1. PROPOSED NOISE MITIGATION PLAN
FORT LAUDERDALE – HOLLYWOOD INTERNATIONAL AIRPORT
RUNWAY 9R/27L EXPANSION PROJECT
Ocean Waterway Mobile Home Park Meeting
February 7, 2011, 5:00 p.m.
2. AGENDA
I. Welcome and Introductions
II. Noise Mitigation Plan Overview
Overview
Project Boundaries
Project Schedule
III. Overview of Acquisition Process
Voluntary Land Acquisition
Relocation Assistance
IV. Next Steps
V. Q
Questions and Comments
February 8, 2011
2
3. WHY DO WE NEED A PLAN?
The Federal Aviation Administration’s (FAA)
ROD for the Expansion of Runway 9R/27L
provides for noise mitigation for residential
properties located in delineated areas where
there is anticipated noise impacts from
operations on the expanded runway.
February 8, 2011
3
4. WHAT IS THE NOISE MITIGATION PLAN?
It is Broward County’s p
y plan for achieving land use
g
compatibility for areas located within the noise
impact areas identified in the FAA’s Record of
Decision (ROD) for the Expansion of Runway
9R/27L.
February 8, 2011
4
5. NOISE MITIGATION PLAN OVERVIEW
The FAA’s Record of Decision (ROD) for the
( )
Runway 9R/27L assessed future (2020) airport
noise impacts on surrounding communities
The
Th ROD identified several noise mitigation
id tifi d l i iti ti
measures, including voluntary acquisition of two
mobile homes parks (Ocean Waterway and
Marshalls Everglade)
Voluntary acquisition of Ocean Waterway may
occur if the land owner and cooperative are in
agreement
February 8, 2011
5
7. OCEAN WATERWAY MOBILE HOME PARK
Sound insulation of mobile home units is not feasible. Acquisition of Ocean Waterway MHP and
mobile home units with relocation of the residents is recommended. The County will request the
City of Dania Beach to rezone the land to a compatible use. Proceeds from the sale of the land will be
returned to the Noise Mitigation F d Th site i l
d h N i Mi i i Fund. The i is located primarily outside the 65 DNL and involves
d i il id h di l
complex components of ownership. There are 47 units located within the 65 DNL contour and 222
units located outside the 65 DNL contour. In accordance with County Commission policy to provide
neighborhood cohesion, it is recommended that an offer be made to purchase the mobile home park
land and all 269 units.
Program Eligibility Est. Cost1 Implementation Schedule Recommendation
Begin End
Voluntary Acquisition of Ocean
y q Mobile Home Park Land and
Waterway Mobile Home Park 269 Mobile Home Units and
$51 M 2011 Undetermined2 Recommended
and Mobile Home Units and Relocation of Residents
Relocation of Residents
Estimated Cost: $51 million1 – no change
Schedule: Implementation begins 2011;
End date determined by market conditions 2
February 8, 2011
Area 2
1 Source: FAA FEIS
2 Upon Board approval of the Final Noise Mitigation Plan, BCAD will contact the MHP owner to
7
determine their level of interest in participation. The program’s end date will be dependent on
negotiations with mobile home park cooperative.
8. PROPOSED NOISE MITIGATION PLAN:
VOLUNTARY ACQUISITION OF MOBILE
HOME PARK AND MOBILE HOME UNITS
Conduct a voluntary acquisition of Ocean Waterway
Mobile Home Park and mobile home units
Provide a relocation program for persons residing in
acquired mobile home units
Funded by Federal Aviation Administration and
BCAD
Program will be administered under:
Uniform Relocation Assistance and Real Property
Acquisition Policies Act of 1970 (Uniform Act) (Public Law
FAA Order 5100.37B Land Acquisition and Relocation
Assistance for Airport Development Projects
Florida Statues, Chapter 723, Mobile Home Park Lot
Tenancies
February 8, 2011
Recommend rezone l d t a compatible l d use and
R d land to tibl land d
resell
8
9. VOLUNTARY ACQUISITION PROGRAM SCHEDULE
Acquisition
q Relocation
Notice of Determine
Park Closing Relocation
Pursuant to Benefits
F.S. 723
Assist Residents
Needs Obtaining
Assessment Replacement
Housing
Attend
Program
Briefing Relocate
Mobile Home
Unit (if needed)
Appraise
Mobile
M bil
Park
Home Unit
Management
Offer to
Purchase Demolition of
Unit Park Structures
Park Structures
Execute
Purchase Zoning Change
February 8, 2011
Agreement and Sale of
Land
L d
Conduct
Closing
9
10. ACQUISITION PROCESS
Community meeting with owners/tenants
y g
Meeting with individual owners/tenants
Distribute Relocation Benefits brochure
Obtain property appraisals
Obtain Phase 1 environmental study
Deliver offer of voluntary purchase
Develop relocation package (owner/occupants)
Schedule l i g
S h d l closings: mobile home park land and units-
bil h k l d d it
Provide relocation assistance to mobile home
tenants and owners
February 8, 2011
10
11. RELOCATION ASSISTANCE –
QUALIFICATION REQUIREMENTS
Relocation Assistance is divided in to two primary categories:
p y g
Owner occupants – residents who own and live in the
mobile home
Tenant occupants – residents who rent the mobile
home that they occupy
To ensure benefits:
DO NOT MOVE
O O OV
Continue to pay Mortgage or Rent
February 8, 2011
11
12. RELOCATION ASSISTANCE –
OWNER OCCUPANT BENEFITS
Owner Occupants – (owned for at least 180 days)
p ( y )
Four primary benefits exist for each owner
occupant:
Replacement Housing Payments
Moving Cost Payments
Incidental Expenses to the Relocation
c e a pe ses o e e oca o
Increased Interest Expenses
February 8, 2011
12
13. RELOCATION ASSISTANCE –
TENANT BENEFITS
Tenant Occupants
p
Two primary benefits exist for each tenant
occupant:
Rent Subsidy Payments
Moving Cost Payments
Note: Tenants may also elect to purchase a new home and
the Rent Supplement Payment can be utilized as Down
Payment Assistance
February 8, 2011
13
14. RELOCATION ASSISTANCE –
TENANT BENEFITS
Rental Subsidy:y
Tenants will receive a payment to compensate
them for increased rent at comparable
replacement residence not t exceed $5 250
l t id t to d $5,250.
The amount is calculated by computing the
difference between the existing rent and the
future rent which is multiplied by 42
Down Payment Assistance:
Tenant may be eligible for a maximum of $5,250
February 8, 2011
to use towards the down payment in purchasing
a home
14
15. NEXT STEPS…
The Aviation Department’s Proposed Noise
p p
Mitigation Plan to be presented to Board of
County Commissioners
The A
Th Approved Plan is submitted to th F d
d Pl i b itt d t the Federal l
Aviation Administration
Broward County selects a consultant team to
manage the project
Broward County applies for FAA funding
Proceed with acquiring Ocean Waterway Mobile
on a voluntary basis by first making an offer to
purchase to the mobile home park land owner
February 8, 2011
15