you are here 4   219
scope management
Exam Questions
1. Which of the following is TRUE about a work breakdown structure?
It contains work packages that are described in a linear, unstructured listA.	
Each item in the WBS represents a feature in the product scopeB.	
The WBS represents all of the work that must be done on the projectC.	
The WBS is created by the product sponsor and stakeholdersD.	
2. Which is NOT an output of a scope management process?
Business CaseA.	
B.	 WBS Dictionary
Requested changesC.	
Accepted deliverablesD.	
3. Which of the following is NOT TRUE about a work breakdown structure?
It describes processes to define the scope, verify work, and manage scope changesA.	
It contains a graphical, hierarchical list of all work to be performedB.	
It can be broken down byC.	 project phase or deliverable
It is an important element of theD.	 scope baseline
4. What is the correct order of the scope management processes?
Define Scope, Create WBS,A.	 Collect Requirements, Scope Verification
Collect Requirements,B.	 Control Scope, Create WBS, Scope Verification
Collect Requirements, Define Scope, Create WBS, Scope VerificationC.	
D.	 Collect Requirements, Scope Baseline, Define Scope, Control Scope
5. You are managing a software project. Your team has been working for eight weeks, and
so far the project is on track. The lead programmer comes to you with a problem: there is a
work package that is causing trouble. Nobody seems to know who is responsible for it, the
accounting department does not know what cost center to bill it against, and it’s not even
clear exactly what work should be performed. Which of the following would BEST help this
situation?
Alternatives AnalysisA.	
WBS DictionaryB.	
Scope Management PlanC.	
Scope VerificationD.	
Download at Boykma.Com
220   Chapter 5
Exam Questions
6. The goal of Verify Scope is:
To inspect the scope statement for defects so that it is correctA.	
To gain formal acceptance of the project deliverables from the sponsor and stakeholdersB.	
To get everyone in the project working together towards a common goalC.	
To verify that all PMBOK® Guide processes are complied withD.	
7. Historical information and lessons learned are part of:
Organizational process assetsA.	
Enterprise environmental factorsB.	
Project management information system (PMIS)C.	
Work performance informationD.	
8. You’ve taken over as a project manager on a highway construction project, and the execution is already underway.
Your sponsor tells you that moving forward, all asphalt should be laid down with a 12” thickness. The scope
statement and the WBS call for 9” thick asphalt. What is the BEST course of action?
Look for a cheaper supplier so the cost impact is minimizedA.	
Tell the sponsor that the work is already underway, so you can’t accommodate his requestB.	
Refuse to alter the plans until the change control system has been usedC.	
Tell the team to accommodate the request immediatelyD.	
9. Which of the following BEST describes the purpose of a traceability matrix?
It describes how WBS Dictionary entries are traced to work packages, and how work packages are decomposedA.	
from deliverables
It’s used to make sure that all of the sub-plans of the Project Management Plan have been createdB.	
It helps you understand the source of each requirement, and how that requirement was verified in a later deliverableC.	
It’s used to trace the source of every change, so that you can keep track of them through the entire Control ScopeD.	
process and verify that the change was properly implemented
10. It’s the end of execution for a large highway construction project. The work has been done, and the workers are
ready to pack up their equipment. The project manager and project sponsor have come by with specialists to check
that each requirement has been met, and that all of the work in the WBS has been performed. What process is being
done?
Control ScopeA.	
Verify ScopeB.	
Scope TestingC.	
Define ScopeD.	
exam questions
Download at Boykma.Com
you are here 4   221
scope management
Exam Questions
11. You have just been put in charge of a project that is already executing. While reviewing the project
documentation, you discover that there is no WBS. You check the Scope Management Plan and discover that
there should be one for this project. What is the BEST thing for you to do:
Immediately alert the sponsor and make sure the project work doesn’t stopA.	
Stop project work and create the WBS, and don’t let work continue until it’s createdB.	
Make sure you closely manage communications to ensure the team doesn’t miss any undocumented workC.	
Mark it down in the lessons learned so it doesn’t happen on future projectsD.	
12. A project manager on an industrial design project finds that the sponsor wants to make a change to the
scope after it has been added to the baseline, and needs to know the procedure for managing changes. What
is the BEST place to look for this information?
WBSA.	
Scope management planB.	
Change request form templateC.	
Business CaseD.	
13. You have just started work on the Project Scope Statement. You are analyzing the expected deliverables,
when you discover that one of them could be delivered in three different ways. You select the best method
for creating that deliverable. What is the BEST way to describe what you are doing?
Alternatives AnalysisA.	
DecompositionB.	
Define ScopeC.	
Stakeholder AnalysisD.	
14. You’re the project manager on a software project. Your team has only completed half of the work, when
the sponsor informs you that the project has been terminated. What is the BEST action for you to take?
Verify the deliverables produced by the team against the scope, and document any place they do not matchA.	
Call a team meeting to figure out how to spend the rest of the budgetB.	
Work with the sponsor to see if there is any way to bring the project backC.	
Tell the team to stop working immediatelyD.	
15. You are managing an industrial design project. One of your team members comes to you with a
suggestion that will let you do more work while at the same time saving the project 15% of the budget. What
is the BEST way for you to proceed?
Tell the team to make the change because it will deliver more work for less moneyA.	
Refuse to make the change until aB.	 change request is documented and change control is performed
Refuse to consider the change because it will affect the baselineC.	
Do a cost-benefit analysis and then make sure to inform the sponsor that the project scope changedD.	
Download at Boykma.Com
222   Chapter 5
Exam Questions
16. You are the project manager for a telecommunications project. You are working on the project scope statement.
Which of the following is NOT included in this document?
Authorization for the project manager to work on the projectA.	
Requirements that the deliverables must meetB.	
A description of the project objectivesC.	
The list of deliverables that must be createdD.	
17. Which of the following is NOT an input to Control Scope?
WBS DictionaryA.	
Approved change requestsB.	
Requested changesC.	
Project scope statementD.	
18. Which of these processes is not a part of Scope Management?
Scope IdentificationA.	
Collect RequirementsB.	
Control ScopeC.	
Scope VerificationD.	
19. You are the project manager for a new project, and you want to save time creating the WBS. Which is the BEST
way to do this?
MakeA.	 decomposition go faster by cutting down the number of deliverables
Use a WBS from a previous project as a templateB.	
Don’t create the WBS DictionaryC.	
Ask the sponsor to provide the work packages for each deliverableD.	
20. The project manager for a design project is using the Define Scope process. Which BEST describes this?
Creating a document that lists all of the features of the productA.	
Creating a plan for managing changes to theB.	 scope baseline
Creating a document that describes all of the work the team does to make the deliverablesC.	
Creating a graphical representation of how the phases or deliverables decompose into work packagesD.	
21. You are the project manager for a construction project. You have completed project initiation activities, and you
are now creating a document that describes processes to document the scope, decompose deliverables into work
packages, verify that all work is complete, and manage changes to the baseline. What process are you performing?
Develop Project Management PlanA.	
Define ScopeB.	
Create WBSC.	
Develop Project CharterD.	
exam questions
Download at Boykma.Com
you are here 4   223
scope management
Exam Questions
22. You are a project manager working on a project. Your sponsor wants to know who a certain work package is
assigned to, what control account to bill it against, and what work is involved. What document do you refer her
to?
Scope Management PlanA.	
WBSB.	
WBS DictionaryC.	
D.	 Scope Statement
24. You are the project manager for a software project. One of the teams discovers that if they deviate from the
plan, they can actually skip one of the deliverables because it’s no longer necessary. They do the calculations,
and realize they can save the customer 10% of the cost of the project without compromising the features in the
product. They take this approach, and inform you the following week what they did during the status meeting.
What is the BEST way to describe this situation?
The project team has taken initiative and saved the customer moneyA.	
A dispute is resolved in favor of the customerB.	
The team informed the project manager of the change, but they should have informed the customer tooC.	
The team did not follow the Control Scope processD.	
25. Which of the following BEST describes the purpose of the project scope statement?
It describes the features of the product of the projectA.	
It is created before theB.	 scope management plan
It decomposes deliverables into work packagesC.	
It describes the objectives, requirements, and deliverables of the project, and the work needed to create themD.	
26. A project manager at a cable and networking company is gathering requirements for a project to build a new
version of their telecommunications equipment. Which of the following is NOT something that she will use?
Specific descriptions of work packages that will be developedA.	
One-on-one interviews with the senior executives who need the new equipment for their teamsB.	
An early working model of the telecommunications equipment to help get feedback from stakeholdersC.	
Notes that she took while being “embedded” with the team that will eventually use the equipment beingD.	
developed
27. Which of the following is NOT an output of Collect Requirements?
Requirements ObservationsA.	
Requirements Traceability MatrixB.	
Requirements DocumentationC.	
Requirements Management PlanD.	
Download at Boykma.Com
224   Chapter 5
Exam Questions
Answers
1. Answer: C
The work breakdown structure is all about breaking down the work that your team needs to do. The WBS is graphical
and hierarchical, not linear and unstructured. Did you notice that answer B was about product scope, not project scope?
2. Answer: A
There are two ways you can get to the right answer for this question. You can recognize that the WBS Dictionary,
Change Requests, and Accepted Deliverables are all Scope Management process outputs. (You’ll see Change
Requests in every knowledge area!) But you can also recognize that the Business Case was created by the Develop
Projct Charter which is part of the Initiating process group.
3. Answer: A
Did you recognize that answer A was describing the scope management plan? Once you know what the WBS is used
for and how to make one, questions like this make sense.
4. Answer: C
You’ll need to know what order processes come in, and one good way to do that is to think
about how the outputs of some processes are used as inputs for another. For example, you
can’t create the WBS until the scope is defined, which is why A is wrong. And you can’t do
change control until you have a baseline WBS, which is why B is wrong.
5. Answer: B
An important tactic for a lot of exam questions is to be able to recognize a particular tool, technique, input, or output
from a description. What have you learned about that tells you who is responsible for a work package, what control
account to associate with it, and describes the work associated with it? That’s a good description of the WBS Dictionary.
6. Answer: B
There are some questions where you’ll just have to know what a process is all about, and this is one of them. That’s
why it’s really helpful to know why Verify Scope is so helpful to you on a project. You use Verify Scope to check that all
of the work packages were completed, and get the stakeholders and sponsor to formally accept the deliverables.
Take a minute and think about how there’s no “right” order for Scope Verification
and Control Scope. You could have a scope change at the beginning of the project, so
Control Scope would come first. But a change could happen late in the project, too! If
there’s a major change to the project after the scope’s verified, you need to redo it.
exam answers
Inspection isn’t just done at the end of the
project. You do Scope Verification on every
single deliverable made by you and the team.
Download at Boykma.Com
you are here 4   225
scope management
Exam Questions
Answers
The PMBOK® Guide says this stuff
is stored in a “corporate knowledge
base,” but that’s just another word
for a file cabinet or a folder on your
network
7. Answer: A
It’s easy to forget that Organizational Process Assets is more than just an input. It’s a real thing that’s part of your
company. Take a second and think about what assets are in your organization that help you with carry out each
process. Get it? Good! So what is historical information, anyway? It’s stuff like reports and data that you or another
project manager wrote down on a previous project and stored in a file cabinet or a database. That’s an asset you can
use now! What are lessons learned? Those are lessons you wrote down at the end of a previous project and stuck in
a file cabinet or a database. And now those lessons are another asset you can use.
8. Answer: C
One thing to remember about change control is that if you want to make the sponsor and stakeholders happy with
the project in the end, sometimes you have to tell them “no” right now. When you’re doing Control Scope, the most
important tool you use is the change control system. It tells you how to take an approved change and put it in place on
a project, and there’s no other way that you should ever make a change to any part of the baseline. That means that
once everyone has approved the scope statement and WBS, if you want to make any change to them, then you need
to get that change approved and put it through the change control system.
9. Answer: C
The Requirements Traceability Matrix is a tool that you use to trace each requirement back to a specific business case,
and then forward to the rest of the scope deliverables (like specific WBS work packages), as well as other parts of the
project: the product design (like specific levels in Cows Gone Wild) or test strategy (like test plans that the Ranch Hand
Games testers use to make sure that the game works).
These inputs and outputs make
sense when I think about how I’d
use them on a project. Organizational
Process Assets are just things that my
organization keeps track of to help me do
my job, like information from old projects
and procedures that help me do my job.
The idea is that you’re tracing a deliverable
from its initial description all the way
through the project through testing, so that
you can make sure that every single deliverable
meets all of its requirements.
Download at Boykma.Com
226   Chapter 5
10. Answer: B
When you’re getting the sponsor and stakeholders to formally accept the results of the project, you’re doing scope
verification. There’s only one tool for it: inspection. That means carefully checking the deliverables (in this case,
what the workers built on the highway) to make sure they match the WBS.
11. Answer: B
This question is a little tricky. The most important thing about a WBS is that if your Scope Management Plan says it
should be there, then your project absolutely cannot be done without it. And a general rule is that if you ever find that
there is no WBS, you should always check the Scope Management Plan to find out why.
12. Answer: B
This is another question that is testing you on the definition of a specific document, in this case the Scope
Management Plan, which is one of the subsidiary plans of the Project Management Plan. Think about what you
use a Scope Management Plan for. It gives you specific procedures for defining the scope, breaking down the work,
verifying the deliverables, and managing scope changes—which is what this question is asking. All of the other
answers don’t have anything to do with managing changes.
Exam Questions
Answers
Answer D is a good idea, but it’s notas important as creating a new WBS.
That way, if I need to
restart the project later or
reuse some of its deliverables, I’ll
know exactly where my team left
off when it ended.
13. Answer: A
Here’s another example of how there are two correct answers but only one
BEST one. Answer C is true – you are doing scope definition. But is that
really the best way to describe this situation? Alternatives analysis is part
of scope definition, and it’s a more accurate way to describe what’s going
on here.
14. Answer: A
This question is an example of how you need to rely on more than just
common sense to pass the PMP exam. All four of these answers could be
good ways to handle a terminated project, but there’s only one of those
answers that corresponds to what the PMBOK® Guide says. When a
project is terminated, you still need to complete the Verify Scope process.
That way, you can document all of the work that has been completed, and
the work that has not been completed.
When you look at a few ways to createa deliverable and then decide on thebest one, that’s alternatives analysis.
exam answers
Download at Boykma.Com
you are here 4   227
scope management
Exam Questions
Answers
15. Answer: B
Are you starting to get the hang of how this change control stuff works? The baseline isn’t etched in stone, and
you need to be able to change it, but you can’t just go ahead and make changes whenever you want. You need
to document the change request and then put that request through change control. If it’s approved, then you can
update the baseline so that it incorporates the change.
16. Answer: A
When a question asks you about what a particular document, input, or output contains, be on the lookout for
answers that talk about a different document. What document do you know about that gives the project manager
authorization to do the work? That’s what the project charter is for.
17. Answer: C
Sometimes Control Scope is easiest to think about if you think of it as a kind of machine that turns approved
changes into updates. It sucks in the approved changes and all of the other Scope Management stuff (the Scope
Statement, WBS, and WBS Dictionary), does all the stuff that it needs to do to update those things, and then spits
out updates. And sometimes it spits out new requested changes because when you’re making changes to the
WBS or Scope Statement you realize that you need to make even more changes.
18. Answer: A
Scope Identification is a made-up process. It
didn’t appear in this chapter, and even though it
sounds real, it’s wrong.
19. Answer: B
WBS templates are a great way to speed up
creating the WBS, and the easiest way to create
a template is to use one from a previous project.
It is not a good idea to cut out deliverables, skip
important outputs like the WBS Dictionary, or
make the sponsor do your job for you.
You definitely can’t just makethe change and inform thesponsor later. All changes needto be approved.
I think of Perform Integrated
Change Control as a machine
that turns change requests into
approved changes, and Control
Scope as the machine that turns
approved changes into updates
to the scope baseline.
You can also use a
template for the scope
management plan.
Download at Boykma.Com
228   Chapter 5
Exam Questions
Answers
20. Answer: C
This question asked you about the Define Scope process, but all of the answers describe various outputs. Which of
these outputs matches Define Scope? Well, the main output of Define Scope is the Scope Statement, and answer
C is a good description of the scope statement.
21. Answer: A
This question asked you where you defined the procedures for doing all of the Scope Management Processes.
Where do you find those procedures? You find them in the Project Management Plan—specifically, the Scope
Management Plan sub-plan. And you build that in the Develop Project Management Plan process.
22. Answer: C
There’s only one document you’ve seen that shows you details of individual work packages and contains a control
account, a statement of work, and a resource assignment. It’s the WBS Dictionary.
23. Answer: D
Here’s another question where you need to know how to describe an important tool. In this case, you need to know
what the change control system is used for. Luckily, answer D is a pretty good description.
Hey, I’ll bet a good way to study for
the exam is to look at answers A, B, and C
in question 23 and figure out what each of
them is describing. It’ll be great practice
identifying an output from a description!
exam answers
Did you guess “Create WBS” because it was a ScopeManagement process and the question mentioneddecomposing deliverables into work packages?
Download at Boykma.Com
you are here 4   229
scope management
Exam Questions
Answers
24. Answer: D
When you read the question, it looks like the team really helped the project, right? But think about what happened: the
team abandoned the plan, and then they made a change to the project without getting approval from the sponsor or
stakeholders. Maybe they discovered a useful shortcut. But isn’t it possible that the shortcut the team found was already
considered and rejected by the sponsor? That’s why change control is so important.
25. Answer: D
Some questions are just definition questions. When that definition is a “Which-is-BEST” question, there could be an
answer that makes some sense, and it’s tempting to stop with it. In this case, answer A sounds like it might be right. But if
you read answer D, it’s much more accurate.
26. Answer: A
The question asked about the tools and techniques for Collect Requirements, and answer A is the only answer that has to
do with the Create WBS process. The rest of the answers were descriptions of Collect Requirements tools and techniques:
Interviews (answer B), Prototypes (answer C), and Observations (answer D).
27. Answer: A
The three outputs of Collect Requirements are Requirements Documentation, the Requirements Management Plan, and
the Requirements Traceability Matrix. “Requirements Observations” isn’t really an output.
Keep an eye out for questions that describe an input
or output and then ask you to name it. Look at each
answer and think up own descriptions for them—one
of them will match the question.
Did you notice how the question made it sound like the team
did a good thing by ignoring Control Scope and making changes
that were never approved?
The easiest way to make sure you get questionslike this right is to think about how each of thoseoutputs are actually used later in the project.
Download at Boykma.Com

Contenu connexe

Tendances

04 pmp integration management exam
04 pmp integration management exam04 pmp integration management exam
04 pmp integration management examJamil Faraj , PMP
 
01 pmp introduct to project management exam
01 pmp introduct to project management exam01 pmp introduct to project management exam
01 pmp introduct to project management examJamil Faraj , PMP
 
04 pmp integration management exam
04 pmp integration management exam04 pmp integration management exam
04 pmp integration management examJamil Faraj , PMP
 
12 pmp procurement management exam
12 pmp procurement management exam12 pmp procurement management exam
12 pmp procurement management examJamil Faraj , PMP
 
PMP 1600 Questions by TechFAQ360
PMP 1600 Questions by TechFAQ360PMP 1600 Questions by TechFAQ360
PMP 1600 Questions by TechFAQ360Artonline Home
 
02 pmp project life cycle exam
02 pmp project life cycle exam02 pmp project life cycle exam
02 pmp project life cycle examJamil Faraj , PMP
 
PMP Chap 5 - Project Scope Management - Part 2
PMP Chap 5 - Project Scope Management - Part 2PMP Chap 5 - Project Scope Management - Part 2
PMP Chap 5 - Project Scope Management - Part 2Anand Bobade
 
13 pmp professional responsibility exam
13 pmp professional responsibility exam13 pmp professional responsibility exam
13 pmp professional responsibility examJamil Faraj , PMP
 
PMP 47 process definitions
PMP 47 process definitionsPMP 47 process definitions
PMP 47 process definitionsAnand Bobade
 
Project management process and Project Management Knowledge areas
Project management process and Project Management Knowledge areasProject management process and Project Management Knowledge areas
Project management process and Project Management Knowledge areasMazen Zbib
 
Design & Development Of A Schedule Management Plan Presentation
Design & Development Of A Schedule Management Plan PresentationDesign & Development Of A Schedule Management Plan Presentation
Design & Development Of A Schedule Management Plan PresentationChris Carson
 

Tendances (20)

Pmp5
Pmp5Pmp5
Pmp5
 
04 pmp integration management exam
04 pmp integration management exam04 pmp integration management exam
04 pmp integration management exam
 
01 pmp introduct to project management exam
01 pmp introduct to project management exam01 pmp introduct to project management exam
01 pmp introduct to project management exam
 
Pmp6
Pmp6Pmp6
Pmp6
 
11 pmp risk management exam
11 pmp risk management exam11 pmp risk management exam
11 pmp risk management exam
 
1
11
1
 
Pmp3
Pmp3Pmp3
Pmp3
 
04 pmp integration management exam
04 pmp integration management exam04 pmp integration management exam
04 pmp integration management exam
 
06 pmp time management exam
06 pmp time  management exam06 pmp time  management exam
06 pmp time management exam
 
Pmp exam q&a
Pmp exam q&aPmp exam q&a
Pmp exam q&a
 
12 pmp procurement management exam
12 pmp procurement management exam12 pmp procurement management exam
12 pmp procurement management exam
 
Pmp1
Pmp1Pmp1
Pmp1
 
PMP 1600 Questions by TechFAQ360
PMP 1600 Questions by TechFAQ360PMP 1600 Questions by TechFAQ360
PMP 1600 Questions by TechFAQ360
 
02 pmp project life cycle exam
02 pmp project life cycle exam02 pmp project life cycle exam
02 pmp project life cycle exam
 
PMP Chap 5 - Project Scope Management - Part 2
PMP Chap 5 - Project Scope Management - Part 2PMP Chap 5 - Project Scope Management - Part 2
PMP Chap 5 - Project Scope Management - Part 2
 
PMP / Framework 1 2-3
PMP / Framework 1 2-3PMP / Framework 1 2-3
PMP / Framework 1 2-3
 
13 pmp professional responsibility exam
13 pmp professional responsibility exam13 pmp professional responsibility exam
13 pmp professional responsibility exam
 
PMP 47 process definitions
PMP 47 process definitionsPMP 47 process definitions
PMP 47 process definitions
 
Project management process and Project Management Knowledge areas
Project management process and Project Management Knowledge areasProject management process and Project Management Knowledge areas
Project management process and Project Management Knowledge areas
 
Design & Development Of A Schedule Management Plan Presentation
Design & Development Of A Schedule Management Plan PresentationDesign & Development Of A Schedule Management Plan Presentation
Design & Development Of A Schedule Management Plan Presentation
 

Similaire à 05 pmp scope management exam

PMP Lite Mock Exam2.pdf
PMP Lite Mock Exam2.pdfPMP Lite Mock Exam2.pdf
PMP Lite Mock Exam2.pdfMoncefMakni1
 
PMP-Prep-Exam-Test-200_Questions.pdf
PMP-Prep-Exam-Test-200_Questions.pdfPMP-Prep-Exam-Test-200_Questions.pdf
PMP-Prep-Exam-Test-200_Questions.pdfProject Cubicle
 
Pmp Questions Complete
Pmp Questions CompletePmp Questions Complete
Pmp Questions CompleteKareemBullard1
 
2.05 scope management 1
2.05 scope management 12.05 scope management 1
2.05 scope management 1reddvise
 
Рынок труда
Рынок трудаРынок труда
Рынок трудаEvgeniya
 
Lec 08 project scope_management
Lec 08 project scope_managementLec 08 project scope_management
Lec 08 project scope_managementSAJID ALI RUK
 
Question 1 Artifacts” in the Scrum terminology are the equiva.docx
Question 1 Artifacts” in the Scrum terminology are the equiva.docxQuestion 1 Artifacts” in the Scrum terminology are the equiva.docx
Question 1 Artifacts” in the Scrum terminology are the equiva.docxIRESH3
 
Full length mock test useful for PMP Exam folks
Full length mock test useful for PMP Exam folksFull length mock test useful for PMP Exam folks
Full length mock test useful for PMP Exam folksSudharsan Purushothaman
 
Pmp project management professional free sample
Pmp project management professional free samplePmp project management professional free sample
Pmp project management professional free sampleAnnsstand
 
PMP assessment exam 1.1
PMP assessment exam 1.1PMP assessment exam 1.1
PMP assessment exam 1.1Daniel Hucks
 
APMP More MC Questions
APMP More MC QuestionsAPMP More MC Questions
APMP More MC QuestionsMonica Waters
 

Similaire à 05 pmp scope management exam (20)

Session 4 gdas pmp study group presentation
Session 4   gdas pmp study group presentationSession 4   gdas pmp study group presentation
Session 4 gdas pmp study group presentation
 
PMP Lite Mock Exam2.pdf
PMP Lite Mock Exam2.pdfPMP Lite Mock Exam2.pdf
PMP Lite Mock Exam2.pdf
 
PMP-Prep-Exam-Test-200_Questions.pdf
PMP-Prep-Exam-Test-200_Questions.pdfPMP-Prep-Exam-Test-200_Questions.pdf
PMP-Prep-Exam-Test-200_Questions.pdf
 
pmp 200 q ans_key
pmp 200 q ans_keypmp 200 q ans_key
pmp 200 q ans_key
 
Ch05
Ch05Ch05
Ch05
 
Pmp sample qa3
Pmp sample qa3Pmp sample qa3
Pmp sample qa3
 
PMP certification
PMP certificationPMP certification
PMP certification
 
Pmp Questions Complete
Pmp Questions CompletePmp Questions Complete
Pmp Questions Complete
 
Pmp test 01
Pmp test 01Pmp test 01
Pmp test 01
 
2.05 scope management 1
2.05 scope management 12.05 scope management 1
2.05 scope management 1
 
Рынок труда
Рынок трудаРынок труда
Рынок труда
 
Lec 08 project scope_management
Lec 08 project scope_managementLec 08 project scope_management
Lec 08 project scope_management
 
Pmp test 02
Pmp test 02Pmp test 02
Pmp test 02
 
Question 1 Artifacts” in the Scrum terminology are the equiva.docx
Question 1 Artifacts” in the Scrum terminology are the equiva.docxQuestion 1 Artifacts” in the Scrum terminology are the equiva.docx
Question 1 Artifacts” in the Scrum terminology are the equiva.docx
 
Full length mock test useful for PMP Exam folks
Full length mock test useful for PMP Exam folksFull length mock test useful for PMP Exam folks
Full length mock test useful for PMP Exam folks
 
Pmp project management professional free sample
Pmp project management professional free samplePmp project management professional free sample
Pmp project management professional free sample
 
Session 3 gdas pmp study group presentation
Session 3   gdas pmp study group presentationSession 3   gdas pmp study group presentation
Session 3 gdas pmp study group presentation
 
02 project scope management
02 project scope management02 project scope management
02 project scope management
 
PMP assessment exam 1.1
PMP assessment exam 1.1PMP assessment exam 1.1
PMP assessment exam 1.1
 
APMP More MC Questions
APMP More MC QuestionsAPMP More MC Questions
APMP More MC Questions
 

Plus de Jamil Faraj , PMP

Plus de Jamil Faraj , PMP (11)

Corona-virus PMP study plan
Corona-virus PMP study planCorona-virus PMP study plan
Corona-virus PMP study plan
 
PMP Study Plan by Jamil Faraj, PMP
PMP Study Plan by Jamil Faraj, PMPPMP Study Plan by Jamil Faraj, PMP
PMP Study Plan by Jamil Faraj, PMP
 
Jamil Faraj CV 2020
Jamil Faraj CV 2020Jamil Faraj CV 2020
Jamil Faraj CV 2020
 
Jamil faraj hassan CV
Jamil faraj hassan CVJamil faraj hassan CV
Jamil faraj hassan CV
 
PMP ITTOs Quick Review
PMP ITTOs Quick Review PMP ITTOs Quick Review
PMP ITTOs Quick Review
 
Jamil pmp Certificate 2020
Jamil pmp Certificate 2020Jamil pmp Certificate 2020
Jamil pmp Certificate 2020
 
2
22
2
 
Jamil Hassan, PMP lessons learned.
Jamil Hassan, PMP lessons learned.Jamil Hassan, PMP lessons learned.
Jamil Hassan, PMP lessons learned.
 
Jamil Faraj CV- English
Jamil Faraj CV- EnglishJamil Faraj CV- English
Jamil Faraj CV- English
 
Pmp Formula Pocket_Guide
Pmp Formula Pocket_GuidePmp Formula Pocket_Guide
Pmp Formula Pocket_Guide
 
دورة وظيفة العمر
دورة وظيفة العمردورة وظيفة العمر
دورة وظيفة العمر
 

Dernier

1911 Gold Corporate Presentation Apr 2024.pdf
1911 Gold Corporate Presentation Apr 2024.pdf1911 Gold Corporate Presentation Apr 2024.pdf
1911 Gold Corporate Presentation Apr 2024.pdfShaun Heinrichs
 
BAILMENT & PLEDGE business law notes.pptx
BAILMENT & PLEDGE business law notes.pptxBAILMENT & PLEDGE business law notes.pptx
BAILMENT & PLEDGE business law notes.pptxran17april2001
 
GUIDELINES ON USEFUL FORMS IN FREIGHT FORWARDING (F) Danny Diep Toh MBA.pdf
GUIDELINES ON USEFUL FORMS IN FREIGHT FORWARDING (F) Danny Diep Toh MBA.pdfGUIDELINES ON USEFUL FORMS IN FREIGHT FORWARDING (F) Danny Diep Toh MBA.pdf
GUIDELINES ON USEFUL FORMS IN FREIGHT FORWARDING (F) Danny Diep Toh MBA.pdfDanny Diep To
 
Welding Electrode Making Machine By Deccan Dynamics
Welding Electrode Making Machine By Deccan DynamicsWelding Electrode Making Machine By Deccan Dynamics
Welding Electrode Making Machine By Deccan DynamicsIndiaMART InterMESH Limited
 
Onemonitar Android Spy App Features: Explore Advanced Monitoring Capabilities
Onemonitar Android Spy App Features: Explore Advanced Monitoring CapabilitiesOnemonitar Android Spy App Features: Explore Advanced Monitoring Capabilities
Onemonitar Android Spy App Features: Explore Advanced Monitoring CapabilitiesOne Monitar
 
How Generative AI Is Transforming Your Business | Byond Growth Insights | Apr...
How Generative AI Is Transforming Your Business | Byond Growth Insights | Apr...How Generative AI Is Transforming Your Business | Byond Growth Insights | Apr...
How Generative AI Is Transforming Your Business | Byond Growth Insights | Apr...Hector Del Castillo, CPM, CPMM
 
Healthcare Feb. & Mar. Healthcare Newsletter
Healthcare Feb. & Mar. Healthcare NewsletterHealthcare Feb. & Mar. Healthcare Newsletter
Healthcare Feb. & Mar. Healthcare NewsletterJamesConcepcion7
 
Intermediate Accounting, Volume 2, 13th Canadian Edition by Donald E. Kieso t...
Intermediate Accounting, Volume 2, 13th Canadian Edition by Donald E. Kieso t...Intermediate Accounting, Volume 2, 13th Canadian Edition by Donald E. Kieso t...
Intermediate Accounting, Volume 2, 13th Canadian Edition by Donald E. Kieso t...ssuserf63bd7
 
Introducing the Analogic framework for business planning applications
Introducing the Analogic framework for business planning applicationsIntroducing the Analogic framework for business planning applications
Introducing the Analogic framework for business planning applicationsKnowledgeSeed
 
APRIL2024_UKRAINE_xml_0000000000000 .pdf
APRIL2024_UKRAINE_xml_0000000000000 .pdfAPRIL2024_UKRAINE_xml_0000000000000 .pdf
APRIL2024_UKRAINE_xml_0000000000000 .pdfRbc Rbcua
 
Supercharge Your eCommerce Stores-acowebs
Supercharge Your eCommerce Stores-acowebsSupercharge Your eCommerce Stores-acowebs
Supercharge Your eCommerce Stores-acowebsGOKUL JS
 
20200128 Ethical by Design - Whitepaper.pdf
20200128 Ethical by Design - Whitepaper.pdf20200128 Ethical by Design - Whitepaper.pdf
20200128 Ethical by Design - Whitepaper.pdfChris Skinner
 
TriStar Gold Corporate Presentation - April 2024
TriStar Gold Corporate Presentation - April 2024TriStar Gold Corporate Presentation - April 2024
TriStar Gold Corporate Presentation - April 2024Adnet Communications
 
Appkodes Tinder Clone Script with Customisable Solutions.pptx
Appkodes Tinder Clone Script with Customisable Solutions.pptxAppkodes Tinder Clone Script with Customisable Solutions.pptx
Appkodes Tinder Clone Script with Customisable Solutions.pptxappkodes
 
WSMM Technology February.March Newsletter_vF.pdf
WSMM Technology February.March Newsletter_vF.pdfWSMM Technology February.March Newsletter_vF.pdf
WSMM Technology February.March Newsletter_vF.pdfJamesConcepcion7
 
Unveiling the Soundscape Music for Psychedelic Experiences
Unveiling the Soundscape Music for Psychedelic ExperiencesUnveiling the Soundscape Music for Psychedelic Experiences
Unveiling the Soundscape Music for Psychedelic ExperiencesDoe Paoro
 
trending-flavors-and-ingredients-in-salty-snacks-us-2024_Redacted-V2.pdf
trending-flavors-and-ingredients-in-salty-snacks-us-2024_Redacted-V2.pdftrending-flavors-and-ingredients-in-salty-snacks-us-2024_Redacted-V2.pdf
trending-flavors-and-ingredients-in-salty-snacks-us-2024_Redacted-V2.pdfMintel Group
 
EUDR Info Meeting Ethiopian coffee exporters
EUDR Info Meeting Ethiopian coffee exportersEUDR Info Meeting Ethiopian coffee exporters
EUDR Info Meeting Ethiopian coffee exportersPeter Horsten
 
Driving Business Impact for PMs with Jon Harmer
Driving Business Impact for PMs with Jon HarmerDriving Business Impact for PMs with Jon Harmer
Driving Business Impact for PMs with Jon HarmerAggregage
 
Guide Complete Set of Residential Architectural Drawings PDF
Guide Complete Set of Residential Architectural Drawings PDFGuide Complete Set of Residential Architectural Drawings PDF
Guide Complete Set of Residential Architectural Drawings PDFChandresh Chudasama
 

Dernier (20)

1911 Gold Corporate Presentation Apr 2024.pdf
1911 Gold Corporate Presentation Apr 2024.pdf1911 Gold Corporate Presentation Apr 2024.pdf
1911 Gold Corporate Presentation Apr 2024.pdf
 
BAILMENT & PLEDGE business law notes.pptx
BAILMENT & PLEDGE business law notes.pptxBAILMENT & PLEDGE business law notes.pptx
BAILMENT & PLEDGE business law notes.pptx
 
GUIDELINES ON USEFUL FORMS IN FREIGHT FORWARDING (F) Danny Diep Toh MBA.pdf
GUIDELINES ON USEFUL FORMS IN FREIGHT FORWARDING (F) Danny Diep Toh MBA.pdfGUIDELINES ON USEFUL FORMS IN FREIGHT FORWARDING (F) Danny Diep Toh MBA.pdf
GUIDELINES ON USEFUL FORMS IN FREIGHT FORWARDING (F) Danny Diep Toh MBA.pdf
 
Welding Electrode Making Machine By Deccan Dynamics
Welding Electrode Making Machine By Deccan DynamicsWelding Electrode Making Machine By Deccan Dynamics
Welding Electrode Making Machine By Deccan Dynamics
 
Onemonitar Android Spy App Features: Explore Advanced Monitoring Capabilities
Onemonitar Android Spy App Features: Explore Advanced Monitoring CapabilitiesOnemonitar Android Spy App Features: Explore Advanced Monitoring Capabilities
Onemonitar Android Spy App Features: Explore Advanced Monitoring Capabilities
 
How Generative AI Is Transforming Your Business | Byond Growth Insights | Apr...
How Generative AI Is Transforming Your Business | Byond Growth Insights | Apr...How Generative AI Is Transforming Your Business | Byond Growth Insights | Apr...
How Generative AI Is Transforming Your Business | Byond Growth Insights | Apr...
 
Healthcare Feb. & Mar. Healthcare Newsletter
Healthcare Feb. & Mar. Healthcare NewsletterHealthcare Feb. & Mar. Healthcare Newsletter
Healthcare Feb. & Mar. Healthcare Newsletter
 
Intermediate Accounting, Volume 2, 13th Canadian Edition by Donald E. Kieso t...
Intermediate Accounting, Volume 2, 13th Canadian Edition by Donald E. Kieso t...Intermediate Accounting, Volume 2, 13th Canadian Edition by Donald E. Kieso t...
Intermediate Accounting, Volume 2, 13th Canadian Edition by Donald E. Kieso t...
 
Introducing the Analogic framework for business planning applications
Introducing the Analogic framework for business planning applicationsIntroducing the Analogic framework for business planning applications
Introducing the Analogic framework for business planning applications
 
APRIL2024_UKRAINE_xml_0000000000000 .pdf
APRIL2024_UKRAINE_xml_0000000000000 .pdfAPRIL2024_UKRAINE_xml_0000000000000 .pdf
APRIL2024_UKRAINE_xml_0000000000000 .pdf
 
Supercharge Your eCommerce Stores-acowebs
Supercharge Your eCommerce Stores-acowebsSupercharge Your eCommerce Stores-acowebs
Supercharge Your eCommerce Stores-acowebs
 
20200128 Ethical by Design - Whitepaper.pdf
20200128 Ethical by Design - Whitepaper.pdf20200128 Ethical by Design - Whitepaper.pdf
20200128 Ethical by Design - Whitepaper.pdf
 
TriStar Gold Corporate Presentation - April 2024
TriStar Gold Corporate Presentation - April 2024TriStar Gold Corporate Presentation - April 2024
TriStar Gold Corporate Presentation - April 2024
 
Appkodes Tinder Clone Script with Customisable Solutions.pptx
Appkodes Tinder Clone Script with Customisable Solutions.pptxAppkodes Tinder Clone Script with Customisable Solutions.pptx
Appkodes Tinder Clone Script with Customisable Solutions.pptx
 
WSMM Technology February.March Newsletter_vF.pdf
WSMM Technology February.March Newsletter_vF.pdfWSMM Technology February.March Newsletter_vF.pdf
WSMM Technology February.March Newsletter_vF.pdf
 
Unveiling the Soundscape Music for Psychedelic Experiences
Unveiling the Soundscape Music for Psychedelic ExperiencesUnveiling the Soundscape Music for Psychedelic Experiences
Unveiling the Soundscape Music for Psychedelic Experiences
 
trending-flavors-and-ingredients-in-salty-snacks-us-2024_Redacted-V2.pdf
trending-flavors-and-ingredients-in-salty-snacks-us-2024_Redacted-V2.pdftrending-flavors-and-ingredients-in-salty-snacks-us-2024_Redacted-V2.pdf
trending-flavors-and-ingredients-in-salty-snacks-us-2024_Redacted-V2.pdf
 
EUDR Info Meeting Ethiopian coffee exporters
EUDR Info Meeting Ethiopian coffee exportersEUDR Info Meeting Ethiopian coffee exporters
EUDR Info Meeting Ethiopian coffee exporters
 
Driving Business Impact for PMs with Jon Harmer
Driving Business Impact for PMs with Jon HarmerDriving Business Impact for PMs with Jon Harmer
Driving Business Impact for PMs with Jon Harmer
 
Guide Complete Set of Residential Architectural Drawings PDF
Guide Complete Set of Residential Architectural Drawings PDFGuide Complete Set of Residential Architectural Drawings PDF
Guide Complete Set of Residential Architectural Drawings PDF
 

05 pmp scope management exam

  • 1. you are here 4   219 scope management Exam Questions 1. Which of the following is TRUE about a work breakdown structure? It contains work packages that are described in a linear, unstructured listA. Each item in the WBS represents a feature in the product scopeB. The WBS represents all of the work that must be done on the projectC. The WBS is created by the product sponsor and stakeholdersD. 2. Which is NOT an output of a scope management process? Business CaseA. B. WBS Dictionary Requested changesC. Accepted deliverablesD. 3. Which of the following is NOT TRUE about a work breakdown structure? It describes processes to define the scope, verify work, and manage scope changesA. It contains a graphical, hierarchical list of all work to be performedB. It can be broken down byC. project phase or deliverable It is an important element of theD. scope baseline 4. What is the correct order of the scope management processes? Define Scope, Create WBS,A. Collect Requirements, Scope Verification Collect Requirements,B. Control Scope, Create WBS, Scope Verification Collect Requirements, Define Scope, Create WBS, Scope VerificationC. D. Collect Requirements, Scope Baseline, Define Scope, Control Scope 5. You are managing a software project. Your team has been working for eight weeks, and so far the project is on track. The lead programmer comes to you with a problem: there is a work package that is causing trouble. Nobody seems to know who is responsible for it, the accounting department does not know what cost center to bill it against, and it’s not even clear exactly what work should be performed. Which of the following would BEST help this situation? Alternatives AnalysisA. WBS DictionaryB. Scope Management PlanC. Scope VerificationD. Download at Boykma.Com
  • 2. 220   Chapter 5 Exam Questions 6. The goal of Verify Scope is: To inspect the scope statement for defects so that it is correctA. To gain formal acceptance of the project deliverables from the sponsor and stakeholdersB. To get everyone in the project working together towards a common goalC. To verify that all PMBOK® Guide processes are complied withD. 7. Historical information and lessons learned are part of: Organizational process assetsA. Enterprise environmental factorsB. Project management information system (PMIS)C. Work performance informationD. 8. You’ve taken over as a project manager on a highway construction project, and the execution is already underway. Your sponsor tells you that moving forward, all asphalt should be laid down with a 12” thickness. The scope statement and the WBS call for 9” thick asphalt. What is the BEST course of action? Look for a cheaper supplier so the cost impact is minimizedA. Tell the sponsor that the work is already underway, so you can’t accommodate his requestB. Refuse to alter the plans until the change control system has been usedC. Tell the team to accommodate the request immediatelyD. 9. Which of the following BEST describes the purpose of a traceability matrix? It describes how WBS Dictionary entries are traced to work packages, and how work packages are decomposedA. from deliverables It’s used to make sure that all of the sub-plans of the Project Management Plan have been createdB. It helps you understand the source of each requirement, and how that requirement was verified in a later deliverableC. It’s used to trace the source of every change, so that you can keep track of them through the entire Control ScopeD. process and verify that the change was properly implemented 10. It’s the end of execution for a large highway construction project. The work has been done, and the workers are ready to pack up their equipment. The project manager and project sponsor have come by with specialists to check that each requirement has been met, and that all of the work in the WBS has been performed. What process is being done? Control ScopeA. Verify ScopeB. Scope TestingC. Define ScopeD. exam questions Download at Boykma.Com
  • 3. you are here 4   221 scope management Exam Questions 11. You have just been put in charge of a project that is already executing. While reviewing the project documentation, you discover that there is no WBS. You check the Scope Management Plan and discover that there should be one for this project. What is the BEST thing for you to do: Immediately alert the sponsor and make sure the project work doesn’t stopA. Stop project work and create the WBS, and don’t let work continue until it’s createdB. Make sure you closely manage communications to ensure the team doesn’t miss any undocumented workC. Mark it down in the lessons learned so it doesn’t happen on future projectsD. 12. A project manager on an industrial design project finds that the sponsor wants to make a change to the scope after it has been added to the baseline, and needs to know the procedure for managing changes. What is the BEST place to look for this information? WBSA. Scope management planB. Change request form templateC. Business CaseD. 13. You have just started work on the Project Scope Statement. You are analyzing the expected deliverables, when you discover that one of them could be delivered in three different ways. You select the best method for creating that deliverable. What is the BEST way to describe what you are doing? Alternatives AnalysisA. DecompositionB. Define ScopeC. Stakeholder AnalysisD. 14. You’re the project manager on a software project. Your team has only completed half of the work, when the sponsor informs you that the project has been terminated. What is the BEST action for you to take? Verify the deliverables produced by the team against the scope, and document any place they do not matchA. Call a team meeting to figure out how to spend the rest of the budgetB. Work with the sponsor to see if there is any way to bring the project backC. Tell the team to stop working immediatelyD. 15. You are managing an industrial design project. One of your team members comes to you with a suggestion that will let you do more work while at the same time saving the project 15% of the budget. What is the BEST way for you to proceed? Tell the team to make the change because it will deliver more work for less moneyA. Refuse to make the change until aB. change request is documented and change control is performed Refuse to consider the change because it will affect the baselineC. Do a cost-benefit analysis and then make sure to inform the sponsor that the project scope changedD. Download at Boykma.Com
  • 4. 222   Chapter 5 Exam Questions 16. You are the project manager for a telecommunications project. You are working on the project scope statement. Which of the following is NOT included in this document? Authorization for the project manager to work on the projectA. Requirements that the deliverables must meetB. A description of the project objectivesC. The list of deliverables that must be createdD. 17. Which of the following is NOT an input to Control Scope? WBS DictionaryA. Approved change requestsB. Requested changesC. Project scope statementD. 18. Which of these processes is not a part of Scope Management? Scope IdentificationA. Collect RequirementsB. Control ScopeC. Scope VerificationD. 19. You are the project manager for a new project, and you want to save time creating the WBS. Which is the BEST way to do this? MakeA. decomposition go faster by cutting down the number of deliverables Use a WBS from a previous project as a templateB. Don’t create the WBS DictionaryC. Ask the sponsor to provide the work packages for each deliverableD. 20. The project manager for a design project is using the Define Scope process. Which BEST describes this? Creating a document that lists all of the features of the productA. Creating a plan for managing changes to theB. scope baseline Creating a document that describes all of the work the team does to make the deliverablesC. Creating a graphical representation of how the phases or deliverables decompose into work packagesD. 21. You are the project manager for a construction project. You have completed project initiation activities, and you are now creating a document that describes processes to document the scope, decompose deliverables into work packages, verify that all work is complete, and manage changes to the baseline. What process are you performing? Develop Project Management PlanA. Define ScopeB. Create WBSC. Develop Project CharterD. exam questions Download at Boykma.Com
  • 5. you are here 4   223 scope management Exam Questions 22. You are a project manager working on a project. Your sponsor wants to know who a certain work package is assigned to, what control account to bill it against, and what work is involved. What document do you refer her to? Scope Management PlanA. WBSB. WBS DictionaryC. D. Scope Statement 24. You are the project manager for a software project. One of the teams discovers that if they deviate from the plan, they can actually skip one of the deliverables because it’s no longer necessary. They do the calculations, and realize they can save the customer 10% of the cost of the project without compromising the features in the product. They take this approach, and inform you the following week what they did during the status meeting. What is the BEST way to describe this situation? The project team has taken initiative and saved the customer moneyA. A dispute is resolved in favor of the customerB. The team informed the project manager of the change, but they should have informed the customer tooC. The team did not follow the Control Scope processD. 25. Which of the following BEST describes the purpose of the project scope statement? It describes the features of the product of the projectA. It is created before theB. scope management plan It decomposes deliverables into work packagesC. It describes the objectives, requirements, and deliverables of the project, and the work needed to create themD. 26. A project manager at a cable and networking company is gathering requirements for a project to build a new version of their telecommunications equipment. Which of the following is NOT something that she will use? Specific descriptions of work packages that will be developedA. One-on-one interviews with the senior executives who need the new equipment for their teamsB. An early working model of the telecommunications equipment to help get feedback from stakeholdersC. Notes that she took while being “embedded” with the team that will eventually use the equipment beingD. developed 27. Which of the following is NOT an output of Collect Requirements? Requirements ObservationsA. Requirements Traceability MatrixB. Requirements DocumentationC. Requirements Management PlanD. Download at Boykma.Com
  • 6. 224   Chapter 5 Exam Questions Answers 1. Answer: C The work breakdown structure is all about breaking down the work that your team needs to do. The WBS is graphical and hierarchical, not linear and unstructured. Did you notice that answer B was about product scope, not project scope? 2. Answer: A There are two ways you can get to the right answer for this question. You can recognize that the WBS Dictionary, Change Requests, and Accepted Deliverables are all Scope Management process outputs. (You’ll see Change Requests in every knowledge area!) But you can also recognize that the Business Case was created by the Develop Projct Charter which is part of the Initiating process group. 3. Answer: A Did you recognize that answer A was describing the scope management plan? Once you know what the WBS is used for and how to make one, questions like this make sense. 4. Answer: C You’ll need to know what order processes come in, and one good way to do that is to think about how the outputs of some processes are used as inputs for another. For example, you can’t create the WBS until the scope is defined, which is why A is wrong. And you can’t do change control until you have a baseline WBS, which is why B is wrong. 5. Answer: B An important tactic for a lot of exam questions is to be able to recognize a particular tool, technique, input, or output from a description. What have you learned about that tells you who is responsible for a work package, what control account to associate with it, and describes the work associated with it? That’s a good description of the WBS Dictionary. 6. Answer: B There are some questions where you’ll just have to know what a process is all about, and this is one of them. That’s why it’s really helpful to know why Verify Scope is so helpful to you on a project. You use Verify Scope to check that all of the work packages were completed, and get the stakeholders and sponsor to formally accept the deliverables. Take a minute and think about how there’s no “right” order for Scope Verification and Control Scope. You could have a scope change at the beginning of the project, so Control Scope would come first. But a change could happen late in the project, too! If there’s a major change to the project after the scope’s verified, you need to redo it. exam answers Inspection isn’t just done at the end of the project. You do Scope Verification on every single deliverable made by you and the team. Download at Boykma.Com
  • 7. you are here 4   225 scope management Exam Questions Answers The PMBOK® Guide says this stuff is stored in a “corporate knowledge base,” but that’s just another word for a file cabinet or a folder on your network 7. Answer: A It’s easy to forget that Organizational Process Assets is more than just an input. It’s a real thing that’s part of your company. Take a second and think about what assets are in your organization that help you with carry out each process. Get it? Good! So what is historical information, anyway? It’s stuff like reports and data that you or another project manager wrote down on a previous project and stored in a file cabinet or a database. That’s an asset you can use now! What are lessons learned? Those are lessons you wrote down at the end of a previous project and stuck in a file cabinet or a database. And now those lessons are another asset you can use. 8. Answer: C One thing to remember about change control is that if you want to make the sponsor and stakeholders happy with the project in the end, sometimes you have to tell them “no” right now. When you’re doing Control Scope, the most important tool you use is the change control system. It tells you how to take an approved change and put it in place on a project, and there’s no other way that you should ever make a change to any part of the baseline. That means that once everyone has approved the scope statement and WBS, if you want to make any change to them, then you need to get that change approved and put it through the change control system. 9. Answer: C The Requirements Traceability Matrix is a tool that you use to trace each requirement back to a specific business case, and then forward to the rest of the scope deliverables (like specific WBS work packages), as well as other parts of the project: the product design (like specific levels in Cows Gone Wild) or test strategy (like test plans that the Ranch Hand Games testers use to make sure that the game works). These inputs and outputs make sense when I think about how I’d use them on a project. Organizational Process Assets are just things that my organization keeps track of to help me do my job, like information from old projects and procedures that help me do my job. The idea is that you’re tracing a deliverable from its initial description all the way through the project through testing, so that you can make sure that every single deliverable meets all of its requirements. Download at Boykma.Com
  • 8. 226   Chapter 5 10. Answer: B When you’re getting the sponsor and stakeholders to formally accept the results of the project, you’re doing scope verification. There’s only one tool for it: inspection. That means carefully checking the deliverables (in this case, what the workers built on the highway) to make sure they match the WBS. 11. Answer: B This question is a little tricky. The most important thing about a WBS is that if your Scope Management Plan says it should be there, then your project absolutely cannot be done without it. And a general rule is that if you ever find that there is no WBS, you should always check the Scope Management Plan to find out why. 12. Answer: B This is another question that is testing you on the definition of a specific document, in this case the Scope Management Plan, which is one of the subsidiary plans of the Project Management Plan. Think about what you use a Scope Management Plan for. It gives you specific procedures for defining the scope, breaking down the work, verifying the deliverables, and managing scope changes—which is what this question is asking. All of the other answers don’t have anything to do with managing changes. Exam Questions Answers Answer D is a good idea, but it’s notas important as creating a new WBS. That way, if I need to restart the project later or reuse some of its deliverables, I’ll know exactly where my team left off when it ended. 13. Answer: A Here’s another example of how there are two correct answers but only one BEST one. Answer C is true – you are doing scope definition. But is that really the best way to describe this situation? Alternatives analysis is part of scope definition, and it’s a more accurate way to describe what’s going on here. 14. Answer: A This question is an example of how you need to rely on more than just common sense to pass the PMP exam. All four of these answers could be good ways to handle a terminated project, but there’s only one of those answers that corresponds to what the PMBOK® Guide says. When a project is terminated, you still need to complete the Verify Scope process. That way, you can document all of the work that has been completed, and the work that has not been completed. When you look at a few ways to createa deliverable and then decide on thebest one, that’s alternatives analysis. exam answers Download at Boykma.Com
  • 9. you are here 4   227 scope management Exam Questions Answers 15. Answer: B Are you starting to get the hang of how this change control stuff works? The baseline isn’t etched in stone, and you need to be able to change it, but you can’t just go ahead and make changes whenever you want. You need to document the change request and then put that request through change control. If it’s approved, then you can update the baseline so that it incorporates the change. 16. Answer: A When a question asks you about what a particular document, input, or output contains, be on the lookout for answers that talk about a different document. What document do you know about that gives the project manager authorization to do the work? That’s what the project charter is for. 17. Answer: C Sometimes Control Scope is easiest to think about if you think of it as a kind of machine that turns approved changes into updates. It sucks in the approved changes and all of the other Scope Management stuff (the Scope Statement, WBS, and WBS Dictionary), does all the stuff that it needs to do to update those things, and then spits out updates. And sometimes it spits out new requested changes because when you’re making changes to the WBS or Scope Statement you realize that you need to make even more changes. 18. Answer: A Scope Identification is a made-up process. It didn’t appear in this chapter, and even though it sounds real, it’s wrong. 19. Answer: B WBS templates are a great way to speed up creating the WBS, and the easiest way to create a template is to use one from a previous project. It is not a good idea to cut out deliverables, skip important outputs like the WBS Dictionary, or make the sponsor do your job for you. You definitely can’t just makethe change and inform thesponsor later. All changes needto be approved. I think of Perform Integrated Change Control as a machine that turns change requests into approved changes, and Control Scope as the machine that turns approved changes into updates to the scope baseline. You can also use a template for the scope management plan. Download at Boykma.Com
  • 10. 228   Chapter 5 Exam Questions Answers 20. Answer: C This question asked you about the Define Scope process, but all of the answers describe various outputs. Which of these outputs matches Define Scope? Well, the main output of Define Scope is the Scope Statement, and answer C is a good description of the scope statement. 21. Answer: A This question asked you where you defined the procedures for doing all of the Scope Management Processes. Where do you find those procedures? You find them in the Project Management Plan—specifically, the Scope Management Plan sub-plan. And you build that in the Develop Project Management Plan process. 22. Answer: C There’s only one document you’ve seen that shows you details of individual work packages and contains a control account, a statement of work, and a resource assignment. It’s the WBS Dictionary. 23. Answer: D Here’s another question where you need to know how to describe an important tool. In this case, you need to know what the change control system is used for. Luckily, answer D is a pretty good description. Hey, I’ll bet a good way to study for the exam is to look at answers A, B, and C in question 23 and figure out what each of them is describing. It’ll be great practice identifying an output from a description! exam answers Did you guess “Create WBS” because it was a ScopeManagement process and the question mentioneddecomposing deliverables into work packages? Download at Boykma.Com
  • 11. you are here 4   229 scope management Exam Questions Answers 24. Answer: D When you read the question, it looks like the team really helped the project, right? But think about what happened: the team abandoned the plan, and then they made a change to the project without getting approval from the sponsor or stakeholders. Maybe they discovered a useful shortcut. But isn’t it possible that the shortcut the team found was already considered and rejected by the sponsor? That’s why change control is so important. 25. Answer: D Some questions are just definition questions. When that definition is a “Which-is-BEST” question, there could be an answer that makes some sense, and it’s tempting to stop with it. In this case, answer A sounds like it might be right. But if you read answer D, it’s much more accurate. 26. Answer: A The question asked about the tools and techniques for Collect Requirements, and answer A is the only answer that has to do with the Create WBS process. The rest of the answers were descriptions of Collect Requirements tools and techniques: Interviews (answer B), Prototypes (answer C), and Observations (answer D). 27. Answer: A The three outputs of Collect Requirements are Requirements Documentation, the Requirements Management Plan, and the Requirements Traceability Matrix. “Requirements Observations” isn’t really an output. Keep an eye out for questions that describe an input or output and then ask you to name it. Look at each answer and think up own descriptions for them—one of them will match the question. Did you notice how the question made it sound like the team did a good thing by ignoring Control Scope and making changes that were never approved? The easiest way to make sure you get questionslike this right is to think about how each of thoseoutputs are actually used later in the project. Download at Boykma.Com