Best investment platform in india-Falcon Invoice Discounting
Best investment platform in india-Falcon Invoice DiscountingBest investment platform in india-Falcon Invoice Discounting
Best investment platform in india-Falcon Invoice Discounting
 
VIP Call Girls Mehsana 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Mehsana 7001035870 Whatsapp Number, 24/07 BookingVIP Call Girls Mehsana 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Mehsana 7001035870 Whatsapp Number, 24/07 Booking
 
VVIP Pune Call Girls Handewadi WhatSapp Number 8005736733 With Elite Staff An...
VVIP Pune Call Girls Handewadi WhatSapp Number 8005736733 With Elite Staff An...VVIP Pune Call Girls Handewadi WhatSapp Number 8005736733 With Elite Staff An...
VVIP Pune Call Girls Handewadi WhatSapp Number 8005736733 With Elite Staff An...
 
Financial Results for the Fiscal Year Ended March 2024
Financial Results for the Fiscal Year Ended March 2024Financial Results for the Fiscal Year Ended March 2024
Financial Results for the Fiscal Year Ended March 2024
 
Teekay Corporation Q1-24 Earnings Results
Teekay Corporation Q1-24 Earnings ResultsTeekay Corporation Q1-24 Earnings Results
Teekay Corporation Q1-24 Earnings Results
 
Diligence Checklist for Early Stage Startups
Diligence Checklist for Early Stage StartupsDiligence Checklist for Early Stage Startups
Diligence Checklist for Early Stage Startups
 
Western Copper and Gold - May 2024 Presentation
Western Copper and Gold - May 2024 PresentationWestern Copper and Gold - May 2024 Presentation
Western Copper and Gold - May 2024 Presentation
 
AMG Quarterly Investor Presentation May 2024
AMG Quarterly Investor Presentation May 2024AMG Quarterly Investor Presentation May 2024
AMG Quarterly Investor Presentation May 2024
 
Editing progress 20th march.docxxxxxxxxx
Editing progress 20th march.docxxxxxxxxxEditing progress 20th march.docxxxxxxxxx
Editing progress 20th march.docxxxxxxxxx
 
Osisko Gold Royalties Ltd - Q1 2024 Results
Osisko Gold Royalties Ltd - Q1 2024 ResultsOsisko Gold Royalties Ltd - Q1 2024 Results
Osisko Gold Royalties Ltd - Q1 2024 Results
 
Osisko Development - Investor Presentation - May 2024
Osisko Development - Investor Presentation - May 2024Osisko Development - Investor Presentation - May 2024
Osisko Development - Investor Presentation - May 2024
 
Terna - 1Q 2024 Consolidated Results Presentation
Terna - 1Q 2024 Consolidated Results PresentationTerna - 1Q 2024 Consolidated Results Presentation
Terna - 1Q 2024 Consolidated Results Presentation
 
Teekay Tankers Q1-24 Earnings Presentation
Teekay Tankers Q1-24 Earnings PresentationTeekay Tankers Q1-24 Earnings Presentation
Teekay Tankers Q1-24 Earnings Presentation
 
VVIP Pune Call Girls Parvati Gaon WhatSapp Number 8005736733 With Elite Staff...
VVIP Pune Call Girls Parvati Gaon WhatSapp Number 8005736733 With Elite Staff...VVIP Pune Call Girls Parvati Gaon WhatSapp Number 8005736733 With Elite Staff...
VVIP Pune Call Girls Parvati Gaon WhatSapp Number 8005736733 With Elite Staff...
 
ITAU EQUITY_STRATEGY_WARM_UP_20240505 DHG.pdf
ITAU EQUITY_STRATEGY_WARM_UP_20240505 DHG.pdfITAU EQUITY_STRATEGY_WARM_UP_20240505 DHG.pdf
ITAU EQUITY_STRATEGY_WARM_UP_20240505 DHG.pdf
 
VIP Call Girls Kheda 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Kheda 7001035870 Whatsapp Number, 24/07 BookingVIP Call Girls Kheda 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Kheda 7001035870 Whatsapp Number, 24/07 Booking
 
💚😋 jamshedpur Escort Service Call Girls, 9352852248 ₹5000 To 25K With AC💚😋
💚😋 jamshedpur Escort Service Call Girls, 9352852248 ₹5000 To 25K With AC💚😋💚😋 jamshedpur Escort Service Call Girls, 9352852248 ₹5000 To 25K With AC💚😋
💚😋 jamshedpur Escort Service Call Girls, 9352852248 ₹5000 To 25K With AC💚😋
 
Collective Mining | Corporate Presentation - May 2024
Collective Mining | Corporate Presentation - May 2024Collective Mining | Corporate Presentation - May 2024
Collective Mining | Corporate Presentation - May 2024
 
Dubai Call Girls O525547&19 Calls Girls In Dubai (L0w+Charger)
Dubai Call Girls O525547&19 Calls Girls In Dubai (L0w+Charger)Dubai Call Girls O525547&19 Calls Girls In Dubai (L0w+Charger)
Dubai Call Girls O525547&19 Calls Girls In Dubai (L0w+Charger)
 
Corporate Presentation Probe Canaccord Conference 2024.pdf
Corporate Presentation Probe Canaccord Conference 2024.pdfCorporate Presentation Probe Canaccord Conference 2024.pdf
Corporate Presentation Probe Canaccord Conference 2024.pdf
 

Euro rail eng_full

  • 2. EURORAIL Project Initiator: Ministry of transport and communications of Ukraine Lviv Oblast State Administration Lviv City Council Cost: 500 mln. EUR Terms: 2010-2015 Prerequisites: • Discrepancy of Ukrainian and CIS countries’ railways (1520) with the EU railway standard UIC (1435) • Increased demand for fast and qualified communication between Ukraine (CIS) and Europe
  • 4. Project main statements Project subject: The construction of 84 km long EU standard rail track and all required infrastructure between Lviv and Polish- Ukrainian border (Prezemysl/Mostyska and Krakivets). Goal: to provide high speed railway connection between Lviv and Polish-Ukrainian border within III Euro transport corridor. Mechanism: Concession for construction and further operation of the rail track and its infrastructure. Participants: Cabinet of Ministers of Ukraine, Ministry of transport and communication of Ukraine, Lviv Oblast State Administration, Lviv City Council, private companiesЛьвівська обласна Рада, Львівська міська Рада, приватні компанії. Participation of Ministry of infrastructure of Poland is also needed.
  • 5. Implementation algorithm 1. JSC “Evrokoliya” set up by experienced in this field companies. 2. The Cabinet of Ministers of Ukraine is to issue the Resolution regarding “Eurorail” Project implementation and assign core Ministry (Ministry of transport and communication of Ukraine) to be responsible for its realization. 3. The Concession Agreement is to be signed with the Company-contractor identified through the Tender. 4. The Concession Agreement is to be prepared and signed by Ministry of transport and communication of Ukraine, Lviv Oblast State Administration, Lviv City Council and JSC “Evrokoliya” and is to contain Project implementation mechanisms. 5. JSC “Evrokoliya” attracts all required financial funds and contractors for the Project implementation. 6. After the project is implemented it is to be managed and used by Ministry of transport and communication of Ukraine. The last is to make payments for the benefit of JSC “Evrokoliya”.
  • 6. Project scheme JSC “Eurokoliya Ministry of transport “Eurokoliya” Specifications Rail track and infrastructure operation Ownership for the rail track and the part of infrastructure JSC Plots ІInformation Ministry of transport Lviv Oblast Administration Investments Lviv City Council Founders Construction process Ownership for the part of infrastructure Euro rail track usage payments according to the Concession Agreement as the investments return source
  • 7. JSC “Evrokoliya” set up  “Evrokoliya” is to be joint-stock company  JSC “Evrokoliya” founders (companies) are to be able to provide qualified Project implementation. Company’s dominant task – is to develop contract and legal platform for its further activity (including possible relations coordination between core Ministers of Ukraine and Poland and between Lviv Oblast Administration and Lviv City Council).  JSC “Evrokoliya” is to hold a research on a Project, provide its feasibility study and approve the Project with all Participants.  The last stage – Project Business Plan, investments attraction and Project implementation.
  • 8. Concession Agreement Main regulations:  Project participant’s collaboration mechanism.  Participant’s obligations (land plots, information, specifications provision for the Project by its Participants).  Constructed object’s ownership (tracks, terminals, technical buildings, warehouses etc.).  Relations among Project Participants on the after construction stage when the rail track and its infrastructure will be operated.  Rail track and its infrastructure usage payments as the investments return source
  • 9. Implementation phases  Phase I: 2008 - 2009 •Pre-feasibility study • Memorandum of Understanding with Dutch MOVARES and NEA for pre-feasibility study, 133,000 EUR attracted from the Dutch government. •Additional investment required for Phase 1 – 250,000 eur  Phase II: 2009 – 2010 •Pre-feasibility study presentation to all the stakeholders for final decision-making •The establishment of the International Project Implementation Consortium •Finalizing Project Finance Structure and Legal Model (PPP)  Phase III: 2010 – 2013 Project Implementation: •Construction the rail track from Polish/Ukrainian border to Lviv (86 km) •New rail infrastructure development, including modern passenger and goods terminal near and in Lviv
  • 10. Project impact assessment Increase of passenger and cargo flows Maximum shortening of the travel time Social and economic development of the region Ukraine’s integration with main European cities
  • 11. Leonid Bogdanov, CEO bogdanov@unidevelop.com Yuryi Stetskiv, CFO stetskiv@unidevelop.com Kyiv, Ukraine 01133 9 Lesi Ukrainki Blvd, Tel.: +38 044 585 10 80 Fax: +38 044 585 10 79 www.unidevelop.com