1. You’re a project manager working on a software engineering project. The programmers have
started building the software, and the testers have started to create the test environment. Which
process group includes these activities?
InitiatingA.	
PlanningB.	
ExecutingC.	
ClosingD.	
2. Which of the following is not a stakeholder?
The project manager who is responsible for building the projectA.	
A project team member who will work on the projectB.	
A customer who will use the final productC.	
A competitor whose company will lose business because of the productD.	
3. A project manager runs into a problem with her project’s contractors, and she isn’t sure
if they’re abiding by the terms of the contract. Which knowledge area is the BEST source of
processes to help her deal with this problem?
Cost ManagementA.	
Risk ManagementB.	
Procurement ManagementC.	
Communications ManagementD.	
4. You’re a project manager for a construction project. You’ve just finished creating a list of all of
the people who will be directly affected by the project. What process group are you in?
InitiatingA.	
PlanningB.	
ExecutingC.	
Monitoring & ControllingD.	
5. Which process group contains the Develop Project Charter process and the Identify
Stakeholders process?
InitiatingA.	
ExecutingB.	
Monitoring and ControllingC.	
ClosingD.	
Download at Boykma.Com
82   Chapter 3
Exam Questions
6. Which of the following is NOT a project?
Repairing a carA.	
Building a highway overpassB.	
Running an IT support departmentC.	
Filming a motion pictureD.	
7. A project manager is running a software project that is supposed to be delivered in phases. She was
planning on dividing the resources into two separate teams to do the work for two phases at the same time,
but one of her senior developers suggested that she use an Agile methodology instead, and she agrees. Which
of the following BEST describes the relationship between her project’s phases?
Sequential relationshipA.	
Iterative relationshipB.	
Constrained relationshipC.	
Overlapping relationshipD.	
8. Which of the following is NOT true about overlapping phases?
Each phase is typically done by a separate teamA.	
There’s an increased risk of delays when a later phase can’t start until an earlier one endsB.	
There’s an increased risk to the project due to potential for reworkC.	
Every phase must go through all five process groupsD.	
9. You’re the project manager for an industrial design project. Your team members report to you, and you’re
responsible for creating the budget, building the schedule, and assigning the tasks. When the project is
complete, you release the team so they can work on other projects for the company. What kind of organization
do you work in?
FunctionalA.	
Weak matrixB.	
Strong matrixC.	
ProjectizedD.	
10. You’re a project manager working in a weak matrix organization. Which of the following is NOT true?
Your team members report to functional managersA.	
You are not in directly charge of resourcesB.	
Functional managers make decisions that can affect your projectsC.	
You have sole responsibility for the success or failure of the projectD.	
exam questions
Download at Boykma.Com
you are here 4   83
the process framework
Exam Questions
Answers
1. Answer: C
The Executing process group is the one where the team does all the work. You’ll get a good feel for the
process groups pretty quickly!
2. Answer: D
One of the hardest things that a project manager has to do on a project is figure out who all the
stakeholders are. The project manager, the team, the sponsor (or client), the customers and people who
will use the software, the senior managers at the company—they’re all stakeholders. Competitors aren’t
stakeholders, because even though they’re affected by the project, they don’t actually have any direct
influence over it.
3. Answer: C
The Procurement Management knowledge area deals with contracts, contractors, buyers and sellers. If
you’ve got a question about a type of contract or how to deal with contract problems, you’re being asked
about a Procurement Management process.
4. Answer: A
People who will be directly affected by the project are stakeholders, and when you’re creating a list of
them you’re performing the Identify Stakeholders process. That’s one of the two processes in the Initiating
process group.
5. Answer: A
The first things that are created on a project are the charter (which you create in the Develop Project
Charter process) and the Stakeholder Register (which you create in the Identify Stakeholders process).
You do those things when you’re initiating the project.
Download at Boykma.Com
84   Chapter 3
Exam Questions
Answers
6. Answer: C
The work of an IT support department doesn’t have an end date—it’s not temporary. That’s why it’s
not a project. Now, if that support team had to work over the weekend to move the data center to a
new location, then that would be a project!
I see—so even when
something is a process and
not a project, there could
be projects related to it.
7. Answer: B
Agile development is a really good example of an iterative approach to project phases. In an Agile
project, the team will typically break down the project into phases, where they work on the current
phase while planning out the next one.
exam answers
Download at Boykma.Com
you are here 4   85
the process framework
Exam Questions
Answers
8. Answer: B
If there’s an increased risk of a project because one phase can’t start until another one ends, that means your project
phases aren’t overlapping. When you’ve got overlapping phases, that means that you typically have multiple teams
that start their phases independently of each other.
Also, take another look at answer C, because it’s an important point about overlapping phases. When your
phases have an overlapping relationship, there’s an increased risk of rework. This typically happens when one
team delivers the results of their project, but made assumptions about what another team is doing as part of their
phase. When that other team delivers their work, it turns out that the results that both teams produced aren’t quite
compatible with each other, and now both teams have to go back and rework their designs. This happens a lot
when your phases overlap, which is why overlapping phases have an increased risk of rework.
9. Answer: D
In a projectized organization, the project manager has the power to assign tasks, manage the budget, and release the
team.
10. Answer: D
In a weak matrix, project managers have very limited authority. They have to share a lot of responsibility with
functional managers, and those functional managers have a lot of leeway to make decisions about how the team
members are managed. In an organization like that, the project manager isn’t given a lot of responsibility.
That’s why you’re likely to
find a project expediter
in a weak matrix.
Download at Boykma.Com

Contenu connexe

Tendances (20)

08 pmp quality management exam
08 pmp quality management exam08 pmp quality management exam
08 pmp quality management exam
 
1
11
1
 
09 pmp human resource management exam
09 pmp human resource  management exam09 pmp human resource  management exam
09 pmp human resource management exam
 
Pmp3
Pmp3Pmp3
Pmp3
 
Exam1
Exam1Exam1
Exam1
 
Pmp4
Pmp4Pmp4
Pmp4
 
Pmp1
Pmp1Pmp1
Pmp1
 
04 pmp integration management exam
04 pmp integration management exam04 pmp integration management exam
04 pmp integration management exam
 
Pmp exam q&a
Pmp exam q&aPmp exam q&a
Pmp exam q&a
 
13 pmp professional responsibility exam
13 pmp professional responsibility exam13 pmp professional responsibility exam
13 pmp professional responsibility exam
 
Pmp5
Pmp5Pmp5
Pmp5
 
01 pmp introduct to project management exam
01 pmp introduct to project management exam01 pmp introduct to project management exam
01 pmp introduct to project management exam
 
Pmp test 02
Pmp test 02Pmp test 02
Pmp test 02
 
02 pmp project life cycle exam
02 pmp project life cycle exam02 pmp project life cycle exam
02 pmp project life cycle exam
 
12 pmp procurement management exam
12 pmp procurement management exam12 pmp procurement management exam
12 pmp procurement management exam
 
Pmp test 01
Pmp test 01Pmp test 01
Pmp test 01
 
PMP 1600 Questions by TechFAQ360
PMP 1600 Questions by TechFAQ360PMP 1600 Questions by TechFAQ360
PMP 1600 Questions by TechFAQ360
 
Pmp test 03
Pmp test 03Pmp test 03
Pmp test 03
 
1440 pmp exam question bank
1440 pmp exam question bank1440 pmp exam question bank
1440 pmp exam question bank
 
Pmi sp questions with answers
Pmi sp questions with answersPmi sp questions with answers
Pmi sp questions with answers
 

En vedette (6)

2
22
2
 
175 pmp sample_questions
175 pmp sample_questions175 pmp sample_questions
175 pmp sample_questions
 
Jamil faraj hassan CV
Jamil faraj hassan CVJamil faraj hassan CV
Jamil faraj hassan CV
 
Jamil Hassan, PMP lessons learned.
Jamil Hassan, PMP lessons learned.Jamil Hassan, PMP lessons learned.
Jamil Hassan, PMP lessons learned.
 
Capm exam prep-questions_2010_ol
Capm exam prep-questions_2010_olCapm exam prep-questions_2010_ol
Capm exam prep-questions_2010_ol
 
Jamil pmp Certificate 2020
Jamil pmp Certificate 2020Jamil pmp Certificate 2020
Jamil pmp Certificate 2020
 

Similaire à 03 pmp project management processes exam

Chapter 2 Questionsand Answers1. There is a difference between t.docx
Chapter 2 Questionsand Answers1. There is a difference between t.docxChapter 2 Questionsand Answers1. There is a difference between t.docx
Chapter 2 Questionsand Answers1. There is a difference between t.docxwalterl4
 
Risk 2 simplelearn-exam1-ans
Risk 2 simplelearn-exam1-ansRisk 2 simplelearn-exam1-ans
Risk 2 simplelearn-exam1-ansMohamed Saeed
 
PMP-Prep-Exam-Test-200_Questions.pdf
PMP-Prep-Exam-Test-200_Questions.pdfPMP-Prep-Exam-Test-200_Questions.pdf
PMP-Prep-Exam-Test-200_Questions.pdfProject Cubicle
 
2009 Top Ten Obstacles To Project Success
2009 Top Ten Obstacles To Project Success2009 Top Ten Obstacles To Project Success
2009 Top Ten Obstacles To Project SuccessLou Gasco
 
questions-just-that.pdf.civil engineering
questions-just-that.pdf.civil engineeringquestions-just-that.pdf.civil engineering
questions-just-that.pdf.civil engineeringmocr84810
 
PMP Certification Training Course Part-64
PMP Certification Training Course Part-64PMP Certification Training Course Part-64
PMP Certification Training Course Part-64Skillogic Solutions
 
Pmp Questions Complete
Pmp Questions CompletePmp Questions Complete
Pmp Questions CompleteKareemBullard1
 

Similaire à 03 pmp project management processes exam (20)

PgMP
PgMP PgMP
PgMP
 
Chapter 2 Questionsand Answers1. There is a difference between t.docx
Chapter 2 Questionsand Answers1. There is a difference between t.docxChapter 2 Questionsand Answers1. There is a difference between t.docx
Chapter 2 Questionsand Answers1. There is a difference between t.docx
 
PMP Exam Q & A
PMP Exam Q & APMP Exam Q & A
PMP Exam Q & A
 
Risk 2 simplelearn-exam1-ans
Risk 2 simplelearn-exam1-ansRisk 2 simplelearn-exam1-ans
Risk 2 simplelearn-exam1-ans
 
PMP-Prep-Exam-Test-200_Questions.pdf
PMP-Prep-Exam-Test-200_Questions.pdfPMP-Prep-Exam-Test-200_Questions.pdf
PMP-Prep-Exam-Test-200_Questions.pdf
 
2009 Top Ten Obstacles To Project Success
2009 Top Ten Obstacles To Project Success2009 Top Ten Obstacles To Project Success
2009 Top Ten Obstacles To Project Success
 
PMP Sample Questions Set 3
PMP Sample Questions Set 3PMP Sample Questions Set 3
PMP Sample Questions Set 3
 
PMP® Sample Questions
PMP® Sample QuestionsPMP® Sample Questions
PMP® Sample Questions
 
Free PMP Exam Sample Question
Free PMP Exam Sample QuestionFree PMP Exam Sample Question
Free PMP Exam Sample Question
 
PMP Five Sample Questions - 3
PMP Five Sample Questions - 3PMP Five Sample Questions - 3
PMP Five Sample Questions - 3
 
PMP® Sample Questions 5
PMP® Sample Questions 5PMP® Sample Questions 5
PMP® Sample Questions 5
 
questions-just-that.pdf.civil engineering
questions-just-that.pdf.civil engineeringquestions-just-that.pdf.civil engineering
questions-just-that.pdf.civil engineering
 
CAPM Study Session 2
CAPM Study Session 2CAPM Study Session 2
CAPM Study Session 2
 
PMP Certificate- introduction
PMP Certificate- introductionPMP Certificate- introduction
PMP Certificate- introduction
 
PMP Certification Training Course Part-64
PMP Certification Training Course Part-64PMP Certification Training Course Part-64
PMP Certification Training Course Part-64
 
Pmp Questions Complete
Pmp Questions CompletePmp Questions Complete
Pmp Questions Complete
 
Itpm question bank
Itpm   question bankItpm   question bank
Itpm question bank
 
PMP® Sample Questions 3
PMP® Sample Questions 3PMP® Sample Questions 3
PMP® Sample Questions 3
 
PMP Exam Sample Questions
PMP Exam Sample QuestionsPMP Exam Sample Questions
PMP Exam Sample Questions
 
15 Free PMP Exam Questions
15 Free PMP Exam Questions15 Free PMP Exam Questions
15 Free PMP Exam Questions
 

Plus de Jamil Faraj , PMP

Plus de Jamil Faraj , PMP (7)

Corona-virus PMP study plan
Corona-virus PMP study planCorona-virus PMP study plan
Corona-virus PMP study plan
 
PMP Study Plan by Jamil Faraj, PMP
PMP Study Plan by Jamil Faraj, PMPPMP Study Plan by Jamil Faraj, PMP
PMP Study Plan by Jamil Faraj, PMP
 
Jamil Faraj CV 2020
Jamil Faraj CV 2020Jamil Faraj CV 2020
Jamil Faraj CV 2020
 
PMP ITTOs Quick Review
PMP ITTOs Quick Review PMP ITTOs Quick Review
PMP ITTOs Quick Review
 
Jamil Faraj CV- English
Jamil Faraj CV- EnglishJamil Faraj CV- English
Jamil Faraj CV- English
 
Pmp Formula Pocket_Guide
Pmp Formula Pocket_GuidePmp Formula Pocket_Guide
Pmp Formula Pocket_Guide
 
دورة وظيفة العمر
دورة وظيفة العمردورة وظيفة العمر
دورة وظيفة العمر
 

Dernier

Call US-88OO1O2216 Call Girls In Mahipalpur Female Escort Service
Call US-88OO1O2216 Call Girls In Mahipalpur Female Escort ServiceCall US-88OO1O2216 Call Girls In Mahipalpur Female Escort Service
Call US-88OO1O2216 Call Girls In Mahipalpur Female Escort Servicecallgirls2057
 
8447779800, Low rate Call girls in Shivaji Enclave Delhi NCR
8447779800, Low rate Call girls in Shivaji Enclave Delhi NCR8447779800, Low rate Call girls in Shivaji Enclave Delhi NCR
8447779800, Low rate Call girls in Shivaji Enclave Delhi NCRashishs7044
 
Youth Involvement in an Innovative Coconut Value Chain by Mwalimu Menza
Youth Involvement in an Innovative Coconut Value Chain by Mwalimu MenzaYouth Involvement in an Innovative Coconut Value Chain by Mwalimu Menza
Youth Involvement in an Innovative Coconut Value Chain by Mwalimu Menzaictsugar
 
Innovation Conference 5th March 2024.pdf
Innovation Conference 5th March 2024.pdfInnovation Conference 5th March 2024.pdf
Innovation Conference 5th March 2024.pdfrichard876048
 
Flow Your Strategy at Flight Levels Day 2024
Flow Your Strategy at Flight Levels Day 2024Flow Your Strategy at Flight Levels Day 2024
Flow Your Strategy at Flight Levels Day 2024Kirill Klimov
 
Marketplace and Quality Assurance Presentation - Vincent Chirchir
Marketplace and Quality Assurance Presentation - Vincent ChirchirMarketplace and Quality Assurance Presentation - Vincent Chirchir
Marketplace and Quality Assurance Presentation - Vincent Chirchirictsugar
 
8447779800, Low rate Call girls in Saket Delhi NCR
8447779800, Low rate Call girls in Saket Delhi NCR8447779800, Low rate Call girls in Saket Delhi NCR
8447779800, Low rate Call girls in Saket Delhi NCRashishs7044
 
APRIL2024_UKRAINE_xml_0000000000000 .pdf
APRIL2024_UKRAINE_xml_0000000000000 .pdfAPRIL2024_UKRAINE_xml_0000000000000 .pdf
APRIL2024_UKRAINE_xml_0000000000000 .pdfRbc Rbcua
 
8447779800, Low rate Call girls in New Ashok Nagar Delhi NCR
8447779800, Low rate Call girls in New Ashok Nagar Delhi NCR8447779800, Low rate Call girls in New Ashok Nagar Delhi NCR
8447779800, Low rate Call girls in New Ashok Nagar Delhi NCRashishs7044
 
IoT Insurance Observatory: summary 2024
IoT Insurance Observatory:  summary 2024IoT Insurance Observatory:  summary 2024
IoT Insurance Observatory: summary 2024Matteo Carbone
 
Annual General Meeting Presentation Slides
Annual General Meeting Presentation SlidesAnnual General Meeting Presentation Slides
Annual General Meeting Presentation SlidesKeppelCorporation
 
Independent Call Girls Andheri Nightlaila 9967584737
Independent Call Girls Andheri Nightlaila 9967584737Independent Call Girls Andheri Nightlaila 9967584737
Independent Call Girls Andheri Nightlaila 9967584737Riya Pathan
 
8447779800, Low rate Call girls in Kotla Mubarakpur Delhi NCR
8447779800, Low rate Call girls in Kotla Mubarakpur Delhi NCR8447779800, Low rate Call girls in Kotla Mubarakpur Delhi NCR
8447779800, Low rate Call girls in Kotla Mubarakpur Delhi NCRashishs7044
 
NewBase 19 April 2024 Energy News issue - 1717 by Khaled Al Awadi.pdf
NewBase  19 April  2024  Energy News issue - 1717 by Khaled Al Awadi.pdfNewBase  19 April  2024  Energy News issue - 1717 by Khaled Al Awadi.pdf
NewBase 19 April 2024 Energy News issue - 1717 by Khaled Al Awadi.pdfKhaled Al Awadi
 
Call Us 📲8800102216📞 Call Girls In DLF City Gurgaon
Call Us 📲8800102216📞 Call Girls In DLF City GurgaonCall Us 📲8800102216📞 Call Girls In DLF City Gurgaon
Call Us 📲8800102216📞 Call Girls In DLF City Gurgaoncallgirls2057
 
8447779800, Low rate Call girls in Tughlakabad Delhi NCR
8447779800, Low rate Call girls in Tughlakabad Delhi NCR8447779800, Low rate Call girls in Tughlakabad Delhi NCR
8447779800, Low rate Call girls in Tughlakabad Delhi NCRashishs7044
 
8447779800, Low rate Call girls in Uttam Nagar Delhi NCR
8447779800, Low rate Call girls in Uttam Nagar Delhi NCR8447779800, Low rate Call girls in Uttam Nagar Delhi NCR
8447779800, Low rate Call girls in Uttam Nagar Delhi NCRashishs7044
 
MAHA Global and IPR: Do Actions Speak Louder Than Words?
MAHA Global and IPR: Do Actions Speak Louder Than Words?MAHA Global and IPR: Do Actions Speak Louder Than Words?
MAHA Global and IPR: Do Actions Speak Louder Than Words?Olivia Kresic
 
Market Sizes Sample Report - 2024 Edition
Market Sizes Sample Report - 2024 EditionMarket Sizes Sample Report - 2024 Edition
Market Sizes Sample Report - 2024 EditionMintel Group
 
Islamabad Escorts | Call 03070433345 | Escort Service in Islamabad
Islamabad Escorts | Call 03070433345 | Escort Service in IslamabadIslamabad Escorts | Call 03070433345 | Escort Service in Islamabad
Islamabad Escorts | Call 03070433345 | Escort Service in IslamabadAyesha Khan
 

Dernier (20)

Call US-88OO1O2216 Call Girls In Mahipalpur Female Escort Service
Call US-88OO1O2216 Call Girls In Mahipalpur Female Escort ServiceCall US-88OO1O2216 Call Girls In Mahipalpur Female Escort Service
Call US-88OO1O2216 Call Girls In Mahipalpur Female Escort Service
 
8447779800, Low rate Call girls in Shivaji Enclave Delhi NCR
8447779800, Low rate Call girls in Shivaji Enclave Delhi NCR8447779800, Low rate Call girls in Shivaji Enclave Delhi NCR
8447779800, Low rate Call girls in Shivaji Enclave Delhi NCR
 
Youth Involvement in an Innovative Coconut Value Chain by Mwalimu Menza
Youth Involvement in an Innovative Coconut Value Chain by Mwalimu MenzaYouth Involvement in an Innovative Coconut Value Chain by Mwalimu Menza
Youth Involvement in an Innovative Coconut Value Chain by Mwalimu Menza
 
Innovation Conference 5th March 2024.pdf
Innovation Conference 5th March 2024.pdfInnovation Conference 5th March 2024.pdf
Innovation Conference 5th March 2024.pdf
 
Flow Your Strategy at Flight Levels Day 2024
Flow Your Strategy at Flight Levels Day 2024Flow Your Strategy at Flight Levels Day 2024
Flow Your Strategy at Flight Levels Day 2024
 
Marketplace and Quality Assurance Presentation - Vincent Chirchir
Marketplace and Quality Assurance Presentation - Vincent ChirchirMarketplace and Quality Assurance Presentation - Vincent Chirchir
Marketplace and Quality Assurance Presentation - Vincent Chirchir
 
8447779800, Low rate Call girls in Saket Delhi NCR
8447779800, Low rate Call girls in Saket Delhi NCR8447779800, Low rate Call girls in Saket Delhi NCR
8447779800, Low rate Call girls in Saket Delhi NCR
 
APRIL2024_UKRAINE_xml_0000000000000 .pdf
APRIL2024_UKRAINE_xml_0000000000000 .pdfAPRIL2024_UKRAINE_xml_0000000000000 .pdf
APRIL2024_UKRAINE_xml_0000000000000 .pdf
 
8447779800, Low rate Call girls in New Ashok Nagar Delhi NCR
8447779800, Low rate Call girls in New Ashok Nagar Delhi NCR8447779800, Low rate Call girls in New Ashok Nagar Delhi NCR
8447779800, Low rate Call girls in New Ashok Nagar Delhi NCR
 
IoT Insurance Observatory: summary 2024
IoT Insurance Observatory:  summary 2024IoT Insurance Observatory:  summary 2024
IoT Insurance Observatory: summary 2024
 
Annual General Meeting Presentation Slides
Annual General Meeting Presentation SlidesAnnual General Meeting Presentation Slides
Annual General Meeting Presentation Slides
 
Independent Call Girls Andheri Nightlaila 9967584737
Independent Call Girls Andheri Nightlaila 9967584737Independent Call Girls Andheri Nightlaila 9967584737
Independent Call Girls Andheri Nightlaila 9967584737
 
8447779800, Low rate Call girls in Kotla Mubarakpur Delhi NCR
8447779800, Low rate Call girls in Kotla Mubarakpur Delhi NCR8447779800, Low rate Call girls in Kotla Mubarakpur Delhi NCR
8447779800, Low rate Call girls in Kotla Mubarakpur Delhi NCR
 
NewBase 19 April 2024 Energy News issue - 1717 by Khaled Al Awadi.pdf
NewBase  19 April  2024  Energy News issue - 1717 by Khaled Al Awadi.pdfNewBase  19 April  2024  Energy News issue - 1717 by Khaled Al Awadi.pdf
NewBase 19 April 2024 Energy News issue - 1717 by Khaled Al Awadi.pdf
 
Call Us 📲8800102216📞 Call Girls In DLF City Gurgaon
Call Us 📲8800102216📞 Call Girls In DLF City GurgaonCall Us 📲8800102216📞 Call Girls In DLF City Gurgaon
Call Us 📲8800102216📞 Call Girls In DLF City Gurgaon
 
8447779800, Low rate Call girls in Tughlakabad Delhi NCR
8447779800, Low rate Call girls in Tughlakabad Delhi NCR8447779800, Low rate Call girls in Tughlakabad Delhi NCR
8447779800, Low rate Call girls in Tughlakabad Delhi NCR
 
8447779800, Low rate Call girls in Uttam Nagar Delhi NCR
8447779800, Low rate Call girls in Uttam Nagar Delhi NCR8447779800, Low rate Call girls in Uttam Nagar Delhi NCR
8447779800, Low rate Call girls in Uttam Nagar Delhi NCR
 
MAHA Global and IPR: Do Actions Speak Louder Than Words?
MAHA Global and IPR: Do Actions Speak Louder Than Words?MAHA Global and IPR: Do Actions Speak Louder Than Words?
MAHA Global and IPR: Do Actions Speak Louder Than Words?
 
Market Sizes Sample Report - 2024 Edition
Market Sizes Sample Report - 2024 EditionMarket Sizes Sample Report - 2024 Edition
Market Sizes Sample Report - 2024 Edition
 
Islamabad Escorts | Call 03070433345 | Escort Service in Islamabad
Islamabad Escorts | Call 03070433345 | Escort Service in IslamabadIslamabad Escorts | Call 03070433345 | Escort Service in Islamabad
Islamabad Escorts | Call 03070433345 | Escort Service in Islamabad
 

03 pmp project management processes exam

  • 1. you are here 4   81 the process framework Exam Questions 1. You’re a project manager working on a software engineering project. The programmers have started building the software, and the testers have started to create the test environment. Which process group includes these activities? InitiatingA. PlanningB. ExecutingC. ClosingD. 2. Which of the following is not a stakeholder? The project manager who is responsible for building the projectA. A project team member who will work on the projectB. A customer who will use the final productC. A competitor whose company will lose business because of the productD. 3. A project manager runs into a problem with her project’s contractors, and she isn’t sure if they’re abiding by the terms of the contract. Which knowledge area is the BEST source of processes to help her deal with this problem? Cost ManagementA. Risk ManagementB. Procurement ManagementC. Communications ManagementD. 4. You’re a project manager for a construction project. You’ve just finished creating a list of all of the people who will be directly affected by the project. What process group are you in? InitiatingA. PlanningB. ExecutingC. Monitoring & ControllingD. 5. Which process group contains the Develop Project Charter process and the Identify Stakeholders process? InitiatingA. ExecutingB. Monitoring and ControllingC. ClosingD. Download at Boykma.Com
  • 2. 82   Chapter 3 Exam Questions 6. Which of the following is NOT a project? Repairing a carA. Building a highway overpassB. Running an IT support departmentC. Filming a motion pictureD. 7. A project manager is running a software project that is supposed to be delivered in phases. She was planning on dividing the resources into two separate teams to do the work for two phases at the same time, but one of her senior developers suggested that she use an Agile methodology instead, and she agrees. Which of the following BEST describes the relationship between her project’s phases? Sequential relationshipA. Iterative relationshipB. Constrained relationshipC. Overlapping relationshipD. 8. Which of the following is NOT true about overlapping phases? Each phase is typically done by a separate teamA. There’s an increased risk of delays when a later phase can’t start until an earlier one endsB. There’s an increased risk to the project due to potential for reworkC. Every phase must go through all five process groupsD. 9. You’re the project manager for an industrial design project. Your team members report to you, and you’re responsible for creating the budget, building the schedule, and assigning the tasks. When the project is complete, you release the team so they can work on other projects for the company. What kind of organization do you work in? FunctionalA. Weak matrixB. Strong matrixC. ProjectizedD. 10. You’re a project manager working in a weak matrix organization. Which of the following is NOT true? Your team members report to functional managersA. You are not in directly charge of resourcesB. Functional managers make decisions that can affect your projectsC. You have sole responsibility for the success or failure of the projectD. exam questions Download at Boykma.Com
  • 3. you are here 4   83 the process framework Exam Questions Answers 1. Answer: C The Executing process group is the one where the team does all the work. You’ll get a good feel for the process groups pretty quickly! 2. Answer: D One of the hardest things that a project manager has to do on a project is figure out who all the stakeholders are. The project manager, the team, the sponsor (or client), the customers and people who will use the software, the senior managers at the company—they’re all stakeholders. Competitors aren’t stakeholders, because even though they’re affected by the project, they don’t actually have any direct influence over it. 3. Answer: C The Procurement Management knowledge area deals with contracts, contractors, buyers and sellers. If you’ve got a question about a type of contract or how to deal with contract problems, you’re being asked about a Procurement Management process. 4. Answer: A People who will be directly affected by the project are stakeholders, and when you’re creating a list of them you’re performing the Identify Stakeholders process. That’s one of the two processes in the Initiating process group. 5. Answer: A The first things that are created on a project are the charter (which you create in the Develop Project Charter process) and the Stakeholder Register (which you create in the Identify Stakeholders process). You do those things when you’re initiating the project. Download at Boykma.Com
  • 4. 84   Chapter 3 Exam Questions Answers 6. Answer: C The work of an IT support department doesn’t have an end date—it’s not temporary. That’s why it’s not a project. Now, if that support team had to work over the weekend to move the data center to a new location, then that would be a project! I see—so even when something is a process and not a project, there could be projects related to it. 7. Answer: B Agile development is a really good example of an iterative approach to project phases. In an Agile project, the team will typically break down the project into phases, where they work on the current phase while planning out the next one. exam answers Download at Boykma.Com
  • 5. you are here 4   85 the process framework Exam Questions Answers 8. Answer: B If there’s an increased risk of a project because one phase can’t start until another one ends, that means your project phases aren’t overlapping. When you’ve got overlapping phases, that means that you typically have multiple teams that start their phases independently of each other. Also, take another look at answer C, because it’s an important point about overlapping phases. When your phases have an overlapping relationship, there’s an increased risk of rework. This typically happens when one team delivers the results of their project, but made assumptions about what another team is doing as part of their phase. When that other team delivers their work, it turns out that the results that both teams produced aren’t quite compatible with each other, and now both teams have to go back and rework their designs. This happens a lot when your phases overlap, which is why overlapping phases have an increased risk of rework. 9. Answer: D In a projectized organization, the project manager has the power to assign tasks, manage the budget, and release the team. 10. Answer: D In a weak matrix, project managers have very limited authority. They have to share a lot of responsibility with functional managers, and those functional managers have a lot of leeway to make decisions about how the team members are managed. In an organization like that, the project manager isn’t given a lot of responsibility. That’s why you’re likely to find a project expediter in a weak matrix. Download at Boykma.Com