SlideShare a Scribd company logo
1 of 50
Power Plant Economics

                                                                       Carl Bozzuto
ALSTOM © 2006. We reserve all rights in this document and in the information contained therein.
  Reproduction, use or disclosure to third parties without express authority is strictly forbidden
Overview


    Economic Terms
    Economic Methodologies
    Cost Models
    Pitfalls
    Cost Studies
    Results
    Some words about CO2
    Conclusions



2
Economic Terms

    Return on Sales = Net after tax/Sales revenue
    Asset turnover = Sales revenue/Assets
    Leverage = Assets/Equity
    PE Ratio = Stock Market Price (per share)/Net after tax (per share)
    Market/Book Ratio = Stock Market Price (per share)/Equity (per share)
    Return on Assets = Net/Assets
    Return on Equity = Net/Equity
    Discount Rate = Time value of Money
    Net Present Value = Present Value of Future Returns @ Discount Rate
    Internal Rate of Return = Discount Rate which yields an NPV of zero
3
Why do we care?




    ROS x Turnover x Leverage x PE = Market/Book
    – Listed firms want to increase stock price (shareholder value)

    The Discount Rate considers risk as well interest rates and inflation
    – The discount rate is often a project hurdle rate

    Many firms use IRR for project evaluation
    Return on Equity is a key consideration for any investment




4
Economic Methodologies



    A Power Plant is a long lived asset that is capital intensive.
    It also takes a long time to acquire the asset.
     – Construction times range from 2 years for a combined cycle plant to 3 – 4
       years for a coal plant to 10 years for a nuclear plant.

    A key issue is treating the time value of money.
    Depreciation is a key consideration.
    Different entities treat these considerations differently.




5
Plant Cost

    Plant Cost is exceptionally site specific.
     – Labor costs
     – Shipping and material costs
     – Environmental costs
     – Site preparation costs
     – Site impacts on performance
     – Fuel costs
     – Cooling water type and availability
     – Connection costs

    Today, we really don’t know what the final cost of a plant will be.
     – Raw material escalation
     – Shipping costs
     – Labor costs
6
Plant Cost Terminology
    There are numerous ways to talk about plant cost.
    – Engineered, Procured, and Constructed (EPC cost)
       • Most commonly used today
       • Fits best with Merchant Plant model
       • Does not included Owner’s Costs
             Ø Land, A/E costs, Owner’s Labor, Interconnection, Site Permits, PR, etc.
        • Can often be obtained as a fixed price contract for proven technology
    – Equipment Cost
       • Generally the cost to fabricate, deliver, and construct the plant equipment
    – Overnight Cost
       • Either the equipment cost or the EPC cost with the NPV of interest during
         construction. This was used in the 70s and 80s to compare coal plants
         with nuclear plants due to the difference in construction times.
    – Total Installed Cost (TIC)
       • The total cost of the equipment and engineering including interest during
          construction in present day dollars. This is the cost that a utility would
          record on its books without the cost of land and other home office costs.
7   – Total Plant Cost (TPC) – includes all costs
Economic Methodologies
    Simple payback
    – The number of years it takes to pay back the original investment

    Return on Equity
    – For regulated utilities, the ROE is set by the regulatory body. The equity is determined
      by the total plant cost being allowed in the rate base. The equity portion is determined by
      the leverage of the company. The ROE is applied to the equity and added to the cost in
      determining the cost of electricity and thus the rate to be charged to the customer.

    Capital Charge Rate
    – This is the rate to be charged on the capital cost of the plant in order to convert capital
      costs (ie investment) into operating costs (or annual costs). This rate can be estimated
      in a number of ways. This rate generally includes most of our ignorance about the future
      (ie interest rates, ROE, inflation, taxes, etc.)

    Discounted Cash Flow Analysis
    – This method is preferred by economists and developers. A spread sheet is set up to
      estimate the cash flows over the life of the project. An IRR can be calculated if an
      electricity price is known (or estimated).
8
Economic Methodologies

    All of these methods can be made equivalent to one another for
    any given set of assumptions.
    – A simple payback time can be selected to give the same cost of electricity
      (COE) as the other methods.
    – A return on equity can be selected to give the same COE.
    – A capital charge rate can be selected to give the same COE.
    – The Discounted Cash Flow method is considered the most accurate. However,
      there are still a considerable number of assumptions that go into such a model
      such as the discount rate, inflation rate, tax rate, interest rates, fuel prices,
      capacity factors, etc. that the accuracy is typically less in reality.

    The Independent Power Producer pioneered the use of the DCF
    model for smaller power projects.
    – In this model, the developer attempted to fix as many costs as possible by
      obtaining fixed price contracts for all of the major cost contributors. These
      included the EPC price, the fuel contract, the Operations & Maintenance
      Contract (O&M), and the Power Purchase Agreement.
9
Cost Models

     Capital Charge Rate Model
     – The goal is to select a capital charge rate that typically covers most of the
       future unknowns. This rate is applied to the EPC cost in order to provide an
       annual cost that will provide the desired return on equity.
     – In its simplest form, one can use the following:
         • Interest rate on debt - 8 - 10% for utility debt
         • ROE - 10 – 12 % for most utilities
         • Inflation rate - 3 – 4%
         • Depreciation - 2 – 4%
         • Taxes and Insurance - 3 – 5%
         • Risk - ? (typically 3% for mature technologies, higher for others)
     – Another approach would be to run a number of DCF cases with different
       assumptions and then assess a capital charge rate that is consistent.
     – A reasonable number for a regulated utility is 20% (one significant figure)



10
Discounted Cash Flow Model

 The goal is to estimate the cash flows of the project over the life of the
 plant. A significant number of variables are involved and must be
 estimated or assumed in order to make the spread sheet work.
     – Input variables include net output, capacity factor, availability, net plant heat rate
       (HHV), degradation, EPC price, construction period, insurance, initial
       spares/consumables, fixed O&M, variable O&M, fuel price, fuel heating value (HHV),
       financial closing date, reference date, depreciation, analysis horizon, owner’s
       contingency, development costs, permitting costs, advisory/legal fees, start up fuel, fuel
       storage, inflation rates, interest rates, debt level, taxes, construction cash flow,
       discount rate, and ROE.
     – A detailed cash flow analysis is set up for each year of the project. For shorter term
       projects, these estimated cash flows are more realistic. For longer term projects, the
       accuracy is debatable.
     – Since the cash generation may be variable, it is often desirable to perform some kind of
       levelizing function to generate an average that is understandable. There are risks
       associated with this step.
     – The most common application is to assume a market price for electricity and then try to
       maximize the IRR for the project.
11
Discounted Cash Flow Model

 The model assumes that we know a lot about the project and the
 number of variables. What if we don’t know very much about the future
 project? For example, what if we don’t know where the plant will be
 located? What if we don’t know which technology we will use for the
 plant? What if we want to compare technologies on a consistent basis?
 One approach is to run the DCF model “backwards”. In this approach,
 we stipulate a required return and calculate an average cost of
 electricity needed to generate that return. We still need to make a lot of
 assumptions, but at least we can be consistent.
 One advantage of having such spread sheet programs is that a wide
 range of scenarios and assumptions can be tested. This approach
 gives us a little more insight into the decision making process and
 helps us understand why some entities might chose one technology
 over another.

12
Typical Construction Period w/Cash Drawdown

1. C ulativeD dow
    um       raw n

        0

                                 11
                                      13
                                           15
                                                17
                                                     19
                                                          21
                                                               23
                                                                    25
                                                                         27
                                                                              29
                                                                                   31
                                                                                        33
                                                                                             35
                                                                                                  37
                                                                                                       39
                                                                                                            41
                                                                                                                 43
                                                                                                                      45
                                                                                                                           47
             1
                 3
                     5
                         7
                             9

  -100,000


  -200,000


  -300,000


  -400,000


  -500,000


  -600,000




 13
Typical Levelized Cash Flow
4. EndingEquityCashflow


    50,000

         0
               1   3   5   7   9   11   13   15   17   19   21   23   25   27   29   31   33   35   37   39   41
    (50,000)

   (100,000)

   (150,000)

   (200,000)

   (250,000)

   (300,000)

   (350,000)




   14
Pitfalls
 The biggest pitfall is thinking that these numbers are “real”. They are
 only indicative. Just because a computer can calculate numbers to the
 penny does not mean that the numbers are accurate. There is a lot of
 uncertainty due to the number of assumptions that have to be made.
 It is important to understand what the goal and/or objective of the
 analysis is. In the following study, the goal was to compare
 technologies that might be used in the future. This goal is different
 from looking at a near term project where the site, technology, fuel,
 customer, and vendors have already been selected.
 There is no substitute for sound management judgement.
 The analysis itself does not identify the risks. The analyzer must
 consider the risks and ask the appropriate “what if” questions. In the
 following study, over 3,000 spread sheet runs were made in order to
 analyze the comparisons effectively.
 Avoid the “Swiss Watch” mentality.
15
Technology Position and Experience

                    Experience      Major Competitors         Technology
                      Base                                     Maturity
Sub-Critical PC     1,200 GW     Alstom,MHI, B&W, FW            Mature
                                 and Several Others
Super-Critical PC    265 GW      Alstom,MHI, B&W                Proven
PFBC                 0.5 GW                                     Demo
IGCC                  1 GW       GE, Shell, Conoco Phillips     Demo
CFB                   20 GW      Alstom, FW                     Proven
NGCC                200 GW GT    GE, Siemens, Alstom            Mature
                    100 GW ST




16
Baseline Economic Inputs – 1997 400 MW Class


                      Subcritical Supercritical P800 PFBC   IGCC
      Size               400         400         400        400
      (MW)
      Capital Cost      1,000       1,050        1,100      1,380
      ($/ kW)
      Heat Rate         9,374       8,385        8,405      8,700
      (Btu/ kWh)
      Availability       80          80           80         80
      (%)
      Cycle Time         36          36           48         48
      (months)
      Fixed O&M         31.14       32.11        33.69      39.08
      ($/ kW)
      Variable O&M      0.77         0.69        1.01       0.42
      (mills/ kWh)

            Source:      Market     Market      ABB         GE


 17
Baseline Economic Inputs – 1997 100 MW Class


                      CFB      P200 PFBC   NGCC
       Size            100        100      270
       (MW)
       Capital Cost   1,000      1,200     500
       ($/ kW)
       Heat Rate      10,035     8,815     6,640
       (Btu/ kWh)
       Availability     80        80        80
       (%)
       Cycle Time       30        32        24
       (months)
       Fixed O&M      44.13      55. 41    16.92
       ($/ kW)
       Variable O&M    1.18      1.06      0.01
       (mills/ kWh)
     Source:          Market        ABB    PGT


18
Baseline Economic Inputs - 2005 400 MW Class

                      Subcritical Supercritical P800 PFBC IGCC
     Size               400         400         400      400
     (MW)
     Capital Cost       750         750         750      1,100
     ($/ kW)
     Heat Rate          8,750      8,125       8,030     7,800
     (Btu/ kWh)
     Availability        80          80          80         80
     (%)
     Cycle Time          24          24          30         36
     (months)
     Fixed O&M          26.33      26.33       26.95     33.69
     ($/ kW)
     Variable O&M       0.81        0.75        1.05     0.37
     (mills/ kWh)
            Source:      BA Plan    BA Plan   SECAR    GE


19
Baseline Economic Inputs – 2005 100 MW Class


                        CFB       P200 PFBC   NGCC
       Size             100          100       270
       (MW)
       Capital Cost     725          850       325
       ($/ kW)
       Heat Rate        9,350       8,530      6195
       (Btu/ kWh)
       Availability      80          80         80
       (%)
       Cycle Time        18          22         18
       (months)
       Fixed O&M        38.84       48.67      16.44
       ($/ kW)
       Variable O&M     1.15        1.12       0.01
       (mills/ kWh)

              Source:   BA Plan     SECAR     PGT


 20
Financing Scenario Summary

     Loan structure         Municipal Utility IPP 1 IPP 2 Industrial
     Horizon (years)           40       30     15     15      10
     Interest rate (%)        5.75     7.75   8.75   8.75     8.25
     Loan term (years)         40       30      9     9       10
     Depreciation (years)      40       30     15     15      10
     Equity (%)                0        50     30     50      75
     Debt (%)                 100       50     70     50      25
     ROE (%)                  n/a       10     20     20      23
     Taxes (%)                 0        20     30     30      30


21
Comparison of Financing Scenarios
                                                           400 MW Subcritical PC Fired Plant
                            10.0


                             9.0       Financial
                                       Fixed O&M
                             8.0       Variable O&M
                                                                                    have
                                       Fuel
                                                                  Finan  cial costs COE
                                                                                 e on
                             7.0
                                                                 majo r influenc
 Levelized Tariff, c/ kWh




                             6.0


                             5.0


                             4.0


                             3.0


                             2.0


                             1.0


                             0.0
                                   Municipal           Utility            IPP-1            IPP-2   Industrial

                                                                 Financing Arrangement
22
Comparison of Technologies
                                                                Municipal Financing - 1997
                                                              (80% CF, $1.20 coal and $3.00 gas)
                            4.0
                                           Financial
                                           Fixed O&M
                            3.5            Variable O&M
                                           Fuel

                            3.0
 Levelized Tariff, c/ kWh




                            2.5


                            2.0


                            1.5


                            1.0


                            0.5


                            0.0
                                  Subcrit PC      Super PC     P-800        IGCC           P-200       CFB       NGCC
                                  (400 MW)        (400 MW)   (400 MW)     (400 MW)       (100 MW)   (100 MW)   (270 MW)

23
Comparison of Technologies
                                                              Utility Financing - 1997
                                                           (80% CF, $1.20 coal and $3.00 gas)
                            5.0


                            4.5
                                                                                                            Financial
                                                                                                            Fixed O&M
                            4.0                           NGCC lo                                           Variable O&M
                                                                  oks bett
                                                            but wor        er on to                         Fuel
                                                                    se on di        tal COE
                                                                                            ,
 Levelized Tariff, c/ kWh




                            3.5                                              spatch b
                                                                                      asis.
                                                 ncial cos t
                            3.0
                                     Hi gher fina      ce on
                                    increase s influen
                            2.5
                                               CO E
                            2.0


                            1.5


                            1.0


                            0.5


                            0.0
                                  Subcrit PC   Super PC     P-800        IGCC           P-200       CFB         NGCC
                                  (400 MW)     (400 MW)   (400 MW)     (400 MW)       (100 MW)   (100 MW)     (270 MW)

24
Comparison of Technologies
                                                                 IPP(1) Financing - 1997
                                                              (80% CF, $1.20 coal and $3.00 gas)
                            8.0
                                          Financial
                                          Fixed O&M
                            7.0           Variable O&M
                                          Fuel


                            6.0
 Levelized Tariff, c/ kWh




                            5.0


                            4.0


                            3.0


                            2.0


                            1.0


                            0.0
                                  Subcrit PC      Super PC     P-800         IGCC           P-200       CFB       NGCC
                                  (400 MW)        (400 MW)   (400 MW)      (400 MW)       (100 MW)   (100 MW)   (270 MW)

25
Comparison of Technologies
                                                                     IPP(2) Financing - 1997
                                                                  (80% CF, $1.20 coal and $3.00 gas)
                            9.0
                                          Financial
                                          Fixed O&M
                            8.0           Variable O&M
                                          Fuel

                            7.0
 Levelized Tariff, c/ kWh




                            6.0


                            5.0


                            4.0


                            3.0


                            2.0


                            1.0


                            0.0
                                  Subcrit PC          Super PC     P-800        IGCC           P-200       CFB       NGCC
                                  (400 MW)            (400 MW)   (400 MW)     (400 MW)       (100 MW)   (100 MW)   (270 MW)

26
Comparison of Technologies
                                                               Industrial Financing - 1997
                                                              (80% CF, $1.20 coal and $3.00 gas)
                            16.0
                                           Financial
                                           Fixed O&M
                            14.0
                                           Variable O&M
                                           Fuel

                            12.0
 Levelized Tariff, c/ kWh




                            10.0


                             8.0


                             6.0


                             4.0


                             2.0


                             0.0
                                   Subcrit PC     Super PC     P-800         IGCC           P-200       CFB       NGCC
                                   (400 MW)       (400 MW)   (400 MW)      (400 MW)       (100 MW)   (100 MW)   (270 MW)

27
Capacity Factor Effect on COE
                                                     Municipal Financing - 1997
                                                       ($1.20 coal and $3.00 gas)

                              8.0

                                                                                           Subcrit PC
                                                                                           Supercrit PC
                              7.0                                                          P-800
                                                                                           IGCC

                                                    D is                                   P-200
                                                       patc
 Levelized Tariff, (c/ kWh)




                                                                                          CFB
                              6.0                           h ra
                                                       hav       te a                     NGCC
                                                           em
                                                               ajor nd/or c
                                                                    influ apac
                                                                         en c     i
                              5.0                                             e on ty facto
                                                                                   COE r

                              4.0




                              3.0




                              2.0
                                20%   30%   40%       50%          60%         70%   80%       90%        100%

                                                           Capacity Factor, (%)
28
Impact of Availability on COE
                                                                   Municipal Financing - 1997
                                                                             ($1.20 coal)
                                  3.5


                                  3.4


                                  3.3                                                                          Subcrit PC
                                            5 days lost availability makes                                     Supercrit PC
     Levelized Tariff, (c/ kWh)




                                  3.2       sub and supercritical equal.

                                  3.1


                                  3.0


                                  2.9


                                  2.8
                                                                        ~5 days

                                  2.7


                                  2.6


                                  2.5
                                   6,500   6,600   6,700   6,800     6,900        7,000     7,100   7,200   7,300     7,400   7,500

                                                                      Capacity, (hrs/ year)
29
Sensitivity Analysis
                                                                Subcritical PC
                                                     1997 IPP1 Financing - $1.20 coal
                      20%
                                                                                   a nd
                                                                  e in availability n COE
                                                     In %, chang      est influe
                                                                                 nce o
                      15%
                                                               e high
                                                 EPC price hav
                      10%
 Change in COE, (%)




                       5%


                       0%


                      -5%


                      -10%                    Availability
                                              EPC price
                                              Plant heat rate
                      -15%                    Fixed O&M
                                              Cycle time
                                              Var O&M

                      -20%
                         -20%   -15%   -10%             -5%           0%         5%     10%   15%   20%

                                                        Percent Variable Change
30
Sensitivity Analysis
                                                             NGCC
                                                  1997 IPP1 Financing - $3.00 gas
                      20%
                                                                                    and
                                                                  in av  ailability
                      15%
                                               NG C C % , change       fluence o
                                                                                  n COE
                                          For                  e st i n
                                                     have high
                      10%
                                         efficiency
 Change in COE, (%)




                       5%


                       0%


                      -5%


                      -10%                Availability
                                          EPC price
                                          Plant heat rate
                                          Fixed O&M
                      -15%
                                          Cycle time
                                          Var O&M

                      -20%
                         -20%   -15%   -10%          -5%        0%           5%     10%   15%   20%

                                                     Percent Variable Change
31
gh
                                                                                                     NGCC hi
                                                            Comparison of Technologies
                                                     China 1997 Municipal Financing Conditions                 el
                                                                ($1.80 coal and $5.00 LNG)           due to fu
                              4.0                                                                       cost

                                                                     ta nt
                              3.5
                                                        t less impor
                                             First cos        e to high
                                                                         c os t
                                                      tive du
                              3.0         f uel sensi
 Levelized Tariff, (c/ kWh)




                              2.5


                              2.0


                              1.5


                              1.0                                                                          Financial
                                                                                                           Fixed O&M
                                                                                                           Variable O&M
                              0.5
                                                                                                           Fuel


                              0.0
                                    Subcrit     Supercrit      P-800          IGCC           P-200   CFB               NGCC
                                     PC           PC


32
Comparison of Technologies
                                                           China 1997 IPP Financing Conditions
                                                                 ($1.80 coal and $5.00 LNG)
                              7.00



                              6.00
 Levelized Tariff, (c/ kWh)




                              5.00



                              4.00



                              3.00



                              2.00
                                                                                                            Financial
                                                                                                            Fixed O&M
                              1.00                                                                          Variable O&M
                                                                                                            Fuel


                              0.00
                                     Subcrit   Supercrit        P-800         IGCC            P-200   CFB               NGCC
                                      PC         PC

33
Comparison of Technologies
                                                          Japan Market Conditions - 1997
                                                                ($2.90 coal and $5.00 LNG)

                            5.0


                            4.5


                            4.0
 Levelized Tariff, c/ kWh




                            3.5


                            3.0


                            2.5


                            2.0
                                                                               r ta nt
                                                                   t less impo
                            1.5                         First cos          to high c
                                                                                       os t                        Financial
                                                                     e due
                                                          l sensitiv
                                                                                                                   Fixed O&M

                            1.0
                                                      fue                                                          Variable O&M
                                                                                                                   Fuel

                            0.5


                            0.0
                                  Subcrit PC   Super PC     P-800         IGCC                 P-200       CFB           NGCC
                                  (400 MW)     (400 MW)   (400 MW)      (400 MW)             (100 MW)   (100 MW)       (270 MW)

34
Net Plant Heat Rate Summary
                                    12,000                                                                                                                                   12%




                                                                                                                                     10,035
                                              9,375
                                                                                                           10%




                                                                                                                                              9,350
                                    10,000                                                                                                                                   10%




                                                                                                                    8,815
                                                      8,750




                                                                                                   8,700




                                                                                                                            8,530
                                                                                  8,405
                                                               8,385
                                                                       8,125




                                                                                          8,030
     Net Plant Heat Rate (Btu/kW)




                                                                                                           7,800




                                                                                                                                                                                   NPHR Improvement (%)
                                     8,000                                                                                                                                   8%




                                                                                                                                                             6,640
                                                                                                                                                                     6,195
                                                      7%                                                                                      7%                     7%
                                     6,000                                                                                                                                   6%


                                                                                          4%
                                     4,000                                                                                                                                   4%

                                                                       3%                                                   3%


                                     2,000                                                                                                            1997                   2%
                                                                                                                                                      2005
                                                                                                                                                      Improvement


                                        0                                                                                                                                    0%
                                             Subcrit PC       Super PC          PFBC-P800           IGCC           PFBC-P200           CFB                    NGCC
                                             (400 MW)         (400 MW)           (400 MW)         (400 MW)          (100 MW)        (100 MW)                (270 MW)



35
Summary of EPC Prices
                             $1,600                                                                                                                               40%




                                                                                          $1,380
                                                                                                                                       1997
                                                                                                                                       2005
                             $1,400                                                                                                    % Decrease                 35%




                                                                                                             $1,200
                                                                                  32%




                                                                         $1,100




                                                                                                   $1,100
                                                        $1,050
                             $1,200                                                                                                                               30%
                                                                                                                      29%
                                       $1,000




                                                                                                                              $1,000
                                                                 29%
                                                                                                                                        28%
     EPC Price ($/kW, net)




                                                                                                                                                                        EPC Decrease (%)
                             $1,000             25%                                                                                                               25%




                                                                                                                      $850
                                                $750




                                                                 $750




                                                                                  $750




                                                                                                                                       $725
                              $800                                                                 20%                                                            20%


                              $600                                                                                                                                15%




                                                                                                                                                    $350
                                                                                                                                                           $325
                              $400                                                                                                                                10%

                                                                                                                                                           7%
                              $200                                                                                                                                5%


                                $0                                                                                                                                0%
                                      Subcrit PC       Super PC         PFBC-P800          IGCC             PFBC-P200           CFB               NGCC
                                      (400 MW)         (400 MW)          (400 MW)        (400 MW)            (100 MW)        (100 MW)           (270 MW)


36
Coal Technology Cost Trends
                                                      Extrapolated to 2005
                             2,000

                             1,800
                                                                                           Subcritical PC
                                                                                           Supercritical PC
                             1,600                                                         P800
                                                                                           P200
                             1,400
     EPC Price ($/kW, net)




                             1,200

                             1,000

                              800

                              600
                                                                          “all
                                                                               4
                              400                                        have 00 MW t
                                                                                the s  echn
                                                                                     ame    olog
                              200                                                        mid     ies
                                                                                             term
                                                                                                   targ
                                0                                                                      et
                                 1989   1991   1993   1995      1997         1999   2001         2003         2005

                                                                Year


37
Market Trends

     Carbon Steel Price Trends



                        175
      Index Base 1982




                        150


                        125


                        100

                         01/02   01/03   01/04      01/05   01/06

                                            Month


38
39
                                                          Spot Nickel




                                                         1.80
                                                         2.20
                                                         2.60
                                                         3.00
                                                         3.40
                                                         3.80
                                                         4.20
                                                         4.60
                                                         5.00
                                                         5.40
                                                         5.80
                                                         6.20
                                                         6.60
                                                         7.00
                                                         7.40
                                                         7.80
                                                         8.20
                                                         8.60
                                                         9.00
                                                         9.40
                                                         9.80
                                                        10.20
                                                        10.60
                                                        11.00
                                                        11.40
                                                        11.80
                                                        12.20
                                                        12.60
                                                        13.00
                                                        13.40
                                                        13.80
                                                        14.20
                                                        14.60
                                                        15.00
                                                        15.40
                                                        15.80
                                                        16.20
                                             January
                                            February
                                              March
                                                April
                                                May
                                                June
                                                 July




                                   2000
                                              August
                                          September
                                             October
                                           November
                                          December
                                             January
                                            February
                                              March
                                                April
                                                 May
                                                June
                                                                                                    Market Trends




                                                 July




                                   2001
                                              August
                                          September
                                             October
                                           November
                                          December
                                             January
                                            February
                                              March
                                                April
                                                 May
                                                June
                                                 July




                                   2002
                                              August
                                          September
                                             October
                                           November
                                          December




     Low Ni
                                             January
                                            February
                                              March
                                                April
                                                 May
                                                June
                                                 July




                                   2003
                                              August
                                          September




                    Month / Year

     Avg. Spot Ni
                                             October
                                           November
                                          December
                                                                        Nickel Trend: 2000 - 2006




                                             January
                                            February
                                              March
                                                April



     High Ni
                                                 May
                                                June
                                                 July
                                   2004


                                              August
                                          September
                                             October
                                           November
                                          December
                                             January
                                            February
                                              March
                                                April
                                                 May
                                                June
                                                 July
                                   2005




                                              August
                                          September
                                             October
                                           November
                                          December
                                            January
                                            February
                                              March
                                                April
                                                 May
                                                June
                                                 July
                                   2006




                                              August
                                          September
                                             October
                                           November
                                          December
Today’s Costs (Estimated)

 Today’s debate centers around conventional pulverized coal plants
 (PC) and integrated gasification combined cycle plants (IGCC).
 As we have seen, the current level of development for IGCC makes it
 uncompetitive with PC, which explains why very few have been built.
 The claim for the future is that the cost of capture of CO2 to mitigate
 greenhouse gas concentrations in the atmosphere will be more
 expensive for PC than for IGCC. Further, as IGCC develops, its costs
 will come down (learning curve).
 As we are in a state of flux with regard to present day costs for plants,
 the best we can assume (to one significant figure) is that costs have
 escalated from their 1997 level to about double. That is, a PC plant is
 now about $2000/Kw and an IGCC is about $3000/Kw (EPC). Recall
 that the forecast in 1997 was for PC to be $750/Kw and the IGCC to be
 $1100/Kw. Unfortunately, that is one of the dangers of forecasting.

40
Today’s Costs (Estimated)

 Fuel costs have also escalated. Recent data for fuel costs delivered to
 new plants is about $1.75/MMBTU for coal and $6.50/MMBTU for gas.
 We can input these new costs into the spread sheet model and get an
 estimate for the COE for a utility trying to make a decision today.
     – Under these conditions, with no CO2 capture, the COE for the PC plant would be 6.55
       cents/Kwhr and the IGCC plant would be 9.41 cents/Kwhr.
     – The natural gas plant would again look competitive at 6.3 cents/Kwhr with an 80%
       capacity factor. However, at a more typical 40% capacity factor, the COE is 8.30
       cents/Kwhr.
     – As a result, we see a lot of utilities considering supercritical pulverized coal plants.

 What about the argument for CO2 capture?
     – This is a subject of intense debate/argument. IGCC costs are expected to increase by
       15 - 20% for CO2 capture. The range for PC is considerable. Old technology could
       increase by as much as 50%. Current technology ranges from 20 – 30%. New
       technology is estimated between 10 – 15%. Who’s right?

41
Efficiency –
               Critical to emissions strategy
Source: National Coal Council
From EPRI study




                                100% Coal


                    Coal w/ 10%
                       co-firingbiomass




                                         Commercial
                                        Supercritical/
                                      First of kind IGCC




 Existing US coal
 fleet @ avg 33%
                                            Net Plant Efficiency (HHV), %

 42
Meeting the Goals for
     Plant Efficiency % (HHV Basis)   Coal Based Power - Efficiency



                                      50

                                      40

                                      30

                                      20

                                      10

                                      0
                                           POLK/WABASH   Target for New   SCPC Today   USC Target   Next Gen IGCC
                                               IGCC          IGCC*




43
CO2 Mitigation Options –
      for Coal Based Power


     Increase efficiency
         Maximize MWs per lb of carbon processed
     Fuel switch with biomass
         Partial replacement of fossil fuels =
          proportional reduction in CO2
     Then, and only then ….Capture remaining CO2
     for EOR/Sequestration
       = Logical path to lowest cost of carbon reduction
44
CO2 Capture – Post Combustion

Technology                   Status

CO2 Scrubbing options –      Demonstration in 2006. Advantage of lower costs than Amines.
ammonia based
                             Applicable for retrofit & new applications

CO2 Frosting                 Uses Refrigeration Principle to Capture CO2 from Flue Gas.
                             Process Being Developed by Ecole de Mines de Paris, France, with ALSTOM Support


CO2 Wheel                    Use Regenerative Air-Heater-Like Device with Solid Absorbent Material to Capture ~ 60% CO2
                             from Flue Gas.
                             Being Developed by Toshiba, with Support from ALSTOM

CO2 Adsorption with Solids   Being Developed by the University of Oslo & SINTEF Materials & Chemistry (Oslo, Norway),
                             in Cooperation with ALSTOM

Advanced Amine Scrubbing     Further Improvements in Solvents, Thermal Integration, and Application of Membranes
                             Technologies Focused on Reducing Cost and Power Usage – Multiple suppliers driving
                             innovations




                Technology Validation & Demonstration
45
Post Combustion CO2 Capture
Chilled Ammonia




                                      Without CO2   MEA-Fluor Dan.   NH3
                                       Removal          Proc.


     Total power plant cost, M$           528            652         648
     Net power output, MWe                462            329         421
     Levelized cost of power, c/KWh      5.15            8.56        6.21
     CO2 Emission, lb/kwh                1.71            0.24        0.19
     Avoided Cost, $/ton CO2             Base            51.1        19.7




46
Going Down The Experience Curve for
Post Combustion CO2 Capture

                                 3000
                                                                   ABB
                                                                  Lumnus
     Heat of Reaction (BTU/lb)




                                 2500                                                 Values From
                                                                                        Current
                                                                                        Projects

                                 2000

                                 1500     1,350 BTU/lb
                                                                                                                  ALSTOM’s
                                                                                                                   Chilled
                                                                                                                  Ammonia
                                 1000         2001 Parsons                                                         Process
                                              Study (Fluor)


                                 500

                                                          Process          Advanced         Process
                                   0                      Optimization     Amines           Innovations
                                   1990         1995
                                              1995               2000
                                                                2000          2005
                                                                              2005              2010
                                                                                                 2010     2015
                                                                                                           2015   2020

                                        Significant Improvements Are Being Achieved

47
Multiple Paths to CO2 Reduction
                                   Innovations for the Future
                                                                                                  ‘Hatched’ Range reflects cost variation from fuels and uncertainty


                                               Technology Choices Reduce Risk and Lower Costs
                                   10      No CO2 Capture ------------------------------With CO2 Capture---------------------------
        Levelized COE cents/Kwhr




                                    8
                                    6
                                    4
                                    2
                                    0




                                                                                         3
                                          PC




                                                                                         2
                                                   CC



                                                                                      EA




                                                                                         e
                                                                                        2




                                                                                        2
                                                                                       es




                                                                                       O
                                                                                     NH
                                                                                      in
                                                                                    CO




                                                                                    CO
                                        SC




                                                                                    in




                                                                                    C
                                                 IG



                                                                                  /M




                                                                                   rb
                                                                               am




                                                                               PC



                                                                                 v


                                                                                 v
                                                                                 w




                                                                                tu
                                                                                w




                                                                              ad


                                                                              ad
                                                                              g




                                                                            SC
                                                     PC




                                                                             F
                                                                             v
                                                                           in




                                                                           C
                                                                         ad




                                                                          w
                                                                        CC
                                                   SC



                                                                        fir




                                                                      CP



                                                                        e
                                                                    PC
                                                                    xy




                                                                    IG




                                                                     in
                                                                   US


                                                                  rb
                                                                  O


                                                                SC




                                                               tu
                                                             H
                                                          CC
Note: Costs include compression , but do not include sequestration – equal for all technologies
                                                        IG

     48
Economic Comparison
Cost of Electricity (common basis)

                                                                        Ref – Air fired CFB w/o
                    9.00                                                capture
                    8.50
                               Ref – IGCC 7FA w/ capture spare

                    8.00                                                         O2 fired PC w/
                    7.50
                                                                                 capture
     (Cents/kWhr)




                    7.00
                                                                              O2 fired CFB w/ capture
                    6.50

                    6.00
                                                                                 Ammonia scrubbing
                    5.50

                    5.00
                                                                                   Chemical Looping
                    4.50

                    4.00
                           0   10           20           30            40             50
                                    CO2 Allowance Price ($/Ton CO2 Emitted)

49
Conclusions


     New coal fired power plants shall be designed for highest
     efficiency to minimize CO2 and other emissions

     Lower cost, higher performance technologies for post
     combustion CO2 capture are actively being developed, and
     more are emerging

     There is no single technology answer to suit all fuels and all
     applications

     The industry is best served by a portfolio approach to drive
     development of competitive coal power with carbon capture
     technology
50

More Related Content

Similar to Carl bozzuto seminar

Energy management for Belgian Businesses
Energy management for Belgian BusinessesEnergy management for Belgian Businesses
Energy management for Belgian BusinessesFilip Modderie
 
Representing Cross-border Trade in Long-term Power System Planning Models wit...
Representing Cross-border Trade in Long-term Power System Planning Models wit...Representing Cross-border Trade in Long-term Power System Planning Models wit...
Representing Cross-border Trade in Long-term Power System Planning Models wit...IEA-ETSAP
 
Emission Statment - Issue 7 - Operational Optimisation
Emission Statment - Issue 7 - Operational OptimisationEmission Statment - Issue 7 - Operational Optimisation
Emission Statment - Issue 7 - Operational OptimisationGrant Budge
 
2022 01 Anfis pendahuluan.pdf
2022 01 Anfis pendahuluan.pdf2022 01 Anfis pendahuluan.pdf
2022 01 Anfis pendahuluan.pdfDewiAjeng5
 
Cost accounting, cost control and cost reduction in TPS
Cost accounting, cost control and cost reduction in TPSCost accounting, cost control and cost reduction in TPS
Cost accounting, cost control and cost reduction in TPSManohar Tatwawadi
 
Financial and economic analysis
Financial and economic analysisFinancial and economic analysis
Financial and economic analysisSiladitya Bag
 
US Petrochemical Industry Future - Integrating Design Operation and Maintenance
US Petrochemical Industry Future -  Integrating Design Operation and MaintenanceUS Petrochemical Industry Future -  Integrating Design Operation and Maintenance
US Petrochemical Industry Future - Integrating Design Operation and MaintenanceBruce LaCour
 
Construction equipment need and factors-nrc
Construction equipment need and factors-nrcConstruction equipment need and factors-nrc
Construction equipment need and factors-nrcnarayanch1979
 
Chapter 15 cost estimation
Chapter 15   cost estimationChapter 15   cost estimation
Chapter 15 cost estimationBich Lien Pham
 
Chapter 15 cost estimation
Chapter 15   cost estimationChapter 15   cost estimation
Chapter 15 cost estimationBich Lien Pham
 
Selecting ERP for Oil and Gas industry contractors and vendors
Selecting ERP for Oil and Gas industry contractors and vendorsSelecting ERP for Oil and Gas industry contractors and vendors
Selecting ERP for Oil and Gas industry contractors and vendorscthomassen
 
SR2SlidePresentation
SR2SlidePresentationSR2SlidePresentation
SR2SlidePresentationPierre Latour
 
Essential program management views
Essential program management viewsEssential program management views
Essential program management viewsGlen Alleman
 
Nrdc edf lease training w audio
Nrdc   edf lease training w audioNrdc   edf lease training w audio
Nrdc edf lease training w audioJbedrin
 
Building Simulation, Its Role, Softwares & Their Limitations
Building Simulation, Its Role, Softwares & Their LimitationsBuilding Simulation, Its Role, Softwares & Their Limitations
Building Simulation, Its Role, Softwares & Their LimitationsPrasad Thanthratey
 
Natural Gas Pipeline Transmission Cost & Economics
Natural Gas Pipeline Transmission Cost & EconomicsNatural Gas Pipeline Transmission Cost & Economics
Natural Gas Pipeline Transmission Cost & EconomicsVijay Sarathy
 

Similar to Carl bozzuto seminar (20)

Energy management for Belgian Businesses
Energy management for Belgian BusinessesEnergy management for Belgian Businesses
Energy management for Belgian Businesses
 
Representing Cross-border Trade in Long-term Power System Planning Models wit...
Representing Cross-border Trade in Long-term Power System Planning Models wit...Representing Cross-border Trade in Long-term Power System Planning Models wit...
Representing Cross-border Trade in Long-term Power System Planning Models wit...
 
Lcca
LccaLcca
Lcca
 
Emission Statment - Issue 7 - Operational Optimisation
Emission Statment - Issue 7 - Operational OptimisationEmission Statment - Issue 7 - Operational Optimisation
Emission Statment - Issue 7 - Operational Optimisation
 
2022 01 Anfis pendahuluan.pdf
2022 01 Anfis pendahuluan.pdf2022 01 Anfis pendahuluan.pdf
2022 01 Anfis pendahuluan.pdf
 
Cost accounting, cost control and cost reduction in TPS
Cost accounting, cost control and cost reduction in TPSCost accounting, cost control and cost reduction in TPS
Cost accounting, cost control and cost reduction in TPS
 
Financial and economic analysis
Financial and economic analysisFinancial and economic analysis
Financial and economic analysis
 
US Petrochemical Industry Future - Integrating Design Operation and Maintenance
US Petrochemical Industry Future -  Integrating Design Operation and MaintenanceUS Petrochemical Industry Future -  Integrating Design Operation and Maintenance
US Petrochemical Industry Future - Integrating Design Operation and Maintenance
 
Replacement Strategies
Replacement StrategiesReplacement Strategies
Replacement Strategies
 
Engineering Economy
Engineering EconomyEngineering Economy
Engineering Economy
 
Construction equipment need and factors-nrc
Construction equipment need and factors-nrcConstruction equipment need and factors-nrc
Construction equipment need and factors-nrc
 
Chapter 15 cost estimation
Chapter 15   cost estimationChapter 15   cost estimation
Chapter 15 cost estimation
 
Chapter 15 cost estimation
Chapter 15   cost estimationChapter 15   cost estimation
Chapter 15 cost estimation
 
Chap007.ppt
Chap007.pptChap007.ppt
Chap007.ppt
 
Selecting ERP for Oil and Gas industry contractors and vendors
Selecting ERP for Oil and Gas industry contractors and vendorsSelecting ERP for Oil and Gas industry contractors and vendors
Selecting ERP for Oil and Gas industry contractors and vendors
 
SR2SlidePresentation
SR2SlidePresentationSR2SlidePresentation
SR2SlidePresentation
 
Essential program management views
Essential program management viewsEssential program management views
Essential program management views
 
Nrdc edf lease training w audio
Nrdc   edf lease training w audioNrdc   edf lease training w audio
Nrdc edf lease training w audio
 
Building Simulation, Its Role, Softwares & Their Limitations
Building Simulation, Its Role, Softwares & Their LimitationsBuilding Simulation, Its Role, Softwares & Their Limitations
Building Simulation, Its Role, Softwares & Their Limitations
 
Natural Gas Pipeline Transmission Cost & Economics
Natural Gas Pipeline Transmission Cost & EconomicsNatural Gas Pipeline Transmission Cost & Economics
Natural Gas Pipeline Transmission Cost & Economics
 

Recently uploaded

Separation of Lanthanides/ Lanthanides and Actinides
Separation of Lanthanides/ Lanthanides and ActinidesSeparation of Lanthanides/ Lanthanides and Actinides
Separation of Lanthanides/ Lanthanides and ActinidesFatimaKhan178732
 
The Most Excellent Way | 1 Corinthians 13
The Most Excellent Way | 1 Corinthians 13The Most Excellent Way | 1 Corinthians 13
The Most Excellent Way | 1 Corinthians 13Steve Thomason
 
Incoming and Outgoing Shipments in 1 STEP Using Odoo 17
Incoming and Outgoing Shipments in 1 STEP Using Odoo 17Incoming and Outgoing Shipments in 1 STEP Using Odoo 17
Incoming and Outgoing Shipments in 1 STEP Using Odoo 17Celine George
 
Introduction to ArtificiaI Intelligence in Higher Education
Introduction to ArtificiaI Intelligence in Higher EducationIntroduction to ArtificiaI Intelligence in Higher Education
Introduction to ArtificiaI Intelligence in Higher Educationpboyjonauth
 
CARE OF CHILD IN INCUBATOR..........pptx
CARE OF CHILD IN INCUBATOR..........pptxCARE OF CHILD IN INCUBATOR..........pptx
CARE OF CHILD IN INCUBATOR..........pptxGaneshChakor2
 
Mastering the Unannounced Regulatory Inspection
Mastering the Unannounced Regulatory InspectionMastering the Unannounced Regulatory Inspection
Mastering the Unannounced Regulatory InspectionSafetyChain Software
 
SOCIAL AND HISTORICAL CONTEXT - LFTVD.pptx
SOCIAL AND HISTORICAL CONTEXT - LFTVD.pptxSOCIAL AND HISTORICAL CONTEXT - LFTVD.pptx
SOCIAL AND HISTORICAL CONTEXT - LFTVD.pptxiammrhaywood
 
Industrial Policy - 1948, 1956, 1973, 1977, 1980, 1991
Industrial Policy - 1948, 1956, 1973, 1977, 1980, 1991Industrial Policy - 1948, 1956, 1973, 1977, 1980, 1991
Industrial Policy - 1948, 1956, 1973, 1977, 1980, 1991RKavithamani
 
PSYCHIATRIC History collection FORMAT.pptx
PSYCHIATRIC   History collection FORMAT.pptxPSYCHIATRIC   History collection FORMAT.pptx
PSYCHIATRIC History collection FORMAT.pptxPoojaSen20
 
“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...
“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...
“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...Marc Dusseiller Dusjagr
 
URLs and Routing in the Odoo 17 Website App
URLs and Routing in the Odoo 17 Website AppURLs and Routing in the Odoo 17 Website App
URLs and Routing in the Odoo 17 Website AppCeline George
 
A Critique of the Proposed National Education Policy Reform
A Critique of the Proposed National Education Policy ReformA Critique of the Proposed National Education Policy Reform
A Critique of the Proposed National Education Policy ReformChameera Dedduwage
 
Arihant handbook biology for class 11 .pdf
Arihant handbook biology for class 11 .pdfArihant handbook biology for class 11 .pdf
Arihant handbook biology for class 11 .pdfchloefrazer622
 
Software Engineering Methodologies (overview)
Software Engineering Methodologies (overview)Software Engineering Methodologies (overview)
Software Engineering Methodologies (overview)eniolaolutunde
 
Introduction to AI in Higher Education_draft.pptx
Introduction to AI in Higher Education_draft.pptxIntroduction to AI in Higher Education_draft.pptx
Introduction to AI in Higher Education_draft.pptxpboyjonauth
 
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...EduSkills OECD
 
Alper Gobel In Media Res Media Component
Alper Gobel In Media Res Media ComponentAlper Gobel In Media Res Media Component
Alper Gobel In Media Res Media ComponentInMediaRes1
 
Presiding Officer Training module 2024 lok sabha elections
Presiding Officer Training module 2024 lok sabha electionsPresiding Officer Training module 2024 lok sabha elections
Presiding Officer Training module 2024 lok sabha electionsanshu789521
 

Recently uploaded (20)

Separation of Lanthanides/ Lanthanides and Actinides
Separation of Lanthanides/ Lanthanides and ActinidesSeparation of Lanthanides/ Lanthanides and Actinides
Separation of Lanthanides/ Lanthanides and Actinides
 
The Most Excellent Way | 1 Corinthians 13
The Most Excellent Way | 1 Corinthians 13The Most Excellent Way | 1 Corinthians 13
The Most Excellent Way | 1 Corinthians 13
 
Incoming and Outgoing Shipments in 1 STEP Using Odoo 17
Incoming and Outgoing Shipments in 1 STEP Using Odoo 17Incoming and Outgoing Shipments in 1 STEP Using Odoo 17
Incoming and Outgoing Shipments in 1 STEP Using Odoo 17
 
Introduction to ArtificiaI Intelligence in Higher Education
Introduction to ArtificiaI Intelligence in Higher EducationIntroduction to ArtificiaI Intelligence in Higher Education
Introduction to ArtificiaI Intelligence in Higher Education
 
CARE OF CHILD IN INCUBATOR..........pptx
CARE OF CHILD IN INCUBATOR..........pptxCARE OF CHILD IN INCUBATOR..........pptx
CARE OF CHILD IN INCUBATOR..........pptx
 
Staff of Color (SOC) Retention Efforts DDSD
Staff of Color (SOC) Retention Efforts DDSDStaff of Color (SOC) Retention Efforts DDSD
Staff of Color (SOC) Retention Efforts DDSD
 
Mastering the Unannounced Regulatory Inspection
Mastering the Unannounced Regulatory InspectionMastering the Unannounced Regulatory Inspection
Mastering the Unannounced Regulatory Inspection
 
SOCIAL AND HISTORICAL CONTEXT - LFTVD.pptx
SOCIAL AND HISTORICAL CONTEXT - LFTVD.pptxSOCIAL AND HISTORICAL CONTEXT - LFTVD.pptx
SOCIAL AND HISTORICAL CONTEXT - LFTVD.pptx
 
Industrial Policy - 1948, 1956, 1973, 1977, 1980, 1991
Industrial Policy - 1948, 1956, 1973, 1977, 1980, 1991Industrial Policy - 1948, 1956, 1973, 1977, 1980, 1991
Industrial Policy - 1948, 1956, 1973, 1977, 1980, 1991
 
PSYCHIATRIC History collection FORMAT.pptx
PSYCHIATRIC   History collection FORMAT.pptxPSYCHIATRIC   History collection FORMAT.pptx
PSYCHIATRIC History collection FORMAT.pptx
 
“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...
“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...
“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...
 
URLs and Routing in the Odoo 17 Website App
URLs and Routing in the Odoo 17 Website AppURLs and Routing in the Odoo 17 Website App
URLs and Routing in the Odoo 17 Website App
 
A Critique of the Proposed National Education Policy Reform
A Critique of the Proposed National Education Policy ReformA Critique of the Proposed National Education Policy Reform
A Critique of the Proposed National Education Policy Reform
 
Arihant handbook biology for class 11 .pdf
Arihant handbook biology for class 11 .pdfArihant handbook biology for class 11 .pdf
Arihant handbook biology for class 11 .pdf
 
Software Engineering Methodologies (overview)
Software Engineering Methodologies (overview)Software Engineering Methodologies (overview)
Software Engineering Methodologies (overview)
 
Introduction to AI in Higher Education_draft.pptx
Introduction to AI in Higher Education_draft.pptxIntroduction to AI in Higher Education_draft.pptx
Introduction to AI in Higher Education_draft.pptx
 
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...
 
Model Call Girl in Tilak Nagar Delhi reach out to us at 🔝9953056974🔝
Model Call Girl in Tilak Nagar Delhi reach out to us at 🔝9953056974🔝Model Call Girl in Tilak Nagar Delhi reach out to us at 🔝9953056974🔝
Model Call Girl in Tilak Nagar Delhi reach out to us at 🔝9953056974🔝
 
Alper Gobel In Media Res Media Component
Alper Gobel In Media Res Media ComponentAlper Gobel In Media Res Media Component
Alper Gobel In Media Res Media Component
 
Presiding Officer Training module 2024 lok sabha elections
Presiding Officer Training module 2024 lok sabha electionsPresiding Officer Training module 2024 lok sabha elections
Presiding Officer Training module 2024 lok sabha elections
 

Carl bozzuto seminar

  • 1. Power Plant Economics Carl Bozzuto ALSTOM © 2006. We reserve all rights in this document and in the information contained therein. Reproduction, use or disclosure to third parties without express authority is strictly forbidden
  • 2. Overview Economic Terms Economic Methodologies Cost Models Pitfalls Cost Studies Results Some words about CO2 Conclusions 2
  • 3. Economic Terms Return on Sales = Net after tax/Sales revenue Asset turnover = Sales revenue/Assets Leverage = Assets/Equity PE Ratio = Stock Market Price (per share)/Net after tax (per share) Market/Book Ratio = Stock Market Price (per share)/Equity (per share) Return on Assets = Net/Assets Return on Equity = Net/Equity Discount Rate = Time value of Money Net Present Value = Present Value of Future Returns @ Discount Rate Internal Rate of Return = Discount Rate which yields an NPV of zero 3
  • 4. Why do we care? ROS x Turnover x Leverage x PE = Market/Book – Listed firms want to increase stock price (shareholder value) The Discount Rate considers risk as well interest rates and inflation – The discount rate is often a project hurdle rate Many firms use IRR for project evaluation Return on Equity is a key consideration for any investment 4
  • 5. Economic Methodologies A Power Plant is a long lived asset that is capital intensive. It also takes a long time to acquire the asset. – Construction times range from 2 years for a combined cycle plant to 3 – 4 years for a coal plant to 10 years for a nuclear plant. A key issue is treating the time value of money. Depreciation is a key consideration. Different entities treat these considerations differently. 5
  • 6. Plant Cost Plant Cost is exceptionally site specific. – Labor costs – Shipping and material costs – Environmental costs – Site preparation costs – Site impacts on performance – Fuel costs – Cooling water type and availability – Connection costs Today, we really don’t know what the final cost of a plant will be. – Raw material escalation – Shipping costs – Labor costs 6
  • 7. Plant Cost Terminology There are numerous ways to talk about plant cost. – Engineered, Procured, and Constructed (EPC cost) • Most commonly used today • Fits best with Merchant Plant model • Does not included Owner’s Costs Ø Land, A/E costs, Owner’s Labor, Interconnection, Site Permits, PR, etc. • Can often be obtained as a fixed price contract for proven technology – Equipment Cost • Generally the cost to fabricate, deliver, and construct the plant equipment – Overnight Cost • Either the equipment cost or the EPC cost with the NPV of interest during construction. This was used in the 70s and 80s to compare coal plants with nuclear plants due to the difference in construction times. – Total Installed Cost (TIC) • The total cost of the equipment and engineering including interest during construction in present day dollars. This is the cost that a utility would record on its books without the cost of land and other home office costs. 7 – Total Plant Cost (TPC) – includes all costs
  • 8. Economic Methodologies Simple payback – The number of years it takes to pay back the original investment Return on Equity – For regulated utilities, the ROE is set by the regulatory body. The equity is determined by the total plant cost being allowed in the rate base. The equity portion is determined by the leverage of the company. The ROE is applied to the equity and added to the cost in determining the cost of electricity and thus the rate to be charged to the customer. Capital Charge Rate – This is the rate to be charged on the capital cost of the plant in order to convert capital costs (ie investment) into operating costs (or annual costs). This rate can be estimated in a number of ways. This rate generally includes most of our ignorance about the future (ie interest rates, ROE, inflation, taxes, etc.) Discounted Cash Flow Analysis – This method is preferred by economists and developers. A spread sheet is set up to estimate the cash flows over the life of the project. An IRR can be calculated if an electricity price is known (or estimated). 8
  • 9. Economic Methodologies All of these methods can be made equivalent to one another for any given set of assumptions. – A simple payback time can be selected to give the same cost of electricity (COE) as the other methods. – A return on equity can be selected to give the same COE. – A capital charge rate can be selected to give the same COE. – The Discounted Cash Flow method is considered the most accurate. However, there are still a considerable number of assumptions that go into such a model such as the discount rate, inflation rate, tax rate, interest rates, fuel prices, capacity factors, etc. that the accuracy is typically less in reality. The Independent Power Producer pioneered the use of the DCF model for smaller power projects. – In this model, the developer attempted to fix as many costs as possible by obtaining fixed price contracts for all of the major cost contributors. These included the EPC price, the fuel contract, the Operations & Maintenance Contract (O&M), and the Power Purchase Agreement. 9
  • 10. Cost Models Capital Charge Rate Model – The goal is to select a capital charge rate that typically covers most of the future unknowns. This rate is applied to the EPC cost in order to provide an annual cost that will provide the desired return on equity. – In its simplest form, one can use the following: • Interest rate on debt - 8 - 10% for utility debt • ROE - 10 – 12 % for most utilities • Inflation rate - 3 – 4% • Depreciation - 2 – 4% • Taxes and Insurance - 3 – 5% • Risk - ? (typically 3% for mature technologies, higher for others) – Another approach would be to run a number of DCF cases with different assumptions and then assess a capital charge rate that is consistent. – A reasonable number for a regulated utility is 20% (one significant figure) 10
  • 11. Discounted Cash Flow Model The goal is to estimate the cash flows of the project over the life of the plant. A significant number of variables are involved and must be estimated or assumed in order to make the spread sheet work. – Input variables include net output, capacity factor, availability, net plant heat rate (HHV), degradation, EPC price, construction period, insurance, initial spares/consumables, fixed O&M, variable O&M, fuel price, fuel heating value (HHV), financial closing date, reference date, depreciation, analysis horizon, owner’s contingency, development costs, permitting costs, advisory/legal fees, start up fuel, fuel storage, inflation rates, interest rates, debt level, taxes, construction cash flow, discount rate, and ROE. – A detailed cash flow analysis is set up for each year of the project. For shorter term projects, these estimated cash flows are more realistic. For longer term projects, the accuracy is debatable. – Since the cash generation may be variable, it is often desirable to perform some kind of levelizing function to generate an average that is understandable. There are risks associated with this step. – The most common application is to assume a market price for electricity and then try to maximize the IRR for the project. 11
  • 12. Discounted Cash Flow Model The model assumes that we know a lot about the project and the number of variables. What if we don’t know very much about the future project? For example, what if we don’t know where the plant will be located? What if we don’t know which technology we will use for the plant? What if we want to compare technologies on a consistent basis? One approach is to run the DCF model “backwards”. In this approach, we stipulate a required return and calculate an average cost of electricity needed to generate that return. We still need to make a lot of assumptions, but at least we can be consistent. One advantage of having such spread sheet programs is that a wide range of scenarios and assumptions can be tested. This approach gives us a little more insight into the decision making process and helps us understand why some entities might chose one technology over another. 12
  • 13. Typical Construction Period w/Cash Drawdown 1. C ulativeD dow um raw n 0 11 13 15 17 19 21 23 25 27 29 31 33 35 37 39 41 43 45 47 1 3 5 7 9 -100,000 -200,000 -300,000 -400,000 -500,000 -600,000 13
  • 14. Typical Levelized Cash Flow 4. EndingEquityCashflow 50,000 0 1 3 5 7 9 11 13 15 17 19 21 23 25 27 29 31 33 35 37 39 41 (50,000) (100,000) (150,000) (200,000) (250,000) (300,000) (350,000) 14
  • 15. Pitfalls The biggest pitfall is thinking that these numbers are “real”. They are only indicative. Just because a computer can calculate numbers to the penny does not mean that the numbers are accurate. There is a lot of uncertainty due to the number of assumptions that have to be made. It is important to understand what the goal and/or objective of the analysis is. In the following study, the goal was to compare technologies that might be used in the future. This goal is different from looking at a near term project where the site, technology, fuel, customer, and vendors have already been selected. There is no substitute for sound management judgement. The analysis itself does not identify the risks. The analyzer must consider the risks and ask the appropriate “what if” questions. In the following study, over 3,000 spread sheet runs were made in order to analyze the comparisons effectively. Avoid the “Swiss Watch” mentality. 15
  • 16. Technology Position and Experience Experience Major Competitors Technology Base Maturity Sub-Critical PC 1,200 GW Alstom,MHI, B&W, FW Mature and Several Others Super-Critical PC 265 GW Alstom,MHI, B&W Proven PFBC 0.5 GW Demo IGCC 1 GW GE, Shell, Conoco Phillips Demo CFB 20 GW Alstom, FW Proven NGCC 200 GW GT GE, Siemens, Alstom Mature 100 GW ST 16
  • 17. Baseline Economic Inputs – 1997 400 MW Class Subcritical Supercritical P800 PFBC IGCC Size 400 400 400 400 (MW) Capital Cost 1,000 1,050 1,100 1,380 ($/ kW) Heat Rate 9,374 8,385 8,405 8,700 (Btu/ kWh) Availability 80 80 80 80 (%) Cycle Time 36 36 48 48 (months) Fixed O&M 31.14 32.11 33.69 39.08 ($/ kW) Variable O&M 0.77 0.69 1.01 0.42 (mills/ kWh) Source: Market Market ABB GE 17
  • 18. Baseline Economic Inputs – 1997 100 MW Class CFB P200 PFBC NGCC Size 100 100 270 (MW) Capital Cost 1,000 1,200 500 ($/ kW) Heat Rate 10,035 8,815 6,640 (Btu/ kWh) Availability 80 80 80 (%) Cycle Time 30 32 24 (months) Fixed O&M 44.13 55. 41 16.92 ($/ kW) Variable O&M 1.18 1.06 0.01 (mills/ kWh) Source: Market ABB PGT 18
  • 19. Baseline Economic Inputs - 2005 400 MW Class Subcritical Supercritical P800 PFBC IGCC Size 400 400 400 400 (MW) Capital Cost 750 750 750 1,100 ($/ kW) Heat Rate 8,750 8,125 8,030 7,800 (Btu/ kWh) Availability 80 80 80 80 (%) Cycle Time 24 24 30 36 (months) Fixed O&M 26.33 26.33 26.95 33.69 ($/ kW) Variable O&M 0.81 0.75 1.05 0.37 (mills/ kWh) Source: BA Plan BA Plan SECAR GE 19
  • 20. Baseline Economic Inputs – 2005 100 MW Class CFB P200 PFBC NGCC Size 100 100 270 (MW) Capital Cost 725 850 325 ($/ kW) Heat Rate 9,350 8,530 6195 (Btu/ kWh) Availability 80 80 80 (%) Cycle Time 18 22 18 (months) Fixed O&M 38.84 48.67 16.44 ($/ kW) Variable O&M 1.15 1.12 0.01 (mills/ kWh) Source: BA Plan SECAR PGT 20
  • 21. Financing Scenario Summary Loan structure Municipal Utility IPP 1 IPP 2 Industrial Horizon (years) 40 30 15 15 10 Interest rate (%) 5.75 7.75 8.75 8.75 8.25 Loan term (years) 40 30 9 9 10 Depreciation (years) 40 30 15 15 10 Equity (%) 0 50 30 50 75 Debt (%) 100 50 70 50 25 ROE (%) n/a 10 20 20 23 Taxes (%) 0 20 30 30 30 21
  • 22. Comparison of Financing Scenarios 400 MW Subcritical PC Fired Plant 10.0 9.0 Financial Fixed O&M 8.0 Variable O&M have Fuel Finan cial costs COE e on 7.0 majo r influenc Levelized Tariff, c/ kWh 6.0 5.0 4.0 3.0 2.0 1.0 0.0 Municipal Utility IPP-1 IPP-2 Industrial Financing Arrangement 22
  • 23. Comparison of Technologies Municipal Financing - 1997 (80% CF, $1.20 coal and $3.00 gas) 4.0 Financial Fixed O&M 3.5 Variable O&M Fuel 3.0 Levelized Tariff, c/ kWh 2.5 2.0 1.5 1.0 0.5 0.0 Subcrit PC Super PC P-800 IGCC P-200 CFB NGCC (400 MW) (400 MW) (400 MW) (400 MW) (100 MW) (100 MW) (270 MW) 23
  • 24. Comparison of Technologies Utility Financing - 1997 (80% CF, $1.20 coal and $3.00 gas) 5.0 4.5 Financial Fixed O&M 4.0 NGCC lo Variable O&M oks bett but wor er on to Fuel se on di tal COE , Levelized Tariff, c/ kWh 3.5 spatch b asis. ncial cos t 3.0 Hi gher fina ce on increase s influen 2.5 CO E 2.0 1.5 1.0 0.5 0.0 Subcrit PC Super PC P-800 IGCC P-200 CFB NGCC (400 MW) (400 MW) (400 MW) (400 MW) (100 MW) (100 MW) (270 MW) 24
  • 25. Comparison of Technologies IPP(1) Financing - 1997 (80% CF, $1.20 coal and $3.00 gas) 8.0 Financial Fixed O&M 7.0 Variable O&M Fuel 6.0 Levelized Tariff, c/ kWh 5.0 4.0 3.0 2.0 1.0 0.0 Subcrit PC Super PC P-800 IGCC P-200 CFB NGCC (400 MW) (400 MW) (400 MW) (400 MW) (100 MW) (100 MW) (270 MW) 25
  • 26. Comparison of Technologies IPP(2) Financing - 1997 (80% CF, $1.20 coal and $3.00 gas) 9.0 Financial Fixed O&M 8.0 Variable O&M Fuel 7.0 Levelized Tariff, c/ kWh 6.0 5.0 4.0 3.0 2.0 1.0 0.0 Subcrit PC Super PC P-800 IGCC P-200 CFB NGCC (400 MW) (400 MW) (400 MW) (400 MW) (100 MW) (100 MW) (270 MW) 26
  • 27. Comparison of Technologies Industrial Financing - 1997 (80% CF, $1.20 coal and $3.00 gas) 16.0 Financial Fixed O&M 14.0 Variable O&M Fuel 12.0 Levelized Tariff, c/ kWh 10.0 8.0 6.0 4.0 2.0 0.0 Subcrit PC Super PC P-800 IGCC P-200 CFB NGCC (400 MW) (400 MW) (400 MW) (400 MW) (100 MW) (100 MW) (270 MW) 27
  • 28. Capacity Factor Effect on COE Municipal Financing - 1997 ($1.20 coal and $3.00 gas) 8.0 Subcrit PC Supercrit PC 7.0 P-800 IGCC D is P-200 patc Levelized Tariff, (c/ kWh) CFB 6.0 h ra hav te a NGCC em ajor nd/or c influ apac en c i 5.0 e on ty facto COE r 4.0 3.0 2.0 20% 30% 40% 50% 60% 70% 80% 90% 100% Capacity Factor, (%) 28
  • 29. Impact of Availability on COE Municipal Financing - 1997 ($1.20 coal) 3.5 3.4 3.3 Subcrit PC 5 days lost availability makes Supercrit PC Levelized Tariff, (c/ kWh) 3.2 sub and supercritical equal. 3.1 3.0 2.9 2.8 ~5 days 2.7 2.6 2.5 6,500 6,600 6,700 6,800 6,900 7,000 7,100 7,200 7,300 7,400 7,500 Capacity, (hrs/ year) 29
  • 30. Sensitivity Analysis Subcritical PC 1997 IPP1 Financing - $1.20 coal 20% a nd e in availability n COE In %, chang est influe nce o 15% e high EPC price hav 10% Change in COE, (%) 5% 0% -5% -10% Availability EPC price Plant heat rate -15% Fixed O&M Cycle time Var O&M -20% -20% -15% -10% -5% 0% 5% 10% 15% 20% Percent Variable Change 30
  • 31. Sensitivity Analysis NGCC 1997 IPP1 Financing - $3.00 gas 20% and in av ailability 15% NG C C % , change fluence o n COE For e st i n have high 10% efficiency Change in COE, (%) 5% 0% -5% -10% Availability EPC price Plant heat rate Fixed O&M -15% Cycle time Var O&M -20% -20% -15% -10% -5% 0% 5% 10% 15% 20% Percent Variable Change 31
  • 32. gh NGCC hi Comparison of Technologies China 1997 Municipal Financing Conditions el ($1.80 coal and $5.00 LNG) due to fu 4.0 cost ta nt 3.5 t less impor First cos e to high c os t tive du 3.0 f uel sensi Levelized Tariff, (c/ kWh) 2.5 2.0 1.5 1.0 Financial Fixed O&M Variable O&M 0.5 Fuel 0.0 Subcrit Supercrit P-800 IGCC P-200 CFB NGCC PC PC 32
  • 33. Comparison of Technologies China 1997 IPP Financing Conditions ($1.80 coal and $5.00 LNG) 7.00 6.00 Levelized Tariff, (c/ kWh) 5.00 4.00 3.00 2.00 Financial Fixed O&M 1.00 Variable O&M Fuel 0.00 Subcrit Supercrit P-800 IGCC P-200 CFB NGCC PC PC 33
  • 34. Comparison of Technologies Japan Market Conditions - 1997 ($2.90 coal and $5.00 LNG) 5.0 4.5 4.0 Levelized Tariff, c/ kWh 3.5 3.0 2.5 2.0 r ta nt t less impo 1.5 First cos to high c os t Financial e due l sensitiv Fixed O&M 1.0 fue Variable O&M Fuel 0.5 0.0 Subcrit PC Super PC P-800 IGCC P-200 CFB NGCC (400 MW) (400 MW) (400 MW) (400 MW) (100 MW) (100 MW) (270 MW) 34
  • 35. Net Plant Heat Rate Summary 12,000 12% 10,035 9,375 10% 9,350 10,000 10% 8,815 8,750 8,700 8,530 8,405 8,385 8,125 8,030 Net Plant Heat Rate (Btu/kW) 7,800 NPHR Improvement (%) 8,000 8% 6,640 6,195 7% 7% 7% 6,000 6% 4% 4,000 4% 3% 3% 2,000 1997 2% 2005 Improvement 0 0% Subcrit PC Super PC PFBC-P800 IGCC PFBC-P200 CFB NGCC (400 MW) (400 MW) (400 MW) (400 MW) (100 MW) (100 MW) (270 MW) 35
  • 36. Summary of EPC Prices $1,600 40% $1,380 1997 2005 $1,400 % Decrease 35% $1,200 32% $1,100 $1,100 $1,050 $1,200 30% 29% $1,000 $1,000 29% 28% EPC Price ($/kW, net) EPC Decrease (%) $1,000 25% 25% $850 $750 $750 $750 $725 $800 20% 20% $600 15% $350 $325 $400 10% 7% $200 5% $0 0% Subcrit PC Super PC PFBC-P800 IGCC PFBC-P200 CFB NGCC (400 MW) (400 MW) (400 MW) (400 MW) (100 MW) (100 MW) (270 MW) 36
  • 37. Coal Technology Cost Trends Extrapolated to 2005 2,000 1,800 Subcritical PC Supercritical PC 1,600 P800 P200 1,400 EPC Price ($/kW, net) 1,200 1,000 800 600 “all 4 400 have 00 MW t the s echn ame olog 200 mid ies term targ 0 et 1989 1991 1993 1995 1997 1999 2001 2003 2005 Year 37
  • 38. Market Trends Carbon Steel Price Trends 175 Index Base 1982 150 125 100 01/02 01/03 01/04 01/05 01/06 Month 38
  • 39. 39 Spot Nickel 1.80 2.20 2.60 3.00 3.40 3.80 4.20 4.60 5.00 5.40 5.80 6.20 6.60 7.00 7.40 7.80 8.20 8.60 9.00 9.40 9.80 10.20 10.60 11.00 11.40 11.80 12.20 12.60 13.00 13.40 13.80 14.20 14.60 15.00 15.40 15.80 16.20 January February March April May June July 2000 August September October November December January February March April May June Market Trends July 2001 August September October November December January February March April May June July 2002 August September October November December Low Ni January February March April May June July 2003 August September Month / Year Avg. Spot Ni October November December Nickel Trend: 2000 - 2006 January February March April High Ni May June July 2004 August September October November December January February March April May June July 2005 August September October November December January February March April May June July 2006 August September October November December
  • 40. Today’s Costs (Estimated) Today’s debate centers around conventional pulverized coal plants (PC) and integrated gasification combined cycle plants (IGCC). As we have seen, the current level of development for IGCC makes it uncompetitive with PC, which explains why very few have been built. The claim for the future is that the cost of capture of CO2 to mitigate greenhouse gas concentrations in the atmosphere will be more expensive for PC than for IGCC. Further, as IGCC develops, its costs will come down (learning curve). As we are in a state of flux with regard to present day costs for plants, the best we can assume (to one significant figure) is that costs have escalated from their 1997 level to about double. That is, a PC plant is now about $2000/Kw and an IGCC is about $3000/Kw (EPC). Recall that the forecast in 1997 was for PC to be $750/Kw and the IGCC to be $1100/Kw. Unfortunately, that is one of the dangers of forecasting. 40
  • 41. Today’s Costs (Estimated) Fuel costs have also escalated. Recent data for fuel costs delivered to new plants is about $1.75/MMBTU for coal and $6.50/MMBTU for gas. We can input these new costs into the spread sheet model and get an estimate for the COE for a utility trying to make a decision today. – Under these conditions, with no CO2 capture, the COE for the PC plant would be 6.55 cents/Kwhr and the IGCC plant would be 9.41 cents/Kwhr. – The natural gas plant would again look competitive at 6.3 cents/Kwhr with an 80% capacity factor. However, at a more typical 40% capacity factor, the COE is 8.30 cents/Kwhr. – As a result, we see a lot of utilities considering supercritical pulverized coal plants. What about the argument for CO2 capture? – This is a subject of intense debate/argument. IGCC costs are expected to increase by 15 - 20% for CO2 capture. The range for PC is considerable. Old technology could increase by as much as 50%. Current technology ranges from 20 – 30%. New technology is estimated between 10 – 15%. Who’s right? 41
  • 42. Efficiency – Critical to emissions strategy Source: National Coal Council From EPRI study 100% Coal Coal w/ 10% co-firingbiomass Commercial Supercritical/ First of kind IGCC Existing US coal fleet @ avg 33% Net Plant Efficiency (HHV), % 42
  • 43. Meeting the Goals for Plant Efficiency % (HHV Basis) Coal Based Power - Efficiency 50 40 30 20 10 0 POLK/WABASH Target for New SCPC Today USC Target Next Gen IGCC IGCC IGCC* 43
  • 44. CO2 Mitigation Options – for Coal Based Power Increase efficiency Maximize MWs per lb of carbon processed Fuel switch with biomass Partial replacement of fossil fuels = proportional reduction in CO2 Then, and only then ….Capture remaining CO2 for EOR/Sequestration = Logical path to lowest cost of carbon reduction 44
  • 45. CO2 Capture – Post Combustion Technology Status CO2 Scrubbing options – Demonstration in 2006. Advantage of lower costs than Amines. ammonia based Applicable for retrofit & new applications CO2 Frosting Uses Refrigeration Principle to Capture CO2 from Flue Gas. Process Being Developed by Ecole de Mines de Paris, France, with ALSTOM Support CO2 Wheel Use Regenerative Air-Heater-Like Device with Solid Absorbent Material to Capture ~ 60% CO2 from Flue Gas. Being Developed by Toshiba, with Support from ALSTOM CO2 Adsorption with Solids Being Developed by the University of Oslo & SINTEF Materials & Chemistry (Oslo, Norway), in Cooperation with ALSTOM Advanced Amine Scrubbing Further Improvements in Solvents, Thermal Integration, and Application of Membranes Technologies Focused on Reducing Cost and Power Usage – Multiple suppliers driving innovations Technology Validation & Demonstration 45
  • 46. Post Combustion CO2 Capture Chilled Ammonia Without CO2 MEA-Fluor Dan. NH3 Removal Proc. Total power plant cost, M$ 528 652 648 Net power output, MWe 462 329 421 Levelized cost of power, c/KWh 5.15 8.56 6.21 CO2 Emission, lb/kwh 1.71 0.24 0.19 Avoided Cost, $/ton CO2 Base 51.1 19.7 46
  • 47. Going Down The Experience Curve for Post Combustion CO2 Capture 3000 ABB Lumnus Heat of Reaction (BTU/lb) 2500 Values From Current Projects 2000 1500 1,350 BTU/lb ALSTOM’s Chilled Ammonia 1000 2001 Parsons Process Study (Fluor) 500 Process Advanced Process 0 Optimization Amines Innovations 1990 1995 1995 2000 2000 2005 2005 2010 2010 2015 2015 2020 Significant Improvements Are Being Achieved 47
  • 48. Multiple Paths to CO2 Reduction Innovations for the Future ‘Hatched’ Range reflects cost variation from fuels and uncertainty Technology Choices Reduce Risk and Lower Costs 10 No CO2 Capture ------------------------------With CO2 Capture--------------------------- Levelized COE cents/Kwhr 8 6 4 2 0 3 PC 2 CC EA e 2 2 es O NH in CO CO SC in C IG /M rb am PC v v w tu w ad ad g SC PC F v in C ad w CC SC fir CP e PC xy IG in US rb O SC tu H CC Note: Costs include compression , but do not include sequestration – equal for all technologies IG 48
  • 49. Economic Comparison Cost of Electricity (common basis) Ref – Air fired CFB w/o 9.00 capture 8.50 Ref – IGCC 7FA w/ capture spare 8.00 O2 fired PC w/ 7.50 capture (Cents/kWhr) 7.00 O2 fired CFB w/ capture 6.50 6.00 Ammonia scrubbing 5.50 5.00 Chemical Looping 4.50 4.00 0 10 20 30 40 50 CO2 Allowance Price ($/Ton CO2 Emitted) 49
  • 50. Conclusions New coal fired power plants shall be designed for highest efficiency to minimize CO2 and other emissions Lower cost, higher performance technologies for post combustion CO2 capture are actively being developed, and more are emerging There is no single technology answer to suit all fuels and all applications The industry is best served by a portfolio approach to drive development of competitive coal power with carbon capture technology 50