SlideShare une entreprise Scribd logo
1  sur  25
CEDAR RAPIDS COMMUNITY SCHOOL DISTRICT SERVICES CAMPUS
Site Design & Construction Buildings Design & Construction CRCSD FLOOD RECOVERY TIMELINE CRCSD, State, FEMA Design Reviews and Approvals – Target Dates Decommissioning ESC @ Kingston May 27, 2012 Nov 9, 2009 2010 2011 2012 JAN MAR NOV DEC FEB APR MAY JUN JUL AUG SEP OCT NOV DEC JAN MAR FEB APR MAY JUN JUL AUG SEP OCT NOV DEC JAN MAR FEB APR MAY DESIGN BID CONSTRUCTION DESIGN BID CONSTRUCTION DESIGN BID CONSTR End of Design Development – April 2010 Schedule is contingent on timely governing authority approvals and weather Completion of Construction Documents – August 2010 Completion of Construction – March 2012 Completion of Project – May 2012 TODAY Substantial Completion of Construction – January 2012
CRCSD CORE TEAM MEMBERS CRCSD Dr. Dave Benson Dr. Gary O’Malley Laurel Day Steve Graham Marcia Hughes Dave Dvorak Tom Day Jeff Rowray Ruth Callahan Lori Bruzek Denny Schreckengast Matt Dunbar Jenna Gardner SHIVE-HATTERY George Kanz Michael Gumm Jim Wignall Mike Hessman Jake Hinkle Jon Fitch Tom Bosch FEMA Jim Waller AI Marty Calabro Robert Wright IHS Emilie Shipley CITIZENS Mike Dawson Lindsay Schumacher
PROJECT STATUS DESIGN IS ON COURSE TO MEET ESTABLISHED TIMELINE BID PACKAGES DEMOLITION & ROUGH GRADING F&F, STEEL AND CONCRETE BUILDING, SITE IMPROVEMENTS, LANDSCAPING B.O.E. APPROVAL – MAY 2010 BIDDING – JUNE 2010 CONSTRUCTION – AUGUST 2010 B.O.E. APPROVAL – JUNE 2010 BIDDING – AUGUST 2010 CONSTRUCTION – SEPTEMBER 2010 B.O.E. APPROVAL – AUGUST 2010 BIDDING – SEPTEMBER 2010 CONSTRUCTION – OCTOBER 2010
SUSTAINABILITY ENERGY MODELING – WHOLE BUILDING CONCEPT The Weidt Group DESIGN STRATEGIES GEOTHERMAL HEATING & COOLING OCCUPANCY SENSORS HIGH PERFORMANCE CURTAINWALL AND WINDOWS R-20 WALL INSULATION R-30 ROOF INSULATION WATER USE REDUCTION DAYLIGHTING STORMWATER QUALITY CONTROL LIGHT POLLUTION REDUCTION ENERGY OPTIMIZATION ENHANCED REFRIGERATION MANAGEMENT RECYCLING CONSTRUCTION WASTE MANAGEMENT MATERIAL REUSE RECYCLED CONTENT IN NEW MATERIALS RAPIDLY RENEWABLE MATERIALS INDOOR AIR QUALITY LOW-EMITTING MATERIALS RAPIDLY RENEWABLE MATERIALS INDOOR POLLUTANT CONTROL LIGHTING CONTROLS THERMAL COMFORT CONTROLS TOTAL HEAT RECOVERY SYSTEMS CO 2  SENSORS VARIABLE FREQUENCY DRIVE PUMPS HEATING & COOLING ZONES HVAC COMMISSIONING ENVELOPE COMMISSIONING GOAL – 50% ENERGY SAVINGS
SUSTAINABILITY COMPARISON TO LEED CHECKLIST 49 POINTS TARGETED ACHIEVE GOLD RATING
SITE PLAN EDGEWOOD RD ELLIS RD VISITOR PARKING EMPLOYEE PARKING PARKING PARKING DISTRICT  VAN DOCK PARKING BUS BUS DRIVER
EXTERIOR WAYFINDING
EXTERIOR WAYFINDING
EXTERIOR WAYFINDING
EXTERIOR WAYFINDING
PROJECT PLANS LOWER LEVEL FLOOR PLAN
PROJECT PLANS FIRST LEVEL FLOOR PLAN
PROJECT PLANS SECOND LEVEL FLOOR PLAN
INTERIOR WAYFINDING LOWER LEVEL MAIN LEVEL SECOND LEVEL
EXTERIOR ELEVATIONS
EXTERIOR ELEVATIONS
ENTRANCE RENDERING
BUDGET 810,353 TRANSPORTATION RELOCATION CURRENT BUDGET $915,647 $5,233,818 $29,142,293 $35,897,252 4,957,361 2,440,528 $44,500,000 PREVIOUS BUDGET $915,647 BID PACKAGE I BID PACKAGE 2 $5,233,818 BID PACKAGE 3 $28,579,985 FOOTINGS, FOUNDATIONS & STEEL BUILDING, FF&E SITE LANDSCAPING AND FINISH GRADING $35,729,450 CONSTRUCTION TOTAL A/E FEES 4,957,361 CONTINGENCY 3,002,836 $44,500,000 PROJECT TOTAL 810,353 PROJECT SF TOTAL 169,419 COST SF (BUILDING) $202.90 COST SF (TOTAL PROJECT) $262.66 $1,000,000 OFF-SITE IMPROVEMENTS $1,000,000
TRANSPORTATION RELOCATION CONSTRUCTION BUS PARKING AT WESTDALE MALL
TRANSPORTATION RELOCATION CONSTRUCTION TRANSPORTATION OFFICES AT WESTDALE MALL
TRANSPORTATION RELOCATION CONSTRUCTION BUS REPAIR SHOP AT 27 TH  AVE SW
ARCHAEOLOGICAL SURVEYS SURVEY COSTS PHASE I $21,254 PHASE II $49,774 MAY 24  JUNE 3 JUNE 7 JUNE 18 JUNE 25 JUNE 29 JULY 6 JULY 16 JULY 22 JULY 28 ALL COSTS ARE REIMBURSED BY FEMA FEMA NOTIFICATION OF PHASE I CONTRACT OSA OSA BEGINS PHASE I FIELD WORK COMPLETED FINDINGS BY OSA & SHPO OSA CONTRACT AMENDMENT  OSA BEGINS PHASE II OSA COMPLETES FIELDWORK OSA & SHPO FINDINGS NO SIGNIFICANT IMPACT FEMA LETTER TO PROCEED SCHEDULE IMPACT – CONSTRUCTION DELAY OF 2 WEEKS SHIVE-HATTERY $12,000
CONSTRUCTION - SUSTAINABILITY SALVAGED BENCHES BUS WASH SYSTEM O.H. DOORS RECYCLED TREES & STUMPS FUEL TANKS USED OIL TANK BATTERIES USED OIL FILTERS CHAIN LINK FENCING OH ELECTRICAL WIRE HYDRAULIC SYSTEM WIRING COPPER CONDUIT STEEL ALUMINUM DUCTILE IRON PRECAST WALL PANELS ASPHALT CONCRETE BLOCK WALLS SIGNS HAND RAILS LIGHT FIXTURES SAND
QUESTIONS AND COMMENTS NEXT REVIEW

Contenu connexe

En vedette

Respiration (includingFermentation)
Respiration (includingFermentation)Respiration (includingFermentation)
Respiration (includingFermentation)LM9
 
Les Meilleures Campagnes Digitales de 2013
Les Meilleures Campagnes Digitales de 2013Les Meilleures Campagnes Digitales de 2013
Les Meilleures Campagnes Digitales de 2013Sabrina Xenofontos
 
Colombia exklusi va trabajo martes 17 agosto harol mera
Colombia exklusi va trabajo martes 17 agosto harol meraColombia exklusi va trabajo martes 17 agosto harol mera
Colombia exklusi va trabajo martes 17 agosto harol meracolombiaexclusiva
 
Music : your social media optimisation
Music : your social media optimisationMusic : your social media optimisation
Music : your social media optimisationaf83media
 
An Introduction To Blueberry Marketing Solutions
An Introduction To Blueberry Marketing SolutionsAn Introduction To Blueberry Marketing Solutions
An Introduction To Blueberry Marketing Solutionslaurahornsey
 
English iii rico the dog
English iii rico the dogEnglish iii rico the dog
English iii rico the dogMeibel Chaves
 
CETS 2010, Joe Gorup, ADA and Section 508: Making eLearning Accessible and Us...
CETS 2010, Joe Gorup, ADA and Section 508: Making eLearning Accessible and Us...CETS 2010, Joe Gorup, ADA and Section 508: Making eLearning Accessible and Us...
CETS 2010, Joe Gorup, ADA and Section 508: Making eLearning Accessible and Us...Chicago eLearning & Technology Showcase
 
Perl web programming
Perl web programmingPerl web programming
Perl web programmingJohnny Pork
 
Экипаж королей
Экипаж королейЭкипаж королей
Экипаж королейPeugeotUA
 

En vedette (16)

Dr. s.n.-khan (1)
Dr. s.n.-khan (1)Dr. s.n.-khan (1)
Dr. s.n.-khan (1)
 
Bgt4
Bgt4Bgt4
Bgt4
 
Respiration (includingFermentation)
Respiration (includingFermentation)Respiration (includingFermentation)
Respiration (includingFermentation)
 
Les Meilleures Campagnes Digitales de 2013
Les Meilleures Campagnes Digitales de 2013Les Meilleures Campagnes Digitales de 2013
Les Meilleures Campagnes Digitales de 2013
 
Colombia exklusi va trabajo martes 17 agosto harol mera
Colombia exklusi va trabajo martes 17 agosto harol meraColombia exklusi va trabajo martes 17 agosto harol mera
Colombia exklusi va trabajo martes 17 agosto harol mera
 
Safety Management Systems in Business & Corporate Aviation
Safety Management Systems in Business & Corporate AviationSafety Management Systems in Business & Corporate Aviation
Safety Management Systems in Business & Corporate Aviation
 
Music : your social media optimisation
Music : your social media optimisationMusic : your social media optimisation
Music : your social media optimisation
 
An Introduction To Blueberry Marketing Solutions
An Introduction To Blueberry Marketing SolutionsAn Introduction To Blueberry Marketing Solutions
An Introduction To Blueberry Marketing Solutions
 
Rudens
RudensRudens
Rudens
 
English iii rico the dog
English iii rico the dogEnglish iii rico the dog
English iii rico the dog
 
Fazd Bovine Babesia Paper
Fazd Bovine Babesia PaperFazd Bovine Babesia Paper
Fazd Bovine Babesia Paper
 
CETS 2010, Joe Gorup, ADA and Section 508: Making eLearning Accessible and Us...
CETS 2010, Joe Gorup, ADA and Section 508: Making eLearning Accessible and Us...CETS 2010, Joe Gorup, ADA and Section 508: Making eLearning Accessible and Us...
CETS 2010, Joe Gorup, ADA and Section 508: Making eLearning Accessible and Us...
 
Perl web programming
Perl web programmingPerl web programming
Perl web programming
 
Экипаж королей
Экипаж королейЭкипаж королей
Экипаж королей
 
Cets 2015 ls marshall were the servants
Cets 2015 ls marshall were the servantsCets 2015 ls marshall were the servants
Cets 2015 ls marshall were the servants
 
Cets 2015 buteyn animation in e learning
Cets 2015 buteyn animation in e learningCets 2015 buteyn animation in e learning
Cets 2015 buteyn animation in e learning
 

Similaire à Crcsd boe presentation 080910

CVE 471 PROJECT (2).pptx department of civil engineering
CVE 471 PROJECT (2).pptx department of civil engineeringCVE 471 PROJECT (2).pptx department of civil engineering
CVE 471 PROJECT (2).pptx department of civil engineeringmuoghogboritse
 
Final Project Presentation
Final Project PresentationFinal Project Presentation
Final Project PresentationAakash Shah
 
Architectural Portfolio - Madarati
Architectural Portfolio - MadaratiArchitectural Portfolio - Madarati
Architectural Portfolio - MadaratiAbdulhamid Madarati
 
2009 Community Development Goals & Acomplishments
2009 Community Development Goals & Acomplishments2009 Community Development Goals & Acomplishments
2009 Community Development Goals & Acomplishmentsmckay
 
City Projects - Concepts, Costing & Construction
City Projects - Concepts, Costing & ConstructionCity Projects - Concepts, Costing & Construction
City Projects - Concepts, Costing & ConstructionUGPTI
 
Clean Air force Board meeting Slides Nov 9 2022.pptx
Clean Air force Board meeting Slides Nov 9 2022.pptxClean Air force Board meeting Slides Nov 9 2022.pptx
Clean Air force Board meeting Slides Nov 9 2022.pptxCapitolTechU
 
G13 - Project Management.pptx
G13 - Project Management.pptxG13 - Project Management.pptx
G13 - Project Management.pptxVatsalPancholi6
 
CICC Accounting by Cebu Gov. Gwen Garcia on Feb. 26, 2009
CICC Accounting by Cebu Gov. Gwen Garcia on Feb. 26, 2009CICC Accounting by Cebu Gov. Gwen Garcia on Feb. 26, 2009
CICC Accounting by Cebu Gov. Gwen Garcia on Feb. 26, 2009Leo Lastimosa
 
St. Cloud, MN: The Path to Energy Neutral
St. Cloud, MN: The Path to Energy NeutralSt. Cloud, MN: The Path to Energy Neutral
St. Cloud, MN: The Path to Energy NeutralUniversity of Minnesota
 
2010 uci douglas hospital team platinum award by bdc
2010 uci douglas hospital team platinum award by bdc2010 uci douglas hospital team platinum award by bdc
2010 uci douglas hospital team platinum award by bdcAvi Grigorescu
 
SITEWORKS & SETTING OUT
SITEWORKS & SETTING OUT SITEWORKS & SETTING OUT
SITEWORKS & SETTING OUT Saurav Shrestha
 
Construction Documents Fall 2014
Construction Documents Fall 2014Construction Documents Fall 2014
Construction Documents Fall 2014Martin Pauly
 

Similaire à Crcsd boe presentation 080910 (20)

CVE 471 PROJECT (2).pptx department of civil engineering
CVE 471 PROJECT (2).pptx department of civil engineeringCVE 471 PROJECT (2).pptx department of civil engineering
CVE 471 PROJECT (2).pptx department of civil engineering
 
Final Project Presentation
Final Project PresentationFinal Project Presentation
Final Project Presentation
 
RESUME JULY 2016
RESUME JULY 2016RESUME JULY 2016
RESUME JULY 2016
 
Architectural Portfolio - Madarati
Architectural Portfolio - MadaratiArchitectural Portfolio - Madarati
Architectural Portfolio - Madarati
 
2009 Community Development Goals & Acomplishments
2009 Community Development Goals & Acomplishments2009 Community Development Goals & Acomplishments
2009 Community Development Goals & Acomplishments
 
City Projects - Concepts, Costing & Construction
City Projects - Concepts, Costing & ConstructionCity Projects - Concepts, Costing & Construction
City Projects - Concepts, Costing & Construction
 
Clean Air force Board meeting Slides Nov 9 2022.pptx
Clean Air force Board meeting Slides Nov 9 2022.pptxClean Air force Board meeting Slides Nov 9 2022.pptx
Clean Air force Board meeting Slides Nov 9 2022.pptx
 
Cbri ib
Cbri ibCbri ib
Cbri ib
 
G13 - Project Management.pptx
G13 - Project Management.pptxG13 - Project Management.pptx
G13 - Project Management.pptx
 
CICC Accounting by Cebu Gov. Gwen Garcia on Feb. 26, 2009
CICC Accounting by Cebu Gov. Gwen Garcia on Feb. 26, 2009CICC Accounting by Cebu Gov. Gwen Garcia on Feb. 26, 2009
CICC Accounting by Cebu Gov. Gwen Garcia on Feb. 26, 2009
 
Olympic Village Project FINAL
Olympic Village Project  FINALOlympic Village Project  FINAL
Olympic Village Project FINAL
 
St. Cloud, MN: The Path to Energy Neutral
St. Cloud, MN: The Path to Energy NeutralSt. Cloud, MN: The Path to Energy Neutral
St. Cloud, MN: The Path to Energy Neutral
 
Police Station Design Concepts
Police Station Design ConceptsPolice Station Design Concepts
Police Station Design Concepts
 
Rick Pacheco
Rick PachecoRick Pacheco
Rick Pacheco
 
Cv Presentation
Cv PresentationCv Presentation
Cv Presentation
 
Un Tearthday
Un TearthdayUn Tearthday
Un Tearthday
 
2010 uci douglas hospital team platinum award by bdc
2010 uci douglas hospital team platinum award by bdc2010 uci douglas hospital team platinum award by bdc
2010 uci douglas hospital team platinum award by bdc
 
SELENDRA CONDOMINIUM CONSTRUCTION ORIENTATION
SELENDRA CONDOMINIUM CONSTRUCTION ORIENTATIONSELENDRA CONDOMINIUM CONSTRUCTION ORIENTATION
SELENDRA CONDOMINIUM CONSTRUCTION ORIENTATION
 
SITEWORKS & SETTING OUT
SITEWORKS & SETTING OUT SITEWORKS & SETTING OUT
SITEWORKS & SETTING OUT
 
Construction Documents Fall 2014
Construction Documents Fall 2014Construction Documents Fall 2014
Construction Documents Fall 2014
 

Crcsd boe presentation 080910

  • 1. CEDAR RAPIDS COMMUNITY SCHOOL DISTRICT SERVICES CAMPUS
  • 2. Site Design & Construction Buildings Design & Construction CRCSD FLOOD RECOVERY TIMELINE CRCSD, State, FEMA Design Reviews and Approvals – Target Dates Decommissioning ESC @ Kingston May 27, 2012 Nov 9, 2009 2010 2011 2012 JAN MAR NOV DEC FEB APR MAY JUN JUL AUG SEP OCT NOV DEC JAN MAR FEB APR MAY JUN JUL AUG SEP OCT NOV DEC JAN MAR FEB APR MAY DESIGN BID CONSTRUCTION DESIGN BID CONSTRUCTION DESIGN BID CONSTR End of Design Development – April 2010 Schedule is contingent on timely governing authority approvals and weather Completion of Construction Documents – August 2010 Completion of Construction – March 2012 Completion of Project – May 2012 TODAY Substantial Completion of Construction – January 2012
  • 3. CRCSD CORE TEAM MEMBERS CRCSD Dr. Dave Benson Dr. Gary O’Malley Laurel Day Steve Graham Marcia Hughes Dave Dvorak Tom Day Jeff Rowray Ruth Callahan Lori Bruzek Denny Schreckengast Matt Dunbar Jenna Gardner SHIVE-HATTERY George Kanz Michael Gumm Jim Wignall Mike Hessman Jake Hinkle Jon Fitch Tom Bosch FEMA Jim Waller AI Marty Calabro Robert Wright IHS Emilie Shipley CITIZENS Mike Dawson Lindsay Schumacher
  • 4. PROJECT STATUS DESIGN IS ON COURSE TO MEET ESTABLISHED TIMELINE BID PACKAGES DEMOLITION & ROUGH GRADING F&F, STEEL AND CONCRETE BUILDING, SITE IMPROVEMENTS, LANDSCAPING B.O.E. APPROVAL – MAY 2010 BIDDING – JUNE 2010 CONSTRUCTION – AUGUST 2010 B.O.E. APPROVAL – JUNE 2010 BIDDING – AUGUST 2010 CONSTRUCTION – SEPTEMBER 2010 B.O.E. APPROVAL – AUGUST 2010 BIDDING – SEPTEMBER 2010 CONSTRUCTION – OCTOBER 2010
  • 5. SUSTAINABILITY ENERGY MODELING – WHOLE BUILDING CONCEPT The Weidt Group DESIGN STRATEGIES GEOTHERMAL HEATING & COOLING OCCUPANCY SENSORS HIGH PERFORMANCE CURTAINWALL AND WINDOWS R-20 WALL INSULATION R-30 ROOF INSULATION WATER USE REDUCTION DAYLIGHTING STORMWATER QUALITY CONTROL LIGHT POLLUTION REDUCTION ENERGY OPTIMIZATION ENHANCED REFRIGERATION MANAGEMENT RECYCLING CONSTRUCTION WASTE MANAGEMENT MATERIAL REUSE RECYCLED CONTENT IN NEW MATERIALS RAPIDLY RENEWABLE MATERIALS INDOOR AIR QUALITY LOW-EMITTING MATERIALS RAPIDLY RENEWABLE MATERIALS INDOOR POLLUTANT CONTROL LIGHTING CONTROLS THERMAL COMFORT CONTROLS TOTAL HEAT RECOVERY SYSTEMS CO 2 SENSORS VARIABLE FREQUENCY DRIVE PUMPS HEATING & COOLING ZONES HVAC COMMISSIONING ENVELOPE COMMISSIONING GOAL – 50% ENERGY SAVINGS
  • 6. SUSTAINABILITY COMPARISON TO LEED CHECKLIST 49 POINTS TARGETED ACHIEVE GOLD RATING
  • 7. SITE PLAN EDGEWOOD RD ELLIS RD VISITOR PARKING EMPLOYEE PARKING PARKING PARKING DISTRICT VAN DOCK PARKING BUS BUS DRIVER
  • 12. PROJECT PLANS LOWER LEVEL FLOOR PLAN
  • 13. PROJECT PLANS FIRST LEVEL FLOOR PLAN
  • 14. PROJECT PLANS SECOND LEVEL FLOOR PLAN
  • 15. INTERIOR WAYFINDING LOWER LEVEL MAIN LEVEL SECOND LEVEL
  • 19. BUDGET 810,353 TRANSPORTATION RELOCATION CURRENT BUDGET $915,647 $5,233,818 $29,142,293 $35,897,252 4,957,361 2,440,528 $44,500,000 PREVIOUS BUDGET $915,647 BID PACKAGE I BID PACKAGE 2 $5,233,818 BID PACKAGE 3 $28,579,985 FOOTINGS, FOUNDATIONS & STEEL BUILDING, FF&E SITE LANDSCAPING AND FINISH GRADING $35,729,450 CONSTRUCTION TOTAL A/E FEES 4,957,361 CONTINGENCY 3,002,836 $44,500,000 PROJECT TOTAL 810,353 PROJECT SF TOTAL 169,419 COST SF (BUILDING) $202.90 COST SF (TOTAL PROJECT) $262.66 $1,000,000 OFF-SITE IMPROVEMENTS $1,000,000
  • 20. TRANSPORTATION RELOCATION CONSTRUCTION BUS PARKING AT WESTDALE MALL
  • 21. TRANSPORTATION RELOCATION CONSTRUCTION TRANSPORTATION OFFICES AT WESTDALE MALL
  • 22. TRANSPORTATION RELOCATION CONSTRUCTION BUS REPAIR SHOP AT 27 TH AVE SW
  • 23. ARCHAEOLOGICAL SURVEYS SURVEY COSTS PHASE I $21,254 PHASE II $49,774 MAY 24 JUNE 3 JUNE 7 JUNE 18 JUNE 25 JUNE 29 JULY 6 JULY 16 JULY 22 JULY 28 ALL COSTS ARE REIMBURSED BY FEMA FEMA NOTIFICATION OF PHASE I CONTRACT OSA OSA BEGINS PHASE I FIELD WORK COMPLETED FINDINGS BY OSA & SHPO OSA CONTRACT AMENDMENT OSA BEGINS PHASE II OSA COMPLETES FIELDWORK OSA & SHPO FINDINGS NO SIGNIFICANT IMPACT FEMA LETTER TO PROCEED SCHEDULE IMPACT – CONSTRUCTION DELAY OF 2 WEEKS SHIVE-HATTERY $12,000
  • 24. CONSTRUCTION - SUSTAINABILITY SALVAGED BENCHES BUS WASH SYSTEM O.H. DOORS RECYCLED TREES & STUMPS FUEL TANKS USED OIL TANK BATTERIES USED OIL FILTERS CHAIN LINK FENCING OH ELECTRICAL WIRE HYDRAULIC SYSTEM WIRING COPPER CONDUIT STEEL ALUMINUM DUCTILE IRON PRECAST WALL PANELS ASPHALT CONCRETE BLOCK WALLS SIGNS HAND RAILS LIGHT FIXTURES SAND
  • 25. QUESTIONS AND COMMENTS NEXT REVIEW

Notes de l'éditeur

  1. 75-100 YEAR BUILDING PROJECT BASIS OF DESIGN – LOOKING FORWARD
  2. AGGRESSIVE SCHEDULE TIMELINE SEEN BEFORE STILL IN DESIGN DEVELOPMENT PLANS WILL CONTINUE TO DEVELOP ADDING DETAIL ON A DAILY BASIS
  3. PROJECT IS ON TRACK TO MEET THE ESTABLISHED SCHEDULE FROM THIS POINT FORWARD PARTS OF THE PROJECT WILL MOVE AHEAD OF THE BUILDING DESIGN STRUCTURAL STEEL HAS APPROXIMATELY A 16 WEEK LEAD TIME FROM THE DATE OF ORDER F&F NEEDS TO BE IN THE GROUND BEFORE FREEZE FF&E WILL BE ANOTHER BID PACKAGE, EITHER WITH THE BUILDING OR AFTER
  4. HVAC COMPARISON COMPLETE MOVING TO WHOLE BUILDING ANALYSIS, ENERGY EFFICIENCY
  5. HVAC COMPARISON COMPLETE MOVING TO WHOLE BUILDING ANALYSIS, ENERGY EFFICIENCY
  6. JANUARY 25 –DIRECTION TO PROCEED WITH MASTER PLAN AS PRESENTED REMOVE AND BUILD NEW: TRANSPORTATION CENTER BUS PARKING BUS DRIVER PARKING BUDGET INCLUDES CONTINGENCY CONSERVATIVE NUMBER
  7. FLOOR AREA RATIO TRANSPORTATION = 87% WAREHOUSE = 87% STORAGE AREA = 99%
  8. FLOOR AREA RATIO ADMINISTRATION = 73% G&G, C&G = 95% SHARED SERVICES WITH OTHER DEPARTMENTS STAIRS FREIGHT ELEVATOR CORRIDORS - CONNECTION PASSENGER ELEVATOR MECHANICAL EQUIPMENT – OUTSIDE AIR EQUIP MAIN CAFETERIA/BREAK ROOM RESTROOMS – PDC, B&G
  9. FLOOR AREA RATIO ADMINISTRATION = 77% SHARED SERVICES WITH OTHER DEPARTMENTS STAIRS FREIGHT ELEVATOR CORRIDORS - CONNECTION PASSENGER ELEVATOR MECHANICAL EQUIPMENT – OUTSIDE AIR EQUIP
  10. SIMPLE STRUCTURE – STRAIGHT FORWARD SINGLE ROOF SHELTERS ALL ELEMENTS, DEPARTMENTS SMALLER PERCEIVED OVERALL SCALE BRICK PLANER ELEMENTS BREAK-UP FAÇADE SIGNIFY OUTREACH – INVITING VISUAL LANGUAGE – FRONT DOOR TRANSPARENT FAÇADE – OPENESS SIMPLE PALATE – COMMON MATERIALS RESPONSIBILITY TO CONTROL SOLAR GAIN ENERGY EFFICIENCY