IT Portfolio PlanningUsing Excel Jerry Bishop The Higher Ed CIO Creative Commons Attribution-NoDerivs 3.0 Unported License.
introduction Foundations  for the slides
Purpose To provide a simple and transparent paper-based method for setting up an IT project portfolio using Excel.
Why View this Presentation Without having prior experience this can seem impossible to know where to start. Before choosing a tool to do this, working out your method using Excel is a major benefit. It’s the only way to accurately commit to a body of work and know you can deliver on it. Tight FY12 budgets and increased demands require reasoned decisions on projects to do.
Who Should Complete This CIO’s IT Governance Committee – Project Approvers Functional Executives – Project Sponsors Functional Managers – Project Requesters IT Managers – Project Managers Project Management Office – Role Project Managers
What is a Portfolio Aggregates all demands expected of IT for review and approval decisions It’s like a “budget” for allocating staff to projects requiring IT resources A tool for building an “annual plan of work” It’s a workload management tool for seeing the total demand for IT resources
resource capacity How to determine your capacity
Guidelines for Capacity Determine the reasonable capacity a resource has to do project work Be conservative – avoid over committing  IT  Initially start with generic resources types Network Admin, Sys Admin, App Admin, DBA, App Analyst, Report Writer, Desktop Admin, Desktop Tech, Help Desk When comfortable  move to named resources if it makes sense
Portfolio Illustration The following illustration is taken from the actual initial FY11 portfolio for a college Reflects all initial requests for IT support and projects work for FY11 prior to approving or denying decisions were made Actual hours used here are from the 3-person Business Analyst group supporting the Banner ERP and related applications
Determining Raw Capacity Note:  2012 is a leap year with 261 weekdays from  July 1, 2011 to June 30, 2012
Raw Capacity Thoughts Keep it simple Averages are better when first starting out If overtime is taken as paid time off then add an additional deduction as with comp time 1 hour overtime becomes 1.5 hours PTO Illustration reflects sick and personal time being treated like non-contract “vacation” Use historical averages if appropriate
Determining Usable Capacity Note: Nobody is 100% productive with their day. There’s email, phone calls,  meetings, breaks ,and  birthday treats to hunt down.  This approach avoids having to track this in any detail.  Can be reconciled in time-tracking if used.
Maximizing Usable Capacity Consider the value of in-service activities HR and IT Governance input on the priority Limit participation to job related activities Manage productivity up to 95% or better Train on time and task management Minimize general team meetings, manager one-on-ones, and committee assignments Don’t use default meeting lengths Instead of 60 minutes use 45 or 30 it adds up
Creating the portfolio Loading the work load and resource demands
Terminology Routine Maintenance: Daily production support obligations. Checking logs, monitoring systems, tape handling, storage management, job scheduling, user administration. Operational Support: This is Incident Management (break-fix) work and standard Service Requests not considered projects.
Setting Up the Portfolio
Project Estimating Avoid getting bogged down on the estimate  Use SWAGs for initial estimates on all projects Take multiple passes through to refine Use ranges of hours 25, 50, 100, 150, 200, 500, 750, etc…. Estimating accuracy will improve Review estimates at project completion
Cautions “Research” and “Investigation” Projects Include them in the Portfolio Big capacity drains, often slow burning of hours Evaluating new technologies and software Managing Contingency Hours Decrement the bank as it is used You can’t use it all at the end, its not like cash Revenue generating (billable) projects Consider special treatment if fully funded in FY12
Organizing the Projects Separate projects by importance Most important come off the top Institutional  Strategic Plan related projects first Required (mandatory this year) Projects next Required for regulatory compliance – financial aid Required to stay on supported versions – Oracle 11G Means they cannot be deferred without risks Discretionary is everything else in rank order Value-add, nice to do, and projects that might become Required by next fiscal year
Loading the Portfolio
Balancing the Portfolio Part 1 Manage down Routine Maintenance  Look for activities to automate and free capacity Use Demand Management to reduce Support Target Top 5 support issues Develop Problem Management process Enforce IT Governance process Stop informal requests and drive-bys Manage scope to <10% variance
Balancing the Portfolio Part 2 Scrutinize ALL Required “Mandatory” Projects “Show Me” the requirement Challenge IT’s own Required Projects just as hard It’s discretionary if it van really wait IT Governance Focus on Priorities: The What, Not How Reduce Contingency Bank Percentage Challenge IT Managers to Free-Up Capacity Trim Scope and complexity of Projects Cancel projects instead of tapping contingency
The completed portfolio Approving the Annual Plan of Work
Assembling the Portfolio
Download the Excel File Download the excel file from SlideShare.net at Project Portfolio Planning - The Workbook
Full Portfolio Worksheet
Simple Resource Planning
Resourcing strategies Balancing the Portfolio
Supplemental Labor Thoughts Backfill labor for Operational work Often cheaper at $60 - $135 per hour More capacity for the same dollar Frees knowledgeable employees for projects Project Labor may be required More costly at $185 - $220 per hour Contract for fixed fee & guaranteed outcome Add contractor resource when it makes sense You have lots of work requiring vendor assistance
Balancing the Portfolio NOTE: Supplemental labor can include limited term employees, temps, contractors, and vendor resources.
Optional Staffing Strategy Staff IT department for normal workload  Routine Maintenance Operational Support Use supplemental labor for ALL project work Requires sponsor to account for full cost & ROI when championing the business case Allows flexing up then down as project load surges Maintains  minimal overhead run rates Simplifies producing savings  and avoids layoffs Add incremental staff FTE as new systems are added
Final Thoughts Portfolio planning takes some getting used to Leave contingency for unplanned projects They always come up Develop good IT Governance Committee Be transparent Publish your process and the Portfolio Train on project management
Questions? Look for others in this series IT Governance Project Requests Jerry Bishop The Higher Ed CIO

Contenu connexe

Tendances

PPM Challenge #1: Prioritizing Demand – 2012 PPM Challenge and Opportunity We...
PPM Challenge #1: Prioritizing Demand – 2012 PPM Challenge and Opportunity We...PPM Challenge #1: Prioritizing Demand – 2012 PPM Challenge and Opportunity We...
PPM Challenge #1: Prioritizing Demand – 2012 PPM Challenge and Opportunity We...
EPM Live
 
Implementing Enterprise PPM for Multi-Maturity Organizations
Implementing Enterprise PPM for Multi-Maturity Organizations Implementing Enterprise PPM for Multi-Maturity Organizations
Implementing Enterprise PPM for Multi-Maturity Organizations
EPM Live
 

Tendances (20)

PPM Challenge #1: Prioritizing Demand – 2012 PPM Challenge and Opportunity We...
PPM Challenge #1: Prioritizing Demand – 2012 PPM Challenge and Opportunity We...PPM Challenge #1: Prioritizing Demand – 2012 PPM Challenge and Opportunity We...
PPM Challenge #1: Prioritizing Demand – 2012 PPM Challenge and Opportunity We...
 
Garter. Project Manager 2014
Garter. Project Manager 2014Garter. Project Manager 2014
Garter. Project Manager 2014
 
Erp Implementation Methodology Wkshp 2.0 120611
Erp Implementation Methodology Wkshp 2.0 120611Erp Implementation Methodology Wkshp 2.0 120611
Erp Implementation Methodology Wkshp 2.0 120611
 
Implementing Enterprise PPM for Multi-Maturity Organizations
Implementing Enterprise PPM for Multi-Maturity Organizations Implementing Enterprise PPM for Multi-Maturity Organizations
Implementing Enterprise PPM for Multi-Maturity Organizations
 
Project Portfolio Strategic Planning
Project Portfolio Strategic PlanningProject Portfolio Strategic Planning
Project Portfolio Strategic Planning
 
ASAP Methodology in Implementing ERP
ASAP Methodology in Implementing ERPASAP Methodology in Implementing ERP
ASAP Methodology in Implementing ERP
 
Workflow and BPM in the New Enterprise Architecture
Workflow and BPM in the New Enterprise ArchitectureWorkflow and BPM in the New Enterprise Architecture
Workflow and BPM in the New Enterprise Architecture
 
Microsoft Project Server 2010
Microsoft Project Server 2010Microsoft Project Server 2010
Microsoft Project Server 2010
 
Ranking portfolio initiatives, Bernard Marshall, june 2012
Ranking portfolio initiatives, Bernard Marshall, june 2012Ranking portfolio initiatives, Bernard Marshall, june 2012
Ranking portfolio initiatives, Bernard Marshall, june 2012
 
How business process mapping saved an IT project.
How business process mapping saved an IT project.How business process mapping saved an IT project.
How business process mapping saved an IT project.
 
Impact of Project Portfolio Management on Project Success
Impact of Project Portfolio Management on Project SuccessImpact of Project Portfolio Management on Project Success
Impact of Project Portfolio Management on Project Success
 
10 tips to manage project portfolio management (ppm) processes
10 tips to manage project portfolio management (ppm) processes10 tips to manage project portfolio management (ppm) processes
10 tips to manage project portfolio management (ppm) processes
 
Vaibhav Misra Telecom Wireless Operations Management Consulting Presentation
Vaibhav Misra Telecom Wireless Operations Management Consulting PresentationVaibhav Misra Telecom Wireless Operations Management Consulting Presentation
Vaibhav Misra Telecom Wireless Operations Management Consulting Presentation
 
Extend Your PPM Application for Projects Products and Services
Extend Your PPM Application for Projects Products and ServicesExtend Your PPM Application for Projects Products and Services
Extend Your PPM Application for Projects Products and Services
 
CA PPM (Project & Portfolio Management
CA PPM (Project & Portfolio ManagementCA PPM (Project & Portfolio Management
CA PPM (Project & Portfolio Management
 
Project portfolio management an introduction
Project portfolio management   an introductionProject portfolio management   an introduction
Project portfolio management an introduction
 
PMI - Portfolio Management
PMI - Portfolio ManagementPMI - Portfolio Management
PMI - Portfolio Management
 
How to set up initiatives portfolio management
How to set up initiatives portfolio managementHow to set up initiatives portfolio management
How to set up initiatives portfolio management
 
It portfolio management case study presentation
It portfolio management case study presentationIt portfolio management case study presentation
It portfolio management case study presentation
 
Portfolio Mgt Presentation
Portfolio Mgt PresentationPortfolio Mgt Presentation
Portfolio Mgt Presentation
 

Similaire à IT Project Portfolio Planning Using Excel

PMO and PPM Best Practices
PMO and PPM Best PracticesPMO and PPM Best Practices
PMO and PPM Best Practices
Jeff McClay
 
Optimize Project Intake Approval and Prioritization
Optimize Project Intake Approval and PrioritizationOptimize Project Intake Approval and Prioritization
Optimize Project Intake Approval and Prioritization
Info-Tech Research Group
 
Project Management Overview
Project Management OverviewProject Management Overview
Project Management Overview
cford1973
 

Similaire à IT Project Portfolio Planning Using Excel (20)

11 Reasons Oracle E-Business Suite projects fail and how to fix them
11 Reasons Oracle E-Business Suite projects fail and how to fix them11 Reasons Oracle E-Business Suite projects fail and how to fix them
11 Reasons Oracle E-Business Suite projects fail and how to fix them
 
Key elements of it portfolio management Dipak Pimpale
Key elements of it portfolio management   Dipak PimpaleKey elements of it portfolio management   Dipak Pimpale
Key elements of it portfolio management Dipak Pimpale
 
You have a project manager yay
You have a project manager   yayYou have a project manager   yay
You have a project manager yay
 
Are your projects making the dean’s list?
Are your projects making the dean’s list?Are your projects making the dean’s list?
Are your projects making the dean’s list?
 
Project Management Office Roles Functions And Benefits
Project Management Office Roles Functions And BenefitsProject Management Office Roles Functions And Benefits
Project Management Office Roles Functions And Benefits
 
Practical application of Enterprise Architecture (abridged)
Practical application of Enterprise Architecture (abridged)Practical application of Enterprise Architecture (abridged)
Practical application of Enterprise Architecture (abridged)
 
Making IT Work for Your Business - 4 Key Concepts to Get the Most Out of Your...
Making IT Work for Your Business - 4 Key Concepts to Get the Most Out of Your...Making IT Work for Your Business - 4 Key Concepts to Get the Most Out of Your...
Making IT Work for Your Business - 4 Key Concepts to Get the Most Out of Your...
 
JF Burguet - ERP Experiences
JF Burguet - ERP ExperiencesJF Burguet - ERP Experiences
JF Burguet - ERP Experiences
 
Ba process plan- IGATE Global Solutions LTD
Ba process plan- IGATE Global Solutions LTDBa process plan- IGATE Global Solutions LTD
Ba process plan- IGATE Global Solutions LTD
 
Business Analyst Role in Hybrid Agile Waterfall
Business Analyst Role in Hybrid Agile WaterfallBusiness Analyst Role in Hybrid Agile Waterfall
Business Analyst Role in Hybrid Agile Waterfall
 
Managingtripleconstraint aam
Managingtripleconstraint aamManagingtripleconstraint aam
Managingtripleconstraint aam
 
PMO and PPM Best Practices
PMO and PPM Best PracticesPMO and PPM Best Practices
PMO and PPM Best Practices
 
Project Workflow Management Ultimate Guide
Project Workflow Management Ultimate GuideProject Workflow Management Ultimate Guide
Project Workflow Management Ultimate Guide
 
Project Workflow Management Ultimate Guidee (1).pdf
Project Workflow Management Ultimate Guidee (1).pdfProject Workflow Management Ultimate Guidee (1).pdf
Project Workflow Management Ultimate Guidee (1).pdf
 
ASAP-01 Implementaion.pptx
ASAP-01 Implementaion.pptxASAP-01 Implementaion.pptx
ASAP-01 Implementaion.pptx
 
1010 cd overview light
1010 cd overview light1010 cd overview light
1010 cd overview light
 
Guide to better Project Management from Severa
Guide to better Project Management from SeveraGuide to better Project Management from Severa
Guide to better Project Management from Severa
 
GJOC_resume_p-c_v4
GJOC_resume_p-c_v4GJOC_resume_p-c_v4
GJOC_resume_p-c_v4
 
Optimize Project Intake Approval and Prioritization
Optimize Project Intake Approval and PrioritizationOptimize Project Intake Approval and Prioritization
Optimize Project Intake Approval and Prioritization
 
Project Management Overview
Project Management OverviewProject Management Overview
Project Management Overview
 

Plus de Jerry Bishop

Plus de Jerry Bishop (17)

Export Control Overview
Export Control OverviewExport Control Overview
Export Control Overview
 
Maximizing SharePoint
Maximizing SharePointMaximizing SharePoint
Maximizing SharePoint
 
Captioning Policy Guide Draft
Captioning Policy Guide DraftCaptioning Policy Guide Draft
Captioning Policy Guide Draft
 
HEOA P2P Assessment
HEOA P2P AssessmentHEOA P2P Assessment
HEOA P2P Assessment
 
Developing an IT Service Strategy Part 1 Describing the Challenge
Developing an IT Service Strategy Part 1 Describing the  ChallengeDeveloping an IT Service Strategy Part 1 Describing the  Challenge
Developing an IT Service Strategy Part 1 Describing the Challenge
 
Project Request
Project RequestProject Request
Project Request
 
UCS Implementation Updates
UCS Implementation UpdatesUCS Implementation Updates
UCS Implementation Updates
 
IT Governance Made Easy
IT Governance Made EasyIT Governance Made Easy
IT Governance Made Easy
 
Desktop Management Using Microsoft SCCM
Desktop Management Using Microsoft SCCMDesktop Management Using Microsoft SCCM
Desktop Management Using Microsoft SCCM
 
The Decision: Build New vs The Cloud
The Decision: Build New vs The CloudThe Decision: Build New vs The Cloud
The Decision: Build New vs The Cloud
 
Crowdsourcing
CrowdsourcingCrowdsourcing
Crowdsourcing
 
Epic Support Model
Epic Support ModelEpic Support Model
Epic Support Model
 
IT Application Plan
IT Application PlanIT Application Plan
IT Application Plan
 
FY11 Teaching Station Refresh Plan
FY11 Teaching Station Refresh PlanFY11 Teaching Station Refresh Plan
FY11 Teaching Station Refresh Plan
 
FY11 PC Refresh Plan
FY11 PC Refresh PlanFY11 PC Refresh Plan
FY11 PC Refresh Plan
 
BTOP Grant for NIACC
BTOP Grant for NIACCBTOP Grant for NIACC
BTOP Grant for NIACC
 
Google Advanced Search
Google Advanced SearchGoogle Advanced Search
Google Advanced Search
 

Dernier

CNv6 Instructor Chapter 6 Quality of Service
CNv6 Instructor Chapter 6 Quality of ServiceCNv6 Instructor Chapter 6 Quality of Service
CNv6 Instructor Chapter 6 Quality of Service
giselly40
 
EIS-Webinar-Prompt-Knowledge-Eng-2024-04-08.pptx
EIS-Webinar-Prompt-Knowledge-Eng-2024-04-08.pptxEIS-Webinar-Prompt-Knowledge-Eng-2024-04-08.pptx
EIS-Webinar-Prompt-Knowledge-Eng-2024-04-08.pptx
Earley Information Science
 

Dernier (20)

The 7 Things I Know About Cyber Security After 25 Years | April 2024
The 7 Things I Know About Cyber Security After 25 Years | April 2024The 7 Things I Know About Cyber Security After 25 Years | April 2024
The 7 Things I Know About Cyber Security After 25 Years | April 2024
 
Evaluating the top large language models.pdf
Evaluating the top large language models.pdfEvaluating the top large language models.pdf
Evaluating the top large language models.pdf
 
Strategies for Unlocking Knowledge Management in Microsoft 365 in the Copilot...
Strategies for Unlocking Knowledge Management in Microsoft 365 in the Copilot...Strategies for Unlocking Knowledge Management in Microsoft 365 in the Copilot...
Strategies for Unlocking Knowledge Management in Microsoft 365 in the Copilot...
 
Handwritten Text Recognition for manuscripts and early printed texts
Handwritten Text Recognition for manuscripts and early printed textsHandwritten Text Recognition for manuscripts and early printed texts
Handwritten Text Recognition for manuscripts and early printed texts
 
Apidays Singapore 2024 - Building Digital Trust in a Digital Economy by Veron...
Apidays Singapore 2024 - Building Digital Trust in a Digital Economy by Veron...Apidays Singapore 2024 - Building Digital Trust in a Digital Economy by Veron...
Apidays Singapore 2024 - Building Digital Trust in a Digital Economy by Veron...
 
presentation ICT roal in 21st century education
presentation ICT roal in 21st century educationpresentation ICT roal in 21st century education
presentation ICT roal in 21st century education
 
CNv6 Instructor Chapter 6 Quality of Service
CNv6 Instructor Chapter 6 Quality of ServiceCNv6 Instructor Chapter 6 Quality of Service
CNv6 Instructor Chapter 6 Quality of Service
 
EIS-Webinar-Prompt-Knowledge-Eng-2024-04-08.pptx
EIS-Webinar-Prompt-Knowledge-Eng-2024-04-08.pptxEIS-Webinar-Prompt-Knowledge-Eng-2024-04-08.pptx
EIS-Webinar-Prompt-Knowledge-Eng-2024-04-08.pptx
 
How to Troubleshoot Apps for the Modern Connected Worker
How to Troubleshoot Apps for the Modern Connected WorkerHow to Troubleshoot Apps for the Modern Connected Worker
How to Troubleshoot Apps for the Modern Connected Worker
 
Strategize a Smooth Tenant-to-tenant Migration and Copilot Takeoff
Strategize a Smooth Tenant-to-tenant Migration and Copilot TakeoffStrategize a Smooth Tenant-to-tenant Migration and Copilot Takeoff
Strategize a Smooth Tenant-to-tenant Migration and Copilot Takeoff
 
🐬 The future of MySQL is Postgres 🐘
🐬  The future of MySQL is Postgres   🐘🐬  The future of MySQL is Postgres   🐘
🐬 The future of MySQL is Postgres 🐘
 
Driving Behavioral Change for Information Management through Data-Driven Gree...
Driving Behavioral Change for Information Management through Data-Driven Gree...Driving Behavioral Change for Information Management through Data-Driven Gree...
Driving Behavioral Change for Information Management through Data-Driven Gree...
 
Tech Trends Report 2024 Future Today Institute.pdf
Tech Trends Report 2024 Future Today Institute.pdfTech Trends Report 2024 Future Today Institute.pdf
Tech Trends Report 2024 Future Today Institute.pdf
 
08448380779 Call Girls In Friends Colony Women Seeking Men
08448380779 Call Girls In Friends Colony Women Seeking Men08448380779 Call Girls In Friends Colony Women Seeking Men
08448380779 Call Girls In Friends Colony Women Seeking Men
 
From Event to Action: Accelerate Your Decision Making with Real-Time Automation
From Event to Action: Accelerate Your Decision Making with Real-Time AutomationFrom Event to Action: Accelerate Your Decision Making with Real-Time Automation
From Event to Action: Accelerate Your Decision Making with Real-Time Automation
 
Understanding Discord NSFW Servers A Guide for Responsible Users.pdf
Understanding Discord NSFW Servers A Guide for Responsible Users.pdfUnderstanding Discord NSFW Servers A Guide for Responsible Users.pdf
Understanding Discord NSFW Servers A Guide for Responsible Users.pdf
 
Bajaj Allianz Life Insurance Company - Insurer Innovation Award 2024
Bajaj Allianz Life Insurance Company - Insurer Innovation Award 2024Bajaj Allianz Life Insurance Company - Insurer Innovation Award 2024
Bajaj Allianz Life Insurance Company - Insurer Innovation Award 2024
 
Partners Life - Insurer Innovation Award 2024
Partners Life - Insurer Innovation Award 2024Partners Life - Insurer Innovation Award 2024
Partners Life - Insurer Innovation Award 2024
 
GenCyber Cyber Security Day Presentation
GenCyber Cyber Security Day PresentationGenCyber Cyber Security Day Presentation
GenCyber Cyber Security Day Presentation
 
ProductAnonymous-April2024-WinProductDiscovery-MelissaKlemke
ProductAnonymous-April2024-WinProductDiscovery-MelissaKlemkeProductAnonymous-April2024-WinProductDiscovery-MelissaKlemke
ProductAnonymous-April2024-WinProductDiscovery-MelissaKlemke
 

IT Project Portfolio Planning Using Excel

  • 1. IT Portfolio PlanningUsing Excel Jerry Bishop The Higher Ed CIO Creative Commons Attribution-NoDerivs 3.0 Unported License.
  • 2. introduction Foundations for the slides
  • 3. Purpose To provide a simple and transparent paper-based method for setting up an IT project portfolio using Excel.
  • 4. Why View this Presentation Without having prior experience this can seem impossible to know where to start. Before choosing a tool to do this, working out your method using Excel is a major benefit. It’s the only way to accurately commit to a body of work and know you can deliver on it. Tight FY12 budgets and increased demands require reasoned decisions on projects to do.
  • 5. Who Should Complete This CIO’s IT Governance Committee – Project Approvers Functional Executives – Project Sponsors Functional Managers – Project Requesters IT Managers – Project Managers Project Management Office – Role Project Managers
  • 6. What is a Portfolio Aggregates all demands expected of IT for review and approval decisions It’s like a “budget” for allocating staff to projects requiring IT resources A tool for building an “annual plan of work” It’s a workload management tool for seeing the total demand for IT resources
  • 7. resource capacity How to determine your capacity
  • 8. Guidelines for Capacity Determine the reasonable capacity a resource has to do project work Be conservative – avoid over committing IT Initially start with generic resources types Network Admin, Sys Admin, App Admin, DBA, App Analyst, Report Writer, Desktop Admin, Desktop Tech, Help Desk When comfortable move to named resources if it makes sense
  • 9. Portfolio Illustration The following illustration is taken from the actual initial FY11 portfolio for a college Reflects all initial requests for IT support and projects work for FY11 prior to approving or denying decisions were made Actual hours used here are from the 3-person Business Analyst group supporting the Banner ERP and related applications
  • 10. Determining Raw Capacity Note: 2012 is a leap year with 261 weekdays from July 1, 2011 to June 30, 2012
  • 11. Raw Capacity Thoughts Keep it simple Averages are better when first starting out If overtime is taken as paid time off then add an additional deduction as with comp time 1 hour overtime becomes 1.5 hours PTO Illustration reflects sick and personal time being treated like non-contract “vacation” Use historical averages if appropriate
  • 12. Determining Usable Capacity Note: Nobody is 100% productive with their day. There’s email, phone calls, meetings, breaks ,and birthday treats to hunt down. This approach avoids having to track this in any detail. Can be reconciled in time-tracking if used.
  • 13. Maximizing Usable Capacity Consider the value of in-service activities HR and IT Governance input on the priority Limit participation to job related activities Manage productivity up to 95% or better Train on time and task management Minimize general team meetings, manager one-on-ones, and committee assignments Don’t use default meeting lengths Instead of 60 minutes use 45 or 30 it adds up
  • 14. Creating the portfolio Loading the work load and resource demands
  • 15. Terminology Routine Maintenance: Daily production support obligations. Checking logs, monitoring systems, tape handling, storage management, job scheduling, user administration. Operational Support: This is Incident Management (break-fix) work and standard Service Requests not considered projects.
  • 16. Setting Up the Portfolio
  • 17. Project Estimating Avoid getting bogged down on the estimate Use SWAGs for initial estimates on all projects Take multiple passes through to refine Use ranges of hours 25, 50, 100, 150, 200, 500, 750, etc…. Estimating accuracy will improve Review estimates at project completion
  • 18. Cautions “Research” and “Investigation” Projects Include them in the Portfolio Big capacity drains, often slow burning of hours Evaluating new technologies and software Managing Contingency Hours Decrement the bank as it is used You can’t use it all at the end, its not like cash Revenue generating (billable) projects Consider special treatment if fully funded in FY12
  • 19. Organizing the Projects Separate projects by importance Most important come off the top Institutional Strategic Plan related projects first Required (mandatory this year) Projects next Required for regulatory compliance – financial aid Required to stay on supported versions – Oracle 11G Means they cannot be deferred without risks Discretionary is everything else in rank order Value-add, nice to do, and projects that might become Required by next fiscal year
  • 21. Balancing the Portfolio Part 1 Manage down Routine Maintenance Look for activities to automate and free capacity Use Demand Management to reduce Support Target Top 5 support issues Develop Problem Management process Enforce IT Governance process Stop informal requests and drive-bys Manage scope to <10% variance
  • 22. Balancing the Portfolio Part 2 Scrutinize ALL Required “Mandatory” Projects “Show Me” the requirement Challenge IT’s own Required Projects just as hard It’s discretionary if it van really wait IT Governance Focus on Priorities: The What, Not How Reduce Contingency Bank Percentage Challenge IT Managers to Free-Up Capacity Trim Scope and complexity of Projects Cancel projects instead of tapping contingency
  • 23. The completed portfolio Approving the Annual Plan of Work
  • 25. Download the Excel File Download the excel file from SlideShare.net at Project Portfolio Planning - The Workbook
  • 29. Supplemental Labor Thoughts Backfill labor for Operational work Often cheaper at $60 - $135 per hour More capacity for the same dollar Frees knowledgeable employees for projects Project Labor may be required More costly at $185 - $220 per hour Contract for fixed fee & guaranteed outcome Add contractor resource when it makes sense You have lots of work requiring vendor assistance
  • 30. Balancing the Portfolio NOTE: Supplemental labor can include limited term employees, temps, contractors, and vendor resources.
  • 31. Optional Staffing Strategy Staff IT department for normal workload Routine Maintenance Operational Support Use supplemental labor for ALL project work Requires sponsor to account for full cost & ROI when championing the business case Allows flexing up then down as project load surges Maintains minimal overhead run rates Simplifies producing savings and avoids layoffs Add incremental staff FTE as new systems are added
  • 32. Final Thoughts Portfolio planning takes some getting used to Leave contingency for unplanned projects They always come up Develop good IT Governance Committee Be transparent Publish your process and the Portfolio Train on project management
  • 33. Questions? Look for others in this series IT Governance Project Requests Jerry Bishop The Higher Ed CIO