2. Site Design & Construction Buildings Design & Construction CRCSD FLOOD RECOVERY TIMELINE CRCSD, State, FEMA Design Reviews and Approvals – Target Dates Decommissioning ESC @ Kingston May 27, 2012 Nov 9, 2009 2010 2011 2012 JAN MAR NOV DEC FEB APR MAY JUN JUL AUG SEP OCT NOV DEC JAN MAR FEB APR MAY JUN JUL AUG SEP OCT NOV DEC JAN MAR FEB APR MAY DESIGN BID CONSTRUCTION DESIGN BID CONSTRUCTION DESIGN BID CONSTR End of Design Development – April 2010 Schedule is contingent on timely governing authority approvals and weather Completion of Construction Documents – August 2010 Completion of Construction – March 2012 Completion of Project – May 2012 TODAY Substantial Completion of Construction – January 2012
3. CRCSD CORE TEAM MEMBERS CRCSD Dr. Dave Benson Dr. Gary O’Malley Laurel Day Steve Graham Marcia Hughes Dave Dvorak Tom Day Jeff Rowray Ruth Callahan Lori Bruzek Denny Schreckengast Matt Dunbar Jenna Gardner SHIVE-HATTERY George Kanz Michael Gumm Jim Wignall Mike Hessman Jake Hinkle Jon Fitch Tom Bosch FEMA Jim Waller AI Marty Calabro Robert Wright IHS Emilie Shipley CITIZENS Mike Dawson Lindsay Schumacher
4. PROJECT STATUS DESIGN IS ON COURSE TO MEET ESTABLISHED TIMELINE BID PACKAGES DEMOLITION & ROUGH GRADING F&F, STEEL AND CONCRETE BUILDING, SITE IMPROVEMENTS, LANDSCAPING B.O.E. APPROVAL – MAY 2010 BIDDING – JUNE 2010 CONSTRUCTION – AUGUST 2010 B.O.E. APPROVAL – JUNE 2010 BIDDING – AUGUST 2010 CONSTRUCTION – SEPTEMBER 2010 B.O.E. APPROVAL – AUGUST 2010 BIDDING – SEPTEMBER 2010 CONSTRUCTION – OCTOBER 2010
5. SUSTAINABILITY ENERGY MODELING – WHOLE BUILDING CONCEPT The Weidt Group DESIGN STRATEGIES GEOTHERMAL HEATING & COOLING OCCUPANCY SENSORS HIGH PERFORMANCE CURTAINWALL AND WINDOWS R-20 WALL INSULATION R-30 ROOF INSULATION WATER USE REDUCTION DAYLIGHTING STORMWATER QUALITY CONTROL LIGHT POLLUTION REDUCTION ENERGY OPTIMIZATION ENHANCED REFRIGERATION MANAGEMENT RECYCLING CONSTRUCTION WASTE MANAGEMENT MATERIAL REUSE RECYCLED CONTENT IN NEW MATERIALS RAPIDLY RENEWABLE MATERIALS INDOOR AIR QUALITY LOW-EMITTING MATERIALS RAPIDLY RENEWABLE MATERIALS INDOOR POLLUTANT CONTROL LIGHTING CONTROLS THERMAL COMFORT CONTROLS TOTAL HEAT RECOVERY SYSTEMS CO 2 SENSORS VARIABLE FREQUENCY DRIVE PUMPS HEATING & COOLING ZONES HVAC COMMISSIONING ENVELOPE COMMISSIONING GOAL – 50% ENERGY SAVINGS
23. ARCHAEOLOGICAL SURVEYS SURVEY COSTS PHASE I $21,254 PHASE II $49,774 MAY 24 JUNE 3 JUNE 7 JUNE 18 JUNE 25 JUNE 29 JULY 6 JULY 16 JULY 22 JULY 28 ALL COSTS ARE REIMBURSED BY FEMA FEMA NOTIFICATION OF PHASE I CONTRACT OSA OSA BEGINS PHASE I FIELD WORK COMPLETED FINDINGS BY OSA & SHPO OSA CONTRACT AMENDMENT OSA BEGINS PHASE II OSA COMPLETES FIELDWORK OSA & SHPO FINDINGS NO SIGNIFICANT IMPACT FEMA LETTER TO PROCEED SCHEDULE IMPACT – CONSTRUCTION DELAY OF 2 WEEKS SHIVE-HATTERY $12,000
24. CONSTRUCTION - SUSTAINABILITY SALVAGED BENCHES BUS WASH SYSTEM O.H. DOORS RECYCLED TREES & STUMPS FUEL TANKS USED OIL TANK BATTERIES USED OIL FILTERS CHAIN LINK FENCING OH ELECTRICAL WIRE HYDRAULIC SYSTEM WIRING COPPER CONDUIT STEEL ALUMINUM DUCTILE IRON PRECAST WALL PANELS ASPHALT CONCRETE BLOCK WALLS SIGNS HAND RAILS LIGHT FIXTURES SAND
75-100 YEAR BUILDING PROJECT BASIS OF DESIGN – LOOKING FORWARD
AGGRESSIVE SCHEDULE TIMELINE SEEN BEFORE STILL IN DESIGN DEVELOPMENT PLANS WILL CONTINUE TO DEVELOP ADDING DETAIL ON A DAILY BASIS
PROJECT IS ON TRACK TO MEET THE ESTABLISHED SCHEDULE FROM THIS POINT FORWARD PARTS OF THE PROJECT WILL MOVE AHEAD OF THE BUILDING DESIGN STRUCTURAL STEEL HAS APPROXIMATELY A 16 WEEK LEAD TIME FROM THE DATE OF ORDER F&F NEEDS TO BE IN THE GROUND BEFORE FREEZE FF&E WILL BE ANOTHER BID PACKAGE, EITHER WITH THE BUILDING OR AFTER
HVAC COMPARISON COMPLETE MOVING TO WHOLE BUILDING ANALYSIS, ENERGY EFFICIENCY
HVAC COMPARISON COMPLETE MOVING TO WHOLE BUILDING ANALYSIS, ENERGY EFFICIENCY
JANUARY 25 –DIRECTION TO PROCEED WITH MASTER PLAN AS PRESENTED REMOVE AND BUILD NEW: TRANSPORTATION CENTER BUS PARKING BUS DRIVER PARKING BUDGET INCLUDES CONTINGENCY CONSERVATIVE NUMBER
FLOOR AREA RATIO TRANSPORTATION = 87% WAREHOUSE = 87% STORAGE AREA = 99%
FLOOR AREA RATIO ADMINISTRATION = 73% G&G, C&G = 95% SHARED SERVICES WITH OTHER DEPARTMENTS STAIRS FREIGHT ELEVATOR CORRIDORS - CONNECTION PASSENGER ELEVATOR MECHANICAL EQUIPMENT – OUTSIDE AIR EQUIP MAIN CAFETERIA/BREAK ROOM RESTROOMS – PDC, B&G
FLOOR AREA RATIO ADMINISTRATION = 77% SHARED SERVICES WITH OTHER DEPARTMENTS STAIRS FREIGHT ELEVATOR CORRIDORS - CONNECTION PASSENGER ELEVATOR MECHANICAL EQUIPMENT – OUTSIDE AIR EQUIP
SIMPLE STRUCTURE – STRAIGHT FORWARD SINGLE ROOF SHELTERS ALL ELEMENTS, DEPARTMENTS SMALLER PERCEIVED OVERALL SCALE BRICK PLANER ELEMENTS BREAK-UP FAÇADE SIGNIFY OUTREACH – INVITING VISUAL LANGUAGE – FRONT DOOR TRANSPARENT FAÇADE – OPENESS SIMPLE PALATE – COMMON MATERIALS RESPONSIBILITY TO CONTROL SOLAR GAIN ENERGY EFFICIENCY